This document discusses improving the productivity of an existing production line that manufactures product X through implementing Kaizens (continuous improvements). It analyzes the current production line and identifies reaming as a bottleneck station, taking 52.4 seconds per cycle which is longer than the target 41 seconds. The document proposes replacing the hydraulic cylinder used for the upstroke/downstroke of the fixture in reaming with a smaller diameter cylinder. Calculations show this would increase velocity 4 times and save around 7 seconds per cycle. Implementation of this and other Kaizens could increase productivity by 30% to meet demand.
The document defines different types of production layout formats including process layout, product layout, group technology (cellular) layout, and fixed-position layout. It then provides examples of using systematic layout planning techniques and computerized layout programs like CRAFT to develop optimized process layouts that minimize material handling costs based on interdepartmental flow data. The examples show how simple exchanges aimed at cost reduction can actually increase costs due to unintended impacts on other department relationships. Overall layout optimization requires consideration of both quantitative factors like costs as well as qualitative factors such as safety and workflow.
International Journal of Engineering Research and DevelopmentIJERD Editor
Electrical, Electronics and Computer Engineering,
Information Engineering and Technology,
Mechanical, Industrial and Manufacturing Engineering,
Automation and Mechatronics Engineering,
Material and Chemical Engineering,
Civil and Architecture Engineering,
Biotechnology and Bio Engineering,
Environmental Engineering,
Petroleum and Mining Engineering,
Marine and Agriculture engineering,
Aerospace Engineering.
This document summarizes line balancing techniques for optimizing production line efficiency. It discusses calculating standard minute values using time studies and setting production targets. Pitch time and control limits are explained to balance the workload across workstations. Bottleneck processes are identified and methods to reduce them are provided, such as work improvement, equipment upgrades, and job reassignment. The overall goal of line balancing is to design a smooth production flow that allows each worker to complete their allotted work within an even time frame.
This document discusses line balancing in garment manufacturing. Line balancing aims to design a smooth production flow by evenly allotting processes to workers so that each can complete their workload within the same amount of time. This keeps inventory costs low and production balanced. Tools for line balancing include production sheets and reports tracking inventory levels and output. Balancing starts by determining required operators and work-in-process inventory levels. It aims to keep all operators working at maximum capacity while solving problems before they become large. Key aspects of balancing include pitch time, bottleneck processes, and setting control limits.
Facility layout planning determines the optimal physical arrangement of resources. There are several types of layouts including process, product, hybrid, and fixed-position layouts. Process layouts group similar resources together and offer flexibility while product layouts are designed to efficiently produce specific products. Hybrid layouts combine elements of process and product layouts. Effective layout design involves gathering information, developing alternative plans, and creating a detailed layout.
This presentation is on the based on case study done by using line balancing technique which a prime concern for an industrial engineer. This shows an efficient line balancing for a better production line performed at Runner Automobiles Ltd, Bangladesh.
Assembly Line Balancing to Improve Productivity using Work Sharing Method in ...ijtsrd
The garment factories are always trying to improve production and the quality of the garments to sustain in the enormous competitive market. This paper is about the productivity improvement by reducing cycle time with work sharing in garment factories. A garment factory manufactures different types of garments. In many types of garment productions, this paper is to improve productivity of lady pencil skirts production process. Overall efficiency of single model assembly line by reducing the non value added activities, cycle time and distribution of work load at each work station by line balancing. For that, the productivity improvement is shown by two ways. The first way is proper training and supervision for activities and the second is work sharing with same type of jobs and skills. Keywords Cycle Time, Line Balancing, Productivity, Training, Work Sharing. Khin Nann Yu Aung | Yin Yin Tun "Assembly Line Balancing to Improve Productivity using Work-Sharing Method in Garment Factories" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-3 | Issue-5 , August 2019, URL: https://www.ijtsrd.com/papers/ijtsrd26656.pdfPaper URL: https://www.ijtsrd.com/engineering/mechanical-engineering/26656/assembly-line-balancing-to-improve-productivity-using-work-sharing-method-in-garment-factories/khin-nann-yu-aung
The document defines different types of production layout formats including process layout, product layout, group technology (cellular) layout, and fixed-position layout. It then provides examples of using systematic layout planning techniques and computerized layout programs like CRAFT to develop optimized process layouts that minimize material handling costs based on interdepartmental flow data. The examples show how simple exchanges aimed at cost reduction can actually increase costs due to unintended impacts on other department relationships. Overall layout optimization requires consideration of both quantitative factors like costs as well as qualitative factors such as safety and workflow.
International Journal of Engineering Research and DevelopmentIJERD Editor
Electrical, Electronics and Computer Engineering,
Information Engineering and Technology,
Mechanical, Industrial and Manufacturing Engineering,
Automation and Mechatronics Engineering,
Material and Chemical Engineering,
Civil and Architecture Engineering,
Biotechnology and Bio Engineering,
Environmental Engineering,
Petroleum and Mining Engineering,
Marine and Agriculture engineering,
Aerospace Engineering.
This document summarizes line balancing techniques for optimizing production line efficiency. It discusses calculating standard minute values using time studies and setting production targets. Pitch time and control limits are explained to balance the workload across workstations. Bottleneck processes are identified and methods to reduce them are provided, such as work improvement, equipment upgrades, and job reassignment. The overall goal of line balancing is to design a smooth production flow that allows each worker to complete their allotted work within an even time frame.
This document discusses line balancing in garment manufacturing. Line balancing aims to design a smooth production flow by evenly allotting processes to workers so that each can complete their workload within the same amount of time. This keeps inventory costs low and production balanced. Tools for line balancing include production sheets and reports tracking inventory levels and output. Balancing starts by determining required operators and work-in-process inventory levels. It aims to keep all operators working at maximum capacity while solving problems before they become large. Key aspects of balancing include pitch time, bottleneck processes, and setting control limits.
Facility layout planning determines the optimal physical arrangement of resources. There are several types of layouts including process, product, hybrid, and fixed-position layouts. Process layouts group similar resources together and offer flexibility while product layouts are designed to efficiently produce specific products. Hybrid layouts combine elements of process and product layouts. Effective layout design involves gathering information, developing alternative plans, and creating a detailed layout.
This presentation is on the based on case study done by using line balancing technique which a prime concern for an industrial engineer. This shows an efficient line balancing for a better production line performed at Runner Automobiles Ltd, Bangladesh.
Assembly Line Balancing to Improve Productivity using Work Sharing Method in ...ijtsrd
The garment factories are always trying to improve production and the quality of the garments to sustain in the enormous competitive market. This paper is about the productivity improvement by reducing cycle time with work sharing in garment factories. A garment factory manufactures different types of garments. In many types of garment productions, this paper is to improve productivity of lady pencil skirts production process. Overall efficiency of single model assembly line by reducing the non value added activities, cycle time and distribution of work load at each work station by line balancing. For that, the productivity improvement is shown by two ways. The first way is proper training and supervision for activities and the second is work sharing with same type of jobs and skills. Keywords Cycle Time, Line Balancing, Productivity, Training, Work Sharing. Khin Nann Yu Aung | Yin Yin Tun "Assembly Line Balancing to Improve Productivity using Work-Sharing Method in Garment Factories" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-3 | Issue-5 , August 2019, URL: https://www.ijtsrd.com/papers/ijtsrd26656.pdfPaper URL: https://www.ijtsrd.com/engineering/mechanical-engineering/26656/assembly-line-balancing-to-improve-productivity-using-work-sharing-method-in-garment-factories/khin-nann-yu-aung
1) The study used value stream mapping to analyze the production process of PLC controllers at PALCO in Jordan. The current state map revealed long cycle times for preparing and wiring controllers.
2) Implementing lean principles and techniques, including purchasing an automated crimping machine and adding staff, reduced the wiring preparation time by 50 minutes. This decreased the production cycle time by 30% and increased output from 2 to 4 units per day.
3) The future state map proposed merging some processes, standardizing roles, and using a supermarket pull system to further improve flow and double production rates.
This paper experiments with different heuristic approaches to solve a real facility layout problem at a furniture manufacturing company. Five layout modeling techniques are applied to the problem: graph theory, CRAFT, optimum sequence, BLOCPLAN, and genetic algorithm. The resulting layouts are evaluated based on total area, flow times distance, and adjacency percentage. The best layout is selected using the analytic hierarchy process and is found to improve upon the existing layout, demonstrating the effectiveness of formal modeling approaches for real industrial problems.
The document discusses production operations and management. It covers topics like production planning and control, scheduling, line balancing, work study techniques like method study, time study and motion study. It provides historical context of production management concepts and examples to illustrate scheduling techniques like Johnson's rule and line balancing calculations.
1) The document provides data on production rates, setup costs, machine times, and failure probabilities for multiple production problems. It asks the reader to calculate economic order quantities, production rates, total costs, and other metrics.
2) Specific calculations include determining EOQ, production rates given changes in efficiency or capacity, optimal production setup based on costs, and expected annual maintenance costs given failure probabilities.
3) Multiple choice questions are included at the end for practice.
Line balancing is a manufacturing process that evenly divides work tasks along an assembly line among workstations. It aims to minimize idle time and improve productivity. The key aspects of line balancing include identifying each task, determining the cycle time of processes, and assigning tasks to workstations in a way that balances the workload. Tools used for line balancing include calculators, stopwatches, and time study sheets to analyze process times and balance the workflow. Metrics like cycle time, takt time, and utilization are calculated to evaluate balancing and identify areas for improvement.
The document discusses various facility layout strategies and concepts. It defines facility layout as determining the placement of departments, workgroups, machines, and stock areas. Key layout formats discussed include process layout, product layout, group technology layout, and fixed-position layout. Assembly line balancing concepts are also covered, including precedence diagrams and determining cycle times and workstation loads.
The document discusses layout planning at various levels including plant location, department location, and machine location. It focuses on department location planning and describes the criteria of minimizing material handling costs. The document outlines the systematic layout planning methodology including data collection, flow analysis, quantitative analysis, relationship diagrams, and consideration of space requirements and constraints to develop an optimal layout. The methodology uses a greedy algorithm and 2-opt heuristic to iteratively improve the layout design based on minimizing material handling costs.
The document discusses production plant layout design. It describes how layout design involves analyzing material and product flows, activity relationships, space requirements and restrictions. The goals are to minimize costs and throughput times while allowing flexibility. Several layout types are described for different production situations. Systematic layout planning methods involve gathering data, analyzing flows and activities, developing relationship diagrams and space plans, generating alternative layouts, and selecting the optimal layout while considering flexibility. Material handling systems should also be designed in parallel with the layout.
Line balancing is a technique used to evenly distribute workloads across operators on an assembly line to achieve optimal output. It aims to ensure that all operators have the same amount of work, work is distributed according to customer requirements, variation is smoothed out, no one is overburdened or waiting, and all work together in a balanced fashion. Line balancing is required before starting a new production style and may need to be adjusted daily depending on factors like individual performance, work in progress, absenteeism, and management efficiency. It helps to improve throughput, reduce costs and work in process, while minimizing the number of work stations, cycle time, and balancing workloads.
Plant layout optimization in crane manufacturing using CRAFT and SLPEr Harshrajsinh Kher
Plant layout is a major concern for improvement of productivity in any organization. Here my main objective is to reduce material handling cost for crane manufacturing industry by optimizing plant layout. By using CRAFT, I optimize 16.23% of crane manufacturing industry plant layout.Further using space relationship analysis, I optimize 17.37% of crane manufacturing industry plant layout.
A case study of building maintenance service based on stakeholders’ perspecti...Ryosuke Ichikari
The document describes a case study analyzing the impact of reorganizing maintenance services for three buildings based on perspectives of different stakeholders. Data was collected before and after the reorganization through indoor localization, work logging, and business records. The analysis found that while office work time decreased and productivity improved for management, employees' workloads increased as indicated by more maintenance tasks, longer walking distances and times. For employees, spare time which indicates work intensity decreased more than expected work increased. The study evaluated the reorganization's effects comprehensively from perspectives of management, employees and customers to understand impacts on all stakeholders in the service system.
A case study of building maintenance service based on stakeholders’ perspecti...Ryosuke Ichikari
The document describes a case study analyzing the impact of reorganizing maintenance services for three buildings based on perspectives of different stakeholders. Data was collected before and after the reorganization through indoor localization, work logging, and business records. The analysis found that while office work time decreased and productivity improved for management, employees' workloads increased as indicated by more maintenance tasks, longer walking distances and times. For employees, spare time which indicates work intensity decreased more than expected work increased. The study evaluated the reorganization's effects comprehensively from perspectives of management, employees and customers to understand impacts on all stakeholders in the service system.
1) The document describes a case study of improving the productivity of an automotive engine assembly line through line balancing techniques.
2) Initially, the assembly line had 39 workstations and produced 225 engines per shift. Through time studies and rearranging activities across workstations, non-value added activities were reduced and processing times were equalized to the takt time of 90 seconds.
3) After implementing line balancing improvements like reducing motions and rearranging activities, productivity increased 16% to 262 engines per shift while maintaining the same number of workers. The line efficiency also improved from 64.19% initially to 71.43% after balancing.
This document provides an overview of industrial engineering topics including line balancing, assembly lines, and progress control. It discusses types of assembly lines like single model, mixed model, and multi model lines. Line balancing aims to distribute work evenly across stations to minimize idle time. Methods like heuristic assignment are used. Progress control monitors production schedules and addresses delays to ensure schedules are met.
This document discusses different types of facility layouts including process-oriented, product-oriented, group technology/cellular, and fixed-position layouts. It provides examples of each type and notes that many facilities use a combination. The document also discusses how Taco, a pump manufacturer, redesigned from a process to a product-oriented layout divided into high, intermediate, and low volume areas. This reduced inventory, throughput times, and increased output and market share for Taco. Managers must consider many factors when determining the best layout type.
The document discusses production plant layout problems and methods. It covers:
1. The facility layout problem of designing locations, dimensions, and configurations of activities with no overall algorithm.
2. Reasons for layout changes including new products, demand changes, and bottlenecks. Goals include minimal costs, investments, throughput times and flexibility. Restrictions include legislation and building constraints.
3. Methods for layout include relationship diagrams, space requirements analysis, and evaluating alternative layouts to select the optimal layout.
This document discusses production plant layout and methods for designing facility layouts. It addresses the facility layout problem of determining locations, dimensions, and configurations of activities. There is no single overall algorithm for solving layout problems as each case depends on factors like products, demand, and equipment. The goals of layout design include minimizing costs and throughput times while achieving flexibility and efficient space use, within restrictions like building constraints and safety regulations. Common methods reviewed are systematic layout planning and relationship diagrams to analyze flows between departments and determine optimal layouts.
This document discusses various facility layout concepts and approaches. It begins by defining facility layout as the process of determining the placement of departments, workgroups, workstations, machines, and stockholding points within a facility based on objectives, demand estimates, processing requirements, and space constraints. The document then covers criteria for a good layout, basic layout formats including process, product, group technology, and fixed-position layouts. It provides examples of developing process and product layouts, including the use of computer models, line balancing concepts, and cellular manufacturing layouts. The key objectives are to optimize material flow, worker efficiency, flexibility, and space utilization.
This presentation provided an overview of Ishikawa's seven basic quality tools: histograms, Pareto charts, cause-and-effect diagrams, run charts, scatter diagrams, flow charts, and control charts. For each tool, the presentation defined the tool, explained how to construct it, and provided an example of how the tool can be used. The tools are designed to be simple visual aids to help analyze data, identify relationships and causes, improve processes, and monitor quality.
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET Journal
1. The document describes efforts to improve the productivity of a manufacturing assembly line through the application of lean tools and concepts like line balancing, bottleneck identification and elimination, and reduction of waste.
2. Analysis identified bottlenecks at several workstations where cycle times exceeded the takt time, including side and profile milling, bolt hole drilling, and machining operations. Travel charts and process maps also showed transportation and wait times between workstations.
3. Recommendations included reducing non-value-added activities and cycle times at bottleneck stations, implementing one-piece flow through line balancing, and applying systematic layout planning to minimize transportation and improve material flow. The goals were to increase line efficiency, throughput, and productivity while
Lead Time Reduction in Manufacturing Process of CNC Machines by Lean PrinciplesIRJET Journal
The document presents a case study on using lean principles to reduce lead times in the manufacturing process of CNC machines. It analyzes the current production process through value stream mapping and identifies non-value added activities. The researchers then propose improvements like process reorganization and layout redesign, which are shown to reduce lead times and increase process capability when implemented.
1) The study used value stream mapping to analyze the production process of PLC controllers at PALCO in Jordan. The current state map revealed long cycle times for preparing and wiring controllers.
2) Implementing lean principles and techniques, including purchasing an automated crimping machine and adding staff, reduced the wiring preparation time by 50 minutes. This decreased the production cycle time by 30% and increased output from 2 to 4 units per day.
3) The future state map proposed merging some processes, standardizing roles, and using a supermarket pull system to further improve flow and double production rates.
This paper experiments with different heuristic approaches to solve a real facility layout problem at a furniture manufacturing company. Five layout modeling techniques are applied to the problem: graph theory, CRAFT, optimum sequence, BLOCPLAN, and genetic algorithm. The resulting layouts are evaluated based on total area, flow times distance, and adjacency percentage. The best layout is selected using the analytic hierarchy process and is found to improve upon the existing layout, demonstrating the effectiveness of formal modeling approaches for real industrial problems.
The document discusses production operations and management. It covers topics like production planning and control, scheduling, line balancing, work study techniques like method study, time study and motion study. It provides historical context of production management concepts and examples to illustrate scheduling techniques like Johnson's rule and line balancing calculations.
1) The document provides data on production rates, setup costs, machine times, and failure probabilities for multiple production problems. It asks the reader to calculate economic order quantities, production rates, total costs, and other metrics.
2) Specific calculations include determining EOQ, production rates given changes in efficiency or capacity, optimal production setup based on costs, and expected annual maintenance costs given failure probabilities.
3) Multiple choice questions are included at the end for practice.
Line balancing is a manufacturing process that evenly divides work tasks along an assembly line among workstations. It aims to minimize idle time and improve productivity. The key aspects of line balancing include identifying each task, determining the cycle time of processes, and assigning tasks to workstations in a way that balances the workload. Tools used for line balancing include calculators, stopwatches, and time study sheets to analyze process times and balance the workflow. Metrics like cycle time, takt time, and utilization are calculated to evaluate balancing and identify areas for improvement.
The document discusses various facility layout strategies and concepts. It defines facility layout as determining the placement of departments, workgroups, machines, and stock areas. Key layout formats discussed include process layout, product layout, group technology layout, and fixed-position layout. Assembly line balancing concepts are also covered, including precedence diagrams and determining cycle times and workstation loads.
The document discusses layout planning at various levels including plant location, department location, and machine location. It focuses on department location planning and describes the criteria of minimizing material handling costs. The document outlines the systematic layout planning methodology including data collection, flow analysis, quantitative analysis, relationship diagrams, and consideration of space requirements and constraints to develop an optimal layout. The methodology uses a greedy algorithm and 2-opt heuristic to iteratively improve the layout design based on minimizing material handling costs.
The document discusses production plant layout design. It describes how layout design involves analyzing material and product flows, activity relationships, space requirements and restrictions. The goals are to minimize costs and throughput times while allowing flexibility. Several layout types are described for different production situations. Systematic layout planning methods involve gathering data, analyzing flows and activities, developing relationship diagrams and space plans, generating alternative layouts, and selecting the optimal layout while considering flexibility. Material handling systems should also be designed in parallel with the layout.
Line balancing is a technique used to evenly distribute workloads across operators on an assembly line to achieve optimal output. It aims to ensure that all operators have the same amount of work, work is distributed according to customer requirements, variation is smoothed out, no one is overburdened or waiting, and all work together in a balanced fashion. Line balancing is required before starting a new production style and may need to be adjusted daily depending on factors like individual performance, work in progress, absenteeism, and management efficiency. It helps to improve throughput, reduce costs and work in process, while minimizing the number of work stations, cycle time, and balancing workloads.
Plant layout optimization in crane manufacturing using CRAFT and SLPEr Harshrajsinh Kher
Plant layout is a major concern for improvement of productivity in any organization. Here my main objective is to reduce material handling cost for crane manufacturing industry by optimizing plant layout. By using CRAFT, I optimize 16.23% of crane manufacturing industry plant layout.Further using space relationship analysis, I optimize 17.37% of crane manufacturing industry plant layout.
A case study of building maintenance service based on stakeholders’ perspecti...Ryosuke Ichikari
The document describes a case study analyzing the impact of reorganizing maintenance services for three buildings based on perspectives of different stakeholders. Data was collected before and after the reorganization through indoor localization, work logging, and business records. The analysis found that while office work time decreased and productivity improved for management, employees' workloads increased as indicated by more maintenance tasks, longer walking distances and times. For employees, spare time which indicates work intensity decreased more than expected work increased. The study evaluated the reorganization's effects comprehensively from perspectives of management, employees and customers to understand impacts on all stakeholders in the service system.
A case study of building maintenance service based on stakeholders’ perspecti...Ryosuke Ichikari
The document describes a case study analyzing the impact of reorganizing maintenance services for three buildings based on perspectives of different stakeholders. Data was collected before and after the reorganization through indoor localization, work logging, and business records. The analysis found that while office work time decreased and productivity improved for management, employees' workloads increased as indicated by more maintenance tasks, longer walking distances and times. For employees, spare time which indicates work intensity decreased more than expected work increased. The study evaluated the reorganization's effects comprehensively from perspectives of management, employees and customers to understand impacts on all stakeholders in the service system.
1) The document describes a case study of improving the productivity of an automotive engine assembly line through line balancing techniques.
2) Initially, the assembly line had 39 workstations and produced 225 engines per shift. Through time studies and rearranging activities across workstations, non-value added activities were reduced and processing times were equalized to the takt time of 90 seconds.
3) After implementing line balancing improvements like reducing motions and rearranging activities, productivity increased 16% to 262 engines per shift while maintaining the same number of workers. The line efficiency also improved from 64.19% initially to 71.43% after balancing.
This document provides an overview of industrial engineering topics including line balancing, assembly lines, and progress control. It discusses types of assembly lines like single model, mixed model, and multi model lines. Line balancing aims to distribute work evenly across stations to minimize idle time. Methods like heuristic assignment are used. Progress control monitors production schedules and addresses delays to ensure schedules are met.
This document discusses different types of facility layouts including process-oriented, product-oriented, group technology/cellular, and fixed-position layouts. It provides examples of each type and notes that many facilities use a combination. The document also discusses how Taco, a pump manufacturer, redesigned from a process to a product-oriented layout divided into high, intermediate, and low volume areas. This reduced inventory, throughput times, and increased output and market share for Taco. Managers must consider many factors when determining the best layout type.
The document discusses production plant layout problems and methods. It covers:
1. The facility layout problem of designing locations, dimensions, and configurations of activities with no overall algorithm.
2. Reasons for layout changes including new products, demand changes, and bottlenecks. Goals include minimal costs, investments, throughput times and flexibility. Restrictions include legislation and building constraints.
3. Methods for layout include relationship diagrams, space requirements analysis, and evaluating alternative layouts to select the optimal layout.
This document discusses production plant layout and methods for designing facility layouts. It addresses the facility layout problem of determining locations, dimensions, and configurations of activities. There is no single overall algorithm for solving layout problems as each case depends on factors like products, demand, and equipment. The goals of layout design include minimizing costs and throughput times while achieving flexibility and efficient space use, within restrictions like building constraints and safety regulations. Common methods reviewed are systematic layout planning and relationship diagrams to analyze flows between departments and determine optimal layouts.
This document discusses various facility layout concepts and approaches. It begins by defining facility layout as the process of determining the placement of departments, workgroups, workstations, machines, and stockholding points within a facility based on objectives, demand estimates, processing requirements, and space constraints. The document then covers criteria for a good layout, basic layout formats including process, product, group technology, and fixed-position layouts. It provides examples of developing process and product layouts, including the use of computer models, line balancing concepts, and cellular manufacturing layouts. The key objectives are to optimize material flow, worker efficiency, flexibility, and space utilization.
This presentation provided an overview of Ishikawa's seven basic quality tools: histograms, Pareto charts, cause-and-effect diagrams, run charts, scatter diagrams, flow charts, and control charts. For each tool, the presentation defined the tool, explained how to construct it, and provided an example of how the tool can be used. The tools are designed to be simple visual aids to help analyze data, identify relationships and causes, improve processes, and monitor quality.
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET Journal
1. The document describes efforts to improve the productivity of a manufacturing assembly line through the application of lean tools and concepts like line balancing, bottleneck identification and elimination, and reduction of waste.
2. Analysis identified bottlenecks at several workstations where cycle times exceeded the takt time, including side and profile milling, bolt hole drilling, and machining operations. Travel charts and process maps also showed transportation and wait times between workstations.
3. Recommendations included reducing non-value-added activities and cycle times at bottleneck stations, implementing one-piece flow through line balancing, and applying systematic layout planning to minimize transportation and improve material flow. The goals were to increase line efficiency, throughput, and productivity while
Lead Time Reduction in Manufacturing Process of CNC Machines by Lean PrinciplesIRJET Journal
The document presents a case study on using lean principles to reduce lead times in the manufacturing process of CNC machines. It analyzes the current production process through value stream mapping and identifies non-value added activities. The researchers then propose improvements like process reorganization and layout redesign, which are shown to reduce lead times and increase process capability when implemented.
Application of value stream mapping tool to reduce wastes in bearing industryijmech
In today’s highly competitive business environment, companies require improvement in Production Lead
Times, costs and customer service levels to survive. Because of this, companies have become more
customers focused. The result is that companies have been putting in significant effort to improve their
efficiency.
This paper present the practical application of Value Stream Mapping (VSM) tool implement in a bearing
industry. A value stream is an assortment of all actions (value added as well as non-value added) that are
required to bring a product through the essential flows, starting with raw material and ending with the
customer. For drawing current state value stream mapping, all relevant data has been collected and analyzed. Then analysis of current state map has been done for identifying non-value adding activities, in
other words waste and suggestions on how to remove or reduce different wastes. From the results achieved
by current VSM, it was observable that the two processes Annealing and CNC Machining have higher cycle
time and WIP. In order to increase their capacity, their cycle should be reduced.
By implementing some lean principles and changes in the production line, the future state map was created and the reduction the different types of wastes reduced. The total processing time was reduced from 409
seconds to 344 seconds.
The document discusses the application of work study concepts in apparel manufacturing at Bombay Rayon Fashions Limited. It aims to optimize workplace utilization and productivity through analyzing existing plant layouts and workflows using process charts. Specific areas covered include redesigning the cutting, sewing and finishing sections layouts which improved space utilization and increased production output. Workstation designs and implementation of work study charts helped enhance efficiency.
The International Journal of Engineering & Science is aimed at providing a platform for researchers, engineers, scientists, or educators to publish their original research results, to exchange new ideas, to disseminate information in innovative designs, engineering experiences and technological skills. It is also the Journal's objective to promote engineering and technology education. All papers submitted to the Journal will be blind peer-reviewed. Only original articles will be published.
The document presents a case study on implementing Overall Equipment Effectiveness (OEE) on a CNC table type boring and milling machine at a heavy machinery manufacturing industry. Initial OEE calculations found the machine's OEE to be 62%, below the world-class level of 85%. Suggestions were made to reduce changeover, break, and downtime, which improved the OEE to 75%. Further improvements could bring the OEE closer to the target world-class level.
The document presents a case study on implementing Overall Equipment Effectiveness (OEE) on a CNC table type boring and milling machine at a heavy machinery manufacturing industry. Initial OEE calculations found the machine's OEE to be 62%, below the world-class level of 85%. Suggestions were made to reduce changeover, break, and downtime which improved OEE to 75%. Further improvements could bring OEE closer to the target world-class level.
Balancing the line by using heuristic method based on cpm in salbp –a case studyeSAT Journals
Abstract
In mass production systems, line balancing plays a great role, but this is not easy even if it is a simple straight line. So, in order to
solve these problems Heuristic methods are very much desirable. It is also found that Heuristic methods play a great role in the
formation of metaheuristic methods.Therefore it is very much important to use more efficient heuristic methods. In this research
paper we presents a heuristic method that is based on critical path method for simple assembly line balancing. This research is
mainly concerned with objectives of minimizing the number of workstations, improvement of smoothness index, mean absolute
deviation (MAD) and increasing line efficiency.
Keywords-Heuristic methods,Assembly line balancing problem, Critical path method, Simple assembly line balancing.
The document provides a report on analyzing and optimizing the manufacturing system of a client company called KCP technologies Private Ltd. Key points:
- The company manufactures screw pump rotors in a batch production process using 3 CNC workstations.
- Cycle times for the two main products were recorded to calculate production rates. Motion studies were conducted to optimize workstation layouts and reduce travel times.
- The current number of workstations was found to be optimal. Modifications like rearranging tools saved an estimated 1 minute per part produced.
- Further analyses included machine cluster possibilities and quality assurance processes to improve the system.
The document provides a report on analyzing and optimizing the manufacturing system of a client company called KCP technologies Private Ltd. Key points:
- The company manufactures screw pump rotors in a batch production process using 3 CNC workstations.
- Cycle times for the two main products were recorded to calculate production rates. Motion studies were conducted to optimize workstation layouts and reduce travel times.
- The current number of workstations was found to be optimal. Modifications like rearranging tools saved an estimated 1 minute per part produced.
- Further analyses included machine cluster possibilities and quality assurance processes to improve the system.
This report analyzes and optimizes the manufacturing system of a client that produces screw pump rotors. Key points:
1) The factory currently has 3 CNC workstations and produces rotors in batch production. Cycle times were recorded to calculate production rates.
2) The optimum number of workstations was calculated to be 2.97, matching the current 3 workstations. Motion studies were conducted to reduce repositioning times.
3) Implementation of layout changes reduced average cycle times, increasing production rates. Machine clustering allowed one worker to manage multiple machines.
4) Cost analyses showed the optimized system with clustering lowered production costs per unit compared to the present situation. Further automation of material handling was recommended
IRJET-Productivity Improvement in a Pressure Vessel using Lean PrinciplesIRJET Journal
This document discusses improving productivity in a pressure vessel manufacturing company through implementing lean principles. The company was facing issues like production line stoppages and long lead times due to an unstructured inventory management system. Value stream mapping revealed long wait times and a very low inventory turnover ratio of 0.17%. To address this, a Kanban system was proposed and implemented in the supply chain for outsourced dish components. This changed the production from a push to a pull system. After implementing Kanban, line stoppages were reduced by 68% and lead time decreased from 6.5 to 4.3 days. The inventory turnover ratio also improved to 0.35%. In conclusion, implementing lean tools like Kanban helped optimize the supply chain and
IRJET- Efficiency Enhancement by Reducing Production and Machining TimeIRJET Journal
This document summarizes a study on improving efficiency in a manufacturing process by reducing production time and machining time. It discusses using lean manufacturing techniques like value stream mapping, work standardization, and line balancing in a CNC machining cell that produces housings for gearboxes. Value stream mapping was used to analyze the current process and identify opportunities for improvement. Process times were analyzed using time studies and video analysis to standardize work and reduce non-value added activities. Line balancing was also implemented to better distribute the workload between operators and reduce idle time. The results showed reductions in lead time and improvements in overall equipment effectiveness.
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENTIRJET Journal
This document discusses techniques to improve productivity at a motor manufacturing company through time study analysis. It finds that the assembly line's bottleneck operation is the routine testing process, which takes over 150 seconds. It is suggested to implement a new, faster testing machine that reduces this time to 90 seconds. It also proposes performing some assembly steps simultaneously, such as having one worker mount terminal boxes while another screws lug terminals, which could reduce the overall cycle time from 269 to 185 seconds and increase the production rate. Time study is presented as a key method for identifying opportunities to eliminate unnecessary tasks and activities to minimize human effort and maximize productivity.
IRJET- Enhance the Capacity of Outer Tube Machining CellIRJET Journal
This document discusses enhancing the capacity of an outer tube machining cell at a manufacturing plant. It begins by outlining the current problem of not being able to meet customer demand and having a production gap. The objectives are then stated as increasing production rate, maximizing resource use, meeting customer requirements, and increasing profit. Data is collected from the shop floor on processing times for each workstation. The longest processing workstation is identified as the bottleneck. Modifications are proposed to reduce processing time at the bottleneck station, such as modifying a scrap fixture, in order to increase production rate and meet forecasted demand. The proposed changes are expected to increase the production rate and fulfill customer requirements while gaining higher profits.
Value Analysis of A Rubber Hose Moulding and Assembly Line: A Case StudyIRJET Journal
This document discusses a case study on applying value analysis techniques to optimize a rubber hose moulding and assembly line. Value analysis tools were used to identify problems like high work-in-process inventory, long throughput times, and low productivity. Solutions proposed combining operations, reducing labor, combining moulding processes, and modifying equipment. These changes reduced throughput time by 87%, space utilization by 51%, and increased individual productivity by 250%. The case study demonstrates how value analysis can significantly improve process efficiency and competitiveness.
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...IRJET Journal
This document presents a case study on improving overall equipment effectiveness (OEE) in a manufacturing industry. It discusses how OEE is calculated based on availability, performance rate, and quality rate. The study was conducted at Avison Industry in Kolhapur, India. Data was collected on production rates and downtime reasons. It was found that the performance rate was below 95%, indicating room for improvement. Various problems were identified through analysis, such as hole shifting during drilling. Solutions proposed included modifying fixtures, combining drilling and reaming, and changing the production process flow. After implementing solutions, the OEE values improved to above 95%, meeting benchmarks for effective equipment performance.
Line Balancing and facility optimization of Machine Shop with Work Study and ...IRJET Journal
1) The document describes a study conducted at a machine shop to improve productivity and optimize facility usage through work study methods and simulation modeling.
2) Time and motion studies were used to calculate standard times for machining processes on an MK 25 hub part. Simulation software was then used to model the existing system and test improvements.
3) Experiments showed dividing the system into two groups that run alternate shifts improved machine utilization above 70% while meeting daily production targets. This addressed issues of low output and machine idle time in the existing setup.
The document discusses production operations and management. It covers topics such as the production process, production planning and control, scheduling, sequencing methods for multiple machines/jobs, line balancing, and key performance metrics like cycle time and balance efficiency. A sample problem is provided to illustrate the calculation of cycle time, number of work stations, balance efficiency, and balance delay for a production line.
AN EXPERIMENTAL STUDY ON THE AUTOMOTIVE PRODUCTION LINE USING ASSEMBLY LINE B...IAEME Publication
The main aim of an assembly line is to group the different facilities and workers inan efficient manner in order to obtain effective utilization of man power and machine.This calls for uniform rate of production as well as decrease in the work in process
inventory. Hence, this paper attempts to achieve these in an assembly line of anautomotive manufacturing unit using three different techniques such as Largestcandidate rule (LCR), Kilbridge and wester column method (KWC) and Rank
positional weighted method (RPW). All the three methods show better efficiency and acomparison is also drawn amongst the three to determine the best suited techniquepertaining to the current research work
AN EXPERIMENTAL STUDY ON THE AUTOMOTIVE PRODUCTION LINE USING ASSEMBLY LINE B...
vignesh conference
1. >FOR CONFERENCE-RELATED PAPERS, REPLACE THIS LINE WITH YOUR SESSION NUMBER, E.G., AB-02 (DOUBLE-CLICK HERE)< 1
IMPROVING THE PRODUCTIVITY OF EXISTING DISC LINE
THROUGH A KAIZEN
S.Sampath Kumar1*
, V.Vignesh2
1*
Professor, Department of Mechanical Engineering, CEG Campus, Anna University, Chennai-600025
2
PG Student, Department of Mechanical Engineering, CEG Campus, Anna University, Chennai – 600025.
Email: ssk@annauniv.edu1*
, vignesh_1610@yahoo.com2
Kaizen, a lean tool which emphasis on smaller but continuous improvements on a production line,
thereby improving the operational excellence and productivity in many industries over the years.
This mainly concentrates on eliminating or reducing the proportion of non-value adding activities
present in each workstation of the production line. This work aims to improve the productivity of the
production line, which manufactures product X by at least thirty percent using Kaizens. A total of
five higher priority Kaizens were found, of which one of the Kaizen is discussed here. The present
time taken for the upstroke and down stroke of the feed cylinder in reaming station constitutes
around fifty percent of the entire work station time. This paper explains the calculations in detail
about how the stroke of the feed cylinder is improved by replacing the higher diameter cylinder with
a lower diameter one without affecting operation characteristics. On replacing the cylinder, the
velocity is improved by four times and a considerable amount of time is saved in the reaming station,
which was one of the bottleneck station. All other Kaizens will be discussed as a future work.
Index Terms—Kaizen, Productivity
I. INTRODUCTION
Automobile has become an essential one to
everyone‟s life. Due to heavier competition,
industries are forced to manufacture cars at lower
cost, higher quality and at quicker pace. Increased
material and labor cost has caused more burden to
the automobile and their ancillary industries. Their
problems are multiplying on day to day basis [1].
The end customers are the most affected, as the
companies force their losses onto them. Though the
cutting edge technology is put in use, still the
problem persists. The companies are trying
different approaches to tackle the problem, one
such approach is the KAIZEN approach [2], which
this work emphasis on. This work is done at an
automobile auxiliary unit, which manufactures
product X and has seven workstation in its
production line.
A) LITERATURE REVIEW
Lean Manufacturing has become a major
revelation among industries, such that they improve
operational excellence, continuous improvement
and the elimination of non-value adding activities
[1].One among the lean tool is Kaizen, which
emphasis on low cost improvement on a continuous
manner [2].This tool brings out complete employee
co-operation, thereby improves teamwork in a firm.
Low cost automation through Kaizen has become
popular among industries, which reduces the cost of
the labour associated to the work [4].Improving the
productivity has been the challenge for many
industries over the years, which Kaizens able to do
it.Study of existing layout through time study needs
accurate results, so as to scale the improvement
needed at each workstations[5].This work able to
concentrate on all aspects from time study to the
implementation of Kaizens, which is discussed in
the coming sections.
B) METHODOLOGY
The following Fig1 summarizes about the detail
methodology followed in this work. The work
started with a detail study of existing layout,
followed by the time study which gives a clearer
image of stations that are bottleneck in the
production line.
2. >FOR CONFERENCE-RELATED PAPERS, REPLACE THIS LINE WITH YOUR SESSION NUMBER, E.G., AB-02 (DOUBLE-CLICK HERE)< 2
Fig1.Methodology of work
A detailed calculation of present and target
cycle time is calculated so as to find the scale of
improvement needed [6]. Next, Identifying the
areas for Kaizens is done and a best solution is
taken and designed. After designing, required
materials are either purchased or fabricated and
then installed. The installed system is monitored
and feedback is taken from the firm.
C) PROBLEM DEFINITION
The objective of this work was to improve the
productivity of existing production line in order to
meet its demand. The company had some
productivity issues on its Product line .The
Company could produce 398 nos of X per shift
against the demand of 600 nos of X per shift. The
company‟s interest was to improve the productivity
by eliminating the huge proportion of non-value
adding activity present in its four workstations out
of seven workstation, through Kaizens. Table 1
summarizes detailed production line characteristics
of the production line.
Figure II .Results From Time Study
Figure II represents the results of time study of all
stations. It is clear that the stations such as
Reaming, Boring, De- burring and Marking are
well above the target cycle time.
II. TIME STUDY
Table I represents the production line
characteristics of the line, which gives a clearer
0
20
40
60
CHART REPRESENTING THE OPERATION TIME AT
EACH STATION
Present cycleTime=64
Target Cycle Time = 41
TABLE I
PRODUCTION LINE CHARACTERISTICS
S No Description Data‟s
1 Nature of
production
system
Batch Production
2 Product Disc for wheels
3 Line Name Escol Disc Line
4 Type of layout In-line layout
5 Product variety 38
6 Transfer type Manual
7 Total man
power
07
8 Total number
of work
stations
07
9 Total number
of machines
05
10 Setup time 45 mins
11 Total layout
area
750 sq.ft/
3. >FOR CONFERENCE-RELATED PAPERS, REPLACE THIS LINE WITH YOUR SESSION NUMBER, E.G., AB-02 (DOUBLE-CLICK HERE)< 3
idea of the existing system.
Time study is a work measurement technique
for recording the time of performing a certain
specific job or its element carried out under specific
condition and for analyzing the data so as to obtain
the time necessary for an operator to carry out at a
defined rate of performance. A detailed time study
was carried out with the help of camcorder and stop
watch.
A detailed calculation of present and target
cycle time is done in coming sections. It is evident
that four workstation (Reaming, Boring, Deburring,
Marking) are well above the target cycle time of 41
sec from figure II. So our utmost concentration lies
on those stations first. This work concentrates only
on reducing the operation time in Reaming station
alone.
1) OPERATION AT THE REAMING STATION
Table II represents the list of activities
performed and their average time at reaming
station. It is clearly evident that the activities A.3
and A.5 have huge proportionate of time as against
other activities performed at the same station.
These activities alone constitutes 35 % of total
workstation time. In here, VA represents Value
Added Activities, NVA represents Non Value
Added Activities, NVA (PT) represents Non Value
Added Activities with present technology. A
detailed time study results are represented here.
III) CALCULATIONS OF CYCLE TIME
In this section, we will be discussing about the
calculations of cycle time from the time study data
and target cycle time needed to achieve the
production rate. This clearly indicates the
workstation that needs improvement and scale of
improvement that has to be implemented.
Cycle time is defined as the maximum time that
one work unit spends at a station. It is the time
between when one work unit begins processing and
when the next unit begins the cycle, Tc is the time
a component spends at a workstation. Now we will
discuss the calculation of present and target cycle
time in the coming section.
1) CALCULATIONS OF PRESENT CYCLE TIME
Cycle time (Tc) = To+Th+Tth (1)
(To=Actual processing Time (min/pc),
Th=handling time (min/pc),
Tth=Tool handling time (min/pc)
Eq (1) can be generalized to most processing
operations in manufacturing.
Assuming Tth=0 in Eq(1)
Tc.=Max (To+Th)=60+4
(Marking station has highest time =60sec)
= 64 sec/pc (1.066min/pc) (2)
1.1) TO FIND TP AND RP FOR BATCH PRODUCTION
Batch processing time (Tb) =Tsu+ (Q*Tc) (3)
(Tsu=Setup time for the batch, Q=Batch Quantity)
Substituting Tc from Eq(2)
Tb= 45+ (400*1.06)
(Setup time=45mins, Batch Quantity=400)
Tb = 471mins (4)
Avg Prod. Time (Tp) = Tb/Q (5)
TABLE II
PRODUCTION LINE CHARACTERISTICS
Task
ID
Activity VA/NVA Avg
Time
(Sec)
A REAMING
A.1 Taking disc from
palette and
keeping on lifter
NVA(PT) 11.5
A.2 Pushing the disc
from lifter to the
machine
NVA 1.9
A.3 Upstroke of the
fixture
NVA 8.7
A.4 Reaming process
(machining)
VA 11
A.5 Down stroke NVA 7.8
A.6 Cleaning of scrap
on the disc
NVA 4.6
A.7 Pushing the disc
from lifter on to
the conveyer
NVA(PT) 2
ADDITIONAL
Waiting for the
rack pinion
arrangement to
turn
1.9
Allowances 3.04
TOTAL 52.40
4. >FOR CONFERENCE-RELATED PAPERS, REPLACE THIS LINE WITH YOUR SESSION NUMBER, E.G., AB-02 (DOUBLE-CLICK HERE)< 4
Substituting the values from eq(4),
Tp=471/400 = 1.18mins/pc (6)
Avg.Prod Rate (Rp) =60/Tp (7)
Rp = 51X‟s/hr (8)
Avg .Prod Level = Rp*no of hours
(Rejections not considered)
51*8=408 X‟s/shift (9)
Avg .Prod Level = (Rp*no of hours)-q
(q-No of rejections)
(Rejections Considered)
= (51*8)-10=398 X‟s/shift (10)
The above mentioned calculations clearly states
that the average demand met with existing cycle
time is only 2, 38,800pieces as against the forecast
demand of 3, 60,000 X per year.
2) CALCULATION OF TARGET CYCLE TIME
Company wants to meet the demand of 3, 60,000
discs per year (30,000 p.m.).
On assuming same rejection level,
Required Hourly production Rate (Rpplanned) =
(Da+qa)/ (50 x Sw x Hsh) (11)
Da=Annual demand needed=3,60,000X‟s
(no rejections)
qa=Annual no of rejections=(10*12*50)
=6,000X‟s/year Sw = No of shifts /week = 12
sh= Hours/Shift = 8hr
(Rpplanned)= (3, 60,000+6000)/ (50x12x8)
= 76 X‟s /hour.
Rpplanned=608 X‟s/shift (12)
Tpplanned=60/Rpplanned = 60/76
Tpplanned=0.79min/X (13)
From Eq (5),
Tpplanned=Tbnew/Q= 0.79 =Tbnew/400
Tbnew = 316mins (14)
Assuming that the setup time remains the same,
From Eq (3)
Batch processing time (Tbnew) =Tsu+ (Q*Tctarget)
Tctarget= (Tbnew-Tsu)/ (Q)
= (316-45)/ (400)
Tctarget=0.6775mins=41 secs (15)
It is clearly evident that our target cycle time comes
to be 41sec which is 23sec lesser than the current
cycle time. So it has to be concentrated such that all
the elemental workstation timings should be well
below the target cycle time, so as to achieve the
demand.
III. KAIZEN
Kaizen is a Japanese philosophy for process
improvement that can be traced to the meaning of
the Japanese words „Kai‟ and „Zen‟, which
translate roughly into „to break apart and
investigate‟ and „to improve upon the existing
situation‟. Kaizen means improvement on a
continuous basis involving everyone in the
organization from top management, to managers
then to supervisors, and to workers. In Japan, the
concept of Kaizen is so deeply engrained in the
minds of both managers and workers that they often
do not even realize they are thinking Kaizen as a
customer-driven strategy for improvement.
1) KAIZEN K.H.1
Our first Kaizen was to reduce the upstroke and
downstroke time of the fixture in reaming station as
summarized in table 2.This is considered as higher
priority Kaizen, so it is named as Kaizen K.H.1.Let
us see the upstroke and downstroke activities in
detail in coming section.
1.1) UPSTROKE OF THE FIXTURE
The activity A.3 of this station represents the
upstroke of the fixture, wherein a cylinder of
160mm is used to lift the fixture along with the
product X. The labour actuates the value for the
upstroke of the hydraulic cylinder for each and
every cycle. The pressure of the oil gives a force to
push up the fixture, so as to help the product X
come closer to the reamer tool. This activity takes
around 9 sec to get it completed. The machining is
done as the next step after the upstroke of the
fixture is done. At present a cylinder of bore size
diameter of 160mm is used, which is seen as a
potential area for improvement.
ACTIVITY A.3
5. >FOR CONFERENCE-RELATED PAPERS, REPLACE THIS LINE WITH YOUR SESSION NUMBER, E.G., AB-02 (DOUBLE-CLICK HERE)< 5
1.2) DOWN STROKE OF THE FIXTURE
ACTIVITY A.5
The activity 5 downstroke of the fixture is
followed by the machining process. Once the
machining process is over, the fixture along with
the product X is downstroked.It takes around 7
seconds for this activity to get completed. This is
seen as the area for improvement, where time to get
the activity completed can be halved if the cylinder
of lesser bore diameter size is used.
1.3) ACTION PLAN
At first, the existing system was completely
studied. A detailed dimension for the feed cylinder
was studied inside, by checking the drawings. We
found that the cylinder of bore size 160mm was
used, which we felt too much for the weight of the
fixture along with the product X. It is evident that
we need more fluid to get filled for the higher
diameter cylinder. Once filled, then the force is
induced by the fluid on the bore, such that the
cylinder actuates as the upstroke process is done. In
reverse, the down stroke of the fixture happens by
the effect of releasing the fluid from the cylinder,
which also takes more time to get emptied.
We found that it is evident to see that the higher
bore size of the cylinder was the case of concern for
this slower process time. Our action plan was to
reduce the bore diameter of the cylinder and
thereby reducing the process time. A detailed
design calculation was done in order to find the
magnitude of reduction needed to achieve the
reduction in process time of this process.
1.4) DESIGN OF CYLINDER
Old cylinder calculation:
Bore diameter of the cylinder = 160mm
pressure of the hydraulic fluid = 5 bar
Vo=Q/Ao (1)
Vo=Velocity of the old cylinder
Q=Flow rate
Ao=Area of cross section for old cylinder
Ao= (π/4) (Do) 2
Sub Ao value to Eq (1)
Vo=Q/ (π/4(Do)2
) (2)
Table III represents the time saved after
installation of the newcylinder.It is clearly seen that
around 7 sec is saved.
New cylinder calculation:
Vn=Q/An (3)
Vn=Velocity of the new cylinder
Q=flow rate
An=Area of cross section for new cylinder
An= (π/4) (Dn) 2
Sub An value in Eq (3)
Vn=Q/ ((π/4) (Dn)2
) (4)
Assuming Vn=4Vo;
So,Vo/Vn=(1/4) (5)
Substituting eq (2) and eq (4) into eq (5), we get
4 Dn2 = Do2
Dn= (Do)/2
Dn=80mm. (6)
The nearest standard dimension is 80 mm Dnc
Festo Cyliner.
It is evident that the velocity of the stroke
increases by 4times, when the diameter of the
bore is reduced by halved.
1.5) FORCE CALCULATION
F=P/A (P=Pressure), (A=Area of the bore)
Old Cylinder
Fo = ((π/4) (Do) 2
) x P
= ((π/4) (0.16)2
) x (5x10 5)
= 10,048 N (7)
New cylinder
Fn = ((π/4) (Dn) 2
) x P
= ((π/4) (0.08)2
) x (5x10 5) = 2,512 N (8)
TABLE III
TIMING OF ACTIVITY A.3 AND A.5 – BEFORE AND AFTER
CYLINDER CHANGE
S.no Activity
Before
(time in
sec)
After
(time in
sec)
1 Upstroke of
fixture
9 5
2 Down stroke of
the fixture
7 4
6. >FOR CONFERENCE-RELATED PAPERS, REPLACE THIS LINE WITH YOUR SESSION NUMBER, E.G., AB-02 (DOUBLE-CLICK HERE)< 6
Required Force calculation:
Maximum Disc Weight = 35Kg
= 35 x 9.81
= 343 N (9)
Supporting Plate and Fixture Weight = 200 Kg
= 200 x 9.81
= 1962 N (10)
Adding the values (9) and (10)
Total weight to be lifted = 1962 + 343
= 2305 N (11)
On comparing the values (9) and (11), it is
clearly evident that the newer cylinder of 80mm
diameter is capable of lifting the required load.
1.6) INSTALLATION
We could see that there is a possibility
reduction of bore size of the cylinder so as to
reduce the process time. We planned to replace the
existing 160mm bore diameter size cylinder to
80mm bore diameter size. This is a standard size of
the cylinder, such that those were easily available at
the stores. With the help of maintenance
department, we could replace the 160mm diameter
cylinder to 80mm diameter cylinder .We could see
the results to be drastically changed.
We could see that 4seconds are reduced in
the Upstroke activity and a 3 seconds change in
Downstroke activity. In total a 7 seconds reduction
was possible in the reaming station, which is
considered to be a vast improvement.
1.7) DIFFERENCE IN PRODUCTION LEVEL
A detailed comparative study of productivity
data were done before and after installation of
cylinder at reaming station [6].
Time Saved
Upstroke of the cylinder operation = 4 sec
Down stroke of the cylinder operation = 3 sec
---------
=7sec (1)
---------
Workstation Time (Old Time) = 52 sec
= 0.86 min/X (2)
Workstation Time (New Time) = 45 sec
= 0.75 min/X (3)
1.8) OLD TIME FOR REAMING STATION
Batch processing time (Tb) =Tsu+ (Q*Tc)
(Tsu=Setup time for thebatch, Q=Batch Quantity)
Substituting Tc from eq (2),
Tb=45+ (300*0.86)
(Setup time=45mins, Batch Quantity=300)
Tb=303mins (4)
Avg Prod. Time (Tp) = Tb/Q
Substituting the values from eq 4,
=303/300
Tp= 1.01mins/pc (5)
Avg.Prod Rate (Rp) = 60/Tp
= (60/1.01)
Rp = 59 X’s/hr (6)
Rp = 59 * 8
Rp = 472 X’s/shift (7)
1.9) NEW TIME FOR REAMING STATION
Batch processing time (Tb*) =Tsu+ (Q*Tc) (8)
(Tsu=Setup time for the batch, Q=Batch Quantity)
Substituting Tc from Value 3
Tb*=45+ (300*0.75)
(Setup time=45mins, Batch Quantity=300)
Tb*=270mins (9)
Avg Prod. Time (Tp*) = Tb*/Q
Substituting the values from eq 9,
=270/300
Tp*= 0.9mins/pc (10)
Avg.Prod Rate (Rp*) = 60/Tp*
= (60/0.9)
Rp* = 67X’s/hr (11)
Rp* = 67 * 8
Rp *= 536 X’s/shift (12)
1.10) DIFFERENCE IN PRODUCTION LEVEL
Eq (12)-(8) we get,
Rp*-Rp=536-472 = 64 X’s/shift
It is clearly evident that there is a clear
difference of 64 X’s can be produced at the
reaming station, without any changes in
operational characteristics.
7. >FOR CONFERENCE-RELATED PAPERS, REPLACE THIS LINE WITH YOUR SESSION NUMBER, E.G., AB-02 (DOUBLE-CLICK HERE)< 7
CONCLUSION AND FUTURE WORK
Due to increased customer expectations and
global competition, companies are forced to
improve their productivity at lower cost and still
retain best product quality. This work addresses the
productivity issues with the above said in mind,
such that nearly 7 seconds of total workstation time
is saved. A simple cylinder change of lower
diameter has increased the stroke of the cylinder
such that it has saved about 20 twenty percent of
the workstation time.
The future work will emphasize on solving
other Kaizens which are found in Marking,
Deburring and Boring stations such that
improvements will be smaller in magnitude, cost
effective and in a continuous manner.
IV. REFERENCES
[1] D.Rajenthirakumar& P. R. Thyla (2009),
“Quality and Productivity Improvement in
Automotive Component Manufacturing
Company Using Kaizen”, Journal of
Manufacturing Systems.
[2] R.Radharaman, L.P Godoy &K.I.Watanbye
(2010), “Quality and Productivity Improvement
in a Custom Made Furniture Industry using
Kaizen”, Elseiver Science Limited, S0630-
8352(96) 001775.
[3] Jr. Jung luye (1996), “Applying Kaizen and
Automation in Process Engineering” Journal of
Manufacturing Systems, Vol 15.
[4] MebyMathewa and D.Samuelraj(2013),
“Reduction of Cycle Time Using Lean Tools in
an Automobile Assembly Line”, Proceedings of
the National Conference on Manufacturing
Innovation Strategies & Appealing
Advancements, P.S.G College of Technology.
[5] Takafumi Ueda (1998), “Quality and
Productivity Improvement JICA‟s Kaizen
assistance”, Japan International Cooperation
Agency.
[6] Mikel.P.Groover (2003), “Automation,
Production Systems and Computer Integrated
Manufacturing”, Page 49, 50.
[7] Walter.G.Holmes (1939), “Applied Time and
Motion Study”, The Ronald Press Company.