SlideShare a Scribd company logo
1 of 9
Topic 9:
Project Scheduling
Topic 9 : Project Scheduling
 Project scheduling is a mechanism to communicate what tasks need to get done
and which organizational resources will be allocated to complete those tasks in
what timeframe.
 The following are the steps needed to schedule a project:
o Define Activities : Create Work Breakdown Structure (WBS) and a
deliverables diagram and organize them by mapping out the tasks .
o Do Estimates : Determine the time and effort it will take to complete them.
o Determine Dependencies : Place a bit of slack in your schedule to
accommodate these related tasks.
o Assign Resources : Finalize the planned schedule by deciding what
resources you are going to need to get those tasks done on time.
 Estimate Activity Duration Inputs
o This process has several tools and techniques ;-
-Expert Judgement, -Analogous Estimating, -Parametric Estimating
-Three-Point Estimating, -Group decision-making techniques, -Reserve Analysis
 3 Point Estimating
o Three-point estimating uses three estimates that when averaged come up with
final estimate.
• Most likely estimate – assumes there are no disaster and activity can be
completed as planned
• Optimistic estimate – fastest time frame in which your resource can
complete the activity
• Pessimistic – Assumes the worst happens and it takes much longer than
planned to get the activity completed
o Formula to calculate the expected duration : E = (O + P + M) / 3
o E=Expected, O = Optimistic, M = Most Likely
o The formula for standard deviation which helps to determine the confidence level
as below : E : (Pessimistic – Optimistic) / 6
 Expert Judgement - The staff members who will perform activities will most
accurately estimate them
 Analogous Estimating ( also called as top-down estimating, an expert
judgement) - Actual duration of a similar activity completed on previous project
will be used to determine the duration of current activity.
 Bottom Up Estimating – Is the most accurate approach to estimate cost and
duration. Setting the estimates of the amount of work, duration and cost at the
task level lets you combine them into estimates of higher-level deliverables and
the project as a whole
 Parametric Estimating - Quantitatively based estimating method that multiplies
the quantity of work by the rate or uses an algorithm in conjunction with historical
data to determine the cost, budget or duration estimates.
 Group decision-making techniques (brainstorming and the Delphi or nominal
group techniques)
o Brainstorming is an old-age technique where all participants have an
opportunity to speak up.
o Delphi technique is similar to brainstorming in that you involve subject matter
experts in determining estimates.
 Reserve Analysis
o Contingency reserve - a portion of time added to the schedule to account
for risk
o Management reserve - used for unknown events that have not been
previously identified
Resource Optimization Techniques
 Resource Leveling - also called as resource-based method is used when the
resources are overallocated and only available at certain times or when they are
assigned to more than one activity at a time. The purpose to use this technique is
to balance out the resource assignments to get tasks completed without
overloading the individual.
 Resource Smoothing - Resource smoothing accommodates resource availability
by modifying activities within their float times without changing the critical path or
project end date. More tasks are given to team members who are under allocated
.
 Reverse Resource - This technique requires the resources to be scheduled in
reverse order in order to assign this key resource at the correct time.
Modeling techniques
 Include the use of what-if scenario analysis and simulation
o What-If scenario : uses different sets of activity assumptions to produce
multiple project durations
o Simulation use a range of probable activity durations for each activity, and
those ranges are then used to calculate a range of probable duration results
for the project itself.
o Monte Carlo is a simulation technique that runs the possible activity durations
and schedule projections many many times to come up with the schedule
projections and their probability, critical path duration estimates and float
time.
Schedule Compression
 Mathematical analysis that’s used to shorten the project schedule duration without
changing the project scope in order to accomplish all activities sooner than
estimated.
o Crashing – accomplished by adding resources to the critical path.Crashing
the schedule can lead to increased risk and increased cost.
o Fast tracking – Performing 2 tasks or project phase in parallel that were
previously scheduled to start sequentially. It increases the project risk and
might cause the project team to re-work the tasks.
Project schedule can be presented in many forms ;
 Project schedule network diagram
 Gantt chart
 Milestone
Start
Activity
1
Activity
2
Activity
3 Activity
5
Activity
4 Activity
6
Task Name Jan Feb Mar Apr May
Planning
Design
Implementation
Milestone Scheduled date Actual Date Responsible
Testing completed 04/12/19 - Rachel
Acceptance and Signoff 07/12/19 15/12/19 Cindy
Project Closure 15/12/19 31/12/19 Carmen

More Related Content

What's hot

5. project activity and risk planning
5. project activity and risk planning5. project activity and risk planning
5. project activity and risk planning
Jeanette C. Patindol
 
Project Scheduling and Control Projects
Project Scheduling and Control ProjectsProject Scheduling and Control Projects
Project Scheduling and Control Projects
haroldtaylor1113
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
Jatindra Malik
 

What's hot (19)

Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Project time management
Project time managementProject time management
Project time management
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
5. project activity and risk planning
5. project activity and risk planning5. project activity and risk planning
5. project activity and risk planning
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
project management
project managementproject management
project management
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
Project Management 4 Schedule Management
Project Management 4 Schedule ManagementProject Management 4 Schedule Management
Project Management 4 Schedule Management
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Project scheduling and tracking
Project scheduling and trackingProject scheduling and tracking
Project scheduling and tracking
 
Project Scheduling and Control Projects
Project Scheduling and Control ProjectsProject Scheduling and Control Projects
Project Scheduling and Control Projects
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
 
Project control. Management
Project control. ManagementProject control. Management
Project control. Management
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time management
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 

Similar to Project Scheduling

3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating
harwoodr
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project Resources
Toyin Osunlaja
 

Similar to Project Scheduling (20)

Agile planning
Agile planningAgile planning
Agile planning
 
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 
Estimating time and cost resoures
Estimating time and cost resouresEstimating time and cost resoures
Estimating time and cost resoures
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
 
Project planning
Project planningProject planning
Project planning
 
3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating
 
5. PMP Training - Time management
5. PMP Training - Time management5. PMP Training - Time management
5. PMP Training - Time management
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project Resources
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & Tricks
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagement
 
Software Test Estimation
Software Test EstimationSoftware Test Estimation
Software Test Estimation
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
Rita's Process Chart
Rita's Process ChartRita's Process Chart
Rita's Process Chart
 
6 time PMBOK
6 time PMBOK6 time PMBOK
6 time PMBOK
 

More from Reema

More from Reema (20)

CSS Basic Introduction
CSS Basic IntroductionCSS Basic Introduction
CSS Basic Introduction
 
Google Analytics Course For Beginners
Google Analytics Course For BeginnersGoogle Analytics Course For Beginners
Google Analytics Course For Beginners
 
Conclusion Of The Course
Conclusion Of The CourseConclusion Of The Course
Conclusion Of The Course
 
Introduction
IntroductionIntroduction
Introduction
 
Create A Texture Pattern:
Create A Texture Pattern:Create A Texture Pattern:
Create A Texture Pattern:
 
Creating The Footer:
Creating The Footer:Creating The Footer:
Creating The Footer:
 
Creating The Main Content Area
Creating The Main Content AreaCreating The Main Content Area
Creating The Main Content Area
 
Create The Quick Quote Section:
Create The Quick Quote Section:Create The Quick Quote Section:
Create The Quick Quote Section:
 
Create The Featured Project Section:
Create The Featured Project Section:Create The Featured Project Section:
Create The Featured Project Section:
 
Creating The Navigation Bar:
Creating The Navigation Bar:Creating The Navigation Bar:
Creating The Navigation Bar:
 
Creating The Logo:
Creating The Logo:Creating The Logo:
Creating The Logo:
 
Prepare Your Photoshop Document:
Prepare Your Photoshop Document:Prepare Your Photoshop Document:
Prepare Your Photoshop Document:
 
Conclusion Of The Course
Conclusion Of The CourseConclusion Of The Course
Conclusion Of The Course
 
Adding A Dash In jQuery:
Adding A Dash In jQuery:Adding A Dash In jQuery:
Adding A Dash In jQuery:
 
Introduction To jQuery:
Introduction To jQuery:Introduction To jQuery:
Introduction To jQuery:
 
Introduction To JavaScript Ajax
Introduction To JavaScript AjaxIntroduction To JavaScript Ajax
Introduction To JavaScript Ajax
 
Introduction To JavaScript
Introduction To JavaScriptIntroduction To JavaScript
Introduction To JavaScript
 
Responsive Web Development
Responsive Web DevelopmentResponsive Web Development
Responsive Web Development
 
How To Add CSS The Correct Way.
How To Add CSS The Correct Way.How To Add CSS The Correct Way.
How To Add CSS The Correct Way.
 
CSS Basic Introduction, Rules, And Tips
CSS Basic Introduction, Rules, And TipsCSS Basic Introduction, Rules, And Tips
CSS Basic Introduction, Rules, And Tips
 

Recently uploaded

Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
bleessingsbender
 
Jual obat aborsi Hongkong ( 085657271886 ) Cytote pil telat bulan penggugur k...
Jual obat aborsi Hongkong ( 085657271886 ) Cytote pil telat bulan penggugur k...Jual obat aborsi Hongkong ( 085657271886 ) Cytote pil telat bulan penggugur k...
Jual obat aborsi Hongkong ( 085657271886 ) Cytote pil telat bulan penggugur k...
Klinik kandungan
 

Recently uploaded (20)

Buy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail AccountsBuy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail Accounts
 
GURGAON CALL GIRL ❤ 8272964427❤ CALL GIRLS IN GURGAON ESCORTS SERVICE PROVIDE
GURGAON CALL GIRL ❤ 8272964427❤ CALL GIRLS IN GURGAON  ESCORTS SERVICE PROVIDEGURGAON CALL GIRL ❤ 8272964427❤ CALL GIRLS IN GURGAON  ESCORTS SERVICE PROVIDE
GURGAON CALL GIRL ❤ 8272964427❤ CALL GIRLS IN GURGAON ESCORTS SERVICE PROVIDE
 
MEHSANA 💋 Call Girl 9827461493 Call Girls in Escort service book now
MEHSANA 💋 Call Girl 9827461493 Call Girls in  Escort service book nowMEHSANA 💋 Call Girl 9827461493 Call Girls in  Escort service book now
MEHSANA 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Ital Liptz - all about Itai Liptz. news.
Ital Liptz - all about Itai Liptz. news.Ital Liptz - all about Itai Liptz. news.
Ital Liptz - all about Itai Liptz. news.
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Thompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptx
Thompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptxThompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptx
Thompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptx
 
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
Abortion pills in Jeddah ! +27737758557, cytotec pill riyadh. Saudi Arabia" A...
 
Pimpri Chinchwad Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Servi...
Pimpri Chinchwad Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Servi...Pimpri Chinchwad Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Servi...
Pimpri Chinchwad Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Servi...
 
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptx
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptxGoal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptx
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptx
 
Moradia Isolada com Logradouro; Detached house with patio in Penacova
Moradia Isolada com Logradouro; Detached house with patio in PenacovaMoradia Isolada com Logradouro; Detached house with patio in Penacova
Moradia Isolada com Logradouro; Detached house with patio in Penacova
 
Jual obat aborsi Hongkong ( 085657271886 ) Cytote pil telat bulan penggugur k...
Jual obat aborsi Hongkong ( 085657271886 ) Cytote pil telat bulan penggugur k...Jual obat aborsi Hongkong ( 085657271886 ) Cytote pil telat bulan penggugur k...
Jual obat aborsi Hongkong ( 085657271886 ) Cytote pil telat bulan penggugur k...
 
The Art of Decision-Making: Navigating Complexity and Uncertainty
The Art of Decision-Making: Navigating Complexity and UncertaintyThe Art of Decision-Making: Navigating Complexity and Uncertainty
The Art of Decision-Making: Navigating Complexity and Uncertainty
 
WheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond InsightsWheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond Insights
 
DUNGARPUR 💋 Call Girl 9827461493 Call Girls in Escort service book now
DUNGARPUR 💋 Call Girl 9827461493 Call Girls in  Escort service book nowDUNGARPUR 💋 Call Girl 9827461493 Call Girls in  Escort service book now
DUNGARPUR 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
Progress Report - Oracle's OCI Analyst Summit 2024
Progress Report - Oracle's OCI Analyst Summit 2024Progress Report - Oracle's OCI Analyst Summit 2024
Progress Report - Oracle's OCI Analyst Summit 2024
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Asansol Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Service Available
Asansol Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Service AvailableAsansol Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Service Available
Asansol Call Girl Just Call♥️ 8084732287 ♥️Top Class Call Girl Service Available
 
HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 

Project Scheduling

  • 2. Topic 9 : Project Scheduling  Project scheduling is a mechanism to communicate what tasks need to get done and which organizational resources will be allocated to complete those tasks in what timeframe.  The following are the steps needed to schedule a project: o Define Activities : Create Work Breakdown Structure (WBS) and a deliverables diagram and organize them by mapping out the tasks . o Do Estimates : Determine the time and effort it will take to complete them. o Determine Dependencies : Place a bit of slack in your schedule to accommodate these related tasks. o Assign Resources : Finalize the planned schedule by deciding what resources you are going to need to get those tasks done on time.
  • 3.  Estimate Activity Duration Inputs o This process has several tools and techniques ;- -Expert Judgement, -Analogous Estimating, -Parametric Estimating -Three-Point Estimating, -Group decision-making techniques, -Reserve Analysis  3 Point Estimating o Three-point estimating uses three estimates that when averaged come up with final estimate. • Most likely estimate – assumes there are no disaster and activity can be completed as planned • Optimistic estimate – fastest time frame in which your resource can complete the activity • Pessimistic – Assumes the worst happens and it takes much longer than planned to get the activity completed o Formula to calculate the expected duration : E = (O + P + M) / 3 o E=Expected, O = Optimistic, M = Most Likely o The formula for standard deviation which helps to determine the confidence level as below : E : (Pessimistic – Optimistic) / 6
  • 4.  Expert Judgement - The staff members who will perform activities will most accurately estimate them  Analogous Estimating ( also called as top-down estimating, an expert judgement) - Actual duration of a similar activity completed on previous project will be used to determine the duration of current activity.  Bottom Up Estimating – Is the most accurate approach to estimate cost and duration. Setting the estimates of the amount of work, duration and cost at the task level lets you combine them into estimates of higher-level deliverables and the project as a whole  Parametric Estimating - Quantitatively based estimating method that multiplies the quantity of work by the rate or uses an algorithm in conjunction with historical data to determine the cost, budget or duration estimates.
  • 5.  Group decision-making techniques (brainstorming and the Delphi or nominal group techniques) o Brainstorming is an old-age technique where all participants have an opportunity to speak up. o Delphi technique is similar to brainstorming in that you involve subject matter experts in determining estimates.  Reserve Analysis o Contingency reserve - a portion of time added to the schedule to account for risk o Management reserve - used for unknown events that have not been previously identified
  • 6. Resource Optimization Techniques  Resource Leveling - also called as resource-based method is used when the resources are overallocated and only available at certain times or when they are assigned to more than one activity at a time. The purpose to use this technique is to balance out the resource assignments to get tasks completed without overloading the individual.  Resource Smoothing - Resource smoothing accommodates resource availability by modifying activities within their float times without changing the critical path or project end date. More tasks are given to team members who are under allocated .  Reverse Resource - This technique requires the resources to be scheduled in reverse order in order to assign this key resource at the correct time.
  • 7. Modeling techniques  Include the use of what-if scenario analysis and simulation o What-If scenario : uses different sets of activity assumptions to produce multiple project durations o Simulation use a range of probable activity durations for each activity, and those ranges are then used to calculate a range of probable duration results for the project itself. o Monte Carlo is a simulation technique that runs the possible activity durations and schedule projections many many times to come up with the schedule projections and their probability, critical path duration estimates and float time.
  • 8. Schedule Compression  Mathematical analysis that’s used to shorten the project schedule duration without changing the project scope in order to accomplish all activities sooner than estimated. o Crashing – accomplished by adding resources to the critical path.Crashing the schedule can lead to increased risk and increased cost. o Fast tracking – Performing 2 tasks or project phase in parallel that were previously scheduled to start sequentially. It increases the project risk and might cause the project team to re-work the tasks.
  • 9. Project schedule can be presented in many forms ;  Project schedule network diagram  Gantt chart  Milestone Start Activity 1 Activity 2 Activity 3 Activity 5 Activity 4 Activity 6 Task Name Jan Feb Mar Apr May Planning Design Implementation Milestone Scheduled date Actual Date Responsible Testing completed 04/12/19 - Rachel Acceptance and Signoff 07/12/19 15/12/19 Cindy Project Closure 15/12/19 31/12/19 Carmen