SlideShare a Scribd company logo
1 of 8
PDE201 – Dam Engineering I
3-1
3 Site Investigation and Selectionof Dam Types
3.1 Introduction
A dam and reservoir site must satisfy certain functional and technical requirements.
Whether these requirements are satisfied can be found out through site investigations
and technical evaluations.
Functional: the balance between its natural physical characteristics and the purpose
of the dam/reservoir governs the functional suitability of a site. The catchment
hydrology, available head and storage volume, etc, must be matched by the
operational parameters needed of the project.
Technical: Technical suitability is associated with the presence or absence of suitable
site for a dam, material of construction, and integrity of reservoir basin with respect to
leakage. Hydrological, geological/geotechnical characteristics of the catchment and
the site are the principal determinants establishing the technical suitability of a
reservoir site.
In addition, assessment of the anticipated environmental consequences of
construction and operation of the dam is needed to be evaluated to select site for
storage and dam construction.
The following are major considerations:
1. Major design inputs: geotechnical, structural, hydraulic, hydrologic, and
environmental impacts/effects;
2. Optimum design solutions: solutions of appropriate type of dam (no clear-cut-
rule) is derived from the above inputs with economic factors including
construction constraints;
3. As 2 (above) implies, there are frequently several alternative solutions, which
are of equal technical, but of different economic validity. Note that, both relative
economic validity and to a lesser extent technical validity are subject to change
as technology develops;
4. Each and every dam is quite unique solution to the problems of the site in
question, in terms of the balance of technical and economic factors at the time
of consideration.
Principal stages involving site appraisal and leading to selection of optimum type of
dam are indicated schematically in Figure 3.1 (after Novak, et al).
In order to meet the requirements of dam site investigation, design and construction, a
fully coordinated team of specialists is needed. A team of hydraulic, structural,
materials, and geotechnical engineers, geologists, and hydrologists should ensure
that all engineering and geological considerations are properly integrated into the
overall design.
PDE201 – Dam Engineering I
3-2
Figure 3.1 Stages in dam site appraisal and project development
Some of the principal aspects of the analysis and design process that require
coordination are (US Army Corps of Engineers):
a. Preliminary assessment of geological data, sub-surface conditions and rock
structure;
b. Selection of material properties, design parameters, loading conditions, loading
effects, potential mechanisms, and other related features of the analytical models;
c. Evaluation of the technical and economic feasibility of alternative type structures;
d. Constructibility reviews to see whether design assumptions and construction
procedures are compatible;
3 - 20
Time span (years)
1 - 3
2 - 4
Strategic planning:
Project initiation
Field reconnaissance Mapping, surveys, data
Collection
Field studies & technical resources,
Report options, etc.
Phase 1 dam site reservoir site
Evaluation evaluation
Confirmation of
Dam type
Phase 2 dam site
Investigation
Dam design
1 - 2
Construction foundation feedback 2 - 6
PDE201 – Dam Engineering I
3-3
e. Refinement of the preliminary structure configuration to reflect the results of
detailed site explorations, material availability studies, laboratory testing, and
numerical analysis;
f. Cofferdam and diversion layout, design and sequencing requirements;
g. Size and type of outlet works and spillways;
h. Modification to the structure configuration during construction due to unexpected
variations in the foundation conditions.
3.2 Collection of data
3.2.1 Physical and Topographic Data
Selection of dam and reservoir sites requires presence of suitable topography. The
topographic information can be obtained through site visit and from large-scale
topographic maps or aerial photographs. The criteria for the choice of the site include
investigation of:
Valley form
- Canyon (gorge)and V-shape: due to erosion,
- U-shape: due to glacier cut,
- Wide valley: due to strong bank erosion,
- Box valley: due to fluvial deposit on the other shapes.
The valley width at the dam site is required to be narrow and wide in the storage part.
Slope: upstream of the dam site, the possible small slope and downstream of the
dam site the possible large slope (by hydropower scheme).
In the collection of relevant topographic information, the following may be followed:
General Plan:
- Obtain a general plan of the catchment and project area from relevant sources
(e.g. EMA),
- Carry out limited survey to include additional information in this plan (aerial
reconnaissance, physical surveys, walkovers),
- It must include: the dam site, irrigable area/power house site, catchment area of
the stream, locality to be supplied with potable water, if any. Scale may vary from
1:1000 to 1:10,000.
The following features should also be included:
i Contours at 0.5 to 1.5 m interval,
ii Location of existing works, if any, affected by the proposed development,
iii Proposed relocation of roads, railways, transmission lines, etc.,
iv Additional transportation facilities such as access roads, cable ways, etc.,
required for the execution of the project,
v Locations of the stream gauging stations, water sampling and meteorological
stations, if any in the area.
PDE201 – Dam Engineering I
3-4
Larger Plans of the Dam and Spillway Sites:
These should be in the scale of 1:500 to 1:1000 with contours as close as possible.
These plans should show:
- Over banks,
- Location and elevation of all features such as buildings, roads, etc.,
- Location and numbering of test pits and borings.
3.2.2 Geotechnical and Geological Data
A geological map of the entire catchment and project area is essential. Investigation of
geological and geotechnical information on the origin, deposition, formation and
physical characteristics of the dam foundation and reservoir area are needed. As a
basis for the investigation, if there is no accurately describing geological map, such
maps are produced on large scale for the dam site and on small scale for reservoir
site.
Dam and Spillway Site
Subsurface investigation should be carried out by experienced geologist to obtain the
following:
- Geological section of the selected dam site,
- Quality of the overburden if an earth dam is to be built,
- Shearing strength of the material of overburden and of the dam material,
- Quantity and quality of the overburden material for construction purposes,
- Presence of joint planes, caverns, solution channels,
- Quality of the rock if concrete dam is to be built,
- Depth to which rock is weathered,
- Presence and extent of seams and joint planes (and orientations)
- Strength of the rock (hardness and durability),
- Availability of aggregate.
Reservoir Site
- Check the existence of cracks which are potential leakage sources,
- Banks should be checked for possible zones of landslide.
Earthquake
Information on seismic activity of the area should be obtained.
Here it is assumed that adequate knowledge of the relevant engineering geology, soil
mechanics and geotechnical parameters are acquired.
PDE201 – Dam Engineering I
3-5
3.2.3 Water Resources Data
Data regarding the following are required for water resources planning and reservoir
design:
- Catchment area;
- Discharge; daily/monthly volume of flow in the stream and peaks of stream flow at
or near dam site;
- Sediment carried by the stream;
- Maximum observed flood, report on damage caused by flood (extent of flood);
- Data establishing water demand (number of people to be served, approximate
maximum and minimum daily requirement, irrigation water requirement, other
requirements for industries, livestock, etc.);
- Meteorological data such as average temperature, average monthly rainfall,
maximum recorded storm intensities, rate of evaporation;
- Ground water level;
- Data on minimum downstream water requirements.
3.2.4 Project Development Data
Data such as agricultural, hydropower and other relevant data to the project purpose.
For irrigation purpose, for instance, the following data are essential for the
determination of water requirements:
- Size of the area to be irrigated,
- Soil structure;
- Possible types of crops;
- Types of soils along the conveyance canals.
3.2.5 Miscellaneous Data
- Materials data: soil, gravel and stone (for aggregate and riprap) are needed in
good quantity and quality for dam construction (possible borrow sites for these
materials should be identified), the borrow area should be within a reasonable
distance from the site. Selection of suitable borrow area is identified by:
 Thickness of the top organic soil which has to be discarded;
 Content of organic matter in the rest of the soil;
 Quantity of oversized cobbles, which would have to be removed from the soil.
- Rock for aggregate and riprap has to pass the standard tests of specific gravity,
absorption, abrasion, soundness, etc.;
- Erosion in the catchment area – identify sources of erosion;
- Transport – existing facilities and rates;
- Local labour availability and rate.
3.3 Investigations
The purpose of site or material investigation in the context of dam engineering is to
determine the suitability of the selected site for dam construction and reservoir storage
as well as to describe the geotechnical parameters necessary for the design and
construction of the structures.
PDE201 – Dam Engineering I
3-6
For such purposes, thus, general site exploration and investigation, in addition to the
above data collection, involve the following:
 Field investigation
 In situ tests/field tests
 Laboratory tests
3.4 Location of Dam
Influencing factors:
- Plan for the use of water,
- Width and shape of the valley,
- Load carrying capacity and impermeability of the foundation,
- Seepage loss in the reservoir area,
- Quantity, quality and transport distance of the construction materials,
- Suitability for appurtenant structures (bottom outlets, intakes, spillways,
powerhouses),
- Danger due to slide, avalanche, etc.,
- Influence on environment and landscape,
- Recreational value,
- Available storage area,
- Dam heightening and capacity augmentation possibilities,
- Cost,
- Social and political implications.
3.5 Height of Dam
The selection of the height of a dam is influenced by:
- Local topographic conditions,
- Dam type,
- Required storage,
- Finance.
3.6 Selection of Dam Type
Influencing factors:
- Topography (valley form),
- Foundation (suitability, impermeability),
- Geology (layers, fishers),
- Required height,
- Purpose of the dam,
- Climate,
- Flood spillway,
- Availability, quality (nature, state) of construction materials,
- Construction (supply, transport, equipment, qualification of personnel),
- Landscape,
- Cost (economy).
PDE201 – Dam Engineering I
3-7
It is necessary to make open the possible alternative solutions until an optimum
solution is found with respect to cost, construction program and available resource.
Novak, ET al., consider four cardinally important points in selection of dam type as:
1. Hydraulic Gradient: the nominal value of hydraulic gradient i for seepage
under, around or through the dam vary by at least one order of magnitude
according to type. The ability of softer and weaker or more erodible
foundations to resist high hydraulic gradients safely is very limited. Notional
values of gradient range from about 0.5 for a homogeneous embankment to
10 or more for a buttress or cupola dam,
2. Foundation Stress: nominal stresses transmitted to the foundation vary
greatly with dam type. The notional foundation stress values for 100m high
dam, for instance, varies from 1.8 MN/m² for embankment to 10 MN/m² for
arch dams (see Table 3.1),
3. Foundation Deformability: certain types of dams are better able to
accommodate significant foundation deformation and/or settlement without
serious damage,
4. Foundation Excavation: economic considerations dictate that the excavation
volume and foundation preparation should be minimized.
Table 3.1 Notional foundation stresses; 100 m height dam (Novak, et al, 1996)
Dam type Notional maximum stress
(MN/m²)
Embankment 1.8 – 2.1
Gravity 3.2 – 4.0
Buttress 5.5 – 7.5
Arch 7.5 – 10.0
Figure 3.2 illustrates examples of valley profiles with suggested dam type and
Table 3.2 provides type characteristics with respect to choice of dam (after Novak,
et al., 1996).
PDE201 – Dam Engineering I
3-8
Figure 3.2 Illustrative examples of dam type in relation to valley profile
Table 3.2 Dam selection: type characteristics.
Type Notes and characteristics
Embankment
Earthfill Suited to either soil or rock foundation and wide valleys; can accept
limited differential settlement given relatively wide and plastic core. Cut-
off to sound, i.e. less permeable, horizons required. Low contact
stresses. Requires range of materials, e.g. for core, shoulder zones,
internal filters, etc.
Rockfill Rock foundations preferable; can accept variable quality and limited
weathering. Cut-off to sound horizons required. Rockfill suitable for all
weather placing. Requires material for core, filters, etc.
Concrete
Gravity Suited to wide valleys, provided that excavation to rock is less than
about 5 m. Limited weathering of rock acceptable. Check discontinuities
in rock with regard to sliding. Moderate contact stress. Requires
imported cement.
Buttress As gravity dam, but higher contact stresses require sound rock.
Concrete saved relative to gravity dam 30 – 60%.
Arch and Cupola Suited to narrow gores, subject to uniform sound rock of high strength
and limited deformability in foundation & most particularly in abutments.
High abutment loading. Concrete saving relative to gravity dam is
50 – 85%

More Related Content

What's hot

A presentation of the main ground improvement techniques
A presentation of the main ground improvement techniquesA presentation of the main ground improvement techniques
A presentation of the main ground improvement techniquesSuper Arc Consultant
 
Geotechnical investigation for road work
Geotechnical investigation for road workGeotechnical investigation for road work
Geotechnical investigation for road workRakesh Meena
 
6 site investigation
6 site investigation6 site investigation
6 site investigationRaghav Gadgil
 
1892 soil investigation for foundations
1892 soil investigation for foundations1892 soil investigation for foundations
1892 soil investigation for foundationsChandra Mouli
 
Case study on burj khalifa FOUNDATION
Case study on burj khalifa FOUNDATIONCase study on burj khalifa FOUNDATION
Case study on burj khalifa FOUNDATIONShagun mahajan
 
Geotechnical engineering 2
Geotechnical engineering   2Geotechnical engineering   2
Geotechnical engineering 2R VIJAYAKUMAR
 
Introduction to Geotechnical Engineering SU - Fall 2015
Introduction to Geotechnical Engineering   SU - Fall 2015Introduction to Geotechnical Engineering   SU - Fall 2015
Introduction to Geotechnical Engineering SU - Fall 2015bhaladog
 
A case study on soft soil improvement of hanoi haiphong expressway project in...
A case study on soft soil improvement of hanoi haiphong expressway project in...A case study on soft soil improvement of hanoi haiphong expressway project in...
A case study on soft soil improvement of hanoi haiphong expressway project in...HoangTienTrung1
 
Site inveswtigation vandana miss
Site inveswtigation vandana missSite inveswtigation vandana miss
Site inveswtigation vandana missSHAMJITH KM
 
Applicability, quality control and quality assurance in
Applicability, quality control and quality assurance inApplicability, quality control and quality assurance in
Applicability, quality control and quality assurance inKulbir Singh gill
 
"A Review of Field Performance of Stone Columns in Soft Soils"
"A Review of Field Performance of Stone Columns in Soft Soils""A Review of Field Performance of Stone Columns in Soft Soils"
"A Review of Field Performance of Stone Columns in Soft Soils"Remedy Geotechnics Ltd
 
Soil cement walls for excavation support
Soil cement walls for excavation supportSoil cement walls for excavation support
Soil cement walls for excavation supportJim McMullan
 
soil_mechanics_lecture_slides
soil_mechanics_lecture_slidessoil_mechanics_lecture_slides
soil_mechanics_lecture_slidesMahendra Gattu
 
124 مبادرة #تواصل_تطوير -المركبات البوليمرية الجيوتقنية و تطبيقاتها في الهندس...
124 مبادرة #تواصل_تطوير -المركبات البوليمرية الجيوتقنية و تطبيقاتها في الهندس...124 مبادرة #تواصل_تطوير -المركبات البوليمرية الجيوتقنية و تطبيقاتها في الهندس...
124 مبادرة #تواصل_تطوير -المركبات البوليمرية الجيوتقنية و تطبيقاتها في الهندس...Egyptian Engineers Association
 
3.0 soil exploration
3.0 soil exploration3.0 soil exploration
3.0 soil explorationRakesh Reddy
 
Présentation de M. Naresh Gurpersaud (Keller) - SCG Ouest Québec
Présentation de M. Naresh Gurpersaud (Keller) - SCG Ouest QuébecPrésentation de M. Naresh Gurpersaud (Keller) - SCG Ouest Québec
Présentation de M. Naresh Gurpersaud (Keller) - SCG Ouest QuébecAlain Plaisant
 
Ground improvement techniques qb
Ground improvement techniques   qbGround improvement techniques   qb
Ground improvement techniques qbPreethi Abinaya
 

What's hot (20)

A presentation of the main ground improvement techniques
A presentation of the main ground improvement techniquesA presentation of the main ground improvement techniques
A presentation of the main ground improvement techniques
 
Geotechnical investigation for road work
Geotechnical investigation for road workGeotechnical investigation for road work
Geotechnical investigation for road work
 
6 site investigation
6 site investigation6 site investigation
6 site investigation
 
1892 soil investigation for foundations
1892 soil investigation for foundations1892 soil investigation for foundations
1892 soil investigation for foundations
 
Case study on burj khalifa FOUNDATION
Case study on burj khalifa FOUNDATIONCase study on burj khalifa FOUNDATION
Case study on burj khalifa FOUNDATION
 
Geotechnical engineering 2
Geotechnical engineering   2Geotechnical engineering   2
Geotechnical engineering 2
 
Lecture 4
Lecture 4Lecture 4
Lecture 4
 
Introduction to Geotechnical Engineering SU - Fall 2015
Introduction to Geotechnical Engineering   SU - Fall 2015Introduction to Geotechnical Engineering   SU - Fall 2015
Introduction to Geotechnical Engineering SU - Fall 2015
 
New Soil Investigation
New Soil InvestigationNew Soil Investigation
New Soil Investigation
 
A case study on soft soil improvement of hanoi haiphong expressway project in...
A case study on soft soil improvement of hanoi haiphong expressway project in...A case study on soft soil improvement of hanoi haiphong expressway project in...
A case study on soft soil improvement of hanoi haiphong expressway project in...
 
Site inveswtigation vandana miss
Site inveswtigation vandana missSite inveswtigation vandana miss
Site inveswtigation vandana miss
 
Applicability, quality control and quality assurance in
Applicability, quality control and quality assurance inApplicability, quality control and quality assurance in
Applicability, quality control and quality assurance in
 
"A Review of Field Performance of Stone Columns in Soft Soils"
"A Review of Field Performance of Stone Columns in Soft Soils""A Review of Field Performance of Stone Columns in Soft Soils"
"A Review of Field Performance of Stone Columns in Soft Soils"
 
Soil cement walls for excavation support
Soil cement walls for excavation supportSoil cement walls for excavation support
Soil cement walls for excavation support
 
soil_mechanics_lecture_slides
soil_mechanics_lecture_slidessoil_mechanics_lecture_slides
soil_mechanics_lecture_slides
 
124 مبادرة #تواصل_تطوير -المركبات البوليمرية الجيوتقنية و تطبيقاتها في الهندس...
124 مبادرة #تواصل_تطوير -المركبات البوليمرية الجيوتقنية و تطبيقاتها في الهندس...124 مبادرة #تواصل_تطوير -المركبات البوليمرية الجيوتقنية و تطبيقاتها في الهندس...
124 مبادرة #تواصل_تطوير -المركبات البوليمرية الجيوتقنية و تطبيقاتها في الهندس...
 
3.0 soil exploration
3.0 soil exploration3.0 soil exploration
3.0 soil exploration
 
Présentation de M. Naresh Gurpersaud (Keller) - SCG Ouest Québec
Présentation de M. Naresh Gurpersaud (Keller) - SCG Ouest QuébecPrésentation de M. Naresh Gurpersaud (Keller) - SCG Ouest Québec
Présentation de M. Naresh Gurpersaud (Keller) - SCG Ouest Québec
 
GeoManitobaPaper373
GeoManitobaPaper373GeoManitobaPaper373
GeoManitobaPaper373
 
Ground improvement techniques qb
Ground improvement techniques   qbGround improvement techniques   qb
Ground improvement techniques qb
 

Similar to Site Selection and Dam Type Determination

Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Mohit Shukla
 
Geotechnical investigations for tunnelling
Geotechnical  investigations for tunnellingGeotechnical  investigations for tunnelling
Geotechnical investigations for tunnellingProf. A.Balasubramanian
 
1.2 iii-gl for-planning_the_projects_on_run_of_river
1.2 iii-gl for-planning_the_projects_on_run_of_river1.2 iii-gl for-planning_the_projects_on_run_of_river
1.2 iii-gl for-planning_the_projects_on_run_of_riverRavi Naid Gorle
 
Geological investigation.pptx
Geological investigation.pptxGeological investigation.pptx
Geological investigation.pptxUmesh Yadav
 
Importance of geological considerations while choosing tunnel sites and align...
Importance of geological considerations while choosing tunnel sites and align...Importance of geological considerations while choosing tunnel sites and align...
Importance of geological considerations while choosing tunnel sites and align...Buddharatna godboley
 
Geotechnical studies_EG-Projects_17-01_2022.pptx
Geotechnical studies_EG-Projects_17-01_2022.pptxGeotechnical studies_EG-Projects_17-01_2022.pptx
Geotechnical studies_EG-Projects_17-01_2022.pptxKumarShubham771183
 
GI For Tunnel Projects
GI For Tunnel ProjectsGI For Tunnel Projects
GI For Tunnel ProjectsKeith Kong
 
Importance of geotechnical engineering knowledge to civil engineers.pdf
Importance of geotechnical engineering knowledge to civil engineers.pdfImportance of geotechnical engineering knowledge to civil engineers.pdf
Importance of geotechnical engineering knowledge to civil engineers.pdfankit482504
 
INTRODUCTION_AND_geotechnical_activities(2).pptx
INTRODUCTION_AND_geotechnical_activities(2).pptxINTRODUCTION_AND_geotechnical_activities(2).pptx
INTRODUCTION_AND_geotechnical_activities(2).pptxCarolTumaneng
 
Management of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsManagement of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsIRJET Journal
 
Management of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsManagement of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsIRJET Journal
 
Design-of-diversion-dam-in-tarbela-dam-pakistan.pptx
Design-of-diversion-dam-in-tarbela-dam-pakistan.pptxDesign-of-diversion-dam-in-tarbela-dam-pakistan.pptx
Design-of-diversion-dam-in-tarbela-dam-pakistan.pptxLeenaMujahed
 
Design of diversion dam in tarbela dam pakistan
Design of diversion dam in tarbela dam pakistanDesign of diversion dam in tarbela dam pakistan
Design of diversion dam in tarbela dam pakistanShoaib Madridista
 
L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3 L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3 Sachin PatiL
 
فصل اول.pdf
فصل اول.pdfفصل اول.pdf
فصل اول.pdfBlackJak2
 
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015Mohd Murtaza
 

Similar to Site Selection and Dam Type Determination (20)

Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
 
Geotechnical investigations for tunnelling
Geotechnical  investigations for tunnellingGeotechnical  investigations for tunnelling
Geotechnical investigations for tunnelling
 
IRTG ppt.pptx
IRTG ppt.pptxIRTG ppt.pptx
IRTG ppt.pptx
 
1.2 iii-gl for-planning_the_projects_on_run_of_river
1.2 iii-gl for-planning_the_projects_on_run_of_river1.2 iii-gl for-planning_the_projects_on_run_of_river
1.2 iii-gl for-planning_the_projects_on_run_of_river
 
Geological investigation.pptx
Geological investigation.pptxGeological investigation.pptx
Geological investigation.pptx
 
DAM ENGINEERING I.pptx
DAM ENGINEERING I.pptxDAM ENGINEERING I.pptx
DAM ENGINEERING I.pptx
 
Importance of geological considerations while choosing tunnel sites and align...
Importance of geological considerations while choosing tunnel sites and align...Importance of geological considerations while choosing tunnel sites and align...
Importance of geological considerations while choosing tunnel sites and align...
 
Geotechnical studies_EG-Projects_17-01_2022.pptx
Geotechnical studies_EG-Projects_17-01_2022.pptxGeotechnical studies_EG-Projects_17-01_2022.pptx
Geotechnical studies_EG-Projects_17-01_2022.pptx
 
GI For Tunnel Projects
GI For Tunnel ProjectsGI For Tunnel Projects
GI For Tunnel Projects
 
Importance of geotechnical engineering knowledge to civil engineers.pdf
Importance of geotechnical engineering knowledge to civil engineers.pdfImportance of geotechnical engineering knowledge to civil engineers.pdf
Importance of geotechnical engineering knowledge to civil engineers.pdf
 
INTRODUCTION_AND_geotechnical_activities(2).pptx
INTRODUCTION_AND_geotechnical_activities(2).pptxINTRODUCTION_AND_geotechnical_activities(2).pptx
INTRODUCTION_AND_geotechnical_activities(2).pptx
 
Unit1 hbn
Unit1 hbnUnit1 hbn
Unit1 hbn
 
LECT 2 - EARTHWORK.pdf
LECT 2 - EARTHWORK.pdfLECT 2 - EARTHWORK.pdf
LECT 2 - EARTHWORK.pdf
 
Management of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsManagement of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructions
 
Management of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructionsManagement of hydrogeological risks in underground constructions
Management of hydrogeological risks in underground constructions
 
Design-of-diversion-dam-in-tarbela-dam-pakistan.pptx
Design-of-diversion-dam-in-tarbela-dam-pakistan.pptxDesign-of-diversion-dam-in-tarbela-dam-pakistan.pptx
Design-of-diversion-dam-in-tarbela-dam-pakistan.pptx
 
Design of diversion dam in tarbela dam pakistan
Design of diversion dam in tarbela dam pakistanDesign of diversion dam in tarbela dam pakistan
Design of diversion dam in tarbela dam pakistan
 
L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3 L4 engineering surveys for highways 1.3
L4 engineering surveys for highways 1.3
 
فصل اول.pdf
فصل اول.pdfفصل اول.pdf
فصل اول.pdf
 
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015
 

More from FeteneBefekadu

More from FeteneBefekadu (20)

eca.ppt
eca.ppteca.ppt
eca.ppt
 
Belete Tafesse.pdf
Belete Tafesse.pdfBelete Tafesse.pdf
Belete Tafesse.pdf
 
TS8_1_belaid.pdf
TS8_1_belaid.pdfTS8_1_belaid.pdf
TS8_1_belaid.pdf
 
ERDAS_1.pdf
ERDAS_1.pdfERDAS_1.pdf
ERDAS_1.pdf
 
s552.pdf
s552.pdfs552.pdf
s552.pdf
 
stonemasonrybc-131212033019-phpapp01.pdf
stonemasonrybc-131212033019-phpapp01.pdfstonemasonrybc-131212033019-phpapp01.pdf
stonemasonrybc-131212033019-phpapp01.pdf
 
Slick.PDF
Slick.PDFSlick.PDF
Slick.PDF
 
stonemasonrybc-131212033019-phpapp01.pdf
stonemasonrybc-131212033019-phpapp01.pdfstonemasonrybc-131212033019-phpapp01.pdf
stonemasonrybc-131212033019-phpapp01.pdf
 
TSX_BBL_2017.pdf
TSX_BBL_2017.pdfTSX_BBL_2017.pdf
TSX_BBL_2017.pdf
 
sustainability-08-00403.pdf
sustainability-08-00403.pdfsustainability-08-00403.pdf
sustainability-08-00403.pdf
 
HCB Manual gtz 2008.doc
HCB Manual gtz 2008.docHCB Manual gtz 2008.doc
HCB Manual gtz 2008.doc
 
dolo_ix_None_Sample_Business_Plan_______ (2).pdf
dolo_ix_None_Sample_Business_Plan_______ (2).pdfdolo_ix_None_Sample_Business_Plan_______ (2).pdf
dolo_ix_None_Sample_Business_Plan_______ (2).pdf
 
Blockbooklet (1).pdf
Blockbooklet (1).pdfBlockbooklet (1).pdf
Blockbooklet (1).pdf
 
10.pdf
10.pdf10.pdf
10.pdf
 
Modern_Equipment_Calculations.pdf
Modern_Equipment_Calculations.pdfModern_Equipment_Calculations.pdf
Modern_Equipment_Calculations.pdf
 
concreteblocks (3).pdf
concreteblocks (3).pdfconcreteblocks (3).pdf
concreteblocks (3).pdf
 
Potential & experience of dams in ethiopia
Potential & experience of dams in ethiopiaPotential & experience of dams in ethiopia
Potential & experience of dams in ethiopia
 
Dam pictures
Dam picturesDam pictures
Dam pictures
 
Dam focus
Dam focusDam focus
Dam focus
 
Dam engineering 6
Dam engineering 6Dam engineering 6
Dam engineering 6
 

Recently uploaded

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 

Recently uploaded (20)

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 

Site Selection and Dam Type Determination

  • 1. PDE201 – Dam Engineering I 3-1 3 Site Investigation and Selectionof Dam Types 3.1 Introduction A dam and reservoir site must satisfy certain functional and technical requirements. Whether these requirements are satisfied can be found out through site investigations and technical evaluations. Functional: the balance between its natural physical characteristics and the purpose of the dam/reservoir governs the functional suitability of a site. The catchment hydrology, available head and storage volume, etc, must be matched by the operational parameters needed of the project. Technical: Technical suitability is associated with the presence or absence of suitable site for a dam, material of construction, and integrity of reservoir basin with respect to leakage. Hydrological, geological/geotechnical characteristics of the catchment and the site are the principal determinants establishing the technical suitability of a reservoir site. In addition, assessment of the anticipated environmental consequences of construction and operation of the dam is needed to be evaluated to select site for storage and dam construction. The following are major considerations: 1. Major design inputs: geotechnical, structural, hydraulic, hydrologic, and environmental impacts/effects; 2. Optimum design solutions: solutions of appropriate type of dam (no clear-cut- rule) is derived from the above inputs with economic factors including construction constraints; 3. As 2 (above) implies, there are frequently several alternative solutions, which are of equal technical, but of different economic validity. Note that, both relative economic validity and to a lesser extent technical validity are subject to change as technology develops; 4. Each and every dam is quite unique solution to the problems of the site in question, in terms of the balance of technical and economic factors at the time of consideration. Principal stages involving site appraisal and leading to selection of optimum type of dam are indicated schematically in Figure 3.1 (after Novak, et al). In order to meet the requirements of dam site investigation, design and construction, a fully coordinated team of specialists is needed. A team of hydraulic, structural, materials, and geotechnical engineers, geologists, and hydrologists should ensure that all engineering and geological considerations are properly integrated into the overall design.
  • 2. PDE201 – Dam Engineering I 3-2 Figure 3.1 Stages in dam site appraisal and project development Some of the principal aspects of the analysis and design process that require coordination are (US Army Corps of Engineers): a. Preliminary assessment of geological data, sub-surface conditions and rock structure; b. Selection of material properties, design parameters, loading conditions, loading effects, potential mechanisms, and other related features of the analytical models; c. Evaluation of the technical and economic feasibility of alternative type structures; d. Constructibility reviews to see whether design assumptions and construction procedures are compatible; 3 - 20 Time span (years) 1 - 3 2 - 4 Strategic planning: Project initiation Field reconnaissance Mapping, surveys, data Collection Field studies & technical resources, Report options, etc. Phase 1 dam site reservoir site Evaluation evaluation Confirmation of Dam type Phase 2 dam site Investigation Dam design 1 - 2 Construction foundation feedback 2 - 6
  • 3. PDE201 – Dam Engineering I 3-3 e. Refinement of the preliminary structure configuration to reflect the results of detailed site explorations, material availability studies, laboratory testing, and numerical analysis; f. Cofferdam and diversion layout, design and sequencing requirements; g. Size and type of outlet works and spillways; h. Modification to the structure configuration during construction due to unexpected variations in the foundation conditions. 3.2 Collection of data 3.2.1 Physical and Topographic Data Selection of dam and reservoir sites requires presence of suitable topography. The topographic information can be obtained through site visit and from large-scale topographic maps or aerial photographs. The criteria for the choice of the site include investigation of: Valley form - Canyon (gorge)and V-shape: due to erosion, - U-shape: due to glacier cut, - Wide valley: due to strong bank erosion, - Box valley: due to fluvial deposit on the other shapes. The valley width at the dam site is required to be narrow and wide in the storage part. Slope: upstream of the dam site, the possible small slope and downstream of the dam site the possible large slope (by hydropower scheme). In the collection of relevant topographic information, the following may be followed: General Plan: - Obtain a general plan of the catchment and project area from relevant sources (e.g. EMA), - Carry out limited survey to include additional information in this plan (aerial reconnaissance, physical surveys, walkovers), - It must include: the dam site, irrigable area/power house site, catchment area of the stream, locality to be supplied with potable water, if any. Scale may vary from 1:1000 to 1:10,000. The following features should also be included: i Contours at 0.5 to 1.5 m interval, ii Location of existing works, if any, affected by the proposed development, iii Proposed relocation of roads, railways, transmission lines, etc., iv Additional transportation facilities such as access roads, cable ways, etc., required for the execution of the project, v Locations of the stream gauging stations, water sampling and meteorological stations, if any in the area.
  • 4. PDE201 – Dam Engineering I 3-4 Larger Plans of the Dam and Spillway Sites: These should be in the scale of 1:500 to 1:1000 with contours as close as possible. These plans should show: - Over banks, - Location and elevation of all features such as buildings, roads, etc., - Location and numbering of test pits and borings. 3.2.2 Geotechnical and Geological Data A geological map of the entire catchment and project area is essential. Investigation of geological and geotechnical information on the origin, deposition, formation and physical characteristics of the dam foundation and reservoir area are needed. As a basis for the investigation, if there is no accurately describing geological map, such maps are produced on large scale for the dam site and on small scale for reservoir site. Dam and Spillway Site Subsurface investigation should be carried out by experienced geologist to obtain the following: - Geological section of the selected dam site, - Quality of the overburden if an earth dam is to be built, - Shearing strength of the material of overburden and of the dam material, - Quantity and quality of the overburden material for construction purposes, - Presence of joint planes, caverns, solution channels, - Quality of the rock if concrete dam is to be built, - Depth to which rock is weathered, - Presence and extent of seams and joint planes (and orientations) - Strength of the rock (hardness and durability), - Availability of aggregate. Reservoir Site - Check the existence of cracks which are potential leakage sources, - Banks should be checked for possible zones of landslide. Earthquake Information on seismic activity of the area should be obtained. Here it is assumed that adequate knowledge of the relevant engineering geology, soil mechanics and geotechnical parameters are acquired.
  • 5. PDE201 – Dam Engineering I 3-5 3.2.3 Water Resources Data Data regarding the following are required for water resources planning and reservoir design: - Catchment area; - Discharge; daily/monthly volume of flow in the stream and peaks of stream flow at or near dam site; - Sediment carried by the stream; - Maximum observed flood, report on damage caused by flood (extent of flood); - Data establishing water demand (number of people to be served, approximate maximum and minimum daily requirement, irrigation water requirement, other requirements for industries, livestock, etc.); - Meteorological data such as average temperature, average monthly rainfall, maximum recorded storm intensities, rate of evaporation; - Ground water level; - Data on minimum downstream water requirements. 3.2.4 Project Development Data Data such as agricultural, hydropower and other relevant data to the project purpose. For irrigation purpose, for instance, the following data are essential for the determination of water requirements: - Size of the area to be irrigated, - Soil structure; - Possible types of crops; - Types of soils along the conveyance canals. 3.2.5 Miscellaneous Data - Materials data: soil, gravel and stone (for aggregate and riprap) are needed in good quantity and quality for dam construction (possible borrow sites for these materials should be identified), the borrow area should be within a reasonable distance from the site. Selection of suitable borrow area is identified by:  Thickness of the top organic soil which has to be discarded;  Content of organic matter in the rest of the soil;  Quantity of oversized cobbles, which would have to be removed from the soil. - Rock for aggregate and riprap has to pass the standard tests of specific gravity, absorption, abrasion, soundness, etc.; - Erosion in the catchment area – identify sources of erosion; - Transport – existing facilities and rates; - Local labour availability and rate. 3.3 Investigations The purpose of site or material investigation in the context of dam engineering is to determine the suitability of the selected site for dam construction and reservoir storage as well as to describe the geotechnical parameters necessary for the design and construction of the structures.
  • 6. PDE201 – Dam Engineering I 3-6 For such purposes, thus, general site exploration and investigation, in addition to the above data collection, involve the following:  Field investigation  In situ tests/field tests  Laboratory tests 3.4 Location of Dam Influencing factors: - Plan for the use of water, - Width and shape of the valley, - Load carrying capacity and impermeability of the foundation, - Seepage loss in the reservoir area, - Quantity, quality and transport distance of the construction materials, - Suitability for appurtenant structures (bottom outlets, intakes, spillways, powerhouses), - Danger due to slide, avalanche, etc., - Influence on environment and landscape, - Recreational value, - Available storage area, - Dam heightening and capacity augmentation possibilities, - Cost, - Social and political implications. 3.5 Height of Dam The selection of the height of a dam is influenced by: - Local topographic conditions, - Dam type, - Required storage, - Finance. 3.6 Selection of Dam Type Influencing factors: - Topography (valley form), - Foundation (suitability, impermeability), - Geology (layers, fishers), - Required height, - Purpose of the dam, - Climate, - Flood spillway, - Availability, quality (nature, state) of construction materials, - Construction (supply, transport, equipment, qualification of personnel), - Landscape, - Cost (economy).
  • 7. PDE201 – Dam Engineering I 3-7 It is necessary to make open the possible alternative solutions until an optimum solution is found with respect to cost, construction program and available resource. Novak, ET al., consider four cardinally important points in selection of dam type as: 1. Hydraulic Gradient: the nominal value of hydraulic gradient i for seepage under, around or through the dam vary by at least one order of magnitude according to type. The ability of softer and weaker or more erodible foundations to resist high hydraulic gradients safely is very limited. Notional values of gradient range from about 0.5 for a homogeneous embankment to 10 or more for a buttress or cupola dam, 2. Foundation Stress: nominal stresses transmitted to the foundation vary greatly with dam type. The notional foundation stress values for 100m high dam, for instance, varies from 1.8 MN/m² for embankment to 10 MN/m² for arch dams (see Table 3.1), 3. Foundation Deformability: certain types of dams are better able to accommodate significant foundation deformation and/or settlement without serious damage, 4. Foundation Excavation: economic considerations dictate that the excavation volume and foundation preparation should be minimized. Table 3.1 Notional foundation stresses; 100 m height dam (Novak, et al, 1996) Dam type Notional maximum stress (MN/m²) Embankment 1.8 – 2.1 Gravity 3.2 – 4.0 Buttress 5.5 – 7.5 Arch 7.5 – 10.0 Figure 3.2 illustrates examples of valley profiles with suggested dam type and Table 3.2 provides type characteristics with respect to choice of dam (after Novak, et al., 1996).
  • 8. PDE201 – Dam Engineering I 3-8 Figure 3.2 Illustrative examples of dam type in relation to valley profile Table 3.2 Dam selection: type characteristics. Type Notes and characteristics Embankment Earthfill Suited to either soil or rock foundation and wide valleys; can accept limited differential settlement given relatively wide and plastic core. Cut- off to sound, i.e. less permeable, horizons required. Low contact stresses. Requires range of materials, e.g. for core, shoulder zones, internal filters, etc. Rockfill Rock foundations preferable; can accept variable quality and limited weathering. Cut-off to sound horizons required. Rockfill suitable for all weather placing. Requires material for core, filters, etc. Concrete Gravity Suited to wide valleys, provided that excavation to rock is less than about 5 m. Limited weathering of rock acceptable. Check discontinuities in rock with regard to sliding. Moderate contact stress. Requires imported cement. Buttress As gravity dam, but higher contact stresses require sound rock. Concrete saved relative to gravity dam 30 – 60%. Arch and Cupola Suited to narrow gores, subject to uniform sound rock of high strength and limited deformability in foundation & most particularly in abutments. High abutment loading. Concrete saving relative to gravity dam is 50 – 85%