“Management is doing things right,
Leadership is doing the right
things!”

Presentation done by

Peter F. Drucker
PHASES OF
PERT
Project management consists of three
phases
Project Planning Phase

Scheduling Phase

Project Control Phase
Project Planning Phase
In order to visualize the sequencing or precedence
requirements of the activities in a project is helpful to
draw a network diagram. For this the following steps
are adopted: Indentify various activities to be performed in the
project, i.e. develop a breakdown structure(WBS).
 Determine the requirement of resources such as
men, material, machines, money, etc.
 Assign responsibility for each work package.
 Allocate resources to work packages.
 Estimate cost and time at various levels of
project completion.
 Develop work performance criteria.
 Establish control channels for project
personnel.
Scheduling Phase
Once all work packages have been
indentified and given unique names or
identifiers, scheduling the project, i.e.
when each of the activities are required
to be performed, is taken up. It prepares
an analysis/estimate of the likelihood of
the project to be completed on or before
the specified time.
The various steps involved in this phase are:Identify all people who will be responsible for each
task.
Estimate the expected duration(s) of each activity.
Specify the interrelationship.
Develop a network diagram.
Based on these time estimates, calculate the total
project duration, identify critical path; calculate
floats; carry out resources smoothing exercise for
critical resources, taking into account the resource
constraints.
Project Control Phase
Project control refers to the evaluation of the
actual progress against the plan. If significant
differences are observed, then the scheduling
and resource allocation decisions are changed
in order to update revise the uncompleted
part of the project. In other words, remedial
or reallocation of resources measures are
adopted in such cases.
WBS

PRECEDENCE
NETWORK

DEVIATION
FROM
PLAN

ACTUAL
PERFORMANCE
DATA

GANTT
CHART

PERIODIC
COST
REPORTS

SCHEDULE
ALLOCATION

RESOURCE
ALLOCATION
Ask me about the topic if you want.
Thanks

Management

  • 1.
    “Management is doingthings right, Leadership is doing the right things!” Presentation done by Peter F. Drucker
  • 2.
  • 3.
    Project management consistsof three phases Project Planning Phase Scheduling Phase Project Control Phase
  • 4.
    Project Planning Phase Inorder to visualize the sequencing or precedence requirements of the activities in a project is helpful to draw a network diagram. For this the following steps are adopted: Indentify various activities to be performed in the project, i.e. develop a breakdown structure(WBS).  Determine the requirement of resources such as men, material, machines, money, etc.
  • 5.
     Assign responsibilityfor each work package.  Allocate resources to work packages.  Estimate cost and time at various levels of project completion.  Develop work performance criteria.  Establish control channels for project personnel.
  • 6.
    Scheduling Phase Once allwork packages have been indentified and given unique names or identifiers, scheduling the project, i.e. when each of the activities are required to be performed, is taken up. It prepares an analysis/estimate of the likelihood of the project to be completed on or before the specified time.
  • 7.
    The various stepsinvolved in this phase are:Identify all people who will be responsible for each task. Estimate the expected duration(s) of each activity. Specify the interrelationship. Develop a network diagram. Based on these time estimates, calculate the total project duration, identify critical path; calculate floats; carry out resources smoothing exercise for critical resources, taking into account the resource constraints.
  • 8.
    Project Control Phase Projectcontrol refers to the evaluation of the actual progress against the plan. If significant differences are observed, then the scheduling and resource allocation decisions are changed in order to update revise the uncompleted part of the project. In other words, remedial or reallocation of resources measures are adopted in such cases.
  • 9.
  • 10.
    Ask me aboutthe topic if you want.
  • 11.