SlideShare a Scribd company logo
G L BAJAJ GROUP OF INSTITUTIONS, MATHURA
UNIT 2 : Production Planning and
control, Project Management
By:
Mohammad Mohsin
Assistant Professor
(M.Tech., B.Tech)
Syllabus
Production Planning and control: Forecasting techniques – causal and time series models, moving average,
exponential smoothing, trend and seasonality; aggregate production planning; master production scheduling; materials
requirement planning (MRP) and MRP‐II; routing, scheduling and priority dispatching, concept of JIT manufacturing
System.
Project Management: Project network analysis, CPM, PERT and Project crashing.
Production, Planning and Control
 Production planning and control may be defined as “the direction and co-ordination of the firm's
material and physical facilities towards the attainment of pre-specified production goals, in
the most efficient and economical manner”.
 Production: Production is the process by which goods or services are created.
 Planning: Planning means preparing the scheme in advance before the actual work is started.
 Control: Control means the supervision of all the relevant operations with the help of control
mechanism that feeds back the progress of the work.
Relationship
PRODUCTION
ACTIVITY
CONTROLLER COMPARISON PRODUCTION
PLAN
OBJECTIVES
INPUT
Men
Material
Machines
OUTPUT
Goods and
Services
Planning
Forecast
Objectives of PPC:
PPC : Process
Production, Planning & Control
Production Planning Production Control
Planning
Routing
Scheduling
Loading Corrective
Inspection
Following Up
Dispatching
Comparison
Production Planning Production Control
a preproduction activity.
will be in action when production activity
begins.
decides the operations which are required
for production
regulates and supervises the operations
required for production.
decides who should do work and when
ensures that each department complete its
work on schedule
shows the directions follows these directions
estimates the resources that are required
for production
makes available resources that are required
for prodcution
Forecasting
 Forecasting is a statement about the future. It is estimating future event (variable), by casting forward past data.
Past data are systematically combined in predetermined way to obtain the estimate.
Forecasting help managers to:
 Plan the system
 Plan the use of system
Types of Forecasts
 Economic forecasts
 Technological forecasts
 Demand forecasts
Forecasting Techniques
 Qualitative methods: These types of forecasting methods are based on judgments, opinions, intuition,
emotions, or personal experiences and are subjective in nature. They do not rely on any rigorous
mathematical computations.
 Quantitative methods: These types of forecasting methods are based on mathematical (quantitative)
models, and are objective in nature. They rely heavily on mathematical computations.
Time Series Models
Simple Mean
(Average)
Simple Moving
Average
Weighted Moving
Average
Exponential
Smoothing
Trend Projection Seasonal Indexes
Naïve
Naïve Forecast
 Uses last period’s actual value as a forecast.
 Applied to a series that exhibits seasonality or trend
 Example: Forecast the order for the month of November by Naïve approach.
Month Orders Per Month Forecast
Jan 120 -
Feb 90 120
Mar 100 90
Apr 75 100
May 110 75
June 50 110
July 75 50
Aug 130 75
Sept 110 130
Oct 90 110
Nov - 90
Simple Moving Average
 Uses an average of all past data as a forecast
 Useful if we can assume that market demands will stay fairly steady over time
 Moving Average = ΣDemand in previous n periods
n
 Where: n = number of periods in the moving average
Example
Ques: Compute a three-period moving average forecast given the following demand for cars for the last five periods.
Solution: The forecast for period 6 should be:
Moving Average Forecast = 65 + 90 + 85 = 80 cars
3
If the actual demand in period 6 turns out to be 95, the moving average forecast for the period 7 would be:
Moving Average Forecast = 90 + 85 + 95 = 90 cars
3
Demand Supply
1 70
2 80
3 65
4 90
5 85
Weighted Moving Average
 Uses an average of a specified number of the most recent observations, with each observation receiving
a different emphasis (weight).
 Formula used:
Weighted Moving Average = Σ[(Weight for period n) (demand in period n)]
ΣWeights
Example
MAD MSE MAPE
Input
Data
Weights Forecast Error Analysis
Period
Actual
Value
w_t w_t-1 w_t-2 Forecast Error
Absolute
error
Squared
error
Absolute
% error
1 10 0.8 0.2 0.1
2 12
3 16
4 13 16.200 -3.200 3.200 10.240 24.61%
5 17 14.800 2.200 2.200 4.840 12.94%
6 19 17.800 1.200 1.200 1.440 6.31%
7 15 19.900 -4.900 4.900 24.010 32.66%
8 20 17.500 2.500 2.500 6.250 12.50%
9 22 20.900 1.100 1.100 1.210 5.00%
10 19 23.100 -4.100 4.100 16.810 21.57%
11 21 21.600 -0.600 0.600 0.360 2.85%
12 19 22.800 -3.800 3.800 14.440 20.00%
13 21.3 2.622 8.844 0.154
Exponential Smoothing
 Used to forecast sales when there is no trend in the demand for goods or services.
 Weighted averaging method based on previous forecast plus a percentage (α) of the forecast error.
Next forecast = Previous forecast + α ( Actual – Previous forescast)
Where (Actual – Previous forecast) = forecast error, α is a percentage of the error.
Example
Use exponential smoothing model to develop a series of forecast for the following data and compute:
[Actual - Forecast] = Error for each period, Use a smoothing factor of 0.10, Use smoothing factor of 0.40.
Plot the actual data and both sets of forecast on a single graph.
Solution:
Period
Actual
Demand
Forecast
Forecast
Error
Forecast Forecast
Error
1 50
2 52 50 2 50 2
3 48 50.20 -2.2 50.80 -2.8
4 51 49.98 1.02 49.68 1.32
5 50 50.08 -0.80 50.21 -0.21
6 54 50.07 3.93 50.13 3.87
7 52 50.46 1.54 51.68 0.32
8 50 50.61 -0.61 51.81 -1.81
9 55 50.55 4.45 51.09 3.91
10 51 2 52.65 0.35
11 51.20 52.79
= 0.10
= 0.40
Trend Line Forecast
Yt = a + bt
*Where:
t = specified number of time periods from t=0
Yt = forecast for period t
a = value of Yt at t=0
b = slope of the line
*The coefficient of line a and b can be computed using two equations:
b = nΣty - Σt Σy OR a = Σy - bΣt
nΣt^2 – (Σt)^2 n
*Where n = number of periods; y = value of the time series
Components of Time Series Model
Trend
Component
Seasonal
Component
Irregular
Component
Cyclical
Component
Aggregate Production Planning (APP)
Aggregate Production Planning is an operational activity that does an aggregate plan for production process in
advance of 6-18 months to give an idea to the management that what quantity of material and resources are to be
procured and when so that the total cost of oganization is kept minimum of that period.
INPUTS:-
 Information about the resources and facilities available
 Demand and forecats for the period for which the planning has to be done.
 Cost of various alternatives and resources (cost of holding inventory, ordering cos, cost of production)
 Organisational pilicy regrading the usage of all alternatives.
Aggregate Production Planning
Production
Planning
External
Capacity
Competition
Raw Material
Supply
Economic
Condition
Demand
Work Force
Capacity
Inventory
Production
EXTERNAL
INTERNAL
Why Is Production Planning Necessary
Demand
Fluctuations
Difficulty level in
altering
production rates
Benefits of
multi period
planning
Capacity
Fluctuation
Master Production Scheduling (MPS)
 It is is a plan for individual commodities to be produced in each time period such as
production, staffing, inventory, etc.
 It is usually linked to manufacturing where the plan indicates when and how much of
each product will be demanded.
 This plan quantifies significant processes, parts, and other resources in order to
optimize production, to identify bottlenecks, and to anticipate needs and
completed goods.
Benefits of MPS
 It provides a solid base to build, improve and track the sales forecast.
 It provides a solid base to determine the desired inventory levels.
 It provides a solid base for calculating the required amount of labor and shifts, as part of the MRP next stage.
 It allows optimizing the installed capacity and balancing the load of the plant.
Material Requirement Planning (MRP)
Material Requirements Planning (MRP) is a production planning, scheduling, and inventory control
system used to manage manufacturing processes.
An MRP system objectives:
 Ensure raw materials are available for production and products are available for delivery to customers.
 Maintain the lowest possible material and product levels in store
 Plan manufacturing activities, delivery schedules and purchasing activities.
MRP
Material
Requirements
Planning
Purchase
Order
Material
Plan
Work
Orders
Report
OUTPUT
Orders
Forecast
BOM
Inventory
Master
Production
Schedule
INPUT
Manufacturing Resource Planning (MRP-II)
Manufacturing Resource Planning is an information system used to plan and control inventories and
capacities in manufacturing companies. MRP II coordinates the sales , purchasing , manufacturing,
finance and engineering functions.
The various modules of MRP II are follows:
 Manufacturing Applications
 Engineering applications.
 Financial Applications.
 Marketing applications
Routing
 Routing is determining the exact path which will be followed in production. It is the selection of
the path from where each unit have to pass before reaching the final stage. The stages from
which goods are to pass are decided in this process.
Routing Procedure:
 Deciding what part to be made or purchased
 Determining Materials required
 Determining Manufacturing Operations and Sequences
 Determining of Lot Sizes
 Determining of Scrap Factors
 Analysis of Cost of the Product
 Preparation of Production Control
Scheduling
 Scheduling is the determining of time and date when each operation is to be commenced or
completed. The time and date of manufacturing each component is fixed in such a way that
assembling for final product is not delayed in any way.
TYPES OF SCHEDULES:
 Master Scheduling
 Manufacturing Scheduling
 Detail Operation Scheduling
Dispatching
 Dispatching refers to the process of actually ordering the work to be done. It involves putting the
plan into effect by issuing orders. It is concerned with starting the process and operation on the
basis of route sheets and schedule charts.
DISPATCHING PROCEDURES:
 Centralized Dispatching
 Decentralized Dispatching
Machine Loading
 Machine load charts show the amount of work (in terms of hours, days, or weeks) that
has been assigned and scheduled to each machine, groups of identical machines or shop
departments.
 Loading provides a complete and correct information about the number of machines
available and their operating characteristics such as speed, capacity, capability etc.
 This information can be used to calculate the difference between work load and actual
capacity and then to determine whether customers order can be completed on due date
or not.
Just In Time (JIT) Manufacturing
 Just-in-time (JIT) manufacturing, also known as just-in-time production or the Toyota
Production System (TPS), is a methodology aimed primarily at reducing cycle times of
various activities within production system as well as response times from suppliers and
to customers.
 JIT is seen as a more cost efficient method of maintaining stock levels.
 Its purpose is to minimise the amount of goods you hold at any one time without
compromising the production volumes.
contd.
Project Management
 Any project involves planning, scheduling and controlling a number of interrelated activities with
use of limited resources, namely, men, machines, materials, money and time.
 It is required that managers must have a dynamic planning and scheduling system to produce the
best possible results and also to react immediately to the changing conditions and make
necessary changes in the plan and schedule.
Contd....
Initiate
Plan
Execute
Monitor
and
Control
Close
Project
Management
Phases of Project Management
 Planning: Planning involves setting the objectives of the project. Identifying various activities to be
performed and determining the requirement of resources such as men, materials, machines, etc.
 Scheduling: Based on the time estimates, the start and finish times for each activity are worked
out by applying forward and backward pass techniques, critical path is identified, along with the
slack and float for the non-critical paths.
 Controlling: Controlling refers to analyzing and evaluating the actual progress against the plan.
Reallocation of resources, crashing and review of projects with periodical reports are carried out.
Project Network Analysis
 Network Analysis is a system which plans the projects by analyzing the project activities.
 Projects are broken down into individual tasks or activities, which are arranged in logical sequence.
 A network diagram is prepared, which presents visually the relationship between all the activities
involved and the cost for different activities.
 Network analysis helps designing, planning, coordinating, controlling and in decision-making in order
to accomplish the project economically in the minimum available time with the limited available
resources.
 The network analysis fulfils the objectives of reducing total time, cost, idle resources, interruptions and
conflicts.
Critical Path Method (CPM)
In CPM activities are shown as a network of precedence relationships using activity-on- node network construction
 Single estimate of activity time
 Deterministic activity times
USED IN:
 Production management - for the jobs of repetitive in nature where the activity time estimates can be predicted
with considerable certainty due to the existence of past experience.
CPM calculation
 Path : A connected sequence of activities leading from the starting event to the ending event
 Critical Path : The longest path (time); determines the project duration
 Critical Activities : All of the activities that make up the critical path
Example
 Draw a network for house construction project. The sequence of activities with their predecessors are given in table
below.
Activity
Starting & Finishing
Event
Description of Activity Predecessor
Time Duration
(days)
A (1,2) Prepare the house plan - 4
B (2,3) Cobstruct the house A 58
C (3,4) Fix the door / windows B 2
D (3,5) Wiring the house B 2
E (4,6) Paint the house C 1
F (5,6) Polish the doors / windows D 1
1 2 3
4
5
6
A
E
C
D
B
F
Programme Evaluation Review Technique (PERT)
In PERT activities are shown as a network of precedence relationships using activity-on- arrow network construction
 Multiple time estimates
 Probabilistic activity times
USED IN:
 Project management - for non-repetitive jobs (research and development work), where the time and cost
estimates tend to be quite uncertain. This technique uses probabilistic time estimates.
Project Crashing
 The process of shortening the time to complete a project is called crashing and is usually achieved by
putting into service additional labour or machines to one activity or more activities.
 Crashing involves more costs.
 A project manager would like to speed up a project by spending as minimum extra cost as possible.
 Project crashing seeks to minimize the extra cost for completion of a project before the stipulated time.
Procedure for Crashing
Step1: Draw the network diagram and mark the Normal time and Crash time.
Step2: Calculate TE and TL for all the activities.
Step3: Find the critical path and other paths.
Step 4: Find the slope for all activities and rank them in ascending order.
Step 5: Establish a tabular column with required field.
Step 6: Select the lowest ranked activity; check whether it is a critical activity. If so,crash
the activity, else go to the next highest ranked activity.
Note: The critical path must remain critical while crashing.
Step 7: Calculate the total cost of project for each crashing
Step 8: Repeat Step 6 until all the activities in the critical path are fully crashed.

More Related Content

What's hot

X bar and R control charts
X bar and R control chartsX bar and R control charts
X bar and R control charts
Dhruv Shah
 
8. chapter 7 work study (time and motion study)
8. chapter 7   work study (time and motion study)8. chapter 7   work study (time and motion study)
8. chapter 7 work study (time and motion study)
sundar sivam
 
Value Stream Mapping
Value Stream MappingValue Stream Mapping
Value Stream Mapping
TKMG, Inc.
 
Production Planning and Control
Production Planning and ControlProduction Planning and Control
Production Planning and Control
Nishant Agrawal
 
TIME STUDY
TIME STUDYTIME STUDY
TIME STUDY
chhavi narayan
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturing
ananya0122
 
Ppc
PpcPpc
Process Failure Modes & Effects Analysis (PFMEA)
Process Failure Modes & Effects Analysis (PFMEA)Process Failure Modes & Effects Analysis (PFMEA)
Process Failure Modes & Effects Analysis (PFMEA)
Anand Subramaniam
 
Control charts for attributes
Control charts for attributesControl charts for attributes
Control charts for attributes
Buddy Krishna
 
Control chart ppt
Control chart pptControl chart ppt
Control chart ppt
Deepak Sarangi
 
production scheduling
production schedulingproduction scheduling
production scheduling
PraveenManickam2
 
Scheduling
SchedulingScheduling
Scheduling
ahmad bassiouny
 
Total productive maintenance(TPM)
Total productive maintenance(TPM)Total productive maintenance(TPM)
Total productive maintenance(TPM)
Md.Muzahid Khan
 
Man and machine chart
Man and machine chartMan and machine chart
Chapter 1 introduction to manufacturing system
Chapter 1   introduction to manufacturing systemChapter 1   introduction to manufacturing system
Chapter 1 introduction to manufacturing system
N. A. Sutisna
 
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
Inter Alliance Werardt
 
FMEA Presentation
FMEA PresentationFMEA Presentation
FMEA Presentation
Gaurav Sharma
 
Manufacturing+process+selection+and+design.ppt
Manufacturing+process+selection+and+design.pptManufacturing+process+selection+and+design.ppt
Manufacturing+process+selection+and+design.ppt
videoaakash15
 
An introduction to weibull analysis
An introduction to weibull analysisAn introduction to weibull analysis
An introduction to weibull analysis
ASQ Reliability Division
 
IMPROVEMENT IN PROCESS INDUSTRIES BY USING WORK STUDY METHODS: A CASE STUDY
IMPROVEMENT IN PROCESS INDUSTRIES BY USING WORK STUDY METHODS: A CASE STUDYIMPROVEMENT IN PROCESS INDUSTRIES BY USING WORK STUDY METHODS: A CASE STUDY
IMPROVEMENT IN PROCESS INDUSTRIES BY USING WORK STUDY METHODS: A CASE STUDY
IAEME Publication
 

What's hot (20)

X bar and R control charts
X bar and R control chartsX bar and R control charts
X bar and R control charts
 
8. chapter 7 work study (time and motion study)
8. chapter 7   work study (time and motion study)8. chapter 7   work study (time and motion study)
8. chapter 7 work study (time and motion study)
 
Value Stream Mapping
Value Stream MappingValue Stream Mapping
Value Stream Mapping
 
Production Planning and Control
Production Planning and ControlProduction Planning and Control
Production Planning and Control
 
TIME STUDY
TIME STUDYTIME STUDY
TIME STUDY
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturing
 
Ppc
PpcPpc
Ppc
 
Process Failure Modes & Effects Analysis (PFMEA)
Process Failure Modes & Effects Analysis (PFMEA)Process Failure Modes & Effects Analysis (PFMEA)
Process Failure Modes & Effects Analysis (PFMEA)
 
Control charts for attributes
Control charts for attributesControl charts for attributes
Control charts for attributes
 
Control chart ppt
Control chart pptControl chart ppt
Control chart ppt
 
production scheduling
production schedulingproduction scheduling
production scheduling
 
Scheduling
SchedulingScheduling
Scheduling
 
Total productive maintenance(TPM)
Total productive maintenance(TPM)Total productive maintenance(TPM)
Total productive maintenance(TPM)
 
Man and machine chart
Man and machine chartMan and machine chart
Man and machine chart
 
Chapter 1 introduction to manufacturing system
Chapter 1   introduction to manufacturing systemChapter 1   introduction to manufacturing system
Chapter 1 introduction to manufacturing system
 
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
 
FMEA Presentation
FMEA PresentationFMEA Presentation
FMEA Presentation
 
Manufacturing+process+selection+and+design.ppt
Manufacturing+process+selection+and+design.pptManufacturing+process+selection+and+design.ppt
Manufacturing+process+selection+and+design.ppt
 
An introduction to weibull analysis
An introduction to weibull analysisAn introduction to weibull analysis
An introduction to weibull analysis
 
IMPROVEMENT IN PROCESS INDUSTRIES BY USING WORK STUDY METHODS: A CASE STUDY
IMPROVEMENT IN PROCESS INDUSTRIES BY USING WORK STUDY METHODS: A CASE STUDYIMPROVEMENT IN PROCESS INDUSTRIES BY USING WORK STUDY METHODS: A CASE STUDY
IMPROVEMENT IN PROCESS INDUSTRIES BY USING WORK STUDY METHODS: A CASE STUDY
 

Similar to Industrial engineering unit 2 new

Forecasting & time series data
Forecasting & time series dataForecasting & time series data
Forecasting & time series data
Jane Karla
 
Operation management-notes
Operation management-notesOperation management-notes
Operation management-notes
Saratha Shanmugam
 
Unit 2 manufacturing system design
Unit   2 manufacturing system designUnit   2 manufacturing system design
Unit 2 manufacturing system design
Lakshmi Life Sciences Ltd.
 
Walk-Through Demand Sales Time Series Forecasting
Walk-Through Demand Sales Time Series ForecastingWalk-Through Demand Sales Time Series Forecasting
Walk-Through Demand Sales Time Series Forecasting
IRJET Journal
 
Forecasting Techniques
Forecasting TechniquesForecasting Techniques
Forecasting Techniques
Anand Subramaniam
 
Forecasting Techniques
Forecasting TechniquesForecasting Techniques
Forecasting Techniques
guest865c0e0c
 
REDUCTION OF WASTAGES THROUGH PPC TECHNIQUES
REDUCTION OF WASTAGES THROUGH    PPC TECHNIQUESREDUCTION OF WASTAGES THROUGH    PPC TECHNIQUES
REDUCTION OF WASTAGES THROUGH PPC TECHNIQUES
Asim Aslam
 
Productionplanning aggregate capacity
Productionplanning aggregate capacityProductionplanning aggregate capacity
Productionplanning aggregate capacity
zmagtoto
 
SAP Flexible Planning
SAP Flexible PlanningSAP Flexible Planning
SAP Flexible Planning
mohamed_elkady
 
Forecasting Models & Their Applications
Forecasting Models & Their ApplicationsForecasting Models & Their Applications
Forecasting Models & Their Applications
Mahmudul Hasan
 
Sales & Operations Planning
Sales & Operations PlanningSales & Operations Planning
Sales & Operations Planning
mubarak2009
 
Unit 2
Unit 2Unit 2
Unit 2
dinesh babu
 
CIM unit-2
CIM unit-2CIM unit-2
CIM unit-2
Dr.PERIASAMY K
 
Pom unit 3
Pom unit 3Pom unit 3
Pom unit 3
riyavidya
 
IRJET- Overview of Forecasting Techniques
IRJET- Overview of Forecasting TechniquesIRJET- Overview of Forecasting Techniques
IRJET- Overview of Forecasting Techniques
IRJET Journal
 
Ch13 - Aggregate Planning
Ch13 - Aggregate PlanningCh13 - Aggregate Planning
Ch13 - Aggregate Planning
Pelly Sianova
 
Demand Forecasting
Demand ForecastingDemand Forecasting
Demand Forecasting
Anupam Basu
 
Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptx
SudipBalLama
 
Paper id 42201622
Paper id 42201622Paper id 42201622
Paper id 42201622
IJRAT
 
Production Planning and Control (Operations Management)
Production Planning and Control (Operations Management)Production Planning and Control (Operations Management)
Production Planning and Control (Operations Management)
Manu Alias
 

Similar to Industrial engineering unit 2 new (20)

Forecasting & time series data
Forecasting & time series dataForecasting & time series data
Forecasting & time series data
 
Operation management-notes
Operation management-notesOperation management-notes
Operation management-notes
 
Unit 2 manufacturing system design
Unit   2 manufacturing system designUnit   2 manufacturing system design
Unit 2 manufacturing system design
 
Walk-Through Demand Sales Time Series Forecasting
Walk-Through Demand Sales Time Series ForecastingWalk-Through Demand Sales Time Series Forecasting
Walk-Through Demand Sales Time Series Forecasting
 
Forecasting Techniques
Forecasting TechniquesForecasting Techniques
Forecasting Techniques
 
Forecasting Techniques
Forecasting TechniquesForecasting Techniques
Forecasting Techniques
 
REDUCTION OF WASTAGES THROUGH PPC TECHNIQUES
REDUCTION OF WASTAGES THROUGH    PPC TECHNIQUESREDUCTION OF WASTAGES THROUGH    PPC TECHNIQUES
REDUCTION OF WASTAGES THROUGH PPC TECHNIQUES
 
Productionplanning aggregate capacity
Productionplanning aggregate capacityProductionplanning aggregate capacity
Productionplanning aggregate capacity
 
SAP Flexible Planning
SAP Flexible PlanningSAP Flexible Planning
SAP Flexible Planning
 
Forecasting Models & Their Applications
Forecasting Models & Their ApplicationsForecasting Models & Their Applications
Forecasting Models & Their Applications
 
Sales & Operations Planning
Sales & Operations PlanningSales & Operations Planning
Sales & Operations Planning
 
Unit 2
Unit 2Unit 2
Unit 2
 
CIM unit-2
CIM unit-2CIM unit-2
CIM unit-2
 
Pom unit 3
Pom unit 3Pom unit 3
Pom unit 3
 
IRJET- Overview of Forecasting Techniques
IRJET- Overview of Forecasting TechniquesIRJET- Overview of Forecasting Techniques
IRJET- Overview of Forecasting Techniques
 
Ch13 - Aggregate Planning
Ch13 - Aggregate PlanningCh13 - Aggregate Planning
Ch13 - Aggregate Planning
 
Demand Forecasting
Demand ForecastingDemand Forecasting
Demand Forecasting
 
Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptx
 
Paper id 42201622
Paper id 42201622Paper id 42201622
Paper id 42201622
 
Production Planning and Control (Operations Management)
Production Planning and Control (Operations Management)Production Planning and Control (Operations Management)
Production Planning and Control (Operations Management)
 

Recently uploaded

Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
PreethaV16
 
Gas agency management system project report.pdf
Gas agency management system project report.pdfGas agency management system project report.pdf
Gas agency management system project report.pdf
Kamal Acharya
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
ElakkiaU
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
21UME003TUSHARDEB
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
shadow0702a
 
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
PriyankaKilaniya
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
AjmalKhan50578
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
Gino153088
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
Engineering Standards Wiring methods.pdf
Engineering Standards Wiring methods.pdfEngineering Standards Wiring methods.pdf
Engineering Standards Wiring methods.pdf
edwin408357
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
ijaia
 
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
Paris Salesforce Developer Group
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
Anant Corporation
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
morris_worm_intro_and_source_code_analysis_.pdf
morris_worm_intro_and_source_code_analysis_.pdfmorris_worm_intro_and_source_code_analysis_.pdf
morris_worm_intro_and_source_code_analysis_.pdf
ycwu0509
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
ydzowc
 
Design and optimization of ion propulsion drone
Design and optimization of ion propulsion droneDesign and optimization of ion propulsion drone
Design and optimization of ion propulsion drone
bjmsejournal
 

Recently uploaded (20)

Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
 
Gas agency management system project report.pdf
Gas agency management system project report.pdfGas agency management system project report.pdf
Gas agency management system project report.pdf
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
 
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
Engineering Standards Wiring methods.pdf
Engineering Standards Wiring methods.pdfEngineering Standards Wiring methods.pdf
Engineering Standards Wiring methods.pdf
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
morris_worm_intro_and_source_code_analysis_.pdf
morris_worm_intro_and_source_code_analysis_.pdfmorris_worm_intro_and_source_code_analysis_.pdf
morris_worm_intro_and_source_code_analysis_.pdf
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
 
Design and optimization of ion propulsion drone
Design and optimization of ion propulsion droneDesign and optimization of ion propulsion drone
Design and optimization of ion propulsion drone
 

Industrial engineering unit 2 new

  • 1. G L BAJAJ GROUP OF INSTITUTIONS, MATHURA UNIT 2 : Production Planning and control, Project Management By: Mohammad Mohsin Assistant Professor (M.Tech., B.Tech)
  • 2. Syllabus Production Planning and control: Forecasting techniques – causal and time series models, moving average, exponential smoothing, trend and seasonality; aggregate production planning; master production scheduling; materials requirement planning (MRP) and MRP‐II; routing, scheduling and priority dispatching, concept of JIT manufacturing System. Project Management: Project network analysis, CPM, PERT and Project crashing.
  • 3. Production, Planning and Control  Production planning and control may be defined as “the direction and co-ordination of the firm's material and physical facilities towards the attainment of pre-specified production goals, in the most efficient and economical manner”.  Production: Production is the process by which goods or services are created.  Planning: Planning means preparing the scheme in advance before the actual work is started.  Control: Control means the supervision of all the relevant operations with the help of control mechanism that feeds back the progress of the work.
  • 6. PPC : Process Production, Planning & Control Production Planning Production Control Planning Routing Scheduling Loading Corrective Inspection Following Up Dispatching
  • 7. Comparison Production Planning Production Control a preproduction activity. will be in action when production activity begins. decides the operations which are required for production regulates and supervises the operations required for production. decides who should do work and when ensures that each department complete its work on schedule shows the directions follows these directions estimates the resources that are required for production makes available resources that are required for prodcution
  • 8. Forecasting  Forecasting is a statement about the future. It is estimating future event (variable), by casting forward past data. Past data are systematically combined in predetermined way to obtain the estimate. Forecasting help managers to:  Plan the system  Plan the use of system Types of Forecasts  Economic forecasts  Technological forecasts  Demand forecasts
  • 9. Forecasting Techniques  Qualitative methods: These types of forecasting methods are based on judgments, opinions, intuition, emotions, or personal experiences and are subjective in nature. They do not rely on any rigorous mathematical computations.  Quantitative methods: These types of forecasting methods are based on mathematical (quantitative) models, and are objective in nature. They rely heavily on mathematical computations.
  • 10. Time Series Models Simple Mean (Average) Simple Moving Average Weighted Moving Average Exponential Smoothing Trend Projection Seasonal Indexes Naïve
  • 11. Naïve Forecast  Uses last period’s actual value as a forecast.  Applied to a series that exhibits seasonality or trend  Example: Forecast the order for the month of November by Naïve approach. Month Orders Per Month Forecast Jan 120 - Feb 90 120 Mar 100 90 Apr 75 100 May 110 75 June 50 110 July 75 50 Aug 130 75 Sept 110 130 Oct 90 110 Nov - 90
  • 12. Simple Moving Average  Uses an average of all past data as a forecast  Useful if we can assume that market demands will stay fairly steady over time  Moving Average = ΣDemand in previous n periods n  Where: n = number of periods in the moving average
  • 13. Example Ques: Compute a three-period moving average forecast given the following demand for cars for the last five periods. Solution: The forecast for period 6 should be: Moving Average Forecast = 65 + 90 + 85 = 80 cars 3 If the actual demand in period 6 turns out to be 95, the moving average forecast for the period 7 would be: Moving Average Forecast = 90 + 85 + 95 = 90 cars 3 Demand Supply 1 70 2 80 3 65 4 90 5 85
  • 14. Weighted Moving Average  Uses an average of a specified number of the most recent observations, with each observation receiving a different emphasis (weight).  Formula used: Weighted Moving Average = Σ[(Weight for period n) (demand in period n)] ΣWeights
  • 15. Example MAD MSE MAPE Input Data Weights Forecast Error Analysis Period Actual Value w_t w_t-1 w_t-2 Forecast Error Absolute error Squared error Absolute % error 1 10 0.8 0.2 0.1 2 12 3 16 4 13 16.200 -3.200 3.200 10.240 24.61% 5 17 14.800 2.200 2.200 4.840 12.94% 6 19 17.800 1.200 1.200 1.440 6.31% 7 15 19.900 -4.900 4.900 24.010 32.66% 8 20 17.500 2.500 2.500 6.250 12.50% 9 22 20.900 1.100 1.100 1.210 5.00% 10 19 23.100 -4.100 4.100 16.810 21.57% 11 21 21.600 -0.600 0.600 0.360 2.85% 12 19 22.800 -3.800 3.800 14.440 20.00% 13 21.3 2.622 8.844 0.154
  • 16. Exponential Smoothing  Used to forecast sales when there is no trend in the demand for goods or services.  Weighted averaging method based on previous forecast plus a percentage (α) of the forecast error. Next forecast = Previous forecast + α ( Actual – Previous forescast) Where (Actual – Previous forecast) = forecast error, α is a percentage of the error.
  • 17. Example Use exponential smoothing model to develop a series of forecast for the following data and compute: [Actual - Forecast] = Error for each period, Use a smoothing factor of 0.10, Use smoothing factor of 0.40. Plot the actual data and both sets of forecast on a single graph. Solution: Period Actual Demand Forecast Forecast Error Forecast Forecast Error 1 50 2 52 50 2 50 2 3 48 50.20 -2.2 50.80 -2.8 4 51 49.98 1.02 49.68 1.32 5 50 50.08 -0.80 50.21 -0.21 6 54 50.07 3.93 50.13 3.87 7 52 50.46 1.54 51.68 0.32 8 50 50.61 -0.61 51.81 -1.81 9 55 50.55 4.45 51.09 3.91 10 51 2 52.65 0.35 11 51.20 52.79 = 0.10 = 0.40
  • 18. Trend Line Forecast Yt = a + bt *Where: t = specified number of time periods from t=0 Yt = forecast for period t a = value of Yt at t=0 b = slope of the line *The coefficient of line a and b can be computed using two equations: b = nΣty - Σt Σy OR a = Σy - bΣt nΣt^2 – (Σt)^2 n *Where n = number of periods; y = value of the time series
  • 19. Components of Time Series Model Trend Component Seasonal Component Irregular Component Cyclical Component
  • 20. Aggregate Production Planning (APP) Aggregate Production Planning is an operational activity that does an aggregate plan for production process in advance of 6-18 months to give an idea to the management that what quantity of material and resources are to be procured and when so that the total cost of oganization is kept minimum of that period. INPUTS:-  Information about the resources and facilities available  Demand and forecats for the period for which the planning has to be done.  Cost of various alternatives and resources (cost of holding inventory, ordering cos, cost of production)  Organisational pilicy regrading the usage of all alternatives.
  • 21. Aggregate Production Planning Production Planning External Capacity Competition Raw Material Supply Economic Condition Demand Work Force Capacity Inventory Production EXTERNAL INTERNAL
  • 22. Why Is Production Planning Necessary Demand Fluctuations Difficulty level in altering production rates Benefits of multi period planning Capacity Fluctuation
  • 23. Master Production Scheduling (MPS)  It is is a plan for individual commodities to be produced in each time period such as production, staffing, inventory, etc.  It is usually linked to manufacturing where the plan indicates when and how much of each product will be demanded.  This plan quantifies significant processes, parts, and other resources in order to optimize production, to identify bottlenecks, and to anticipate needs and completed goods.
  • 24. Benefits of MPS  It provides a solid base to build, improve and track the sales forecast.  It provides a solid base to determine the desired inventory levels.  It provides a solid base for calculating the required amount of labor and shifts, as part of the MRP next stage.  It allows optimizing the installed capacity and balancing the load of the plant.
  • 25. Material Requirement Planning (MRP) Material Requirements Planning (MRP) is a production planning, scheduling, and inventory control system used to manage manufacturing processes. An MRP system objectives:  Ensure raw materials are available for production and products are available for delivery to customers.  Maintain the lowest possible material and product levels in store  Plan manufacturing activities, delivery schedules and purchasing activities.
  • 27. Manufacturing Resource Planning (MRP-II) Manufacturing Resource Planning is an information system used to plan and control inventories and capacities in manufacturing companies. MRP II coordinates the sales , purchasing , manufacturing, finance and engineering functions. The various modules of MRP II are follows:  Manufacturing Applications  Engineering applications.  Financial Applications.  Marketing applications
  • 28. Routing  Routing is determining the exact path which will be followed in production. It is the selection of the path from where each unit have to pass before reaching the final stage. The stages from which goods are to pass are decided in this process. Routing Procedure:  Deciding what part to be made or purchased  Determining Materials required  Determining Manufacturing Operations and Sequences  Determining of Lot Sizes  Determining of Scrap Factors  Analysis of Cost of the Product  Preparation of Production Control
  • 29. Scheduling  Scheduling is the determining of time and date when each operation is to be commenced or completed. The time and date of manufacturing each component is fixed in such a way that assembling for final product is not delayed in any way. TYPES OF SCHEDULES:  Master Scheduling  Manufacturing Scheduling  Detail Operation Scheduling
  • 30. Dispatching  Dispatching refers to the process of actually ordering the work to be done. It involves putting the plan into effect by issuing orders. It is concerned with starting the process and operation on the basis of route sheets and schedule charts. DISPATCHING PROCEDURES:  Centralized Dispatching  Decentralized Dispatching
  • 31. Machine Loading  Machine load charts show the amount of work (in terms of hours, days, or weeks) that has been assigned and scheduled to each machine, groups of identical machines or shop departments.  Loading provides a complete and correct information about the number of machines available and their operating characteristics such as speed, capacity, capability etc.  This information can be used to calculate the difference between work load and actual capacity and then to determine whether customers order can be completed on due date or not.
  • 32. Just In Time (JIT) Manufacturing  Just-in-time (JIT) manufacturing, also known as just-in-time production or the Toyota Production System (TPS), is a methodology aimed primarily at reducing cycle times of various activities within production system as well as response times from suppliers and to customers.  JIT is seen as a more cost efficient method of maintaining stock levels.  Its purpose is to minimise the amount of goods you hold at any one time without compromising the production volumes.
  • 34. Project Management  Any project involves planning, scheduling and controlling a number of interrelated activities with use of limited resources, namely, men, machines, materials, money and time.  It is required that managers must have a dynamic planning and scheduling system to produce the best possible results and also to react immediately to the changing conditions and make necessary changes in the plan and schedule.
  • 36. Phases of Project Management  Planning: Planning involves setting the objectives of the project. Identifying various activities to be performed and determining the requirement of resources such as men, materials, machines, etc.  Scheduling: Based on the time estimates, the start and finish times for each activity are worked out by applying forward and backward pass techniques, critical path is identified, along with the slack and float for the non-critical paths.  Controlling: Controlling refers to analyzing and evaluating the actual progress against the plan. Reallocation of resources, crashing and review of projects with periodical reports are carried out.
  • 37. Project Network Analysis  Network Analysis is a system which plans the projects by analyzing the project activities.  Projects are broken down into individual tasks or activities, which are arranged in logical sequence.  A network diagram is prepared, which presents visually the relationship between all the activities involved and the cost for different activities.  Network analysis helps designing, planning, coordinating, controlling and in decision-making in order to accomplish the project economically in the minimum available time with the limited available resources.  The network analysis fulfils the objectives of reducing total time, cost, idle resources, interruptions and conflicts.
  • 38. Critical Path Method (CPM) In CPM activities are shown as a network of precedence relationships using activity-on- node network construction  Single estimate of activity time  Deterministic activity times USED IN:  Production management - for the jobs of repetitive in nature where the activity time estimates can be predicted with considerable certainty due to the existence of past experience.
  • 39. CPM calculation  Path : A connected sequence of activities leading from the starting event to the ending event  Critical Path : The longest path (time); determines the project duration  Critical Activities : All of the activities that make up the critical path
  • 40. Example  Draw a network for house construction project. The sequence of activities with their predecessors are given in table below. Activity Starting & Finishing Event Description of Activity Predecessor Time Duration (days) A (1,2) Prepare the house plan - 4 B (2,3) Cobstruct the house A 58 C (3,4) Fix the door / windows B 2 D (3,5) Wiring the house B 2 E (4,6) Paint the house C 1 F (5,6) Polish the doors / windows D 1 1 2 3 4 5 6 A E C D B F
  • 41. Programme Evaluation Review Technique (PERT) In PERT activities are shown as a network of precedence relationships using activity-on- arrow network construction  Multiple time estimates  Probabilistic activity times USED IN:  Project management - for non-repetitive jobs (research and development work), where the time and cost estimates tend to be quite uncertain. This technique uses probabilistic time estimates.
  • 42. Project Crashing  The process of shortening the time to complete a project is called crashing and is usually achieved by putting into service additional labour or machines to one activity or more activities.  Crashing involves more costs.  A project manager would like to speed up a project by spending as minimum extra cost as possible.  Project crashing seeks to minimize the extra cost for completion of a project before the stipulated time.
  • 43. Procedure for Crashing Step1: Draw the network diagram and mark the Normal time and Crash time. Step2: Calculate TE and TL for all the activities. Step3: Find the critical path and other paths. Step 4: Find the slope for all activities and rank them in ascending order. Step 5: Establish a tabular column with required field. Step 6: Select the lowest ranked activity; check whether it is a critical activity. If so,crash the activity, else go to the next highest ranked activity. Note: The critical path must remain critical while crashing. Step 7: Calculate the total cost of project for each crashing Step 8: Repeat Step 6 until all the activities in the critical path are fully crashed.