This document discusses improving productivity at a thermocole manufacturing plant through time study and motion study. It was found that delays between tasks were affecting production rates. Time study and motion study techniques from work study were used to analyze the processes. The analysis found a lack of proper time standards, uneven task distribution, inefficient space utilization, safety issues, and communication problems. After conducting time studies and setting proper time standards, production increased by 48 extra pieces per month on one machine. Implementing standards from time study and motion study analysis can effectively improve productivity by reducing delays in work processes.