International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072
One Day National Conference on Recent Advancement in Civil Engineering (RACE 2K19)
25th February 2019
Organized by
Department of Civil Engineering, T John Institute of Technology, Bangalore-83
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1906
CONSTRUCTION APPROACH AND SCHEDULE TECHNICAL FOR
TREATMENT PLANT
Rejo George1, Gokul2
1PG Scholar Department of Civil Engineering, EASA College of Engineering and Technology (ECET),
Coimbatore, Tamil Nadu, India.
2Assistant Professor Department of Civil Engineering, EASA College of Engineering and Technology (ECET)
Coimbatore, Tamil Nadu, India.
-------------------------------------------------------------------------***----------------------------------------------------------------------
Abstract:- Construction of the Waste Treatment Plant will occur over multiple phases for various aspects of the work. Each
work phase will require different resource levels, staging requirements, materials, equipment, and overall durations. In
addition, each phase will result in varying impacts to the site and its surrounding area in terms of noise and vibration, dust,
light and glare, erosion, traffic impacts, and workforce requirements. The following sections provide a discussion of the major
phases that are anticipated to occur over the course of the plant construction, and the expected impacts that will result during
each phase. Work described herein is related to the construction of the 36 mgd treatment plant required by 2019. Work related
to future capacity expansions is not accounted for in this document.
Index Terms:-Treatment plant, construction, scheduling, pri- mavera, EVM,
I. INTRODUCTION
Since the 1960s INDIA has been designing and constructing regional wastewater treatment and collection systems. Begin- ning
with the initial treatment plants at Renton and West Point, the organization that is now the Wastewater Treatment Division
within the Department of Natural Resources and Parks has expanded treatment capacity, improved the level of treatment, and
built collection systems as necessary to respond to the growth of the region over the past 40 years.
There have been major upgrades and expansions to wastewater treatment and conveyance facilities in the 1980s and 1990s.
The work performed as part of those expansions and upgrades resulted in high-quality and reliable facilities that have
performed to required standards for many years. As these projects were constructed, the work conformed to rigorous
schedules and budgetary controls, as well as environmental controls. The work was also performed in a manner that
recognized and addressed local community concerns related to construction.
The Brightwater System will be implemented using approaches and methods of construction that have been successfully
utilized on similar projects in the past and that are safe, reasonable and reliable approaches in the construction industry today.
This TM describes the major elements of work required for the Brightwater Program, provides descriptions of the anticipated
processes for performing the work and provides the anticipated schedule for each activity. It describes the anticipated impacts
at each major work location, including proposed wastewater treatment facilities, conveyance systems and marine outfall
alternatives as described in the Brightwater Draft Environmental Impact Statement (DEIS).
II. LITERATURE REVIEW
This literature review on wastes from water treatment plants discusses previous literature reviews on the subject, sources and
types of waste, characteristics of each type of waste, and waste management. The discussion of management of sludge (waste)
covers minimizing sludge production, methods of sludge treatment, and ultimate sludge disposal.
During the period 1969 to 1981 the American Water Works Association (AWWA) Research Foundation and the AWWA Sludge
Disposal Committee prepared a series of reports with a comprehensive literature review on the nature and solutions of water
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072
One Day National Conference on Recent Advancement in Civil Engineering (RACE 2K19)
25th February 2019
Organized by
Department of Civil Engineering, T John Institute of Technology, Bangalore-83
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1907
treatment plant waste disposal problems. The first report, prepared by the AWWA Research Foundation, was divided into four
parts (AWWA Research Foundation, 1969a, 1969b, 1969c, 1970) and was entitled”Disposal of Wastes from Water Treatment
Plants.” The first part of this report (AWWA, 1969a) covered the status of research and engineering practices for treating
various wastes from water treatment plants. The second part (AWWA, 1969b) reviewed plant operations for the disposal of
various types of wastes, and the regulatory aspects of disposal. The third part (AWWA, 1969c) described various treatment
processes employed and their efficiency and degree of success, and presented cost analyses. The last part (AWWA, 1970)
summarized research needs, engineering needs, plant operation needs, and regulatory needs.
In 1972, the AWWA Disposal of Water Treatment Plant Waste Committee published an updated report (AWWA, 1972). It dealt
with processing and re-processing in sludge production, i.e., selection and modification of treatment processes, reclamation of
lime and alum, recovery of filter backwash water, processing of wastes to recover useful by-products, processing of wastes for
disposal, ultimate disposal, and future research needs.
In 1978, the AWWA Sludge Disposal Committee prepared a 2-part article (AWWA Sludge Disposal Committee, 1978a, 1978b)
entitled”Water Treatment Plant Sludge an Update of the State of the Art.” Part 1 dealt with regulatory requirements, sludge
production and characteristics, minimizing of waste production, and European and Japanese practices. Part 2 de- tailed non-
mechanical and mechanical methods of dewatering water plant sludges, ultimate solids disposal, and research and
development needs. These reports focused mainly on coagulant sludges. In 1981, the AWWA Sludge Disposal Committee
provided an overview of the production, processing, and disposal of lime-softening sludges; recent technological advances in
handling, treatment, and disposal of softening sludges; and research needs (AWWA, 1981).
III. METHODOLOGY
The construction projects are so vast and complex in nature and therefore for simplification of work, use of softwares came
into existence. The project was scheduled and monitored using Primavera P6 software. Primavera is the Project Management
software use for Planning, Scheduling and Controlling the Construction Project. The steps involved in treatment plant are
Earthwork, Concrete Work, Brickwork, Plastering, Flooring, Plumbing etc.
The WBS for the project is created and several activities are identified. The durations of the activities are estimated on basis of
Historical data, interviews with project manager, applying labour productivity factor formulae and application of analysis of
rates. The relationships are examined and applied to the activities. The following procedure involved in scheduling and
monitoring projects.
A. Objective of Study
The objectives of this study are:
• Toidentify construction sequence for a treatment plant construction.
• Towork out the practical durations required to carry out the activities.
• Toidentify scheduling technique used by the organization in developing plan and scheduling.
• Todevelop scheduling using Primavera project planners software.
• Totrack the project and analyse the reasons for delays, and increase in estimated budget etc.
• To investigate defects in the planning and scheduling procedure of the organization, and suggest suitable improvements
in their methods.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072
One Day National Conference on Recent Advancement in Civil Engineering (RACE 2K19)
25th February 2019
Organized by
Department of Civil Engineering, T John Institute of Technology, Bangalore-83
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1908
B. Use of PMS in construction
The construction industry has a poor image in general. In 1999 alone, in the India, the industries spent more than 1 billion
on rework and in 2003, more than 1 5 billion on performance measurement applications .In spite of high expenditure,
only 34% of construction projects today meet the iron triangle criteria. During the review we found Primavera and MS Project
to be the most frequent PMS used in the construction industry .In the India, over 64 of construction companies indicated
Primavera as their specified software, with only just over 20 % requiring the MS Project.
Primary reasons for using a PMS in the US construction industry were (in ascending order) a periodic control of work after the
start of construction, development of ’look ahead’ schedules, coordination of subcontractors, detailed planning of work prior
to construction, schedule impact, claims analysis, tracking of changes, coordination of own trades, estimating and bidding,
tracking shop drawings and submits, calculating payment requests for work performed, design development, operation and
maintenance of projects, tracking costs and materials planning. This affirms that the construction industry still sees and
acknowledges the PM mainly as Critical Path Method (CPM). Nonetheless, it is encouraging that academia anticipates that by
the end of this decade, the industry will have implemented the PMS in their day-to-day business. Furthermore, in the area of IS,
a resource and an IT management have become the most frequent topics of discussions today.
1) PMS in the SEE construction: The construction industry in the SEE has even lower performance than that of the developed
countries. Following the end of the socialist regime, where software development was mostly carried out through the internal
IS functions of a large government controlled enterprises the economic and political pressures have been forcing the industry
to change its everyday processes listed the purposes for the IS use in the SEE construction industry: 98 % for accounting and
bookkeeping, 89,8 % for personnel management, 79,6 % for spreadsheets, 73,5 % for cost prediction, bidding and Bills of
Quantities (BoQ), 53,1 % for CAD and only 28,6 % for scheduling. This indicates that the sector is still trying to Cope with
traditional management procedures through accounting and that the SEE is still a transitional economy.
In addition, the SEE construction has a specific business culture. Unlike the US, the SEE countries have a strict law regulation
that defines project stakeholders. There are three main management perspectives: investors (sponsors, developers),
consultants (project managers, designers, architects, supervision) and contractors. Owing to the former socialist regime policy,
the project management is still unknown to the construction companies. It was introduced into the Croatian regulations only
recently, in 2008, while Slovenia and Bosnia and Herzegovina still have no such terminology in place. Furthermore,
construction companies are not allowed to appear in projects of two different functions at the same time, for instance in a
project management and building or a project management and design. Hence, the ’Design and Build’ types of projects are not
allowed by the law in Croatia. Construction projects are under strict government control and their performance has to be
reported by the law defined templates. This is mainly the responsibility of the supervision and the contractor. For this reason,
the supervision and the contractors are actually the ones who manage projects, while project managers are often put aside and
seen as an obstruction to the construction process.
C. Construction, Planning, and Scheduling Tracking
1) Construction Planning: Construction planning is a fundamental and challenging activity in management and execution of
construction projects. It includes the selection of technology, the definition of work task, the estimation of required
durations and resources of individual task, and identify the interactions between different work tasks. A good construction
plan is the base for developing the schedule and the budget for work. Developing the construction plan is acritical task in
construction management, even if the plan isnot written or else for ly recorded.
During planning a planner begins with a result (a design) and he must synthesize the steps required to yield this result. The
necessary aspects of construction planning include the generation of required activities, analysis of the implications of these
activities and the choice among various alternatives methods of performing these activities. A planner must imagine the final
design and describe it in plans and specifications. In developing a construction plan the importance is given either cost or
schedule. Some projects a primarily divided into expense categories with associated cost in these cases planning is cost
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072
One Day National Conference on Recent Advancement in Civil Engineering (RACE 2K19)
25th February 2019
Organized by
Department of Civil Engineering, T John Institute of Technology, Bangalore-83
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1909
oriented. In this category, a distinction is made between cost incurred directly in the performance of the activity and indirectly
for the accomplishment of the project.
For other projects where time is a critical or the planner ensures that proper predeceasing among activities is maintained and
that efficient scheduling of the available resource prevails. In such cases a critical path scheduling procedure is followed. Finally
most of the complex projects require considerations of both cost and schedule over time, so that planning; monitoring and
record keeping must be considered in both dimensions. In these cases integration of budget and scheduling information is a
major concern.
2) Scheduling: Scheduling is determination the timing of events in the project that is when and which task will be performed?
Putting it in simple words it is a reflection of plan. In other words we can say, planning is How, What and Who whereas
scheduling is when and why. Scheduling can be also defined as the detailed plan of the project work tasks with respect to time.
A schedule is al so a good communication tool between all the stakeholders of the project. Schedule gives an overall sense of
expected progress of the project without schedule it is very difficult to explain someone unfamiliar with the project what is
going on and what is expected to take place
3) Tracking: Tracking is the process of collecting, enterin‘g and analyzing of actual project performance values, such as work on
tasks and actual durations. Tracking is the second major phase of project management. The main thing to focus on project
planning is developing and communicating the details of project plan before actual work starts. When work begins, the next
phase of project management is tracking progress. Tracking means recording project details such as what work did by whom,
when the work was done, and at what costs these details are called as actual. Properly tracking actual work and comparing its
against original plan is useful to identify the difference in actual and planned and it enables to adjust incomplete task
of the plan.
IV. RESEARCH METHODOLOGY
Research methodology is designed in three stages:
A. Data Collection
This stage consists of literature review, setting of objectives and problem statement and based on that selection of
research area has been done. For the research purpose, residential building is taken as a case study. The data collection has
been done in three parts:
1) Daily progress reports: The DPR consist of detailed description of the work done, labor and resources required for the
work and record of the inventory. All the DPR from the starting day of project till now have been collected. Sample of DPR is
given in Appendix A.
2) Work Output of labor: Work output is the amount of work done by one person (Labor) in 1 day. It is used to calculate
durations required for activity based on the available manpower on site.
3) Activities with their planned duration: Total activities for construction of the residential project with their planned
duration (based on work output and man power available onsite) are entered in primavera for further working.
B. Data Analysis
For data analysis each activity of construction of building are found out and noted down, which are used in Primavera
software for working. Practical construction sequence is under- stood during field training and is used in linking of activities
in primavera along with provision of necessary lag (Float) in predeceasing and succeeding activities. Resources required for
each activity have been allocated in primavera along with their cost, which have given a cost of total project, which will be
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072
One Day National Conference on Recent Advancement in Civil Engineering (RACE 2K19)
25th February 2019
Organized by
Department of Civil Engineering, T John Institute of Technology, Bangalore-83
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1910
further referred to actual cost.
C. Resource Planning
In planning resource requirement the following points to be considered:
a) The total resource requirements for a project over its duration.
b) Minimum delay in completion of the project when insufficient resources are available.
c) Most efficient utilization of resources to carry out the project in a fixed time.
Resource planning is the process of making sure resources are available as required to execute the project according to
schedule. Two types of resource planning problems exist while preparing schedule. In one, the project faces a scarcity of
resources and the activities on network must be arranged in such a way that the requirement of resources does not exceed
availability. In case such an arrangement is not feasible, the one which gives the minimum additional requirement of resources
is chosen. The resources are allocated among competing activities in the order of importance. In other type of resource
planning problem the scarcity condition is relaxed and what is needed is to level up the highly fluctuating demand for resources
at different times, primarily to facilitate project supervision and enhance efficiency.
D. Cost Estimation
Cost estimating is the process of calculating the cost of the identified resources needed to complete the project work. One
doing estimating must consider the possible fluctuations, conditions and other causes of variances that could affect the total
cost the estimation. There is distinct difference between cost estimating and pricing. A cost estimate is the cost of the
resource required to complete the project work. Pricing however includes a profit margin. During the actual execution of the
construction, detailed analysis of costs are required to be made. The cost estimates prepared during the design stage may not
be sufficient or applicable during the execution stage. During the execution stage, the control estimation system serves two
useful purposes. It develops the production information for materials, labour and equipment that can be used as inputs for
future estimates. It generates information so that one may study to take corrective measures to minimize the cost at any step.
1) Cost Estimate Inputs:
• Using the Work Breakdown Structure
• Relying on the resource Requirements
• Calculating Resource Rates
• Estimating Activity Duration
• Historical Information
2) Estimating Project Costs:
• Analogous Estimating
• Parametric Modeling
• Bottom-up Estimating
• Computerized Tools
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072
One Day National Conference on Recent Advancement in Civil Engineering (RACE 2K19)
25th February 2019
Organized by
Department of Civil Engineering, T John Institute of Technology, Bangalore-83
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1911
3) Outputs From Cost Estimation:
• Cost Estimates
• Supporting details
• Cost management plan
E. Concepts of EVM
Earned value analysis is a method of performance measurement. Earned value is a program management technique that uses
work in progress to indicate what will happen to work in future. EVM is system for planning and controlling the project cost
performances. EVM establish work packages earned value baseline by integrating project scope, time and cost objectives .This
baseline is called as cost control and is used for Performance evaluation of project on a given date. Analysis of variance from
the baseline provides the cost related informations for problem identification, trend analysis and corrective actions such as re-
planning and revising budget. Earned value analysis serves two main purposes, it analyses cost changes which is resulting in
time and cost over-run or under-run so that timely corrective actions are taken such as modification of cash flow, updating
financial forecast and project profitability expectations. Analysis of variance from baseline using earned value management
systems given variety of variances which are analyzed to provide current status of project, to initiate corrective actions and to
forecast future trends.
F. Sschedule Analysis
Earned value is a technique for measuring project performance according to project cost and schedule. The comparison
between budgeted and actual performance is performed. There are three earned value parameters as shown below.
Planned Value (PV): It is the cost of the project according to the schedule of the project. It is also called Budgeted Cost of Work
Schedule (BCWS).
Earned Value (EV): It is the Budgeted Cost of the Work Performed (BCWP) till date. It is cumulative budgeted cost incurred in
activities that have been completed on the due date.
Actual Cost (AC): It is the actual cost that has spent on the project till date. It is also called as actual Cost of Work Performed
(ACWP).
The variances are used to check deflection or deviation of project from the path of original schedule. It is also used to analyze
the extent and cause for the delays of works or tasks of the project. Following are two variances:
Cost Variances (CV): It is used to check the difference between the proposed planned project and present project on the
specific date. It shows the variation of project in form of cost.
Schedule Variance (SV): It is used to examine the deflection of present project in from the planned project. If considerable
change appears than the project objectives must be revised.
Schedule Performance Index (SPI): SPI can be used to estimate the projected time to complete the project. It is calculated as
follows,
SPI = Earned Value / Planned Value SPI = 1 means Project is on Schedule
SPI lessthan 1 means Project is behind Schedule
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072
One Day National Conference on Recent Advancement in Civil Engineering (RACE 2K19)
25th February 2019
Organized by
Department of Civil Engineering, T John Institute of Technology, Bangalore-83
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1912
SPI greaterthan 1 means Project is ahead of Schedule Cost Performance Index (CPI):
CPI can be used estimate the project cost to complete the project based on performance to date. It is calculated as follows,
CPI = Earned Value / Actual Cost
CPI = 1 means Planned and Actual cost are same CPI lessthan 1 means Project is under Budget CPI greaterthan 1 means
Project is over Budget
Estimate at Completion (EAC): The Estimate at Completion is the actual cost to date plus an objective estimate of costs for
remaining authorized work. The most common is
EAC = Actual cost + Estimate to Complete
V. CONCLUSIONS
The provision of centralized wastewater collection and treatment for a subdivision with failing onsite sewage systems was
evaluated. Collection systems evaluated consisted of con- ventional collection systems, vacuum Collection systems and
pressure systems using individual grinder pumps. Treatment systems evaluated included individual package wastewater
treatment plants for each subdivision, regional wastewater treatment plants treating wastes from several subdivisions and
collecting and transporting the wastewater to existing wastewater treatment plants in the closest municipality. Likewise, an
analysis for the proposed developments in the southern portion of the county was also completed. The analysis for the pro-
posed developments was similar to the analysis completed for the existing subdivisions with failing onsite sewage systems.
EVM provides important information for project work pack- age decision making. The efficiency of project is demonstrated by
SPI is 0.88 which is less than 1 hence project performed less efficiently and running at about 88% of the planned schedule. The
study shows important, implementation and unique features of EVM that benefits project managers and ultimately results in
project success.
The key point here is that Earned Value Analysis enables you to spot a potential problem early in the project and do something
to correct the situation. Earned Value Management is a remarkable method of project management because it integrates cost,
schedule and scope and can be used to forecast future performances and project completion dates. It allows projects to be
managed better on time and in budget.
REFERENCES
[1] Practice Standard for Earn Value Management, Project Management Institute, USA 2005.
[2] Frank. T. Anbari “Earned Value Project Management Method and Extensions”, Project Management Journal, Vol-3.
[3] T.N. Weerasinghe Mohottige, Standard Practice of Earn Value Manage- ment and its Impact on Construction Industry”,
International Journal of Recent Technology and Engineering ISSN:2277-3878, Volume-2, 2013.
[4] J.R. Turner, “The Handbook of Project-Based Management”, 2nd edi- tion, McGraw, New York 1999.
[5] Shatanand Patil, Akshay Patil and Pramila Chavan, Earned Value Management for Tracking Project Progress,
International Journal ofEngineering Research and Application. Vol-2, 2012.
[6] K.KChithkara, “Construction Project Management ”, Tata McGrawHill, 10th edition, 2006.
[7] Sharma V.K, Earned Value Management: A Tool for Project Perfor- mance Advances in Management Journal, Vol-6, 2013.

More Related Content

What's hot

Environment clearance mandatory for real estate projects
Environment clearance mandatory for real estate projectsEnvironment clearance mandatory for real estate projects
Environment clearance mandatory for real estate projectsProperty Document Verification
 
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...IRJET Journal
 
Saurabh Gupta Ctran Consulting Pvt. Ltd
Saurabh Gupta Ctran Consulting Pvt. LtdSaurabh Gupta Ctran Consulting Pvt. Ltd
Saurabh Gupta Ctran Consulting Pvt. LtdIIT Kharagpur
 
Pollution control in small and medium scale
Pollution control in small and medium scalePollution control in small and medium scale
Pollution control in small and medium scaleECRD IN
 
Pollution control in small and medium scale industry
Pollution control in small and medium scale industryPollution control in small and medium scale industry
Pollution control in small and medium scale industryECRD2015
 
Om Krishna Profile (EIA,EHS)
Om Krishna Profile (EIA,EHS)Om Krishna Profile (EIA,EHS)
Om Krishna Profile (EIA,EHS)?? ?????
 
EIA amendments - 2006 and 2009
EIA amendments - 2006 and 2009EIA amendments - 2006 and 2009
EIA amendments - 2006 and 2009Jenson Samraj
 
Delivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & DataDelivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & Dataconstructingexcellence
 
Executive Summary Of Federal State Climate Change Policy Rebates Grants
Executive Summary Of Federal State Climate Change Policy Rebates GrantsExecutive Summary Of Federal State Climate Change Policy Rebates Grants
Executive Summary Of Federal State Climate Change Policy Rebates GrantsDermotDuncan
 
Project management chapter 4
Project management chapter 4Project management chapter 4
Project management chapter 4VancityInstitute
 
Daniel K Hom Resume And Projects 031611 Li
Daniel K Hom Resume And Projects 031611 LiDaniel K Hom Resume And Projects 031611 Li
Daniel K Hom Resume And Projects 031611 Lidanielkhom
 

What's hot (15)

Environment clearance mandatory for real estate projects
Environment clearance mandatory for real estate projectsEnvironment clearance mandatory for real estate projects
Environment clearance mandatory for real estate projects
 
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
 
Saurabh Gupta Ctran Consulting Pvt. Ltd
Saurabh Gupta Ctran Consulting Pvt. LtdSaurabh Gupta Ctran Consulting Pvt. Ltd
Saurabh Gupta Ctran Consulting Pvt. Ltd
 
Pollution control in small and medium scale
Pollution control in small and medium scalePollution control in small and medium scale
Pollution control in small and medium scale
 
Pollution control in small and medium scale industry
Pollution control in small and medium scale industryPollution control in small and medium scale industry
Pollution control in small and medium scale industry
 
Om Krishna Profile (EIA,EHS)
Om Krishna Profile (EIA,EHS)Om Krishna Profile (EIA,EHS)
Om Krishna Profile (EIA,EHS)
 
EIA amendments - 2006 and 2009
EIA amendments - 2006 and 2009EIA amendments - 2006 and 2009
EIA amendments - 2006 and 2009
 
EIA repot for Airport
EIA repot for AirportEIA repot for Airport
EIA repot for Airport
 
Delivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & DataDelivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & Data
 
Project Management
Project ManagementProject Management
Project Management
 
Griha
GrihaGriha
Griha
 
Executive Summary Of Federal State Climate Change Policy Rebates Grants
Executive Summary Of Federal State Climate Change Policy Rebates GrantsExecutive Summary Of Federal State Climate Change Policy Rebates Grants
Executive Summary Of Federal State Climate Change Policy Rebates Grants
 
Project management chapter 4
Project management chapter 4Project management chapter 4
Project management chapter 4
 
Daniel K Hom Resume And Projects 031611 Li
Daniel K Hom Resume And Projects 031611 LiDaniel K Hom Resume And Projects 031611 Li
Daniel K Hom Resume And Projects 031611 Li
 
The Commercial Energy Codes Support Program
The Commercial Energy Codes Support ProgramThe Commercial Energy Codes Support Program
The Commercial Energy Codes Support Program
 

Similar to IRJET- Construction Approach and Schedule Technical for Treatment Plant

A Comparative Study of different Sewage Treatment Technologies
A Comparative Study of different Sewage Treatment TechnologiesA Comparative Study of different Sewage Treatment Technologies
A Comparative Study of different Sewage Treatment TechnologiesIRJET Journal
 
IRJET- Value Engineering: Better Way of Implementing Conventional Methods
IRJET- Value Engineering: Better Way of Implementing Conventional MethodsIRJET- Value Engineering: Better Way of Implementing Conventional Methods
IRJET- Value Engineering: Better Way of Implementing Conventional MethodsIRJET Journal
 
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.IRJET Journal
 
IRJET- Multiple Project Execution System for a Construction Contracting Organ...
IRJET- Multiple Project Execution System for a Construction Contracting Organ...IRJET- Multiple Project Execution System for a Construction Contracting Organ...
IRJET- Multiple Project Execution System for a Construction Contracting Organ...IRJET Journal
 
Cost Effectiveness of LID Implementation
Cost Effectiveness of LID ImplementationCost Effectiveness of LID Implementation
Cost Effectiveness of LID ImplementationRobert Muir
 
IRJET- Self-Cleaning of Street by Sewage Treated Water using Street Stud
IRJET-  	  Self-Cleaning of Street by Sewage Treated Water using Street StudIRJET-  	  Self-Cleaning of Street by Sewage Treated Water using Street Stud
IRJET- Self-Cleaning of Street by Sewage Treated Water using Street StudIRJET Journal
 
IRJET- Role of Construction Waste Material Management in Construction Ind...
IRJET-  	  Role of Construction Waste Material Management in Construction Ind...IRJET-  	  Role of Construction Waste Material Management in Construction Ind...
IRJET- Role of Construction Waste Material Management in Construction Ind...IRJET Journal
 
IRJET- Quality Assurance & Project Scheduling for Residential Building
IRJET-  	  Quality Assurance & Project Scheduling for Residential BuildingIRJET-  	  Quality Assurance & Project Scheduling for Residential Building
IRJET- Quality Assurance & Project Scheduling for Residential BuildingIRJET Journal
 
IRJET- Assessing the Major Factors for Construction Material Wastage and thei...
IRJET- Assessing the Major Factors for Construction Material Wastage and thei...IRJET- Assessing the Major Factors for Construction Material Wastage and thei...
IRJET- Assessing the Major Factors for Construction Material Wastage and thei...IRJET Journal
 
IRJET- An Investigation of Maintenance Management of Construction Equipment f...
IRJET- An Investigation of Maintenance Management of Construction Equipment f...IRJET- An Investigation of Maintenance Management of Construction Equipment f...
IRJET- An Investigation of Maintenance Management of Construction Equipment f...IRJET Journal
 
IDENTIFYING AND ASSESSING WASTE MANAGEMENT INFLUENCE FACTORS AND CHECK LEVEL ...
IDENTIFYING AND ASSESSING WASTE MANAGEMENT INFLUENCE FACTORS AND CHECK LEVEL ...IDENTIFYING AND ASSESSING WASTE MANAGEMENT INFLUENCE FACTORS AND CHECK LEVEL ...
IDENTIFYING AND ASSESSING WASTE MANAGEMENT INFLUENCE FACTORS AND CHECK LEVEL ...IRJET Journal
 
IRJET- Sustainability of Recycled Aggregate – A Futuristic Prospect
IRJET- Sustainability of Recycled Aggregate – A Futuristic ProspectIRJET- Sustainability of Recycled Aggregate – A Futuristic Prospect
IRJET- Sustainability of Recycled Aggregate – A Futuristic ProspectIRJET Journal
 
IRJET- Rainwater Harvesting System
IRJET-  	  Rainwater Harvesting SystemIRJET-  	  Rainwater Harvesting System
IRJET- Rainwater Harvesting SystemIRJET Journal
 
IRJET- Study on Economic Sustainability of Industrial Buildings
IRJET-  	  Study on Economic Sustainability of Industrial BuildingsIRJET-  	  Study on Economic Sustainability of Industrial Buildings
IRJET- Study on Economic Sustainability of Industrial BuildingsIRJET Journal
 
A Review on Waste Material Minimization in Construction Industry
A Review on Waste Material Minimization in Construction IndustryA Review on Waste Material Minimization in Construction Industry
A Review on Waste Material Minimization in Construction IndustryIRJET Journal
 
Development of Demolished Concrete Mix Using Pre-Coating Technique
Development of Demolished Concrete Mix Using Pre-Coating TechniqueDevelopment of Demolished Concrete Mix Using Pre-Coating Technique
Development of Demolished Concrete Mix Using Pre-Coating TechniqueIRJET Journal
 
Identification & Minimization Of Waste In Building Construction
Identification & Minimization Of Waste In Building ConstructionIdentification & Minimization Of Waste In Building Construction
Identification & Minimization Of Waste In Building ConstructionIRJET Journal
 
IRJET- A Study of Implementing Lean & Fast Tracking in Construction Proje...
IRJET-  	  A Study of Implementing Lean & Fast Tracking in Construction Proje...IRJET-  	  A Study of Implementing Lean & Fast Tracking in Construction Proje...
IRJET- A Study of Implementing Lean & Fast Tracking in Construction Proje...IRJET Journal
 
Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...
Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...
Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...IRJET Journal
 
Solar based Pond Cleaning Machine
Solar based Pond Cleaning MachineSolar based Pond Cleaning Machine
Solar based Pond Cleaning MachineIRJET Journal
 

Similar to IRJET- Construction Approach and Schedule Technical for Treatment Plant (20)

A Comparative Study of different Sewage Treatment Technologies
A Comparative Study of different Sewage Treatment TechnologiesA Comparative Study of different Sewage Treatment Technologies
A Comparative Study of different Sewage Treatment Technologies
 
IRJET- Value Engineering: Better Way of Implementing Conventional Methods
IRJET- Value Engineering: Better Way of Implementing Conventional MethodsIRJET- Value Engineering: Better Way of Implementing Conventional Methods
IRJET- Value Engineering: Better Way of Implementing Conventional Methods
 
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
 
IRJET- Multiple Project Execution System for a Construction Contracting Organ...
IRJET- Multiple Project Execution System for a Construction Contracting Organ...IRJET- Multiple Project Execution System for a Construction Contracting Organ...
IRJET- Multiple Project Execution System for a Construction Contracting Organ...
 
Cost Effectiveness of LID Implementation
Cost Effectiveness of LID ImplementationCost Effectiveness of LID Implementation
Cost Effectiveness of LID Implementation
 
IRJET- Self-Cleaning of Street by Sewage Treated Water using Street Stud
IRJET-  	  Self-Cleaning of Street by Sewage Treated Water using Street StudIRJET-  	  Self-Cleaning of Street by Sewage Treated Water using Street Stud
IRJET- Self-Cleaning of Street by Sewage Treated Water using Street Stud
 
IRJET- Role of Construction Waste Material Management in Construction Ind...
IRJET-  	  Role of Construction Waste Material Management in Construction Ind...IRJET-  	  Role of Construction Waste Material Management in Construction Ind...
IRJET- Role of Construction Waste Material Management in Construction Ind...
 
IRJET- Quality Assurance & Project Scheduling for Residential Building
IRJET-  	  Quality Assurance & Project Scheduling for Residential BuildingIRJET-  	  Quality Assurance & Project Scheduling for Residential Building
IRJET- Quality Assurance & Project Scheduling for Residential Building
 
IRJET- Assessing the Major Factors for Construction Material Wastage and thei...
IRJET- Assessing the Major Factors for Construction Material Wastage and thei...IRJET- Assessing the Major Factors for Construction Material Wastage and thei...
IRJET- Assessing the Major Factors for Construction Material Wastage and thei...
 
IRJET- An Investigation of Maintenance Management of Construction Equipment f...
IRJET- An Investigation of Maintenance Management of Construction Equipment f...IRJET- An Investigation of Maintenance Management of Construction Equipment f...
IRJET- An Investigation of Maintenance Management of Construction Equipment f...
 
IDENTIFYING AND ASSESSING WASTE MANAGEMENT INFLUENCE FACTORS AND CHECK LEVEL ...
IDENTIFYING AND ASSESSING WASTE MANAGEMENT INFLUENCE FACTORS AND CHECK LEVEL ...IDENTIFYING AND ASSESSING WASTE MANAGEMENT INFLUENCE FACTORS AND CHECK LEVEL ...
IDENTIFYING AND ASSESSING WASTE MANAGEMENT INFLUENCE FACTORS AND CHECK LEVEL ...
 
IRJET- Sustainability of Recycled Aggregate – A Futuristic Prospect
IRJET- Sustainability of Recycled Aggregate – A Futuristic ProspectIRJET- Sustainability of Recycled Aggregate – A Futuristic Prospect
IRJET- Sustainability of Recycled Aggregate – A Futuristic Prospect
 
IRJET- Rainwater Harvesting System
IRJET-  	  Rainwater Harvesting SystemIRJET-  	  Rainwater Harvesting System
IRJET- Rainwater Harvesting System
 
IRJET- Study on Economic Sustainability of Industrial Buildings
IRJET-  	  Study on Economic Sustainability of Industrial BuildingsIRJET-  	  Study on Economic Sustainability of Industrial Buildings
IRJET- Study on Economic Sustainability of Industrial Buildings
 
A Review on Waste Material Minimization in Construction Industry
A Review on Waste Material Minimization in Construction IndustryA Review on Waste Material Minimization in Construction Industry
A Review on Waste Material Minimization in Construction Industry
 
Development of Demolished Concrete Mix Using Pre-Coating Technique
Development of Demolished Concrete Mix Using Pre-Coating TechniqueDevelopment of Demolished Concrete Mix Using Pre-Coating Technique
Development of Demolished Concrete Mix Using Pre-Coating Technique
 
Identification & Minimization Of Waste In Building Construction
Identification & Minimization Of Waste In Building ConstructionIdentification & Minimization Of Waste In Building Construction
Identification & Minimization Of Waste In Building Construction
 
IRJET- A Study of Implementing Lean & Fast Tracking in Construction Proje...
IRJET-  	  A Study of Implementing Lean & Fast Tracking in Construction Proje...IRJET-  	  A Study of Implementing Lean & Fast Tracking in Construction Proje...
IRJET- A Study of Implementing Lean & Fast Tracking in Construction Proje...
 
Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...
Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...
Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...
 
Solar based Pond Cleaning Machine
Solar based Pond Cleaning MachineSolar based Pond Cleaning Machine
Solar based Pond Cleaning Machine
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Ramkumar k
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksMagic Marks
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfsumitt6_25730773
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptxrouholahahmadi9876
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...vershagrag
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 

Recently uploaded (20)

HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic Marks
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 

IRJET- Construction Approach and Schedule Technical for Treatment Plant

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072 One Day National Conference on Recent Advancement in Civil Engineering (RACE 2K19) 25th February 2019 Organized by Department of Civil Engineering, T John Institute of Technology, Bangalore-83 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1906 CONSTRUCTION APPROACH AND SCHEDULE TECHNICAL FOR TREATMENT PLANT Rejo George1, Gokul2 1PG Scholar Department of Civil Engineering, EASA College of Engineering and Technology (ECET), Coimbatore, Tamil Nadu, India. 2Assistant Professor Department of Civil Engineering, EASA College of Engineering and Technology (ECET) Coimbatore, Tamil Nadu, India. -------------------------------------------------------------------------***---------------------------------------------------------------------- Abstract:- Construction of the Waste Treatment Plant will occur over multiple phases for various aspects of the work. Each work phase will require different resource levels, staging requirements, materials, equipment, and overall durations. In addition, each phase will result in varying impacts to the site and its surrounding area in terms of noise and vibration, dust, light and glare, erosion, traffic impacts, and workforce requirements. The following sections provide a discussion of the major phases that are anticipated to occur over the course of the plant construction, and the expected impacts that will result during each phase. Work described herein is related to the construction of the 36 mgd treatment plant required by 2019. Work related to future capacity expansions is not accounted for in this document. Index Terms:-Treatment plant, construction, scheduling, pri- mavera, EVM, I. INTRODUCTION Since the 1960s INDIA has been designing and constructing regional wastewater treatment and collection systems. Begin- ning with the initial treatment plants at Renton and West Point, the organization that is now the Wastewater Treatment Division within the Department of Natural Resources and Parks has expanded treatment capacity, improved the level of treatment, and built collection systems as necessary to respond to the growth of the region over the past 40 years. There have been major upgrades and expansions to wastewater treatment and conveyance facilities in the 1980s and 1990s. The work performed as part of those expansions and upgrades resulted in high-quality and reliable facilities that have performed to required standards for many years. As these projects were constructed, the work conformed to rigorous schedules and budgetary controls, as well as environmental controls. The work was also performed in a manner that recognized and addressed local community concerns related to construction. The Brightwater System will be implemented using approaches and methods of construction that have been successfully utilized on similar projects in the past and that are safe, reasonable and reliable approaches in the construction industry today. This TM describes the major elements of work required for the Brightwater Program, provides descriptions of the anticipated processes for performing the work and provides the anticipated schedule for each activity. It describes the anticipated impacts at each major work location, including proposed wastewater treatment facilities, conveyance systems and marine outfall alternatives as described in the Brightwater Draft Environmental Impact Statement (DEIS). II. LITERATURE REVIEW This literature review on wastes from water treatment plants discusses previous literature reviews on the subject, sources and types of waste, characteristics of each type of waste, and waste management. The discussion of management of sludge (waste) covers minimizing sludge production, methods of sludge treatment, and ultimate sludge disposal. During the period 1969 to 1981 the American Water Works Association (AWWA) Research Foundation and the AWWA Sludge Disposal Committee prepared a series of reports with a comprehensive literature review on the nature and solutions of water
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072 One Day National Conference on Recent Advancement in Civil Engineering (RACE 2K19) 25th February 2019 Organized by Department of Civil Engineering, T John Institute of Technology, Bangalore-83 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1907 treatment plant waste disposal problems. The first report, prepared by the AWWA Research Foundation, was divided into four parts (AWWA Research Foundation, 1969a, 1969b, 1969c, 1970) and was entitled”Disposal of Wastes from Water Treatment Plants.” The first part of this report (AWWA, 1969a) covered the status of research and engineering practices for treating various wastes from water treatment plants. The second part (AWWA, 1969b) reviewed plant operations for the disposal of various types of wastes, and the regulatory aspects of disposal. The third part (AWWA, 1969c) described various treatment processes employed and their efficiency and degree of success, and presented cost analyses. The last part (AWWA, 1970) summarized research needs, engineering needs, plant operation needs, and regulatory needs. In 1972, the AWWA Disposal of Water Treatment Plant Waste Committee published an updated report (AWWA, 1972). It dealt with processing and re-processing in sludge production, i.e., selection and modification of treatment processes, reclamation of lime and alum, recovery of filter backwash water, processing of wastes to recover useful by-products, processing of wastes for disposal, ultimate disposal, and future research needs. In 1978, the AWWA Sludge Disposal Committee prepared a 2-part article (AWWA Sludge Disposal Committee, 1978a, 1978b) entitled”Water Treatment Plant Sludge an Update of the State of the Art.” Part 1 dealt with regulatory requirements, sludge production and characteristics, minimizing of waste production, and European and Japanese practices. Part 2 de- tailed non- mechanical and mechanical methods of dewatering water plant sludges, ultimate solids disposal, and research and development needs. These reports focused mainly on coagulant sludges. In 1981, the AWWA Sludge Disposal Committee provided an overview of the production, processing, and disposal of lime-softening sludges; recent technological advances in handling, treatment, and disposal of softening sludges; and research needs (AWWA, 1981). III. METHODOLOGY The construction projects are so vast and complex in nature and therefore for simplification of work, use of softwares came into existence. The project was scheduled and monitored using Primavera P6 software. Primavera is the Project Management software use for Planning, Scheduling and Controlling the Construction Project. The steps involved in treatment plant are Earthwork, Concrete Work, Brickwork, Plastering, Flooring, Plumbing etc. The WBS for the project is created and several activities are identified. The durations of the activities are estimated on basis of Historical data, interviews with project manager, applying labour productivity factor formulae and application of analysis of rates. The relationships are examined and applied to the activities. The following procedure involved in scheduling and monitoring projects. A. Objective of Study The objectives of this study are: • Toidentify construction sequence for a treatment plant construction. • Towork out the practical durations required to carry out the activities. • Toidentify scheduling technique used by the organization in developing plan and scheduling. • Todevelop scheduling using Primavera project planners software. • Totrack the project and analyse the reasons for delays, and increase in estimated budget etc. • To investigate defects in the planning and scheduling procedure of the organization, and suggest suitable improvements in their methods.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072 One Day National Conference on Recent Advancement in Civil Engineering (RACE 2K19) 25th February 2019 Organized by Department of Civil Engineering, T John Institute of Technology, Bangalore-83 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1908 B. Use of PMS in construction The construction industry has a poor image in general. In 1999 alone, in the India, the industries spent more than 1 billion on rework and in 2003, more than 1 5 billion on performance measurement applications .In spite of high expenditure, only 34% of construction projects today meet the iron triangle criteria. During the review we found Primavera and MS Project to be the most frequent PMS used in the construction industry .In the India, over 64 of construction companies indicated Primavera as their specified software, with only just over 20 % requiring the MS Project. Primary reasons for using a PMS in the US construction industry were (in ascending order) a periodic control of work after the start of construction, development of ’look ahead’ schedules, coordination of subcontractors, detailed planning of work prior to construction, schedule impact, claims analysis, tracking of changes, coordination of own trades, estimating and bidding, tracking shop drawings and submits, calculating payment requests for work performed, design development, operation and maintenance of projects, tracking costs and materials planning. This affirms that the construction industry still sees and acknowledges the PM mainly as Critical Path Method (CPM). Nonetheless, it is encouraging that academia anticipates that by the end of this decade, the industry will have implemented the PMS in their day-to-day business. Furthermore, in the area of IS, a resource and an IT management have become the most frequent topics of discussions today. 1) PMS in the SEE construction: The construction industry in the SEE has even lower performance than that of the developed countries. Following the end of the socialist regime, where software development was mostly carried out through the internal IS functions of a large government controlled enterprises the economic and political pressures have been forcing the industry to change its everyday processes listed the purposes for the IS use in the SEE construction industry: 98 % for accounting and bookkeeping, 89,8 % for personnel management, 79,6 % for spreadsheets, 73,5 % for cost prediction, bidding and Bills of Quantities (BoQ), 53,1 % for CAD and only 28,6 % for scheduling. This indicates that the sector is still trying to Cope with traditional management procedures through accounting and that the SEE is still a transitional economy. In addition, the SEE construction has a specific business culture. Unlike the US, the SEE countries have a strict law regulation that defines project stakeholders. There are three main management perspectives: investors (sponsors, developers), consultants (project managers, designers, architects, supervision) and contractors. Owing to the former socialist regime policy, the project management is still unknown to the construction companies. It was introduced into the Croatian regulations only recently, in 2008, while Slovenia and Bosnia and Herzegovina still have no such terminology in place. Furthermore, construction companies are not allowed to appear in projects of two different functions at the same time, for instance in a project management and building or a project management and design. Hence, the ’Design and Build’ types of projects are not allowed by the law in Croatia. Construction projects are under strict government control and their performance has to be reported by the law defined templates. This is mainly the responsibility of the supervision and the contractor. For this reason, the supervision and the contractors are actually the ones who manage projects, while project managers are often put aside and seen as an obstruction to the construction process. C. Construction, Planning, and Scheduling Tracking 1) Construction Planning: Construction planning is a fundamental and challenging activity in management and execution of construction projects. It includes the selection of technology, the definition of work task, the estimation of required durations and resources of individual task, and identify the interactions between different work tasks. A good construction plan is the base for developing the schedule and the budget for work. Developing the construction plan is acritical task in construction management, even if the plan isnot written or else for ly recorded. During planning a planner begins with a result (a design) and he must synthesize the steps required to yield this result. The necessary aspects of construction planning include the generation of required activities, analysis of the implications of these activities and the choice among various alternatives methods of performing these activities. A planner must imagine the final design and describe it in plans and specifications. In developing a construction plan the importance is given either cost or schedule. Some projects a primarily divided into expense categories with associated cost in these cases planning is cost
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072 One Day National Conference on Recent Advancement in Civil Engineering (RACE 2K19) 25th February 2019 Organized by Department of Civil Engineering, T John Institute of Technology, Bangalore-83 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1909 oriented. In this category, a distinction is made between cost incurred directly in the performance of the activity and indirectly for the accomplishment of the project. For other projects where time is a critical or the planner ensures that proper predeceasing among activities is maintained and that efficient scheduling of the available resource prevails. In such cases a critical path scheduling procedure is followed. Finally most of the complex projects require considerations of both cost and schedule over time, so that planning; monitoring and record keeping must be considered in both dimensions. In these cases integration of budget and scheduling information is a major concern. 2) Scheduling: Scheduling is determination the timing of events in the project that is when and which task will be performed? Putting it in simple words it is a reflection of plan. In other words we can say, planning is How, What and Who whereas scheduling is when and why. Scheduling can be also defined as the detailed plan of the project work tasks with respect to time. A schedule is al so a good communication tool between all the stakeholders of the project. Schedule gives an overall sense of expected progress of the project without schedule it is very difficult to explain someone unfamiliar with the project what is going on and what is expected to take place 3) Tracking: Tracking is the process of collecting, enterin‘g and analyzing of actual project performance values, such as work on tasks and actual durations. Tracking is the second major phase of project management. The main thing to focus on project planning is developing and communicating the details of project plan before actual work starts. When work begins, the next phase of project management is tracking progress. Tracking means recording project details such as what work did by whom, when the work was done, and at what costs these details are called as actual. Properly tracking actual work and comparing its against original plan is useful to identify the difference in actual and planned and it enables to adjust incomplete task of the plan. IV. RESEARCH METHODOLOGY Research methodology is designed in three stages: A. Data Collection This stage consists of literature review, setting of objectives and problem statement and based on that selection of research area has been done. For the research purpose, residential building is taken as a case study. The data collection has been done in three parts: 1) Daily progress reports: The DPR consist of detailed description of the work done, labor and resources required for the work and record of the inventory. All the DPR from the starting day of project till now have been collected. Sample of DPR is given in Appendix A. 2) Work Output of labor: Work output is the amount of work done by one person (Labor) in 1 day. It is used to calculate durations required for activity based on the available manpower on site. 3) Activities with their planned duration: Total activities for construction of the residential project with their planned duration (based on work output and man power available onsite) are entered in primavera for further working. B. Data Analysis For data analysis each activity of construction of building are found out and noted down, which are used in Primavera software for working. Practical construction sequence is under- stood during field training and is used in linking of activities in primavera along with provision of necessary lag (Float) in predeceasing and succeeding activities. Resources required for each activity have been allocated in primavera along with their cost, which have given a cost of total project, which will be
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072 One Day National Conference on Recent Advancement in Civil Engineering (RACE 2K19) 25th February 2019 Organized by Department of Civil Engineering, T John Institute of Technology, Bangalore-83 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1910 further referred to actual cost. C. Resource Planning In planning resource requirement the following points to be considered: a) The total resource requirements for a project over its duration. b) Minimum delay in completion of the project when insufficient resources are available. c) Most efficient utilization of resources to carry out the project in a fixed time. Resource planning is the process of making sure resources are available as required to execute the project according to schedule. Two types of resource planning problems exist while preparing schedule. In one, the project faces a scarcity of resources and the activities on network must be arranged in such a way that the requirement of resources does not exceed availability. In case such an arrangement is not feasible, the one which gives the minimum additional requirement of resources is chosen. The resources are allocated among competing activities in the order of importance. In other type of resource planning problem the scarcity condition is relaxed and what is needed is to level up the highly fluctuating demand for resources at different times, primarily to facilitate project supervision and enhance efficiency. D. Cost Estimation Cost estimating is the process of calculating the cost of the identified resources needed to complete the project work. One doing estimating must consider the possible fluctuations, conditions and other causes of variances that could affect the total cost the estimation. There is distinct difference between cost estimating and pricing. A cost estimate is the cost of the resource required to complete the project work. Pricing however includes a profit margin. During the actual execution of the construction, detailed analysis of costs are required to be made. The cost estimates prepared during the design stage may not be sufficient or applicable during the execution stage. During the execution stage, the control estimation system serves two useful purposes. It develops the production information for materials, labour and equipment that can be used as inputs for future estimates. It generates information so that one may study to take corrective measures to minimize the cost at any step. 1) Cost Estimate Inputs: • Using the Work Breakdown Structure • Relying on the resource Requirements • Calculating Resource Rates • Estimating Activity Duration • Historical Information 2) Estimating Project Costs: • Analogous Estimating • Parametric Modeling • Bottom-up Estimating • Computerized Tools
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072 One Day National Conference on Recent Advancement in Civil Engineering (RACE 2K19) 25th February 2019 Organized by Department of Civil Engineering, T John Institute of Technology, Bangalore-83 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1911 3) Outputs From Cost Estimation: • Cost Estimates • Supporting details • Cost management plan E. Concepts of EVM Earned value analysis is a method of performance measurement. Earned value is a program management technique that uses work in progress to indicate what will happen to work in future. EVM is system for planning and controlling the project cost performances. EVM establish work packages earned value baseline by integrating project scope, time and cost objectives .This baseline is called as cost control and is used for Performance evaluation of project on a given date. Analysis of variance from the baseline provides the cost related informations for problem identification, trend analysis and corrective actions such as re- planning and revising budget. Earned value analysis serves two main purposes, it analyses cost changes which is resulting in time and cost over-run or under-run so that timely corrective actions are taken such as modification of cash flow, updating financial forecast and project profitability expectations. Analysis of variance from baseline using earned value management systems given variety of variances which are analyzed to provide current status of project, to initiate corrective actions and to forecast future trends. F. Sschedule Analysis Earned value is a technique for measuring project performance according to project cost and schedule. The comparison between budgeted and actual performance is performed. There are three earned value parameters as shown below. Planned Value (PV): It is the cost of the project according to the schedule of the project. It is also called Budgeted Cost of Work Schedule (BCWS). Earned Value (EV): It is the Budgeted Cost of the Work Performed (BCWP) till date. It is cumulative budgeted cost incurred in activities that have been completed on the due date. Actual Cost (AC): It is the actual cost that has spent on the project till date. It is also called as actual Cost of Work Performed (ACWP). The variances are used to check deflection or deviation of project from the path of original schedule. It is also used to analyze the extent and cause for the delays of works or tasks of the project. Following are two variances: Cost Variances (CV): It is used to check the difference between the proposed planned project and present project on the specific date. It shows the variation of project in form of cost. Schedule Variance (SV): It is used to examine the deflection of present project in from the planned project. If considerable change appears than the project objectives must be revised. Schedule Performance Index (SPI): SPI can be used to estimate the projected time to complete the project. It is calculated as follows, SPI = Earned Value / Planned Value SPI = 1 means Project is on Schedule SPI lessthan 1 means Project is behind Schedule
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072 One Day National Conference on Recent Advancement in Civil Engineering (RACE 2K19) 25th February 2019 Organized by Department of Civil Engineering, T John Institute of Technology, Bangalore-83 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1912 SPI greaterthan 1 means Project is ahead of Schedule Cost Performance Index (CPI): CPI can be used estimate the project cost to complete the project based on performance to date. It is calculated as follows, CPI = Earned Value / Actual Cost CPI = 1 means Planned and Actual cost are same CPI lessthan 1 means Project is under Budget CPI greaterthan 1 means Project is over Budget Estimate at Completion (EAC): The Estimate at Completion is the actual cost to date plus an objective estimate of costs for remaining authorized work. The most common is EAC = Actual cost + Estimate to Complete V. CONCLUSIONS The provision of centralized wastewater collection and treatment for a subdivision with failing onsite sewage systems was evaluated. Collection systems evaluated consisted of con- ventional collection systems, vacuum Collection systems and pressure systems using individual grinder pumps. Treatment systems evaluated included individual package wastewater treatment plants for each subdivision, regional wastewater treatment plants treating wastes from several subdivisions and collecting and transporting the wastewater to existing wastewater treatment plants in the closest municipality. Likewise, an analysis for the proposed developments in the southern portion of the county was also completed. The analysis for the pro- posed developments was similar to the analysis completed for the existing subdivisions with failing onsite sewage systems. EVM provides important information for project work pack- age decision making. The efficiency of project is demonstrated by SPI is 0.88 which is less than 1 hence project performed less efficiently and running at about 88% of the planned schedule. The study shows important, implementation and unique features of EVM that benefits project managers and ultimately results in project success. The key point here is that Earned Value Analysis enables you to spot a potential problem early in the project and do something to correct the situation. Earned Value Management is a remarkable method of project management because it integrates cost, schedule and scope and can be used to forecast future performances and project completion dates. It allows projects to be managed better on time and in budget. REFERENCES [1] Practice Standard for Earn Value Management, Project Management Institute, USA 2005. [2] Frank. T. Anbari “Earned Value Project Management Method and Extensions”, Project Management Journal, Vol-3. [3] T.N. Weerasinghe Mohottige, Standard Practice of Earn Value Manage- ment and its Impact on Construction Industry”, International Journal of Recent Technology and Engineering ISSN:2277-3878, Volume-2, 2013. [4] J.R. Turner, “The Handbook of Project-Based Management”, 2nd edi- tion, McGraw, New York 1999. [5] Shatanand Patil, Akshay Patil and Pramila Chavan, Earned Value Management for Tracking Project Progress, International Journal ofEngineering Research and Application. Vol-2, 2012. [6] K.KChithkara, “Construction Project Management ”, Tata McGrawHill, 10th edition, 2006. [7] Sharma V.K, Earned Value Management: A Tool for Project Perfor- mance Advances in Management Journal, Vol-6, 2013.