SlideShare a Scribd company logo
PLANNING & PROJECT MANAGEMENT CONFERENCE
ANALYSIS &DELAY
DISPUTE RESOLUTION
2
WHAT IS DELAY?
• DELAY is an act or event that extends the time required to
perform tasks or activities under a Contract . It is usually
reflected as additional days of work or as delayed start of
activities.
• DELAY May or may not include change(s) in the scope of work
of activity(s) or the Contract.
3
Baseline Programme
- Baseline is an approved version of Programme.
-Define the baseline as a Target of schedule update.
4
• Activity duration and relation determination.
• Network Forward and Backward calculations lead
to float (most used is total float).
• Total float is margin for delay, and equal the
difference between late and early dates.
• Total Float Indicator
Positive Float: Project/Activity in good situation
Zero Float: Project/ Activity is critical
Negative Float: Project/ Activity is delayed
5
REASONS OF DELAYS
6
Risk Events:
Usually causes will be categorized as Contractor Risk
Events (CRE), or Employer Risk Events (ERE). Until
any of these events are confirmed as having caused
actual delay, they are only risk events.
There is another category is Neutral event such as
Force majeure.
7
Delay
Neutral Event
In-Excusable (CRE)Excusable
ERE
CompensableNon- Compensable
Concurrent
8
Concurrent Delay
(ERE) exceed (CRE)(CRE) exceed (ERE) (ERE) after completion date
Excusable Delay 
(ERE) 
In‐Excusable Delay  (CRE) 
Excusable Non 
Compensable  Delay 
In-Excusable
Delay
concurrent
with shorter
Excusable
Delay yields
a net
Excusable
Non
Compensable
Delay
ONLY Time
Extension is
Granted
Should be 
recovered 
Excusable Delay (ERE) 
In‐Excusable Delay  
(CRE) 
Excusable Non 
Compensable  Delay 
In-Excusable
Delay
concurrent
with longer
Excusable
Delay yields
an Excusable
Delay and
Partial
Compensation
- Time
Extension is
Granted with
prolongation
cost
Excusable 
Compensable 
9
Delay Analysis Techniques
10
Prospective Delay Analysis:
Analysis of facts associated with delay events during
construction of a project and the estimation of their effect
upon the planned completion date of a project. (Interim
Extension of Time)
Retrospective Delay Analysis:
Analysis of facts associated with delay events after completion
of the construction period of a project. (Final Extension of
Time)
11
Guidance Section 4
4. Guidelines on dealing with disputed extension of time issues after completion of
the project – retrospective delay analysis
4.13 The table below summarises the types of analysis that can be conducted depending
on the types of factual material available. An ‘X’ indicates the factual material that is
required for a particular analysis, but in some cases there are alternatives, as indicated in
the table:
Why Dispute Reached??
13
Change Request
Instruction or Proposal of new woks
requested by any stakeholder may
include: addition, omission, corrective
action or preventive action.
Claim Submittal
Request from one contracting party to
another party for additional payment/
compensation, or/and extension of the
time for completion, as result of change
or any other event / issue.
Variation Order
Description of the work to be performed
including the time impact or/and cost
impact if applicable, as result of change
or claim.
Dispute
Unresolved claim, and resolution
methods are: negotiation, mediation,
arbitration & litigation.
14
Methods of Dispute
resolving
 Negotiation
The most direct method for
resolving any type of
construction claim.
Requires certain skills that reduce the gap between the
negotiation parties.
The objective: is to reach a solution that might be acceptable
to both parties.
15
 Mediation
When negotiation does not work, either because of lack of
trust or a lack of skills, mediation may be an option.
The mediator may be an individual or a team.
 Dispute review boards
The owner and the contractor select
an independent neutral panel with
construction experience when the
contract is signed .
Rather than waiting until the end of project to settle claims,
(DRBs) resolve disputes as they arise.
16
 Arbitration
It is usually a formal process performed
by an independent professional
arbitrator.
 Arbitration is voluntary.
 Arbitration does not require the use
of lawyers
 Litigation
When none of the previous work and parties can not
reach a settlement, the complaining party uses the
other party in a court of law.
Construction litigation is usually complicated lengthy,
and expensive.
17
ARBITRATION
Institutional vs. 'ad hoc' arbitration
Domestic vs. International arbitration
(address is the difference)
Types of Arbitration
Arbitration agreement :
The arbitration agreement is ordinarily a
clause in a larger contract.
or, post-dispute arbitration agreement.
Procedure, dispute, arbitrator panel, seat /
legal place, duration, language, the applicable
law and rules.
Arbitration award:
Legally-binding and enforceable decision
Appeal & recourse against an award
21
Thank You
–Don’t Hesitate to Contact….
M.Maged

More Related Content

What's hot

خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأول
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأولخمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأول
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأول
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
Essam Lotffy, PMP®, CCP®
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
Introduction to construction contracts fundamentals
Introduction to construction contracts fundamentalsIntroduction to construction contracts fundamentals
Introduction to construction contracts fundamentals
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Michael Pink
 
Performance Measurement and Weightage Systems
Performance Measurement and Weightage SystemsPerformance Measurement and Weightage Systems
Performance Measurement and Weightage Systems
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
John Buchovecky
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Standard Forms of Construction Contracts
Standard Forms of Construction ContractsStandard Forms of Construction Contracts
Standard Forms of Construction Contracts
M Maged Hegazy, LLM, MBA, CCP, P3O
 
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
M Maged Hegazy, LLM, MBA, CCP, P3O
 
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEotمحاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
Khaled M. Al Kolfat MS.Eng,MoP,P3O,PMOC,PMP,M.ASCE
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
Moustafa Ismail Abu Dief
 
Delay Analysis from a Technical and Legal Perspective presentation slides.pdf
Delay Analysis from a Technical and Legal Perspective presentation slides.pdfDelay Analysis from a Technical and Legal Perspective presentation slides.pdf
Delay Analysis from a Technical and Legal Perspective presentation slides.pdf
Association for Project Management
 
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Divyanshu Dayal
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
ASHISH KUMAR SINGH
 
Concurrent Delay in Construction
Concurrent Delay in ConstructionConcurrent Delay in Construction
Concurrent Delay in Construction
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Contracts classification
Contracts classificationContracts classification
Contracts classification
M Maged Hegazy, LLM, MBA, CCP, P3O
 

What's hot (20)

خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأول
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأولخمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأول
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الأول
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
Introduction to construction contracts fundamentals
Introduction to construction contracts fundamentalsIntroduction to construction contracts fundamentals
Introduction to construction contracts fundamentals
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
Performance Measurement and Weightage Systems
Performance Measurement and Weightage SystemsPerformance Measurement and Weightage Systems
Performance Measurement and Weightage Systems
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
Standard Forms of Construction Contracts
Standard Forms of Construction ContractsStandard Forms of Construction Contracts
Standard Forms of Construction Contracts
 
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
 
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEotمحاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
Delay Analysis from a Technical and Legal Perspective presentation slides.pdf
Delay Analysis from a Technical and Legal Perspective presentation slides.pdfDelay Analysis from a Technical and Legal Perspective presentation slides.pdf
Delay Analysis from a Technical and Legal Perspective presentation slides.pdf
 
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Concurrent Delay in Construction
Concurrent Delay in ConstructionConcurrent Delay in Construction
Concurrent Delay in Construction
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Contracts classification
Contracts classificationContracts classification
Contracts classification
 

Similar to Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged

Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
Loay Ghazaleh MBA, BSc Civil Eng.
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
Joseph Sangpang
 
projectclosure-rutik.pptx project management
projectclosure-rutik.pptx project managementprojectclosure-rutik.pptx project management
projectclosure-rutik.pptx project management
akashdhewale87
 
Project closure
Project closureProject closure
Project closure
Gyaneshwar Suman
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
ByishimoBTCChef
 
6 software contracts
6 software contracts6 software contracts
6 software contracts
Saqib Raza
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract
Sarah Fox
 
Contract admn ajit philip
Contract admn ajit philipContract admn ajit philip
Contract admn ajit philipFarhan Moosa
 
APM Presents - Contracts and Procurement: what you must know to get the contr...
APM Presents - Contracts and Procurement: what you must know to get the contr...APM Presents - Contracts and Procurement: what you must know to get the contr...
APM Presents - Contracts and Procurement: what you must know to get the contr...
Association for Project Management
 
Liquidated damages
Liquidated damagesLiquidated damages
Liquidated damages
Erfan Ghassempour
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 CompleteJohn Ashton
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
srinivas2036
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
IJMER
 
Sheet1Silver Fiddle Company Risk MatrixRisk DescriptionProbability.docx
Sheet1Silver Fiddle Company Risk MatrixRisk DescriptionProbability.docxSheet1Silver Fiddle Company Risk MatrixRisk DescriptionProbability.docx
Sheet1Silver Fiddle Company Risk MatrixRisk DescriptionProbability.docx
lesleyryder69361
 
Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith
mark woodward-smith
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
IrfanAwan25
 
2 claims under new fidic
2 claims under new fidic2 claims under new fidic
2 claims under new fidic
AhmetArslan47
 
PROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptxPROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptx
MeenalKulkarni12
 
Pai 3-03
Pai 3-03Pai 3-03
Pai 3-03
ypinada
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Rae Davies
 

Similar to Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged (20)

Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 
projectclosure-rutik.pptx project management
projectclosure-rutik.pptx project managementprojectclosure-rutik.pptx project management
projectclosure-rutik.pptx project management
 
Project closure
Project closureProject closure
Project closure
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
6 software contracts
6 software contracts6 software contracts
6 software contracts
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract
 
Contract admn ajit philip
Contract admn ajit philipContract admn ajit philip
Contract admn ajit philip
 
APM Presents - Contracts and Procurement: what you must know to get the contr...
APM Presents - Contracts and Procurement: what you must know to get the contr...APM Presents - Contracts and Procurement: what you must know to get the contr...
APM Presents - Contracts and Procurement: what you must know to get the contr...
 
Liquidated damages
Liquidated damagesLiquidated damages
Liquidated damages
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 Complete
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
 
Sheet1Silver Fiddle Company Risk MatrixRisk DescriptionProbability.docx
Sheet1Silver Fiddle Company Risk MatrixRisk DescriptionProbability.docxSheet1Silver Fiddle Company Risk MatrixRisk DescriptionProbability.docx
Sheet1Silver Fiddle Company Risk MatrixRisk DescriptionProbability.docx
 
Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
 
2 claims under new fidic
2 claims under new fidic2 claims under new fidic
2 claims under new fidic
 
PROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptxPROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptx
 
Pai 3-03
Pai 3-03Pai 3-03
Pai 3-03
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
 

More from M Maged Hegazy, LLM, MBA, CCP, P3O

Variation Orders – Types, Permission and Consequences
Variation Orders – Types, Permission and ConsequencesVariation Orders – Types, Permission and Consequences
Variation Orders – Types, Permission and Consequences
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
M Maged Hegazy, LLM, MBA, CCP, P3O
 
CCP Course - Introduction.pdf
CCP Course - Introduction.pdfCCP Course - Introduction.pdf
CCP Course - Introduction.pdf
M Maged Hegazy, LLM, MBA, CCP, P3O
 
International Delay Analysis Approaches
International Delay Analysis ApproachesInternational Delay Analysis Approaches
International Delay Analysis Approaches
M Maged Hegazy, LLM, MBA, CCP, P3O
 
CCP Technical Paper and Application
CCP Technical Paper and ApplicationCCP Technical Paper and Application
CCP Technical Paper and Application
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Missing and modern necessary skills
Missing and modern necessary skillsMissing and modern necessary skills
Missing and modern necessary skills
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Procurement negotiation tips and phases
Procurement negotiation tips and phasesProcurement negotiation tips and phases
Procurement negotiation tips and phases
M Maged Hegazy, LLM, MBA, CCP, P3O
 
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامسأسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
M Maged Hegazy, LLM, MBA, CCP, P3O
 
5th Anniversary of Planning & Project Control Group
5th Anniversary of Planning & Project Control Group5th Anniversary of Planning & Project Control Group
5th Anniversary of Planning & Project Control Group
M Maged Hegazy, LLM, MBA, CCP, P3O
 
26 مؤتمر ادارة المشروعات contract relations management
26 مؤتمر ادارة المشروعات contract relations management26 مؤتمر ادارة المشروعات contract relations management
26 مؤتمر ادارة المشروعات contract relations management
M Maged Hegazy, LLM, MBA, CCP, P3O
 
4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice
4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice
4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice
M Maged Hegazy, LLM, MBA, CCP, P3O
 
3 years acheivements
3 years acheivements3 years acheivements
PMP integration review
PMP integration reviewPMP integration review
PMP integration review
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Pmp procurement rev
Pmp procurement revPmp procurement rev

More from M Maged Hegazy, LLM, MBA, CCP, P3O (15)

Variation Orders – Types, Permission and Consequences
Variation Orders – Types, Permission and ConsequencesVariation Orders – Types, Permission and Consequences
Variation Orders – Types, Permission and Consequences
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
CCP Course - Introduction.pdf
CCP Course - Introduction.pdfCCP Course - Introduction.pdf
CCP Course - Introduction.pdf
 
International Delay Analysis Approaches
International Delay Analysis ApproachesInternational Delay Analysis Approaches
International Delay Analysis Approaches
 
CCP Technical Paper and Application
CCP Technical Paper and ApplicationCCP Technical Paper and Application
CCP Technical Paper and Application
 
Missing and modern necessary skills
Missing and modern necessary skillsMissing and modern necessary skills
Missing and modern necessary skills
 
Procurement negotiation tips and phases
Procurement negotiation tips and phasesProcurement negotiation tips and phases
Procurement negotiation tips and phases
 
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامسأسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
 
5th Anniversary of Planning & Project Control Group
5th Anniversary of Planning & Project Control Group5th Anniversary of Planning & Project Control Group
5th Anniversary of Planning & Project Control Group
 
26 مؤتمر ادارة المشروعات contract relations management
26 مؤتمر ادارة المشروعات contract relations management26 مؤتمر ادارة المشروعات contract relations management
26 مؤتمر ادارة المشروعات contract relations management
 
4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice
4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice
4 أعوام الصفحة الرئيسية التابع لها جروبات Best Advice
 
3 years acheivements
3 years acheivements3 years acheivements
3 years acheivements
 
PMP integration review
PMP integration reviewPMP integration review
PMP integration review
 
Pmp procurement rev
Pmp procurement revPmp procurement rev
Pmp procurement rev
 

Recently uploaded

MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Basic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparelBasic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparel
top1002
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 

Recently uploaded (20)

MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Basic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparelBasic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparel
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 

Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged

  • 1. PLANNING & PROJECT MANAGEMENT CONFERENCE ANALYSIS &DELAY DISPUTE RESOLUTION
  • 2. 2 WHAT IS DELAY? • DELAY is an act or event that extends the time required to perform tasks or activities under a Contract . It is usually reflected as additional days of work or as delayed start of activities. • DELAY May or may not include change(s) in the scope of work of activity(s) or the Contract.
  • 3. 3 Baseline Programme - Baseline is an approved version of Programme. -Define the baseline as a Target of schedule update.
  • 4. 4 • Activity duration and relation determination. • Network Forward and Backward calculations lead to float (most used is total float). • Total float is margin for delay, and equal the difference between late and early dates. • Total Float Indicator Positive Float: Project/Activity in good situation Zero Float: Project/ Activity is critical Negative Float: Project/ Activity is delayed
  • 6. 6 Risk Events: Usually causes will be categorized as Contractor Risk Events (CRE), or Employer Risk Events (ERE). Until any of these events are confirmed as having caused actual delay, they are only risk events. There is another category is Neutral event such as Force majeure.
  • 8. 8 Concurrent Delay (ERE) exceed (CRE)(CRE) exceed (ERE) (ERE) after completion date Excusable Delay  (ERE)  In‐Excusable Delay  (CRE)  Excusable Non  Compensable  Delay  In-Excusable Delay concurrent with shorter Excusable Delay yields a net Excusable Non Compensable Delay ONLY Time Extension is Granted Should be  recovered  Excusable Delay (ERE)  In‐Excusable Delay   (CRE)  Excusable Non  Compensable  Delay  In-Excusable Delay concurrent with longer Excusable Delay yields an Excusable Delay and Partial Compensation - Time Extension is Granted with prolongation cost Excusable  Compensable 
  • 10. 10 Prospective Delay Analysis: Analysis of facts associated with delay events during construction of a project and the estimation of their effect upon the planned completion date of a project. (Interim Extension of Time) Retrospective Delay Analysis: Analysis of facts associated with delay events after completion of the construction period of a project. (Final Extension of Time)
  • 11. 11 Guidance Section 4 4. Guidelines on dealing with disputed extension of time issues after completion of the project – retrospective delay analysis 4.13 The table below summarises the types of analysis that can be conducted depending on the types of factual material available. An ‘X’ indicates the factual material that is required for a particular analysis, but in some cases there are alternatives, as indicated in the table:
  • 13. 13 Change Request Instruction or Proposal of new woks requested by any stakeholder may include: addition, omission, corrective action or preventive action. Claim Submittal Request from one contracting party to another party for additional payment/ compensation, or/and extension of the time for completion, as result of change or any other event / issue. Variation Order Description of the work to be performed including the time impact or/and cost impact if applicable, as result of change or claim. Dispute Unresolved claim, and resolution methods are: negotiation, mediation, arbitration & litigation.
  • 14. 14 Methods of Dispute resolving  Negotiation The most direct method for resolving any type of construction claim. Requires certain skills that reduce the gap between the negotiation parties. The objective: is to reach a solution that might be acceptable to both parties.
  • 15. 15  Mediation When negotiation does not work, either because of lack of trust or a lack of skills, mediation may be an option. The mediator may be an individual or a team.  Dispute review boards The owner and the contractor select an independent neutral panel with construction experience when the contract is signed . Rather than waiting until the end of project to settle claims, (DRBs) resolve disputes as they arise.
  • 16. 16  Arbitration It is usually a formal process performed by an independent professional arbitrator.  Arbitration is voluntary.  Arbitration does not require the use of lawyers  Litigation When none of the previous work and parties can not reach a settlement, the complaining party uses the other party in a court of law. Construction litigation is usually complicated lengthy, and expensive.
  • 18. Institutional vs. 'ad hoc' arbitration Domestic vs. International arbitration (address is the difference) Types of Arbitration
  • 19. Arbitration agreement : The arbitration agreement is ordinarily a clause in a larger contract. or, post-dispute arbitration agreement. Procedure, dispute, arbitrator panel, seat / legal place, duration, language, the applicable law and rules.
  • 20. Arbitration award: Legally-binding and enforceable decision Appeal & recourse against an award
  • 21. 21 Thank You –Don’t Hesitate to Contact…. M.Maged