SlideShare a Scribd company logo
The International Journal Of Engineering And Science (IJES)
|| Volume || 3 || Issue || 7 || Pages || 55-62 || 2014 ||
ISSN (e): 2319 – 1813 ISSN (p): 2319 – 1805
www.theijes.com The IJES Page 55
 Productivity Evaluation and Improvement of an Essential Balm
Manufacturing Plant Using a Time Study Approach
1
*O.A. Olalere, 2
P.A. Adedeji, 3
Adebimpe O.A., 4
B.Olayiwola
1-4
Department of Industrial and Production Engineering, University of Ibadan, Nigeria
----------------------------------------------------------ABSTRACT----------------------------------------------------------
The higher demand for essential balm during cold season accounted for the need to increasing production and
improving the product quality. This necessitated a change in the method of production from manual operation
(which involves the use of mainly the manual labourer) to a semi-automated operation. It is therefore
imperative to quantitatively justify the use of a semi- automated machine over the manual method of
production.
This work therefore evaluated the semi-automated system and manual method using the time study approach
which estimated the basic and standard time required for both methods. All the necessary cost inputs such as
the bill of materials, cost of power and other fixed cost such as depreciation were incorporated to obtain the
overall multi-factor productivity of each methods of production.
From the results obtained, the total standard time calculated from the semi-automated production
system provided a sharp reduction by 39hours 24minutes in the use of machine operation, given us a
percentage difference of 62.7% with the cost of production reduced by 30.20%. The productivity index when
the machine was used for production was 0.003 as compared to 0.02 from manual method. Productivity of the
machine operation is therefore greater by 33.3% as compared to that of manual operation. A critical
assessment of the productivities in essential balm production, justified that using the automated machine is
more productive in terms of ease, time, and economical point of view.
Keywords - Essential Balm, Semi-automated, Time Study, Multi-factor Productivity.
--------------------------------------------------------------------------------------------------------------------------------------
Date of Submission: 25 June 2014 Date of Publication: 20 July 2014
--------------------------------------------------------------------------------------------------------------------------------------
I. INTRODUCTION
The improvement of productivity of a manual work compared to the use of an automated machine
gives a desired expectation for a high quality and reliable goods. By this, the consumer has access to products
of higher design, quality, and functionality at lower prices. What makes the concept of productivity dominant
issues in the international market is that the consumers makes their buying decisions on product quality, and
sometimes are ready to pay more for what they consider as high quality product.
Productivity improvement and evaluation is therefore an integral strategy towards excellence in
manufacturing enterprise. It is an essential ingredient towards the attainment of a good financial and
operational performance. It enhances the customer’s satisfaction and reduces time and the cost to develop,
produce and deliver product and services. It therefore has a close relationship to performance measurement for
process utilization, process output, product cost, work-in-process inventory levels and on-time delivery. The
improvement of production processes can be in the form of elimination, correction of ineffective processes,
simplification of production processes, system optimization, throughput maximization, and reduction of set-
up time. This research work described the magnitude of change in the productivity when the company changed
from using manual production processes to the use of an automated machine. The improvement in the
productivity of the company per product is then quantified using the time study productivity approach to show
the production set-up time when an automated machine method is adopted
Productivity Evaluation and Improvement of an Essential Balm Manufacturing Plant...
www.theijes.com The IJES Page 56
II. PRODUCTIVITY AND PRODUCTIVITY IMPROVEMENT
Productivity is the quantitative relationship between what we produce and what we have spent on a
particular product and services. It is the ratio of output to input which ensures a reduction in the wastage of
resources like men, material, machine, time, space, capital etc (Stephenson,1999). It can be expressed as
human efforts to produce more and more with less and less inputs of resources so that there will be maximum
distribution of benefits among maximum number of people. Improving productivity means increasing or
raising productivity with the help of using same amount of materials, machine time, land, labour or
technology. Productivity denotes relationship between output and one or all associated inputs. It is a continual
effort to apply new techniques and methods to apply little input to obtain a higher output.
Patil (2007) defined productivity as a balance between all factors of production that will give the
maximum output with the smallest effort. These definitions apply to an enterprise, industry or an economy as a
whole. Therefore higher (improved) productivity means that more is produced with the same expenditure of
resource i.e. at the same cost in terms of land, materials, machine, time or labour, alternatively, it means same
amount is produced at less cost in terms of land, materials, machine time or labour that is utilized.
Productivity improvement techniques can be applied effectively to enterprises of any size, from one-
person companies to corporations with thousands of staff. The majority of the techniques were first seen in
mass-production operations but the benefits they can yield in SMEs are not to be underestimated. Indeed, the
absence in SMEs of many of the rigidities commonly found in large companies make it easier for them to reap
the benefits of productivity improvement techniques. Hence there is an increasing pressure on manufacturing
companies to exploit such methods to become agile manufacturers of mass-customised products (Lisa,2001).
III. WORK STUDY: A TOOL FOR PRODUCTIVITY IMPROVEMENT
Work study is an effective method used in evaluating the performance of a production plant. It breaks work into
smaller element, studies the task, and re-arrange it to obtain the same or an improved efficiency at a reduced cost.
According to the International Labour Organization ILO (1986),work study was defined as the technique of method and
time study(work measurement) which ensures the best use of material and human resources to carry out a specific task. It
is also a service/management-based method which examines the human work and investigate all the resources affecting the
efficiency and cost of production (Glossary B.S. 1969).It minimizes cost either by designing a new method of performing
the task for higher productivity or improving upon an existing method to effect a desired improvement. It is mostly used to
increase production from a given quantity of input resources with little or no additional cost input (Chester,1980). Hence
work study has a direct relation to productivity improvement.
The use of a bad operation or procedure to produce a particular product can hampered or delayed the
overall production time. This singular factor reduces the company’s productivity. To therefore reduce and
improve the productivity, work measurement can be used, and this is concerned with investing, reducing, and
eliminating ineffective time from the production effective time. According to Patil (2007),work measurement
or time study establishes volume of work to be done by an operator or labourer in a given time of a specified
task, under a specified condition and at a defined level of performance. It is therefore a scientific approach into
fixing production standard in term of the standard time in executing a specific task.
IV. RESEARCH METHOD
The time study was used for this study. It establish the time for an operator or labourer to execute the
task of producing the essential balm to a specified set of condition and under a defined level of
performance.Three time measures were used under this study, they include, the observed time, basic time ,and
the standard time. The time study equipment used included a stop watch, a study- board, and a time study
form. And following steps were followed to obtain the standard time of operation and subsequently calculated
the overall multi-factor productivity index for the balm manufacturing plant under study.
1. Select the task involved in producing an essential balm. This task include material preparation, heating
process, mixing process,cooling,pre-melting,filling,capping,labelling,arrangement,and packaging.
2. Selection of operator or labourer to be used for the study
3. Recording of details
4. Measurement of the duration of each work element
5. Estimating the time taken for each work element.
6. Converting the observed time to a normal time: The normal rating is measured in percentage.
Productivity Evaluation and Improvement of an Essential Balm Manufacturing Plant...
www.theijes.com The IJES Page 57
Basic time = ………………………………….………………….1
7. Calculating the relaxation and other allowances: Relaxation allowance may be determined scientifically
when observed time and performance rating are being recorded, depending on the nature of the work. Other
factors which contribute to time allowance include posture at work, type of motion of the body, eye or visual
strain and thermal conditions. There is also the contingency time allowance due to unanticipated official
disturbance to one at work. The value can be determined as a matter of policy in an establishment.. It requires
long periods of observations of task being performed. The total resting time the worker used during this period
of work may be expressed as a proportion of the total observation period (Owaba, 2002).
Relaxation Allowance + Contingency time was assumed to be 9% of basic time
8. Estimating the Standard time of production: This is calculated using the formula below.
Standard time =Basic time + (Relaxation time allowance + Contingency time allowance)…………2
The multi-factor productivity index for both the manual and semi-automated production is respectively
given below as:
……………..……………..…….3
………………………………………….…………..4
V. RESULTS AND DISCUSSION
The available task in terms of time units, were obtained using the three types of time measurement.
This includes the observed time, basic time and standard time. The normal time is the time a qualified worker
spent producing a bottle of balm, while basic time is the product of normalized speed and the observed time.
The standard time was the basic time the qualified worker takes to complete the producing the bottle of balm
plus the associated relaxation time. For the purpose of this study, time study was carried out for a period of 11
days of manual operation and 5days of machine production to be able to determine the time taken in producing
packet of balm. The production of 900 packets was observed during this period, and the time taken during the
operation was recorded for both the manual and machine operation. This was done with the aid of a stop
watch. The results were obtained using Matlab2012® and Microsoft Excel®, as shown in Table 5.0 and 5.1
5.1 ESTIMATING THE BILL OF MATERIALS
The bill of material was also obtained to obtain the quantity of raw material needed for production and
their corresponding price. Bill of raw materials obtainable as at April 2014 in Nigeria market is given below:
Table 5.0: Bill of Material Cost for producing 750 Packet of Rub
Raw Material Quantity Cost Total Costin
Naira
Petroleum Jelly 98kg N700 per kg 68,600
Methylsalicylate 24kg N1200 per kg 28,800
Peppermint Oil 10kg N500 per kg 5,000
Dyes 50g N2500 per 50g 2,500
Paraffin oil 10Litres N500 per Litre 5,000
Paraffin wax 5.9kg N200 per kg 1,180
Labeling 30 Rolls N350 per roll 10,500
Glass Bottles and
cover
750 bottle…I bottle is
N25
N300 per
dozen
18,750
Sources: Cost of Chemicals & Materials Nigeria Market from Afram Chemicals
Total Cost of Material = 140,330 Naira
Productivity Evaluation and Improvement of an Essential Balm Manufacturing Plant...
www.theijes.com The IJES Page 58
Fig.5.0: Bill of Material
5.2 COST IMPLICATION OF THE INPUT PARAMETERS
There are two types of cost which are the
1. Fixed costs
2. Variable costs
The fixed cost of tooling the machine and depreciation cost depreciation cost and do not vary as the output
varies
The variable costs are the costs which vary as the quantity of products made varies. E.g. direct labour cost,
material cost, fuel, power etc. The total cost is given by:
Total cost of production = fixed cost + variable cost
5.3 ESTIMATION THE COST INCURRED OF MANUAL OPERATION
The cost incurred using the manual labour is given in table 4.1 and Table 4.2 below:
Table 5.1: Data for the Man-Hour for Manual Labour
Observed Days(d) Number of Manual Labourer Hired Total Packet Produced
Monday 11 82
Tuesday 10 79
Wednesday 7 67
Thursday 8 66
Friday 10 100
SECOND WEEK OF MANUAL PRODUCTION
Monday 12 80
Tuesday 8 78
Wednesday 10 77
Thursday 8 84
Friday 8 104
Overtime 15 93
TOTAL PACKET PRODUCED FOR 1 BATCH = 900 PACKET
Source: Tisco Industrial Limited (Research & Development)
Given that Cost per Standard Labour-hour =N500
The Cost of Hiring Manual Labourers (Naira) for each day is given below as:
Number of Manual Labourer Hired(n) x Standard-Man-Hour(S) x Amount collected per hour
Cost of Hiring Manual Labourer = Cost per Standard Labour-hour x Number of Manual Labourer Hired
Productivity Evaluation and Improvement of an Essential Balm Manufacturing Plant...
www.theijes.com The IJES Page 59
Table 5.2: Results Generated for Man-Hour
Number
of
Manual
Laboure
r
Hired(n)
ProductionTim
e Per Day(Min)
BasicTim
e
Conting
.
Standard_Time(minutes
)
Standar
d
Man-
Hour(S)
Manual
Labourers(Naira
)
11 360 378.0000 34.0200 412.0200 6.8670 37,769
10 345 362.2500 32.6025 394.8525 6.5809 32,905
7 285 299.2500 26.9325 326.1825 5.4364 19,027
8 280 294.0000 26.4600 320.4600 5.3410 21,364
10 350 367.5000 33.0750 400.5750 6.6763 33,382
12 415 435.7500 39.2175 474.9675 7.9161 47,497
8 300 315.0000 28.3500 343.3500 5.7225 13,734
10 340 357.0000 32.1300 389.1300 6.4855 32,428
8 285 299.2500 26.9325 326.1825 5.4363 21,745
8 320 336.0000 30.2400 366.2400 6.1040 24,416
Total Standard Hour =62hours 57minutes
TOTAL COST INCURRED ON MANUAL LABOURERS =N284,266
5.4 ESTIMATING THE PRODUCTIVITY INDEX FOR MANUAL OPERATION
The total Cost incurred using the manual production technique = Fixed Cost + Variable Cost
The fixed cost are the costs that do not change with the change in the unit of balm produced within the
relevant range whereas variable cost changes with change in the units of balm produced per day.
Total Cost incurred on manual labour =N284, 266
Bill of Material =N140, 330
Heating Fuel =N 5,000
Variable Cost =Cost incurred on manual labour +Bill of Material +Heating Fuel
Variable Cost incurred using the manual production technique = 284,266 + 140,330 + 5,000 =N429, 596
The fixed cost is assumed to be negligible ≈ 0
Therefore the total cost input = N429, 596
The Productivity index for manual production is given below as:
= = 0.002
Therefore the productivity index using the manual method of operation is given as 0.002.
5.5 ESTIMATING THE COST INCURRED FOR MACHINEOPERATION
Table 5.3: Data for the Machine Hour
Observed Days Number of Workers on Duty Total Packet Produced
Monday 3 150
Tuesday 3 165
Wednesday 3 172
Thursday 3 200
Friday 3 213
Source: Tisco Industrial Limited (Research & Development)
Note:Estimated average time spent in producing one packet of the balm by Machine= 3mins
Productivity Evaluation and Improvement of an Essential Balm Manufacturing Plant...
www.theijes.com The IJES Page 60
Table 5.4: Results Generated for Machine-Hour
Number Trained
Operation
Production
Time Per
Day
Basic
Time
Conting+Relax Standard
Time(Min)
Standard
Machine
Hour
Cost of Trained
Operator/day (Naira)
3 200 240.000
0
21.6000 261.6000 4.3600 19,620
3 250 300.000
0
27.0000 327.0000 5.4500 24,620
3 150 180.000
0
16.2000 196.2000 3.2700 14,715
3 220 264.000
0
23.7600 287.7600 4.7960 21,582
3 250 300.000
0
27.0000 327.0000 5.4500 24,525
Total Standard machine Hour =23hours 33minutes
TOTAL COST INCURRED ON TRAINED OPERATOR =N129,492
Given that Cost per Standard Labour-hour of a trained operator =N1, 500
Fig.5.1: Depreciation Curve
The Cost of Hiring a trained operator(Naira) for each day is given below as:
Cost of Hiring trained operator= Number of trained operator Hired (n) x Standard Man-Hour(S) x Amount
collected per hour.
Fig.5.2: Interaction of Cost of Man-hour/Machine Hour on Standard Time
The above shows an interaction between the cost spent on both the manual labourer and that of a trained
machine operator for a certain period of operation.
5.6 ESTIMATING THE PRODUCTIVITY INDEX FOR MACHINEOPERATION
Variable Cost =Total Cost incurred on trained Operator +Bill of Material +Power
Total Cost incurred on trained Operator =N129, 492
Bill of Material =N140, 330
Power = N30, 000
Variable cost = 129,492+ 140,330 + 30,000 =299,822 Naira
Fixed cost=Cost of Maintenance + Depreciation cost for the machine
Productivity Evaluation and Improvement of an Essential Balm Manufacturing Plant...
www.theijes.com The IJES Page 61
Note: The maintenance cost is distributed over a period of 2 month. Hence it is not easy obtaining the accurate
amount spent on maintenance since we are dealing with a single production.The depreciation cost for the
machine.
Therefore Total cost of production of machine operation = 299,822 Naira
The Multi-factor Productivity index for machine operation is given below as:
= = 0.003
Therefore the productivity index using the manual method of operation is given as 0.003
5.7 ESTIMATING DEPRECIATION COST
The declining balance depreciation method uses the depreciable basis of the machine multiplied by a factor
based on the life of the asset. The depreciable basis of the asset is the book value of the fixed asset -- cost less
accumulated depreciation.
The machine was bought for $20,000 ≈ 3.2Million Naira (At N160 conversion rate to 1 US dollar).
The expected life of the automated filling machine is 10years.
Using double declining balance the depreciation would be calculated as follows:
factor = 2 * (1/10) = 0.20
Table 5.5 Depreciation Expenses of the Automated Machine
Year Depreciation
Basis(106
)
Depreciation
Calculation(106
)
Depreciation
Expenses(106
)
Accumulation
Depreciation (106
)
1 3.2000 3.2000 x 0.2 0.6400 0.6400
2 0.6400 0.6400 x 0.2 0.1280 0.7680
3 0.7680 0.7680 x 0.2 0.1536 0.9216
4 0.9216 0.9216 x 0.2 0.1843 1.1059
5 1.1059 1.1059 x 0.2 0.2212 1.3271
6 1.3271 1.3271 x 0.2 0.2654 1.5925
7 1.5925 1.5925 x 0.2 0.3185 1.9110
8 1.9110 1.9110 x 0.2 0.3822 2.2932
9 2.2932 2.2932 x 0.2 0.4586 2.7519
10 2.7519 2.7519 x 0.2 0.5504 3.3023
Note: The depreciation cost or depreciation expenses is a non-cash item i.e. no cash flows are involved as
depreciation cost is mere estimate and not a real cash outflow and thus can never be a relevant cost, therefore
the discussion whether a depreciation expenses is a fixed or variable cost in nature might be pointless.
5.7 ESTIMATING THE PERCENTAGE DIFFERENCE BETWEEN THE MANUAL AND MACHINE
OPERATION
The percentage increase in productivity was calculated as:
× 100
× 100 =33.33%
VI. DISCUSSION OF RESULTS
The summary of the above results is given below in Table 6.0
Productivity Evaluation and Improvement of an Essential Balm Manufacturing Plant...
www.theijes.com The IJES Page 62
Table 6.0: Summary of Estimated Results
Estimated Parameter Manual
Operation
Machine Operation Difference Percentage Difference
Total Standard Hour 62hours
57minutes
23hours 33minutes 39hours24minutes 62.7%
Labour Cost N284,266 N129,492 N154,774 54.4%
Cost of Production N429, 596 N299,822 N129,774 30.20%
Multi-factor Productivity Index 0.002 0.003 0.001 33.3%
From table 6.0, From the results obtained, the total standard time calculated from the manual production system
was gotten as 62hours 57minutes, whereas the value obtained for the machine operation is 23hours 33minutes.We can then
deduced that there is a sharp difference of 39hours 24minutes in the use of machine operation as compared to the manual
method of producing medicated balm, given us a percentage difference of 62.7%.
Similarly, the cost expended on the three operators using machine operation is less compared to that on the
manual labour, giving us a difference of N154,774 (54.4% difference).The same applied to the cost of production which
differs by N129,774.
From the two method of producing the essential balm, we can justify that we are able to save cost of production by
30.20%.
The productivity of the machine operation is therefore greater by 33.3% as compared to that of manual operation.
VII. CONCLUSION
A critical assessment of the production processes in essential balm production, inwe can justify that using the
automated machine is more productive in terms of time saving, economical consideration, ease of production. It is therefore
faster to adopt the automated machine than the manual production system. The time of production using the traditional
manual method is much when compared to the use of automated machine. The productivity index when the machine is
used for production was calculated as 0.003 as compared to 0.02 from manual method. This gives a 33.33% increment
when compared to the manual production.
The automated method would incur more cost, but a trade-off between the cost of setting up and the quality with
time saved is a gain for the company. Time saved is money saved.
REFERENCES
[1] Barker, A .M and Rollinus E.H,2009, “Motion and Time study: Design and Measurement,” Journal of Industrial Engineering,45 (8), pp
24-28.
[2] Barnes, R. M., 1998, Motion and Time study: Design and Measurement, John Wiley, London.
[3] Beverly, E., 1994, “Evaluating Knowledge Workers Productivity,” Thomas and John P. Baron.
[4] Black, S. & Lynch,1996, “Human-Capital Investments And Productivity, Technology, Human Capital and the Wage Structure,”
86.(2),pp.263 – 267.
[5] Carnevale, D.G., 1992, “Physical Settings of Work. Public Productivity and Management Review,” 15( 4), 423-436.
[6] Charles-Owaba O.E.,2002, Organizational Design: A Quantitative Approach, Oputoru Books, Ibadan.
[7] Chester L.Brisley,1979,”Work Measurement in the 1980‟s‟, 43rd Annual IMS Clinic Proceedings,” Industrial Management Society,
Des Plaines, IL.
[8] Chester L.B.,1978,“Comparison of Predetermined Time Systems (PTS)‟, Proceedings, AIIE spring Annual Conference, American
Institute of Industrial Engineers, Norcross, GA.
[10] Craig C.L.,1972, “Balancing Cost and Accuracy in Setting Up Standards for Work Measurement, Industrial Engineering,” 14,pp.82 –
92.
[11] Fritscher-Porter, K.,2003, “Ergonomic Advice,” Office Solutions, 20(1).
[16] Gilbert F.B. and L.B.,1984, “Classifying the element of work management and administration,” Journal of Industrial
Engineering,45(8),24-28.
[17] Gilhooley, M.J.,1999, “Green Green Grass of Work,” Facilities Design and Management, 21(9), pp.26-29.
[18] Glossary, B.S., 1969,”British Standards Institution: Glossary of terms used in Work Study,‟ London.
[19] Hicks P. E.,1994, Industrial Engineering and Management, a New perspective, 2nd Ed.,McGrew Hill Int Eel.
[20] International Labour Organisation,1986 “Introduction to Work Study”, Universal Publishing Corporation, India, PP.4.
[21] Jhamb L.C., 2006, Production (Operations) Management‟, Everest Publishing House, Pune, pp. 595-708.
[22] Kanaway G.,1992, Introduction to work study, International Labour Organisation, 4th Ed,Geneva.
[21] Keeling, B.L. and Kallaus, N.F.,1996, Administrative Office Management. 11th. Ed.
[22] Leaman, A, Bordass, B., “Building Design, Complexity and Manageability Facilities,” vol. 11(9),pp. 16-27, 1993.
[23] Leaman, A.,1995 “Dissatisfaction and Office Productivity,” Journal of Facilities Management, 13(2), ,pp. 3-19.
[24] Patil S. and Hukari N., 2007,”Industrial Engineering and Production and Operations Management”, 4th Edition, Electro-Tech
Publication, Satara, pp. 236.
[28] Smith, S. 2003,“Elements of Effective Ergonomics,” Industrial Engineer, 35(1), 49-52.
[29] Stevenson W.J.,1999, Production and Operations Management, Boston, MA: Irwin McGraw-Hill.
[30] Taylor F. W.,1929, The Principles of Scientific Management Harper and Bros:,New York.
[31] The Gensler Design + Performance Index, 2006,The U.S. Workplace Survey , www.gensler.com.
[32] Uzee, J., 1999,“The Inclusive Approach: Creating a Place Where People Want to Work.,” Facility Management Journal of the
International Facility Management Association,pp.26-30.

More Related Content

What's hot

IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
Journal For Research
 
Effect of work study & time study on production and quality
Effect of work study & time study on production and qualityEffect of work study & time study on production and quality
Effect of work study & time study on production and qualityMd. Mazadul Hasan Shishir
 
Productivity
ProductivityProductivity
Productivitybappykazi
 
Production And Operation Materials
Production And Operation MaterialsProduction And Operation Materials
Production And Operation Materials
pikuoec
 
Productivity of human resources
Productivity of human resourcesProductivity of human resources
Productivity of human resources
Selva Prakash
 
work study impact on productivity
work study impact on productivity work study impact on productivity
work study impact on productivity
Mohammad Younus
 
Effect of time and motion study
Effect of time and motion studyEffect of time and motion study
Effect of time and motion studyAnkur Shukla
 
Sumanth's total productivity model
Sumanth's total productivity modelSumanth's total productivity model
Sumanth's total productivity model
Anil Prajapati
 
Work study manual
Work study manualWork study manual
Work study manual
shamim hossain
 
Artistic apparel audit presentation ...
Artistic apparel audit presentation ...Artistic apparel audit presentation ...
Artistic apparel audit presentation ...Üzâîr Âhmêd
 
Productivity management
Productivity management   Productivity management
Productivity management
Nikhil Nimbarte
 
Industrial engineering for apparel production
Industrial engineering for apparel productionIndustrial engineering for apparel production
Industrial engineering for apparel production
Niloy Rahman
 
Introduction to work study
Introduction to work study Introduction to work study
Introduction to work study
safiqulislam728
 
Productivity
ProductivityProductivity
Productivity
J.T.A.JONES
 
Organisational Productivity
Organisational ProductivityOrganisational Productivity
Organisational Productivity
David Alman
 
Lecture notes of production & operation management
Lecture notes of production & operation managementLecture notes of production & operation management
Lecture notes of production & operation management
Complaint2015
 
Productivity Improvement R
Productivity Improvement RProductivity Improvement R
Productivity Improvement R
Syed Rashid Mubashir
 
project-presentation
project-presentationproject-presentation
project-presentationronybste
 
line balancing in garment industry
 line balancing in garment industry line balancing in garment industry
line balancing in garment industry
Lioul Mekonnen
 
Work study IEM unit v for MEs2
Work study   IEM unit v  for MEs2Work study   IEM unit v  for MEs2
Work study IEM unit v for MEs2
kishorereddy_btech
 

What's hot (20)

IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
IMPLEMENTATION OF LEAN MANUFACTURING TOOLS FOR IMPROVING PRODUCTIVITY: A CASE...
 
Effect of work study & time study on production and quality
Effect of work study & time study on production and qualityEffect of work study & time study on production and quality
Effect of work study & time study on production and quality
 
Productivity
ProductivityProductivity
Productivity
 
Production And Operation Materials
Production And Operation MaterialsProduction And Operation Materials
Production And Operation Materials
 
Productivity of human resources
Productivity of human resourcesProductivity of human resources
Productivity of human resources
 
work study impact on productivity
work study impact on productivity work study impact on productivity
work study impact on productivity
 
Effect of time and motion study
Effect of time and motion studyEffect of time and motion study
Effect of time and motion study
 
Sumanth's total productivity model
Sumanth's total productivity modelSumanth's total productivity model
Sumanth's total productivity model
 
Work study manual
Work study manualWork study manual
Work study manual
 
Artistic apparel audit presentation ...
Artistic apparel audit presentation ...Artistic apparel audit presentation ...
Artistic apparel audit presentation ...
 
Productivity management
Productivity management   Productivity management
Productivity management
 
Industrial engineering for apparel production
Industrial engineering for apparel productionIndustrial engineering for apparel production
Industrial engineering for apparel production
 
Introduction to work study
Introduction to work study Introduction to work study
Introduction to work study
 
Productivity
ProductivityProductivity
Productivity
 
Organisational Productivity
Organisational ProductivityOrganisational Productivity
Organisational Productivity
 
Lecture notes of production & operation management
Lecture notes of production & operation managementLecture notes of production & operation management
Lecture notes of production & operation management
 
Productivity Improvement R
Productivity Improvement RProductivity Improvement R
Productivity Improvement R
 
project-presentation
project-presentationproject-presentation
project-presentation
 
line balancing in garment industry
 line balancing in garment industry line balancing in garment industry
line balancing in garment industry
 
Work study IEM unit v for MEs2
Work study   IEM unit v  for MEs2Work study   IEM unit v  for MEs2
Work study IEM unit v for MEs2
 

Viewers also liked

D0363022039
D0363022039D0363022039
D0363022039
theijes
 
The International Journal of Engineering and Science
The International Journal of Engineering and ScienceThe International Journal of Engineering and Science
The International Journal of Engineering and Sciencetheijes
 
H0362053057
H0362053057H0362053057
H0362053057
theijes
 
The International Journal of Engineering and Science (IJES)
The International Journal of Engineering and Science (IJES)The International Journal of Engineering and Science (IJES)
The International Journal of Engineering and Science (IJES)
theijes
 
The International Journal of Engineering and Science
The International Journal of Engineering and ScienceThe International Journal of Engineering and Science
The International Journal of Engineering and Sciencetheijes
 
F0366041045
F0366041045F0366041045
F0366041045
theijes
 
P036401020107
P036401020107P036401020107
P036401020107
theijes
 
O03640900101
O03640900101O03640900101
O03640900101
theijes
 
F0363046051
F0363046051F0363046051
F0363046051
theijes
 
C0373013023
C0373013023C0373013023
C0373013023
theijes
 
I0373072083
I0373072083I0373072083
I0373072083
theijes
 
The International Journal of Engineering and Science (IJES)
The International Journal of Engineering and Science (IJES)The International Journal of Engineering and Science (IJES)
The International Journal of Engineering and Science (IJES)
theijes
 
The International Journal of Engineering and Science (IJES)
The International Journal of Engineering and Science (IJES)The International Journal of Engineering and Science (IJES)
The International Journal of Engineering and Science (IJES)
theijes
 
J0364057060
J0364057060J0364057060
J0364057060
theijes
 
G0373049057
G0373049057G0373049057
G0373049057
theijes
 
A03640106
A03640106A03640106
A03640106
theijes
 
A0363001009
A0363001009A0363001009
A0363001009
theijes
 
The International Journal of Engineering and Science
The International Journal of Engineering and ScienceThe International Journal of Engineering and Science
The International Journal of Engineering and Sciencetheijes
 

Viewers also liked (18)

D0363022039
D0363022039D0363022039
D0363022039
 
The International Journal of Engineering and Science
The International Journal of Engineering and ScienceThe International Journal of Engineering and Science
The International Journal of Engineering and Science
 
H0362053057
H0362053057H0362053057
H0362053057
 
The International Journal of Engineering and Science (IJES)
The International Journal of Engineering and Science (IJES)The International Journal of Engineering and Science (IJES)
The International Journal of Engineering and Science (IJES)
 
The International Journal of Engineering and Science
The International Journal of Engineering and ScienceThe International Journal of Engineering and Science
The International Journal of Engineering and Science
 
F0366041045
F0366041045F0366041045
F0366041045
 
P036401020107
P036401020107P036401020107
P036401020107
 
O03640900101
O03640900101O03640900101
O03640900101
 
F0363046051
F0363046051F0363046051
F0363046051
 
C0373013023
C0373013023C0373013023
C0373013023
 
I0373072083
I0373072083I0373072083
I0373072083
 
The International Journal of Engineering and Science (IJES)
The International Journal of Engineering and Science (IJES)The International Journal of Engineering and Science (IJES)
The International Journal of Engineering and Science (IJES)
 
The International Journal of Engineering and Science (IJES)
The International Journal of Engineering and Science (IJES)The International Journal of Engineering and Science (IJES)
The International Journal of Engineering and Science (IJES)
 
J0364057060
J0364057060J0364057060
J0364057060
 
G0373049057
G0373049057G0373049057
G0373049057
 
A03640106
A03640106A03640106
A03640106
 
A0363001009
A0363001009A0363001009
A0363001009
 
The International Journal of Engineering and Science
The International Journal of Engineering and ScienceThe International Journal of Engineering and Science
The International Journal of Engineering and Science
 

Similar to J0371055062

IRJET- Improving Productivity in a Mechanical Industry using Industrial Engin...
IRJET- Improving Productivity in a Mechanical Industry using Industrial Engin...IRJET- Improving Productivity in a Mechanical Industry using Industrial Engin...
IRJET- Improving Productivity in a Mechanical Industry using Industrial Engin...
IRJET Journal
 
Productivity improvement through lean deployment & work study methods
Productivity improvement through lean deployment & work study methodsProductivity improvement through lean deployment & work study methods
Productivity improvement through lean deployment & work study methods
eSAT Journals
 
I012536474
I012536474I012536474
I012536474
IOSR Journals
 
A case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringA case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ring
IJECSJournal
 
Industrial Engineering - Method Study
Industrial Engineering - Method StudyIndustrial Engineering - Method Study
Industrial Engineering - Method Study
josy2108
 
Productivity improvement through lean deployment &
Productivity improvement through lean deployment &Productivity improvement through lean deployment &
Productivity improvement through lean deployment &
eSAT Publishing House
 
IRJET- Application of Work Study in Construction Project
IRJET-  	  Application of Work Study in Construction ProjectIRJET-  	  Application of Work Study in Construction Project
IRJET- Application of Work Study in Construction Project
IRJET Journal
 
Production management
Production managementProduction management
Production management
Vivan Kumar
 
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
PERUMALSAMY M
 
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump IndustryManufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
IRJET Journal
 
IRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion Study
IRJET Journal
 
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET Journal
 
Productivity - Personnel Management
Productivity - Personnel ManagementProductivity - Personnel Management
Productivity - Personnel Management
MANNU KUMAR
 
A038301010
A038301010A038301010
A038301010
theijes
 
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET Journal
 
Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...
IRJET Journal
 
Productivity Improvement by Optimum Utilization of Plant Layout: A Case Study
Productivity Improvement by Optimum Utilization of Plant Layout: A Case StudyProductivity Improvement by Optimum Utilization of Plant Layout: A Case Study
Productivity Improvement by Optimum Utilization of Plant Layout: A Case Study
IRJET Journal
 
Production And Operation Materials
Production And Operation MaterialsProduction And Operation Materials
Production And Operation Materials
pikuoec
 
Industrial Engineering unit 4.Production planning and control Notes by badebhau.
Industrial Engineering unit 4.Production planning and control Notes by badebhau.Industrial Engineering unit 4.Production planning and control Notes by badebhau.
Industrial Engineering unit 4.Production planning and control Notes by badebhau.
Er. Bade Bhausaheb
 

Similar to J0371055062 (20)

IRJET- Improving Productivity in a Mechanical Industry using Industrial Engin...
IRJET- Improving Productivity in a Mechanical Industry using Industrial Engin...IRJET- Improving Productivity in a Mechanical Industry using Industrial Engin...
IRJET- Improving Productivity in a Mechanical Industry using Industrial Engin...
 
Productivity improvement through lean deployment & work study methods
Productivity improvement through lean deployment & work study methodsProductivity improvement through lean deployment & work study methods
Productivity improvement through lean deployment & work study methods
 
I012536474
I012536474I012536474
I012536474
 
A case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringA case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ring
 
Industrial Engineering - Method Study
Industrial Engineering - Method StudyIndustrial Engineering - Method Study
Industrial Engineering - Method Study
 
Productivity improvement through lean deployment &
Productivity improvement through lean deployment &Productivity improvement through lean deployment &
Productivity improvement through lean deployment &
 
IRJET- Application of Work Study in Construction Project
IRJET-  	  Application of Work Study in Construction ProjectIRJET-  	  Application of Work Study in Construction Project
IRJET- Application of Work Study in Construction Project
 
Production management
Production managementProduction management
Production management
 
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
 
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump IndustryManufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
 
IRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion Study
 
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining Cell
 
Productivity - Personnel Management
Productivity - Personnel ManagementProductivity - Personnel Management
Productivity - Personnel Management
 
Improving the productivity_and_introducing_the_work_study
Improving the productivity_and_introducing_the_work_studyImproving the productivity_and_introducing_the_work_study
Improving the productivity_and_introducing_the_work_study
 
A038301010
A038301010A038301010
A038301010
 
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
 
Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...
 
Productivity Improvement by Optimum Utilization of Plant Layout: A Case Study
Productivity Improvement by Optimum Utilization of Plant Layout: A Case StudyProductivity Improvement by Optimum Utilization of Plant Layout: A Case Study
Productivity Improvement by Optimum Utilization of Plant Layout: A Case Study
 
Production And Operation Materials
Production And Operation MaterialsProduction And Operation Materials
Production And Operation Materials
 
Industrial Engineering unit 4.Production planning and control Notes by badebhau.
Industrial Engineering unit 4.Production planning and control Notes by badebhau.Industrial Engineering unit 4.Production planning and control Notes by badebhau.
Industrial Engineering unit 4.Production planning and control Notes by badebhau.
 

Recently uploaded

一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 

Recently uploaded (20)

一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 

J0371055062

  • 1. The International Journal Of Engineering And Science (IJES) || Volume || 3 || Issue || 7 || Pages || 55-62 || 2014 || ISSN (e): 2319 – 1813 ISSN (p): 2319 – 1805 www.theijes.com The IJES Page 55  Productivity Evaluation and Improvement of an Essential Balm Manufacturing Plant Using a Time Study Approach 1 *O.A. Olalere, 2 P.A. Adedeji, 3 Adebimpe O.A., 4 B.Olayiwola 1-4 Department of Industrial and Production Engineering, University of Ibadan, Nigeria ----------------------------------------------------------ABSTRACT---------------------------------------------------------- The higher demand for essential balm during cold season accounted for the need to increasing production and improving the product quality. This necessitated a change in the method of production from manual operation (which involves the use of mainly the manual labourer) to a semi-automated operation. It is therefore imperative to quantitatively justify the use of a semi- automated machine over the manual method of production. This work therefore evaluated the semi-automated system and manual method using the time study approach which estimated the basic and standard time required for both methods. All the necessary cost inputs such as the bill of materials, cost of power and other fixed cost such as depreciation were incorporated to obtain the overall multi-factor productivity of each methods of production. From the results obtained, the total standard time calculated from the semi-automated production system provided a sharp reduction by 39hours 24minutes in the use of machine operation, given us a percentage difference of 62.7% with the cost of production reduced by 30.20%. The productivity index when the machine was used for production was 0.003 as compared to 0.02 from manual method. Productivity of the machine operation is therefore greater by 33.3% as compared to that of manual operation. A critical assessment of the productivities in essential balm production, justified that using the automated machine is more productive in terms of ease, time, and economical point of view. Keywords - Essential Balm, Semi-automated, Time Study, Multi-factor Productivity. -------------------------------------------------------------------------------------------------------------------------------------- Date of Submission: 25 June 2014 Date of Publication: 20 July 2014 -------------------------------------------------------------------------------------------------------------------------------------- I. INTRODUCTION The improvement of productivity of a manual work compared to the use of an automated machine gives a desired expectation for a high quality and reliable goods. By this, the consumer has access to products of higher design, quality, and functionality at lower prices. What makes the concept of productivity dominant issues in the international market is that the consumers makes their buying decisions on product quality, and sometimes are ready to pay more for what they consider as high quality product. Productivity improvement and evaluation is therefore an integral strategy towards excellence in manufacturing enterprise. It is an essential ingredient towards the attainment of a good financial and operational performance. It enhances the customer’s satisfaction and reduces time and the cost to develop, produce and deliver product and services. It therefore has a close relationship to performance measurement for process utilization, process output, product cost, work-in-process inventory levels and on-time delivery. The improvement of production processes can be in the form of elimination, correction of ineffective processes, simplification of production processes, system optimization, throughput maximization, and reduction of set- up time. This research work described the magnitude of change in the productivity when the company changed from using manual production processes to the use of an automated machine. The improvement in the productivity of the company per product is then quantified using the time study productivity approach to show the production set-up time when an automated machine method is adopted
  • 2. Productivity Evaluation and Improvement of an Essential Balm Manufacturing Plant... www.theijes.com The IJES Page 56 II. PRODUCTIVITY AND PRODUCTIVITY IMPROVEMENT Productivity is the quantitative relationship between what we produce and what we have spent on a particular product and services. It is the ratio of output to input which ensures a reduction in the wastage of resources like men, material, machine, time, space, capital etc (Stephenson,1999). It can be expressed as human efforts to produce more and more with less and less inputs of resources so that there will be maximum distribution of benefits among maximum number of people. Improving productivity means increasing or raising productivity with the help of using same amount of materials, machine time, land, labour or technology. Productivity denotes relationship between output and one or all associated inputs. It is a continual effort to apply new techniques and methods to apply little input to obtain a higher output. Patil (2007) defined productivity as a balance between all factors of production that will give the maximum output with the smallest effort. These definitions apply to an enterprise, industry or an economy as a whole. Therefore higher (improved) productivity means that more is produced with the same expenditure of resource i.e. at the same cost in terms of land, materials, machine, time or labour, alternatively, it means same amount is produced at less cost in terms of land, materials, machine time or labour that is utilized. Productivity improvement techniques can be applied effectively to enterprises of any size, from one- person companies to corporations with thousands of staff. The majority of the techniques were first seen in mass-production operations but the benefits they can yield in SMEs are not to be underestimated. Indeed, the absence in SMEs of many of the rigidities commonly found in large companies make it easier for them to reap the benefits of productivity improvement techniques. Hence there is an increasing pressure on manufacturing companies to exploit such methods to become agile manufacturers of mass-customised products (Lisa,2001). III. WORK STUDY: A TOOL FOR PRODUCTIVITY IMPROVEMENT Work study is an effective method used in evaluating the performance of a production plant. It breaks work into smaller element, studies the task, and re-arrange it to obtain the same or an improved efficiency at a reduced cost. According to the International Labour Organization ILO (1986),work study was defined as the technique of method and time study(work measurement) which ensures the best use of material and human resources to carry out a specific task. It is also a service/management-based method which examines the human work and investigate all the resources affecting the efficiency and cost of production (Glossary B.S. 1969).It minimizes cost either by designing a new method of performing the task for higher productivity or improving upon an existing method to effect a desired improvement. It is mostly used to increase production from a given quantity of input resources with little or no additional cost input (Chester,1980). Hence work study has a direct relation to productivity improvement. The use of a bad operation or procedure to produce a particular product can hampered or delayed the overall production time. This singular factor reduces the company’s productivity. To therefore reduce and improve the productivity, work measurement can be used, and this is concerned with investing, reducing, and eliminating ineffective time from the production effective time. According to Patil (2007),work measurement or time study establishes volume of work to be done by an operator or labourer in a given time of a specified task, under a specified condition and at a defined level of performance. It is therefore a scientific approach into fixing production standard in term of the standard time in executing a specific task. IV. RESEARCH METHOD The time study was used for this study. It establish the time for an operator or labourer to execute the task of producing the essential balm to a specified set of condition and under a defined level of performance.Three time measures were used under this study, they include, the observed time, basic time ,and the standard time. The time study equipment used included a stop watch, a study- board, and a time study form. And following steps were followed to obtain the standard time of operation and subsequently calculated the overall multi-factor productivity index for the balm manufacturing plant under study. 1. Select the task involved in producing an essential balm. This task include material preparation, heating process, mixing process,cooling,pre-melting,filling,capping,labelling,arrangement,and packaging. 2. Selection of operator or labourer to be used for the study 3. Recording of details 4. Measurement of the duration of each work element 5. Estimating the time taken for each work element. 6. Converting the observed time to a normal time: The normal rating is measured in percentage.
  • 3. Productivity Evaluation and Improvement of an Essential Balm Manufacturing Plant... www.theijes.com The IJES Page 57 Basic time = ………………………………….………………….1 7. Calculating the relaxation and other allowances: Relaxation allowance may be determined scientifically when observed time and performance rating are being recorded, depending on the nature of the work. Other factors which contribute to time allowance include posture at work, type of motion of the body, eye or visual strain and thermal conditions. There is also the contingency time allowance due to unanticipated official disturbance to one at work. The value can be determined as a matter of policy in an establishment.. It requires long periods of observations of task being performed. The total resting time the worker used during this period of work may be expressed as a proportion of the total observation period (Owaba, 2002). Relaxation Allowance + Contingency time was assumed to be 9% of basic time 8. Estimating the Standard time of production: This is calculated using the formula below. Standard time =Basic time + (Relaxation time allowance + Contingency time allowance)…………2 The multi-factor productivity index for both the manual and semi-automated production is respectively given below as: ……………..……………..…….3 ………………………………………….…………..4 V. RESULTS AND DISCUSSION The available task in terms of time units, were obtained using the three types of time measurement. This includes the observed time, basic time and standard time. The normal time is the time a qualified worker spent producing a bottle of balm, while basic time is the product of normalized speed and the observed time. The standard time was the basic time the qualified worker takes to complete the producing the bottle of balm plus the associated relaxation time. For the purpose of this study, time study was carried out for a period of 11 days of manual operation and 5days of machine production to be able to determine the time taken in producing packet of balm. The production of 900 packets was observed during this period, and the time taken during the operation was recorded for both the manual and machine operation. This was done with the aid of a stop watch. The results were obtained using Matlab2012® and Microsoft Excel®, as shown in Table 5.0 and 5.1 5.1 ESTIMATING THE BILL OF MATERIALS The bill of material was also obtained to obtain the quantity of raw material needed for production and their corresponding price. Bill of raw materials obtainable as at April 2014 in Nigeria market is given below: Table 5.0: Bill of Material Cost for producing 750 Packet of Rub Raw Material Quantity Cost Total Costin Naira Petroleum Jelly 98kg N700 per kg 68,600 Methylsalicylate 24kg N1200 per kg 28,800 Peppermint Oil 10kg N500 per kg 5,000 Dyes 50g N2500 per 50g 2,500 Paraffin oil 10Litres N500 per Litre 5,000 Paraffin wax 5.9kg N200 per kg 1,180 Labeling 30 Rolls N350 per roll 10,500 Glass Bottles and cover 750 bottle…I bottle is N25 N300 per dozen 18,750 Sources: Cost of Chemicals & Materials Nigeria Market from Afram Chemicals Total Cost of Material = 140,330 Naira
  • 4. Productivity Evaluation and Improvement of an Essential Balm Manufacturing Plant... www.theijes.com The IJES Page 58 Fig.5.0: Bill of Material 5.2 COST IMPLICATION OF THE INPUT PARAMETERS There are two types of cost which are the 1. Fixed costs 2. Variable costs The fixed cost of tooling the machine and depreciation cost depreciation cost and do not vary as the output varies The variable costs are the costs which vary as the quantity of products made varies. E.g. direct labour cost, material cost, fuel, power etc. The total cost is given by: Total cost of production = fixed cost + variable cost 5.3 ESTIMATION THE COST INCURRED OF MANUAL OPERATION The cost incurred using the manual labour is given in table 4.1 and Table 4.2 below: Table 5.1: Data for the Man-Hour for Manual Labour Observed Days(d) Number of Manual Labourer Hired Total Packet Produced Monday 11 82 Tuesday 10 79 Wednesday 7 67 Thursday 8 66 Friday 10 100 SECOND WEEK OF MANUAL PRODUCTION Monday 12 80 Tuesday 8 78 Wednesday 10 77 Thursday 8 84 Friday 8 104 Overtime 15 93 TOTAL PACKET PRODUCED FOR 1 BATCH = 900 PACKET Source: Tisco Industrial Limited (Research & Development) Given that Cost per Standard Labour-hour =N500 The Cost of Hiring Manual Labourers (Naira) for each day is given below as: Number of Manual Labourer Hired(n) x Standard-Man-Hour(S) x Amount collected per hour Cost of Hiring Manual Labourer = Cost per Standard Labour-hour x Number of Manual Labourer Hired
  • 5. Productivity Evaluation and Improvement of an Essential Balm Manufacturing Plant... www.theijes.com The IJES Page 59 Table 5.2: Results Generated for Man-Hour Number of Manual Laboure r Hired(n) ProductionTim e Per Day(Min) BasicTim e Conting . Standard_Time(minutes ) Standar d Man- Hour(S) Manual Labourers(Naira ) 11 360 378.0000 34.0200 412.0200 6.8670 37,769 10 345 362.2500 32.6025 394.8525 6.5809 32,905 7 285 299.2500 26.9325 326.1825 5.4364 19,027 8 280 294.0000 26.4600 320.4600 5.3410 21,364 10 350 367.5000 33.0750 400.5750 6.6763 33,382 12 415 435.7500 39.2175 474.9675 7.9161 47,497 8 300 315.0000 28.3500 343.3500 5.7225 13,734 10 340 357.0000 32.1300 389.1300 6.4855 32,428 8 285 299.2500 26.9325 326.1825 5.4363 21,745 8 320 336.0000 30.2400 366.2400 6.1040 24,416 Total Standard Hour =62hours 57minutes TOTAL COST INCURRED ON MANUAL LABOURERS =N284,266 5.4 ESTIMATING THE PRODUCTIVITY INDEX FOR MANUAL OPERATION The total Cost incurred using the manual production technique = Fixed Cost + Variable Cost The fixed cost are the costs that do not change with the change in the unit of balm produced within the relevant range whereas variable cost changes with change in the units of balm produced per day. Total Cost incurred on manual labour =N284, 266 Bill of Material =N140, 330 Heating Fuel =N 5,000 Variable Cost =Cost incurred on manual labour +Bill of Material +Heating Fuel Variable Cost incurred using the manual production technique = 284,266 + 140,330 + 5,000 =N429, 596 The fixed cost is assumed to be negligible ≈ 0 Therefore the total cost input = N429, 596 The Productivity index for manual production is given below as: = = 0.002 Therefore the productivity index using the manual method of operation is given as 0.002. 5.5 ESTIMATING THE COST INCURRED FOR MACHINEOPERATION Table 5.3: Data for the Machine Hour Observed Days Number of Workers on Duty Total Packet Produced Monday 3 150 Tuesday 3 165 Wednesday 3 172 Thursday 3 200 Friday 3 213 Source: Tisco Industrial Limited (Research & Development) Note:Estimated average time spent in producing one packet of the balm by Machine= 3mins
  • 6. Productivity Evaluation and Improvement of an Essential Balm Manufacturing Plant... www.theijes.com The IJES Page 60 Table 5.4: Results Generated for Machine-Hour Number Trained Operation Production Time Per Day Basic Time Conting+Relax Standard Time(Min) Standard Machine Hour Cost of Trained Operator/day (Naira) 3 200 240.000 0 21.6000 261.6000 4.3600 19,620 3 250 300.000 0 27.0000 327.0000 5.4500 24,620 3 150 180.000 0 16.2000 196.2000 3.2700 14,715 3 220 264.000 0 23.7600 287.7600 4.7960 21,582 3 250 300.000 0 27.0000 327.0000 5.4500 24,525 Total Standard machine Hour =23hours 33minutes TOTAL COST INCURRED ON TRAINED OPERATOR =N129,492 Given that Cost per Standard Labour-hour of a trained operator =N1, 500 Fig.5.1: Depreciation Curve The Cost of Hiring a trained operator(Naira) for each day is given below as: Cost of Hiring trained operator= Number of trained operator Hired (n) x Standard Man-Hour(S) x Amount collected per hour. Fig.5.2: Interaction of Cost of Man-hour/Machine Hour on Standard Time The above shows an interaction between the cost spent on both the manual labourer and that of a trained machine operator for a certain period of operation. 5.6 ESTIMATING THE PRODUCTIVITY INDEX FOR MACHINEOPERATION Variable Cost =Total Cost incurred on trained Operator +Bill of Material +Power Total Cost incurred on trained Operator =N129, 492 Bill of Material =N140, 330 Power = N30, 000 Variable cost = 129,492+ 140,330 + 30,000 =299,822 Naira Fixed cost=Cost of Maintenance + Depreciation cost for the machine
  • 7. Productivity Evaluation and Improvement of an Essential Balm Manufacturing Plant... www.theijes.com The IJES Page 61 Note: The maintenance cost is distributed over a period of 2 month. Hence it is not easy obtaining the accurate amount spent on maintenance since we are dealing with a single production.The depreciation cost for the machine. Therefore Total cost of production of machine operation = 299,822 Naira The Multi-factor Productivity index for machine operation is given below as: = = 0.003 Therefore the productivity index using the manual method of operation is given as 0.003 5.7 ESTIMATING DEPRECIATION COST The declining balance depreciation method uses the depreciable basis of the machine multiplied by a factor based on the life of the asset. The depreciable basis of the asset is the book value of the fixed asset -- cost less accumulated depreciation. The machine was bought for $20,000 ≈ 3.2Million Naira (At N160 conversion rate to 1 US dollar). The expected life of the automated filling machine is 10years. Using double declining balance the depreciation would be calculated as follows: factor = 2 * (1/10) = 0.20 Table 5.5 Depreciation Expenses of the Automated Machine Year Depreciation Basis(106 ) Depreciation Calculation(106 ) Depreciation Expenses(106 ) Accumulation Depreciation (106 ) 1 3.2000 3.2000 x 0.2 0.6400 0.6400 2 0.6400 0.6400 x 0.2 0.1280 0.7680 3 0.7680 0.7680 x 0.2 0.1536 0.9216 4 0.9216 0.9216 x 0.2 0.1843 1.1059 5 1.1059 1.1059 x 0.2 0.2212 1.3271 6 1.3271 1.3271 x 0.2 0.2654 1.5925 7 1.5925 1.5925 x 0.2 0.3185 1.9110 8 1.9110 1.9110 x 0.2 0.3822 2.2932 9 2.2932 2.2932 x 0.2 0.4586 2.7519 10 2.7519 2.7519 x 0.2 0.5504 3.3023 Note: The depreciation cost or depreciation expenses is a non-cash item i.e. no cash flows are involved as depreciation cost is mere estimate and not a real cash outflow and thus can never be a relevant cost, therefore the discussion whether a depreciation expenses is a fixed or variable cost in nature might be pointless. 5.7 ESTIMATING THE PERCENTAGE DIFFERENCE BETWEEN THE MANUAL AND MACHINE OPERATION The percentage increase in productivity was calculated as: × 100 × 100 =33.33% VI. DISCUSSION OF RESULTS The summary of the above results is given below in Table 6.0
  • 8. Productivity Evaluation and Improvement of an Essential Balm Manufacturing Plant... www.theijes.com The IJES Page 62 Table 6.0: Summary of Estimated Results Estimated Parameter Manual Operation Machine Operation Difference Percentage Difference Total Standard Hour 62hours 57minutes 23hours 33minutes 39hours24minutes 62.7% Labour Cost N284,266 N129,492 N154,774 54.4% Cost of Production N429, 596 N299,822 N129,774 30.20% Multi-factor Productivity Index 0.002 0.003 0.001 33.3% From table 6.0, From the results obtained, the total standard time calculated from the manual production system was gotten as 62hours 57minutes, whereas the value obtained for the machine operation is 23hours 33minutes.We can then deduced that there is a sharp difference of 39hours 24minutes in the use of machine operation as compared to the manual method of producing medicated balm, given us a percentage difference of 62.7%. Similarly, the cost expended on the three operators using machine operation is less compared to that on the manual labour, giving us a difference of N154,774 (54.4% difference).The same applied to the cost of production which differs by N129,774. From the two method of producing the essential balm, we can justify that we are able to save cost of production by 30.20%. The productivity of the machine operation is therefore greater by 33.3% as compared to that of manual operation. VII. CONCLUSION A critical assessment of the production processes in essential balm production, inwe can justify that using the automated machine is more productive in terms of time saving, economical consideration, ease of production. It is therefore faster to adopt the automated machine than the manual production system. The time of production using the traditional manual method is much when compared to the use of automated machine. The productivity index when the machine is used for production was calculated as 0.003 as compared to 0.02 from manual method. This gives a 33.33% increment when compared to the manual production. The automated method would incur more cost, but a trade-off between the cost of setting up and the quality with time saved is a gain for the company. Time saved is money saved. REFERENCES [1] Barker, A .M and Rollinus E.H,2009, “Motion and Time study: Design and Measurement,” Journal of Industrial Engineering,45 (8), pp 24-28. [2] Barnes, R. M., 1998, Motion and Time study: Design and Measurement, John Wiley, London. [3] Beverly, E., 1994, “Evaluating Knowledge Workers Productivity,” Thomas and John P. Baron. [4] Black, S. & Lynch,1996, “Human-Capital Investments And Productivity, Technology, Human Capital and the Wage Structure,” 86.(2),pp.263 – 267. [5] Carnevale, D.G., 1992, “Physical Settings of Work. Public Productivity and Management Review,” 15( 4), 423-436. [6] Charles-Owaba O.E.,2002, Organizational Design: A Quantitative Approach, Oputoru Books, Ibadan. [7] Chester L.Brisley,1979,”Work Measurement in the 1980‟s‟, 43rd Annual IMS Clinic Proceedings,” Industrial Management Society, Des Plaines, IL. [8] Chester L.B.,1978,“Comparison of Predetermined Time Systems (PTS)‟, Proceedings, AIIE spring Annual Conference, American Institute of Industrial Engineers, Norcross, GA. [10] Craig C.L.,1972, “Balancing Cost and Accuracy in Setting Up Standards for Work Measurement, Industrial Engineering,” 14,pp.82 – 92. [11] Fritscher-Porter, K.,2003, “Ergonomic Advice,” Office Solutions, 20(1). [16] Gilbert F.B. and L.B.,1984, “Classifying the element of work management and administration,” Journal of Industrial Engineering,45(8),24-28. [17] Gilhooley, M.J.,1999, “Green Green Grass of Work,” Facilities Design and Management, 21(9), pp.26-29. [18] Glossary, B.S., 1969,”British Standards Institution: Glossary of terms used in Work Study,‟ London. [19] Hicks P. E.,1994, Industrial Engineering and Management, a New perspective, 2nd Ed.,McGrew Hill Int Eel. [20] International Labour Organisation,1986 “Introduction to Work Study”, Universal Publishing Corporation, India, PP.4. [21] Jhamb L.C., 2006, Production (Operations) Management‟, Everest Publishing House, Pune, pp. 595-708. [22] Kanaway G.,1992, Introduction to work study, International Labour Organisation, 4th Ed,Geneva. [21] Keeling, B.L. and Kallaus, N.F.,1996, Administrative Office Management. 11th. Ed. [22] Leaman, A, Bordass, B., “Building Design, Complexity and Manageability Facilities,” vol. 11(9),pp. 16-27, 1993. [23] Leaman, A.,1995 “Dissatisfaction and Office Productivity,” Journal of Facilities Management, 13(2), ,pp. 3-19. [24] Patil S. and Hukari N., 2007,”Industrial Engineering and Production and Operations Management”, 4th Edition, Electro-Tech Publication, Satara, pp. 236. [28] Smith, S. 2003,“Elements of Effective Ergonomics,” Industrial Engineer, 35(1), 49-52. [29] Stevenson W.J.,1999, Production and Operations Management, Boston, MA: Irwin McGraw-Hill. [30] Taylor F. W.,1929, The Principles of Scientific Management Harper and Bros:,New York. [31] The Gensler Design + Performance Index, 2006,The U.S. Workplace Survey , www.gensler.com. [32] Uzee, J., 1999,“The Inclusive Approach: Creating a Place Where People Want to Work.,” Facility Management Journal of the International Facility Management Association,pp.26-30.