2. 2
CONTENTS
•BF # 2 at JSW Salem Works
•Introduction
•Operating parameters
•First visual inspection
•Accretion Analysis
•Possible reasons for Accretion formation
•Alkali & ZnO balance
•Actions initiated & Review
•Selection of Cardox method
•Working of Cardox system
•Execution methodology
•Post removal - Furnace Performance
3. 3
BF # 2 AT JSW SALEM WORKS
The Blast Furnace-2 of JSW
Salem works was
commissioned in July 2007
It is a 550m3 furnace and the
design & technology supplied
by CERI, China.
Raw material source
Iron ore – Karnataka
(Bellary)
Coke – Captive &
Purchased
BF 2 Main features
Working Volume 495 M3
Useful volume 550 M3
No. of tuyeres 16
Hearth dia 5900 mm
Tuyere dia 110 mm
HBP 2.10 Kg/cm2
TP 0.85 Kg/cm2
HBT 1075° C
Sinter 60%
Stoves Top combustion
GCP Dry type
Charging system BLT
4. 4
INTRODUCTION
NORMAL PERFORMANCE
Productivity - 2.6 to 2.8 MT/M3/Day.
Average Coal injection rate 95 -100 Kg/THM in July & Aug-09.
DETERIORATED PERFORMANCE FROM SEP-09
Blast acceptance was in decreasing trend.
Furnace movement disturbed.
Top temperatures were in increasing trend.
Refractory lining temperatures were in dropping trend.
Furnace got drifted towards unstable regime of operation.
Primary reason - inferior quality sinter & coke.
8. 8
FIRST VISUAL INSPECTION
• Shutdown was taken on 08.12.09 for visually inspecting the condition
inside the furnace.
• Stock level was brought down by 9 meters & shutdown was taken.
• The Furnace inspection holes at different elevations were opened.
• On inspection, huge accretion formation was noticed. The exact
location and thickness of accretion was estimated.
• The accretion build up started from 23-m elevation (Middle stack)
and extended downwards up to 20m elevation.
• It was spread between 180° to 360° with reference to tap hole at 0°.
• The accretion appeared to have blocked 25 – 30% of area.
• The size was in the order of 30 to 35 M3.
11. 11
ACCRETION ANALYSIS
High in ZnO & K2O.
All the inputs like coke, ore,
sinter, mill scale etc and
outputs like flue dust and GCP
dust are normally subjected to
chemical analysis.
Special analysis was carried
out to identify the Zn carrying
input.
Analysis
Near
the wall
Middle
portion
Away
from
the wall
Fe2O3 38.30 5.16 17.19
Al2O3 24.80 31.19 15.13
SiO2 18.10 13.63 21.75
MgO 0.65 0.92 4.55
CaO 2.30 3.34 18.43
K2O 2.36 16.50 12.22
TiO2 0.92 0.90 0.48
P2O5 0.15 0.12 0.51
Na2O 0.09 2.06 2.60
ZnO 10.76 14.93 1.83
12. 12
POSSIBLE REASONS FOR ACCRETION FORMATION
EOF Sludge
Higher Zn
through
purchased
scrap
Accretion
formation
Alkali
accumulation
Low level
dumping
during
hanging /
slipping
Higher
Zn
input
Sinter
Higher Zn
through
purchased
Mill scale
Coke
Higher
Zn
through
coking
coal
15. 15
ACTIONS INITIATED
Following operational practices were initiated:
Peripheral working was intensified,
Charging extra cokes,
Clean up charges at regular intervals,
Lower RAFT,
Low basicity of 0.90 to 0.95
Usage of BF2 flue dust in sinter plant stopped
These actions showed some improvement but the trend of revival was
very marginal.
16. 16
REVIEWING THE SITUATION
On 10th Jan 2010 another
shutdown was taken.
The stock level was brought
down by 10 meters.
Visual inspection carried out.
REVIEW FINDINGS
Not much change in the Accretion size.
Conventional method could take much longer time to
normalize the furnace operation.
17. 17
VARIOUS OPTIONS AVAILABLE FOR ACCRETION DISLODGING
Coke bunches charging along with Clean up charges
Furnace has to run consistently.
Higher silicon to be maintained.
Difficult to dislodge the accretion if it is located in granular
zone.
It may take much longer time for normailising the furnace.
18. 18
VARIOUS OPTIONS AVAILABLE FOR ACCRETION DISLODGING
Controlled Blasting
Faster recovery compared to other methods.
Holes to be drilled through shell & lining.
Requires expert blasters.
Blasting effect on lining unpredictable.
Temperature where Explosive to be placed shall be maximum 40°C.
Personal & equipment safety is a key factor.
19. 19
VARIOUS OPTIONS AVAILABLE FOR ACCRETION DISLODGING
Blowing down the furnace & manual breaking
Furnace to be blown down up to tuyere level.
Inside atmosphere shall be suitable for people to enter
inside the furnace.
Personal safety is a key factor.
Time consuming and startup will be slow.
20. 20
SELECTION OF CARDOX METHOD FOR ACCRETION REMOVAL
Available options
Coke bunches
charging along with
Clean up charges
Controlled Blasting
Blowing down the
furnace & manual
breaking
Constraints
Longer time for
normalising the
furnace
More coke
consumption
Personal risk
Potential risk of
damage to
equipment /
refractory
Expertise
requirement
Search
for
new
Methods
_____________
Cardox
method
(Liquid CO2
Activation)
21. 21
THE WORKING OF CARDOX SYSTEM
Cardox consists of a high strength reusable steel tube filled with liquid
carbon dioxide, a chemical heater and a rupture disc.
When energised by the application of a small electrical charge, the
chemical heater instantly converts the liquid carbon dioxide to a gas.
This conversion expands the CO2 volume and builds up pressure inside
the tube until it causes the rupture disc at the end of the tube to burst.
This releases the CO2 - now 600 times the original volume - through a
special discharge nozzle to create a powerful heaving force, at pressures
up to 40,000 psi (3,000bar).
This all takes place in milliseconds.
22. 22
THE WORKING OF CARDOX SYSTEM
Before :
Socket welded in to
hole provided in the
shell
Cardox tube is
placed in the tube
holder, inserted and
then secured in the
socket. The tube is
then activated.
After: The tube is
removed and system
is ready for use
24. 24
EXECUTION METHODOLOGY
• On 02.02.10, burden level was lowered by 10 meters and shut down
taken.
• Accretion was from 23 meter elevation (Middle stack) and extended
downwards up to 20 meter elevation.
• In four identified locations at 21 meter elevation, Shell plate was cut by
gas cutting
• In those locations, four holes of 75 mm dia were drilled by core drilling
machine
• Special stainless steel sockets with locking arrangement were welded
inside the holes.
26. 26
EXECUTION METHODOLOGY
• Cardox tubes were filled with liquid CO2 from cryogenic cylinders
using Cryogenic pump .
• Actual quantity of CO2 filled was measured by weighing the tube
before and after filling.
• Cardox tubes were fixed in the sockets and locked.
• Liquid CO2 activation was initiated.