The significant Causes and effects of delays in Ghadir 2206
residential project
1
Ebrahim Aboutorabi Najafabadi, 2
Prof. Dr. S. S. Pimplikar,
1
Research Graduate ME (Construction & Management)
2
Professor & Head-Civil Department MIT- Pune
Abstract: Delays in the construction projects are global events and the construction industry in Iran is no
exception. The main purpose of this study is to identify the delay factors and their effect on a particular project
completion named Ghadir 2206 residential construction project located in Fooladshahr, Iran.
It is attempted to analyze the most important causes and their impacts on specific effects.
This study identified nine most important causes of delay and effects of delay. Nine most important causes were:
1) Contractor’s improper planning, 2) Design changes, 3) Contractor’s poor site management and mistaken
decision in changing managers, 4) Inadequate contractor experience, 5) Inadequate client’s finance and
payments for completed work, 6) Problems with subcontractors, 7) Lack of communication between parties, 8)
Construction mistakes and defective works ,9) Material price escalation. The causes categories in contractor-
related factors, consultant-related factors, client-related factors and external factors.
The high significant causes identified are 1) Design changes 2) Material price escalation
Six main effects of delay were:
1) Time overrun 2) Cost overrun, 3) Disputes, 4) Arbitration, 5) Litigation, and 6) Abandonment
Keywords: Delay causes; Delay effects; Construction industry; Iran; Ghadir 2206 residential project;
I. Introduction
Delays are insidious often resulting in time overrun, cost overrun, disputes, litigation, and complete
abandonment of projects (Sambasivan and Soon, 2007).
Many projects are of such a nature that the client will suffer hardship, expense, or loss of revenue if the
work is delayed beyond the time specified in the contract (Clough, 1986). Then again, delay has cost
consequences for the contractor.
Delay is a reality in the construction process in the world. Although there may be unique aspects of the
different projects, sites, contract terms and customs and practices in different parts of the world, for the most
part the reality of delay unfortunately is universal to the construction industry.
In construction claims, the term “delay” is used to mean two different but related matters. Delay is
often used to mean the time period during which some part of the construction project has been extended
beyond what was originally planned due to unanticipated circumstances. Extension beyond what was initially
planned may also be called prolongation. Delay can also be the incident that affects the performance of a
particular activity, with or without affecting project completion. This concept of postponement occurs when the
planned start of an activity or project is delayed. An incident delay can originate from within the contractor's
organization or from any of the other factors interacting with the construction project. Incidences of delay from
within the contractor's organization are essentially those occurrences that the contractor himself has caused or
for which he is legally responsible.
Incidences outside of the contractor's organization may be caused by the owner (or employer) the
designer, other prime contractors, subcontractors, suppliers, labor unions, nature, or any of a number of other
organizations and entities that participate in the construction process.
Many events may occur on the construction project to increase the time of performance of the overall
project or affect any given activity. The most common causes of delay are contractor management and
performance problems; differing site conditions; changes in requirements or design; inclement weather;
unavailability of labor, material, or equipment; defective plans and specifications; and owner interference. These
and other delays not only increase the time required to perform the contract work but may also increase the costs
for many of the parties involved.
The present study focuses on the following objectives:
(i) Identify factors that significantly contributed to time and costs overruns in Ghadir project;
(ii) Establish the relative importance of these factors;
(iii) Quantify the time and costs associated with the significant factors.
(iv) Finding the solution to decrease delays
The significant Causes and effects of delays in Ghadir 2206 residential project
www.iosrjournals.org 76 | Page
II. Methodology Used
Field research based on the author's observations, interviews, formal correspondence, photos, project
scheduling, and interview with experienced people, study of the drawings and plans, and the author‟s
perceptions of project management requirements, examined popular causes of delay in this project.
Ghadir project:
The project is inclusive of 2206 residential units with about 222000-sqm floor area, which should be
handed over in about 24 months excluding landscaping. The type of contract was fixed price (2650000 IRR/sqm
on the time of agreement≈240USD/sqm)
The site location (32° 31' 50.26"N, 51° 20' 35.96"E) is in Fooladshahr, the new town of Fooladshahr at
the central part of Lenjan city, 25 kilometers from the south-west of Isfahan, is located in the communication
axis of Isfahan and Shahrecord. The area of this town is over 7700 hectares.
Fooladshahr was established for the residence of Zobe-ahan staff in 1963 and it started its activities
from 1984 as a new town. More than 85000 people live in this town at present.
Because of its nearness to the center of the province with an easy access to great industries such as
Zobe-ahan, Foolad Mobarakeh, and Sepahan Cement factory, this town is diverted into a suitable location for
residence. Other living advantages of this new town are its nearness to higher educational centers such as
Isfahan University of Technology, Isfahan University, and Najafabad Azad University.
The general information of Ghadir project is shown in table
Blocktype
No.of
blocks
Numberof
Stories
Numberof
units
No.ofunits
insametype
Numberof
roofs
Liftand
staircase’s
area(m²)
Lobby’s
area(m²)
Parking’s
area(m²)
Block’sarea
(m²)
non-useful
Areaof
everytype
(m²)
UsefulArea
ofevery
type(m²)
Totalarea
ofevery
type(m²)
A 43 4 18 774 5 161.05 41.2 106.7 1750 13284 61966 75250
B 12 4 26 312 5 388 78.1 194.67 2710 7929.7 24590 32520
C 14 5 22 308 6 132.6 32.9 362.58 2338 7393.1 25339 32732
D 4 5 27 108 6 260.4 15.3 421.23 2952 2787.6 9020 11808
E 8 6 38 304 7 456.96 72.3 235.27 3780 6116.6 24123 30240
E-1 2 8 50 100 9 587.52 72.3 235.27 4860 1790.3 7930 9720
F 2 4 18 36 5 155 19.7 319.5 1820 988.34 4472 5460
F-1 12 5 22 264 6 186 19.7 319.5 2186 6302 17744 24046
Tota
l
97 ---------- 2206 --- 2327.5 352 2194.7 22396 46592 17518
4
221776
Table 1-General information of Ghadir project residential units
III. Studies on significant causes of delay
1. Design changes:
Design changes and delays in design approval have caused delay to the project.
A number of studies have been carried out to determine the causes of delay in construction projects.
Sweis et al. (2008) studied the causes of delay in residential projects in Jordan and concluded that financial
difficulties faced by the contractor and too many change orders by the owner are the leading causes of
construction delay.
Assaf and Al-Hejji [6] conducted a survey on time performance of large construction projects in Saudi
Arabia. The survey had 73 different causes of delay. The researcher studied the importance of various causes
from the viewpoint of contractors, consultants, and owners. The most common cause of delay identified by all
the parties was „„change order‟‟. The researcher also found that about 70% of the projects experienced time
overruns.
1.1. Change in structure system
Primary design (Insulating concrete formwork system (ICF)) changed to Steel Frame structure system
(with steel joist roofing system)
In the Ghadir project, started the execution of some foundations, on 29th march 2010 with ICF method-
insulating concrete formwork-by the contractor (Tak-Ista).
But the main contractor-HESACO-halted the work and changed the plan from ICF to steel structure
The significant Causes and effects of delays in Ghadir 2206 residential project
www.iosrjournals.org 77 | Page
Figure 1-primery typical ICF drawings of Ghadir 2206 residential project
Since the written permission for the various changes were not obtained from the government, they were
carried out based on oral discussion with competent authorities.
Because of these changes, the contract between HESACO and contractor (Tak-Ista) revoked whereas they
had already done mobilization. All drawings also had to change, causing delays and problems.
Furthermore, seven foundation of hat type (ICF) had been done and they had to be changed and retrofitted
for new design. (Figure 1)
1.2. Change in the type of supports
The sub-contractor of steel structure‟s execution, with the coordination and approval of the main
contractor changed the type of supports for faster installation.(figure 2 and 3)
Figure 2 - sample supports of the beams
Figure 3 -executed supports of beams.
The executed supports were, fixed support; whereas most of those designed, were hinged support.
Supervisors of the project‟s structure, rejected the work, and sent a non-conformance report to the client.
Structural designer ordered that new connections must completely be fixed and two ends of beam must be
changed to hinged support (as per design).
The significant Causes and effects of delays in Ghadir 2206 residential project
www.iosrjournals.org 78 | Page
Many beams and columns had been made in wrong shape and company spent a lot of time to correct
and rectify the problems.
To do the changed work, at least four plates were required and a large number of labours were added to
each beam. Because of this, the project got affected in terms of economy and time.
1.3. Change in foundation execution level
Use of pedestal;
Regardless of the designer‟s idea, contractor‟s project manager decided to break the height differences
in implementation of foundations by two-levels. This decision caused the following:
 The volume of excavation reduced.
 Increase in speed
 Achieved lower cost
Figure 4 – A two-levels foundation
The Level differences in foundations created disputes between the structural designer and the
contractor; the designer did not accept changes in foundations without new calculations. This dispute also arose
with the employer and the employer convened some meetings on the employer's office and on-site. Finally,
designer did not accept the situation to continue the work, refused to accept responsibility, refused to continue
with the process, and finally canceled his contract with contractor.
The Contractor negotiated with another designer and he accepted to prepare a corrective structural
design. This design took a significant time of the project.
Finally, the new designer agreed with the composition of same foundations with metal pedestals. Three
different types of pedestals (0cm to 50cm and from 50cm to 100cm and from 100cm to 150cm and relevant
reinforcement around each pedestal filled with concrete). Moreover, the specific reinforced concrete wall around
the elevator's foundation made around the foundations and framed. (Figure 5a, 5b, 5c)
Figure 5a-Special concrete wall around the lift foundation
In approximately all foundations, a large amount of time and cost incurred because of improper level
due to a steep slope. These included:
 Drilling time and costs for installation of reinforcements
 Special adhesive reinforcement installation costs
 Reinforcement costs
 Formworking costs
 Additional cost of concreting
 Overhead costs, and the like
The significant Causes and effects of delays in Ghadir 2206 residential project
www.iosrjournals.org 79 | Page
Figure 5b -Steel pedestals
Figure 5c -Many pedestals
The corrective drawings got ready when a large number of structural columns were prepared and how
to install a column on pedestal was another problem. The designer‟s idea was that the pedestal should be built in
the factory and carried to project site, then by controlled welding should install the pedestal on base plates and
in the next step, by using bolts and nuts, place the column on the pedestal.
This work involved using three base plates instead of one base plate (figure 6).
This decision resulted in increased time and cost.
Figure7 – A pedestal before pouring concrete
The total Extra steel that was used for pedestals is more than 200 tonnes.
The total extra steel that was used for beam correction is about 20 tonnes.
The total extra steel that used for span correction in the new method of roofing system resulted in 495
tones. The total time that got delayed in this part of the work was more than 6 months.
IV. Material price escalation
America's sanctions against Iran‟s nuclear power had led to a decrease in the value of national
currency.
Not only this project but also most of the other projects that had a fixed price contract (in private and
public sectors) were affected of this cause.
Price of steel and other material and production facilities increased as well as foreign currency rates.
The significant Causes and effects of delays in Ghadir 2206 residential project
www.iosrjournals.org 80 | Page
Figure 17-Diagram of the currency rate changes during one year
Senior managers believe the increased prices of all materials that are using in construction works have
big losses, COE of HESACO believes: if they wish to continue the project, at least 50% of the total contract
cost is wasteful.
The contractor did not work anymore and contract revoked.
The real price on the time of revocation should be equal to240 USD means ≈
(3500/1100)*240=7,640,000 IRR/sqm) means about 3.18 time more than the time of agreement.
Effect of delay on project:
Identification of causes and effects alone do not help the project managers to take appropriate remedial
or preventive reaction. The project managers need to understand, what factors result in time overrun or cost
overrun. When these factors become clear, the managers can take proactive steps to avoid such situations. For
example, if it is known that time overruns are predominantly caused by any force majeure or contractor related
factors, the project manager can: (1) make sure that payments for the completed work are paid on time, (2)
reduce owner interference, (3) speed up the decision-making process, and (4) avoid unrealistic contract duration
and requirements. Therefore, the link between causes and effects of delays need to be established.
In case of delay common effects are (1) time overrun, (2) cost overrun, (3) disputes, (4) arbitration, (5)
litigation, and (6) total abandonment
Prescription to reduce delay:
1. In case of design changes, contractors must study all the drawings Very carefully before doing
anything.
2. If contractor started the work and faced with wrong in drawings, must immediately inform the
consultant engineer and client for start to correct the designs and contractor should consider the delay
time in project schedule.
3. Sanction and unbelievable price escalation in fixed price contracts can be considered as a force majeure
situation.
V. Conclusions
This paper investigated the causes and effects of delays facing in the Ghadir 2206 residential units.
Based on Field research collected the information and I identified main causes of delay and ten most important
causes were:
1) Contractor‟s improper planning, 2) Design changes, 3) Contractor‟s poor site management and
mistaken decision in change managers, 4) Inadequate contractor experience, 5) Inadequate client‟s finance and
payments for completed work, 6) Problems with subcontractors, 7) Lack of communication between parties, 8)
Construction Mistakes and Defective Works ,9) Sanction.
I identified main effects of delay and they were: (1) time overrun, (2) cost overrun, (3) disputes, (4)
arbitration, (5) litigation, and (6) total abandonment.
Researcher believes that the results of this study can be of immense help to the related parts (clients,
contractors, and consultants) in future projects and academicians. The practitioners can better understand the
dynamics of project management and make efforts to reduce the incidences of delays. The academicians can
conduct similar studies in other parts of world and identify causes and effects of delays. As mentioned earlier,
some causes and effects may be unique to certain countries.
The significant Causes and effects of delays in Ghadir 2206 residential project
www.iosrjournals.org 81 | Page
References
[1]. Agyakwah-Baah, Frank D.K. Fugar and Adwoa B. "Delays in Building Construction Projects in Ghana." Australasian Journal of
Construction Economics and Building, (2010)10 (1/2): 103-116.
[2]. Andersson; Claes-Axel;et al. Site management handbook. Geneva: International Labour Office, 1996.
[3]. Assaf, S.A. AlHejji S. "Causes of delay in large construction projects." International Journal of Project Management, , (2006)24 (4):
349-357.
[4]. Murali Sambasivan, Yau Wen Soon. "Causes and effects of delays in Malaysian construction industry." International Journal of
Project Management, (2007) 27: 517-526.
[5]. Sweis, G., Sweis, R., Abu Hammad, A. and Shboul, A. "Delays in construction projects: The case of Jordan." International Journal
of Project Management , (2008)26 (6): 65-74.
[6]. T, Barry B. Bramble and Michael. Construction Delay Claims. Wolters Kluwer Law & Business, 2010.
[7]. Z, Prosci. web page:Change Management Pilot Professional. http://www.change-management.com/cm-pilot.htm.
[8]. Ziabari, Kourosh. web page:Iran Hyperinflation. http://www.marketoracle.co.uk/Article37225.html.
[9]. websit of municipality, Fooladshahr. web page :about Fooladshahr. http://www.fooladshahr.ir/web/fooladshahren/fooladshahr

More Related Content

What's hot

Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Charles Abraham Scheck
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...IJERA Editor
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET Journal
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Managementijsrd.com
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsTwana Ahmad
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Sankalp Swarnkar
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...IJMER
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...iosrjce
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libreUTHM
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSIAEME Publication
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...World-Academic Journal
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of timeJoseph Sangpang
 
IJSRED-V2I3P74
IJSRED-V2I3P74IJSRED-V2I3P74
IJSRED-V2I3P74IJSRED
 
A Study in Construction Delays of Residential Structures
A Study in Construction Delays of Residential StructuresA Study in Construction Delays of Residential Structures
A Study in Construction Delays of Residential StructuresIRJESJOURNAL
 
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )Engr_Emad Khan
 
IRJET - Delay Analysis of a Construction Project- A Case Study
IRJET - Delay Analysis of a Construction Project- A Case StudyIRJET - Delay Analysis of a Construction Project- A Case Study
IRJET - Delay Analysis of a Construction Project- A Case StudyIRJET Journal
 

What's hot (19)

Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libre
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
 
Risk management
Risk managementRisk management
Risk management
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 
D012522433
D012522433D012522433
D012522433
 
IJSRED-V2I3P74
IJSRED-V2I3P74IJSRED-V2I3P74
IJSRED-V2I3P74
 
A Study in Construction Delays of Residential Structures
A Study in Construction Delays of Residential StructuresA Study in Construction Delays of Residential Structures
A Study in Construction Delays of Residential Structures
 
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
 
IRJET - Delay Analysis of a Construction Project- A Case Study
IRJET - Delay Analysis of a Construction Project- A Case StudyIRJET - Delay Analysis of a Construction Project- A Case Study
IRJET - Delay Analysis of a Construction Project- A Case Study
 

Viewers also liked

Evaluation of Radiation Emmission from Refuse Dump Sites in Owerri, Nigeria
Evaluation of Radiation Emmission from Refuse Dump Sites in Owerri, NigeriaEvaluation of Radiation Emmission from Refuse Dump Sites in Owerri, Nigeria
Evaluation of Radiation Emmission from Refuse Dump Sites in Owerri, NigeriaIOSR Journals
 
Hydrochemistry of groundwater with special reference to arsenic in Lakhimpur ...
Hydrochemistry of groundwater with special reference to arsenic in Lakhimpur ...Hydrochemistry of groundwater with special reference to arsenic in Lakhimpur ...
Hydrochemistry of groundwater with special reference to arsenic in Lakhimpur ...IOSR Journals
 
Structural, Dielectric and Optical properties of Sputtered TiO2 nano-films
Structural, Dielectric and Optical properties of Sputtered TiO2 nano-filmsStructural, Dielectric and Optical properties of Sputtered TiO2 nano-films
Structural, Dielectric and Optical properties of Sputtered TiO2 nano-filmsIOSR Journals
 
Awareness of Orthodontic Treatment in School Children of Karnataka State – A ...
Awareness of Orthodontic Treatment in School Children of Karnataka State – A ...Awareness of Orthodontic Treatment in School Children of Karnataka State – A ...
Awareness of Orthodontic Treatment in School Children of Karnataka State – A ...IOSR Journals
 
Cationic and anionic dye adsorption by agricultural solid wastes: A comprehen...
Cationic and anionic dye adsorption by agricultural solid wastes: A comprehen...Cationic and anionic dye adsorption by agricultural solid wastes: A comprehen...
Cationic and anionic dye adsorption by agricultural solid wastes: A comprehen...IOSR Journals
 
Synthesis, spectroscopic, electrochemical, magnetic properties and super oxid...
Synthesis, spectroscopic, electrochemical, magnetic properties and super oxid...Synthesis, spectroscopic, electrochemical, magnetic properties and super oxid...
Synthesis, spectroscopic, electrochemical, magnetic properties and super oxid...IOSR Journals
 
Discovery of superluminal velocities of X-rays and Bharat Radiation challengi...
Discovery of superluminal velocities of X-rays and Bharat Radiation challengi...Discovery of superluminal velocities of X-rays and Bharat Radiation challengi...
Discovery of superluminal velocities of X-rays and Bharat Radiation challengi...IOSR Journals
 
Modeling & Analysis of Centrifugal Blower using Composite Material
Modeling & Analysis of Centrifugal Blower using Composite MaterialModeling & Analysis of Centrifugal Blower using Composite Material
Modeling & Analysis of Centrifugal Blower using Composite MaterialIOSR Journals
 
Effect of Spiritual Intelligence and Asta Brata Leadership to the Culture of ...
Effect of Spiritual Intelligence and Asta Brata Leadership to the Culture of ...Effect of Spiritual Intelligence and Asta Brata Leadership to the Culture of ...
Effect of Spiritual Intelligence and Asta Brata Leadership to the Culture of ...IOSR Journals
 
Stock Selection Skills of Indian Mutual Fund Managers during 2000-2012
Stock Selection Skills of Indian Mutual Fund Managers during 2000-2012Stock Selection Skills of Indian Mutual Fund Managers during 2000-2012
Stock Selection Skills of Indian Mutual Fund Managers during 2000-2012IOSR Journals
 
Investigation of the Anodic Dissolution of Zinc in Sodium Chloride Electrolyt...
Investigation of the Anodic Dissolution of Zinc in Sodium Chloride Electrolyt...Investigation of the Anodic Dissolution of Zinc in Sodium Chloride Electrolyt...
Investigation of the Anodic Dissolution of Zinc in Sodium Chloride Electrolyt...IOSR Journals
 
Role of mixed ligand Pd(II) and Pt(II)complexes in photooxygenation reaction
Role of mixed ligand Pd(II) and Pt(II)complexes in photooxygenation reactionRole of mixed ligand Pd(II) and Pt(II)complexes in photooxygenation reaction
Role of mixed ligand Pd(II) and Pt(II)complexes in photooxygenation reactionIOSR Journals
 
Distortion Analysis of Differential Amplifier
Distortion Analysis of Differential AmplifierDistortion Analysis of Differential Amplifier
Distortion Analysis of Differential AmplifierIOSR Journals
 
Insulin like growth factor and risk of breast cancer
Insulin like growth factor and risk of breast cancerInsulin like growth factor and risk of breast cancer
Insulin like growth factor and risk of breast cancerIOSR Journals
 
Preliminary Assessment of Physicochemical Properties of Borehole Water in the...
Preliminary Assessment of Physicochemical Properties of Borehole Water in the...Preliminary Assessment of Physicochemical Properties of Borehole Water in the...
Preliminary Assessment of Physicochemical Properties of Borehole Water in the...IOSR Journals
 
Enhancement of Specific Power Output of a Gas Turbine Using Filtered Chilled Air
Enhancement of Specific Power Output of a Gas Turbine Using Filtered Chilled AirEnhancement of Specific Power Output of a Gas Turbine Using Filtered Chilled Air
Enhancement of Specific Power Output of a Gas Turbine Using Filtered Chilled AirIOSR Journals
 
Experimental investigation on buckling of GFRP cylindrical shells subjected t...
Experimental investigation on buckling of GFRP cylindrical shells subjected t...Experimental investigation on buckling of GFRP cylindrical shells subjected t...
Experimental investigation on buckling of GFRP cylindrical shells subjected t...IOSR Journals
 
Dynamics of Twointeracting Electronsinthree-Dimensional Lattice
Dynamics of Twointeracting Electronsinthree-Dimensional LatticeDynamics of Twointeracting Electronsinthree-Dimensional Lattice
Dynamics of Twointeracting Electronsinthree-Dimensional LatticeIOSR Journals
 
High Performance Temperature Insensitive Current Mode Rectifier without Diode
High Performance Temperature Insensitive Current Mode Rectifier without DiodeHigh Performance Temperature Insensitive Current Mode Rectifier without Diode
High Performance Temperature Insensitive Current Mode Rectifier without DiodeIOSR Journals
 
Simulation of N2 Gas Separation Process from Air
Simulation of N2 Gas Separation Process from AirSimulation of N2 Gas Separation Process from Air
Simulation of N2 Gas Separation Process from AirIOSR Journals
 

Viewers also liked (20)

Evaluation of Radiation Emmission from Refuse Dump Sites in Owerri, Nigeria
Evaluation of Radiation Emmission from Refuse Dump Sites in Owerri, NigeriaEvaluation of Radiation Emmission from Refuse Dump Sites in Owerri, Nigeria
Evaluation of Radiation Emmission from Refuse Dump Sites in Owerri, Nigeria
 
Hydrochemistry of groundwater with special reference to arsenic in Lakhimpur ...
Hydrochemistry of groundwater with special reference to arsenic in Lakhimpur ...Hydrochemistry of groundwater with special reference to arsenic in Lakhimpur ...
Hydrochemistry of groundwater with special reference to arsenic in Lakhimpur ...
 
Structural, Dielectric and Optical properties of Sputtered TiO2 nano-films
Structural, Dielectric and Optical properties of Sputtered TiO2 nano-filmsStructural, Dielectric and Optical properties of Sputtered TiO2 nano-films
Structural, Dielectric and Optical properties of Sputtered TiO2 nano-films
 
Awareness of Orthodontic Treatment in School Children of Karnataka State – A ...
Awareness of Orthodontic Treatment in School Children of Karnataka State – A ...Awareness of Orthodontic Treatment in School Children of Karnataka State – A ...
Awareness of Orthodontic Treatment in School Children of Karnataka State – A ...
 
Cationic and anionic dye adsorption by agricultural solid wastes: A comprehen...
Cationic and anionic dye adsorption by agricultural solid wastes: A comprehen...Cationic and anionic dye adsorption by agricultural solid wastes: A comprehen...
Cationic and anionic dye adsorption by agricultural solid wastes: A comprehen...
 
Synthesis, spectroscopic, electrochemical, magnetic properties and super oxid...
Synthesis, spectroscopic, electrochemical, magnetic properties and super oxid...Synthesis, spectroscopic, electrochemical, magnetic properties and super oxid...
Synthesis, spectroscopic, electrochemical, magnetic properties and super oxid...
 
Discovery of superluminal velocities of X-rays and Bharat Radiation challengi...
Discovery of superluminal velocities of X-rays and Bharat Radiation challengi...Discovery of superluminal velocities of X-rays and Bharat Radiation challengi...
Discovery of superluminal velocities of X-rays and Bharat Radiation challengi...
 
Modeling & Analysis of Centrifugal Blower using Composite Material
Modeling & Analysis of Centrifugal Blower using Composite MaterialModeling & Analysis of Centrifugal Blower using Composite Material
Modeling & Analysis of Centrifugal Blower using Composite Material
 
Effect of Spiritual Intelligence and Asta Brata Leadership to the Culture of ...
Effect of Spiritual Intelligence and Asta Brata Leadership to the Culture of ...Effect of Spiritual Intelligence and Asta Brata Leadership to the Culture of ...
Effect of Spiritual Intelligence and Asta Brata Leadership to the Culture of ...
 
Stock Selection Skills of Indian Mutual Fund Managers during 2000-2012
Stock Selection Skills of Indian Mutual Fund Managers during 2000-2012Stock Selection Skills of Indian Mutual Fund Managers during 2000-2012
Stock Selection Skills of Indian Mutual Fund Managers during 2000-2012
 
Investigation of the Anodic Dissolution of Zinc in Sodium Chloride Electrolyt...
Investigation of the Anodic Dissolution of Zinc in Sodium Chloride Electrolyt...Investigation of the Anodic Dissolution of Zinc in Sodium Chloride Electrolyt...
Investigation of the Anodic Dissolution of Zinc in Sodium Chloride Electrolyt...
 
Role of mixed ligand Pd(II) and Pt(II)complexes in photooxygenation reaction
Role of mixed ligand Pd(II) and Pt(II)complexes in photooxygenation reactionRole of mixed ligand Pd(II) and Pt(II)complexes in photooxygenation reaction
Role of mixed ligand Pd(II) and Pt(II)complexes in photooxygenation reaction
 
Distortion Analysis of Differential Amplifier
Distortion Analysis of Differential AmplifierDistortion Analysis of Differential Amplifier
Distortion Analysis of Differential Amplifier
 
Insulin like growth factor and risk of breast cancer
Insulin like growth factor and risk of breast cancerInsulin like growth factor and risk of breast cancer
Insulin like growth factor and risk of breast cancer
 
Preliminary Assessment of Physicochemical Properties of Borehole Water in the...
Preliminary Assessment of Physicochemical Properties of Borehole Water in the...Preliminary Assessment of Physicochemical Properties of Borehole Water in the...
Preliminary Assessment of Physicochemical Properties of Borehole Water in the...
 
Enhancement of Specific Power Output of a Gas Turbine Using Filtered Chilled Air
Enhancement of Specific Power Output of a Gas Turbine Using Filtered Chilled AirEnhancement of Specific Power Output of a Gas Turbine Using Filtered Chilled Air
Enhancement of Specific Power Output of a Gas Turbine Using Filtered Chilled Air
 
Experimental investigation on buckling of GFRP cylindrical shells subjected t...
Experimental investigation on buckling of GFRP cylindrical shells subjected t...Experimental investigation on buckling of GFRP cylindrical shells subjected t...
Experimental investigation on buckling of GFRP cylindrical shells subjected t...
 
Dynamics of Twointeracting Electronsinthree-Dimensional Lattice
Dynamics of Twointeracting Electronsinthree-Dimensional LatticeDynamics of Twointeracting Electronsinthree-Dimensional Lattice
Dynamics of Twointeracting Electronsinthree-Dimensional Lattice
 
High Performance Temperature Insensitive Current Mode Rectifier without Diode
High Performance Temperature Insensitive Current Mode Rectifier without DiodeHigh Performance Temperature Insensitive Current Mode Rectifier without Diode
High Performance Temperature Insensitive Current Mode Rectifier without Diode
 
Simulation of N2 Gas Separation Process from Air
Simulation of N2 Gas Separation Process from AirSimulation of N2 Gas Separation Process from Air
Simulation of N2 Gas Separation Process from Air
 

Similar to The significant Causes and effects of delays in Ghadir 2206 residential project

A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsRick Vogel
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A ReviewIRJET Journal
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delayEst
 
(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 Sigma(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 SigmaDimitrios Kordas
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsDr. Amarjeet Singh
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...IRJET Journal
 
A Study for the Causes of Variation Orders in Different Sectors of Constructi...
A Study for the Causes of Variation Orders in Different Sectors of Constructi...A Study for the Causes of Variation Orders in Different Sectors of Constructi...
A Study for the Causes of Variation Orders in Different Sectors of Constructi...Sarah Adams
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTIRJET Journal
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectseSAT Journals
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectseSAT Journals
 
Analysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims inAnalysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims ineSAT Publishing House
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET Journal
 
Delay Analysis in Construction of Redevelopment Residential Project
Delay Analysis in Construction of Redevelopment Residential ProjectDelay Analysis in Construction of Redevelopment Residential Project
Delay Analysis in Construction of Redevelopment Residential ProjectIRJET Journal
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsIRJET Journal
 

Similar to The significant Causes and effects of delays in Ghadir 2206 residential project (20)

A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
B012140812
B012140812B012140812
B012140812
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delay
 
(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 Sigma(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 Sigma
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
 
A Study for the Causes of Variation Orders in Different Sectors of Constructi...
A Study for the Causes of Variation Orders in Different Sectors of Constructi...A Study for the Causes of Variation Orders in Different Sectors of Constructi...
A Study for the Causes of Variation Orders in Different Sectors of Constructi...
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projects
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projects
 
Analysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims inAnalysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims in
 
I012646171
I012646171I012646171
I012646171
 
I012646171
I012646171I012646171
I012646171
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
 
Delay Analysis in Construction of Redevelopment Residential Project
Delay Analysis in Construction of Redevelopment Residential ProjectDelay Analysis in Construction of Redevelopment Residential Project
Delay Analysis in Construction of Redevelopment Residential Project
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
 

More from IOSR Journals (20)

A011140104
A011140104A011140104
A011140104
 
M0111397100
M0111397100M0111397100
M0111397100
 
L011138596
L011138596L011138596
L011138596
 
K011138084
K011138084K011138084
K011138084
 
J011137479
J011137479J011137479
J011137479
 
I011136673
I011136673I011136673
I011136673
 
G011134454
G011134454G011134454
G011134454
 
H011135565
H011135565H011135565
H011135565
 
F011134043
F011134043F011134043
F011134043
 
E011133639
E011133639E011133639
E011133639
 
D011132635
D011132635D011132635
D011132635
 
C011131925
C011131925C011131925
C011131925
 
B011130918
B011130918B011130918
B011130918
 
A011130108
A011130108A011130108
A011130108
 
I011125160
I011125160I011125160
I011125160
 
H011124050
H011124050H011124050
H011124050
 
G011123539
G011123539G011123539
G011123539
 
F011123134
F011123134F011123134
F011123134
 
E011122530
E011122530E011122530
E011122530
 
D011121524
D011121524D011121524
D011121524
 

Recently uploaded

CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 

Recently uploaded (20)

CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 

The significant Causes and effects of delays in Ghadir 2206 residential project

  • 1. IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 7, Issue 4 (Jul. - Aug. 2013), PP 75-81 www.iosrjournals.org www.iosrjournals.org 75 | Page The significant Causes and effects of delays in Ghadir 2206 residential project 1 Ebrahim Aboutorabi Najafabadi, 2 Prof. Dr. S. S. Pimplikar, 1 Research Graduate ME (Construction & Management) 2 Professor & Head-Civil Department MIT- Pune Abstract: Delays in the construction projects are global events and the construction industry in Iran is no exception. The main purpose of this study is to identify the delay factors and their effect on a particular project completion named Ghadir 2206 residential construction project located in Fooladshahr, Iran. It is attempted to analyze the most important causes and their impacts on specific effects. This study identified nine most important causes of delay and effects of delay. Nine most important causes were: 1) Contractor’s improper planning, 2) Design changes, 3) Contractor’s poor site management and mistaken decision in changing managers, 4) Inadequate contractor experience, 5) Inadequate client’s finance and payments for completed work, 6) Problems with subcontractors, 7) Lack of communication between parties, 8) Construction mistakes and defective works ,9) Material price escalation. The causes categories in contractor- related factors, consultant-related factors, client-related factors and external factors. The high significant causes identified are 1) Design changes 2) Material price escalation Six main effects of delay were: 1) Time overrun 2) Cost overrun, 3) Disputes, 4) Arbitration, 5) Litigation, and 6) Abandonment Keywords: Delay causes; Delay effects; Construction industry; Iran; Ghadir 2206 residential project; I. Introduction Delays are insidious often resulting in time overrun, cost overrun, disputes, litigation, and complete abandonment of projects (Sambasivan and Soon, 2007). Many projects are of such a nature that the client will suffer hardship, expense, or loss of revenue if the work is delayed beyond the time specified in the contract (Clough, 1986). Then again, delay has cost consequences for the contractor. Delay is a reality in the construction process in the world. Although there may be unique aspects of the different projects, sites, contract terms and customs and practices in different parts of the world, for the most part the reality of delay unfortunately is universal to the construction industry. In construction claims, the term “delay” is used to mean two different but related matters. Delay is often used to mean the time period during which some part of the construction project has been extended beyond what was originally planned due to unanticipated circumstances. Extension beyond what was initially planned may also be called prolongation. Delay can also be the incident that affects the performance of a particular activity, with or without affecting project completion. This concept of postponement occurs when the planned start of an activity or project is delayed. An incident delay can originate from within the contractor's organization or from any of the other factors interacting with the construction project. Incidences of delay from within the contractor's organization are essentially those occurrences that the contractor himself has caused or for which he is legally responsible. Incidences outside of the contractor's organization may be caused by the owner (or employer) the designer, other prime contractors, subcontractors, suppliers, labor unions, nature, or any of a number of other organizations and entities that participate in the construction process. Many events may occur on the construction project to increase the time of performance of the overall project or affect any given activity. The most common causes of delay are contractor management and performance problems; differing site conditions; changes in requirements or design; inclement weather; unavailability of labor, material, or equipment; defective plans and specifications; and owner interference. These and other delays not only increase the time required to perform the contract work but may also increase the costs for many of the parties involved. The present study focuses on the following objectives: (i) Identify factors that significantly contributed to time and costs overruns in Ghadir project; (ii) Establish the relative importance of these factors; (iii) Quantify the time and costs associated with the significant factors. (iv) Finding the solution to decrease delays
  • 2. The significant Causes and effects of delays in Ghadir 2206 residential project www.iosrjournals.org 76 | Page II. Methodology Used Field research based on the author's observations, interviews, formal correspondence, photos, project scheduling, and interview with experienced people, study of the drawings and plans, and the author‟s perceptions of project management requirements, examined popular causes of delay in this project. Ghadir project: The project is inclusive of 2206 residential units with about 222000-sqm floor area, which should be handed over in about 24 months excluding landscaping. The type of contract was fixed price (2650000 IRR/sqm on the time of agreement≈240USD/sqm) The site location (32° 31' 50.26"N, 51° 20' 35.96"E) is in Fooladshahr, the new town of Fooladshahr at the central part of Lenjan city, 25 kilometers from the south-west of Isfahan, is located in the communication axis of Isfahan and Shahrecord. The area of this town is over 7700 hectares. Fooladshahr was established for the residence of Zobe-ahan staff in 1963 and it started its activities from 1984 as a new town. More than 85000 people live in this town at present. Because of its nearness to the center of the province with an easy access to great industries such as Zobe-ahan, Foolad Mobarakeh, and Sepahan Cement factory, this town is diverted into a suitable location for residence. Other living advantages of this new town are its nearness to higher educational centers such as Isfahan University of Technology, Isfahan University, and Najafabad Azad University. The general information of Ghadir project is shown in table Blocktype No.of blocks Numberof Stories Numberof units No.ofunits insametype Numberof roofs Liftand staircase’s area(m²) Lobby’s area(m²) Parking’s area(m²) Block’sarea (m²) non-useful Areaof everytype (m²) UsefulArea ofevery type(m²) Totalarea ofevery type(m²) A 43 4 18 774 5 161.05 41.2 106.7 1750 13284 61966 75250 B 12 4 26 312 5 388 78.1 194.67 2710 7929.7 24590 32520 C 14 5 22 308 6 132.6 32.9 362.58 2338 7393.1 25339 32732 D 4 5 27 108 6 260.4 15.3 421.23 2952 2787.6 9020 11808 E 8 6 38 304 7 456.96 72.3 235.27 3780 6116.6 24123 30240 E-1 2 8 50 100 9 587.52 72.3 235.27 4860 1790.3 7930 9720 F 2 4 18 36 5 155 19.7 319.5 1820 988.34 4472 5460 F-1 12 5 22 264 6 186 19.7 319.5 2186 6302 17744 24046 Tota l 97 ---------- 2206 --- 2327.5 352 2194.7 22396 46592 17518 4 221776 Table 1-General information of Ghadir project residential units III. Studies on significant causes of delay 1. Design changes: Design changes and delays in design approval have caused delay to the project. A number of studies have been carried out to determine the causes of delay in construction projects. Sweis et al. (2008) studied the causes of delay in residential projects in Jordan and concluded that financial difficulties faced by the contractor and too many change orders by the owner are the leading causes of construction delay. Assaf and Al-Hejji [6] conducted a survey on time performance of large construction projects in Saudi Arabia. The survey had 73 different causes of delay. The researcher studied the importance of various causes from the viewpoint of contractors, consultants, and owners. The most common cause of delay identified by all the parties was „„change order‟‟. The researcher also found that about 70% of the projects experienced time overruns. 1.1. Change in structure system Primary design (Insulating concrete formwork system (ICF)) changed to Steel Frame structure system (with steel joist roofing system) In the Ghadir project, started the execution of some foundations, on 29th march 2010 with ICF method- insulating concrete formwork-by the contractor (Tak-Ista). But the main contractor-HESACO-halted the work and changed the plan from ICF to steel structure
  • 3. The significant Causes and effects of delays in Ghadir 2206 residential project www.iosrjournals.org 77 | Page Figure 1-primery typical ICF drawings of Ghadir 2206 residential project Since the written permission for the various changes were not obtained from the government, they were carried out based on oral discussion with competent authorities. Because of these changes, the contract between HESACO and contractor (Tak-Ista) revoked whereas they had already done mobilization. All drawings also had to change, causing delays and problems. Furthermore, seven foundation of hat type (ICF) had been done and they had to be changed and retrofitted for new design. (Figure 1) 1.2. Change in the type of supports The sub-contractor of steel structure‟s execution, with the coordination and approval of the main contractor changed the type of supports for faster installation.(figure 2 and 3) Figure 2 - sample supports of the beams Figure 3 -executed supports of beams. The executed supports were, fixed support; whereas most of those designed, were hinged support. Supervisors of the project‟s structure, rejected the work, and sent a non-conformance report to the client. Structural designer ordered that new connections must completely be fixed and two ends of beam must be changed to hinged support (as per design).
  • 4. The significant Causes and effects of delays in Ghadir 2206 residential project www.iosrjournals.org 78 | Page Many beams and columns had been made in wrong shape and company spent a lot of time to correct and rectify the problems. To do the changed work, at least four plates were required and a large number of labours were added to each beam. Because of this, the project got affected in terms of economy and time. 1.3. Change in foundation execution level Use of pedestal; Regardless of the designer‟s idea, contractor‟s project manager decided to break the height differences in implementation of foundations by two-levels. This decision caused the following:  The volume of excavation reduced.  Increase in speed  Achieved lower cost Figure 4 – A two-levels foundation The Level differences in foundations created disputes between the structural designer and the contractor; the designer did not accept changes in foundations without new calculations. This dispute also arose with the employer and the employer convened some meetings on the employer's office and on-site. Finally, designer did not accept the situation to continue the work, refused to accept responsibility, refused to continue with the process, and finally canceled his contract with contractor. The Contractor negotiated with another designer and he accepted to prepare a corrective structural design. This design took a significant time of the project. Finally, the new designer agreed with the composition of same foundations with metal pedestals. Three different types of pedestals (0cm to 50cm and from 50cm to 100cm and from 100cm to 150cm and relevant reinforcement around each pedestal filled with concrete). Moreover, the specific reinforced concrete wall around the elevator's foundation made around the foundations and framed. (Figure 5a, 5b, 5c) Figure 5a-Special concrete wall around the lift foundation In approximately all foundations, a large amount of time and cost incurred because of improper level due to a steep slope. These included:  Drilling time and costs for installation of reinforcements  Special adhesive reinforcement installation costs  Reinforcement costs  Formworking costs  Additional cost of concreting  Overhead costs, and the like
  • 5. The significant Causes and effects of delays in Ghadir 2206 residential project www.iosrjournals.org 79 | Page Figure 5b -Steel pedestals Figure 5c -Many pedestals The corrective drawings got ready when a large number of structural columns were prepared and how to install a column on pedestal was another problem. The designer‟s idea was that the pedestal should be built in the factory and carried to project site, then by controlled welding should install the pedestal on base plates and in the next step, by using bolts and nuts, place the column on the pedestal. This work involved using three base plates instead of one base plate (figure 6). This decision resulted in increased time and cost. Figure7 – A pedestal before pouring concrete The total Extra steel that was used for pedestals is more than 200 tonnes. The total extra steel that was used for beam correction is about 20 tonnes. The total extra steel that used for span correction in the new method of roofing system resulted in 495 tones. The total time that got delayed in this part of the work was more than 6 months. IV. Material price escalation America's sanctions against Iran‟s nuclear power had led to a decrease in the value of national currency. Not only this project but also most of the other projects that had a fixed price contract (in private and public sectors) were affected of this cause. Price of steel and other material and production facilities increased as well as foreign currency rates.
  • 6. The significant Causes and effects of delays in Ghadir 2206 residential project www.iosrjournals.org 80 | Page Figure 17-Diagram of the currency rate changes during one year Senior managers believe the increased prices of all materials that are using in construction works have big losses, COE of HESACO believes: if they wish to continue the project, at least 50% of the total contract cost is wasteful. The contractor did not work anymore and contract revoked. The real price on the time of revocation should be equal to240 USD means ≈ (3500/1100)*240=7,640,000 IRR/sqm) means about 3.18 time more than the time of agreement. Effect of delay on project: Identification of causes and effects alone do not help the project managers to take appropriate remedial or preventive reaction. The project managers need to understand, what factors result in time overrun or cost overrun. When these factors become clear, the managers can take proactive steps to avoid such situations. For example, if it is known that time overruns are predominantly caused by any force majeure or contractor related factors, the project manager can: (1) make sure that payments for the completed work are paid on time, (2) reduce owner interference, (3) speed up the decision-making process, and (4) avoid unrealistic contract duration and requirements. Therefore, the link between causes and effects of delays need to be established. In case of delay common effects are (1) time overrun, (2) cost overrun, (3) disputes, (4) arbitration, (5) litigation, and (6) total abandonment Prescription to reduce delay: 1. In case of design changes, contractors must study all the drawings Very carefully before doing anything. 2. If contractor started the work and faced with wrong in drawings, must immediately inform the consultant engineer and client for start to correct the designs and contractor should consider the delay time in project schedule. 3. Sanction and unbelievable price escalation in fixed price contracts can be considered as a force majeure situation. V. Conclusions This paper investigated the causes and effects of delays facing in the Ghadir 2206 residential units. Based on Field research collected the information and I identified main causes of delay and ten most important causes were: 1) Contractor‟s improper planning, 2) Design changes, 3) Contractor‟s poor site management and mistaken decision in change managers, 4) Inadequate contractor experience, 5) Inadequate client‟s finance and payments for completed work, 6) Problems with subcontractors, 7) Lack of communication between parties, 8) Construction Mistakes and Defective Works ,9) Sanction. I identified main effects of delay and they were: (1) time overrun, (2) cost overrun, (3) disputes, (4) arbitration, (5) litigation, and (6) total abandonment. Researcher believes that the results of this study can be of immense help to the related parts (clients, contractors, and consultants) in future projects and academicians. The practitioners can better understand the dynamics of project management and make efforts to reduce the incidences of delays. The academicians can conduct similar studies in other parts of world and identify causes and effects of delays. As mentioned earlier, some causes and effects may be unique to certain countries.
  • 7. The significant Causes and effects of delays in Ghadir 2206 residential project www.iosrjournals.org 81 | Page References [1]. Agyakwah-Baah, Frank D.K. Fugar and Adwoa B. "Delays in Building Construction Projects in Ghana." Australasian Journal of Construction Economics and Building, (2010)10 (1/2): 103-116. [2]. Andersson; Claes-Axel;et al. Site management handbook. Geneva: International Labour Office, 1996. [3]. Assaf, S.A. AlHejji S. "Causes of delay in large construction projects." International Journal of Project Management, , (2006)24 (4): 349-357. [4]. Murali Sambasivan, Yau Wen Soon. "Causes and effects of delays in Malaysian construction industry." International Journal of Project Management, (2007) 27: 517-526. [5]. Sweis, G., Sweis, R., Abu Hammad, A. and Shboul, A. "Delays in construction projects: The case of Jordan." International Journal of Project Management , (2008)26 (6): 65-74. [6]. T, Barry B. Bramble and Michael. Construction Delay Claims. Wolters Kluwer Law & Business, 2010. [7]. Z, Prosci. web page:Change Management Pilot Professional. http://www.change-management.com/cm-pilot.htm. [8]. Ziabari, Kourosh. web page:Iran Hyperinflation. http://www.marketoracle.co.uk/Article37225.html. [9]. websit of municipality, Fooladshahr. web page :about Fooladshahr. http://www.fooladshahr.ir/web/fooladshahren/fooladshahr