SlideShare a Scribd company logo
1 of 46
TO IMPROVE OEE OF MODULE IMPLANTING
MACHINE IN A SIM-CARD MANUFACTURING
COMPANY USING LEAN TOOLS
SUBMITTED BY: SANCHIT JAIN
M.TECH P&IE)
2016-18
UNDER THE SUPERVISION OF:
DR. RAHUL O. VAISHYA
ASSISTANT PROFESSOR
27-7-2018 BY- SANCHIT JAIN
INTRODUCTION
R1. Can Lean Tools be used to improve system performance of a SIM Card
manufacturing company?
R2. Can Overall Equipment Effectiveness be used as a measure to improve
equipment effectiveness?
RESEARCH QUESTATION
27-7-2018 BY- SANCHIT JAIN
RESEARCH METHODOLOGY
RESEARCH DESIGN Defined as the framework for collecting and
analysing data.
 5 research designs suggested by Bryman and Bell (2003) are:
• Experimental Design - Comprising an experiment that is being conducted
in a laboratory or a natural setting in a systematic way.
• Cross-Sectional Design - A snap-shot of an on-going situation to investigate economic
characteristics of large numbers of people or organisations.
• Longitudinal Design - The approach that collects data for two or more distinct time
periods with the subjects being the same or comparable from
one period to the next.
• Comparative Design - Used to uncover contrasting findings between two or more
cases
• Case Study Design - An up-close, in-depth, and detailed examination of a subject of
study (the case), as well as its related contextual conditions.
Action Research – This approach allows the researcher to make a 'real-time'
contribution to the research in parallel to matching the expected academic rigour.
27-7-2018 BY- SANCHIT JAIN
RESEARCH METHODOLOGY
Research opportunities
Literature Review
Research Methodology
Data Collection
Applying Lean Tools in
Case Studies
Analysis of Outcomes
OEE Improvement/ Achieving research objectives
RESEARCH DESIGN FOR THIS THESIS PROJECT
Case Study and Action Research both seems
useful approaches to be adopted for this
thesis. For this, a SIM card Manufacturing
Company is used as the sole case organisation
in order to be aware of what type of problems
can be met, and how to get around them. As
the main aim of this project is to improve the
effectiveness of a machine, some aspects
surrounding the machine will change. It could
be some technical devices, some operation
modification or some way to act, that could be
modified.
RESEARCH MODEL
27-7-2018 BY- SANCHIT JAIN
OVERVIEW OF CASE
ORGANIZATION
The case organization specialises in Smart Cards manufacturing
INDUSTRY CHARACTERISTICS DETAILS ABOUT CASE ORGANIZATION
Company Name & Location Syscom Corporation Pvt Ltd, Noida (IDEMIA, France MNC)
Industry sector Telecommunication
Product SIM Cards/Telco Cards
Production volume and variety High Volume - High Variety
Manufacturing Type/ Process Batch Manufacturing / Make To Order process
MAIN UNIT CBC ULCC
27-7-2018 BY- SANCHIT JAIN
PRODUCT RANGE
GOVT / Health ID
BANKING
BIOMETRIC
QUARTER
TELCO
ID1 HALF
27-7-2018 BY- SANCHIT JAIN
PRODUCTION PROCESS
Module
lamination
Card Body
Milling
Module
Implanting
Chip
Personalisation
Card Body
PunchingWarehouse
(RM Stock)
Warehouse
(Finished
Stock)
Production Process Flow Value Stream.
The production process flow begins with
Cavity milling process on the card body
(CB) to host the module and an adjacent
process to prepare modules by Chip
module lamination before Implanting
Chip Module on CB. The next stage is
Card Personalization which includes
within itself the sequence of steps that
make every smart card unique. During
this process individual card holder data
are loaded into the chip memory. The
final stage is Card Breaking / Punching
where the plug-in of two types (Combi
SIM card: which comes with Mini SIM &
Micro SIM cards plug-in and Trio SIM:
which supports all three plug-in variants
of Mini SIM (2FF), Micro SIM (3FF) and
Nano SIM (4FF) all in one SIM) is punched
on SIM card and also the card is break in
half or quarters using a metallic tools.
27-7-2018 BY- SANCHIT JAIN
AVAILABLE RESOURCE
Process (Pn)
Machine
Name (Xn)
Number of
machines
Hourly
Capacity
Module Lamination (P1) CML 3 36000
Card Body Milling (P2) JMD 5 40000
Module Implanting on Card body (P3) JED 5 36000
Chip Personalisation (P4) SYE 3 36000
Card Breaking / Punching (P5) CB+YMJ 3+1 36000
Theoretical Capacity per month = XBottleneck*(Base Hour/day)*(Planned Days/ Month)
= 36000*24*26 = 22.4 Mu/month
A review of the existing process indicated that data driven improvements and therefore
more process specific data was needed to understand the problems that indicate where
and what improvements could be made.
Actual Production (61% OEE) = 13.6 Mu
27-7-2018 BY- SANCHIT JAIN
OVERALL EQUIPMENT
EFFECTIVENESS (OEE)
The accurate estimation of the equipment utilization is very important especially in a
capital-intensive industry (e.g. the semiconductor, SIM-card and chemical industries) and
Overall Equipment Effectiveness (OEE) is the best known indicator of equipment
performance.
YEAR AUTHOR THEME
1988-
89
Nakajima
Introduces OEE as the measure of TPM used for collecting and
analysing the combined effects of plant availability, performance
and quality.
1992 Hartmann
Concept of Hidden Factory and suggested TPM is the key to
unlock.
2000
Willmott and
McCarthy
Confirms the work of Nakajima on OEE and applied to achieve
best of the best equipment efficiency
2001 Jeong & Phillips
Redefined OEE based on capital intensive Industry and
introduced TPIS.
In a capital intensive industry managers want to utilize their equipment as effectively as
possible to get an early return on their investment.
27-7-2018 BY- SANCHIT JAIN
Nakajima (1988) define OEE as a measure of the effective utilisation of capital assets by
expressing the impact of equipment losses based on six types of equipment losses
tracked in the OEE calculation.
NAKAJIMA’S OEE
CALCULATION
27-7-2018 BY- SANCHIT JAIN
CRITIQUE ON OEE
CALCULATION
Nakajima’s OEE calculation does not include scheduled maintenance time for preventive
maintenance and non-scheduled time such as off-shift and holiday. These time losses are
however, important in capital-intensive industry. For example, to reduce nonscheduled
time, most SIM card manufacturers are operating three eight hour shifts.
1. Non Scheduled Time: time duration for which equipment is not scheduled to
operate. This time may include holiday and leave, etc.
2. Scheduled maintenance time: time spent for preventive maintenance in the
equipment.
3. Unscheduled maintenance time: time spent for breakdown.
4. R&D time: time spent for the purpose of research and development.
5. Engineering usage time: time spent for an engineering check-up.
6. Setup and adjustment time: time spent for setup and adjustment for operation.
7. WIP starvation: the time for which equipment is operating when there is no WIP to
process.
8. Idle time without operator: time for which WIP is ready; however there is no
operator available.
27-7-2018 BY- SANCHIT JAIN
According to Jeong & Phillips (2001), the downtime category varies from company to
company and must be individually defined and categorized accordingly to meet the
requirements of OEE in their company.
Sr. No. Organization's D/T Categories Jeong & Phillips D/T Categories
1 Preventive Maintenance Scheduled Maintenance Time
2 No plan by PPC Non Scheduled Time
3 New product Trail R&D
4 Planned facility Down Scheduled Maintenance
5 Material not procured timely* N.A.
6 Machine breakdown Unscheduled maintenance time
7 No Milled Cards WIP starvation
8 Batch Change Setup & Adjustment
9 Machine Cleaning Engineering usage time
10 ATR Rejection Unscheduled maintenance time
11 Setup change Setup & Adjustment
12 Kanban buffer* N.A.
13 No Operator Idle Without Operator
CRITIQUE ON OEE
CALCULATION
27-7-2018 BY- SANCHIT JAIN
OEE CALCULATION FOR
CASE ORGANIZATION
Preventive
Maintenance
No plan by PPC
New Product Trail
No milled Cards
Machine Cleaning
Machine Breakdown
Batch change
Setup change
No Operator
Throughput Loss
Total Time
Net Operation Time
Operating Time
Availability = Operating Time/ Total Time
OEE= Availablity x Performance x Quality
Valuable
operating
Time
Quality Loss
Performance = Net Operating Time/ Operating
Time
Quality = Valuable Operating Time/ Net
Operating Time
27-7-2018 BY- SANCHIT JAIN
IMPLEMENTING TAKT TIME
Takt time is the maximum amount of time in which a product needs to be produced in
order to satisfy customer demand.
Steps To Implement TAKT Time
1. Measuring individual cycle times of each process.
2. Comparing each cycle time with the Takt time to identify bottleneck processes-
those with cycle time more than Takt time.
3. These bottleneck processes are made free from NVA in order to bring cycle time
below takt time and achieve customer demand.
The Calculation for takt time is as follows
• Available Production time = Total production time – (breaks + maintenance activities +
shift changeover + clean down time) (Eq2)
• Customer demand = amount of units required by customer/ time period (Eq3)
• Takt Time = Available Production Time/Customer demand (Eq4)
0
5
10
15
P1 P2 P3 P4
NVA
VA
Takt
Time
Cycle
0
5
10
15
P1 P2 P3 P4
VA
Takt
Time
0
5
10
P1 P2 P3 P4
Cycle
Time
Takt
Time
27-7-2018 BY- SANCHIT JAIN
IMPLEMENTING TAKT TIME
Takt Time Calculation Based On One
Month Forecasted Loading:
• Available time (hour/month) = 705
• Forecast demand (card/month)
= 17000000
• Takt time (sec)
= 705*3600/17000000 = 0.149 sec
0.125
0.143
0.164
0.133 0.133
0.149
0.000
0.040
0.080
0.120
0.160
0.200
P1 P2 P3 P4 P5
C/T /card Actual
(sec)
Takt Time (sec)
Descriptions Formulae Used
Processes
P1 P2 P3 P4 P5
Declared Capacity/Mc/hr - 12000 8000 7200 12000 9000
Standard Time/Machine (Sec) =
Time sec
declared capacity
0.30 0.45 0.50 0.30 0.40
No. Of Machine - 3 5 5 3 4
Production efficiency %* =
Output ST
Loading time
80% 63% 61% 75% 75%
Declared Cycle Time/card(sec) =
Standard Time
no.of Machine
0.10 0.09 0.10 0.10 0.10
Actual Cycle Time/card (sec) * =
𝐃𝐞𝐜𝐥𝐚𝐫𝐞𝐝 𝐂𝐲𝐜𝐥𝐞 𝐓𝐢𝐦𝐞
𝐏𝐫𝐨𝐝𝐮𝐜𝐭𝐢𝐨𝐧 𝐞𝐟𝐟𝐢𝐜𝐢𝐞𝐧𝐜𝐲
0.125 0.143 0.164 0.133 0.133
Actual Cycle Time VS Takt Time.
27-7-2018 BY- SANCHIT JAIN
OEE ANALYSIS OF BOTTLENECK
PROCESS
1 M1 59% 95% 99.9992% 56%
2 M2 60% 97% 99.9994% 58%
3 M3 61% 97% 99.9992% 59%
4 M4 67% 97% 99.9993% 65%
5 M5 67% 97% 99.9997% 65%
Overall 63% 97% 99.9994% 61%
OEE Breakup Of Five Module Implanting Machines
1
Machine breakdown (unscheduled
maintenance time)
24535 25940 23480 19535 17650 111140
2 No Milled Cards (WIP starvation) 5895 9625 9575 2375 6035 33505
3 Batch Change 4700 5410 4090 5595 5430 25225
4 Machine Cleaning (Engg. usage time) 4735 4990 4950 5215 5150 25040
5 ATR Rejection 1510 405 660 3140 3245 8960
6 Setup change 4525 1460 1110 1765 60 8920
7 Kanban buffer 1020 230 0 2475 1905 5630
8 No Operator 0 580 720 0 0 1300
Total DT(Min.) 46980 48640 44585 40100 39475
DT(Hrs.) 783 811 743 668 658
27-7-2018 BY- SANCHIT JAIN
111140
33505
25225 25040
8960 8920
5630
1300 60
51%
66%
77%
89%
93%
97% 99% 100%
0%
20%
40%
60%
80%
100%
120%
0
20000
40000
60000
80000
100000
120000
Mahcine
breakdown
No Milled
Cards
Batch
Change
Machine
Cleaning
ATR
Rejection
m/c
conversion
Kanban
buffer
No
operator
Other
DT(M)
Cum. DT
%age
Pareto Diagram Of Down Time Data Collected
OEE ANALYSIS OF BOTTLENECK
PROCESS
27-7-2018 BY- SANCHIT JAIN
SINGLE MINUTE EXCHANGE OF
DIES (SMED)
SMED is a Lean Tool used to shorten the changeover time hence reducing total production
cost.
Year
Authors/
Organization
Theme
1950 Shigeo Shingo
Initial developments on the concept while working with Toyota
Industries.
1970
Shigeo Shingo
&Taichi Ohno
Improved setup process for a 1000 ton press at Toyota motors main plant
from 4 hours to 90 minutes and creating a systematic technique for
achieving SMED.
1980
Toyota Gosei
Plant, Japan
Setup time of cold forging machine was reduced by 69% from 100
minutes to 31 minutes using same approach.
1985 Shigeo Shingo
In his book ‘A revolution in manufacturing: The SMED system’ shared with
the world concept of SMED.
2001 McIntosh
Improving changeover performance: A strategy for becoming a lean,
responsive manufacturer
2008
Buket
Boztınaztepe
Lean Tools for Reducing Production Time and Satisfying Employees: A
Case Study.
2013 Aurelien Narses
Case study: Production and OEE improvement for an 800 tons stamping
press.
It is evident from all the examples that this approach could be applied to any factory and
on any machine.
27-7-2018 BY- SANCHIT JAIN
APPLICATION OF SMED IN CASE
ORGANISATION
SMED on Setup Change of Module Implanting Machine
Stage 1. Data Collection
1. Interviewing operator, maintenance engineer and production supervisor:
• Questions to Production supervisor:
-When and how are you communicated that a machine is required to undergo conversion?
-Who all are involved in conversion activity and what are their roles?
-What is your role in conversion process after you are being communicated?
• Questions to maintenance engineer:
-When and how are you communicated that a machine is required to undergo conversion?
-What is the standard operating procedure of existing setup change process (if any)?
• Questions to operator:
-When and how are you communicated that your machine is required to undergo
conversion?
-What is your role in conversion process?
PPC plans &
share to prod.
Mail from Prod. to
maintenance
Machine &
equipments
preparation
Converting each
part of machine
Final adjustments
& trial run
Machine under
observation till
stable production
Mass productionMachine setup change process flow (Macro)
3.Final adjustments and trial runs (36%)
3.1 New Reel loading 3.2 Raising hot weld temp. to required limit 3.3 First card Inspection
2.Converting each part of machine (41%)
2.1 Change
module
punch
tool(Die)
2.2 Allign
Pick&Place
arm with
punch tool
2.3 Hot
weld
heads
shifting
2.4 Hot
weld base
plate
shifting
2.5 Cold
weld
tool
shifting
2.6 card
detection
sensor
shifting
2.7 Tacking
(Prepress)
station
shifting
2.8 Slot
tester
shifting
2.9 Module
detection
sensor
shifting
2.10 ATR
tester
Head
shifting
1.Machine and Equipment Preparation (23%)
1.1 Bring hand Tools (
L-key set, screw driver
etc.)
1.2 Bring module punch
die of new module type
from tool room
1.3 Make available test cards,
test module reel(laminated),
visual gauge template
1.4 Making the machine ready for conversion
(open covers ,turn off heating elements,
remove previous card box, remove old Reel,
install test reel etc.)
First stage Bifurcation of Setup Change Process & Percentage Contribution
2. Using stopwatch with intermittent Videotaping:
27-7-2018 BY- SANCHIT JAIN
SMED on Setup Change of Module
Implanting Machine
Module implanting Machine-Setup Change Process
No. 1ststage Element Breakup 2nd Stage Element Breakup Activity Observed Time (sec)
1.1 Bring Test Material
Bring Test cards EXTERNAL 312
Bring test module reel EXTERNAL 210
Sub total 5% 522
1.2
Bring New Module punch Die from
tool room
Change fittings on the new die EXTERNAL 380
Sub total 4% 380
1.3 Prepare Machine for conversion
Turn off heating Elements and wait till it comes to room temperature, Open machine cover INTERNAL 680
remove previous batch card boxes INTERNAL 63
Remove & wind old reel INTERNAL 160
Install test reel INTERNAL 235
Sub total 12% 1138
2.1 Change module punch tool(Die)
Change fittings on the new die EXTERNAL 410
Remove previous die from the machine INTERNAL 220
placing and connecting new die to the machine INTERNAL 122
Insert test reel in die and trial run to test the punch position INTERNAL 170
Sub total 10% 922
2.5
Alignment of Pick & Place arm
with punch tool
Open front bolt by L-key INTERNAL 10
Back front bolt by L-key INTERNAL 21
lifting>shifting>placing>aligning INTERNAL 100
Adjustments INTERNAL 30
Close front and back bolt simultaneously INTERNAL 13
Sub total 2% 174
2.3 Hot weld head shifting
Place Test card under 1st weld head for reference INTERNAL 25
Move 1st weld head to new position with X & Y lead screws >visually check using test
card>adjust to finalize
INTERNAL 150
Place Test card under 2nd weld head for reference INTERNAL 24
Move 2nd weld head to new position with X & Y lead screws >visually check using test
card>adjust to finalize
INTERNAL 166
Place Test card under 3rd weld head for reference INTERNAL 26
Move 3rd weld head to new position with X & Y lead screws >visually check using test
card>adjust to finalize
INTERNAL 210
Place Test card under 4th weld head for reference INTERNAL 25
Move 4th weld head to new position with X & Y lead screws >visually check using test
card>adjust to finalize
INTERNAL 156
Sub total 11% 782
2.4 Hot weld base plate (BP) shifting
Open weld head INTERNAL 18
look for required L-key EXTERNAL 18
1st base plate (loosen the bolt>shift BP.>tighten bolts) INTERNAL 107
2nd base plate (loosen the bolt>shift BP.>tighten bolt) INTERNAL 87
Again1st base plate (tighten bolts) WASTE 25
3rd base plate (loosen the bolt>shift BP.>tighten bolt) INTERNAL 81
4th base plate (loosen the bolt>shift BP.>tighten bolt) INTERNAL 94
Sub total 4% 430
2.5 Cold weld tool shifting Loosen bolts>shift/adjust>tighten bolts INTERNAL 80
Sub total 1% 80
2.6 Card detection sensor shifting Loosen bolts>shift/adjust>tighten bolts INTERNAL 91
Sub total 1% 91
2.7 Tacking(Prepress) station shifting
Open front cover INTERNAL 11
loosen bolts by L-Key>shifting INTERNAL 50
Centring INTERNAL 43
Adjusting/Aligning Press Tool Tip with embedded module of test card INTERNAL 22
half tighten bolt>adjustment/aligning>full tighten Bolt INTERNAL 142
1st check (centring+tacking>observe>untack>visual check) INTERNAL 29
2nd check (centring+tacking>observe>untack>visual check) INTERNAL 39
Slight shifting(half tighten bolt>shifting>full tighten Bolt) INTERNAL 188
Sub total 5% 524
2.8 Slot tester shifting
open front cover INTERNAL 50
open front channel INTERNAL 107
Front Slot tester(loosen the bolt>shift gauge.>tighten bolt) INTERNAL 122
Back Slot tester(remove the bolt>shift gauge>tighten bolt) INTERNAL 150
close front channel and cover INTERNAL 225
Sub total 7% 654
2.9 Module detection sensor shifting Loosen bolts>shift/adjust>tighten bolts INTERNAL 91
Sub total 1% 91
2.10 ATR tester Head shifting
loosen the bolts>removing bolts INTERNAL 60
place test card for reference INTERNAL 12
alignment/shifting INTERNAL 40
tighten the bolts while aligning tester pins with card module INTERNAL 92
Sub total 2% 204
3.1 New Reel loading Replacing Test Module reel with New Module Reel INTERNAL 450
Sub total 5% 450
3.2
Raising hot weld temp. to required
limit
INTERNAL 718
Sub total 7% 718
3.3
First card Inspection, Trial run and
final adjustments
1st trial run on test card INTERNAL 140
CTQ parameters check. INTERNAL 340
Adjustments of critical parameters INTERNAL 185
2nd trial run on test card INTERNAL 137
CTQ parameters check. INTERNAL 356
1st test run on live card INTERNAL 164
CTQ parameters check. INTERNAL 320
Intermittent minor adjustments till mass production at stable rate INTERNAL 545
Sub total 23% 2187
Current Total Time (sec) 100% 9578
Current Total Time (min) 160
Stage 2. Separating Internal and External Elements
By the end of this stage of
improvement process, external
elements were separated from
internal. The percentage share of the
external elements was 15% of the
total time.
27-7-2018 BY- SANCHIT JAIN
Stage 3. Streamlining Operations: Improvement of operations
A. Problem- Hot Weld Heads Shifting- (Step number 2.3 of Table 10)
SMED on Setup Change of Module
Implanting Machine
The ‘Hot weld head’ is the most critical element of Module Implanting machine. Its function is the
permanent assembly (or Embedding) of module on the card body (CB) by the progressive heating
and fusion of tape layer (at the bottom side of module) with top surface of plastic (ABS material)
CB. The heating is done in four progressive steps with four weld heads maintained around 220°C
temperature. The position of heating element must be right above the module at all the time and
accuracy up to microns is required for effective heat transfer and plastic fusion. The conversion of
all the four weld head took a total of 50 minutes in the study done.
X-Axis Lead
Screws
Y-Axis Lead
Screws
Mounting Plate
Heating
Elements
Labelled image of
Hot Weld Heads
27-7-2018 BY- SANCHIT JAIN
Solution- A brainstorming session held with the team resulted in a unique solution of
this problem. The solution was to modify design of plate where all weld heads are
mounted such that conversion could be simple, accurate, require less skill and need to
turn off heating elements was no more required. A 3D CAD design was prepared with
the modification suggested by the team. The main design modification was that of a
mounting change of weld heads. A new slider plate was introduces in the design
between weld heads and mounting plate. This will be enabling all the weld heads to
move simultaneously and accurately at the required position of new product. Figure
18 shows the 3D design created by author to the required specifications after several
reviews and modification with the team.
Sliding Guides
Slider Plate
Mounting
plate
SMED on Setup Change of Module
Implanting Machine
CAD Design of
modified
Mounting
27-7-2018 BY- SANCHIT JAIN
3D CAD Design of Modified Mounting using Solid Works
SMED on Setup Change of Module
Implanting Machine
27-7-2018 BY- SANCHIT JAIN
The modification required large capital expenditure which must be justified with the
amount of time reduction this modification would provide.
Some calculations shown below will clear that the investment required is justified.
• Estimated cost of expenses on modification = ₹15000 (1)
• Estimated time saved/ Conversion = 50 minutes = 3000 sec (2)
• Total conversion per month (estimated from previous data) = 3.5 times (3)
• Time saved per month = (2)*(3) = 10500 sec (4)
• Standard production throughput = 3600 cards/ hour = 1 card/ sec (5)
• Price per card = ₹ 2.4 (6)
• Total cost saved = (4)*(5)*(6) = ₹ 25200/ Month (7)
• Return To Investment (ROI) = (1)/(7) = 0.595 Month
The Calculation shows that it will take about half a month, i.e. not more than two
conversions, to start returning the profits of the design modification. This justifies the
expenditure of modification proposed.
Project Proposal
SMED on Setup Change of Module
Implanting Machine
27-7-2018 BY- SANCHIT JAIN
Improvement- Final modification of hot weld design mounting was successfully
made. Figure 19 shows the actual image of modified weld mounting with slider plate.
This innovative improvement reduces about 32% of total internal time.
Slider Plate
Linear guides
Mounting
Plate
Actual Modified Weld
Mounting
SMED on Setup Change of Module
Implanting Machine
27-7-2018 BY- SANCHIT JAIN
B. Problem- Slot Tester shifting - (Step number 2.8 of Table 10)
Slot tester is nothing but a depth gauge which measures depth of cavity milled on cards
during milling process. The function of slot tester is to ensure that the cavity milled is of
required depth, so that module is implanted with no defect. The problem with shifting
slot tester was a tedious job and can be understand with the image shown below. Slot
tester needs to be shifted towards right for new product (Red arrow). Before shifting the
slot tester, three more parts need to unbolt and removed i.e. first the front cover (Black),
then two T- shaped support columns (Behind cover) and then channel. These are all
necessary but wasteful activities. Total extra time in removing and then reassembling
after shifting slot tester is 4% of total changeover time (6.3 minutes).
Channel
Cover
Slot Tester
Back view of Slot
Tester Mounting
SMED on Setup Change of Module
Implanting Machine
27-7-2018 BY- SANCHIT JAIN
Solution- Taking feedback from the operators, a rather simple solution was applied to
the seemingly complex problem. The solution to eliminate this waste is to cut a
rectangular shaped slot on the channel. Now, no more dismantling of extra parts is
required. Final image after the improvement looks as shown below. It shows a cut
portion of channel. This enable direct access to slot tester mounting bolts which mere
needs to be shifted from one screw hole to another for shifting.
Cut Section
Mounting bolts
Slot tester mounting After
Improvement
Learning- The important aspects of such improvement are as follows:-
1. The active participation of operators in problem solving.
2. An effective and No-cost solution to a complex problem.
SMED on Setup Change of Module
Implanting Machine
27-7-2018 BY- SANCHIT JAIN
C. Problem- Screw type clamps used in weld head assembly are time consuming while
opening and closing heads. The frequent opening and closing of weld head, owing to
major and minor adjustments, require a quick and accurate clamping solution. Refer
figure 1 for previously used screw type clamp.
Screw Type Clamp
1. Screw Type Clamp on
weld assembly
Solution- New Toggle type clamp was used to simplify the operation and reduces time by
allowing quick clamping of the assembly. Figure 2 shows new type of clamp.
Toggle Clamp
2. New Toggle Clamp After
Improvement
SMED on Setup Change of Module
Implanting Machine
Improvement- A rough estimation of the impact on internal time due to this
improvement is about 5-10 minutes reduction.
27-7-2018 BY- SANCHIT JAIN
D. Problem- Ineffective manpower utilization-
The entire conversion process was carried out by two men: Maintenance engineer and
operator. Maintenance engineer is an expert in machine conversion and works actively to
perform all the elements, while operator plays a supportive role and his involvement is
passive most of the time owing to the complexity of operations as well as lower skill level.
Another factor contributing to low manpower utility is a lot of wasted motion moving from
front of machine to the back, and vice versa because most of the operations were performed
by one worker (the engineer). To understand the utility of both, following graph was made
from video recording. Figure 24 divides the total time of conversion in useful and idle time
for both men. This gives us their respective percentage utility: engineer =78% and operator
=31%.
Manpower utility graph
SMED on Setup Change of Module
Implanting Machine
27-7-2018 BY- SANCHIT JAIN
Solution- Since, major complex operations are now made simple and required lower
skill, the operator can easily perform such operations and have more active
participation in conversion process. With few more training sessions about the
modified processes, the operator’s utility would increase significantly. Training and
skill enhancement is a good but an old strategy and is discarded by Shingo. Instead, a
better solution of adopting parallel operations was suggested in his book. Since,
operator can now perform most of the task on his own. The concept of parallel
tasking will play an effective role in time reduction. Instead of performing each task in
series one after the other, a better strategy is to work parallel and perform two
different tasks simultaneously. Few important points were considered while
constructing the optimum flow.
1. Equal time distribution among both men.
2. Proper sequencing of operations based on essential precedence order.
For example: ‘Tacking tool (Prepress) shifting’ must follow after ‘Alignment of Pick &
Place arm’ and ‘Alignment of Pick & Place arm with punch tool’ must follow after
‘Change module punch die’ operation
SMED on Setup Change of Module
Implanting Machine
27-7-2018 BY- SANCHIT JAIN
Parallel Operations Flow
Card detection sensor shifting
Machine running stable
Prepare
machine for
conversion
Change
module punch
die
Hot weld head shifting
Cold weld tool shifting
Hot weld base plate shifting
Tacking tool (Prepress) shifting
Alignment of Pick &
Place arm with punch
tool
First card Inspection,
Trial run and final
adjustments
Bring new
module punch die
Start
Bring Test
Cards and
module Reel
Change Fitting on new die
Slot tester shifting
Module detection
sensor shifting
Stop machine
MAINTENANCE
ENGINEER
MACHINE
OPERATOR
E
X
T
E
R
N
A
L
I
N
T
E
R
N
A
L
ATR Tester shifting
The entire process is equally
divided among machine
operator and maintenance
engineer such that, they
perform separate operations
simultaneously which
consumes equal amount of
time.
Improvement- Using two
men working on front and back
jobs concurrently, the
implementation of parallel
operations had improved utility
of both operator and engineer
up to 95% each. Thus, the
reduction of 25% more internal
time was achieved.
SMED on Setup Change of Module
Implanting Machine
27-7-2018 BY- SANCHIT JAIN
SMED on Setup Change of Module
Implanting Machine
Result Of SMED on Setup Change Process
After training the operators and engineers of
new setup change process, new video study on
setup change was conducted on same machine.
The total time taken to complete the setup
change process was close to 20 minutes. So, with
the application of SMED concept a reduction of
87.5% in setup change time has achieved.
160
20
0
50
100
150
200
Before After
Setup Time (minutes)
Setup Time
(minutes)
87.5%
Impact on OEE:
Following calculations were made to show impact on OEE :-
Total base time per day per machine = 1440 min;
Total time saved per machine per day = (160-20)*0.2 = 28 min
Increase in Availability = 28/1440 = 1.94 %
Increase in OEE = Increased Availability* Old Quality* Old performance rate
Therefore, Increase in OEE due to improvement using SMED = 1.9 %.
27-7-2018 BY- SANCHIT JAIN
SMED On Batch Change Activity
Stage 1. Data Collection
• Data collection was
done using videotaping
and recording the entire
batch change process as
it is.
S.N. Element Description Activity
Observed
Time (sec)
1 Stop the machine and clear it of last batch material INTERNAL 42
2 Open the door and cut the module reel with cutter INTERNAL 11
3 Cut the module reels & make a roll of reels & keep them on trolley INTERNAL 60
4 Count Bad modules and keep them in the box. EXTERNAL 79
5 Entry in check sheet for closing batch EXTERNAL 42
6 Pick airgun and clean the m/c INTERNAL 36
7 Bring the IPA bottle to m/c for cleaning EXTERNAL 14
8 Clean die and suction pipes of module Transfer INTERNAL 20
9 Again go back to keep the IPA bottle EXTERNAL 16
10 Using command panel to clean the die INTERNAL 56
11 Filling log book, check sheet, downtime sheet and etc. EXTERNAL 150
12 Waiting for the correct module reel. EXTERNAL 140
13 Pick and installed the module reel on machine output side INTERNAL 190
14 Pick the scrap material and go to throw them in dustbin EXTERNAL 27
15 Pick the tape from OQC station EXTERNAL 22
16 Paste tape on bad module cup and correct the module reel INTERNAL 78
17 Pick and installed the module reel on machine input side INTERNAL 147
18 Paste tape to correct the module reel INTERNAL 76
19 Looking for the box of CB to run on machine EXTERNAL 14
20 Using air gun on fresh cards to segregate the burr on card INTERNAL 18
21 Pick the cards and feed to input magazine in three turns INTERNAL 16
22 Now close the machine and run INTERNAL 18
Total Time (Second) 1272
Total Time (Minutes) 21.2
• The elemental breakup of
entire operation was
done with the help of an
engineer from
maintenance department
such that a notable
difference can be easily
made between each
element
27-7-2018 BY- SANCHIT JAIN
S.N. Element Description Activity
Observe
d Time
(sec)
Internal
(Sec)
Exter
nal
(Sec)
1 Stop the machine and clear it of last batch material INTERNAL 42 42 -
2 Open the door and cut the module reel with cutter INTERNAL 11 11 -
3
Cut the module reels & make a roll of reels & keep them on
trolley
INTERNAL 60 60 -
4 Count Bad modules and keep them in the box. EXTERNAL 79 - 79
5 Entry in check sheet for closing batch EXTERNAL 42 - 42
6 Pick airgun and clean the m/c INTERNAL 36 36 -
7 Bring the IPA bottle to m/c for cleaning EXTERNAL 14 - 14
8 Clean die and suction pipes of module Transfer INTERNAL 20 20 -
9 Again go back to keep the IPA bottle EXTERNAL 16 - 16
10 Using command panel to clean the die INTERNAL 56 56 -
11 Filling log book, check sheet, downtime sheet and etc. EXTERNAL 150 - 150
12 Waiting for the correct module reel. EXTERNAL 140 - 140
13 Pick and installed the module reel on machine output side INTERNAL 190 190 -
14 Pick the scrap material and go to throw them in dustbin EXTERNAL 27 - 27
15 Pick the tape from OQC station EXTERNAL 22 - 22
16 Paste tape on bad module cup and correct the module reel INTERNAL 78 78 -
17 Pick and installed the module reel on machine input side INTERNAL 147 153 -
18 Paste tape to correct the module reel INTERNAL 76 76 -
19 Looking for the box of CB to run on machine EXTERNAL 14 - 14
20 Using air gun on fresh cards to segregate the burr on card INTERNAL 18 18 -
21 Pick the cards and feed to input magazine in three turns INTERNAL 16 16 -
22 Now close the machine and run INTERNAL 18 18 -
Total Time (Second) 1272 768 504
Total Time (Minutes) 21.2 12.8 8.4
Stage 2. Separating
Internal from External
Elements
The data was then analysed
to look for elements that
can be categorised as
‘internal’ and ‘external’.
SMED On Batch Change Activity
It was observed that 8.4
minutes out of 21.2
minutes was spent on doing
activities that could have
been done when the
machine was running i.e.
41%of total time.
Fractional share of Internal and
External Activities
27-7-2018 BY- SANCHIT JAIN
To streamline operation,
all the elements were
analysed to know their
functional requirement
and whether a particular
element is actually
required to be performed
while doing batch change
S.N. Element Description Activity Function
Observe
d Time
(sec)
Internal +
Functional
1 Stop the machine and clear it of last batch material INTERNAL
Machine
Preparation
42 42
2 Open the door and cut the module reel with cutter INTERNAL Reel change 11 11
3
Cut the module reels & make a roll of reels & keep
them on trolley
INTERNAL Reel change 60 60
4
Count Bad modules and keep them in the rejection
box.
EXTERNAL Batch closing 79 -
5 Entry in check sheet for closing batch EXTERNAL Batch closing 42 -
6 Pick air gun and clean the m/c INTERNAL Machine cleaning 36 -
7 Bring the IPA bottle to m/c for cleaning EXTERNAL Machine cleaning 14 -
8 Clean die and suction pipes of module Transfer INTERNAL Machine cleaning 20 -
9 Again go back to keep the IPA bottle EXTERNAL Machine cleaning 16 -
10 Using command panel to clean the die INTERNAL Machine cleaning 56 -
11 Filling log book, check sheet, downtime sheet and etc. EXTERNAL Batch closing 150 -
12 Waiting for the correct module reel. EXTERNAL Wait for material 140 -
13 Pick and install the 1st module reel on machine INTERNAL Reel change 190 190
14
Pick the scrap material and go to throw them in
dustbin
EXTERNAL Machine cleaning 27 -
15 Pick the tape from OQC station EXTERNAL Waste 22 -
16 Paste tape on bad module and correct the module reel INTERNAL Reel Change 78 78
17 Pick and install the 2nd module reel on machine INTERNAL Reel Change 147 147
18 Paste tape to correct the module reel INTERNAL Reel Change 76 76
19 Looking for the box of CB to run on machine EXTERNAL CB change 14 -
20
Using air gun on fresh cards to segregate the burr on
card
INTERNAL CB change 18 18
21
Pick the cards and feed to input magazine in three
turns
INTERNAL CB change 16 16
22 Now close the machine and run first good part INTERNAL Final Adjustments 18 18
Total Time (Second) 1272 656
Total Time (Minutes) 21.2 10.9
Stage 3. Streamlining
operations and Operator
Training
These contribute 330
seconds i.e. 5.5 minutes
of total observed time
and 112 seconds of total
internal time. Hence, the
final effective time
remains 656 seconds or
10.9 minutes.
SMED On Batch Change Activity
27-7-2018 BY- SANCHIT JAIN
Brainstorming with team (production, maintenance and quality) was done and priority
of the tasks was decided such that machine cleaning was secondary to batch change
and could be avoided during batch change.
This yield following decisions:
1. To make available all the essentials such as Tape, cutter etc. on the machine all the
time to avoid motion and searching time loss.
2. Machine Cleaning is a separate regular activity of DPM (Daily Preventive
Maintenance) and must be done during that time only and must not be included
during batch change.
3. A standard work instruction needs to be prepared with new sequence of steps. This
is now used for training the operators about new process
SMED On Batch Change Activity
27-7-2018 BY- SANCHIT JAIN
After training the operators of new batch change
process, new video study was conducted on three
batch change done on similar machine by three
different operators. The total time taken was:
10.3 minutes, 10.5 minutes and 9.8 minutes
respectively i.e. an average 10.2 minutes. So, with
the use of SMED concept a reduction of 52% in
batch change time has achieved
Result Of SMED on Batch Change Process
Impact on KPI:
Following calculations were made to show impact on OEE :-
Total time per day per machine = 1440 min;
Total time saved per machine per day = (20-10.2)*3.5 = 34.3 min
Increase in Availability = 34.3/1440 = 2.38%
Increase in OEE = Increased Availability* Old Quality* Old performance rate
Therefore, Increase in OEE due to improvement using SMED = 2.26 %.
SMED On Batch Change Activity
27-7-2018 BY- SANCHIT JAIN
Aim is to reduce the time of activities done during Machine Cleaning.
CONTINUOUS IMPROVEMENT:
Kaizen on Machine Cleaning
1. Elemental breakup of the process such that proper distinguish can be made
between two activities.
2. Time Study by camera recording of the process. (stop watch can also be used)
3. Element wise time assigning from the recording (observed time).
4. Deciding which elements are useful and which one are wasteful i.e. distributing
data into three categories- Value added, Non value added and Waste.
5. Rating each activity based on level of commitment of the operator. This means
whether the operator is performing 100% or less to do a particular activity.
6. Multiply rating factor with observed time to get Normal Time.
7. Assign allowance to each task and multiply with normal time to get Standard
Operating time.
Step involved for data measurement and analysis:
27-7-2018 BY- SANCHIT JAIN
Firstly open the door and cut the module reel with cutter 1 NVA 11.0 100% 11 11 11
Cut the module reel by hand & make a roll of reel & keep this on trolley (
From both side)
1 NVA 60.0 100% 60 60 60
Count Bad modules and keep them into a box. 1 Waste 79.0 100% 79 79 79
Entry in checksheet 1 NVA 42.0 100% 42 42 42
Pick airgun and clean the m/c 1 VA 36.0 100% 36 36 36
Pic the module & parallaly waiting for the new batch 1 Waste 72.0 100% 72 72 72
Pick the IPA and go back to m/c to clean it 1 Waste 14.0 100% 14 14 14
Clean die and suction pipes of IC T/F 1 VA 20.0 100% 20 20 20
Again go back to keep the ipa bottle on back trolley 1 Waste 16.0 100% 16 16 16
Now by using command on pannel clean the die 1 VA 56.0 100% 56 56 56
Again using air gun to clean the machine 1 NVA 74.0 100% 74 74 74
Now going to lineleader to confirm about the next batch module reel 1 Waste 20.0 100% 20 20 20
Now pick the module reel and go to lamination machine station to change
it
1 Waste 67.0 100% 67 67 67
Pick the cutter form input trolley and placed on back trolley 1 Waste 8.0 100% 8 8 8
Now going to the output of machine aand pick and fill the log
book,checksheet,production sheet and etc.
1 NVA 150.0 100% 150 150 150
Now still waiting for the correct module reel. 1 Waste 140.0 100% 140 140 140
Now pick and installed the actual module reel on output side 1 VA 190.0 100% 190 190 190
Pick the scrap material and go to fall them in dustbin 1 Waste 27.0 100% 27 27 27
Pick the tape from oqc station 1 Waste 22.0 100% 22 22 22
paste on bad module cup and correct the module reel 1 NVA 78.0 100% 78 78 78
Now pick the input module reel and go to installed 1 VA 153.0 100% 153 153 153
Now again pick the tape from oqc station 1 NVA 18.0 100% 18 18 18
and paste on moduel reel joint at output side and correct the module reel 1 Waste 76.0 100% 76 76 76
Now going to the trolley at input side and find the box to run on machine 1 Waste 14.0 100% 14 14 14
Now after finding the running box going to machine 1 Waste 20.0 100% 20 20 20
Using air gun on fresh cards to segregate the burr on card 1 VA 18.0 100% 18 18 18
Pick the cards and feed into the magzine in three turns 1 VA 16.0 100% 16 16 16
Now correct the machine and run 1 VA 18.0 100% 18 18 18
Sub Total 1515.0 1 1515 1515 507 433 575 25.3
8.45 7.22 9.58
S. N.
Process
Description
Element Description Task
1
Batch
Qty
1
Batch
Change
Observed
Time (sec)
VA NVA Waste Remarks
No. of
Operators
Rating
Normal
Time (sec)
Std. Time
(sec)
Machine
Cleaning
CONTINUOUS IMPROVEMENT:
Kaizen on Machine Cleaning
27-7-2018 BY- SANCHIT JAIN
The report shows that only 33% of total time was utilised to perform useful activities
and 38% of time was invested in completely wasteful activity which needs immediate
elimination.
Module Implanting Machine Cleaning process
S.No. Problems Corrective Actions
Time
(s)
1
Wrong module reel feeding by the lamination
machine operator
Paste a machine name sticker on every
module reel
227
2 Count Bad Module Manually
No need to count the bad module just keep
them in pouch.(Because this is NVA activity
and we have no need to do this)
79
3 Waiting for new batch After doing preplanning for new batch 72
4
Pick and place the usable tools (Cutter,Tape
etc.) from here and there.
Make a cardboard tool box for keeping the all
using tools
48
5 Box finding problem Box no. identification by marker 34
6
Motion loss for finding the IPA bottle ( Come
and go timing)
Fix one IPA Bottle on every machine 30
7
To drop the scap material due to lack of
dustbins operator need to extra motion
Need to increase more numbers of dustbins
to avoid this delay
27
Total Time Saved per batch (Sec) 517
Total Time Saved per batch (Minutes) 8.62
Results of Kaizen:
1. Reduction in
cleaning time by
almost 50%.
2. Improvement
in OEE by 3%
CONTINUOUS IMPROVEMENT:
Kaizen on Machine Cleaning
27-7-2018 BY- SANCHIT JAIN
CONCLUSION AND FUTURE SCOPE
Project Results
OEE improvement from all the applications of different lean tools:
1. Machine cleaning activity was reduced to half the time it used to take to complete
the activity. This improved process OEE of Module implanting machine by 3%.
2. SMED on Batch change reduced the total lost time by 52% i.e. now it takes 10
minutes to change the batch which was 21 minutes before the project. The impact
on process OEE of Module implanting machine is an increase of 2.2%.
3. SMED on Setup change process of reduced the lost time by 87.5% i.e. now it takes 20
minutes to completely change machine setup which was 160 minutes before the
start of project. The impact on process OEE of module implanting machine is an
increase of 1.9%.
27-7-2018 BY- SANCHIT JAIN
CONCLUSION
Summing up of all the improvement activities shows a total of 7.1% OEE
improvement of Module implanting process in manufacturing SIM card.
Earlier, Module Implanting process was identified as system bottleneck with the
application of Takt time. Since, a bottleneck process the weakest part of system, any
improvement made will be reflecting at system level.
Therefore, it can be said that the OEE of SIM card manufacturing company was
improved by 7.1%. The Final OEE of system is 68.1%.
1. The application of Lean tools in the company in order to improve its performance
was a success. Hence, the answer to the first research question i.e. ‘R1. Can Lean
Tools be used to improve system performance of a SIM Card manufacturing
company?’ is obvious.
2. Also the second research question i.e. ‘R2. Can Overall Equipment Effectiveness be
used as a lean measure to improve equipment effectiveness?’ is made clear.
CONCLUSION AND FUTURE SCOPE
27-7-2018 BY- SANCHIT JAIN
Academic Achievements
Publication/Journal Paper Title Indexed
Publication
Status
IJTIMES
Applying SMED to reduce Changeover
Time and Improve System
Performance
UGC
Published,
Volume 04 Issue
07, July-2018
Inderscience
Publication/ IJPQM
Case Study: Application of SMED in
SIM Card Manufacturing Company
SCOPUS, UGC
Screening for
Acceptance
27-7-2018 BY- SANCHIT JAIN
Certification Of Publication
27-7-2018 BY- SANCHIT JAIN
Plagiarism Report

More Related Content

What's hot

Hot isostatic pressing
Hot isostatic pressingHot isostatic pressing
Hot isostatic pressingLahiru Dilshan
 
Ultrasonic machining
Ultrasonic machiningUltrasonic machining
Ultrasonic machiningmohit99033
 
Advanced Manufacturing Technology
Advanced Manufacturing TechnologyAdvanced Manufacturing Technology
Advanced Manufacturing TechnologyM. Soundarrajan
 
Hydrogen Embrittlement : Causes, Effects, Prevention.
Hydrogen Embrittlement : Causes, Effects, Prevention.Hydrogen Embrittlement : Causes, Effects, Prevention.
Hydrogen Embrittlement : Causes, Effects, Prevention.Sidheshwar Kumar
 
Squeeze casting process
Squeeze casting processSqueeze casting process
Squeeze casting processDipanshu Kawle
 
Injection moulding ppt
Injection moulding pptInjection moulding ppt
Injection moulding pptdobhal001
 
Nickel Based Superalloys:Processing and Applications.
Nickel Based Superalloys:Processing and Applications.Nickel Based Superalloys:Processing and Applications.
Nickel Based Superalloys:Processing and Applications.Sidheshwar Kumar
 
12 fatigue of metals
12 fatigue of metals12 fatigue of metals
12 fatigue of metalsRajeev Ranjan
 
Composites manufacturing
Composites manufacturingComposites manufacturing
Composites manufacturingtej kumar
 
MF5103 Advanced casting and_welding previous year question paper
 MF5103 Advanced casting and_welding previous year question paper MF5103 Advanced casting and_welding previous year question paper
MF5103 Advanced casting and_welding previous year question paperDineshS158
 
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )TAMILMECHKIT
 
Metal Matrix Composite (MMC)
Metal Matrix Composite (MMC)Metal Matrix Composite (MMC)
Metal Matrix Composite (MMC)Sazzad Hossain
 
Mechanical Testing : Testing Of Materials
Mechanical Testing : Testing Of MaterialsMechanical Testing : Testing Of Materials
Mechanical Testing : Testing Of MaterialsDr.S.Thirumalvalavan
 

What's hot (20)

Hot isostatic pressing
Hot isostatic pressingHot isostatic pressing
Hot isostatic pressing
 
Metal Forming & Shaping: Lecture Introduction
Metal Forming & Shaping: Lecture IntroductionMetal Forming & Shaping: Lecture Introduction
Metal Forming & Shaping: Lecture Introduction
 
Ultrasonic machining
Ultrasonic machiningUltrasonic machining
Ultrasonic machining
 
Advanced Manufacturing Technology
Advanced Manufacturing TechnologyAdvanced Manufacturing Technology
Advanced Manufacturing Technology
 
Hydrogen Embrittlement : Causes, Effects, Prevention.
Hydrogen Embrittlement : Causes, Effects, Prevention.Hydrogen Embrittlement : Causes, Effects, Prevention.
Hydrogen Embrittlement : Causes, Effects, Prevention.
 
Cutting fluids
Cutting fluidsCutting fluids
Cutting fluids
 
Squeeze casting process
Squeeze casting processSqueeze casting process
Squeeze casting process
 
Plasma Arc Machining
Plasma Arc MachiningPlasma Arc Machining
Plasma Arc Machining
 
Injection moulding ppt
Injection moulding pptInjection moulding ppt
Injection moulding ppt
 
Nickel Based Superalloys:Processing and Applications.
Nickel Based Superalloys:Processing and Applications.Nickel Based Superalloys:Processing and Applications.
Nickel Based Superalloys:Processing and Applications.
 
12 fatigue of metals
12 fatigue of metals12 fatigue of metals
12 fatigue of metals
 
Composites manufacturing
Composites manufacturingComposites manufacturing
Composites manufacturing
 
Powder metallurgy
Powder metallurgyPowder metallurgy
Powder metallurgy
 
MF5103 Advanced casting and_welding previous year question paper
 MF5103 Advanced casting and_welding previous year question paper MF5103 Advanced casting and_welding previous year question paper
MF5103 Advanced casting and_welding previous year question paper
 
Powder metallurgy
Powder metallurgyPowder metallurgy
Powder metallurgy
 
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
 
Metal Matrix Composite (MMC)
Metal Matrix Composite (MMC)Metal Matrix Composite (MMC)
Metal Matrix Composite (MMC)
 
Mechanical Testing : Testing Of Materials
Mechanical Testing : Testing Of MaterialsMechanical Testing : Testing Of Materials
Mechanical Testing : Testing Of Materials
 
Super plastic forming and explosive forming
Super plastic forming and explosive formingSuper plastic forming and explosive forming
Super plastic forming and explosive forming
 
Lean manufacturing
Lean manufacturingLean manufacturing
Lean manufacturing
 

Similar to M.tech (Production and Industrial Engineering) Thesis Presentation

IRJET- Study and Analysis of Time Factor in the Utilization Process
IRJET- Study and Analysis of Time Factor in the Utilization ProcessIRJET- Study and Analysis of Time Factor in the Utilization Process
IRJET- Study and Analysis of Time Factor in the Utilization ProcessIRJET Journal
 
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET-  	  Efficiency Enhancement by Reducing Production and Machining TimeIRJET-  	  Efficiency Enhancement by Reducing Production and Machining Time
IRJET- Efficiency Enhancement by Reducing Production and Machining TimeIRJET Journal
 
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET-  	  Productivity Improvement by Time Study Analysis Moderate Scale Ind...IRJET-  	  Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...IRJET Journal
 
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining CellIRJET Journal
 
IRJET- Productivity Improvement by Implementing Lean Manufacturing Tools ...
IRJET-  	  Productivity Improvement by Implementing Lean Manufacturing Tools ...IRJET-  	  Productivity Improvement by Implementing Lean Manufacturing Tools ...
IRJET- Productivity Improvement by Implementing Lean Manufacturing Tools ...IRJET Journal
 
Software Solution for Production Planning and Scheduling
Software Solution for Production Planning and SchedulingSoftware Solution for Production Planning and Scheduling
Software Solution for Production Planning and SchedulingIRJET Journal
 
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET Journal
 
Computer Govern Maintenance System for a Process Industry
Computer Govern Maintenance System for a Process IndustryComputer Govern Maintenance System for a Process Industry
Computer Govern Maintenance System for a Process IndustrySushil kumar Choudhary
 
Computer Govern Maintenance System for a Process Industry
Computer Govern Maintenance System for a Process IndustryComputer Govern Maintenance System for a Process Industry
Computer Govern Maintenance System for a Process Industrysushil Choudhary
 
IRJET- A Case Study Approach of Quality Tools in Manufacturing Industry
IRJET- A Case Study Approach of Quality Tools in Manufacturing IndustryIRJET- A Case Study Approach of Quality Tools in Manufacturing Industry
IRJET- A Case Study Approach of Quality Tools in Manufacturing IndustryIRJET Journal
 
IRJET - Invistigation and Implement of Six Sigma and Reduce Labour Cost a...
IRJET -  	  Invistigation and Implement of Six Sigma and Reduce Labour Cost a...IRJET -  	  Invistigation and Implement of Six Sigma and Reduce Labour Cost a...
IRJET - Invistigation and Implement of Six Sigma and Reduce Labour Cost a...IRJET Journal
 
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET Journal
 
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET Journal
 
Just in Time System: A Study and Review
Just in Time System: A Study and ReviewJust in Time System: A Study and Review
Just in Time System: A Study and Reviewvivatechijri
 
Failure of tube reduced in split air conditioner
Failure of tube reduced in split air conditionerFailure of tube reduced in split air conditioner
Failure of tube reduced in split air conditionerprjpublications
 
Challenges in implementing Total Productive Maintenance in Indian Manufacturi...
Challenges in implementing Total Productive Maintenance in Indian Manufacturi...Challenges in implementing Total Productive Maintenance in Indian Manufacturi...
Challenges in implementing Total Productive Maintenance in Indian Manufacturi...IRJET Journal
 
VSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTVSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTFASI93
 
Sheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
Sheet Metal Assembly Process Optimization Using Lean Manufacturing ToolSheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
Sheet Metal Assembly Process Optimization Using Lean Manufacturing ToolIRJET Journal
 

Similar to M.tech (Production and Industrial Engineering) Thesis Presentation (20)

IRJET- Study and Analysis of Time Factor in the Utilization Process
IRJET- Study and Analysis of Time Factor in the Utilization ProcessIRJET- Study and Analysis of Time Factor in the Utilization Process
IRJET- Study and Analysis of Time Factor in the Utilization Process
 
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET-  	  Efficiency Enhancement by Reducing Production and Machining TimeIRJET-  	  Efficiency Enhancement by Reducing Production and Machining Time
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
 
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET-  	  Productivity Improvement by Time Study Analysis Moderate Scale Ind...IRJET-  	  Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...
 
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining Cell
 
IRJET- Productivity Improvement by Implementing Lean Manufacturing Tools ...
IRJET-  	  Productivity Improvement by Implementing Lean Manufacturing Tools ...IRJET-  	  Productivity Improvement by Implementing Lean Manufacturing Tools ...
IRJET- Productivity Improvement by Implementing Lean Manufacturing Tools ...
 
Iss 9
Iss 9Iss 9
Iss 9
 
Software Solution for Production Planning and Scheduling
Software Solution for Production Planning and SchedulingSoftware Solution for Production Planning and Scheduling
Software Solution for Production Planning and Scheduling
 
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
 
Computer Govern Maintenance System for a Process Industry
Computer Govern Maintenance System for a Process IndustryComputer Govern Maintenance System for a Process Industry
Computer Govern Maintenance System for a Process Industry
 
Computer Govern Maintenance System for a Process Industry
Computer Govern Maintenance System for a Process IndustryComputer Govern Maintenance System for a Process Industry
Computer Govern Maintenance System for a Process Industry
 
IRJET- A Case Study Approach of Quality Tools in Manufacturing Industry
IRJET- A Case Study Approach of Quality Tools in Manufacturing IndustryIRJET- A Case Study Approach of Quality Tools in Manufacturing Industry
IRJET- A Case Study Approach of Quality Tools in Manufacturing Industry
 
IRJET - Invistigation and Implement of Six Sigma and Reduce Labour Cost a...
IRJET -  	  Invistigation and Implement of Six Sigma and Reduce Labour Cost a...IRJET -  	  Invistigation and Implement of Six Sigma and Reduce Labour Cost a...
IRJET - Invistigation and Implement of Six Sigma and Reduce Labour Cost a...
 
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
 
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
 
Just in Time System: A Study and Review
Just in Time System: A Study and ReviewJust in Time System: A Study and Review
Just in Time System: A Study and Review
 
Failure of tube reduced in split air conditioner
Failure of tube reduced in split air conditionerFailure of tube reduced in split air conditioner
Failure of tube reduced in split air conditioner
 
Challenges in implementing Total Productive Maintenance in Indian Manufacturi...
Challenges in implementing Total Productive Maintenance in Indian Manufacturi...Challenges in implementing Total Productive Maintenance in Indian Manufacturi...
Challenges in implementing Total Productive Maintenance in Indian Manufacturi...
 
VSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTVSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPT
 
Ppt jit
Ppt jitPpt jit
Ppt jit
 
Sheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
Sheet Metal Assembly Process Optimization Using Lean Manufacturing ToolSheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
Sheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
 

Recently uploaded

(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 

M.tech (Production and Industrial Engineering) Thesis Presentation

  • 1. TO IMPROVE OEE OF MODULE IMPLANTING MACHINE IN A SIM-CARD MANUFACTURING COMPANY USING LEAN TOOLS SUBMITTED BY: SANCHIT JAIN M.TECH P&IE) 2016-18 UNDER THE SUPERVISION OF: DR. RAHUL O. VAISHYA ASSISTANT PROFESSOR
  • 2. 27-7-2018 BY- SANCHIT JAIN INTRODUCTION R1. Can Lean Tools be used to improve system performance of a SIM Card manufacturing company? R2. Can Overall Equipment Effectiveness be used as a measure to improve equipment effectiveness? RESEARCH QUESTATION
  • 3. 27-7-2018 BY- SANCHIT JAIN RESEARCH METHODOLOGY RESEARCH DESIGN Defined as the framework for collecting and analysing data.  5 research designs suggested by Bryman and Bell (2003) are: • Experimental Design - Comprising an experiment that is being conducted in a laboratory or a natural setting in a systematic way. • Cross-Sectional Design - A snap-shot of an on-going situation to investigate economic characteristics of large numbers of people or organisations. • Longitudinal Design - The approach that collects data for two or more distinct time periods with the subjects being the same or comparable from one period to the next. • Comparative Design - Used to uncover contrasting findings between two or more cases • Case Study Design - An up-close, in-depth, and detailed examination of a subject of study (the case), as well as its related contextual conditions. Action Research – This approach allows the researcher to make a 'real-time' contribution to the research in parallel to matching the expected academic rigour.
  • 4. 27-7-2018 BY- SANCHIT JAIN RESEARCH METHODOLOGY Research opportunities Literature Review Research Methodology Data Collection Applying Lean Tools in Case Studies Analysis of Outcomes OEE Improvement/ Achieving research objectives RESEARCH DESIGN FOR THIS THESIS PROJECT Case Study and Action Research both seems useful approaches to be adopted for this thesis. For this, a SIM card Manufacturing Company is used as the sole case organisation in order to be aware of what type of problems can be met, and how to get around them. As the main aim of this project is to improve the effectiveness of a machine, some aspects surrounding the machine will change. It could be some technical devices, some operation modification or some way to act, that could be modified. RESEARCH MODEL
  • 5. 27-7-2018 BY- SANCHIT JAIN OVERVIEW OF CASE ORGANIZATION The case organization specialises in Smart Cards manufacturing INDUSTRY CHARACTERISTICS DETAILS ABOUT CASE ORGANIZATION Company Name & Location Syscom Corporation Pvt Ltd, Noida (IDEMIA, France MNC) Industry sector Telecommunication Product SIM Cards/Telco Cards Production volume and variety High Volume - High Variety Manufacturing Type/ Process Batch Manufacturing / Make To Order process MAIN UNIT CBC ULCC
  • 6. 27-7-2018 BY- SANCHIT JAIN PRODUCT RANGE GOVT / Health ID BANKING BIOMETRIC QUARTER TELCO ID1 HALF
  • 7. 27-7-2018 BY- SANCHIT JAIN PRODUCTION PROCESS Module lamination Card Body Milling Module Implanting Chip Personalisation Card Body PunchingWarehouse (RM Stock) Warehouse (Finished Stock) Production Process Flow Value Stream. The production process flow begins with Cavity milling process on the card body (CB) to host the module and an adjacent process to prepare modules by Chip module lamination before Implanting Chip Module on CB. The next stage is Card Personalization which includes within itself the sequence of steps that make every smart card unique. During this process individual card holder data are loaded into the chip memory. The final stage is Card Breaking / Punching where the plug-in of two types (Combi SIM card: which comes with Mini SIM & Micro SIM cards plug-in and Trio SIM: which supports all three plug-in variants of Mini SIM (2FF), Micro SIM (3FF) and Nano SIM (4FF) all in one SIM) is punched on SIM card and also the card is break in half or quarters using a metallic tools.
  • 8. 27-7-2018 BY- SANCHIT JAIN AVAILABLE RESOURCE Process (Pn) Machine Name (Xn) Number of machines Hourly Capacity Module Lamination (P1) CML 3 36000 Card Body Milling (P2) JMD 5 40000 Module Implanting on Card body (P3) JED 5 36000 Chip Personalisation (P4) SYE 3 36000 Card Breaking / Punching (P5) CB+YMJ 3+1 36000 Theoretical Capacity per month = XBottleneck*(Base Hour/day)*(Planned Days/ Month) = 36000*24*26 = 22.4 Mu/month A review of the existing process indicated that data driven improvements and therefore more process specific data was needed to understand the problems that indicate where and what improvements could be made. Actual Production (61% OEE) = 13.6 Mu
  • 9. 27-7-2018 BY- SANCHIT JAIN OVERALL EQUIPMENT EFFECTIVENESS (OEE) The accurate estimation of the equipment utilization is very important especially in a capital-intensive industry (e.g. the semiconductor, SIM-card and chemical industries) and Overall Equipment Effectiveness (OEE) is the best known indicator of equipment performance. YEAR AUTHOR THEME 1988- 89 Nakajima Introduces OEE as the measure of TPM used for collecting and analysing the combined effects of plant availability, performance and quality. 1992 Hartmann Concept of Hidden Factory and suggested TPM is the key to unlock. 2000 Willmott and McCarthy Confirms the work of Nakajima on OEE and applied to achieve best of the best equipment efficiency 2001 Jeong & Phillips Redefined OEE based on capital intensive Industry and introduced TPIS. In a capital intensive industry managers want to utilize their equipment as effectively as possible to get an early return on their investment.
  • 10. 27-7-2018 BY- SANCHIT JAIN Nakajima (1988) define OEE as a measure of the effective utilisation of capital assets by expressing the impact of equipment losses based on six types of equipment losses tracked in the OEE calculation. NAKAJIMA’S OEE CALCULATION
  • 11. 27-7-2018 BY- SANCHIT JAIN CRITIQUE ON OEE CALCULATION Nakajima’s OEE calculation does not include scheduled maintenance time for preventive maintenance and non-scheduled time such as off-shift and holiday. These time losses are however, important in capital-intensive industry. For example, to reduce nonscheduled time, most SIM card manufacturers are operating three eight hour shifts. 1. Non Scheduled Time: time duration for which equipment is not scheduled to operate. This time may include holiday and leave, etc. 2. Scheduled maintenance time: time spent for preventive maintenance in the equipment. 3. Unscheduled maintenance time: time spent for breakdown. 4. R&D time: time spent for the purpose of research and development. 5. Engineering usage time: time spent for an engineering check-up. 6. Setup and adjustment time: time spent for setup and adjustment for operation. 7. WIP starvation: the time for which equipment is operating when there is no WIP to process. 8. Idle time without operator: time for which WIP is ready; however there is no operator available.
  • 12. 27-7-2018 BY- SANCHIT JAIN According to Jeong & Phillips (2001), the downtime category varies from company to company and must be individually defined and categorized accordingly to meet the requirements of OEE in their company. Sr. No. Organization's D/T Categories Jeong & Phillips D/T Categories 1 Preventive Maintenance Scheduled Maintenance Time 2 No plan by PPC Non Scheduled Time 3 New product Trail R&D 4 Planned facility Down Scheduled Maintenance 5 Material not procured timely* N.A. 6 Machine breakdown Unscheduled maintenance time 7 No Milled Cards WIP starvation 8 Batch Change Setup & Adjustment 9 Machine Cleaning Engineering usage time 10 ATR Rejection Unscheduled maintenance time 11 Setup change Setup & Adjustment 12 Kanban buffer* N.A. 13 No Operator Idle Without Operator CRITIQUE ON OEE CALCULATION
  • 13. 27-7-2018 BY- SANCHIT JAIN OEE CALCULATION FOR CASE ORGANIZATION Preventive Maintenance No plan by PPC New Product Trail No milled Cards Machine Cleaning Machine Breakdown Batch change Setup change No Operator Throughput Loss Total Time Net Operation Time Operating Time Availability = Operating Time/ Total Time OEE= Availablity x Performance x Quality Valuable operating Time Quality Loss Performance = Net Operating Time/ Operating Time Quality = Valuable Operating Time/ Net Operating Time
  • 14. 27-7-2018 BY- SANCHIT JAIN IMPLEMENTING TAKT TIME Takt time is the maximum amount of time in which a product needs to be produced in order to satisfy customer demand. Steps To Implement TAKT Time 1. Measuring individual cycle times of each process. 2. Comparing each cycle time with the Takt time to identify bottleneck processes- those with cycle time more than Takt time. 3. These bottleneck processes are made free from NVA in order to bring cycle time below takt time and achieve customer demand. The Calculation for takt time is as follows • Available Production time = Total production time – (breaks + maintenance activities + shift changeover + clean down time) (Eq2) • Customer demand = amount of units required by customer/ time period (Eq3) • Takt Time = Available Production Time/Customer demand (Eq4) 0 5 10 15 P1 P2 P3 P4 NVA VA Takt Time Cycle 0 5 10 15 P1 P2 P3 P4 VA Takt Time 0 5 10 P1 P2 P3 P4 Cycle Time Takt Time
  • 15. 27-7-2018 BY- SANCHIT JAIN IMPLEMENTING TAKT TIME Takt Time Calculation Based On One Month Forecasted Loading: • Available time (hour/month) = 705 • Forecast demand (card/month) = 17000000 • Takt time (sec) = 705*3600/17000000 = 0.149 sec 0.125 0.143 0.164 0.133 0.133 0.149 0.000 0.040 0.080 0.120 0.160 0.200 P1 P2 P3 P4 P5 C/T /card Actual (sec) Takt Time (sec) Descriptions Formulae Used Processes P1 P2 P3 P4 P5 Declared Capacity/Mc/hr - 12000 8000 7200 12000 9000 Standard Time/Machine (Sec) = Time sec declared capacity 0.30 0.45 0.50 0.30 0.40 No. Of Machine - 3 5 5 3 4 Production efficiency %* = Output ST Loading time 80% 63% 61% 75% 75% Declared Cycle Time/card(sec) = Standard Time no.of Machine 0.10 0.09 0.10 0.10 0.10 Actual Cycle Time/card (sec) * = 𝐃𝐞𝐜𝐥𝐚𝐫𝐞𝐝 𝐂𝐲𝐜𝐥𝐞 𝐓𝐢𝐦𝐞 𝐏𝐫𝐨𝐝𝐮𝐜𝐭𝐢𝐨𝐧 𝐞𝐟𝐟𝐢𝐜𝐢𝐞𝐧𝐜𝐲 0.125 0.143 0.164 0.133 0.133 Actual Cycle Time VS Takt Time.
  • 16. 27-7-2018 BY- SANCHIT JAIN OEE ANALYSIS OF BOTTLENECK PROCESS 1 M1 59% 95% 99.9992% 56% 2 M2 60% 97% 99.9994% 58% 3 M3 61% 97% 99.9992% 59% 4 M4 67% 97% 99.9993% 65% 5 M5 67% 97% 99.9997% 65% Overall 63% 97% 99.9994% 61% OEE Breakup Of Five Module Implanting Machines 1 Machine breakdown (unscheduled maintenance time) 24535 25940 23480 19535 17650 111140 2 No Milled Cards (WIP starvation) 5895 9625 9575 2375 6035 33505 3 Batch Change 4700 5410 4090 5595 5430 25225 4 Machine Cleaning (Engg. usage time) 4735 4990 4950 5215 5150 25040 5 ATR Rejection 1510 405 660 3140 3245 8960 6 Setup change 4525 1460 1110 1765 60 8920 7 Kanban buffer 1020 230 0 2475 1905 5630 8 No Operator 0 580 720 0 0 1300 Total DT(Min.) 46980 48640 44585 40100 39475 DT(Hrs.) 783 811 743 668 658
  • 17. 27-7-2018 BY- SANCHIT JAIN 111140 33505 25225 25040 8960 8920 5630 1300 60 51% 66% 77% 89% 93% 97% 99% 100% 0% 20% 40% 60% 80% 100% 120% 0 20000 40000 60000 80000 100000 120000 Mahcine breakdown No Milled Cards Batch Change Machine Cleaning ATR Rejection m/c conversion Kanban buffer No operator Other DT(M) Cum. DT %age Pareto Diagram Of Down Time Data Collected OEE ANALYSIS OF BOTTLENECK PROCESS
  • 18. 27-7-2018 BY- SANCHIT JAIN SINGLE MINUTE EXCHANGE OF DIES (SMED) SMED is a Lean Tool used to shorten the changeover time hence reducing total production cost. Year Authors/ Organization Theme 1950 Shigeo Shingo Initial developments on the concept while working with Toyota Industries. 1970 Shigeo Shingo &Taichi Ohno Improved setup process for a 1000 ton press at Toyota motors main plant from 4 hours to 90 minutes and creating a systematic technique for achieving SMED. 1980 Toyota Gosei Plant, Japan Setup time of cold forging machine was reduced by 69% from 100 minutes to 31 minutes using same approach. 1985 Shigeo Shingo In his book ‘A revolution in manufacturing: The SMED system’ shared with the world concept of SMED. 2001 McIntosh Improving changeover performance: A strategy for becoming a lean, responsive manufacturer 2008 Buket Boztınaztepe Lean Tools for Reducing Production Time and Satisfying Employees: A Case Study. 2013 Aurelien Narses Case study: Production and OEE improvement for an 800 tons stamping press. It is evident from all the examples that this approach could be applied to any factory and on any machine.
  • 19. 27-7-2018 BY- SANCHIT JAIN APPLICATION OF SMED IN CASE ORGANISATION SMED on Setup Change of Module Implanting Machine Stage 1. Data Collection 1. Interviewing operator, maintenance engineer and production supervisor: • Questions to Production supervisor: -When and how are you communicated that a machine is required to undergo conversion? -Who all are involved in conversion activity and what are their roles? -What is your role in conversion process after you are being communicated? • Questions to maintenance engineer: -When and how are you communicated that a machine is required to undergo conversion? -What is the standard operating procedure of existing setup change process (if any)? • Questions to operator: -When and how are you communicated that your machine is required to undergo conversion? -What is your role in conversion process? PPC plans & share to prod. Mail from Prod. to maintenance Machine & equipments preparation Converting each part of machine Final adjustments & trial run Machine under observation till stable production Mass productionMachine setup change process flow (Macro)
  • 20. 3.Final adjustments and trial runs (36%) 3.1 New Reel loading 3.2 Raising hot weld temp. to required limit 3.3 First card Inspection 2.Converting each part of machine (41%) 2.1 Change module punch tool(Die) 2.2 Allign Pick&Place arm with punch tool 2.3 Hot weld heads shifting 2.4 Hot weld base plate shifting 2.5 Cold weld tool shifting 2.6 card detection sensor shifting 2.7 Tacking (Prepress) station shifting 2.8 Slot tester shifting 2.9 Module detection sensor shifting 2.10 ATR tester Head shifting 1.Machine and Equipment Preparation (23%) 1.1 Bring hand Tools ( L-key set, screw driver etc.) 1.2 Bring module punch die of new module type from tool room 1.3 Make available test cards, test module reel(laminated), visual gauge template 1.4 Making the machine ready for conversion (open covers ,turn off heating elements, remove previous card box, remove old Reel, install test reel etc.) First stage Bifurcation of Setup Change Process & Percentage Contribution 2. Using stopwatch with intermittent Videotaping:
  • 21. 27-7-2018 BY- SANCHIT JAIN SMED on Setup Change of Module Implanting Machine Module implanting Machine-Setup Change Process No. 1ststage Element Breakup 2nd Stage Element Breakup Activity Observed Time (sec) 1.1 Bring Test Material Bring Test cards EXTERNAL 312 Bring test module reel EXTERNAL 210 Sub total 5% 522 1.2 Bring New Module punch Die from tool room Change fittings on the new die EXTERNAL 380 Sub total 4% 380 1.3 Prepare Machine for conversion Turn off heating Elements and wait till it comes to room temperature, Open machine cover INTERNAL 680 remove previous batch card boxes INTERNAL 63 Remove & wind old reel INTERNAL 160 Install test reel INTERNAL 235 Sub total 12% 1138 2.1 Change module punch tool(Die) Change fittings on the new die EXTERNAL 410 Remove previous die from the machine INTERNAL 220 placing and connecting new die to the machine INTERNAL 122 Insert test reel in die and trial run to test the punch position INTERNAL 170 Sub total 10% 922 2.5 Alignment of Pick & Place arm with punch tool Open front bolt by L-key INTERNAL 10 Back front bolt by L-key INTERNAL 21 lifting>shifting>placing>aligning INTERNAL 100 Adjustments INTERNAL 30 Close front and back bolt simultaneously INTERNAL 13 Sub total 2% 174 2.3 Hot weld head shifting Place Test card under 1st weld head for reference INTERNAL 25 Move 1st weld head to new position with X & Y lead screws >visually check using test card>adjust to finalize INTERNAL 150 Place Test card under 2nd weld head for reference INTERNAL 24 Move 2nd weld head to new position with X & Y lead screws >visually check using test card>adjust to finalize INTERNAL 166 Place Test card under 3rd weld head for reference INTERNAL 26 Move 3rd weld head to new position with X & Y lead screws >visually check using test card>adjust to finalize INTERNAL 210 Place Test card under 4th weld head for reference INTERNAL 25 Move 4th weld head to new position with X & Y lead screws >visually check using test card>adjust to finalize INTERNAL 156 Sub total 11% 782 2.4 Hot weld base plate (BP) shifting Open weld head INTERNAL 18 look for required L-key EXTERNAL 18 1st base plate (loosen the bolt>shift BP.>tighten bolts) INTERNAL 107 2nd base plate (loosen the bolt>shift BP.>tighten bolt) INTERNAL 87 Again1st base plate (tighten bolts) WASTE 25 3rd base plate (loosen the bolt>shift BP.>tighten bolt) INTERNAL 81 4th base plate (loosen the bolt>shift BP.>tighten bolt) INTERNAL 94 Sub total 4% 430 2.5 Cold weld tool shifting Loosen bolts>shift/adjust>tighten bolts INTERNAL 80 Sub total 1% 80 2.6 Card detection sensor shifting Loosen bolts>shift/adjust>tighten bolts INTERNAL 91 Sub total 1% 91 2.7 Tacking(Prepress) station shifting Open front cover INTERNAL 11 loosen bolts by L-Key>shifting INTERNAL 50 Centring INTERNAL 43 Adjusting/Aligning Press Tool Tip with embedded module of test card INTERNAL 22 half tighten bolt>adjustment/aligning>full tighten Bolt INTERNAL 142 1st check (centring+tacking>observe>untack>visual check) INTERNAL 29 2nd check (centring+tacking>observe>untack>visual check) INTERNAL 39 Slight shifting(half tighten bolt>shifting>full tighten Bolt) INTERNAL 188 Sub total 5% 524 2.8 Slot tester shifting open front cover INTERNAL 50 open front channel INTERNAL 107 Front Slot tester(loosen the bolt>shift gauge.>tighten bolt) INTERNAL 122 Back Slot tester(remove the bolt>shift gauge>tighten bolt) INTERNAL 150 close front channel and cover INTERNAL 225 Sub total 7% 654 2.9 Module detection sensor shifting Loosen bolts>shift/adjust>tighten bolts INTERNAL 91 Sub total 1% 91 2.10 ATR tester Head shifting loosen the bolts>removing bolts INTERNAL 60 place test card for reference INTERNAL 12 alignment/shifting INTERNAL 40 tighten the bolts while aligning tester pins with card module INTERNAL 92 Sub total 2% 204 3.1 New Reel loading Replacing Test Module reel with New Module Reel INTERNAL 450 Sub total 5% 450 3.2 Raising hot weld temp. to required limit INTERNAL 718 Sub total 7% 718 3.3 First card Inspection, Trial run and final adjustments 1st trial run on test card INTERNAL 140 CTQ parameters check. INTERNAL 340 Adjustments of critical parameters INTERNAL 185 2nd trial run on test card INTERNAL 137 CTQ parameters check. INTERNAL 356 1st test run on live card INTERNAL 164 CTQ parameters check. INTERNAL 320 Intermittent minor adjustments till mass production at stable rate INTERNAL 545 Sub total 23% 2187 Current Total Time (sec) 100% 9578 Current Total Time (min) 160 Stage 2. Separating Internal and External Elements By the end of this stage of improvement process, external elements were separated from internal. The percentage share of the external elements was 15% of the total time.
  • 22. 27-7-2018 BY- SANCHIT JAIN Stage 3. Streamlining Operations: Improvement of operations A. Problem- Hot Weld Heads Shifting- (Step number 2.3 of Table 10) SMED on Setup Change of Module Implanting Machine The ‘Hot weld head’ is the most critical element of Module Implanting machine. Its function is the permanent assembly (or Embedding) of module on the card body (CB) by the progressive heating and fusion of tape layer (at the bottom side of module) with top surface of plastic (ABS material) CB. The heating is done in four progressive steps with four weld heads maintained around 220°C temperature. The position of heating element must be right above the module at all the time and accuracy up to microns is required for effective heat transfer and plastic fusion. The conversion of all the four weld head took a total of 50 minutes in the study done. X-Axis Lead Screws Y-Axis Lead Screws Mounting Plate Heating Elements Labelled image of Hot Weld Heads
  • 23. 27-7-2018 BY- SANCHIT JAIN Solution- A brainstorming session held with the team resulted in a unique solution of this problem. The solution was to modify design of plate where all weld heads are mounted such that conversion could be simple, accurate, require less skill and need to turn off heating elements was no more required. A 3D CAD design was prepared with the modification suggested by the team. The main design modification was that of a mounting change of weld heads. A new slider plate was introduces in the design between weld heads and mounting plate. This will be enabling all the weld heads to move simultaneously and accurately at the required position of new product. Figure 18 shows the 3D design created by author to the required specifications after several reviews and modification with the team. Sliding Guides Slider Plate Mounting plate SMED on Setup Change of Module Implanting Machine CAD Design of modified Mounting
  • 24. 27-7-2018 BY- SANCHIT JAIN 3D CAD Design of Modified Mounting using Solid Works SMED on Setup Change of Module Implanting Machine
  • 25. 27-7-2018 BY- SANCHIT JAIN The modification required large capital expenditure which must be justified with the amount of time reduction this modification would provide. Some calculations shown below will clear that the investment required is justified. • Estimated cost of expenses on modification = ₹15000 (1) • Estimated time saved/ Conversion = 50 minutes = 3000 sec (2) • Total conversion per month (estimated from previous data) = 3.5 times (3) • Time saved per month = (2)*(3) = 10500 sec (4) • Standard production throughput = 3600 cards/ hour = 1 card/ sec (5) • Price per card = ₹ 2.4 (6) • Total cost saved = (4)*(5)*(6) = ₹ 25200/ Month (7) • Return To Investment (ROI) = (1)/(7) = 0.595 Month The Calculation shows that it will take about half a month, i.e. not more than two conversions, to start returning the profits of the design modification. This justifies the expenditure of modification proposed. Project Proposal SMED on Setup Change of Module Implanting Machine
  • 26. 27-7-2018 BY- SANCHIT JAIN Improvement- Final modification of hot weld design mounting was successfully made. Figure 19 shows the actual image of modified weld mounting with slider plate. This innovative improvement reduces about 32% of total internal time. Slider Plate Linear guides Mounting Plate Actual Modified Weld Mounting SMED on Setup Change of Module Implanting Machine
  • 27. 27-7-2018 BY- SANCHIT JAIN B. Problem- Slot Tester shifting - (Step number 2.8 of Table 10) Slot tester is nothing but a depth gauge which measures depth of cavity milled on cards during milling process. The function of slot tester is to ensure that the cavity milled is of required depth, so that module is implanted with no defect. The problem with shifting slot tester was a tedious job and can be understand with the image shown below. Slot tester needs to be shifted towards right for new product (Red arrow). Before shifting the slot tester, three more parts need to unbolt and removed i.e. first the front cover (Black), then two T- shaped support columns (Behind cover) and then channel. These are all necessary but wasteful activities. Total extra time in removing and then reassembling after shifting slot tester is 4% of total changeover time (6.3 minutes). Channel Cover Slot Tester Back view of Slot Tester Mounting SMED on Setup Change of Module Implanting Machine
  • 28. 27-7-2018 BY- SANCHIT JAIN Solution- Taking feedback from the operators, a rather simple solution was applied to the seemingly complex problem. The solution to eliminate this waste is to cut a rectangular shaped slot on the channel. Now, no more dismantling of extra parts is required. Final image after the improvement looks as shown below. It shows a cut portion of channel. This enable direct access to slot tester mounting bolts which mere needs to be shifted from one screw hole to another for shifting. Cut Section Mounting bolts Slot tester mounting After Improvement Learning- The important aspects of such improvement are as follows:- 1. The active participation of operators in problem solving. 2. An effective and No-cost solution to a complex problem. SMED on Setup Change of Module Implanting Machine
  • 29. 27-7-2018 BY- SANCHIT JAIN C. Problem- Screw type clamps used in weld head assembly are time consuming while opening and closing heads. The frequent opening and closing of weld head, owing to major and minor adjustments, require a quick and accurate clamping solution. Refer figure 1 for previously used screw type clamp. Screw Type Clamp 1. Screw Type Clamp on weld assembly Solution- New Toggle type clamp was used to simplify the operation and reduces time by allowing quick clamping of the assembly. Figure 2 shows new type of clamp. Toggle Clamp 2. New Toggle Clamp After Improvement SMED on Setup Change of Module Implanting Machine Improvement- A rough estimation of the impact on internal time due to this improvement is about 5-10 minutes reduction.
  • 30. 27-7-2018 BY- SANCHIT JAIN D. Problem- Ineffective manpower utilization- The entire conversion process was carried out by two men: Maintenance engineer and operator. Maintenance engineer is an expert in machine conversion and works actively to perform all the elements, while operator plays a supportive role and his involvement is passive most of the time owing to the complexity of operations as well as lower skill level. Another factor contributing to low manpower utility is a lot of wasted motion moving from front of machine to the back, and vice versa because most of the operations were performed by one worker (the engineer). To understand the utility of both, following graph was made from video recording. Figure 24 divides the total time of conversion in useful and idle time for both men. This gives us their respective percentage utility: engineer =78% and operator =31%. Manpower utility graph SMED on Setup Change of Module Implanting Machine
  • 31. 27-7-2018 BY- SANCHIT JAIN Solution- Since, major complex operations are now made simple and required lower skill, the operator can easily perform such operations and have more active participation in conversion process. With few more training sessions about the modified processes, the operator’s utility would increase significantly. Training and skill enhancement is a good but an old strategy and is discarded by Shingo. Instead, a better solution of adopting parallel operations was suggested in his book. Since, operator can now perform most of the task on his own. The concept of parallel tasking will play an effective role in time reduction. Instead of performing each task in series one after the other, a better strategy is to work parallel and perform two different tasks simultaneously. Few important points were considered while constructing the optimum flow. 1. Equal time distribution among both men. 2. Proper sequencing of operations based on essential precedence order. For example: ‘Tacking tool (Prepress) shifting’ must follow after ‘Alignment of Pick & Place arm’ and ‘Alignment of Pick & Place arm with punch tool’ must follow after ‘Change module punch die’ operation SMED on Setup Change of Module Implanting Machine
  • 32. 27-7-2018 BY- SANCHIT JAIN Parallel Operations Flow Card detection sensor shifting Machine running stable Prepare machine for conversion Change module punch die Hot weld head shifting Cold weld tool shifting Hot weld base plate shifting Tacking tool (Prepress) shifting Alignment of Pick & Place arm with punch tool First card Inspection, Trial run and final adjustments Bring new module punch die Start Bring Test Cards and module Reel Change Fitting on new die Slot tester shifting Module detection sensor shifting Stop machine MAINTENANCE ENGINEER MACHINE OPERATOR E X T E R N A L I N T E R N A L ATR Tester shifting The entire process is equally divided among machine operator and maintenance engineer such that, they perform separate operations simultaneously which consumes equal amount of time. Improvement- Using two men working on front and back jobs concurrently, the implementation of parallel operations had improved utility of both operator and engineer up to 95% each. Thus, the reduction of 25% more internal time was achieved. SMED on Setup Change of Module Implanting Machine
  • 33. 27-7-2018 BY- SANCHIT JAIN SMED on Setup Change of Module Implanting Machine Result Of SMED on Setup Change Process After training the operators and engineers of new setup change process, new video study on setup change was conducted on same machine. The total time taken to complete the setup change process was close to 20 minutes. So, with the application of SMED concept a reduction of 87.5% in setup change time has achieved. 160 20 0 50 100 150 200 Before After Setup Time (minutes) Setup Time (minutes) 87.5% Impact on OEE: Following calculations were made to show impact on OEE :- Total base time per day per machine = 1440 min; Total time saved per machine per day = (160-20)*0.2 = 28 min Increase in Availability = 28/1440 = 1.94 % Increase in OEE = Increased Availability* Old Quality* Old performance rate Therefore, Increase in OEE due to improvement using SMED = 1.9 %.
  • 34. 27-7-2018 BY- SANCHIT JAIN SMED On Batch Change Activity Stage 1. Data Collection • Data collection was done using videotaping and recording the entire batch change process as it is. S.N. Element Description Activity Observed Time (sec) 1 Stop the machine and clear it of last batch material INTERNAL 42 2 Open the door and cut the module reel with cutter INTERNAL 11 3 Cut the module reels & make a roll of reels & keep them on trolley INTERNAL 60 4 Count Bad modules and keep them in the box. EXTERNAL 79 5 Entry in check sheet for closing batch EXTERNAL 42 6 Pick airgun and clean the m/c INTERNAL 36 7 Bring the IPA bottle to m/c for cleaning EXTERNAL 14 8 Clean die and suction pipes of module Transfer INTERNAL 20 9 Again go back to keep the IPA bottle EXTERNAL 16 10 Using command panel to clean the die INTERNAL 56 11 Filling log book, check sheet, downtime sheet and etc. EXTERNAL 150 12 Waiting for the correct module reel. EXTERNAL 140 13 Pick and installed the module reel on machine output side INTERNAL 190 14 Pick the scrap material and go to throw them in dustbin EXTERNAL 27 15 Pick the tape from OQC station EXTERNAL 22 16 Paste tape on bad module cup and correct the module reel INTERNAL 78 17 Pick and installed the module reel on machine input side INTERNAL 147 18 Paste tape to correct the module reel INTERNAL 76 19 Looking for the box of CB to run on machine EXTERNAL 14 20 Using air gun on fresh cards to segregate the burr on card INTERNAL 18 21 Pick the cards and feed to input magazine in three turns INTERNAL 16 22 Now close the machine and run INTERNAL 18 Total Time (Second) 1272 Total Time (Minutes) 21.2 • The elemental breakup of entire operation was done with the help of an engineer from maintenance department such that a notable difference can be easily made between each element
  • 35. 27-7-2018 BY- SANCHIT JAIN S.N. Element Description Activity Observe d Time (sec) Internal (Sec) Exter nal (Sec) 1 Stop the machine and clear it of last batch material INTERNAL 42 42 - 2 Open the door and cut the module reel with cutter INTERNAL 11 11 - 3 Cut the module reels & make a roll of reels & keep them on trolley INTERNAL 60 60 - 4 Count Bad modules and keep them in the box. EXTERNAL 79 - 79 5 Entry in check sheet for closing batch EXTERNAL 42 - 42 6 Pick airgun and clean the m/c INTERNAL 36 36 - 7 Bring the IPA bottle to m/c for cleaning EXTERNAL 14 - 14 8 Clean die and suction pipes of module Transfer INTERNAL 20 20 - 9 Again go back to keep the IPA bottle EXTERNAL 16 - 16 10 Using command panel to clean the die INTERNAL 56 56 - 11 Filling log book, check sheet, downtime sheet and etc. EXTERNAL 150 - 150 12 Waiting for the correct module reel. EXTERNAL 140 - 140 13 Pick and installed the module reel on machine output side INTERNAL 190 190 - 14 Pick the scrap material and go to throw them in dustbin EXTERNAL 27 - 27 15 Pick the tape from OQC station EXTERNAL 22 - 22 16 Paste tape on bad module cup and correct the module reel INTERNAL 78 78 - 17 Pick and installed the module reel on machine input side INTERNAL 147 153 - 18 Paste tape to correct the module reel INTERNAL 76 76 - 19 Looking for the box of CB to run on machine EXTERNAL 14 - 14 20 Using air gun on fresh cards to segregate the burr on card INTERNAL 18 18 - 21 Pick the cards and feed to input magazine in three turns INTERNAL 16 16 - 22 Now close the machine and run INTERNAL 18 18 - Total Time (Second) 1272 768 504 Total Time (Minutes) 21.2 12.8 8.4 Stage 2. Separating Internal from External Elements The data was then analysed to look for elements that can be categorised as ‘internal’ and ‘external’. SMED On Batch Change Activity It was observed that 8.4 minutes out of 21.2 minutes was spent on doing activities that could have been done when the machine was running i.e. 41%of total time. Fractional share of Internal and External Activities
  • 36. 27-7-2018 BY- SANCHIT JAIN To streamline operation, all the elements were analysed to know their functional requirement and whether a particular element is actually required to be performed while doing batch change S.N. Element Description Activity Function Observe d Time (sec) Internal + Functional 1 Stop the machine and clear it of last batch material INTERNAL Machine Preparation 42 42 2 Open the door and cut the module reel with cutter INTERNAL Reel change 11 11 3 Cut the module reels & make a roll of reels & keep them on trolley INTERNAL Reel change 60 60 4 Count Bad modules and keep them in the rejection box. EXTERNAL Batch closing 79 - 5 Entry in check sheet for closing batch EXTERNAL Batch closing 42 - 6 Pick air gun and clean the m/c INTERNAL Machine cleaning 36 - 7 Bring the IPA bottle to m/c for cleaning EXTERNAL Machine cleaning 14 - 8 Clean die and suction pipes of module Transfer INTERNAL Machine cleaning 20 - 9 Again go back to keep the IPA bottle EXTERNAL Machine cleaning 16 - 10 Using command panel to clean the die INTERNAL Machine cleaning 56 - 11 Filling log book, check sheet, downtime sheet and etc. EXTERNAL Batch closing 150 - 12 Waiting for the correct module reel. EXTERNAL Wait for material 140 - 13 Pick and install the 1st module reel on machine INTERNAL Reel change 190 190 14 Pick the scrap material and go to throw them in dustbin EXTERNAL Machine cleaning 27 - 15 Pick the tape from OQC station EXTERNAL Waste 22 - 16 Paste tape on bad module and correct the module reel INTERNAL Reel Change 78 78 17 Pick and install the 2nd module reel on machine INTERNAL Reel Change 147 147 18 Paste tape to correct the module reel INTERNAL Reel Change 76 76 19 Looking for the box of CB to run on machine EXTERNAL CB change 14 - 20 Using air gun on fresh cards to segregate the burr on card INTERNAL CB change 18 18 21 Pick the cards and feed to input magazine in three turns INTERNAL CB change 16 16 22 Now close the machine and run first good part INTERNAL Final Adjustments 18 18 Total Time (Second) 1272 656 Total Time (Minutes) 21.2 10.9 Stage 3. Streamlining operations and Operator Training These contribute 330 seconds i.e. 5.5 minutes of total observed time and 112 seconds of total internal time. Hence, the final effective time remains 656 seconds or 10.9 minutes. SMED On Batch Change Activity
  • 37. 27-7-2018 BY- SANCHIT JAIN Brainstorming with team (production, maintenance and quality) was done and priority of the tasks was decided such that machine cleaning was secondary to batch change and could be avoided during batch change. This yield following decisions: 1. To make available all the essentials such as Tape, cutter etc. on the machine all the time to avoid motion and searching time loss. 2. Machine Cleaning is a separate regular activity of DPM (Daily Preventive Maintenance) and must be done during that time only and must not be included during batch change. 3. A standard work instruction needs to be prepared with new sequence of steps. This is now used for training the operators about new process SMED On Batch Change Activity
  • 38. 27-7-2018 BY- SANCHIT JAIN After training the operators of new batch change process, new video study was conducted on three batch change done on similar machine by three different operators. The total time taken was: 10.3 minutes, 10.5 minutes and 9.8 minutes respectively i.e. an average 10.2 minutes. So, with the use of SMED concept a reduction of 52% in batch change time has achieved Result Of SMED on Batch Change Process Impact on KPI: Following calculations were made to show impact on OEE :- Total time per day per machine = 1440 min; Total time saved per machine per day = (20-10.2)*3.5 = 34.3 min Increase in Availability = 34.3/1440 = 2.38% Increase in OEE = Increased Availability* Old Quality* Old performance rate Therefore, Increase in OEE due to improvement using SMED = 2.26 %. SMED On Batch Change Activity
  • 39. 27-7-2018 BY- SANCHIT JAIN Aim is to reduce the time of activities done during Machine Cleaning. CONTINUOUS IMPROVEMENT: Kaizen on Machine Cleaning 1. Elemental breakup of the process such that proper distinguish can be made between two activities. 2. Time Study by camera recording of the process. (stop watch can also be used) 3. Element wise time assigning from the recording (observed time). 4. Deciding which elements are useful and which one are wasteful i.e. distributing data into three categories- Value added, Non value added and Waste. 5. Rating each activity based on level of commitment of the operator. This means whether the operator is performing 100% or less to do a particular activity. 6. Multiply rating factor with observed time to get Normal Time. 7. Assign allowance to each task and multiply with normal time to get Standard Operating time. Step involved for data measurement and analysis:
  • 40. 27-7-2018 BY- SANCHIT JAIN Firstly open the door and cut the module reel with cutter 1 NVA 11.0 100% 11 11 11 Cut the module reel by hand & make a roll of reel & keep this on trolley ( From both side) 1 NVA 60.0 100% 60 60 60 Count Bad modules and keep them into a box. 1 Waste 79.0 100% 79 79 79 Entry in checksheet 1 NVA 42.0 100% 42 42 42 Pick airgun and clean the m/c 1 VA 36.0 100% 36 36 36 Pic the module & parallaly waiting for the new batch 1 Waste 72.0 100% 72 72 72 Pick the IPA and go back to m/c to clean it 1 Waste 14.0 100% 14 14 14 Clean die and suction pipes of IC T/F 1 VA 20.0 100% 20 20 20 Again go back to keep the ipa bottle on back trolley 1 Waste 16.0 100% 16 16 16 Now by using command on pannel clean the die 1 VA 56.0 100% 56 56 56 Again using air gun to clean the machine 1 NVA 74.0 100% 74 74 74 Now going to lineleader to confirm about the next batch module reel 1 Waste 20.0 100% 20 20 20 Now pick the module reel and go to lamination machine station to change it 1 Waste 67.0 100% 67 67 67 Pick the cutter form input trolley and placed on back trolley 1 Waste 8.0 100% 8 8 8 Now going to the output of machine aand pick and fill the log book,checksheet,production sheet and etc. 1 NVA 150.0 100% 150 150 150 Now still waiting for the correct module reel. 1 Waste 140.0 100% 140 140 140 Now pick and installed the actual module reel on output side 1 VA 190.0 100% 190 190 190 Pick the scrap material and go to fall them in dustbin 1 Waste 27.0 100% 27 27 27 Pick the tape from oqc station 1 Waste 22.0 100% 22 22 22 paste on bad module cup and correct the module reel 1 NVA 78.0 100% 78 78 78 Now pick the input module reel and go to installed 1 VA 153.0 100% 153 153 153 Now again pick the tape from oqc station 1 NVA 18.0 100% 18 18 18 and paste on moduel reel joint at output side and correct the module reel 1 Waste 76.0 100% 76 76 76 Now going to the trolley at input side and find the box to run on machine 1 Waste 14.0 100% 14 14 14 Now after finding the running box going to machine 1 Waste 20.0 100% 20 20 20 Using air gun on fresh cards to segregate the burr on card 1 VA 18.0 100% 18 18 18 Pick the cards and feed into the magzine in three turns 1 VA 16.0 100% 16 16 16 Now correct the machine and run 1 VA 18.0 100% 18 18 18 Sub Total 1515.0 1 1515 1515 507 433 575 25.3 8.45 7.22 9.58 S. N. Process Description Element Description Task 1 Batch Qty 1 Batch Change Observed Time (sec) VA NVA Waste Remarks No. of Operators Rating Normal Time (sec) Std. Time (sec) Machine Cleaning CONTINUOUS IMPROVEMENT: Kaizen on Machine Cleaning
  • 41. 27-7-2018 BY- SANCHIT JAIN The report shows that only 33% of total time was utilised to perform useful activities and 38% of time was invested in completely wasteful activity which needs immediate elimination. Module Implanting Machine Cleaning process S.No. Problems Corrective Actions Time (s) 1 Wrong module reel feeding by the lamination machine operator Paste a machine name sticker on every module reel 227 2 Count Bad Module Manually No need to count the bad module just keep them in pouch.(Because this is NVA activity and we have no need to do this) 79 3 Waiting for new batch After doing preplanning for new batch 72 4 Pick and place the usable tools (Cutter,Tape etc.) from here and there. Make a cardboard tool box for keeping the all using tools 48 5 Box finding problem Box no. identification by marker 34 6 Motion loss for finding the IPA bottle ( Come and go timing) Fix one IPA Bottle on every machine 30 7 To drop the scap material due to lack of dustbins operator need to extra motion Need to increase more numbers of dustbins to avoid this delay 27 Total Time Saved per batch (Sec) 517 Total Time Saved per batch (Minutes) 8.62 Results of Kaizen: 1. Reduction in cleaning time by almost 50%. 2. Improvement in OEE by 3% CONTINUOUS IMPROVEMENT: Kaizen on Machine Cleaning
  • 42. 27-7-2018 BY- SANCHIT JAIN CONCLUSION AND FUTURE SCOPE Project Results OEE improvement from all the applications of different lean tools: 1. Machine cleaning activity was reduced to half the time it used to take to complete the activity. This improved process OEE of Module implanting machine by 3%. 2. SMED on Batch change reduced the total lost time by 52% i.e. now it takes 10 minutes to change the batch which was 21 minutes before the project. The impact on process OEE of Module implanting machine is an increase of 2.2%. 3. SMED on Setup change process of reduced the lost time by 87.5% i.e. now it takes 20 minutes to completely change machine setup which was 160 minutes before the start of project. The impact on process OEE of module implanting machine is an increase of 1.9%.
  • 43. 27-7-2018 BY- SANCHIT JAIN CONCLUSION Summing up of all the improvement activities shows a total of 7.1% OEE improvement of Module implanting process in manufacturing SIM card. Earlier, Module Implanting process was identified as system bottleneck with the application of Takt time. Since, a bottleneck process the weakest part of system, any improvement made will be reflecting at system level. Therefore, it can be said that the OEE of SIM card manufacturing company was improved by 7.1%. The Final OEE of system is 68.1%. 1. The application of Lean tools in the company in order to improve its performance was a success. Hence, the answer to the first research question i.e. ‘R1. Can Lean Tools be used to improve system performance of a SIM Card manufacturing company?’ is obvious. 2. Also the second research question i.e. ‘R2. Can Overall Equipment Effectiveness be used as a lean measure to improve equipment effectiveness?’ is made clear. CONCLUSION AND FUTURE SCOPE
  • 44. 27-7-2018 BY- SANCHIT JAIN Academic Achievements Publication/Journal Paper Title Indexed Publication Status IJTIMES Applying SMED to reduce Changeover Time and Improve System Performance UGC Published, Volume 04 Issue 07, July-2018 Inderscience Publication/ IJPQM Case Study: Application of SMED in SIM Card Manufacturing Company SCOPUS, UGC Screening for Acceptance
  • 45. 27-7-2018 BY- SANCHIT JAIN Certification Of Publication
  • 46. 27-7-2018 BY- SANCHIT JAIN Plagiarism Report

Editor's Notes

  1. Developing specific research objectives and providing structure to this thesis, the following research questions will be answered by this thesis
  2. RM- The procedure which researchers follow to achieve their work.