SlideShare a Scribd company logo
1
2
Indigenisation of Russian Make
Waste Heat Boilers System
Our Experience
1. Salim G Purushothaman, AGM, Vizag Steel
2. B. Ravishankar, Manager, Vizag Steel
3. Jeevan Kumar, Assistant Manager, Vizag Steel
3
Waste Heat
Heat Evolved from Dry Quenching of
Metallurgical Coke Produced In House
Quenching Medium – Circulating Nitrogen
Before Recovery - 800 Deg C
After Recovery - 160 Deg C
9 x 80,000 N Cu M/Hr
TOTAL Net HEAT AVAILABILITY = 124 G Cal/Hr
4
Metallurgical Coke
Required for Smelting Iron Ore in Blast Furnace
Each Ton of Hot Metal Produced needs Half Ton Coke
We make Aprox 8500 Tons a Day
5
COKE MAKING
Destructive Distillation of Low Ash Coal
- Heating Coal in the absence of Air to 1100 Deg C
Thus expelling all volatiles
To obtain Porous Carbon Concentrate, COKE
Made in Coke Ovens
6
Coke Ovens
Coal Charged
Part of A Battery – Coke Ovens
Coking Time /Oven - 16 Hours
1 Battery – 67 Ovens
Batteries - 4
Rated Production– 100Pushings/Day/Battery
1 Oven – 32 Ton Coal to 25 Tons Coke
7
Our Coke Oven Battery
Total Such Batteries in VSP – 4 Numbers
8
Coke Produced
Collected In Buckets, 1 Pushout = 25Tons Coke
Temperature = 1000 to 1100 Deg C
Nature - Incandescent
9
Need to Quench Coke
Coke to be Shipped to Blast Furnace
Shipment through Conveyors
Temperatures above 180Degrees Burns Conveyor
For Safety of Conveyor and Handling
Coke to be Quenched to 160 Deg C
Implication:
350 M Cal Heat /Ton Coke to be Removed
10
Types of Quenching
Cooling Water
Coke Car
1.WET Quenching
All Heat – Lost
Pollution - Severe
11
Types of Quenching
2. DRY Quenching
All Heat –Recovered
Pollution- Eliminated
12
DRY vs WET (Quenching)
13
CDCP Blocks of VSP
14
RUSSIAN BOILERS OF CDCP
• Commissioned in 1986-87
• Make: Belgorod Power , Russia (Erstwhile USSR)
• Model : KCTK 39/440
• Type : Drum, Forced Circulation
• Rating : 39 Bar, 440 Deg C , 25.5 TPH MCR
• Gas Flow Rate : 80 000 N CuM/Hr
• Hot Gas Inlet : 800 Deg C
• Cooled Gas Outlet : 160 Deg C
• Construction : Twin Shaft , Refractory walled , Counter Flow Eco, & Evap
15
RUSSIAN BOILERS OF CDCP
16
SIDE VIEW
To Drum
From
Circulation Pump
Output
SH
Steam,
39 Bar
17
RUSSIAN BOILERS OF CDCP
18
Problems Faced
• Heavy Erosion – at Riser Tubes
-- at Evaporator side Bends
• Bi Metallic Corrosion – Bracket Area of Evap Top
Bundle
• 2 Days Cooling Time for shutdown inspections
• No access to inspect Sides of Bundles
• Frequent damages to Refractory lining due to
cyclic stresses, causing forced outages
19
Problems Faced
• Heavy Erosion – at Riser Tubes
-- at Evaporator side Bends
• Bi Metallic Corrosion – Bracket Area of Evap Top
Bundle
• 2 Days Cooling Time for shutdown inspections
• No access to inspect Sides of Bundles
• Frequent damages to Refractory lining due to
cyclic stresses, causing forced outages
20
Gas Erosion
• Evaporator Cross Section = 3.8 x 3.66 = 13.9 sqM
• Projected Area of Tubes =
100 Nos x 28mm x 3.6 M long = 10.1 sq M
NET FLOW AREA = 3.8 sq M
Gas Flow Rate = 80,000 NCuM/Hr
Gas Velocity = 80000/3.8/3600 = 5.85 m/Sec
Dust Loading = 5-10 gm/N CuM of Gas
21
RISER TUBES
22
SIDE BENDS
SIDE WALL
23
Erosion – of Evaporator side Bends
24
Improvement Plan
• Immediate:
1. Baffled the Bends to protect them
2. Shielded the Riser tubes by providing Armour plate upstream
• Long Term:
1. Monitor Tube Thinning & Schedule for Phased Replacement
2. Indigenisation of tubes with Erosion Resistant Indian Makes
• Futuristic:
Future Boilers for Plant Expansion to have lesser gas
Velocity.
25
SIDE BENDS
SIDE WALL
Side Baffles
26
Trigger For Tube Replacement
• Annual Tube Thickness Survey with D Meter
• Monitoring of Thinning Trend with recorded D Meter Readings
• Forecasting Thinning Rate and Procurement of Spare Tubes
• Determined value of Residual thickness to replace Tubes as
- 1.9 to 2.0 mm for Straight Part
- 1.8 mm at Bends ( Based on IBR Regn 338)
Tubes = OD 28 mm , Seamless
Original Thickness = 3mm Nominal with +0 , -10% Tolerance (GOST)
Calculated Thickness for Working Pr of 47 Bar as per GOST = 0.64 mm
Calculated Thickness for Working Pr of 47 Bar as per IBR = 1.31mm,
But Required Minimum Thickness for Coil Tubes, For Forced Circulation
and Tube OD < 29 mm = 1.62 mm (IBR Reg 338, b)
27
Towards Indigenisation
• Evaporator Top Coils – 15 XM (GOST)
• Evaporator Other Coils – Steel 20 (GOST)
•Evaporator Service Conditions:
Water Temp – 270 Deg Max,
Pressure 47 Bar Max (Excess Condition)
MCR: Inlet 46 Bar, Outlet 43 Bar
Outside Temp – 800 Deg Max
Material Testing Done in our own Laboratory – QATD Dept of VSP
•Hardness
Brinnell Hardness value Varied
from 130 to 135 sample to
sample
ie Rockwell B (HRB) 72 to 75
28
Material Selection
• Involved Plant Design Dept , & QATD Dept of VSP
• Consulted Dy Chief Inspector of Boilers , Visakhapatnam
• Furnished Sample tubes to BHEL
• Advice of Design Engineers from BHEL
Objectives
# Medium Carbon Steel for Evaporator service ; C = 0.2 to 0.25 % range
# Hardness to be around 80 HRB to be more resistant to Erosion
# At the same time % Elongation to be minimum 27% - Bends to be safe
in repeated Thermal Cycling (Bend R = 2D)
# Economy
29
Material Selection
• SA 192
SA 210 Gr A1
SA 210 Gr C
SA 213 T11
Selected SA 210 Gr A1- CDS
• Hardness > 75 HRB; CDS will have more due
to work hardening.
• % Elongation = 30% Better Flexibility for Bends
• Thickness : Always > 3mm (as Tol = +20%, - 0%)
• Easy Availability, Weldability
Considered
Plant Design Dept of VSP Developed Tender Drawings accordingly
for Procurement of Spares from Indian Market
30
Bundle Replacement
• Thickness Reduction found reaching Threshold in
Two Boilers during Annual Thickness Survey
(Residual thickness, 2.2 mm against Normal 3 mm)
• Procurement Action Initiated . Planned to Replace
next Year
Year : 2000
31
Bundle Replacement
• Residual Thickness varied from 1.9 to 2.1- Time to Replace!
• Dy Chief Inspector of Boilers advised Evaporator Bundle
Replacement
• Replacement Program was approved by DOB , Hyderabad
• First Indegeneous Coil Bundle Erected in one of the Boilers in
2001
Erosion Rate Drastically Reduced in that Boiler Ever since
Thereafter All Russian Boilers underwent Indigenisation of Coils
Including Economiser Coils
Over a 10 Year Period
Year : 2001
32
New CDCP Boiler Installation
• 2002-03 Planning for Capacity Expansion involving new Coke Oven
Battery
• Plan Entailed 4 More CDCP Boilers with similar Capacity
• Desired to have Design Gas Velocity as minimum as possible
• Thermax Pune Introduced the idea of Single Shaft CDCP Boilers
– As Working in Vental Steel Plant,Russia - Designed by a Finnish
Corporation Rautaruukki
– Thermax offering such CDCP Boilers to Neelanchal Ispat, Orissa
33
Rautaruukki Design
• Retains the Elevation of Gas Entry Axis; Overall
Height increased
• Water Wall with Natural Circulation and Evaporators
with Forced Circulation.
• Overall Foot Print within Russian CDCP Boiler’s
• Bigger Tubes
• Bigger Pitches –Longitudinal & Transverse
• Cross Section Area gets doubled almost but Projected
area of Coils is reduced by reduction in tubings ( HSA
requirement curtailed by Water Wall).
• Marginal increase only in Overall HSA
CIRCULATING GAS VELOCITY REDUCTION OF 30 %
34
New CDCP Boiler Installation
• Thermax designed Single Shaft CDCP Boiler for NINL
• We inspected Thermax Boilers at NINL : During their
Erection & Commissioning (Consultant MECON)
• Their Operation was found satisfactory
• Decided to Opt for Single Shaft Boilers; Made Specs
accordingly , under Consultancy of MECON, &
Tendered out.
• Thermal Systems, Hyderabad Bagged the Order (L-1) for
Design ,Supply & Erection of Single Shaft CDCP Boilers.
35
Thermal Systems Boiler
36
Thermal Systems Boiler
Cross Section Area = 5.2 M x 4.8 M = 24.96 sq M
Total Projected area for Coils and Hanger Tubes
(46 Tubes x 44.5mm x 5.2 M) + 15% =12.25 sq M
Net Flow Area = 24.96 – 12.25 = 12.71 sq M
Max Gas Velocity at MCR = 80000/12.71/3600
=1.75 m/Sec
Reduction in Velocity = (5.85-1.75)/5.85
=70.1% Reduction
4 Such Boilers in service since 2008
No Erosion Mark Reported yet
37
38
Problems Faced
• Heavy Erosion – at Riser Tubes
-- at Evaporator side Bends
• Bi Metallic Corrosion – Bracket Area of Evap Top
Bundle
• 2 Days Cooling Time for shutdown inspections
• No access to inspect Sides of Bundles
• Frequent damages to Refractory lining due to
cyclic stresses, causing forced outages
39
Bi Metallic Corrosion
BRACKETS
40
Bi Metallic Corrosion
Tube Material - Alloy Steel ( 15 XM) 1.5 Cr, 0.44 Mo
Clamp Material - Micro Alloy Steel
High apart in Electro chemical Series
During Service Period Coke Dust gets filled between pipe and clamp
During off Service period Coke Dust absorbs Moisture and turns
conductive
Electrolytic Corrosion starts, Anodising the Tube. Pittings formed
41
Improvement Plan
• Immediate:
1. Stopped Water Washing
2. Placement of Silica Gel Bags inside Shaft during down period
• Long Term:
Specified Safe material for Clamp while ordering for
indigeneous tubes
• Futuristic:
Future Boilers for Plant Expansion to have this angle
considered during design phase .(Included in Specification)
42
Problems Faced
• Heavy Erosion – at Riser Tubes
-- at Evaporator side Bends
• Bi Metallic Corrosion – Bracket Area of Evap Top
Bundle
• 2 Days Cooling Time for shutdown inspections
• No access to inspect Sides of Bundles
• Frequent damages to Refractory lining due to
cyclic stresses, causing forced outages
Reason: Thick Refractory Walls
43
Refractory Walls
HEAT
Wall thickness = 410 mm
44
Improvement Plan
• Frequent Damages:
1. Refractory Engg Dept of VSP selected better materials
to resist Cyclical Changes
2. Improved Re inforcement with steel wire nets
• Long Term:
Planned Replacement of Refractory Lining in all Boilers
undergoing
• Futuristic:
Future Boilers for Plant Expansion not to have Refractory Walls
, but to have water walls instead
45
Results of Indigenisation
• Russian Boilers:
1. Mitigating the Erosion Problem with Indigeneous Coils
2. Eliminated Bi Metallic Corrosion Altogether
3. Eliminated Refractory Damage related Outages
4. Sustained the OEM Norms of Output and Efficiency
• Expansion Boilers:
1. Indigenised Sourcing.
2. Proven Freedom from all problems faced in Russian Boilers
3. Improved Energy Efficiency : 5 TPH extra steam production
per Boiler with same Heat Input Rate
4. Improved Service Life ; Reliablitiy, Availability
46
Our Enablers
Directors of Boilers, AP
Dy Chief Inspectors of Boilers, Visakhapatnam
# Technical Guidance
# Timely Advises
# Boundless Co-Operation
We are indeed indebted to them………………………
47
1. Salim G Purushothaman
AGM, Thermal Power Plant
2. B Ravishankar
Manager, Thermal Power Plant
3. Jeevan Kumar
Asst. Manager, Thermal Power Plant

More Related Content

What's hot

Industrial training report- Visakhapatnam Steel Plant.
Industrial training report- Visakhapatnam Steel Plant. Industrial training report- Visakhapatnam Steel Plant.
Industrial training report- Visakhapatnam Steel Plant.
Ishankamal Mitra
 
Industrial Training Report on Direct Reduced Iron Plant(DRI)
Industrial Training Report on Direct Reduced Iron Plant(DRI)Industrial Training Report on Direct Reduced Iron Plant(DRI)
Industrial Training Report on Direct Reduced Iron Plant(DRI)
Shani Kumar Singh
 
Industrial Training Report on Blast Furnace
Industrial Training Report on Blast FurnaceIndustrial Training Report on Blast Furnace
Industrial Training Report on Blast Furnace
Shani Kumar Singh
 
Industrial Training Report on Plate Mill
Industrial Training Report on Plate MillIndustrial Training Report on Plate Mill
Industrial Training Report on Plate Mill
Shani Kumar Singh
 
Sinter Plant,Lime & Dolo Plant industrial Training Report
Sinter Plant,Lime & Dolo Plant industrial Training ReportSinter Plant,Lime & Dolo Plant industrial Training Report
Sinter Plant,Lime & Dolo Plant industrial Training Report
Shani Kumar Singh
 
TATA STEEL PPT
TATA STEEL PPTTATA STEEL PPT
TATA STEEL PPT
Abhishek Paul
 
Sintering plant at a glance
Sintering plant at a glanceSintering plant at a glance
Sintering plant at a glance
Rahul5694
 
Bhilai Sms 1.
Bhilai Sms 1.Bhilai Sms 1.
Bhilai Sms 1.
A Y V CHENULU
 
Fbc fluidized bed combustion
Fbc fluidized bed combustionFbc fluidized bed combustion
Fbc fluidized bed combustion
Gulab Siraskar
 
Steel plant presentation
Steel plant presentationSteel plant presentation
Steel plant presentation
joycecm
 
SAIL ROURKELA SINTER PLANT
SAIL ROURKELA SINTER PLANTSAIL ROURKELA SINTER PLANT
SAIL ROURKELA SINTER PLANT
Ashish Kholia
 
Design And Fabrication Of Iron Ore Sintering Machine
Design And Fabrication Of Iron Ore Sintering MachineDesign And Fabrication Of Iron Ore Sintering Machine
Design And Fabrication Of Iron Ore Sintering Machine
Albin Cherian
 
Steel Authority of India Ltd bokaro
Steel Authority of India Ltd bokaroSteel Authority of India Ltd bokaro
Steel Authority of India Ltd bokaro
Suman Sourabh
 
PSM INTERNSHIP 2
PSM INTERNSHIP 2PSM INTERNSHIP 2
PSM INTERNSHIP 2
Asim Aslam
 
Ppt on bokaro steel plant
Ppt on bokaro steel plantPpt on bokaro steel plant
Ppt on bokaro steel plant
Prashant Kumar
 
TRAINING REPORT
TRAINING REPORTTRAINING REPORT
TRAINING REPORT
Kshitij Tiwari
 
Report of Pakistan Steel Mill
Report of Pakistan Steel MillReport of Pakistan Steel Mill
Report of Pakistan Steel Mill
Muhammad Ahmed
 
Internship report file on Rail Wheel Plant
Internship report file on Rail Wheel PlantInternship report file on Rail Wheel Plant
Internship report file on Rail Wheel Plant
Shani Kumar Singh
 
A critical review of recent technological developments in electric arc furnaces
A critical review of recent technological developments in electric arc furnacesA critical review of recent technological developments in electric arc furnaces
A critical review of recent technological developments in electric arc furnaces
Jorge Madias
 
Practa
PractaPracta

What's hot (20)

Industrial training report- Visakhapatnam Steel Plant.
Industrial training report- Visakhapatnam Steel Plant. Industrial training report- Visakhapatnam Steel Plant.
Industrial training report- Visakhapatnam Steel Plant.
 
Industrial Training Report on Direct Reduced Iron Plant(DRI)
Industrial Training Report on Direct Reduced Iron Plant(DRI)Industrial Training Report on Direct Reduced Iron Plant(DRI)
Industrial Training Report on Direct Reduced Iron Plant(DRI)
 
Industrial Training Report on Blast Furnace
Industrial Training Report on Blast FurnaceIndustrial Training Report on Blast Furnace
Industrial Training Report on Blast Furnace
 
Industrial Training Report on Plate Mill
Industrial Training Report on Plate MillIndustrial Training Report on Plate Mill
Industrial Training Report on Plate Mill
 
Sinter Plant,Lime & Dolo Plant industrial Training Report
Sinter Plant,Lime & Dolo Plant industrial Training ReportSinter Plant,Lime & Dolo Plant industrial Training Report
Sinter Plant,Lime & Dolo Plant industrial Training Report
 
TATA STEEL PPT
TATA STEEL PPTTATA STEEL PPT
TATA STEEL PPT
 
Sintering plant at a glance
Sintering plant at a glanceSintering plant at a glance
Sintering plant at a glance
 
Bhilai Sms 1.
Bhilai Sms 1.Bhilai Sms 1.
Bhilai Sms 1.
 
Fbc fluidized bed combustion
Fbc fluidized bed combustionFbc fluidized bed combustion
Fbc fluidized bed combustion
 
Steel plant presentation
Steel plant presentationSteel plant presentation
Steel plant presentation
 
SAIL ROURKELA SINTER PLANT
SAIL ROURKELA SINTER PLANTSAIL ROURKELA SINTER PLANT
SAIL ROURKELA SINTER PLANT
 
Design And Fabrication Of Iron Ore Sintering Machine
Design And Fabrication Of Iron Ore Sintering MachineDesign And Fabrication Of Iron Ore Sintering Machine
Design And Fabrication Of Iron Ore Sintering Machine
 
Steel Authority of India Ltd bokaro
Steel Authority of India Ltd bokaroSteel Authority of India Ltd bokaro
Steel Authority of India Ltd bokaro
 
PSM INTERNSHIP 2
PSM INTERNSHIP 2PSM INTERNSHIP 2
PSM INTERNSHIP 2
 
Ppt on bokaro steel plant
Ppt on bokaro steel plantPpt on bokaro steel plant
Ppt on bokaro steel plant
 
TRAINING REPORT
TRAINING REPORTTRAINING REPORT
TRAINING REPORT
 
Report of Pakistan Steel Mill
Report of Pakistan Steel MillReport of Pakistan Steel Mill
Report of Pakistan Steel Mill
 
Internship report file on Rail Wheel Plant
Internship report file on Rail Wheel PlantInternship report file on Rail Wheel Plant
Internship report file on Rail Wheel Plant
 
A critical review of recent technological developments in electric arc furnaces
A critical review of recent technological developments in electric arc furnacesA critical review of recent technological developments in electric arc furnaces
A critical review of recent technological developments in electric arc furnaces
 
Practa
PractaPracta
Practa
 

Viewers also liked

changwon MVP, EMDB, SMDB & DB
changwon MVP, EMDB, SMDB & DBchangwon MVP, EMDB, SMDB & DB
changwon MVP, EMDB, SMDB & DB
Sheikh Imran
 
Lscc fa project 1 getting to know lawson state
Lscc fa project 1 getting to know lawson stateLscc fa project 1 getting to know lawson state
Lscc fa project 1 getting to know lawson state
sdavis_lawsonstate_edu
 
Keynote technical daily report for 050313
Keynote technical daily report for 050313Keynote technical daily report for 050313
Keynote technical daily report for 050313
Keynote Capitals Ltd.
 
2011 10-12 migbank-daily technical-analysis-report
2011 10-12 migbank-daily technical-analysis-report2011 10-12 migbank-daily technical-analysis-report
2011 10-12 migbank-daily technical-analysis-report
MIG BANK
 
Factory Tour Report 120309
Factory Tour Report 120309Factory Tour Report 120309
Factory Tour Report 120309
wangyangzhong
 
vizag steel plant 2014 synonyms
vizag steel plant 2014 synonyms vizag steel plant 2014 synonyms
vizag steel plant 2014 synonyms
varsha nihanth lade
 
Optimizing Combustion using a Flue Gas Analyser
Optimizing Combustion using a Flue Gas AnalyserOptimizing Combustion using a Flue Gas Analyser
Optimizing Combustion using a Flue Gas Analyser
National Productivity Council, Hyderabad, India
 
Minimum Energy Performance Standards for Boilers in India
Minimum Energy Performance Standards for Boilers in IndiaMinimum Energy Performance Standards for Boilers in India
Minimum Energy Performance Standards for Boilers in India
National Productivity Council, Hyderabad, India
 
Online Efficiency Monitoring and Diagnostics in Coal Fired Boiler
Online Efficiency Monitoring and Diagnostics in Coal Fired BoilerOnline Efficiency Monitoring and Diagnostics in Coal Fired Boiler
Online Efficiency Monitoring and Diagnostics in Coal Fired Boiler
National Productivity Council, Hyderabad, India
 
New Technologies in Process Heating
New Technologies in Process HeatingNew Technologies in Process Heating
New Technologies in Process Heating
National Productivity Council, Hyderabad, India
 
Javanotes
JavanotesJavanotes
Javanotes
John Cutajar
 
Case Studies on CFBC Boilers
Case Studies on CFBC BoilersCase Studies on CFBC Boilers
System design
System designSystem design
System design
John Cutajar
 
Developments in Industrial Boilers, WHR and Power Boilers
Developments in Industrial Boilers, WHR and Power BoilersDevelopments in Industrial Boilers, WHR and Power Boilers
Developments in Industrial Boilers, WHR and Power Boilers
National Productivity Council, Hyderabad, India
 
Intermediate machine architecture
Intermediate machine architectureIntermediate machine architecture
Intermediate machine architecture
John Cutajar
 
Module 5 2010
Module 5 2010Module 5 2010
Module 5 2010
John Cutajar
 
Oop principles
Oop principlesOop principles
Oop principles
John Cutajar
 
A presentation on furnaces and refractories by stead fast engineers
A presentation on furnaces and refractories by stead fast engineersA presentation on furnaces and refractories by stead fast engineers
A presentation on furnaces and refractories by stead fast engineers
steadfast123
 
Boiler Water Treatment for LP,MP and HP Boiler
Boiler Water Treatment for LP,MP and HP BoilerBoiler Water Treatment for LP,MP and HP Boiler
Boiler Water Treatment for LP,MP and HP Boiler
National Productivity Council, Hyderabad, India
 
role of ECE in steel plant
role of ECE  in steel plantrole of ECE  in steel plant
role of ECE in steel plant
Sandya Anusha
 

Viewers also liked (20)

changwon MVP, EMDB, SMDB & DB
changwon MVP, EMDB, SMDB & DBchangwon MVP, EMDB, SMDB & DB
changwon MVP, EMDB, SMDB & DB
 
Lscc fa project 1 getting to know lawson state
Lscc fa project 1 getting to know lawson stateLscc fa project 1 getting to know lawson state
Lscc fa project 1 getting to know lawson state
 
Keynote technical daily report for 050313
Keynote technical daily report for 050313Keynote technical daily report for 050313
Keynote technical daily report for 050313
 
2011 10-12 migbank-daily technical-analysis-report
2011 10-12 migbank-daily technical-analysis-report2011 10-12 migbank-daily technical-analysis-report
2011 10-12 migbank-daily technical-analysis-report
 
Factory Tour Report 120309
Factory Tour Report 120309Factory Tour Report 120309
Factory Tour Report 120309
 
vizag steel plant 2014 synonyms
vizag steel plant 2014 synonyms vizag steel plant 2014 synonyms
vizag steel plant 2014 synonyms
 
Optimizing Combustion using a Flue Gas Analyser
Optimizing Combustion using a Flue Gas AnalyserOptimizing Combustion using a Flue Gas Analyser
Optimizing Combustion using a Flue Gas Analyser
 
Minimum Energy Performance Standards for Boilers in India
Minimum Energy Performance Standards for Boilers in IndiaMinimum Energy Performance Standards for Boilers in India
Minimum Energy Performance Standards for Boilers in India
 
Online Efficiency Monitoring and Diagnostics in Coal Fired Boiler
Online Efficiency Monitoring and Diagnostics in Coal Fired BoilerOnline Efficiency Monitoring and Diagnostics in Coal Fired Boiler
Online Efficiency Monitoring and Diagnostics in Coal Fired Boiler
 
New Technologies in Process Heating
New Technologies in Process HeatingNew Technologies in Process Heating
New Technologies in Process Heating
 
Javanotes
JavanotesJavanotes
Javanotes
 
Case Studies on CFBC Boilers
Case Studies on CFBC BoilersCase Studies on CFBC Boilers
Case Studies on CFBC Boilers
 
System design
System designSystem design
System design
 
Developments in Industrial Boilers, WHR and Power Boilers
Developments in Industrial Boilers, WHR and Power BoilersDevelopments in Industrial Boilers, WHR and Power Boilers
Developments in Industrial Boilers, WHR and Power Boilers
 
Intermediate machine architecture
Intermediate machine architectureIntermediate machine architecture
Intermediate machine architecture
 
Module 5 2010
Module 5 2010Module 5 2010
Module 5 2010
 
Oop principles
Oop principlesOop principles
Oop principles
 
A presentation on furnaces and refractories by stead fast engineers
A presentation on furnaces and refractories by stead fast engineersA presentation on furnaces and refractories by stead fast engineers
A presentation on furnaces and refractories by stead fast engineers
 
Boiler Water Treatment for LP,MP and HP Boiler
Boiler Water Treatment for LP,MP and HP BoilerBoiler Water Treatment for LP,MP and HP Boiler
Boiler Water Treatment for LP,MP and HP Boiler
 
role of ECE in steel plant
role of ECE  in steel plantrole of ECE  in steel plant
role of ECE in steel plant
 

Similar to Indigenization of Russian Make WHR by Vizag Steel

BOILER C.PPT
BOILER  C.PPTBOILER  C.PPT
BOILER C.PPT
ShanmukhaRao37
 
Thermoplastic Liners
Thermoplastic LinersThermoplastic Liners
Thermoplastic Liners
westernfalcontx
 
Ref Recomendatin in Cement Plant.ppt
Ref Recomendatin in Cement Plant.pptRef Recomendatin in Cement Plant.ppt
Ref Recomendatin in Cement Plant.ppt
AneesReddy
 
Presentation on Accretion removal in BF2 at JSW Salem.ppt
Presentation on Accretion removal in BF2 at JSW Salem.pptPresentation on Accretion removal in BF2 at JSW Salem.ppt
Presentation on Accretion removal in BF2 at JSW Salem.ppt
AshoksinghDhurua
 
EM-Unit-IV- case hardening
EM-Unit-IV- case hardeningEM-Unit-IV- case hardening
EM-Unit-IV- case hardening
Mohanumar S
 
Case Hardening
Case HardeningCase Hardening
Case Hardening
Muthukumar V
 
Case hardening
Case hardeningCase hardening
Case hardening
MohanKirthik
 
Case hardening
Case hardeningCase hardening
Case hardening
Muthukumar V
 
2 case hardening
2 case hardening2 case hardening
2 case hardening
MathankumarA5
 
2 case hardening
2 case hardening2 case hardening
2 case hardening
Chandra Kumar S
 
case hardening
case hardeningcase hardening
case hardening
PraveenManickam2
 
Heat pipes
Heat pipesHeat pipes
Heat pipes
SUBHASH PATEL
 
02 Boiler Construction.ppt
02 Boiler Construction.ppt02 Boiler Construction.ppt
02 Boiler Construction.ppt
HirajanSandragesan
 
Heat-Exchanger Mechanical Engineering Power Engineering
Heat-Exchanger Mechanical Engineering Power EngineeringHeat-Exchanger Mechanical Engineering Power Engineering
Heat-Exchanger Mechanical Engineering Power Engineering
Sagar Porlekar
 
Forming Welding & Heat treatment of ss equipment & components for Nuclear Rec...
Forming Welding & Heat treatment of ss equipment & components for Nuclear Rec...Forming Welding & Heat treatment of ss equipment & components for Nuclear Rec...
Forming Welding & Heat treatment of ss equipment & components for Nuclear Rec...
Santosh Takale
 
Presentation final 2.0
Presentation final 2.0Presentation final 2.0
Presentation final 2.0
Michael Garibaldi
 
Presentation
PresentationPresentation
Presentation
Sethu Ram
 
Heat pipes
Heat pipesHeat pipes
Heat pipes
gowthaamk1
 
120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx
120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx
120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx
Subrat Kumar Gaana
 
Gas CCS in the UK - Tom Snow at the UKCCSRC Gas CCS Meeting, University of Su...
Gas CCS in the UK - Tom Snow at the UKCCSRC Gas CCS Meeting, University of Su...Gas CCS in the UK - Tom Snow at the UKCCSRC Gas CCS Meeting, University of Su...
Gas CCS in the UK - Tom Snow at the UKCCSRC Gas CCS Meeting, University of Su...
UK Carbon Capture and Storage Research Centre
 

Similar to Indigenization of Russian Make WHR by Vizag Steel (20)

BOILER C.PPT
BOILER  C.PPTBOILER  C.PPT
BOILER C.PPT
 
Thermoplastic Liners
Thermoplastic LinersThermoplastic Liners
Thermoplastic Liners
 
Ref Recomendatin in Cement Plant.ppt
Ref Recomendatin in Cement Plant.pptRef Recomendatin in Cement Plant.ppt
Ref Recomendatin in Cement Plant.ppt
 
Presentation on Accretion removal in BF2 at JSW Salem.ppt
Presentation on Accretion removal in BF2 at JSW Salem.pptPresentation on Accretion removal in BF2 at JSW Salem.ppt
Presentation on Accretion removal in BF2 at JSW Salem.ppt
 
EM-Unit-IV- case hardening
EM-Unit-IV- case hardeningEM-Unit-IV- case hardening
EM-Unit-IV- case hardening
 
Case Hardening
Case HardeningCase Hardening
Case Hardening
 
Case hardening
Case hardeningCase hardening
Case hardening
 
Case hardening
Case hardeningCase hardening
Case hardening
 
2 case hardening
2 case hardening2 case hardening
2 case hardening
 
2 case hardening
2 case hardening2 case hardening
2 case hardening
 
case hardening
case hardeningcase hardening
case hardening
 
Heat pipes
Heat pipesHeat pipes
Heat pipes
 
02 Boiler Construction.ppt
02 Boiler Construction.ppt02 Boiler Construction.ppt
02 Boiler Construction.ppt
 
Heat-Exchanger Mechanical Engineering Power Engineering
Heat-Exchanger Mechanical Engineering Power EngineeringHeat-Exchanger Mechanical Engineering Power Engineering
Heat-Exchanger Mechanical Engineering Power Engineering
 
Forming Welding & Heat treatment of ss equipment & components for Nuclear Rec...
Forming Welding & Heat treatment of ss equipment & components for Nuclear Rec...Forming Welding & Heat treatment of ss equipment & components for Nuclear Rec...
Forming Welding & Heat treatment of ss equipment & components for Nuclear Rec...
 
Presentation final 2.0
Presentation final 2.0Presentation final 2.0
Presentation final 2.0
 
Presentation
PresentationPresentation
Presentation
 
Heat pipes
Heat pipesHeat pipes
Heat pipes
 
120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx
120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx
120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx
 
Gas CCS in the UK - Tom Snow at the UKCCSRC Gas CCS Meeting, University of Su...
Gas CCS in the UK - Tom Snow at the UKCCSRC Gas CCS Meeting, University of Su...Gas CCS in the UK - Tom Snow at the UKCCSRC Gas CCS Meeting, University of Su...
Gas CCS in the UK - Tom Snow at the UKCCSRC Gas CCS Meeting, University of Su...
 

More from National Productivity Council, Hyderabad, India

Boiler Water Treatment -
Boiler Water Treatment - Boiler Water Treatment -
Efficient Steam Systems -
Efficient Steam Systems -Efficient Steam Systems -
Efficient steam systems - Generation to WHR
Efficient steam systems - Generation to WHREfficient steam systems - Generation to WHR
Efficient steam systems - Generation to WHR
National Productivity Council, Hyderabad, India
 
Boiler Performance Monitoring
Boiler Performance MonitoringBoiler Performance Monitoring
CFBC Boiler vs Pulverized Fired Boiler
CFBC Boiler vs Pulverized Fired BoilerCFBC Boiler vs Pulverized Fired Boiler
CFBC Boiler vs Pulverized Fired Boiler
National Productivity Council, Hyderabad, India
 
Boiler Superheater Design Modification
Boiler Superheater Design ModificationBoiler Superheater Design Modification
Boiler Superheater Design Modification
National Productivity Council, Hyderabad, India
 
Boiler Maintenance & Safety
Boiler Maintenance & SafetyBoiler Maintenance & Safety
Presentation on CFBC Boilers
Presentation on CFBC BoilersPresentation on CFBC Boilers
Boiler Operation and Maintenance Experiences
Boiler Operation and Maintenance ExperiencesBoiler Operation and Maintenance Experiences
Boiler Operation and Maintenance Experiences
National Productivity Council, Hyderabad, India
 
Safe Operation and Explosions in Boilers
Safe Operation and Explosions in BoilersSafe Operation and Explosions in Boilers
Safe Operation and Explosions in Boilers
National Productivity Council, Hyderabad, India
 

More from National Productivity Council, Hyderabad, India (10)

Boiler Water Treatment -
Boiler Water Treatment - Boiler Water Treatment -
Boiler Water Treatment -
 
Efficient Steam Systems -
Efficient Steam Systems -Efficient Steam Systems -
Efficient Steam Systems -
 
Efficient steam systems - Generation to WHR
Efficient steam systems - Generation to WHREfficient steam systems - Generation to WHR
Efficient steam systems - Generation to WHR
 
Boiler Performance Monitoring
Boiler Performance MonitoringBoiler Performance Monitoring
Boiler Performance Monitoring
 
CFBC Boiler vs Pulverized Fired Boiler
CFBC Boiler vs Pulverized Fired BoilerCFBC Boiler vs Pulverized Fired Boiler
CFBC Boiler vs Pulverized Fired Boiler
 
Boiler Superheater Design Modification
Boiler Superheater Design ModificationBoiler Superheater Design Modification
Boiler Superheater Design Modification
 
Boiler Maintenance & Safety
Boiler Maintenance & SafetyBoiler Maintenance & Safety
Boiler Maintenance & Safety
 
Presentation on CFBC Boilers
Presentation on CFBC BoilersPresentation on CFBC Boilers
Presentation on CFBC Boilers
 
Boiler Operation and Maintenance Experiences
Boiler Operation and Maintenance ExperiencesBoiler Operation and Maintenance Experiences
Boiler Operation and Maintenance Experiences
 
Safe Operation and Explosions in Boilers
Safe Operation and Explosions in BoilersSafe Operation and Explosions in Boilers
Safe Operation and Explosions in Boilers
 

Recently uploaded

Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
mamamaam477
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
HODECEDSIET
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
enizeyimana36
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
zubairahmad848137
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 

Recently uploaded (20)

Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 

Indigenization of Russian Make WHR by Vizag Steel

  • 1. 1
  • 2. 2 Indigenisation of Russian Make Waste Heat Boilers System Our Experience 1. Salim G Purushothaman, AGM, Vizag Steel 2. B. Ravishankar, Manager, Vizag Steel 3. Jeevan Kumar, Assistant Manager, Vizag Steel
  • 3. 3 Waste Heat Heat Evolved from Dry Quenching of Metallurgical Coke Produced In House Quenching Medium – Circulating Nitrogen Before Recovery - 800 Deg C After Recovery - 160 Deg C 9 x 80,000 N Cu M/Hr TOTAL Net HEAT AVAILABILITY = 124 G Cal/Hr
  • 4. 4 Metallurgical Coke Required for Smelting Iron Ore in Blast Furnace Each Ton of Hot Metal Produced needs Half Ton Coke We make Aprox 8500 Tons a Day
  • 5. 5 COKE MAKING Destructive Distillation of Low Ash Coal - Heating Coal in the absence of Air to 1100 Deg C Thus expelling all volatiles To obtain Porous Carbon Concentrate, COKE Made in Coke Ovens
  • 6. 6 Coke Ovens Coal Charged Part of A Battery – Coke Ovens Coking Time /Oven - 16 Hours 1 Battery – 67 Ovens Batteries - 4 Rated Production– 100Pushings/Day/Battery 1 Oven – 32 Ton Coal to 25 Tons Coke
  • 7. 7 Our Coke Oven Battery Total Such Batteries in VSP – 4 Numbers
  • 8. 8 Coke Produced Collected In Buckets, 1 Pushout = 25Tons Coke Temperature = 1000 to 1100 Deg C Nature - Incandescent
  • 9. 9 Need to Quench Coke Coke to be Shipped to Blast Furnace Shipment through Conveyors Temperatures above 180Degrees Burns Conveyor For Safety of Conveyor and Handling Coke to be Quenched to 160 Deg C Implication: 350 M Cal Heat /Ton Coke to be Removed
  • 10. 10 Types of Quenching Cooling Water Coke Car 1.WET Quenching All Heat – Lost Pollution - Severe
  • 11. 11 Types of Quenching 2. DRY Quenching All Heat –Recovered Pollution- Eliminated
  • 12. 12 DRY vs WET (Quenching)
  • 14. 14 RUSSIAN BOILERS OF CDCP • Commissioned in 1986-87 • Make: Belgorod Power , Russia (Erstwhile USSR) • Model : KCTK 39/440 • Type : Drum, Forced Circulation • Rating : 39 Bar, 440 Deg C , 25.5 TPH MCR • Gas Flow Rate : 80 000 N CuM/Hr • Hot Gas Inlet : 800 Deg C • Cooled Gas Outlet : 160 Deg C • Construction : Twin Shaft , Refractory walled , Counter Flow Eco, & Evap
  • 16. 16 SIDE VIEW To Drum From Circulation Pump Output SH Steam, 39 Bar
  • 18. 18 Problems Faced • Heavy Erosion – at Riser Tubes -- at Evaporator side Bends • Bi Metallic Corrosion – Bracket Area of Evap Top Bundle • 2 Days Cooling Time for shutdown inspections • No access to inspect Sides of Bundles • Frequent damages to Refractory lining due to cyclic stresses, causing forced outages
  • 19. 19 Problems Faced • Heavy Erosion – at Riser Tubes -- at Evaporator side Bends • Bi Metallic Corrosion – Bracket Area of Evap Top Bundle • 2 Days Cooling Time for shutdown inspections • No access to inspect Sides of Bundles • Frequent damages to Refractory lining due to cyclic stresses, causing forced outages
  • 20. 20 Gas Erosion • Evaporator Cross Section = 3.8 x 3.66 = 13.9 sqM • Projected Area of Tubes = 100 Nos x 28mm x 3.6 M long = 10.1 sq M NET FLOW AREA = 3.8 sq M Gas Flow Rate = 80,000 NCuM/Hr Gas Velocity = 80000/3.8/3600 = 5.85 m/Sec Dust Loading = 5-10 gm/N CuM of Gas
  • 23. 23 Erosion – of Evaporator side Bends
  • 24. 24 Improvement Plan • Immediate: 1. Baffled the Bends to protect them 2. Shielded the Riser tubes by providing Armour plate upstream • Long Term: 1. Monitor Tube Thinning & Schedule for Phased Replacement 2. Indigenisation of tubes with Erosion Resistant Indian Makes • Futuristic: Future Boilers for Plant Expansion to have lesser gas Velocity.
  • 26. 26 Trigger For Tube Replacement • Annual Tube Thickness Survey with D Meter • Monitoring of Thinning Trend with recorded D Meter Readings • Forecasting Thinning Rate and Procurement of Spare Tubes • Determined value of Residual thickness to replace Tubes as - 1.9 to 2.0 mm for Straight Part - 1.8 mm at Bends ( Based on IBR Regn 338) Tubes = OD 28 mm , Seamless Original Thickness = 3mm Nominal with +0 , -10% Tolerance (GOST) Calculated Thickness for Working Pr of 47 Bar as per GOST = 0.64 mm Calculated Thickness for Working Pr of 47 Bar as per IBR = 1.31mm, But Required Minimum Thickness for Coil Tubes, For Forced Circulation and Tube OD < 29 mm = 1.62 mm (IBR Reg 338, b)
  • 27. 27 Towards Indigenisation • Evaporator Top Coils – 15 XM (GOST) • Evaporator Other Coils – Steel 20 (GOST) •Evaporator Service Conditions: Water Temp – 270 Deg Max, Pressure 47 Bar Max (Excess Condition) MCR: Inlet 46 Bar, Outlet 43 Bar Outside Temp – 800 Deg Max Material Testing Done in our own Laboratory – QATD Dept of VSP •Hardness Brinnell Hardness value Varied from 130 to 135 sample to sample ie Rockwell B (HRB) 72 to 75
  • 28. 28 Material Selection • Involved Plant Design Dept , & QATD Dept of VSP • Consulted Dy Chief Inspector of Boilers , Visakhapatnam • Furnished Sample tubes to BHEL • Advice of Design Engineers from BHEL Objectives # Medium Carbon Steel for Evaporator service ; C = 0.2 to 0.25 % range # Hardness to be around 80 HRB to be more resistant to Erosion # At the same time % Elongation to be minimum 27% - Bends to be safe in repeated Thermal Cycling (Bend R = 2D) # Economy
  • 29. 29 Material Selection • SA 192 SA 210 Gr A1 SA 210 Gr C SA 213 T11 Selected SA 210 Gr A1- CDS • Hardness > 75 HRB; CDS will have more due to work hardening. • % Elongation = 30% Better Flexibility for Bends • Thickness : Always > 3mm (as Tol = +20%, - 0%) • Easy Availability, Weldability Considered Plant Design Dept of VSP Developed Tender Drawings accordingly for Procurement of Spares from Indian Market
  • 30. 30 Bundle Replacement • Thickness Reduction found reaching Threshold in Two Boilers during Annual Thickness Survey (Residual thickness, 2.2 mm against Normal 3 mm) • Procurement Action Initiated . Planned to Replace next Year Year : 2000
  • 31. 31 Bundle Replacement • Residual Thickness varied from 1.9 to 2.1- Time to Replace! • Dy Chief Inspector of Boilers advised Evaporator Bundle Replacement • Replacement Program was approved by DOB , Hyderabad • First Indegeneous Coil Bundle Erected in one of the Boilers in 2001 Erosion Rate Drastically Reduced in that Boiler Ever since Thereafter All Russian Boilers underwent Indigenisation of Coils Including Economiser Coils Over a 10 Year Period Year : 2001
  • 32. 32 New CDCP Boiler Installation • 2002-03 Planning for Capacity Expansion involving new Coke Oven Battery • Plan Entailed 4 More CDCP Boilers with similar Capacity • Desired to have Design Gas Velocity as minimum as possible • Thermax Pune Introduced the idea of Single Shaft CDCP Boilers – As Working in Vental Steel Plant,Russia - Designed by a Finnish Corporation Rautaruukki – Thermax offering such CDCP Boilers to Neelanchal Ispat, Orissa
  • 33. 33 Rautaruukki Design • Retains the Elevation of Gas Entry Axis; Overall Height increased • Water Wall with Natural Circulation and Evaporators with Forced Circulation. • Overall Foot Print within Russian CDCP Boiler’s • Bigger Tubes • Bigger Pitches –Longitudinal & Transverse • Cross Section Area gets doubled almost but Projected area of Coils is reduced by reduction in tubings ( HSA requirement curtailed by Water Wall). • Marginal increase only in Overall HSA CIRCULATING GAS VELOCITY REDUCTION OF 30 %
  • 34. 34 New CDCP Boiler Installation • Thermax designed Single Shaft CDCP Boiler for NINL • We inspected Thermax Boilers at NINL : During their Erection & Commissioning (Consultant MECON) • Their Operation was found satisfactory • Decided to Opt for Single Shaft Boilers; Made Specs accordingly , under Consultancy of MECON, & Tendered out. • Thermal Systems, Hyderabad Bagged the Order (L-1) for Design ,Supply & Erection of Single Shaft CDCP Boilers.
  • 36. 36 Thermal Systems Boiler Cross Section Area = 5.2 M x 4.8 M = 24.96 sq M Total Projected area for Coils and Hanger Tubes (46 Tubes x 44.5mm x 5.2 M) + 15% =12.25 sq M Net Flow Area = 24.96 – 12.25 = 12.71 sq M Max Gas Velocity at MCR = 80000/12.71/3600 =1.75 m/Sec Reduction in Velocity = (5.85-1.75)/5.85 =70.1% Reduction 4 Such Boilers in service since 2008 No Erosion Mark Reported yet
  • 37. 37
  • 38. 38 Problems Faced • Heavy Erosion – at Riser Tubes -- at Evaporator side Bends • Bi Metallic Corrosion – Bracket Area of Evap Top Bundle • 2 Days Cooling Time for shutdown inspections • No access to inspect Sides of Bundles • Frequent damages to Refractory lining due to cyclic stresses, causing forced outages
  • 40. 40 Bi Metallic Corrosion Tube Material - Alloy Steel ( 15 XM) 1.5 Cr, 0.44 Mo Clamp Material - Micro Alloy Steel High apart in Electro chemical Series During Service Period Coke Dust gets filled between pipe and clamp During off Service period Coke Dust absorbs Moisture and turns conductive Electrolytic Corrosion starts, Anodising the Tube. Pittings formed
  • 41. 41 Improvement Plan • Immediate: 1. Stopped Water Washing 2. Placement of Silica Gel Bags inside Shaft during down period • Long Term: Specified Safe material for Clamp while ordering for indigeneous tubes • Futuristic: Future Boilers for Plant Expansion to have this angle considered during design phase .(Included in Specification)
  • 42. 42 Problems Faced • Heavy Erosion – at Riser Tubes -- at Evaporator side Bends • Bi Metallic Corrosion – Bracket Area of Evap Top Bundle • 2 Days Cooling Time for shutdown inspections • No access to inspect Sides of Bundles • Frequent damages to Refractory lining due to cyclic stresses, causing forced outages Reason: Thick Refractory Walls
  • 44. 44 Improvement Plan • Frequent Damages: 1. Refractory Engg Dept of VSP selected better materials to resist Cyclical Changes 2. Improved Re inforcement with steel wire nets • Long Term: Planned Replacement of Refractory Lining in all Boilers undergoing • Futuristic: Future Boilers for Plant Expansion not to have Refractory Walls , but to have water walls instead
  • 45. 45 Results of Indigenisation • Russian Boilers: 1. Mitigating the Erosion Problem with Indigeneous Coils 2. Eliminated Bi Metallic Corrosion Altogether 3. Eliminated Refractory Damage related Outages 4. Sustained the OEM Norms of Output and Efficiency • Expansion Boilers: 1. Indigenised Sourcing. 2. Proven Freedom from all problems faced in Russian Boilers 3. Improved Energy Efficiency : 5 TPH extra steam production per Boiler with same Heat Input Rate 4. Improved Service Life ; Reliablitiy, Availability
  • 46. 46 Our Enablers Directors of Boilers, AP Dy Chief Inspectors of Boilers, Visakhapatnam # Technical Guidance # Timely Advises # Boundless Co-Operation We are indeed indebted to them………………………
  • 47. 47 1. Salim G Purushothaman AGM, Thermal Power Plant 2. B Ravishankar Manager, Thermal Power Plant 3. Jeevan Kumar Asst. Manager, Thermal Power Plant