A STUDY ON LOW COST HOUSING CONSTRUCTION WITH DELAY
MANAGEMENT
Mr. I. Michael Raj1, Ms. M. Panimalar2
1Assistant Professor, Department of Civil Engineering, RVS Technical Campus, Coimbatore-641402, India,
2PG Student, Department of Civil Engineering, RVS Technical Campus, Coimbatore-641402, India.
---------------------------------------------------------------------***----------------------------------------------------------------------
Abstract - Low value housing construction technologies
aim to chop down construction value by victimization
alternatives to standard strategies and Input. “It is effective
budgeting and technique that facilitate in reducing value of
construction through use regionally obtainable material in
conjunction with improve skills and technology while not
sacrificing the strength, performance and life of structure.
’’Low value housing simply satisfies the foremost bottom
and basic human desires for shelter and neglects different
desires that individuals aim home as well as psychological,
social, and aesthetic desires and ultimately, need for self-
actualization. By victimization Low value Housing
Technologies we will scale back approx. 25% of the total
cost of housing. The problem of delays in industry may be a
world development and there's no exception. The main
purpose of this study is to spot the delay factors and also the
result on the project completion by doing a case study in in
progress comes. By analyzing the explanations for delay,
potential recommendations square measure given. The
major factors known during this case study square measure
delays thanks to contractor, consumer and conjointly thanks
to nature’s act like rain. The most important causes were
delays in contractor's payments, shortage of material in
construction, change in material, the weather condition,
shortage of manpower (skilled, semi-skilled and unskilled
labor ), frequent modification of staffs, poor web site
management and improper management of the engineers.
Some of the delays square measure delay in submission of
drawings, house constraints, and delay in payment by
consumer, delay in material offer and native issues like
strikes. The major effects of delay square measure value
impact, reduced labour productivity, postponement in work,
change in labour allocation etc. Not all delays may be
corrected; however few of them may be overcome by up
management responsibilities.
Key Words: Low cost housing construction, Delay
management, Delay analysis,
1. INTRODUCTION
Affordable housing could be a term won’t to
describe domicile units whose total housing price area
unit deemed “Affordable” to a bunch of individuals among
a given financial gain vary. In recent years, there has been
considerable debate over the definition of low cost
housing; low cost housing may be defined as a provision of
housing which caters to the requirements of lots among
their financial gain capabilities, while not sacrificing the
strength, performance and lifetime of the structure. India
is a developing country having only 20% population of
higher income group, who are able to afford normal
housing units. The low-income teams in developing
countries area unit usually unable to access the housing
market. As the 3 basic desires of individuals area unit food,
clothes and shelter so main objective is to provide one of
the basic need i.e. shelter to low income earner. Low cost
housing is a relative concept and has more to do with
budgeting and seeks to reduce construction cost through
better management, appropriate use of local materials,
skills and technology however while not sacrificing the
performance and structure life. Delays and disruptions
area among the challenges faced in the course of executing
construction projects. Delays in addition as disruptions
area unit sources of potential risks that current studies
area unit trying into ways that to manage. There is a
general exodus of rural population to the cities with the
fast manufacture in developing countries. The
infrastructure to support these cities, like buildings for
housing and business, mass transit for moving folks and
merchandise, and facilities for handling water and
sewerage would force large amounts of construction
2. LITERATURE REVIEW
Sunil Kumar (2002) studied the production of fly ash–
lime– gypsum (FaL-G) bricks and hollow blocks to solve
the problems of housing shortage and at the same time to
build houses economically by utilizing industrial wastes
and investigated the compressive strength, water
absorption, density and durability of these bricks and
hollow blocks. He observed that these bricks and hollow
blocks have sufficient strength for their use in low cost
housing development.
P K Adlakha and H C puri (2003) studied prefabrication
building methodologies for low cost housing by
highlighting the different prefabrication techniques, and
the economical advantages achieved by its adoption.
Vivian W.Y. Tam (2011) compared the construction cost
for the traditional and low cost housing technologies. He
compared the construction methods of walling, roofing
and lintel. Strength and durability of the structure,
stability, safety and mental satisfaction are factors that
assume top priority during cost reduction.
A K Jain and M C Paliwal (2012) gave an overview of the
housing status in India and adoption of appropriate and
cost effective technologies in the country.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 12 | Dec 2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 416
SenguptaNilanjan & Roy Souvanic (2013) studied the
acceptability and adaptability potential of different Eco-
friendly Construction Technologies through field survey,
literature study and technical calculations and tried to find
out the most appropriate one among those. From the
study and analysis concluded that Rat-trap bond wall and
Filler Slab roof would be the most appropriate and
acceptable CECT among people belonging to Middle
Income Group and below in India as they are satisfying all
their guiding criteria.
Amit D Chougule et al., (2015) described the literature
review studies and various results with context to
embedded energy, Design and durability, Cost effective,
Design optimization for filler slab. Compared to
conventional in situ RC slab, this technique is economical
and will result in saving of cement and steel and is an ideal
step towards generation of affordable housing, for
developing countries.
P PBhangale and Ajay K Mahajan (2015) examined the
cost effectiveness of using low cost housing technologies
in comparison with the traditional construction methods.
It was found that about 26.11% and 22.68% of the
construction cost, including material and labour cost, can
be saved by using the low cost housing technologies in
comparison with traditional construction methods for
walling and roofing respectively.
Bredenoord J, (2016), Measures concerning the physical
development of neighborhoods, such as urban density and
connectivity are equally as important as measures
concerning community development. The final comprise
support for community built organizations, small housing
cooperatives (or similar forms of cooperation) and
individual households – or small groups – that build and
increase their houses incrementally.
Frank Fugar, et al., (2010), This study investigates the
causes of delay of building construction projects in Ghana
to determine the most important according to the key
project participants; clients, consultants, and contractors.
Haseeb, (2007), The main objective of this study is the
identification of factors of delay and their effects on the
success and completion of project. The most common
factor of delay are natural disaster in Pakistan like flood
and earthquake and some others like financial and
payment problems, improper planning, poor site
management, insufficient experience, shortage of materials
and equipment etc. Several factors cause the overall delay
in the construction project such as some within
contractor’s liability and some are within owner’s liability.
It is hard to distinguish due to overlapping nature of the
events that which party or parties are responsible and
what ingredients of the delay cause. It is mostly seen that
delay problems are cause of dispute, negotiation, lawsuit,
total desertion, litigation and abandonment.
ZakiKraiem & James Dietmann(1987) Compensable
Delay is those which is within the control of, is the fault of,
or is due to the negligence of the owner. These delays can
occur under different situations. Excusable Delays are
those which occur when the contractor is delayed by
occurrences which are not attributable to either the
Contractor or owner.
F.Paceco torgal , Said jalai, (2012) Carried out study on
Earth construction and Building materials, it is observed
that in this paper earth construction has a major
expression in less developed countries .In order to
disclosure and highlight the importance of earth
construction this article reviews some environmental
benefits.
Ajibade Ayodeji Aibinu,(2006), The analyzed
quantitative data from completed building projects to
assess the extent of delays, and data obtained from a
postal questionnaire survey of construction managers to
assess the extent to which 44 identified factors
contributed to overall delays on a typical project they have
been involved with. The factors were finally categorized
into client-related; contractor-related; quantity surveyor-
related; architect-related; structural engineer related;
services engineer-related; supplier-related; subcontractor-
related; Delays not caused by the project participants
demarcated as “external factors”.
3. CONCLUSION
In the present study various technologies have
been studied such as Prefabrication, Economical Walling
System, Rat Trap Bond and Filler Slab Technology. Mass
housing targets can be achieved by replacing the
conventional methods of planning and executing building
operation based on special and individual needs and
accepting common denominator based on surveys,
population needs and rational use of materials and
resources. Adoption of any alternative technology on large
scale needs a guaranteed market to function and this
cannot be established unless the product is effective and
economical. Partial prefabrication is an approach towards
the above operation under controlled conditions. List of
suggestions in this study for reducing construction cost is
of general nature and it varies depending upon the nature
of the building to be constructed, budget of owner,
geographical location where the house is to be
constructed, availability of the building material, good
construction management practices etc. however it is
necessary that good planning and design methods shall be
adopted by utilizing the services of an experienced
engineer or an architect for supervising the work, thereby
achieving overall cost effectiveness to the extent of 25 %
in actual practice. The main causes of delay that affect
construction project. The most important causes identified
were: delay in payment by the head office, frequent change
of staffs, poor site management, improper management of
the engineers, delay in supply of material and lack of
manpower. Similarly the effects of these delays are: time
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 12 | Dec 2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 417
overruns cost overrun, negative social impact, idling
resources and disputes. An analysis of the responsibilities
of delay causes suggests that a joint effort based on
teamwork is required to overcome delays. In summary,
this project summarized some reasons behind the delays
caused in these sites and proposes some possible
recommendation to overcome those delays. Further
research is needed to investigate the limitations and
potential improvements to causes of delays within each
construction site.
REFERENCES
[1] A.K. Jain and M.C. Paliwal, “Adoption of Appropriate
and Cost Effective Technologies in Housing: Indian
Experience”, World Academy of Science, Engineering
and Technology, Vol. 6, 169-171, 2012.
[2] Ajibade Ayodeji Aibinu and Henry Agboola Odeyinka,
(2006) “Construction Delays and Their Causative
Factors in Nigeria”, Research Scholar, School of Design
and Environment, Dept. of Building, National Univ. of
Singapore, Vol. 132
[3] Amit D Chougule, Manoj H Mota and Ushadevi S Patil,
“To Study the Filler Slab as Alternative Construction
Technology - a review”, Journal Of Information,
Knowledge And Research In Civil Engineering, Vol. 2,
Issue 3, 199-202, 2015.
[4] Bredenoord J, (2016), “Sustainable Housing and
Building Materials for Low-income Households”, Jr
ArchitEng Tech 5: 158.
[5] F.Paceco torgal, Said jalai, (2012), “Construction &
building materials, Construction & building materials”,
29, pp-512-519.
[6] Frank Fugar, and Adwoa Agyakwah-Baah. (2010),
“Delays In Building Construction Projects In Ghana ”,
Department Of Building Technology, Kwame Nkrumah
University Of Science And Technology, Kumasi, Ghana,
10 (1/2) 103‐116
[7] Haseeb, (2007), “ Problems Of Projects And Effects Of
Delays In The Construction Industry Of Pakistan ”
College Of Public Administration, Huazhong University
Of Science And Technology, Wuhan, P.R. China Vol.1
[8] P K Adlakha and H C Puri, “Prefabrication Building
Methodologies for Low Cost Housing”, IE Journal, AR,
Vol. 84, 4-9, 2013.
[9] P.P. Bhangale and Ajay K. Mahajan, “Cost Reduction
through Cost Effective Construction Techniques”,
International Journal of Science and Research, Vol. 4,
Issue 2, 2167-2169, 2015.
[10] SenguptaNilanjan and Roy Souvanic, “Study of
Appropriateness of Cost-Effective Building
Construction Technologies in Housing Sector in India”,
JAET, Vol. 2, Issue 2, 2013.
[11] Sunil Kumar, “A Perspective Study on Fly Ash-Lime-
Gypsum Bricks and Hollow Blocks for Low Cost
Housing Development”, ELSEVIER, Construction and
Building Material 16, 519-525, 2002.
[12] Vivian W.Y. Tam, “Cost Effectiveness of using Low
Cost Housing Technologies in Construction”,
ELSEVIER, Procedia Engineering 14, 156-160, 2011.
[13] Zaki Kraiem and James Diekmann. (1987),
“Concurrent Delays In Construction Projects”, Member
Of ASCE, Vol. 113.

More Related Content

What's hot

Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
eSAT Journals
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
IRJET Journal
 
Green Building Effect in Commercial Building
Green Building Effect in Commercial Building Green Building Effect in Commercial Building
Green Building Effect in Commercial Building
vivatechijri
 
Cost Control on Construction with Maximum Usage of Ecofriendly Materials
Cost Control on Construction with Maximum Usage of Ecofriendly MaterialsCost Control on Construction with Maximum Usage of Ecofriendly Materials
Cost Control on Construction with Maximum Usage of Ecofriendly Materials
IRJET Journal
 
M012329497
M012329497M012329497
M012329497
IOSR Journals
 
IJSRED-V2I3P76
IJSRED-V2I3P76IJSRED-V2I3P76
IJSRED-V2I3P76
IJSRED
 
Attitude of Construction Participants on Building Materials Wastage
Attitude of Construction Participants on Building Materials WastageAttitude of Construction Participants on Building Materials Wastage
Attitude of Construction Participants on Building Materials Wastage
IRJET Journal
 
R01231110116
R01231110116R01231110116
R01231110116
IOSR Journals
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET Journal
 
Performance Evaluation of Cost Saving Towards Sustainability in Traditional C...
Performance Evaluation of Cost Saving Towards Sustainability in Traditional C...Performance Evaluation of Cost Saving Towards Sustainability in Traditional C...
Performance Evaluation of Cost Saving Towards Sustainability in Traditional C...
IJRESJOURNAL
 
33 article text-127-1-10-20181005
33 article text-127-1-10-2018100533 article text-127-1-10-20181005
33 article text-127-1-10-20181005
Dr.Madhav Prasad Koirala
 
REHABILITATION/RETROFITING OF CONCRETE STRUCTURES ALONG WITH CASE STUDY
REHABILITATION/RETROFITING OF CONCRETE STRUCTURES ALONG WITH CASE STUDYREHABILITATION/RETROFITING OF CONCRETE STRUCTURES ALONG WITH CASE STUDY
REHABILITATION/RETROFITING OF CONCRETE STRUCTURES ALONG WITH CASE STUDY
civej
 
Architects requirements of decision support tools to deliver low impact housi...
Architects requirements of decision support tools to deliver low impact housi...Architects requirements of decision support tools to deliver low impact housi...
Architects requirements of decision support tools to deliver low impact housi...
Alexander Decker
 
IRJET- Replacement of Aggregate by C&D Waste Concrete
IRJET- Replacement of Aggregate by C&D Waste ConcreteIRJET- Replacement of Aggregate by C&D Waste Concrete
IRJET- Replacement of Aggregate by C&D Waste Concrete
IRJET Journal
 
Review of green building demand factors for malaysia
Review of green building demand factors for malaysiaReview of green building demand factors for malaysia
Review of green building demand factors for malaysia
Alexander Decker
 
Effects of Construction Materials to Achieve Sustainable Buildings
Effects of Construction Materials to Achieve Sustainable BuildingsEffects of Construction Materials to Achieve Sustainable Buildings
Effects of Construction Materials to Achieve Sustainable Buildings
Dr. Amarjeet Singh
 
IRJET- Low Cost Housing
IRJET- Low Cost HousingIRJET- Low Cost Housing
IRJET- Low Cost Housing
IRJET Journal
 
Management of government funded construction projects in ghana
Management of government funded construction projects in ghanaManagement of government funded construction projects in ghana
Management of government funded construction projects in ghana
Alexander Decker
 
Final paper rizky citra islami
Final paper  rizky citra islamiFinal paper  rizky citra islami
Final paper rizky citra islami
Rizky Islami
 
IRJET- Interface Management and its Effect on Project Complexity in Constr...
IRJET- 	  Interface Management and its Effect on Project Complexity in Constr...IRJET- 	  Interface Management and its Effect on Project Complexity in Constr...
IRJET- Interface Management and its Effect on Project Complexity in Constr...
IRJET Journal
 

What's hot (20)

Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
 
Green Building Effect in Commercial Building
Green Building Effect in Commercial Building Green Building Effect in Commercial Building
Green Building Effect in Commercial Building
 
Cost Control on Construction with Maximum Usage of Ecofriendly Materials
Cost Control on Construction with Maximum Usage of Ecofriendly MaterialsCost Control on Construction with Maximum Usage of Ecofriendly Materials
Cost Control on Construction with Maximum Usage of Ecofriendly Materials
 
M012329497
M012329497M012329497
M012329497
 
IJSRED-V2I3P76
IJSRED-V2I3P76IJSRED-V2I3P76
IJSRED-V2I3P76
 
Attitude of Construction Participants on Building Materials Wastage
Attitude of Construction Participants on Building Materials WastageAttitude of Construction Participants on Building Materials Wastage
Attitude of Construction Participants on Building Materials Wastage
 
R01231110116
R01231110116R01231110116
R01231110116
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
 
Performance Evaluation of Cost Saving Towards Sustainability in Traditional C...
Performance Evaluation of Cost Saving Towards Sustainability in Traditional C...Performance Evaluation of Cost Saving Towards Sustainability in Traditional C...
Performance Evaluation of Cost Saving Towards Sustainability in Traditional C...
 
33 article text-127-1-10-20181005
33 article text-127-1-10-2018100533 article text-127-1-10-20181005
33 article text-127-1-10-20181005
 
REHABILITATION/RETROFITING OF CONCRETE STRUCTURES ALONG WITH CASE STUDY
REHABILITATION/RETROFITING OF CONCRETE STRUCTURES ALONG WITH CASE STUDYREHABILITATION/RETROFITING OF CONCRETE STRUCTURES ALONG WITH CASE STUDY
REHABILITATION/RETROFITING OF CONCRETE STRUCTURES ALONG WITH CASE STUDY
 
Architects requirements of decision support tools to deliver low impact housi...
Architects requirements of decision support tools to deliver low impact housi...Architects requirements of decision support tools to deliver low impact housi...
Architects requirements of decision support tools to deliver low impact housi...
 
IRJET- Replacement of Aggregate by C&D Waste Concrete
IRJET- Replacement of Aggregate by C&D Waste ConcreteIRJET- Replacement of Aggregate by C&D Waste Concrete
IRJET- Replacement of Aggregate by C&D Waste Concrete
 
Review of green building demand factors for malaysia
Review of green building demand factors for malaysiaReview of green building demand factors for malaysia
Review of green building demand factors for malaysia
 
Effects of Construction Materials to Achieve Sustainable Buildings
Effects of Construction Materials to Achieve Sustainable BuildingsEffects of Construction Materials to Achieve Sustainable Buildings
Effects of Construction Materials to Achieve Sustainable Buildings
 
IRJET- Low Cost Housing
IRJET- Low Cost HousingIRJET- Low Cost Housing
IRJET- Low Cost Housing
 
Management of government funded construction projects in ghana
Management of government funded construction projects in ghanaManagement of government funded construction projects in ghana
Management of government funded construction projects in ghana
 
Final paper rizky citra islami
Final paper  rizky citra islamiFinal paper  rizky citra islami
Final paper rizky citra islami
 
IRJET- Interface Management and its Effect on Project Complexity in Constr...
IRJET- 	  Interface Management and its Effect on Project Complexity in Constr...IRJET- 	  Interface Management and its Effect on Project Complexity in Constr...
IRJET- Interface Management and its Effect on Project Complexity in Constr...
 

Similar to IRJET- A Study on Low Cost Housing Construction with Delay Management

IRJET- Cost Estimation of a Building using Cost Effective Building Materials
IRJET-  	  Cost Estimation of a Building using Cost Effective Building MaterialsIRJET-  	  Cost Estimation of a Building using Cost Effective Building Materials
IRJET- Cost Estimation of a Building using Cost Effective Building Materials
IRJET Journal
 
L012238891
L012238891L012238891
L012238891
IOSR Journals
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
IRJET Journal
 
Construction Standards of Residential Buildings Post Handover
Construction Standards of Residential Buildings Post HandoverConstruction Standards of Residential Buildings Post Handover
Construction Standards of Residential Buildings Post Handover
IRJET Journal
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
IAEME Publication
 
IRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction ProjectsIRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction Projects
IRJET Journal
 
The Impact of Project Environment Study on Sustainable Change Control: A Case...
The Impact of Project Environment Study on Sustainable Change Control: A Case...The Impact of Project Environment Study on Sustainable Change Control: A Case...
The Impact of Project Environment Study on Sustainable Change Control: A Case...
IRJET Journal
 
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
IRJET Journal
 
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET Journal
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delay
Est
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
IJERA Editor
 
IRJET - Failure in Commercial Building and Management - Case Study
IRJET - Failure in Commercial Building and Management - Case StudyIRJET - Failure in Commercial Building and Management - Case Study
IRJET - Failure in Commercial Building and Management - Case Study
IRJET Journal
 
Review Application of value engineering in construction project.
Review Application of value engineering in construction project.Review Application of value engineering in construction project.
Review Application of value engineering in construction project.
IRJET Journal
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET Journal
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Sankalp Swarnkar
 
20320140503023
2032014050302320320140503023
20320140503023
IAEME Publication
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
Rick Vogel
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET Journal
 
Dual Engineering And Integrated Product Development
Dual Engineering And Integrated Product DevelopmentDual Engineering And Integrated Product Development
Dual Engineering And Integrated Product Development
Tracy Berry
 
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET Journal
 

Similar to IRJET- A Study on Low Cost Housing Construction with Delay Management (20)

IRJET- Cost Estimation of a Building using Cost Effective Building Materials
IRJET-  	  Cost Estimation of a Building using Cost Effective Building MaterialsIRJET-  	  Cost Estimation of a Building using Cost Effective Building Materials
IRJET- Cost Estimation of a Building using Cost Effective Building Materials
 
L012238891
L012238891L012238891
L012238891
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
 
Construction Standards of Residential Buildings Post Handover
Construction Standards of Residential Buildings Post HandoverConstruction Standards of Residential Buildings Post Handover
Construction Standards of Residential Buildings Post Handover
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
 
IRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction ProjectsIRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction Projects
 
The Impact of Project Environment Study on Sustainable Change Control: A Case...
The Impact of Project Environment Study on Sustainable Change Control: A Case...The Impact of Project Environment Study on Sustainable Change Control: A Case...
The Impact of Project Environment Study on Sustainable Change Control: A Case...
 
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
 
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delay
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
 
IRJET - Failure in Commercial Building and Management - Case Study
IRJET - Failure in Commercial Building and Management - Case StudyIRJET - Failure in Commercial Building and Management - Case Study
IRJET - Failure in Commercial Building and Management - Case Study
 
Review Application of value engineering in construction project.
Review Application of value engineering in construction project.Review Application of value engineering in construction project.
Review Application of value engineering in construction project.
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
20320140503023
2032014050302320320140503023
20320140503023
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
 
Dual Engineering And Integrated Product Development
Dual Engineering And Integrated Product DevelopmentDual Engineering And Integrated Product Development
Dual Engineering And Integrated Product Development
 
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
IRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
IRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
IRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
IRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
IRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
IRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
IRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Supermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdfSupermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdf
Kamal Acharya
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
VANDANAMOHANGOUDA
 
5G Radio Network Througput Problem Analysis HCIA.pdf
5G Radio Network Througput Problem Analysis HCIA.pdf5G Radio Network Througput Problem Analysis HCIA.pdf
5G Radio Network Througput Problem Analysis HCIA.pdf
AlvianRamadhani5
 
Open Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surfaceOpen Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surface
Indrajeet sahu
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
21UME003TUSHARDEB
 
SCALING OF MOS CIRCUITS m .pptx
SCALING OF MOS CIRCUITS m                 .pptxSCALING OF MOS CIRCUITS m                 .pptx
SCALING OF MOS CIRCUITS m .pptx
harshapolam10
 
Pressure Relief valve used in flow line to release the over pressure at our d...
Pressure Relief valve used in flow line to release the over pressure at our d...Pressure Relief valve used in flow line to release the over pressure at our d...
Pressure Relief valve used in flow line to release the over pressure at our d...
cannyengineerings
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
upoux
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
Prakhyath Rai
 
AI-Based Home Security System : Home security
AI-Based Home Security System : Home securityAI-Based Home Security System : Home security
AI-Based Home Security System : Home security
AIRCC Publishing Corporation
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Sinan KOZAK
 
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
upoux
 
TIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptxTIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptx
CVCSOfficial
 
Mechatronics material . Mechanical engineering
Mechatronics material . Mechanical engineeringMechatronics material . Mechanical engineering
Mechatronics material . Mechanical engineering
sachin chaurasia
 
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Transcat
 
Height and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdfHeight and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdf
q30122000
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
Roger Rozario
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...
Prakhyath Rai
 

Recently uploaded (20)

Supermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdfSupermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdf
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
 
5G Radio Network Througput Problem Analysis HCIA.pdf
5G Radio Network Througput Problem Analysis HCIA.pdf5G Radio Network Througput Problem Analysis HCIA.pdf
5G Radio Network Througput Problem Analysis HCIA.pdf
 
Open Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surfaceOpen Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surface
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
 
SCALING OF MOS CIRCUITS m .pptx
SCALING OF MOS CIRCUITS m                 .pptxSCALING OF MOS CIRCUITS m                 .pptx
SCALING OF MOS CIRCUITS m .pptx
 
Pressure Relief valve used in flow line to release the over pressure at our d...
Pressure Relief valve used in flow line to release the over pressure at our d...Pressure Relief valve used in flow line to release the over pressure at our d...
Pressure Relief valve used in flow line to release the over pressure at our d...
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
 
AI-Based Home Security System : Home security
AI-Based Home Security System : Home securityAI-Based Home Security System : Home security
AI-Based Home Security System : Home security
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
 
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
 
TIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptxTIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptx
 
Mechatronics material . Mechanical engineering
Mechatronics material . Mechanical engineeringMechatronics material . Mechanical engineering
Mechatronics material . Mechanical engineering
 
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
 
Height and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdfHeight and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdf
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...
 

IRJET- A Study on Low Cost Housing Construction with Delay Management

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 12 | Dec 2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 415 A STUDY ON LOW COST HOUSING CONSTRUCTION WITH DELAY MANAGEMENT Mr. I. Michael Raj1, Ms. M. Panimalar2 1Assistant Professor, Department of Civil Engineering, RVS Technical Campus, Coimbatore-641402, India, 2PG Student, Department of Civil Engineering, RVS Technical Campus, Coimbatore-641402, India. ---------------------------------------------------------------------***---------------------------------------------------------------------- Abstract - Low value housing construction technologies aim to chop down construction value by victimization alternatives to standard strategies and Input. “It is effective budgeting and technique that facilitate in reducing value of construction through use regionally obtainable material in conjunction with improve skills and technology while not sacrificing the strength, performance and life of structure. ’’Low value housing simply satisfies the foremost bottom and basic human desires for shelter and neglects different desires that individuals aim home as well as psychological, social, and aesthetic desires and ultimately, need for self- actualization. By victimization Low value Housing Technologies we will scale back approx. 25% of the total cost of housing. The problem of delays in industry may be a world development and there's no exception. The main purpose of this study is to spot the delay factors and also the result on the project completion by doing a case study in in progress comes. By analyzing the explanations for delay, potential recommendations square measure given. The major factors known during this case study square measure delays thanks to contractor, consumer and conjointly thanks to nature’s act like rain. The most important causes were delays in contractor's payments, shortage of material in construction, change in material, the weather condition, shortage of manpower (skilled, semi-skilled and unskilled labor ), frequent modification of staffs, poor web site management and improper management of the engineers. Some of the delays square measure delay in submission of drawings, house constraints, and delay in payment by consumer, delay in material offer and native issues like strikes. The major effects of delay square measure value impact, reduced labour productivity, postponement in work, change in labour allocation etc. Not all delays may be corrected; however few of them may be overcome by up management responsibilities. Key Words: Low cost housing construction, Delay management, Delay analysis, 1. INTRODUCTION Affordable housing could be a term won’t to describe domicile units whose total housing price area unit deemed “Affordable” to a bunch of individuals among a given financial gain vary. In recent years, there has been considerable debate over the definition of low cost housing; low cost housing may be defined as a provision of housing which caters to the requirements of lots among their financial gain capabilities, while not sacrificing the strength, performance and lifetime of the structure. India is a developing country having only 20% population of higher income group, who are able to afford normal housing units. The low-income teams in developing countries area unit usually unable to access the housing market. As the 3 basic desires of individuals area unit food, clothes and shelter so main objective is to provide one of the basic need i.e. shelter to low income earner. Low cost housing is a relative concept and has more to do with budgeting and seeks to reduce construction cost through better management, appropriate use of local materials, skills and technology however while not sacrificing the performance and structure life. Delays and disruptions area among the challenges faced in the course of executing construction projects. Delays in addition as disruptions area unit sources of potential risks that current studies area unit trying into ways that to manage. There is a general exodus of rural population to the cities with the fast manufacture in developing countries. The infrastructure to support these cities, like buildings for housing and business, mass transit for moving folks and merchandise, and facilities for handling water and sewerage would force large amounts of construction 2. LITERATURE REVIEW Sunil Kumar (2002) studied the production of fly ash– lime– gypsum (FaL-G) bricks and hollow blocks to solve the problems of housing shortage and at the same time to build houses economically by utilizing industrial wastes and investigated the compressive strength, water absorption, density and durability of these bricks and hollow blocks. He observed that these bricks and hollow blocks have sufficient strength for their use in low cost housing development. P K Adlakha and H C puri (2003) studied prefabrication building methodologies for low cost housing by highlighting the different prefabrication techniques, and the economical advantages achieved by its adoption. Vivian W.Y. Tam (2011) compared the construction cost for the traditional and low cost housing technologies. He compared the construction methods of walling, roofing and lintel. Strength and durability of the structure, stability, safety and mental satisfaction are factors that assume top priority during cost reduction. A K Jain and M C Paliwal (2012) gave an overview of the housing status in India and adoption of appropriate and cost effective technologies in the country.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 12 | Dec 2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 416 SenguptaNilanjan & Roy Souvanic (2013) studied the acceptability and adaptability potential of different Eco- friendly Construction Technologies through field survey, literature study and technical calculations and tried to find out the most appropriate one among those. From the study and analysis concluded that Rat-trap bond wall and Filler Slab roof would be the most appropriate and acceptable CECT among people belonging to Middle Income Group and below in India as they are satisfying all their guiding criteria. Amit D Chougule et al., (2015) described the literature review studies and various results with context to embedded energy, Design and durability, Cost effective, Design optimization for filler slab. Compared to conventional in situ RC slab, this technique is economical and will result in saving of cement and steel and is an ideal step towards generation of affordable housing, for developing countries. P PBhangale and Ajay K Mahajan (2015) examined the cost effectiveness of using low cost housing technologies in comparison with the traditional construction methods. It was found that about 26.11% and 22.68% of the construction cost, including material and labour cost, can be saved by using the low cost housing technologies in comparison with traditional construction methods for walling and roofing respectively. Bredenoord J, (2016), Measures concerning the physical development of neighborhoods, such as urban density and connectivity are equally as important as measures concerning community development. The final comprise support for community built organizations, small housing cooperatives (or similar forms of cooperation) and individual households – or small groups – that build and increase their houses incrementally. Frank Fugar, et al., (2010), This study investigates the causes of delay of building construction projects in Ghana to determine the most important according to the key project participants; clients, consultants, and contractors. Haseeb, (2007), The main objective of this study is the identification of factors of delay and their effects on the success and completion of project. The most common factor of delay are natural disaster in Pakistan like flood and earthquake and some others like financial and payment problems, improper planning, poor site management, insufficient experience, shortage of materials and equipment etc. Several factors cause the overall delay in the construction project such as some within contractor’s liability and some are within owner’s liability. It is hard to distinguish due to overlapping nature of the events that which party or parties are responsible and what ingredients of the delay cause. It is mostly seen that delay problems are cause of dispute, negotiation, lawsuit, total desertion, litigation and abandonment. ZakiKraiem & James Dietmann(1987) Compensable Delay is those which is within the control of, is the fault of, or is due to the negligence of the owner. These delays can occur under different situations. Excusable Delays are those which occur when the contractor is delayed by occurrences which are not attributable to either the Contractor or owner. F.Paceco torgal , Said jalai, (2012) Carried out study on Earth construction and Building materials, it is observed that in this paper earth construction has a major expression in less developed countries .In order to disclosure and highlight the importance of earth construction this article reviews some environmental benefits. Ajibade Ayodeji Aibinu,(2006), The analyzed quantitative data from completed building projects to assess the extent of delays, and data obtained from a postal questionnaire survey of construction managers to assess the extent to which 44 identified factors contributed to overall delays on a typical project they have been involved with. The factors were finally categorized into client-related; contractor-related; quantity surveyor- related; architect-related; structural engineer related; services engineer-related; supplier-related; subcontractor- related; Delays not caused by the project participants demarcated as “external factors”. 3. CONCLUSION In the present study various technologies have been studied such as Prefabrication, Economical Walling System, Rat Trap Bond and Filler Slab Technology. Mass housing targets can be achieved by replacing the conventional methods of planning and executing building operation based on special and individual needs and accepting common denominator based on surveys, population needs and rational use of materials and resources. Adoption of any alternative technology on large scale needs a guaranteed market to function and this cannot be established unless the product is effective and economical. Partial prefabrication is an approach towards the above operation under controlled conditions. List of suggestions in this study for reducing construction cost is of general nature and it varies depending upon the nature of the building to be constructed, budget of owner, geographical location where the house is to be constructed, availability of the building material, good construction management practices etc. however it is necessary that good planning and design methods shall be adopted by utilizing the services of an experienced engineer or an architect for supervising the work, thereby achieving overall cost effectiveness to the extent of 25 % in actual practice. The main causes of delay that affect construction project. The most important causes identified were: delay in payment by the head office, frequent change of staffs, poor site management, improper management of the engineers, delay in supply of material and lack of manpower. Similarly the effects of these delays are: time
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 12 | Dec 2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 417 overruns cost overrun, negative social impact, idling resources and disputes. An analysis of the responsibilities of delay causes suggests that a joint effort based on teamwork is required to overcome delays. In summary, this project summarized some reasons behind the delays caused in these sites and proposes some possible recommendation to overcome those delays. Further research is needed to investigate the limitations and potential improvements to causes of delays within each construction site. REFERENCES [1] A.K. Jain and M.C. Paliwal, “Adoption of Appropriate and Cost Effective Technologies in Housing: Indian Experience”, World Academy of Science, Engineering and Technology, Vol. 6, 169-171, 2012. [2] Ajibade Ayodeji Aibinu and Henry Agboola Odeyinka, (2006) “Construction Delays and Their Causative Factors in Nigeria”, Research Scholar, School of Design and Environment, Dept. of Building, National Univ. of Singapore, Vol. 132 [3] Amit D Chougule, Manoj H Mota and Ushadevi S Patil, “To Study the Filler Slab as Alternative Construction Technology - a review”, Journal Of Information, Knowledge And Research In Civil Engineering, Vol. 2, Issue 3, 199-202, 2015. [4] Bredenoord J, (2016), “Sustainable Housing and Building Materials for Low-income Households”, Jr ArchitEng Tech 5: 158. [5] F.Paceco torgal, Said jalai, (2012), “Construction & building materials, Construction & building materials”, 29, pp-512-519. [6] Frank Fugar, and Adwoa Agyakwah-Baah. (2010), “Delays In Building Construction Projects In Ghana ”, Department Of Building Technology, Kwame Nkrumah University Of Science And Technology, Kumasi, Ghana, 10 (1/2) 103‐116 [7] Haseeb, (2007), “ Problems Of Projects And Effects Of Delays In The Construction Industry Of Pakistan ” College Of Public Administration, Huazhong University Of Science And Technology, Wuhan, P.R. China Vol.1 [8] P K Adlakha and H C Puri, “Prefabrication Building Methodologies for Low Cost Housing”, IE Journal, AR, Vol. 84, 4-9, 2013. [9] P.P. Bhangale and Ajay K. Mahajan, “Cost Reduction through Cost Effective Construction Techniques”, International Journal of Science and Research, Vol. 4, Issue 2, 2167-2169, 2015. [10] SenguptaNilanjan and Roy Souvanic, “Study of Appropriateness of Cost-Effective Building Construction Technologies in Housing Sector in India”, JAET, Vol. 2, Issue 2, 2013. [11] Sunil Kumar, “A Perspective Study on Fly Ash-Lime- Gypsum Bricks and Hollow Blocks for Low Cost Housing Development”, ELSEVIER, Construction and Building Material 16, 519-525, 2002. [12] Vivian W.Y. Tam, “Cost Effectiveness of using Low Cost Housing Technologies in Construction”, ELSEVIER, Procedia Engineering 14, 156-160, 2011. [13] Zaki Kraiem and James Diekmann. (1987), “Concurrent Delays In Construction Projects”, Member Of ASCE, Vol. 113.