High Profile Call Girls Jaipur Vani 8445551418 Independent Escort Service Jaipur
GANTT CHART nursing Management for Msc nursing
1.
2. SUBMITTED TO
SUBMITTED TO
Dr. A. Bhavani.M.Sc(N),Ph.D,
Tutor in nursing
Government college of nursing,
Cuddalore.
SUBMITTED BY
S.P.Mahalakshmi,
M.Sc(n) II Year,
Government college of nursing,
Cuddalore.
3. Nowadays Healthcare is being considered as an
industry.
The optimization of resources and continuous
quality improvement application of network
analysis to hospital processes is must.
A network is a graphic plan of all the activities
to be completed in order to reach to the end
objectives.
There are three major techniques for this
analysis. Gantt chart, milestone budgeting and
Program Evaluation and Review Technique
(PERT) and critical path method (CPM).
4. A Gantt chart is a horizontal bar chart
developed as a production control tool in 1910
by Henry L Gantt, an American engineer and
social scientist.
A Gantt chart provides a graphical illustration
of a schedule that helps to plan, coordinate and
track specific tasks in a project.
Project usually involves more than one person
or more than one step poses many questions
and the answer is the time oriented diagram
(i.e) the Gantt chart.
5. Karol Adamiecki -1896 – Harmonogram.
1910-1915 Henry Gantt devised his own version of
the chart.
The earliest Gantt charts were drawn on paper.
In the 1980s personal computers allowed widespread
creation of complex and elaborate Gantt chart.
At the end of 1990 Gantt chart became a common
feature of web-based applications by 2012 almost all
Gantt charts were made by software which can easily
adjust to schedule changes.
1999 Gantt charts were identified as one of the most
widely used management tools for project scheduling
and control.
6. PLANNING
planning is the process of determining the objectives
of administrative effort and devising the means
calculated to achieve them.
- Millet
GANTT CHART
Gantt chart is a type of bar chart that illustrates a
project schedule
-Jogindra Vati
It is defined as a graphical device that illustrates the
tasks, machines, personnel and resources used to
complete your task. It is always done on a calendar
oriented grid.
8. LOAD CHART
Schematic and graphic device to indicate the
amount of authorized work yet to be performed
by a machine, a group or any other producing
unit in a factory.
SCHEDULE CHART
Schedule chart focuses on that activity
sequence and timing for various components of
a job it can also be used to monitor the actual
progress of your job in relation to the plan.
9. HORIZONTAL AXIS
Represents time scale expressed as absolute time
from the project start to its end. It indicates time
needed to do the project.
VERTICAL AXIS
Used to represent the present point in time vertical
lines are indicated to denote progress and
completion. It helps to understand progress and
end of the project schedule.
10. BROKEN LINES indicates gap or slippage
times during the project schedule.
DIAMOND SYMBOL indicates rescheduled
work.
MILESTONES represented in the chart.
RESOURCE allocation can be specified for
each task.
COLOR CODE used for certain specific task.
11. NEED
Keep everyone
on the same
page
Effective
allocation of
resources
Get a handle on
the future
Understand task
relationship
Avoid
completion
confusion
12. Avoid completion confusion
Gantt charts were created to keep users on track,
providing a visual timeline for starting and finishing
specific tasks.
Keep everyone on the same page
Where there is a visual framework for the work to be
done, there are fewer chances of misunderstanding
especially when it comes to highly complex tasks.
Understand task relationships
Charts can make clear how various tasks are inter-
related and perhaps rely on the completion of another
to meet specific objectives. charts makes it very easy
to visualize related tasks.
13. EFFECTIVELYALLOCATE RESOURCES
The more closely the chart is followed the better
chance there is of keeping project costs within
budget. While also better assuring on-time
completion.
GET A HANDLE ON THE FUTURE
It helps decision makers look further ahead to ensure
each given project is working toward the
achievement of the organization’s long term strategic
objectives.
14. To show the current schedule status.
To measure task duration in the project.
To represent cost, time and scope of the
project.
A useful tool for planning and scheduling
projects.
To plan how long a project should take.
Lays out the order in which the tasks need to
be carried out.
15. Modern Gantt chart software provides
dependencies between tasks.
To monitor your project’s progress.
To visualize immediately what should have
been achieved at any point in time.
To assist in taking remedial action to bring the
project back on course, if required.
16. FORWARD SCHEDULING
Here start from the beginning of the project and
work your way down to the deadline.
BACKWARD SCHEDULING
Here start from the deadline and then logically
work your way up to the start.
17. The bar in each row identifies the
corresponding task.
The horizontal position of the bar identifies
start and end times of the task.
Bar length represents the duration of the task.
Task durations can be compared easily.
Good for allocating resources and re-
scheduling. Precedence relationships can be
represented using arrows.
18. Critical activities are usually highlighted.
Slap times are represented using bars with
dotted lines.
The bar of each activity begins at the activity
earliest start times.
The bar of each activity inside the activity
latest finish time.
19. Gather data.
Analyze data.
Develop a plan.
Implement the plan.
Evaluation, feedback and modification.
Application of this controlling process by nurse
managers would be specific to the project or
program.
The nurse manager’s goal is to complete each
activity or phase on or before the projected date.
21. Gantt charts don’t give useful information
unless they include all of the activities needed
for the project to be completed.
So to start , list all of these activities . use a
work breakdown structure if you need to
establish what the tasks are.
Then for each tasks, note its earlier start date
and its estimated duration.
22. The chart shows the relationship between the
tasks in your project.
Some tasks will need to be completed before
you can start the next one, and others can’t end
until proceeding once have ended.
For example, if you are creating a brochure you
need to finish the design before you can send it
to print.
This dependent activities are called
“sequential” or “linear” tasks other tasks will
be “parallel”.
23. Draw your charts by hand or use specialist
software, such as Gantto, Matchware or
Microsoft project.
Some of this tools are cloud - based, meaning
that you and your team can access the
document simultaneously from any location.
This helps a lot when you are discussing
optimizing and reporting on a project.
24. As project moves along it will evolve
Update your chart to reflect changes as soon as
they occur.
This will help you to keep your plans your
team and your sponsors up to date.
For example if quality assurance of core
modules revealed a problem then you may
need to delay training, and halt development of
the management information system until the
issue is resolved.
25. Identify the purpose.
Define the project timeline.
Break the project down into
manageable pieces.
Create progress bars.
Define the critical path.
Add milestone markers.
26. IDENTIFY THE PURPOSE
It is helpful to first decide whether this is a project
or a process, because diagramming a process
might work better with a flow chart.
DEFINE THE PROJECT TIMELINE
Decide how to divide the increments of time for
the duration of the project.
Each one should have a start date and end date
27. BREAK THE PROJECT DOWN INTO
MANAGEABLE PIECES
Divide the project into major components then
tasks and sub tasks. Continue breaking them
down until they are each straight forward tasks.
CREATE PROGRESS BARS
To create a progress bar for each task.
A progress bar is simply a horizontal bar that
should be in line with the task name it
represents and should begin beneath its start
date and end beneath its end date.
28. DEFINE THE CRITICAL PATH
It is a method of looking at all of the activities in
the Gantt chart considering the timing and
dependent relationships of each and calculating
the longest path from start to completion of the
project.
ADD MILESTONE MARKERS
Choose a symbol to represent milestones, that is
major events that either have a large part in the
process.
Place them on the chart beneath the date or time
when they occur.
29. • Can only
complete task A
once you start
task B.
• Can only
complete task
A once you
complete task
B
• Must start task
A before you
start task B
• Must complete
task A before
you start task
B.
Finish
to start
Start to
start
Start to
finish
Finish
to finish
30.
31.
32. Once the project schedule has been constructed,
take into account,
Available staff hours
Slack times &
Project schedule.
Resource smoothing is a technique used to
reallocate resources and reschedule activities.
In resource smoothing non - critical tasks are
rescheduled within their time window.
33. Helps in planning and monitoring the work of
project.
Time is explicitly expressed in the chart.
All tasks are visible at a glance in relation to other.
Deadlines are depicted in the chart.
Excellent tool to communicate wide population.
At a single glance work done can be analyzed
quickly through the work breakdown structure.
Used as a reporting tool for large projects.
Gives cost, time & scope of the project.
34. It cannot effortlessly display more than 30
activities.
It is valuable only for short projects.
Chart can communicate only little information at a
time.
Magnitude behind the schedule is easily
miscommunicated, since it does not represent full
size of the project.
It does not explain the reasoning behind the chosen
duration of each activity.
It do not consider project costs or resources.
Difficult to update manually.
35. Gantt chart provide a visual and organized way
to plan, schedule and track tasks within a
project.
They enhance project management efficiency by
clearly displaying timelines, dependencies and
progress, fostering better communication among
team members.
Integrating Gantt charts can lead to improved
project coordination and successful execution.
36. Time for self
actualization
goals.
Gantt chart for
opportunities for
achievement.
Social activities Gantt
chart to address the
social needs.
Security checks on the Gantt
chart.
Assessments on the Gantt chart to
ensure the client’s basic physical
needs are met.
37. Journal name: International Journal of innovative
technology and exploring engineering.
Topic: Gantt chart: An important tools of
management.
Author : KK Ramachandran KK kartik.
A study on the important technique of time saving
and money saving of the management. Gantt study
is continued and he expressed scientific method of
activity which can save time and money of an
organization. Henry Fayol defined 14 principles of
the management and Gantt declared activity chart.
This chart is yet used in several industries as an
ideal chart of activity plan.
38. Write an assignment on Preparation of Gantt
chart for your research study.