This document compares the Critical Path Method (CPM) and Monte Carlo simulation for project scheduling. CPM uses deterministic activity durations to calculate the critical path and project duration. Monte Carlo simulation incorporates uncertainty by using three time estimates per activity - optimistic, pessimistic, and most likely - represented as probability distributions. It runs thousands of simulations to determine the likely project duration based on random sampling from these distributions. The document reviews literature on applying Monte Carlo simulation in construction projects. It then describes a study that uses both CPM and Monte Carlo simulation on a real construction project to compare the results and evaluate Monte Carlo simulation's usefulness for the construction industry.
CPM and PERT are most commonly used methods for project management. There are some similarities and differences between PERT and CPM. PERT can be applied to any field requiring planned, controlled and integrated work efforts to accomplish defined objectives.
CPM and PERT are most commonly used methods for project management. There are some similarities and differences between PERT and CPM. PERT can be applied to any field requiring planned, controlled and integrated work efforts to accomplish defined objectives.
Resource levelling minimizes resource fluctuations by postpone the earliest start time (EST) of non-critical activities with corresponding floats. Float consumption for resource leveling may reduces the project completion probability. This paper presents a method to minimize the resource fluctuations with minimum impact of float consumption. A case study is presented to verify the validity and usability of the method.
Time Cost Trade off Optimization Using Harmony Search and Monte-Carlo Method Mohammad Lemar ZALMAİ
Project cost and project duration are main factors in construction management. In real-life projects, both the trade-off between the project cost and the Project completion time, and the uncertainty of the environment are considerable aspects for decision-makers. Moreover, in some projects, activity durations show their complexity with time-dependence as well as randomness. Time cost trade off problem have been solved by using vast of methods such as genetic algorithms, particle swarm optimization. Most of these studies considered deterministic project values and includes CPM calculations for fitness value calculation. However most of construction projects are stochastic processes. In this paper, a stochastic time–cost trade-off problem is introduced. This study takes into account that activity duration and cost are uncertain variables. this study differs from other studies that for each fitness value calculation. The proposed model is dealt with an intelligent algorithm combining stochastic simulation and Harmony search, where stochastic simulation technique is employed to estimate random functions and Harmony search is designed to search optimal schedules under different decision-making criteria. Beside this Monte Carlo simulation is made for fitness value calculation in order to make more realistic optimization. Finally, some numerical experiments are given to illustrate the algorithm effectiveness.
Production Planning and control: Forecasting techniques – causal and time series models, moving average,
exponential smoothing, trend and seasonality; aggregate production planning; master production scheduling; materials
requirement planning (MRP) and MRP‐II; routing, scheduling and priority dispatching, concept of JIT manufacturing
System.
Project Management: Project network analysis, CPM, PERT and Project crashing.
Program (Project) Evaluation and Review Technique (PERT): is a project management tool used to schedule, organize, and coordinate tasks within a project.
Crashing is the procedure by which project duration can be shorten up by expediting selective
activities with in the project. But it requires allocating more resources than usual to compress an activity’s
duration, which in turns increases the budget of that activity. So, crashing is basically a time-cost trade-off by
which specific deadline can be achieved. The traditional method of crashing only considers average activity
times for the calculation of the critical path, ignoring the stochastic nature of activity time. This report is written
to develop an algorithm for optimum crashing method to minimize the required cost while attaining a specified
completion time.
project management-cpm and pert methods for managersNaganna Chetty
A project is a one shot, time limited, goal directed, major undertaking, requiring the commitment of varied skills & resources.
A project:
Has a unique purpose.
Is temporary.
Is developed using progressive elaboration.
Requires resources, often from various areas.
Should have a primary customer or sponsor.
The project sponsor usually provides the direction and funding for the project.
Involves uncertainty.
Project managers work with project sponsors, project teams, and other people involved in projects to meet project goals.
Program: “A group of related projects managed in a coordinated way to obtain benefits and control not available from managing them individually.”
Program managers oversee programs and often act as bosses for project managers.
Project management is “the application of knowledge, skills, tools and techniques to project activities to meet project requirements.”
Resource levelling minimizes resource fluctuations by postpone the earliest start time (EST) of non-critical activities with corresponding floats. Float consumption for resource leveling may reduces the project completion probability. This paper presents a method to minimize the resource fluctuations with minimum impact of float consumption. A case study is presented to verify the validity and usability of the method.
Time Cost Trade off Optimization Using Harmony Search and Monte-Carlo Method Mohammad Lemar ZALMAİ
Project cost and project duration are main factors in construction management. In real-life projects, both the trade-off between the project cost and the Project completion time, and the uncertainty of the environment are considerable aspects for decision-makers. Moreover, in some projects, activity durations show their complexity with time-dependence as well as randomness. Time cost trade off problem have been solved by using vast of methods such as genetic algorithms, particle swarm optimization. Most of these studies considered deterministic project values and includes CPM calculations for fitness value calculation. However most of construction projects are stochastic processes. In this paper, a stochastic time–cost trade-off problem is introduced. This study takes into account that activity duration and cost are uncertain variables. this study differs from other studies that for each fitness value calculation. The proposed model is dealt with an intelligent algorithm combining stochastic simulation and Harmony search, where stochastic simulation technique is employed to estimate random functions and Harmony search is designed to search optimal schedules under different decision-making criteria. Beside this Monte Carlo simulation is made for fitness value calculation in order to make more realistic optimization. Finally, some numerical experiments are given to illustrate the algorithm effectiveness.
Production Planning and control: Forecasting techniques – causal and time series models, moving average,
exponential smoothing, trend and seasonality; aggregate production planning; master production scheduling; materials
requirement planning (MRP) and MRP‐II; routing, scheduling and priority dispatching, concept of JIT manufacturing
System.
Project Management: Project network analysis, CPM, PERT and Project crashing.
Program (Project) Evaluation and Review Technique (PERT): is a project management tool used to schedule, organize, and coordinate tasks within a project.
Crashing is the procedure by which project duration can be shorten up by expediting selective
activities with in the project. But it requires allocating more resources than usual to compress an activity’s
duration, which in turns increases the budget of that activity. So, crashing is basically a time-cost trade-off by
which specific deadline can be achieved. The traditional method of crashing only considers average activity
times for the calculation of the critical path, ignoring the stochastic nature of activity time. This report is written
to develop an algorithm for optimum crashing method to minimize the required cost while attaining a specified
completion time.
project management-cpm and pert methods for managersNaganna Chetty
A project is a one shot, time limited, goal directed, major undertaking, requiring the commitment of varied skills & resources.
A project:
Has a unique purpose.
Is temporary.
Is developed using progressive elaboration.
Requires resources, often from various areas.
Should have a primary customer or sponsor.
The project sponsor usually provides the direction and funding for the project.
Involves uncertainty.
Project managers work with project sponsors, project teams, and other people involved in projects to meet project goals.
Program: “A group of related projects managed in a coordinated way to obtain benefits and control not available from managing them individually.”
Program managers oversee programs and often act as bosses for project managers.
Project management is “the application of knowledge, skills, tools and techniques to project activities to meet project requirements.”
Overview1) Overview – The continued discussion of .docxalfred4lewis58146
Overview
1)
Overview – The continued discussion of project implementation by covering various scheduling techniques.
2) Background – Per the text, “A schedule is the conversion of a project action plan into an operating timetable.” A schedule is important because each project is unique in its own way. The basic process is to identify all tasks and sequential relationships between them, that is, which tasks must precede or succeed others. There are a number of benefits to the creation and use of these networks. Some of them are as follows:
a) It is a consistent framework for planning, scheduling, and controlling the project.
b) It can be used to determine a start and end date for every project task.
c) It identifies so-called critical activities that, if delayed will delay the project completion.
3) Network Techniques: PERT (ADM) and CPM (PDM) – PERT and CPM are the most commonly used approaches to project scheduling. Both were introduced in the 1950s. PERT has been primarily associated with R&D projects, while CPM with construction projects. Today PERT is not used much since project management software generates CPM style networks. The primary difference between them is that PERT uses probabilistic techniques to determine task durations, while CPM relies on a single duration estimate for each task. Both techniques identify the critical path (tasks that cannot be delayed without delaying the project) and associated float or slack in the schedule. In 2005 the Project Management Institute (PMI) deemed it necessary to change the names of these techniques. According to PMI, PERT is called ADM/PERT (Arrow Diagram Method) and CPM is PDM/CPM (Precedence Diagramming Method).
a) Terminology – Following are the key terms associated with the development and use of networks:
i) Activity – A specific task or set of tasks that have a start and end, and consume resources.
ii) Event – The result of completing one or more activities. Events don’t use resources.
iii) Network – The arrangement of all activities and events in their logical sequence represented by arcs and nodes.
iv) Path – The series of connected activities between any two events in a network.
v) Critical – Activities, events or paths which, if delayed, will delay the completion of the project.
To construct a network the predecessors and successors of each activity must be identified. Activities that start the network will have no predecessor. Activities that end the network will have no successor. Regardless of the technique used, it is a good practice to link the activities with no other predecessor to a START milestone. Those without any successor should be linked to an END milestone. PDM/CPM networks identify the activities as nodes in the network, called the Activity on Node (AON) network. The arrows in between the nodes depict the predecessor/successor relationships among the activities. The ADM/PERT method, on the other hand, uses Activity on Arrow (AOA) networks. Her.
Overview1) Overview – The continued discussion of project implem.docxalfred4lewis58146
Overview
1) Overview – The continued discussion of project implementation by covering various scheduling techniques.
2) Background – Per the text, “A schedule is the conversion of a project action plan into an operating timetable.” A schedule is important because each project is unique in its own way. The basic process is to identify all tasks and sequential relationships between them, that is, which tasks must precede or succeed others. There are a number of benefits to the creation and use of these networks. Some of them are as follows:
a) It is a consistent framework for planning, scheduling, and controlling the project.
b) It can be used to determine a start and end date for every project task.
c) It identifies so-called critical activities that, if delayed will delay the project completion.
3) Network Techniques: PERT (ADM) and CPM (PDM) – PERT and CPM are the most commonly used approaches to project scheduling. Both were introduced in the 1950s. PERT has been primarily associated with R&D projects, while CPM with construction projects. Today PERT is not used much since project management software generates CPM style networks. The primary difference between them is that PERT uses probabilistic techniques to determine task durations, while CPM relies on a single duration estimate for each task. Both techniques identify the critical path (tasks that cannot be delayed without delaying the project) and associated float or slack in the schedule. In 2005 the Project Management Institute (PMI) deemed it necessary to change the names of these techniques. According to PMI, PERT is called ADM/PERT (Arrow Diagram Method) and CPM is PDM/CPM (Precedence Diagramming Method).
a) Terminology – Following are the key terms associated with the development and use of networks:
i) Activity – A specific task or set of tasks that have a start and end, and consume resources.
ii) Event – The result of completing one or more activities. Events don’t use resources.
iii) Network – The arrangement of all activities and events in their logical sequence represented by arcs and nodes.
iv) Path – The series of connected activities between any two events in a network.
v) Critical – Activities, events or paths which, if delayed, will delay the completion of the project.
To construct a network the predecessors and successors of each activity must be identified. Activities that start the network will have no predecessor. Activities that end the network will have no successor. Regardless of the technique used, it is a good practice to link the activities with no other predecessor to a START milestone. Those without any successor should be linked to an END milestone. PDM/CPM networks identify the activities as nodes in the network, called the Activity on Node (AON) network. The arrows in between the nodes depict the predecessor/successor relationships among the activities. The ADM/PERT method, on the other hand, uses Activity on Arrow (AOA) networks. Here the nodes represent .
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docxjeffevans62972
Yagmur Bostanci
47 Hackensack Street, East Rutherford, NJ
929-229-8834
[email protected]
EDUCATON
BERKELEY COLLEGE
YORK, UNITED STATES
· Bachelor of Business Management
· Cumulative GPA 3.00
PROFESSIONAL EXPERIENCE
Lincoln House Outreach
303 W 66th St, New York, NY
Nurse
July 2014 – September 2014
· Responsible for the old women in Lincoln House Outreach
· Managing all the payments and organizing listing
· Balancing firm objectives and old women satisfaction
CANDLEWYCK DINNER
East Rutherford, New Jersey, United States
Waitress
· Food delivery
· Fulfill costumer’s wants
· Accounting (Cash, Credit Card, and tax for prices of the food)
TECHNICAL SKILLS
· Phone Settings
· Microsoft Office (Excel, Word, Power point)
· Adobe Photoshop
Overview
1) Overview – The continued discussion of project implementation by covering various scheduling techniques.
2) Background – Per the text, “A schedule is the conversion of a project action plan into an operating timetable.” A schedule is important because each project is unique in its own way. The basic process is to identify all tasks and sequential relationships between them, that is, which tasks must precede or succeed others. There are a number of benefits to the creation and use of these networks. Some of them are as follows:
a) It is a consistent framework for planning, scheduling, and controlling the project.
b) It can be used to determine a start and end date for every project task.
c) It identifies so-called critical activities that, if delayed will delay the project completion.
3) Network Techniques: PERT (ADM) and CPM (PDM) – PERT and CPM are the most commonly used approaches to project scheduling. Both were introduced in the 1950s. PERT has been primarily associated with R&D projects, while CPM with construction projects. Today PERT is not used much since project management software generates CPM style networks. The primary difference between them is that PERT uses probabilistic techniques to determine task durations, while CPM relies on a single duration estimate for each task. Both techniques identify the critical path (tasks that cannot be delayed without delaying the project) and associated float or slack in the schedule. In 2005 the Project Management Institute (PMI) deemed it necessary to change the names of these techniques. According to PMI, PERT is called ADM/PERT (Arrow Diagram Method) and CPM is PDM/CPM (Precedence Diagramming Method).
a) Terminology – Following are the key terms associated with the development and use of networks:
i) Activity – A specific task or set of tasks that have a start and end, and consume resources.
ii) Event – The result of completing one or more activities. Events don’t use resources.
iii) Network – The arrangement of all activities and events in their logical sequence represented by arcs and nodes.
iv) Path – The series of connected activities between any two events in a network.
v) Critical – Activities, events or paths which, if delayed, w.
Introduction
CPM/PERT or Network Analysis as the technique is sometimes called, developed along two parallel streams, one industrial and the other military.
CPM (Critical Path Method) was the discovery of M.R.Walker of E.I.Du Pont de Nemours & Co. and J.E.Kelly of Remington Rand, circa 1957. The computation was designed for the UNIVAC-I computer. The first test was made in 1958, when CPM was applied to the construction of a new chemical plant. In March 1959, the method was applied to maintenance shut-down at the Du Pont works in Louisville, Kentucky. Unproductive time was reduced from 125 to 93 hours.
PERT (Project Evaluation and Review Technique) was devised in 1958 for the POLARIS missile program by the Program Evaluation Branch of the Special Projects office of the U.S.Navy, helped by the Lockheed Missile Systems division and the Consultant firm of Booz-Allen & Hamilton. The calculations were so arranged so that they could be carried out on the IBM Naval Ordinance Research Computer (NORC) at Dahlgren, Virginia.
A Study on Project Planning Using the Deterministic and Probabilistic Models ...IJERA Editor
Project planning is the important task in many areas like construction, resource allocation and many. A sequence of activities has to be performed to complete one task. Each activity has its unique processing time and all together to identify the critical activities which affect the completion of the project. In this paper the probabilistic and deterministic models to determine the project completion time and also the critical activities are considered. A case study on building construction project has been performed to demonstrate the application of the above said models. The two project scheduling namely PERT and CPM are used to determine numerically the different types of floating times of each activity and hence determined the critical path which plays an important role in the project completion time. Also a linear programing model has been developed to reduce the project completion time which optimize the resource allocation. To apply these techniques numerically the primary data from a housing project company in a metropolitan city has been taken, the network diagram of the activities involved in the building construction project has been drawn and the results are tabulated
Planning is a guideline in implementing the project so that development can be
implemented in accordance with the time and cost planned. Control discrepancy
between initial plan and realization that exists in implementation project required a
project management, therefore required optimization analysis of project duration, so
it can be known how long a project is completed and look for the possibility of project
acceleration implementation by Project Evaluation and Review Technique (PERT)
and Critical Path Method (CPM) or critical path method. This research aims to apply
Project Evaluation and Review Technique (PERT) and Critical Project Management
(CPM) methods to find optimize solutions and control the performance of time and
cost in project scheduling. The research method used case study method at hospital
project in Bogor District, Indonesia, by collecting data direct observation and
interview results at contractor. Based on these data, create a schedule by using PERT
and CPM methods, which will be measured performance of time performance and
project cost which is expected to overcome the problem of controlling and completion
of project. The results of this study, using PERT and CPM methods proved to optimize
the project. Based on calculation by PERT method reduce duration of work: 12 days
(13, 18%). Based on calculation by CPM method reduce duration of work: 31 days
(34, 06%) but direct cost increase 112.208,300, - rupiahs (0, 25%).
Similar to IRJET- Comparative Analysis between Critical Path Method and Monte Carlo Simulation (20)
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
Water scarcity is the lack of fresh water resources to meet the standard water demand. There are two type of water scarcity. One is physical. The other is economic water scarcity.
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Dr.Costas Sachpazis
Terzaghi's soil bearing capacity theory, developed by Karl Terzaghi, is a fundamental principle in geotechnical engineering used to determine the bearing capacity of shallow foundations. This theory provides a method to calculate the ultimate bearing capacity of soil, which is the maximum load per unit area that the soil can support without undergoing shear failure. The Calculation HTML Code included.
Student information management system project report ii.pdfKamal Acharya
Our project explains about the student management. This project mainly explains the various actions related to student details. This project shows some ease in adding, editing and deleting the student details. It also provides a less time consuming process for viewing, adding, editing and deleting the marks of the students.
Immunizing Image Classifiers Against Localized Adversary Attacksgerogepatton
This paper addresses the vulnerability of deep learning models, particularly convolutional neural networks
(CNN)s, to adversarial attacks and presents a proactive training technique designed to counter them. We
introduce a novel volumization algorithm, which transforms 2D images into 3D volumetric representations.
When combined with 3D convolution and deep curriculum learning optimization (CLO), itsignificantly improves
the immunity of models against localized universal attacks by up to 40%. We evaluate our proposed approach
using contemporary CNN architectures and the modified Canadian Institute for Advanced Research (CIFAR-10
and CIFAR-100) and ImageNet Large Scale Visual Recognition Challenge (ILSVRC12) datasets, showcasing
accuracy improvements over previous techniques. The results indicate that the combination of the volumetric
input and curriculum learning holds significant promise for mitigating adversarial attacks without necessitating
adversary training.
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdffxintegritypublishin
Advancements in technology unveil a myriad of electrical and electronic breakthroughs geared towards efficiently harnessing limited resources to meet human energy demands. The optimization of hybrid solar PV panels and pumped hydro energy supply systems plays a pivotal role in utilizing natural resources effectively. This initiative not only benefits humanity but also fosters environmental sustainability. The study investigated the design optimization of these hybrid systems, focusing on understanding solar radiation patterns, identifying geographical influences on solar radiation, formulating a mathematical model for system optimization, and determining the optimal configuration of PV panels and pumped hydro storage. Through a comparative analysis approach and eight weeks of data collection, the study addressed key research questions related to solar radiation patterns and optimal system design. The findings highlighted regions with heightened solar radiation levels, showcasing substantial potential for power generation and emphasizing the system's efficiency. Optimizing system design significantly boosted power generation, promoted renewable energy utilization, and enhanced energy storage capacity. The study underscored the benefits of optimizing hybrid solar PV panels and pumped hydro energy supply systems for sustainable energy usage. Optimizing the design of solar PV panels and pumped hydro energy supply systems as examined across diverse climatic conditions in a developing country, not only enhances power generation but also improves the integration of renewable energy sources and boosts energy storage capacities, particularly beneficial for less economically prosperous regions. Additionally, the study provides valuable insights for advancing energy research in economically viable areas. Recommendations included conducting site-specific assessments, utilizing advanced modeling tools, implementing regular maintenance protocols, and enhancing communication among system components.
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.