SlideShare a Scribd company logo
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4704
Productivity Improvement in Manufacturing Industry Using Lean tools
Subodh Patil1, Pramod Rajput2, Akash Rathod3, Rajkumar Rodge4, Sandip Nage5
1Assistant Professor, Department of mechanical Engineering, JSPM’s Imperial College of Engineering and Research,
Pune 412207.
2345Student of JSPM’s Imperial College of Engineering and Research, Pune 412207.
Savitribai Phule Pune University, Maharashtra, India.
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - Assembly line balancing along with the associated operation analysis assists in constructing an assembly line.
Which is the key step in improving the overall performance of an assembly line.Thus paper reveals to improve the line
efficiency and productivity of component. When data were observed in production line which were needed to focus.
Eliminating the bottleneck on this workstation the solution was to increase line efficiency.Minimizationoftransportationcost
of handling material line as well as number of workers reduction. The concept describe in line balancing to overcome the
bottleneck the result obtained were satisfactory. The actual performance and after improving performance measured and
observed that productivity improved with considerable reduction in transportation time, manpower reduction and space
saving at line
Key Words: Productivity, Line balancing, Eliminating wastage, Travel chart, multiple activity chart, TIMWOOD.
1. INTRODUCTION
The concept productivity is used to determine efficiency and effectiveness of processes conducted inaneconomy business. To
increase productivity the systemic plant layout is good and an advantageous arrangement of operating workstation, storage
space, material handling equipment and other services to facilitate the design the product. The plant can be design by using
line balancing, due to line balancing concept the transportation time reducesandalsogivestheonepieceflowprocess,reduces
the idle time of man and machines.
To design and assess the performance, bottleneck identification, reductioninbottleneck cycletime,minimizinglineimbalance,
workstation organization, reduction in man power and space saving. Increasing man power and space utilizationof industrial
production assembly line is discussed. We use systematiclayoutplanningapproachtoimproveexistinglayoutofcompany.The
detail study of plant layout such as time study operation process chart, flow of material and activity relationship chart has be
examine.
2. Methodology
For increasing production, productivity improvement techniques have been chosen are as follows.
2.1. Cycle time
First of all to know the status of production capacity of each and every workstation, detailed cycle time study at each
workstation can be taken. The 15 Repetitive cycles was taken for three different shifts, and from this average time is taken for
improving productivity. Then activity cycle time are classified in value added and non-value added time activity. Non-value
added activities are reduced to improve the throughput time.
2.2. Lean manufacturing
For all the workstation time study is carried out, 7 waste tools “TIMWOOD” are visualized at every workstation. Also line
efficiency calculated for current state which is 35.20 % which is shown in table no.2.
2.3. Flow Process
For the current state of assembly line the material flow can be identified by using multiple activity and travel activity chart.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4705
3. Observation
Table no.1 shows the cycle time of product which sorted in value added and non-value added time before improvement.
Table -1: Cycle time before improvement
The initial state of connecting rod assembly line having 19workstationsand20numberofoperatorsareshownintableno.2
Table -2: Initial state of line
Number of workstation 19
Throughput time 1319.21 sec
Maximum cycle time 197.24 sec
Takt time 96 sec
Number of operator 20
Line efficiency 35.20 %
Space required 135 ft
Sr.No.
Cycle time
before VD(sec) NVD(SEC)
1 55.82 54.65 1.16
2 86.95 85.82 1.12
3 89.95 88.08 1
4 127.55 126.42 1.12
5 123.59 122.42 1.16
6 3.82 2.82 1
7 32.28 31.28
8 0 0 1
9 21.31 20.31 1
10 71.46 70.41 1.04
11 13.18 12.09 1.08
12 197.24 150.07 47.16
13 80.15 30.23 49.91
14 193.06 143.22 49.83
15 45.29 44.16 1.12
16 27.17 26.17 1
17 26.78 25.73 1.04
18 95 94 1
19 27.48 26.43 1.04
TOTAL 1319.21 1154.37 163.83
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4706
4. Bottleneck Identification
4.1. Side and profile milling and number marking
By using the fifteen repetitive cycle time study measurement can be taken. The takt time was 96 seconds for required
production demand as shown in graph no. 1 and machine number 4 has total cycle time is 127.55sec, Out of which cycle time
31.55sec is above takt time and this is above bottleneck operation which is essential to reduce for improve productivity.
4.2. Bolt hole drilling
As shown in graph no 1 machine number 5 has the total cycle time 123.59sec. Out of which cycle time 27.59sec is above takt
time and this is above bottleneck operation which is essential to reduce for improve productivity.
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19
Series 2 0 0 0 31.55 27.59 0 0 0 0 0 0 101.2 0 97.06 0 0 0 0 0
Series 1 55.82 86.95 89.08 96 96 5.82 32.28 0 21.31 71.46 13.18 96 80.15 96 45.29 27.17 26.78 95 27.48
0
50
100
150
200
250
Time(seconds)
Machine Operation
Series 1 Series 2
Graph-1: Machine operation vs. Cycle time
4.3. Small End and Big End bore and side milling on both side
As shown in graph no. 1 machine number 12 has total cycle time is 197.24sec. Out of which cycle time 101.24sec is above takt
time and this is above bottleneck operation which is essential to reduce for improve productivity.
4.4. Big End chamfer
As shown in graph no. 1 machine number 14 has total cycle time 193.06sec. Out of which cycletime97.06secisabovetakttime
and this is above bottleneck operation which is essential to reduce for improve productivity.
5. Travel activity chart before
A travel chart is a tabular record for presenting quantitativedata i.e.movementanddistance.Aboutthemovementsofmaterial,
workers, material handling devices between number of places over a stipulated period of time.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4707
All departments or workstation are listed in row and column with same sequence. Each intersecting box presents the data for
the movements of the object from one location to other.
6. Multiple activity charts
Multiple activity charts are the process charts using a time scale. It usually comes in picture when work study man wants to
record the activities of one subject with respect to other on a single chart. Subject may be the worker, machine or equipment.
Multiple activity charts are a very useful tool for understanding the flow of work in a cyclical process and as a result
understanding which resource is controlling the overall progress of the work.
From
Travel Activity Chart (Before Implementation)
From
M/c
No
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
1
2 #
3 #
4
5
6 #
7 #
8 #
9 #
10 #
11 #
12 #
13 # #
14
15 # #
16
17 #
18 #
19 #
TO
Chart-1: From –To chart
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4708
FLOW PROCESS CHART
CHART NO.1 SHEET NO.1 OF 1 SUMMARY
SUBJECT CHARTED: ACTIVITY PRESENT PROPOSED SAVINGS
Transportation OPERATION 9
TRANSPORT 2
ACTIVITY: DELAY
machine operation INSPECTION
STORAGE 1
METHOD:-Present DISTANCE (ft.) 14.5
LOCATION: Shop Floor TIME (sec) 127.6
OPERATIVE(S): COST
LABOUR 1
CHARTED BY: DATE: MATERIAL
APPROVED BY: DATE: TOTAL
DESCRIPTION QUANTITY
DISTANC
E (ft.)
TIME
(sec) SYMBOL REMARKS
O → D □ ▼
Machine No:4(side &profile milling and number marking) .
Taking job from machine no 3 14.5 4(4) . 1 labour
Open the door 1 . 1 labour
Clean the fixture 3 . 1 labour
Fix the job on fixture 2 . 1 labour
Close the door 1 . 1 labour
Load the programe 110.55 . 1 labour
Open the door 1 . 1 labour
Remove the job from fixture 2 . 1 labour
Put on table 1 . 1 labour
Load the next job . 1 labour
Check the quality of first job 5 . 1 labour
Chart -2: Machine No 4
FLOW PROCESS CHART
CHART NO.2 SHEET NO.1 OF 2 SUMMARY
SUBJECT CHARTED: ACTIVITY PRESENT PROPOSED SAVINGS
Transportation OPERATION 9
TRANSPORT 2
ACTIVITY: DELAY
machine operation INSPECTION
STORAGE 1
METHOD:-Present DISTANCE (ft.) 4.5
LOCATION: Shop Floor TIME (sec) 123.59
OPERATIVE(S): COST
LABOUR 1
CHARTED BY: DATE: MATERIAL
APPROVED BY: DATE: TOTAL
DESCRIPTION
QUANTIT
Y
DISTANC
E (ft.)
TIME
(sec) SYMBOL REMARKS
O → D □ ▼
Machine No:5 (Bolt Hole Drilling) .
Taking job from M/C no 4 4.5 4(4) . 1 labour
Open the door 2 . 1 labour
Clean the fixture 4 . 1 labour
Fix the job on fixture 2 . 1 labour
Close the door 1 . 1 labour
Load the programe 103.59 . 1 labour
Open the door 1 . 1 labour
Remove the job from fixture 2 . 1 labour
Put on table 1 . 1 labour
Load the next job . 1 labour
Check the quality of first job 6 . 1 labour
Chart -3: Machine No 5
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4709
FLOW PROCESS CHART
CHART NO.3 SHEET NO.1 OF 3 SUMMARY
SUBJECT CHARTED: ACTIVITY PRESENT PROPOSED SAVINGS
Transportation OPERATION 9
TRANSPORT 2
ACTIVITY: DELAY
machine operation INSPECTION
STORAGE 1
DISTANCE (ft.) 6
LOCATION: Shop Floor TIME (sec) 197.24
OPERATIVE(S): COST
LABOUR 1
CHARTED BY: DATE: MATERIAL
APPROVED BY: DATE: TOTAL
DESCRIPTION QUANTITY
DISTANC
E (ft.)
TIME
(sec) SYMBOL REMARKS
O → D □ ▼
Machine No:12 (SE & BE bore and side milling) .
Taking job from M/C no 11 6 47(1) . 1 labour
Open the door 1 . 1 labour
Clean the fixture 2 . 1 labour
Fix the job on fixture 2 . 1 labour
Close the door 1 . 1 labour
Load the programe 135.24 . 1 labour
Open the door 1 . 1 labour
Remove the job from fixture 2 . 1 labour
Put on table 2 . 1 labour
Load the next job . 1 labour
Check the quality of first job 4 . 1 labour
Chart -4: Machine No 12
FLOW PROCESS CHART
CHART NO.4 SHEET NO.1 OF 4 SUMMARY
SUBJECT CHARTED: ACTIVITY PRESENT PROPOSED SAVINGS
Transportation OPERATION 9
TRANSPORT 2
ACTIVITY: DELAY
machine operation INSPECTION
STORAGE 1
METHOD:-Present DISTANCE (ft.) 5.5
LOCATION: Shop Floor TIME (sec) 198.66
OPERATIVE(S): COST
LABOUR 1
CHARTED BY: DATE: MATERIAL
APPROVED BY: DATE: TOTAL
DESCRIPTION QUANTITY
DISTANC
E (ft.)
TIME
(sec) SYMBOL REMARKS
O → D □ ▼
Machine No:14 (Big end chamfer) .
Taking job from M/C no 13 5.5 50(1) . 1 labour
Open the door 1 . 1 labour
Clean the fixture 2 . 1 labour
Fix the job on fixture 2 . 1 labour
Close the door 1 . 1 labour
Load the programe 129.06 . 1 labour
Open the door 1 . 1 labour
Remove the job from fixture 2 . 1 labour
Put on table 1 . 1 labour
Load the next job . 1 labour
Check the quality of first job 4 . 1 labour
Chart -5: Machine No 14
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4710
7. TIMWOOD
To avoid the unnecessary non-value added time 7 waste tool were used
 T-Transportation,
 I-Inventory,
 M-motion,
 W-Waiting,
 O-Overproduction,
 O-Over processing,
 D-Defect
Out of which transportation waste indicated non-value added time, according to chart (chart no. 2, 3, 4, 5.).
7.1. Systematic layout planning
The systematic layout planning is concept used to arrange a workplace in plant by locating workstations in a proper way to
make one piece flow production. This helps to reduces transportation waste,man power(by1)andincreasesproductionrates.
The material handling and plant layout cannot be treated separately.Theyareinter-relatedtoeachother.Fig1showstheinter-
relation between material handling and plant layout. The product to be manufactured determines the sequence of operations
required. Depending upon the quantity of machine, equipment and production quantity required can be estimated which can
determines the flow of material. This enables to work out the space required and arrangement of machine and equipment i.e.
plant layout.
Fig -1: Relationship between plant layout and material handling
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4711
7.2. Man Machine Chart
By clubbing workstation no.14 (Big end chamfer) which required 143.2268 sec and workstation no.15 (big end chamfer on
both side) which required 44.1654 sec. After clubbing of workstation the man power reduced by 1. Clubbing of workstation
does not affect the cycle time and product quality.
Chart -6: Man machine chart
7.2. Space Saving
The current state of assembly line required more floor space (189ft). By using U-Shape layout balanceefficiencyincreasesand
save floor space.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4712
Before After
Fig -2: Plant layout
8. Result
8.1. Bottleneck operation after improvement
After improvement in plant layout, the cycle time reduced by elimination of non value added and improving material
handling processes. For 19 number of workstation, the tabulated data is shown in graph no. 2.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4713
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19
Series 2 0 0 0 30.4 26.4 0 0 0 0 0 0 54.0 0 47.2 0 0 0 0
Series 1 54.6 85.8 88.0 96 96 2.82 31.2 0 20.3 70.4 12.1 96 30.2 96 44.1 26.1 25.7 94 26.4
0
20
40
60
80
100
120
140
160
Time(seconds)
Machine Operation
Series 1 Series 2
Graph-2: Machine operation vs. Cycle time
Table -3: State of line after
8.2. Travel activity chart (After Improvement)
Travel chart shows quantitative data on material flow by recording movement between two machines. The Chart 1 shows
movement between two machines in zigzag way, but after U-shape line balancing Chart 7 shows movement between two
machines in straight way. After U-shape line balancing the one piece flow production is obtained and one piece flow helps
to reduce non-value added time, lead time and increases the production with minimum waste. Travel chart are useful to
determine degree of closeness necessary between two machines.
Number of workstation 19
Throughput time 1154.3778sec
Maximum cycle time 150.0735sec
Takt time 96 sec
Number of operator 18
Line efficiency 40.5127 %
Space required 124 ft
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4714
Chart -7: Travel activity chart
8.3. Multiple activity chart (After Improvement)
FLOW PROCESS CHART
CHART NO.1 SHEET NO.1 OF 1 SUMMARY
SUBJECT CHARTED: ACTIVITY PRESENT PROPOSED SAVINGS
Transportation OPERATION 9
TRANSPORT 2
ACTIVITY: DELAY
machine operation INSPECTION
STORAGE 1
METHOD:-Present DISTANCE (ft.) 7.5
LOCATION: Shop Floor TIME (sec) 124.18
OPERATIVE(S): COST
LABOUR 1
CHARTED BY: DATE: MATERIAL
APPROVED BY: DATE: TOTAL
DESCRIPTION QUANTITY
DISTANCE
(ft.) TIME (sec) SYMBOL REMARKS
O → D □ ▼
Machine No:4(side &profile milling and number marking) .
Taking job from machine no 3 7.5 0.7875(1) . 1 labour
Open the door 1 . 1 labour
Clean the fixture 3 . 1 labour
Fix the job on fixture 2 . 1 labour
Close the door 1 . 1 labour
Load the programe 110.55 . 1 labour
Open the door 1 . 1 labour
Remove the job from fixture 2 . 1 labour
Put on table 1 . 1 labour
Load the next job . 1 labour
Check the quality of first job 5 . 1 labour
Summery :for 1 job (before transportation time - after transportation time by layout )=save time
1(1.125-0.7875)=0.3375=0.3375*4=1.35
Chart -8: Machine No 4
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4715
FLOW PROCESS CHART
CHART NO.2 SHEET NO.1 OF 2 SUMMARY
SUBJECT CHARTED: ACTIVITY PRESENT PROPOSED SAVINGS
Transportation OPERATION 9
TRANSPORT 2
ACTIVITY: DELAY
machine operation INSPECTION
STORAGE 1
METHOD:-Present DISTANCE (ft.) 7.5
LOCATION: Shop Floor TIME (sec) 123.416
OPERATIVE(S): COST
LABOUR 1
CHARTED BY: DATE: MATERIAL
APPROVED BY: DATE: TOTAL
DESCRIPTION QUANTITY
DISTANC
E (ft.) TIME (sec) SYMBOL REMARKS
O → D □ ▼
Machine No:5 (Bolt Hole Drilling) .
Taking job from M/C no 4 7.5 0.81665(1) . 1 labour
Open the door 2 . 1 labour
Clean the fixture 4 . 1 labour
Fix the job on fixture 2 . 1 labour
Close the door 1 . 1 labour
Load the programe 103.59 . 1 labour
Open the door 1 . 1 labour
Remove the job from fixture 2 . 1 labour
Put on table 1 . 1 labour
Load the next job . 1 labour
Check the quality of first job 6 . 1 labour
Summery :for 1 job (before transportation time - after transportation time by layout )=save time
1(1.1665-0.81665)=0.3498=0.3498*4=0.6999
Chart -9: Machine No 5
FLOW PROCESS CHART
CHART NO.3 SHEET NO.1 OF 3 SUMMARY
SUBJECT CHARTED: ACTIVITY PRESENT PROPOSED SAVINGS
Transportation OPERATION 9
TRANSPORT 2
ACTIVITY: DELAY
machine operation INSPECTION
STORAGE 1
DISTANCE (ft.) 4.5
LOCATION: Shop Floor TIME (sec) 183.22
OPERATIVE(S): COST
LABOUR 1
CHARTED BY: DATE: MATERIAL
APPROVED BY: DATE: TOTAL
DESCRIPTION QUANTITY
DISTANC
E (ft.) TIME (sec) SYMBOL REMARKS
O → D □ ▼
Machine No:12 (SE & BE bore and side milling) .
Taking job from M/C no 11 4.5 33.0166(1) . 1 labour
Open the door 1 . 1 labour
Clean the fixture 2 . 1 labour
Fix the job on fixture 2 . 1 labour
Close the door 1 . 1 labour
Load the programe 135.24 . 1 labour
Open the door 1 . 1 labour
Remove the job from fixture 2 . 1 labour
Put on table 2 . 1 labour
Load the next job . 1 labour
Check the quality of first job 4 . 1 labour
Summery :for 1 job (before transportation time - after transportation time by layout )=save time
1(47.1666-33.0166)=14.1499
Chart -10: Machine No 12
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4716
FLOW PROCESS CHART
CHART NO.4 SHEET NO.1 OF 4 SUMMARY
SUBJECT CHARTED: ACTIVITY PRESENT PROPOSED SAVINGS
Transportation OPERATION 9
TRANSPORT 2
ACTIVITY: DELAY
machine operation INSPECTION
STORAGE 1
METHOD:-Present DISTANCE (ft.) 7.5
LOCATION: Shop Floor TIME (sec) 158.05
OPERATIVE(S): COST
LABOUR 1
CHARTED BY: DATE: MATERIAL
APPROVED BY: DATE: TOTAL
DESCRIPTION QUANTITY
DISTANC
E (ft.)
TIME
(sec) SYMBOL REMARKS
O → D □ ▼
Machine No:14 (Big end chamfer) .
Taking job from M/C no 13 7.5 14.95(1) . 1 labour
Open the door 1 . 1 labour
Clean the fixture 2 . 1 labour
Fix the job on fixture 2 . 1 labour
Close the door 1 . 1 labour
Load the programe 129.06 . 1 labour
Open the door 1 . 1 labour
Remove the job from fixture 2 . 1 labour
Put on table 1 . 1 labour
Load the next job . 1 labour
Check the quality of first job 4 . 1 labour
Summery :for 1 job (before transportation time - after transportation time by layout )=save time
1(49.8333-34.8833)=14.95=14.95*2=29.8999
Chart -11: Machine No 14
After improvement in plant layout and material handling due to closeness of workstation the non value added time
reduced. It improves the production rate and line efficiency.
Table -4: After Improvement
Sr.No. Improvement Before After Saving %Improvement
1 Maximum cycle time (sec) 197.24 150.0735 37.1665 23.9132
2 Total cycle time (sec) 1319.21 1154.3778 164.83 12.4947
3 No. of workstation 19 18 1 5.27
4 Space saving 189 176 13 6.87
5 Man power 20 18 2 10
6 Production rate /hrs 33 38 5 15.15
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4717
9. Conclusion
By using systematic layout planning to the assembly line of company we have get the following result
 Majorly reduces the material handling by reducing transportation due to closeness of machine.
 Improve the line efficiency from 35.20% to 40.517%
 The production rates increase to 38 per hour from per hour.
 We successfully completed the work to minimize the material handling times, labour cost and transportation costfor
same workstation.
10. Future scope
 Increase line productivity by using all remaining 6 waste tool.
 Increase assets of company.
 Reduces the inventory cost and manpower by clubbing of more workstation.
 11. References
[1] B. Naveen, Dr. Ramesh Babu, Productivity Improvement in Manufacturing Industry Using Industrial Engineering
Tools.” IOSR Journal of Mechanical and Civil Engineering,
[2] “ Hadi Gokcen , Kursat Agpak , Cevriye Gencer , Emel Kizilkaya, A shortest route formulation of simple U-type
assembly line balancing problem.” Elsevier, 13 Dec 2004.
[3] Nguyen Thi Lam, Le Minh Toi, Vu Thi Thanh Tuyen, Do Ngoc Hien, Lean line balancing foranelectronicsassembly
line.” Elsevier, 2016.
[4] “S B Patil, S.S. Kuber, PRODUCTIVITY IMPROVEMENT IN PLANT BY USING SYSTEMATIC LAYOUT PLANNING
(SLP)-A CASE STUDY OF MEDIUM SCALE INDUSTRY. “ International Journal of Research in Engineering and
Technology, Volum 03 , Issue :04 , Apr-2014.
[5] Zelio Geraldo dos Santos,Leandro Vieira,GilesBalbinotti, LeanManufacturingandergonomicsworkingconditions
in the automotive industry.” Elsevier, 2015.
BIOGRAPHIE
Asst. Professor, Department of
mechanical Engineering, JSPM’s
ICOER, Pune.412207.
Student of JSPM’s, Imperial College
Of Engineering and Research Pune
412207.
Student of JSPM’s, Imperial College
Of Engineering and Research,Pune
412207.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4718
Student of JSPM’s, Imperial College
Of Engineering and Research,Pune
412207.
.
Student of JSPM’s,Imperial College
Of Engineering and Research ,
Pune 412207

More Related Content

What's hot

Improving productivity of apparel manufacturing
Improving productivity of apparel manufacturingImproving productivity of apparel manufacturing
Improving productivity of apparel manufacturing
eSAT Publishing House
 
Improving productivity of apparel manufacturing system using value stream map...
Improving productivity of apparel manufacturing system using value stream map...Improving productivity of apparel manufacturing system using value stream map...
Improving productivity of apparel manufacturing system using value stream map...
eSAT Journals
 
Ppc 2 m and 16m
Ppc 2 m and 16mPpc 2 m and 16m
Ppc 2 m and 16m
Javith Saleem
 
CIM & Automation Lab Manual VTU
CIM & Automation Lab Manual VTUCIM & Automation Lab Manual VTU
CIM & Automation Lab Manual VTUTHANMAY JS
 
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET Journal
 
Application of Lean Concepts in Molding Department
Application of Lean Concepts in Molding DepartmentApplication of Lean Concepts in Molding Department
Application of Lean Concepts in Molding Department
IRJET Journal
 
MANUFACTURING OF CNC MACHINES- TRAINING REPORT AT JYOTI CNC
MANUFACTURING OF CNC MACHINES- TRAINING REPORT AT JYOTI CNCMANUFACTURING OF CNC MACHINES- TRAINING REPORT AT JYOTI CNC
MANUFACTURING OF CNC MACHINES- TRAINING REPORT AT JYOTI CNC
Bhaumik Sheth
 
Capacity utilization for product mix using operation based time standard eval...
Capacity utilization for product mix using operation based time standard eval...Capacity utilization for product mix using operation based time standard eval...
Capacity utilization for product mix using operation based time standard eval...
eSAT Journals
 
Capacity utilization for product mix using operation based time standard eval...
Capacity utilization for product mix using operation based time standard eval...Capacity utilization for product mix using operation based time standard eval...
Capacity utilization for product mix using operation based time standard eval...
eSAT Publishing House
 
Ie microsoft office power point presentation
Ie  microsoft office power point presentationIe  microsoft office power point presentation
Ie microsoft office power point presentation
Shamim Hasan
 
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET Journal
 
Assembly line balancing
Assembly line balancingAssembly line balancing
Assembly line balancing
Aman Shyamsukha
 
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET-  	  Productivity Improvement by Time Study Analysis Moderate Scale Ind...IRJET-  	  Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET Journal
 
IRJET-Effective Improvement of a Plant Layout using Pugh Matrix Approach
IRJET-Effective Improvement of a Plant Layout using Pugh Matrix ApproachIRJET-Effective Improvement of a Plant Layout using Pugh Matrix Approach
IRJET-Effective Improvement of a Plant Layout using Pugh Matrix Approach
IRJET Journal
 
IRJET- Experimental Review of Machining Time Cycles between Manual Programmin...
IRJET- Experimental Review of Machining Time Cycles between Manual Programmin...IRJET- Experimental Review of Machining Time Cycles between Manual Programmin...
IRJET- Experimental Review of Machining Time Cycles between Manual Programmin...
IRJET Journal
 
PALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPINGPALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPINGFuratAj
 

What's hot (17)

Improving productivity of apparel manufacturing
Improving productivity of apparel manufacturingImproving productivity of apparel manufacturing
Improving productivity of apparel manufacturing
 
Improving productivity of apparel manufacturing system using value stream map...
Improving productivity of apparel manufacturing system using value stream map...Improving productivity of apparel manufacturing system using value stream map...
Improving productivity of apparel manufacturing system using value stream map...
 
Ppc 2 m and 16m
Ppc 2 m and 16mPpc 2 m and 16m
Ppc 2 m and 16m
 
Sip
SipSip
Sip
 
CIM & Automation Lab Manual VTU
CIM & Automation Lab Manual VTUCIM & Automation Lab Manual VTU
CIM & Automation Lab Manual VTU
 
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
 
Application of Lean Concepts in Molding Department
Application of Lean Concepts in Molding DepartmentApplication of Lean Concepts in Molding Department
Application of Lean Concepts in Molding Department
 
MANUFACTURING OF CNC MACHINES- TRAINING REPORT AT JYOTI CNC
MANUFACTURING OF CNC MACHINES- TRAINING REPORT AT JYOTI CNCMANUFACTURING OF CNC MACHINES- TRAINING REPORT AT JYOTI CNC
MANUFACTURING OF CNC MACHINES- TRAINING REPORT AT JYOTI CNC
 
Capacity utilization for product mix using operation based time standard eval...
Capacity utilization for product mix using operation based time standard eval...Capacity utilization for product mix using operation based time standard eval...
Capacity utilization for product mix using operation based time standard eval...
 
Capacity utilization for product mix using operation based time standard eval...
Capacity utilization for product mix using operation based time standard eval...Capacity utilization for product mix using operation based time standard eval...
Capacity utilization for product mix using operation based time standard eval...
 
Ie microsoft office power point presentation
Ie  microsoft office power point presentationIe  microsoft office power point presentation
Ie microsoft office power point presentation
 
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
 
Assembly line balancing
Assembly line balancingAssembly line balancing
Assembly line balancing
 
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET-  	  Productivity Improvement by Time Study Analysis Moderate Scale Ind...IRJET-  	  Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...
 
IRJET-Effective Improvement of a Plant Layout using Pugh Matrix Approach
IRJET-Effective Improvement of a Plant Layout using Pugh Matrix ApproachIRJET-Effective Improvement of a Plant Layout using Pugh Matrix Approach
IRJET-Effective Improvement of a Plant Layout using Pugh Matrix Approach
 
IRJET- Experimental Review of Machining Time Cycles between Manual Programmin...
IRJET- Experimental Review of Machining Time Cycles between Manual Programmin...IRJET- Experimental Review of Machining Time Cycles between Manual Programmin...
IRJET- Experimental Review of Machining Time Cycles between Manual Programmin...
 
PALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPINGPALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPING
 

Similar to IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools

K012556370
K012556370K012556370
K012556370
IOSR Journals
 
IRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall Productivity
IRJET Journal
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
IJERD Editor
 
Application Of Workstudy
Application Of WorkstudyApplication Of Workstudy
Application Of Workstudy
bejayrocks
 
H0432045055
H0432045055H0432045055
H0432045055
theijes
 
IRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall Productivity
IRJET Journal
 
PRODUCTIVITY IMPROVEMENT IN SPREADING (CUTTING) SECTION BY IMPLEMENTING PRE-D...
PRODUCTIVITY IMPROVEMENT IN SPREADING (CUTTING) SECTION BY IMPLEMENTING PRE-D...PRODUCTIVITY IMPROVEMENT IN SPREADING (CUTTING) SECTION BY IMPLEMENTING PRE-D...
PRODUCTIVITY IMPROVEMENT IN SPREADING (CUTTING) SECTION BY IMPLEMENTING PRE-D...
IRJET Journal
 
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industry
ijmech
 
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET Journal
 
IRJET- Preventive Maintenance of Utility Equipments at MANMUL, Gejjalagere Ma...
IRJET- Preventive Maintenance of Utility Equipments at MANMUL, Gejjalagere Ma...IRJET- Preventive Maintenance of Utility Equipments at MANMUL, Gejjalagere Ma...
IRJET- Preventive Maintenance of Utility Equipments at MANMUL, Gejjalagere Ma...
IRJET Journal
 
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
IRJET Journal
 
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
IRJET Journal
 
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing FacilityIRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET Journal
 
IRJET- Productivity Improvement Kaizen of XC-60 Housing
IRJET- Productivity Improvement Kaizen of XC-60 HousingIRJET- Productivity Improvement Kaizen of XC-60 Housing
IRJET- Productivity Improvement Kaizen of XC-60 Housing
IRJET Journal
 
I012536474
I012536474I012536474
I012536474
IOSR Journals
 
Sheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
Sheet Metal Assembly Process Optimization Using Lean Manufacturing ToolSheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
Sheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
IRJET Journal
 
Industrial engineeering pli
Industrial engineeering   pliIndustrial engineeering   pli
Industrial engineeering pli
Dhyey Shukla
 
Reducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingReducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casing
eSAT Publishing House
 
M.tech (Production and Industrial Engineering) Thesis Presentation
M.tech (Production and Industrial Engineering) Thesis PresentationM.tech (Production and Industrial Engineering) Thesis Presentation
M.tech (Production and Industrial Engineering) Thesis Presentation
Sanchit Jain
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
Karina Islam
 

Similar to IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools (20)

K012556370
K012556370K012556370
K012556370
 
IRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall Productivity
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
Application Of Workstudy
Application Of WorkstudyApplication Of Workstudy
Application Of Workstudy
 
H0432045055
H0432045055H0432045055
H0432045055
 
IRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall Productivity
 
PRODUCTIVITY IMPROVEMENT IN SPREADING (CUTTING) SECTION BY IMPLEMENTING PRE-D...
PRODUCTIVITY IMPROVEMENT IN SPREADING (CUTTING) SECTION BY IMPLEMENTING PRE-D...PRODUCTIVITY IMPROVEMENT IN SPREADING (CUTTING) SECTION BY IMPLEMENTING PRE-D...
PRODUCTIVITY IMPROVEMENT IN SPREADING (CUTTING) SECTION BY IMPLEMENTING PRE-D...
 
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industry
 
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
 
IRJET- Preventive Maintenance of Utility Equipments at MANMUL, Gejjalagere Ma...
IRJET- Preventive Maintenance of Utility Equipments at MANMUL, Gejjalagere Ma...IRJET- Preventive Maintenance of Utility Equipments at MANMUL, Gejjalagere Ma...
IRJET- Preventive Maintenance of Utility Equipments at MANMUL, Gejjalagere Ma...
 
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
Implementation of 5S and KOBETSU KAIZEN (TPM Pillar) in a Manufacturing Organ...
 
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
 
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing FacilityIRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
 
IRJET- Productivity Improvement Kaizen of XC-60 Housing
IRJET- Productivity Improvement Kaizen of XC-60 HousingIRJET- Productivity Improvement Kaizen of XC-60 Housing
IRJET- Productivity Improvement Kaizen of XC-60 Housing
 
I012536474
I012536474I012536474
I012536474
 
Sheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
Sheet Metal Assembly Process Optimization Using Lean Manufacturing ToolSheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
Sheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
 
Industrial engineeering pli
Industrial engineeering   pliIndustrial engineeering   pli
Industrial engineeering pli
 
Reducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingReducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casing
 
M.tech (Production and Industrial Engineering) Thesis Presentation
M.tech (Production and Industrial Engineering) Thesis PresentationM.tech (Production and Industrial Engineering) Thesis Presentation
M.tech (Production and Industrial Engineering) Thesis Presentation
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
IRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
IRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
IRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
IRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
IRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
IRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
IRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 

Recently uploaded (20)

H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 

IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4704 Productivity Improvement in Manufacturing Industry Using Lean tools Subodh Patil1, Pramod Rajput2, Akash Rathod3, Rajkumar Rodge4, Sandip Nage5 1Assistant Professor, Department of mechanical Engineering, JSPM’s Imperial College of Engineering and Research, Pune 412207. 2345Student of JSPM’s Imperial College of Engineering and Research, Pune 412207. Savitribai Phule Pune University, Maharashtra, India. ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - Assembly line balancing along with the associated operation analysis assists in constructing an assembly line. Which is the key step in improving the overall performance of an assembly line.Thus paper reveals to improve the line efficiency and productivity of component. When data were observed in production line which were needed to focus. Eliminating the bottleneck on this workstation the solution was to increase line efficiency.Minimizationoftransportationcost of handling material line as well as number of workers reduction. The concept describe in line balancing to overcome the bottleneck the result obtained were satisfactory. The actual performance and after improving performance measured and observed that productivity improved with considerable reduction in transportation time, manpower reduction and space saving at line Key Words: Productivity, Line balancing, Eliminating wastage, Travel chart, multiple activity chart, TIMWOOD. 1. INTRODUCTION The concept productivity is used to determine efficiency and effectiveness of processes conducted inaneconomy business. To increase productivity the systemic plant layout is good and an advantageous arrangement of operating workstation, storage space, material handling equipment and other services to facilitate the design the product. The plant can be design by using line balancing, due to line balancing concept the transportation time reducesandalsogivestheonepieceflowprocess,reduces the idle time of man and machines. To design and assess the performance, bottleneck identification, reductioninbottleneck cycletime,minimizinglineimbalance, workstation organization, reduction in man power and space saving. Increasing man power and space utilizationof industrial production assembly line is discussed. We use systematiclayoutplanningapproachtoimproveexistinglayoutofcompany.The detail study of plant layout such as time study operation process chart, flow of material and activity relationship chart has be examine. 2. Methodology For increasing production, productivity improvement techniques have been chosen are as follows. 2.1. Cycle time First of all to know the status of production capacity of each and every workstation, detailed cycle time study at each workstation can be taken. The 15 Repetitive cycles was taken for three different shifts, and from this average time is taken for improving productivity. Then activity cycle time are classified in value added and non-value added time activity. Non-value added activities are reduced to improve the throughput time. 2.2. Lean manufacturing For all the workstation time study is carried out, 7 waste tools “TIMWOOD” are visualized at every workstation. Also line efficiency calculated for current state which is 35.20 % which is shown in table no.2. 2.3. Flow Process For the current state of assembly line the material flow can be identified by using multiple activity and travel activity chart.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4705 3. Observation Table no.1 shows the cycle time of product which sorted in value added and non-value added time before improvement. Table -1: Cycle time before improvement The initial state of connecting rod assembly line having 19workstationsand20numberofoperatorsareshownintableno.2 Table -2: Initial state of line Number of workstation 19 Throughput time 1319.21 sec Maximum cycle time 197.24 sec Takt time 96 sec Number of operator 20 Line efficiency 35.20 % Space required 135 ft Sr.No. Cycle time before VD(sec) NVD(SEC) 1 55.82 54.65 1.16 2 86.95 85.82 1.12 3 89.95 88.08 1 4 127.55 126.42 1.12 5 123.59 122.42 1.16 6 3.82 2.82 1 7 32.28 31.28 8 0 0 1 9 21.31 20.31 1 10 71.46 70.41 1.04 11 13.18 12.09 1.08 12 197.24 150.07 47.16 13 80.15 30.23 49.91 14 193.06 143.22 49.83 15 45.29 44.16 1.12 16 27.17 26.17 1 17 26.78 25.73 1.04 18 95 94 1 19 27.48 26.43 1.04 TOTAL 1319.21 1154.37 163.83
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4706 4. Bottleneck Identification 4.1. Side and profile milling and number marking By using the fifteen repetitive cycle time study measurement can be taken. The takt time was 96 seconds for required production demand as shown in graph no. 1 and machine number 4 has total cycle time is 127.55sec, Out of which cycle time 31.55sec is above takt time and this is above bottleneck operation which is essential to reduce for improve productivity. 4.2. Bolt hole drilling As shown in graph no 1 machine number 5 has the total cycle time 123.59sec. Out of which cycle time 27.59sec is above takt time and this is above bottleneck operation which is essential to reduce for improve productivity. M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 Series 2 0 0 0 31.55 27.59 0 0 0 0 0 0 101.2 0 97.06 0 0 0 0 0 Series 1 55.82 86.95 89.08 96 96 5.82 32.28 0 21.31 71.46 13.18 96 80.15 96 45.29 27.17 26.78 95 27.48 0 50 100 150 200 250 Time(seconds) Machine Operation Series 1 Series 2 Graph-1: Machine operation vs. Cycle time 4.3. Small End and Big End bore and side milling on both side As shown in graph no. 1 machine number 12 has total cycle time is 197.24sec. Out of which cycle time 101.24sec is above takt time and this is above bottleneck operation which is essential to reduce for improve productivity. 4.4. Big End chamfer As shown in graph no. 1 machine number 14 has total cycle time 193.06sec. Out of which cycletime97.06secisabovetakttime and this is above bottleneck operation which is essential to reduce for improve productivity. 5. Travel activity chart before A travel chart is a tabular record for presenting quantitativedata i.e.movementanddistance.Aboutthemovementsofmaterial, workers, material handling devices between number of places over a stipulated period of time.
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4707 All departments or workstation are listed in row and column with same sequence. Each intersecting box presents the data for the movements of the object from one location to other. 6. Multiple activity charts Multiple activity charts are the process charts using a time scale. It usually comes in picture when work study man wants to record the activities of one subject with respect to other on a single chart. Subject may be the worker, machine or equipment. Multiple activity charts are a very useful tool for understanding the flow of work in a cyclical process and as a result understanding which resource is controlling the overall progress of the work. From Travel Activity Chart (Before Implementation) From M/c No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 1 2 # 3 # 4 5 6 # 7 # 8 # 9 # 10 # 11 # 12 # 13 # # 14 15 # # 16 17 # 18 # 19 # TO Chart-1: From –To chart
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4708 FLOW PROCESS CHART CHART NO.1 SHEET NO.1 OF 1 SUMMARY SUBJECT CHARTED: ACTIVITY PRESENT PROPOSED SAVINGS Transportation OPERATION 9 TRANSPORT 2 ACTIVITY: DELAY machine operation INSPECTION STORAGE 1 METHOD:-Present DISTANCE (ft.) 14.5 LOCATION: Shop Floor TIME (sec) 127.6 OPERATIVE(S): COST LABOUR 1 CHARTED BY: DATE: MATERIAL APPROVED BY: DATE: TOTAL DESCRIPTION QUANTITY DISTANC E (ft.) TIME (sec) SYMBOL REMARKS O → D □ ▼ Machine No:4(side &profile milling and number marking) . Taking job from machine no 3 14.5 4(4) . 1 labour Open the door 1 . 1 labour Clean the fixture 3 . 1 labour Fix the job on fixture 2 . 1 labour Close the door 1 . 1 labour Load the programe 110.55 . 1 labour Open the door 1 . 1 labour Remove the job from fixture 2 . 1 labour Put on table 1 . 1 labour Load the next job . 1 labour Check the quality of first job 5 . 1 labour Chart -2: Machine No 4 FLOW PROCESS CHART CHART NO.2 SHEET NO.1 OF 2 SUMMARY SUBJECT CHARTED: ACTIVITY PRESENT PROPOSED SAVINGS Transportation OPERATION 9 TRANSPORT 2 ACTIVITY: DELAY machine operation INSPECTION STORAGE 1 METHOD:-Present DISTANCE (ft.) 4.5 LOCATION: Shop Floor TIME (sec) 123.59 OPERATIVE(S): COST LABOUR 1 CHARTED BY: DATE: MATERIAL APPROVED BY: DATE: TOTAL DESCRIPTION QUANTIT Y DISTANC E (ft.) TIME (sec) SYMBOL REMARKS O → D □ ▼ Machine No:5 (Bolt Hole Drilling) . Taking job from M/C no 4 4.5 4(4) . 1 labour Open the door 2 . 1 labour Clean the fixture 4 . 1 labour Fix the job on fixture 2 . 1 labour Close the door 1 . 1 labour Load the programe 103.59 . 1 labour Open the door 1 . 1 labour Remove the job from fixture 2 . 1 labour Put on table 1 . 1 labour Load the next job . 1 labour Check the quality of first job 6 . 1 labour Chart -3: Machine No 5
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4709 FLOW PROCESS CHART CHART NO.3 SHEET NO.1 OF 3 SUMMARY SUBJECT CHARTED: ACTIVITY PRESENT PROPOSED SAVINGS Transportation OPERATION 9 TRANSPORT 2 ACTIVITY: DELAY machine operation INSPECTION STORAGE 1 DISTANCE (ft.) 6 LOCATION: Shop Floor TIME (sec) 197.24 OPERATIVE(S): COST LABOUR 1 CHARTED BY: DATE: MATERIAL APPROVED BY: DATE: TOTAL DESCRIPTION QUANTITY DISTANC E (ft.) TIME (sec) SYMBOL REMARKS O → D □ ▼ Machine No:12 (SE & BE bore and side milling) . Taking job from M/C no 11 6 47(1) . 1 labour Open the door 1 . 1 labour Clean the fixture 2 . 1 labour Fix the job on fixture 2 . 1 labour Close the door 1 . 1 labour Load the programe 135.24 . 1 labour Open the door 1 . 1 labour Remove the job from fixture 2 . 1 labour Put on table 2 . 1 labour Load the next job . 1 labour Check the quality of first job 4 . 1 labour Chart -4: Machine No 12 FLOW PROCESS CHART CHART NO.4 SHEET NO.1 OF 4 SUMMARY SUBJECT CHARTED: ACTIVITY PRESENT PROPOSED SAVINGS Transportation OPERATION 9 TRANSPORT 2 ACTIVITY: DELAY machine operation INSPECTION STORAGE 1 METHOD:-Present DISTANCE (ft.) 5.5 LOCATION: Shop Floor TIME (sec) 198.66 OPERATIVE(S): COST LABOUR 1 CHARTED BY: DATE: MATERIAL APPROVED BY: DATE: TOTAL DESCRIPTION QUANTITY DISTANC E (ft.) TIME (sec) SYMBOL REMARKS O → D □ ▼ Machine No:14 (Big end chamfer) . Taking job from M/C no 13 5.5 50(1) . 1 labour Open the door 1 . 1 labour Clean the fixture 2 . 1 labour Fix the job on fixture 2 . 1 labour Close the door 1 . 1 labour Load the programe 129.06 . 1 labour Open the door 1 . 1 labour Remove the job from fixture 2 . 1 labour Put on table 1 . 1 labour Load the next job . 1 labour Check the quality of first job 4 . 1 labour Chart -5: Machine No 14
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4710 7. TIMWOOD To avoid the unnecessary non-value added time 7 waste tool were used  T-Transportation,  I-Inventory,  M-motion,  W-Waiting,  O-Overproduction,  O-Over processing,  D-Defect Out of which transportation waste indicated non-value added time, according to chart (chart no. 2, 3, 4, 5.). 7.1. Systematic layout planning The systematic layout planning is concept used to arrange a workplace in plant by locating workstations in a proper way to make one piece flow production. This helps to reduces transportation waste,man power(by1)andincreasesproductionrates. The material handling and plant layout cannot be treated separately.Theyareinter-relatedtoeachother.Fig1showstheinter- relation between material handling and plant layout. The product to be manufactured determines the sequence of operations required. Depending upon the quantity of machine, equipment and production quantity required can be estimated which can determines the flow of material. This enables to work out the space required and arrangement of machine and equipment i.e. plant layout. Fig -1: Relationship between plant layout and material handling
  • 8. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4711 7.2. Man Machine Chart By clubbing workstation no.14 (Big end chamfer) which required 143.2268 sec and workstation no.15 (big end chamfer on both side) which required 44.1654 sec. After clubbing of workstation the man power reduced by 1. Clubbing of workstation does not affect the cycle time and product quality. Chart -6: Man machine chart 7.2. Space Saving The current state of assembly line required more floor space (189ft). By using U-Shape layout balanceefficiencyincreasesand save floor space.
  • 9. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4712 Before After Fig -2: Plant layout 8. Result 8.1. Bottleneck operation after improvement After improvement in plant layout, the cycle time reduced by elimination of non value added and improving material handling processes. For 19 number of workstation, the tabulated data is shown in graph no. 2.
  • 10. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4713 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 Series 2 0 0 0 30.4 26.4 0 0 0 0 0 0 54.0 0 47.2 0 0 0 0 Series 1 54.6 85.8 88.0 96 96 2.82 31.2 0 20.3 70.4 12.1 96 30.2 96 44.1 26.1 25.7 94 26.4 0 20 40 60 80 100 120 140 160 Time(seconds) Machine Operation Series 1 Series 2 Graph-2: Machine operation vs. Cycle time Table -3: State of line after 8.2. Travel activity chart (After Improvement) Travel chart shows quantitative data on material flow by recording movement between two machines. The Chart 1 shows movement between two machines in zigzag way, but after U-shape line balancing Chart 7 shows movement between two machines in straight way. After U-shape line balancing the one piece flow production is obtained and one piece flow helps to reduce non-value added time, lead time and increases the production with minimum waste. Travel chart are useful to determine degree of closeness necessary between two machines. Number of workstation 19 Throughput time 1154.3778sec Maximum cycle time 150.0735sec Takt time 96 sec Number of operator 18 Line efficiency 40.5127 % Space required 124 ft
  • 11. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4714 Chart -7: Travel activity chart 8.3. Multiple activity chart (After Improvement) FLOW PROCESS CHART CHART NO.1 SHEET NO.1 OF 1 SUMMARY SUBJECT CHARTED: ACTIVITY PRESENT PROPOSED SAVINGS Transportation OPERATION 9 TRANSPORT 2 ACTIVITY: DELAY machine operation INSPECTION STORAGE 1 METHOD:-Present DISTANCE (ft.) 7.5 LOCATION: Shop Floor TIME (sec) 124.18 OPERATIVE(S): COST LABOUR 1 CHARTED BY: DATE: MATERIAL APPROVED BY: DATE: TOTAL DESCRIPTION QUANTITY DISTANCE (ft.) TIME (sec) SYMBOL REMARKS O → D □ ▼ Machine No:4(side &profile milling and number marking) . Taking job from machine no 3 7.5 0.7875(1) . 1 labour Open the door 1 . 1 labour Clean the fixture 3 . 1 labour Fix the job on fixture 2 . 1 labour Close the door 1 . 1 labour Load the programe 110.55 . 1 labour Open the door 1 . 1 labour Remove the job from fixture 2 . 1 labour Put on table 1 . 1 labour Load the next job . 1 labour Check the quality of first job 5 . 1 labour Summery :for 1 job (before transportation time - after transportation time by layout )=save time 1(1.125-0.7875)=0.3375=0.3375*4=1.35 Chart -8: Machine No 4
  • 12. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4715 FLOW PROCESS CHART CHART NO.2 SHEET NO.1 OF 2 SUMMARY SUBJECT CHARTED: ACTIVITY PRESENT PROPOSED SAVINGS Transportation OPERATION 9 TRANSPORT 2 ACTIVITY: DELAY machine operation INSPECTION STORAGE 1 METHOD:-Present DISTANCE (ft.) 7.5 LOCATION: Shop Floor TIME (sec) 123.416 OPERATIVE(S): COST LABOUR 1 CHARTED BY: DATE: MATERIAL APPROVED BY: DATE: TOTAL DESCRIPTION QUANTITY DISTANC E (ft.) TIME (sec) SYMBOL REMARKS O → D □ ▼ Machine No:5 (Bolt Hole Drilling) . Taking job from M/C no 4 7.5 0.81665(1) . 1 labour Open the door 2 . 1 labour Clean the fixture 4 . 1 labour Fix the job on fixture 2 . 1 labour Close the door 1 . 1 labour Load the programe 103.59 . 1 labour Open the door 1 . 1 labour Remove the job from fixture 2 . 1 labour Put on table 1 . 1 labour Load the next job . 1 labour Check the quality of first job 6 . 1 labour Summery :for 1 job (before transportation time - after transportation time by layout )=save time 1(1.1665-0.81665)=0.3498=0.3498*4=0.6999 Chart -9: Machine No 5 FLOW PROCESS CHART CHART NO.3 SHEET NO.1 OF 3 SUMMARY SUBJECT CHARTED: ACTIVITY PRESENT PROPOSED SAVINGS Transportation OPERATION 9 TRANSPORT 2 ACTIVITY: DELAY machine operation INSPECTION STORAGE 1 DISTANCE (ft.) 4.5 LOCATION: Shop Floor TIME (sec) 183.22 OPERATIVE(S): COST LABOUR 1 CHARTED BY: DATE: MATERIAL APPROVED BY: DATE: TOTAL DESCRIPTION QUANTITY DISTANC E (ft.) TIME (sec) SYMBOL REMARKS O → D □ ▼ Machine No:12 (SE & BE bore and side milling) . Taking job from M/C no 11 4.5 33.0166(1) . 1 labour Open the door 1 . 1 labour Clean the fixture 2 . 1 labour Fix the job on fixture 2 . 1 labour Close the door 1 . 1 labour Load the programe 135.24 . 1 labour Open the door 1 . 1 labour Remove the job from fixture 2 . 1 labour Put on table 2 . 1 labour Load the next job . 1 labour Check the quality of first job 4 . 1 labour Summery :for 1 job (before transportation time - after transportation time by layout )=save time 1(47.1666-33.0166)=14.1499 Chart -10: Machine No 12
  • 13. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4716 FLOW PROCESS CHART CHART NO.4 SHEET NO.1 OF 4 SUMMARY SUBJECT CHARTED: ACTIVITY PRESENT PROPOSED SAVINGS Transportation OPERATION 9 TRANSPORT 2 ACTIVITY: DELAY machine operation INSPECTION STORAGE 1 METHOD:-Present DISTANCE (ft.) 7.5 LOCATION: Shop Floor TIME (sec) 158.05 OPERATIVE(S): COST LABOUR 1 CHARTED BY: DATE: MATERIAL APPROVED BY: DATE: TOTAL DESCRIPTION QUANTITY DISTANC E (ft.) TIME (sec) SYMBOL REMARKS O → D □ ▼ Machine No:14 (Big end chamfer) . Taking job from M/C no 13 7.5 14.95(1) . 1 labour Open the door 1 . 1 labour Clean the fixture 2 . 1 labour Fix the job on fixture 2 . 1 labour Close the door 1 . 1 labour Load the programe 129.06 . 1 labour Open the door 1 . 1 labour Remove the job from fixture 2 . 1 labour Put on table 1 . 1 labour Load the next job . 1 labour Check the quality of first job 4 . 1 labour Summery :for 1 job (before transportation time - after transportation time by layout )=save time 1(49.8333-34.8833)=14.95=14.95*2=29.8999 Chart -11: Machine No 14 After improvement in plant layout and material handling due to closeness of workstation the non value added time reduced. It improves the production rate and line efficiency. Table -4: After Improvement Sr.No. Improvement Before After Saving %Improvement 1 Maximum cycle time (sec) 197.24 150.0735 37.1665 23.9132 2 Total cycle time (sec) 1319.21 1154.3778 164.83 12.4947 3 No. of workstation 19 18 1 5.27 4 Space saving 189 176 13 6.87 5 Man power 20 18 2 10 6 Production rate /hrs 33 38 5 15.15
  • 14. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4717 9. Conclusion By using systematic layout planning to the assembly line of company we have get the following result  Majorly reduces the material handling by reducing transportation due to closeness of machine.  Improve the line efficiency from 35.20% to 40.517%  The production rates increase to 38 per hour from per hour.  We successfully completed the work to minimize the material handling times, labour cost and transportation costfor same workstation. 10. Future scope  Increase line productivity by using all remaining 6 waste tool.  Increase assets of company.  Reduces the inventory cost and manpower by clubbing of more workstation.  11. References [1] B. Naveen, Dr. Ramesh Babu, Productivity Improvement in Manufacturing Industry Using Industrial Engineering Tools.” IOSR Journal of Mechanical and Civil Engineering, [2] “ Hadi Gokcen , Kursat Agpak , Cevriye Gencer , Emel Kizilkaya, A shortest route formulation of simple U-type assembly line balancing problem.” Elsevier, 13 Dec 2004. [3] Nguyen Thi Lam, Le Minh Toi, Vu Thi Thanh Tuyen, Do Ngoc Hien, Lean line balancing foranelectronicsassembly line.” Elsevier, 2016. [4] “S B Patil, S.S. Kuber, PRODUCTIVITY IMPROVEMENT IN PLANT BY USING SYSTEMATIC LAYOUT PLANNING (SLP)-A CASE STUDY OF MEDIUM SCALE INDUSTRY. “ International Journal of Research in Engineering and Technology, Volum 03 , Issue :04 , Apr-2014. [5] Zelio Geraldo dos Santos,Leandro Vieira,GilesBalbinotti, LeanManufacturingandergonomicsworkingconditions in the automotive industry.” Elsevier, 2015. BIOGRAPHIE Asst. Professor, Department of mechanical Engineering, JSPM’s ICOER, Pune.412207. Student of JSPM’s, Imperial College Of Engineering and Research Pune 412207. Student of JSPM’s, Imperial College Of Engineering and Research,Pune 412207.
  • 15. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 4718 Student of JSPM’s, Imperial College Of Engineering and Research,Pune 412207. . Student of JSPM’s,Imperial College Of Engineering and Research , Pune 412207