A Critical Literature Review on Main Cause of Delay in Construction
Projects
1PG student at Parul University department of civil engineering, Gujarat, India
2Assistant professor, Civil engineering department, Birla Vishwakarma Mahavidyalaya Engineering College
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract – An in construction industry time is a very
important measure and crucial resource in project
management life cycle! In construction project context wecan
explain the delay of time as postponement of time to finish the
project progress. It is the driving force for the project success.
If we didn't use time properly even it is one cause for failure.
So, in Construction Project cycle delay is the greatest common
problems. When the real project work duration is more than
planned project duration we call it project time delay. The
result of delay will cause many unwanted effects on projects;
like the conflict between the project owner and contractors or
claim between the project participants, overstated prices, loss
of production and income, and contract closed. Delay is a very
recurrent and non-planned phenomenon which is almost
related to all ongoing construction projects. This review work
attempts to find and investigate the main factors perceived to
affect delays in projects. On this review, the basicdelay causes
in construction project reviewed on the past literature review.
The frameworks and the delay critical review was obtained
based on past literature reviews conclusion. The researcher
achieves their aims to get the main cause of delay on building
constructions by inviting the construction stakeholders
specifically contractor, developers, designer, and client. The
most conducted method to find the main cause of delays is
Relative Important Index (RII) and Importanceindexbasedon
the degree of severity and degree of frequency.
Key Words: (time, delay, cause of delay, Construction
project
I. INTRODUCTION
This Construction industriesare an industry, whichcontains
planning of project work. Scheduling of project duration,
organizing, evaluating, executing project progress and
observing of all project works. The Structural organizations
such as infrastructures, energy and communication &
energy-related construction works, water supply & disposal
construction work etc., are some of the the-the work to be
performed construction industry. From the management
function (planning, organizing, staffing, scheduling,
executing, monitoring) scheduling can relate with a
completion time of the project, also related with time delay.
If the project duration (real work duration) is either above
finishing point date detailed in a contract document, or
above the date that the project owner and contractors
agreed upon for transfer of the project, and exceed the
expected time is identified as time delay. This is when the
project work is out of date, and it requires more cost of
construction and addition working time on before agreed
planned scheduled on contract document. For project
holdersdelay can be defined lossof income in the absenceof
construction services and rentable space or a dependencyto
the services on the hand. For contractors or project
developers delay is a loss of a lot of finance for the reason
that the work takes long time duration to be progressed,
higher cost of construction material due to inflation,
increasing of workerscost. Usually delay in the construction
industry by many factors linked with the performance of
time, quality, and cost. The construction project is
universally approved as successful when it finished on time,
within budget, according to specifications and to
stakeholder's satisfaction. Delay increases work sliding and
late finishing of the project, disagreement of client and
contractors. This may cause disturbance of project progress
and loss of services, also increases time linked costs, and
finally, it may cause termination of construction project
work and its contract.
II. LITERATURE REVIEW
Definition: delay is a period of late time of project that
identified in a contract agreement or greater than the date
that contractor and client decided upon submission of a
project. It is a project time lag over its planned schedule and
is well thought-out ascommon difficultiesintheconstruction
industry. To the project holder’s side, a delay is known by a
loss of income through lack of manufacture services and
rentable space or a dependency on present services. In
another case, to the project developer/ contractor side,delay
means higher loss of costs because of the extended work
period and late project submitting, a high cost of material
than at cost at before through cost rise, and due to workers
cost increases than previously planned within the estimated
time duration.
Construction Project: construction projects are those of
projects related to the construction field who have limited
time dimension with specific allocation of resources, and a
particular purpose. To finish construction projects, have
adhered to the boundary three obstacles are:
Project cost (Budget): the construction project should be
efficient.
Project time duration: (Schedule): the construction
projects to be effective.
Required project quality (Quality): performance must
meet the required of specifications and criteria. The main
elements that are within a project:
Desalegn Disasa Daba1, Dr. Jayeshkumar Pitroda 2
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 01 | Jan-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 613
 Cost: finance and investmentrequiredforproject
completion
 Quality: the scope of the wanted quality and
understandable requirements.
 Quantities: scope of the project.
 Time: howlong andwhen it takesforprogressof
the construction.
Many ofresearchesandstudieshavecompletedtoexplore
the reasons why delays happens in construction projects;
both nearby and globally research have been reviewed.
Doloi, Hemanta, Sawhney, Anil,Iyer, and K. C. Rentala,
Sameer(2012) developed the study on cause of delay on
Indian construction, and they categorized the cause of
delay:(1) Site related (2) project related (3) process related
(4) human related and (5) technical issue related [1]
In Egypt, Cairo Mohamed M. Marzouk *, Tarek I. El-
Rasas(2014) also study to analyse the cause ofdelayinEgypt
construction and according to his analyzing result the
following are the main groups of cause of delay(1) project
holder,(2) advisors,(3),developer (4) Material,(5)workers&
machines),(6) Project,(7), External related delay factors,[2]
El-Razek et al. (2014) identified basic causes of delays in
Egyptianconstruction projects and summarizedthat,mostof
construction parties do not agree on the RII of variousdelay,
more censuring each other of delays by IMP.I. He recognizes
significance of team roles in the achievement of a project.[2]
Reviews done by Assaf, Sadi A.Al-Hejji, Sadiq (2006)
defined fifty six basic causes of delay in huge construction
projects. He grouped the delay causes into nine (9) basic
groups with dissimilar levels and dissimilar parties. As he
concluded, out of hundred percent 76% project developer
have specified that average of delay is between 10 percent
and 30 percent (10%-30%)of originalduration.Andtwenty-
five percent of construction consultants (advisors) have
specified from 30 percent to 50 percent (30%-50%) average
timedelay. According to hisresearch surveyownersexplains
that cause of project delays are related to labors and
contractors. Research identifies that consultants and clients
realize that giving the contract for the list (lowest) biddersis
the most frequent cause of delay, while, construction
contractors thought asownersare severe reasonof delay [3]
Al-Ghafly (1995) explained about the delay in public
water and sewage projects. He finds and group sixty (60)
cause of the delay. Al-Ghafly decided the following: most of
the time delay happened in large and medium project scope
(projects size), and measured as very severe in a small
project. Based on his research and its summary, the main
delay causes are related to the project holder, contractor’s
activity, the original planning, duration forecast and
preparation of the project. Main causes are (1) finance (2)
delay in agreement and decision-making by owner, (3)
variations in the plan and size (project scope), (4)problemin
gaining a work permit, and (5) organization and
communication problems. [4].
Al-Momani (2000) surveyed causesofdelayin130public
projects in Jordan. So, according to his research survey the
important delay causeswereinterrelatedwith:(1)design,(2)
user changes, (3) weather, (4) site conditions, (5)latesupply,
(6) financial conditions and (7) rise quantity of work. This
scholarship proposed that special care to factors causing
delay will help production consultants in reducing contract
disputes. [5]
As Megha Desai and, Rajiv Bhatt (2250*):59 factors of
delays are identified for residential construction projects.
These factors are collected into nine (9) main are delay
related to : (1)Project,(2) project holder (user), (2)
construction developer (3) Consultant (4) Design, (5)
construction Material, (6) Equipment (7) workers and
(8)External factors based on their nature & way of its
existence.(9) project related [6]
Aziz, Remon Fayek (2013) explored ninety-nine (99)
factors of delay in construction project and the discovered
causes were categorized under the following 9 primary
category: (1) Consultant (2) Contractor (3) Design; (4)
Equipment (5) External (6) Labour (7) Material; (8) Owner
and (9) Project related factors of delay. [7]
Aziz, remain Fayek(2013) also analysis and identifies
high-impact value of delay causes in Egypt as follows:
Funding problems, different strategies patterns for bribes,
Shortage of equipment, Ineffective project planning and
scheduling, Poor site management and investigation, Poor
monetary control on site, Rework, Selecting non-skilled
contractors, Sudden Accidents ,poor planning, low-skilled
working team, Inadequate contractor experience, Frequent
equipment breakdowns, Global financial crisis,Complexityof
the work (project type, project scale, etc.) Project Legal
arguments between project stakeholders, disagreement
between joint-ownership variation, poor construction
method, non-skilled labor, Conflicts [7]
Tsegay Gebrehiwet and Hanbin Luo (2017) studied that
contrast between the three construction stages and overall
result as the overall is the most similar to all stages of delay
causes. And they conclude the top greatest main causes of
delay in the Ethiopian construction project identified from
overall. According to their research analysis, thehighestrank
of the cause of delay in Ethiopian construction is corruption.
Also unavailability of services (utilities) at the site, inflation,
less quality material, late design and design documents, less
speed of material supply, late in agreement of contract and
receiving of completed project work, poor site management
and performance, late release budget/ funds, and
unsuccessful project preparation and scheduling. The result
of this research showsthat the two most basic cause of delay
in Ethiopian construction projects are cost overrun and time
overrun. Also, they grouped the main cause of delay as the
following: 1) Responsibility Related Causes, 2) Resource-
Related Causes, 3) Contract conditionrelatedcausesAbsence,
4) External Causes Adverse.[8]
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 01 | Jan-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 614
L. Muhwezi, J. Acai, and G. Otim (2014) prepared a
research in Uganda on "An assessment of the factors causing
delays on building construction projects in Uganda" and as
they concluded a whole of eighty-one (81)reasonsthatcause
delay were known and grouped into 4 groups of advisors
related factorsof delay, contractorrelateddelaycause,client-
related delay cause, and external related delay cause. [9]
Tushar Khattri1, Sohit Agarwal2, Vaishant Gupta3,
Mukesh Pandey4(2016) addresses the most noteworthy
variables and groups to reasons for delays.by using
Important Index (IMPI) method and they listed the most
critical top ten cause of delay as follows 1) Delay in material
supply,2) Price Variation,3) Robberies at project site,4) Less
quality Material,5) Delay in material inquiries ,6) Un reliable
sub-contractor.7) Poor productivity workers.8) Critical
weather condition.9) Variation in specification and material
at working time .10) Delay in providing servicesfromutilities
[10]
Dinesh Kumar R (2016) studies on Causes and Effects of
Delays in Indian Construction Projects and the paper aimsto
findout the most significant Factorscausing delays in Indian
construction projects through literature review and
questionnaire survey. This paper conclude that most
significant factors causing delay in the construction,
inadequate contractor'swork & experience & their poor risk
management and ignorance By recognising this fact,
awarding theprojecttothe competentcontractorwhohaslot
of experience in the specific project type will avoid this kind
of delay in the project, in which specialised and global
contractors know well to tackle the pressurised situation by
adopting effective risk management skills. [11]
MAJOR FINDING FROM THE ABOVE REVIEWPAPER
L Muhwezi, J. Acai, and G. Otim (2014) found that: Although
most of the basic delay cause in Ugandan building
construction project conduct thesamemethodologywiththe
other research the highest rank among the top 10 main
cause of the delay is "corruption tendencies".[9]
El-Razek et al. (2008) found that fiscal problem of a
contractor (developer) is the basic cause. Poor site
supervision and site management is definitely the other key
cause of delay affecting time performance of most
construction projects in India. [2]
Aziz, Remon Fayek 2013), by using RII method he listed the
rank of top 20 main cause delay .according to his result the
highest main cause delay is client related delay factor.[7]
3. CONCLUSIONS
Although different researchersfrom different area studythe
cause delay in a construction project, some of the explored
delay causes are similar. So, based on different literature
study many delay causeswere placed underdifferentgroups
with their different subgroups. The main groupsofdelayand
their sub-groups in construction projects are as follows
A.CONSULTANT RELATED DELAY FACTORS/CAUSE:
Lack of experience ,disagreement with a design engineer
,delay in approving project scope ,delay in performing
inspection and testing, poor site investigation, unskilled
project management assistance, delay in approving and
checking design documents, inadequate coordination and
communication between project holders and developers,
recurrent change of contractorsand sub-contractors,kindof
project award and bidding ,variation during constructionby
owners, unfavorable weather condition during construction
work, poor experience of consultant and contractors, delay
in checking working drawing, error in design documents
and discrepancies, less brief specifications in drawings
,quality pledge
B.CONTRACTOR RELATED DELAY FACTORS/CAUSE
Dishonesty/problems in funding by contractor ,ineffective
site supervision, ineffective scheduling ,revise due to
mistakes during work ,sub-contractors work related delay,
poor experience of the contractor, delay in sitearrangement,
delay in preparation of working drawing and sample of
material, delay in payment of executed work foracontractor
by the owner, slow decision-making ,late approving design
documents ,variation by owner, delay in procurement of
materials, mistakes in design documents,recurrentchanging
of subcontractors, poor methods of construction, unskilled
project crew, poor technology, poor coordination and
communication between them, ineffective contractor’s
policies, unskilled sub-contractors, ineffective economic
control on site, inadequate procurement of construction
materials, improper equipment, frequent equipment
breakdowns ,shortage of equipment, subcontractor turn-
over ,lack of labour, slow mobilization of labour, ineffective
equipment ,slow equipment deliver, materials damage,
strike, conflict between labor and client
C.OWNER RELATED DELAY FACTORS/CAUSE:-
Corruption ,intermittent termination of variation while
project is ongoing, less on-time payment for developers,
variation of specifications and material type during
construction work, delay in checking contract document,
variation of project scope, poor coordination with other
stakeholders, slow decision-making,inadequate information
during project feasibility study ,delay in site delivery, lack of
motivations for contractor to finish ahead of schedule
,ineffective representative, poor experience, interference
during actual project work, joint-owners disagreement,
improper feasibility study ,poor coordination and
communication, interruption of work ,slow document
approve ,nature bidding and award ,impractical contract
duration ,unrealistic delay penalties
D.EXTERNAL RELATED DELAY FACTORS/CAUSE:
Claim, unexpected natural disasters ,accidents at the site,
social and environmental factors, escalation oflocalmaterial
prices and global economic rise, price rise on the
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 01 | Jan-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 615
international market ,Unreliable suppliers, public enemy ,
war, and conflict, delay in obtaining permits from local
authority, geopolitical stability, variation in government
regulations ,late access to the site (like electricity, road ,
water) ,neighbors problems, delay by traffic restriction and
control ,corruption, social factors, cultures, government
policy and its commitment ,late certification from 3rd party,
lack of communication ,thieves, international economic
crisis, time delay by traffic restriction at the place of work,
raw materials unavailability
E.RESOURCERELATED FACTOR/CAUSE
I.LABOURS RELATED FACTORS:-Absenteeism,Lowmorale
Low productivity, conflicts, Lack of labour, slow
mobilization, strikes Poor labour experience injuries, less
experience with equipment handling
II .CONSTRUCTION MATERIAL RELATED FACTOR:-Less
qualified materials, late material supply, and Material
variation during project work, Material Damage, Inflation
III. FINANCE RELATED DELAY CAUSES:-claims due to
financial, funding processes by government, slow funds
release by fund raisers, International economic crisis
IV. EQUIPMENT RELATEDCAUSES:-Insufficientorshortage
of equipment, Low efficiency and productivity of equipment
lack of spare parts, lack of equipment, equipment failure,
Delay in delivery of equipment, mobilizing problems of
material
F. PROJECT RELATED DELAY CAUSE
Unsuccessful delay punishments, too short duration of
original contract, Legal disputes between various part
REFERENCES
[1] Hemanta Doloi ,⁎, Anil Sawhney , K.C. Iyer , Sameer
Rentala “Analyzing factors affecting delays in Indian
construction projects”, International Journal of Project
Management 30 (2012) 479–489.
[2] Mohamed M. Marzouk *, Tarek I. El-Rasas, “Analyzing
delay causes in Egyptian construction projects”, Journal
of Advanced Research (2014) 5,49–55
[3] Assaf SA, Al-Khalil M, Al-Hazmi M. “Causes of delays in
large building construction projects.” ASCE J Manage
Eng. 1995; 11(2):45–50..
[4] Al-Ghafly MA. “Delays in the construction of public
utility projects in Saudi Arabia”. Master thesis, CEM
Dept., KFUPM, Dhahran, Saudi Arabia, 1995.
[6] Megha Desai , Rajiv Bhatt P.G.Student, “CriticalCausesof
Delay in Residential Construction Projects”,
International Journal of Emerging Technology and
Advanced Engineering ,(ISSN 2250-2459, ISO
9001:2008 Certified Journal, Volume 3, Issue 3, March
2013)
[7] Remon Fayek Aziz * “Ranking of delay factors in
construction projects after Egyptian revolution” ,
Alexandria Engineering Journal (2013) 52, 387–406
[8] Tsegay Gebrehiwet and Hanbin Luo , “Analysis of Delay
Impact on Construction Project Based on RII and
Correlation Coefficient: Empirical Study”, Creative
Construction Conference 2017, CCC 2017, 19-22 June
2017
[9] L.Muhwezi, J. Acai, and G. Otim, “An Assessment of the
Factors Causing Delays on Building Construction
Projects in Uganda” , International Journal of
Construction Engineering and Management 2014, 3(1):
13-23
[10] Tushar Khattri1, Sohit Agarwal2, Vaishant Gupta3
,Mukesh Pandey4 “Critical Causes of Delay In
Construction Project In Jhansi Region”, International
Research Journal of Engineering andTechnology(IRJET)
Volume: 03 Issue: 10 Oct -2016
[11] Dinesh Kumar R “causes and Effects of Delays in Indian
Construction Projects”, International Research Journal
of Engineering and Technology (IRJET) e-ISSN: 2395 -
0056,Volume: 03 Issue: 04 | Apr-2016 www.irjet.net p-
ISSN: 2395-0072
BIOGRAPHIES
Desalegn Dsasa Daba , PG student at
Parul university ,M-Tech in
Construction Project Management ,
and graduated by construction
technology and Management in
bachelor at wollega University
,Oromia ,Ethiopia
Dr. Jayeshkumar Pitroda Assistant
professor and research scholar at
BVM engineering college Anand,
Gujarat. india
[5] Al-Momani. A. H (2000) “construction delay, a
quantitative analysis” Journal of Project Management ,
18 (2000) ,51-59

More Related Content

What's hot

Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...Antonio Coladarce
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoignitetribes
 
The significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential projectThe significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential projectIOSR Journals
 
I0313048051
I0313048051I0313048051
I0313048051theijes
 
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons..."Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...Abhishek Shah
 
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...Project Controls Expo
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes managementMohammed Tanbouz
 
Critical Review on Causes and Effects of Variation Order on Construction Project
Critical Review on Causes and Effects of Variation Order on Construction ProjectCritical Review on Causes and Effects of Variation Order on Construction Project
Critical Review on Causes and Effects of Variation Order on Construction ProjectIRJET Journal
 
Delay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping StationDelay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping Stationchetlapally balakrishna
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Roland_Nikles
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsDr. Amarjeet Singh
 

What's hot (19)

D012522433
D012522433D012522433
D012522433
 
Kandil_Sameh_CPMPart 3 _b
Kandil_Sameh_CPMPart 3 _bKandil_Sameh_CPMPart 3 _b
Kandil_Sameh_CPMPart 3 _b
 
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promo
 
Kandil_Sameh_CPMPart 5 _b
Kandil_Sameh_CPMPart 5 _bKandil_Sameh_CPMPart 5 _b
Kandil_Sameh_CPMPart 5 _b
 
Kandil_Sameh_AR50360
Kandil_Sameh_AR50360Kandil_Sameh_AR50360
Kandil_Sameh_AR50360
 
The significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential projectThe significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential project
 
I0313048051
I0313048051I0313048051
I0313048051
 
Kandil Mohammed Ibrahim_Sameh_Dissertation
Kandil Mohammed Ibrahim_Sameh_DissertationKandil Mohammed Ibrahim_Sameh_Dissertation
Kandil Mohammed Ibrahim_Sameh_Dissertation
 
Detailed engineering-design-phase
Detailed engineering-design-phaseDetailed engineering-design-phase
Detailed engineering-design-phase
 
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons..."Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
 
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes management
 
Critical Review on Causes and Effects of Variation Order on Construction Project
Critical Review on Causes and Effects of Variation Order on Construction ProjectCritical Review on Causes and Effects of Variation Order on Construction Project
Critical Review on Causes and Effects of Variation Order on Construction Project
 
Delay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping StationDelay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping Station
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 

Similar to IRJET-A Critical Literature Review on Main Cause of Delay in Construction Projects

A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...IRJET Journal
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET Journal
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET Journal
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET Journal
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...IJERA Editor
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...IJMER
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectseSAT Journals
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectseSAT Journals
 
Analysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims inAnalysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims ineSAT Publishing House
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTIRJET Journal
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of timeJoseph Sangpang
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewIRJET Journal
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delayEst
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...IRJET Journal
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...iosrjce
 

Similar to IRJET-A Critical Literature Review on Main Cause of Delay in Construction Projects (20)

A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projects
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projects
 
Analysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims inAnalysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims in
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
B012140812
B012140812B012140812
B012140812
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delay
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 

Recently uploaded (20)

Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 

IRJET-A Critical Literature Review on Main Cause of Delay in Construction Projects

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 01 | Jan-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 612 A Critical Literature Review on Main Cause of Delay in Construction Projects 1PG student at Parul University department of civil engineering, Gujarat, India 2Assistant professor, Civil engineering department, Birla Vishwakarma Mahavidyalaya Engineering College ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract – An in construction industry time is a very important measure and crucial resource in project management life cycle! In construction project context wecan explain the delay of time as postponement of time to finish the project progress. It is the driving force for the project success. If we didn't use time properly even it is one cause for failure. So, in Construction Project cycle delay is the greatest common problems. When the real project work duration is more than planned project duration we call it project time delay. The result of delay will cause many unwanted effects on projects; like the conflict between the project owner and contractors or claim between the project participants, overstated prices, loss of production and income, and contract closed. Delay is a very recurrent and non-planned phenomenon which is almost related to all ongoing construction projects. This review work attempts to find and investigate the main factors perceived to affect delays in projects. On this review, the basicdelay causes in construction project reviewed on the past literature review. The frameworks and the delay critical review was obtained based on past literature reviews conclusion. The researcher achieves their aims to get the main cause of delay on building constructions by inviting the construction stakeholders specifically contractor, developers, designer, and client. The most conducted method to find the main cause of delays is Relative Important Index (RII) and Importanceindexbasedon the degree of severity and degree of frequency. Key Words: (time, delay, cause of delay, Construction project I. INTRODUCTION This Construction industriesare an industry, whichcontains planning of project work. Scheduling of project duration, organizing, evaluating, executing project progress and observing of all project works. The Structural organizations such as infrastructures, energy and communication & energy-related construction works, water supply & disposal construction work etc., are some of the the-the work to be performed construction industry. From the management function (planning, organizing, staffing, scheduling, executing, monitoring) scheduling can relate with a completion time of the project, also related with time delay. If the project duration (real work duration) is either above finishing point date detailed in a contract document, or above the date that the project owner and contractors agreed upon for transfer of the project, and exceed the expected time is identified as time delay. This is when the project work is out of date, and it requires more cost of construction and addition working time on before agreed planned scheduled on contract document. For project holdersdelay can be defined lossof income in the absenceof construction services and rentable space or a dependencyto the services on the hand. For contractors or project developers delay is a loss of a lot of finance for the reason that the work takes long time duration to be progressed, higher cost of construction material due to inflation, increasing of workerscost. Usually delay in the construction industry by many factors linked with the performance of time, quality, and cost. The construction project is universally approved as successful when it finished on time, within budget, according to specifications and to stakeholder's satisfaction. Delay increases work sliding and late finishing of the project, disagreement of client and contractors. This may cause disturbance of project progress and loss of services, also increases time linked costs, and finally, it may cause termination of construction project work and its contract. II. LITERATURE REVIEW Definition: delay is a period of late time of project that identified in a contract agreement or greater than the date that contractor and client decided upon submission of a project. It is a project time lag over its planned schedule and is well thought-out ascommon difficultiesintheconstruction industry. To the project holder’s side, a delay is known by a loss of income through lack of manufacture services and rentable space or a dependency on present services. In another case, to the project developer/ contractor side,delay means higher loss of costs because of the extended work period and late project submitting, a high cost of material than at cost at before through cost rise, and due to workers cost increases than previously planned within the estimated time duration. Construction Project: construction projects are those of projects related to the construction field who have limited time dimension with specific allocation of resources, and a particular purpose. To finish construction projects, have adhered to the boundary three obstacles are: Project cost (Budget): the construction project should be efficient. Project time duration: (Schedule): the construction projects to be effective. Required project quality (Quality): performance must meet the required of specifications and criteria. The main elements that are within a project: Desalegn Disasa Daba1, Dr. Jayeshkumar Pitroda 2
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 01 | Jan-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 613  Cost: finance and investmentrequiredforproject completion  Quality: the scope of the wanted quality and understandable requirements.  Quantities: scope of the project.  Time: howlong andwhen it takesforprogressof the construction. Many ofresearchesandstudieshavecompletedtoexplore the reasons why delays happens in construction projects; both nearby and globally research have been reviewed. Doloi, Hemanta, Sawhney, Anil,Iyer, and K. C. Rentala, Sameer(2012) developed the study on cause of delay on Indian construction, and they categorized the cause of delay:(1) Site related (2) project related (3) process related (4) human related and (5) technical issue related [1] In Egypt, Cairo Mohamed M. Marzouk *, Tarek I. El- Rasas(2014) also study to analyse the cause ofdelayinEgypt construction and according to his analyzing result the following are the main groups of cause of delay(1) project holder,(2) advisors,(3),developer (4) Material,(5)workers& machines),(6) Project,(7), External related delay factors,[2] El-Razek et al. (2014) identified basic causes of delays in Egyptianconstruction projects and summarizedthat,mostof construction parties do not agree on the RII of variousdelay, more censuring each other of delays by IMP.I. He recognizes significance of team roles in the achievement of a project.[2] Reviews done by Assaf, Sadi A.Al-Hejji, Sadiq (2006) defined fifty six basic causes of delay in huge construction projects. He grouped the delay causes into nine (9) basic groups with dissimilar levels and dissimilar parties. As he concluded, out of hundred percent 76% project developer have specified that average of delay is between 10 percent and 30 percent (10%-30%)of originalduration.Andtwenty- five percent of construction consultants (advisors) have specified from 30 percent to 50 percent (30%-50%) average timedelay. According to hisresearch surveyownersexplains that cause of project delays are related to labors and contractors. Research identifies that consultants and clients realize that giving the contract for the list (lowest) biddersis the most frequent cause of delay, while, construction contractors thought asownersare severe reasonof delay [3] Al-Ghafly (1995) explained about the delay in public water and sewage projects. He finds and group sixty (60) cause of the delay. Al-Ghafly decided the following: most of the time delay happened in large and medium project scope (projects size), and measured as very severe in a small project. Based on his research and its summary, the main delay causes are related to the project holder, contractor’s activity, the original planning, duration forecast and preparation of the project. Main causes are (1) finance (2) delay in agreement and decision-making by owner, (3) variations in the plan and size (project scope), (4)problemin gaining a work permit, and (5) organization and communication problems. [4]. Al-Momani (2000) surveyed causesofdelayin130public projects in Jordan. So, according to his research survey the important delay causeswereinterrelatedwith:(1)design,(2) user changes, (3) weather, (4) site conditions, (5)latesupply, (6) financial conditions and (7) rise quantity of work. This scholarship proposed that special care to factors causing delay will help production consultants in reducing contract disputes. [5] As Megha Desai and, Rajiv Bhatt (2250*):59 factors of delays are identified for residential construction projects. These factors are collected into nine (9) main are delay related to : (1)Project,(2) project holder (user), (2) construction developer (3) Consultant (4) Design, (5) construction Material, (6) Equipment (7) workers and (8)External factors based on their nature & way of its existence.(9) project related [6] Aziz, Remon Fayek (2013) explored ninety-nine (99) factors of delay in construction project and the discovered causes were categorized under the following 9 primary category: (1) Consultant (2) Contractor (3) Design; (4) Equipment (5) External (6) Labour (7) Material; (8) Owner and (9) Project related factors of delay. [7] Aziz, remain Fayek(2013) also analysis and identifies high-impact value of delay causes in Egypt as follows: Funding problems, different strategies patterns for bribes, Shortage of equipment, Ineffective project planning and scheduling, Poor site management and investigation, Poor monetary control on site, Rework, Selecting non-skilled contractors, Sudden Accidents ,poor planning, low-skilled working team, Inadequate contractor experience, Frequent equipment breakdowns, Global financial crisis,Complexityof the work (project type, project scale, etc.) Project Legal arguments between project stakeholders, disagreement between joint-ownership variation, poor construction method, non-skilled labor, Conflicts [7] Tsegay Gebrehiwet and Hanbin Luo (2017) studied that contrast between the three construction stages and overall result as the overall is the most similar to all stages of delay causes. And they conclude the top greatest main causes of delay in the Ethiopian construction project identified from overall. According to their research analysis, thehighestrank of the cause of delay in Ethiopian construction is corruption. Also unavailability of services (utilities) at the site, inflation, less quality material, late design and design documents, less speed of material supply, late in agreement of contract and receiving of completed project work, poor site management and performance, late release budget/ funds, and unsuccessful project preparation and scheduling. The result of this research showsthat the two most basic cause of delay in Ethiopian construction projects are cost overrun and time overrun. Also, they grouped the main cause of delay as the following: 1) Responsibility Related Causes, 2) Resource- Related Causes, 3) Contract conditionrelatedcausesAbsence, 4) External Causes Adverse.[8]
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 01 | Jan-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 614 L. Muhwezi, J. Acai, and G. Otim (2014) prepared a research in Uganda on "An assessment of the factors causing delays on building construction projects in Uganda" and as they concluded a whole of eighty-one (81)reasonsthatcause delay were known and grouped into 4 groups of advisors related factorsof delay, contractorrelateddelaycause,client- related delay cause, and external related delay cause. [9] Tushar Khattri1, Sohit Agarwal2, Vaishant Gupta3, Mukesh Pandey4(2016) addresses the most noteworthy variables and groups to reasons for delays.by using Important Index (IMPI) method and they listed the most critical top ten cause of delay as follows 1) Delay in material supply,2) Price Variation,3) Robberies at project site,4) Less quality Material,5) Delay in material inquiries ,6) Un reliable sub-contractor.7) Poor productivity workers.8) Critical weather condition.9) Variation in specification and material at working time .10) Delay in providing servicesfromutilities [10] Dinesh Kumar R (2016) studies on Causes and Effects of Delays in Indian Construction Projects and the paper aimsto findout the most significant Factorscausing delays in Indian construction projects through literature review and questionnaire survey. This paper conclude that most significant factors causing delay in the construction, inadequate contractor'swork & experience & their poor risk management and ignorance By recognising this fact, awarding theprojecttothe competentcontractorwhohaslot of experience in the specific project type will avoid this kind of delay in the project, in which specialised and global contractors know well to tackle the pressurised situation by adopting effective risk management skills. [11] MAJOR FINDING FROM THE ABOVE REVIEWPAPER L Muhwezi, J. Acai, and G. Otim (2014) found that: Although most of the basic delay cause in Ugandan building construction project conduct thesamemethodologywiththe other research the highest rank among the top 10 main cause of the delay is "corruption tendencies".[9] El-Razek et al. (2008) found that fiscal problem of a contractor (developer) is the basic cause. Poor site supervision and site management is definitely the other key cause of delay affecting time performance of most construction projects in India. [2] Aziz, Remon Fayek 2013), by using RII method he listed the rank of top 20 main cause delay .according to his result the highest main cause delay is client related delay factor.[7] 3. CONCLUSIONS Although different researchersfrom different area studythe cause delay in a construction project, some of the explored delay causes are similar. So, based on different literature study many delay causeswere placed underdifferentgroups with their different subgroups. The main groupsofdelayand their sub-groups in construction projects are as follows A.CONSULTANT RELATED DELAY FACTORS/CAUSE: Lack of experience ,disagreement with a design engineer ,delay in approving project scope ,delay in performing inspection and testing, poor site investigation, unskilled project management assistance, delay in approving and checking design documents, inadequate coordination and communication between project holders and developers, recurrent change of contractorsand sub-contractors,kindof project award and bidding ,variation during constructionby owners, unfavorable weather condition during construction work, poor experience of consultant and contractors, delay in checking working drawing, error in design documents and discrepancies, less brief specifications in drawings ,quality pledge B.CONTRACTOR RELATED DELAY FACTORS/CAUSE Dishonesty/problems in funding by contractor ,ineffective site supervision, ineffective scheduling ,revise due to mistakes during work ,sub-contractors work related delay, poor experience of the contractor, delay in sitearrangement, delay in preparation of working drawing and sample of material, delay in payment of executed work foracontractor by the owner, slow decision-making ,late approving design documents ,variation by owner, delay in procurement of materials, mistakes in design documents,recurrentchanging of subcontractors, poor methods of construction, unskilled project crew, poor technology, poor coordination and communication between them, ineffective contractor’s policies, unskilled sub-contractors, ineffective economic control on site, inadequate procurement of construction materials, improper equipment, frequent equipment breakdowns ,shortage of equipment, subcontractor turn- over ,lack of labour, slow mobilization of labour, ineffective equipment ,slow equipment deliver, materials damage, strike, conflict between labor and client C.OWNER RELATED DELAY FACTORS/CAUSE:- Corruption ,intermittent termination of variation while project is ongoing, less on-time payment for developers, variation of specifications and material type during construction work, delay in checking contract document, variation of project scope, poor coordination with other stakeholders, slow decision-making,inadequate information during project feasibility study ,delay in site delivery, lack of motivations for contractor to finish ahead of schedule ,ineffective representative, poor experience, interference during actual project work, joint-owners disagreement, improper feasibility study ,poor coordination and communication, interruption of work ,slow document approve ,nature bidding and award ,impractical contract duration ,unrealistic delay penalties D.EXTERNAL RELATED DELAY FACTORS/CAUSE: Claim, unexpected natural disasters ,accidents at the site, social and environmental factors, escalation oflocalmaterial prices and global economic rise, price rise on the
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 01 | Jan-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 615 international market ,Unreliable suppliers, public enemy , war, and conflict, delay in obtaining permits from local authority, geopolitical stability, variation in government regulations ,late access to the site (like electricity, road , water) ,neighbors problems, delay by traffic restriction and control ,corruption, social factors, cultures, government policy and its commitment ,late certification from 3rd party, lack of communication ,thieves, international economic crisis, time delay by traffic restriction at the place of work, raw materials unavailability E.RESOURCERELATED FACTOR/CAUSE I.LABOURS RELATED FACTORS:-Absenteeism,Lowmorale Low productivity, conflicts, Lack of labour, slow mobilization, strikes Poor labour experience injuries, less experience with equipment handling II .CONSTRUCTION MATERIAL RELATED FACTOR:-Less qualified materials, late material supply, and Material variation during project work, Material Damage, Inflation III. FINANCE RELATED DELAY CAUSES:-claims due to financial, funding processes by government, slow funds release by fund raisers, International economic crisis IV. EQUIPMENT RELATEDCAUSES:-Insufficientorshortage of equipment, Low efficiency and productivity of equipment lack of spare parts, lack of equipment, equipment failure, Delay in delivery of equipment, mobilizing problems of material F. PROJECT RELATED DELAY CAUSE Unsuccessful delay punishments, too short duration of original contract, Legal disputes between various part REFERENCES [1] Hemanta Doloi ,⁎, Anil Sawhney , K.C. Iyer , Sameer Rentala “Analyzing factors affecting delays in Indian construction projects”, International Journal of Project Management 30 (2012) 479–489. [2] Mohamed M. Marzouk *, Tarek I. El-Rasas, “Analyzing delay causes in Egyptian construction projects”, Journal of Advanced Research (2014) 5,49–55 [3] Assaf SA, Al-Khalil M, Al-Hazmi M. “Causes of delays in large building construction projects.” ASCE J Manage Eng. 1995; 11(2):45–50.. [4] Al-Ghafly MA. “Delays in the construction of public utility projects in Saudi Arabia”. Master thesis, CEM Dept., KFUPM, Dhahran, Saudi Arabia, 1995. [6] Megha Desai , Rajiv Bhatt P.G.Student, “CriticalCausesof Delay in Residential Construction Projects”, International Journal of Emerging Technology and Advanced Engineering ,(ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 3, Issue 3, March 2013) [7] Remon Fayek Aziz * “Ranking of delay factors in construction projects after Egyptian revolution” , Alexandria Engineering Journal (2013) 52, 387–406 [8] Tsegay Gebrehiwet and Hanbin Luo , “Analysis of Delay Impact on Construction Project Based on RII and Correlation Coefficient: Empirical Study”, Creative Construction Conference 2017, CCC 2017, 19-22 June 2017 [9] L.Muhwezi, J. Acai, and G. Otim, “An Assessment of the Factors Causing Delays on Building Construction Projects in Uganda” , International Journal of Construction Engineering and Management 2014, 3(1): 13-23 [10] Tushar Khattri1, Sohit Agarwal2, Vaishant Gupta3 ,Mukesh Pandey4 “Critical Causes of Delay In Construction Project In Jhansi Region”, International Research Journal of Engineering andTechnology(IRJET) Volume: 03 Issue: 10 Oct -2016 [11] Dinesh Kumar R “causes and Effects of Delays in Indian Construction Projects”, International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 - 0056,Volume: 03 Issue: 04 | Apr-2016 www.irjet.net p- ISSN: 2395-0072 BIOGRAPHIES Desalegn Dsasa Daba , PG student at Parul university ,M-Tech in Construction Project Management , and graduated by construction technology and Management in bachelor at wollega University ,Oromia ,Ethiopia Dr. Jayeshkumar Pitroda Assistant professor and research scholar at BVM engineering college Anand, Gujarat. india [5] Al-Momani. A. H (2000) “construction delay, a quantitative analysis” Journal of Project Management , 18 (2000) ,51-59