Geocience skills have a place in the future. Geophysical & geotechnical data, interpretation will be required for identifying the best places & ways to install wind turbines.
This document summarizes a case study of a gas pipeline project in Antioch, California that utilized horizontal directional drilling (HDD) due to constraints of the limited right-of-way. HDD was used to install 2 miles of 16-inch and 5 miles of 24-inch diameter pipelines beneath an active railroad and environmentally sensitive wetlands. Geotechnical investigations were performed to evaluate soil conditions and feasibility of HDD. The project encountered difficulties during some of the HDD crossings including losing drill strings and frac-outs, but was ultimately completed in 2000 using HDD, slick bore, and conventional trenching methods.
This document summarizes a study evaluating mining methods for the 543-S copper deposit in Michigan's Keweenaw Peninsula. An underground cut-and-fill method was selected based on the deposit's geometry. A block model of the deposit was created from drill data. Economic analysis was conducted to determine optimal pit limits and underground development. The study concluded the deposit has potential for open-pit, underground, or hybrid mining and that cut-and-fill is reasonable given the deposit. Future work includes environmental monitoring and feasibility assessments.
This document provides details of a senior capstone design project proposing a new driving range and recreational facility. A team of 5 engineering students from Boston Engineering & Design presents plans for renovating a contaminated 16-acre site including a double-tiered synthetic turf driving range, pro shop, restaurant, and stormwater management. The project requires zoning changes and addresses environmental permitting needs. Engineering designs cover site work, utilities, foundations, and structural components to develop the site while remediating contamination issues.
This document summarizes a presentation about mitigation efforts after a 2004 wildfire impacted a hydroelectric facility in Tuolumne County, California. It describes:
1) An overview of the early fire that burned 1,600 acres and impacted infrastructure.
2) A damage assessment that identified erosion potential, rockfall hazards, and drainage issues.
3) Aerial mapping and field work to further evaluate hazards.
4) The mitigation design including rockfall simulation modeling, culvert design, revegetation, and erosion control.
5) Construction from December 2004 to May 2005 that included over 3,000 feet of rock fencing, mesh installation, new access roads and culverts, hardened crossings
Dr. Malek Smadi, Ph.D. thesis lateral deformation and associated settlement r...Dr. Malek Smadi
Settlement of structures on soft clay deposits results from flow and consolidation of soil. In the latter case, water squeezes out from under the structure, whereas in the former case soil squeezes out. Settlement resulting from flow of soil depends on the factor of safety against undrained instability.
In construction situations where the factor of safety is small, an accurate prediction of settlement reSUlting from flow of soil is required. Field measurements of horizontal deformation of soft clays during and after construction of embankments and storage facilities have been collected from throughout the world, covering 180 case histories, to relate lateral deformation to the factor of safety and to develop a practical procedure for computing settlements resulting from flow of soil.
This document discusses geotechnical seismic services, including 2D and 3D seismic acquisition. It outlines the objectives, preparation, planning, and parameter selection involved in 2D/3D seismic surveys. These include determining acquisition parameters, source and receiver layouts, and raw shot recording. The goals are regional exploration, prospect delineation, and field development.
Djama Ali Guelleh, General Director of EDD
Mohamed Chaari, Director of Fiale Project
Jalludin Mohamed, General Director of CERD
Iceland Geothermal Conference 2018 - Breaking the Barriers
24 - 27 April, 2018, Harpa, Reykjavík
This document summarizes several porous pavement projects completed by Onondaga County to manage stormwater runoff. It outlines case studies for four parking lots that used designs with porous asphalt and concrete to infiltrate runoff on-site. The case studies describe the design components, costs, estimated runoff reductions, and lessons learned. Key findings include the projects achieved runoff reductions at costs of $0.38 to $0.57 per gallon, and that proper construction and maintenance are important for ensuring the porous pavements function as intended over time.
This document summarizes a case study of a gas pipeline project in Antioch, California that utilized horizontal directional drilling (HDD) due to constraints of the limited right-of-way. HDD was used to install 2 miles of 16-inch and 5 miles of 24-inch diameter pipelines beneath an active railroad and environmentally sensitive wetlands. Geotechnical investigations were performed to evaluate soil conditions and feasibility of HDD. The project encountered difficulties during some of the HDD crossings including losing drill strings and frac-outs, but was ultimately completed in 2000 using HDD, slick bore, and conventional trenching methods.
This document summarizes a study evaluating mining methods for the 543-S copper deposit in Michigan's Keweenaw Peninsula. An underground cut-and-fill method was selected based on the deposit's geometry. A block model of the deposit was created from drill data. Economic analysis was conducted to determine optimal pit limits and underground development. The study concluded the deposit has potential for open-pit, underground, or hybrid mining and that cut-and-fill is reasonable given the deposit. Future work includes environmental monitoring and feasibility assessments.
This document provides details of a senior capstone design project proposing a new driving range and recreational facility. A team of 5 engineering students from Boston Engineering & Design presents plans for renovating a contaminated 16-acre site including a double-tiered synthetic turf driving range, pro shop, restaurant, and stormwater management. The project requires zoning changes and addresses environmental permitting needs. Engineering designs cover site work, utilities, foundations, and structural components to develop the site while remediating contamination issues.
This document summarizes a presentation about mitigation efforts after a 2004 wildfire impacted a hydroelectric facility in Tuolumne County, California. It describes:
1) An overview of the early fire that burned 1,600 acres and impacted infrastructure.
2) A damage assessment that identified erosion potential, rockfall hazards, and drainage issues.
3) Aerial mapping and field work to further evaluate hazards.
4) The mitigation design including rockfall simulation modeling, culvert design, revegetation, and erosion control.
5) Construction from December 2004 to May 2005 that included over 3,000 feet of rock fencing, mesh installation, new access roads and culverts, hardened crossings
Dr. Malek Smadi, Ph.D. thesis lateral deformation and associated settlement r...Dr. Malek Smadi
Settlement of structures on soft clay deposits results from flow and consolidation of soil. In the latter case, water squeezes out from under the structure, whereas in the former case soil squeezes out. Settlement resulting from flow of soil depends on the factor of safety against undrained instability.
In construction situations where the factor of safety is small, an accurate prediction of settlement reSUlting from flow of soil is required. Field measurements of horizontal deformation of soft clays during and after construction of embankments and storage facilities have been collected from throughout the world, covering 180 case histories, to relate lateral deformation to the factor of safety and to develop a practical procedure for computing settlements resulting from flow of soil.
This document discusses geotechnical seismic services, including 2D and 3D seismic acquisition. It outlines the objectives, preparation, planning, and parameter selection involved in 2D/3D seismic surveys. These include determining acquisition parameters, source and receiver layouts, and raw shot recording. The goals are regional exploration, prospect delineation, and field development.
Djama Ali Guelleh, General Director of EDD
Mohamed Chaari, Director of Fiale Project
Jalludin Mohamed, General Director of CERD
Iceland Geothermal Conference 2018 - Breaking the Barriers
24 - 27 April, 2018, Harpa, Reykjavík
This document summarizes several porous pavement projects completed by Onondaga County to manage stormwater runoff. It outlines case studies for four parking lots that used designs with porous asphalt and concrete to infiltrate runoff on-site. The case studies describe the design components, costs, estimated runoff reductions, and lessons learned. Key findings include the projects achieved runoff reductions at costs of $0.38 to $0.57 per gallon, and that proper construction and maintenance are important for ensuring the porous pavements function as intended over time.
The North Carolina General Assembly requested a coastal wind energy study. The University of North Carolina at Chapel Hill was designated to conduct the study, examining the Pamlico and Albemarle Sounds for offshore wind development over waters less than 30 meters deep. The study evaluated the wind resource, ecological impacts, utility infrastructure, and preliminary economic analysis. It identified large areas offshore with potential for wind farms, which could meet 20% of North Carolina's power demand. A potential turbine demonstration site was identified in the Pamlico Sound.
This document provides guidance for students on conducting fieldwork for the iGCSE Geography exam. It outlines the steps of the enquiry process, including planning, data collection, presentation, analysis and evaluation. It then describes various fieldwork opportunities organized by topic area and exam unit. For each opportunity, it provides details on skills needed, aims, location, hypotheses, data collection techniques, risks, and potential exam questions. The document aims to help students plan and carry out fieldwork investigations that meet the requirements of the iGCSE Geography exam.
Igcse geography coastal environments fieldworkWill Williams
The document provides information about a fieldwork investigation into coastal environments at Shoreham, England. It discusses:
1) Two themes for the fieldwork - measuring beach profiles and material to analyze the impact of coastal protection structures, and conducting a survey to understand local residents' views on coastal management.
2) Background context on the regeneration plans for Shoreham and the need to protect the coastline given new development.
3) Details on the coastal protection methods used, including groynes, seawalls, and beach nourishment.
4) An overview of the fieldwork process, from formulating aims and hypotheses to collecting and analyzing data and drawing conclusions.
5) Instructions for tasks to measure
This document discusses land surface modeling in weather and climate models. It describes the role of land surface models in providing surface boundary conditions, such as heat and water fluxes. It outlines the requirements for land models, including atmospheric forcing data, appropriate physical representations, land cover and soil data, and initial land states. It then covers applications for weather and climate modeling, validation of land models, ongoing work to improve them, and their expanding role within Earth system modeling.
The Parkersburg Site in West Virginia contains an engineered disposal cell for radioactive waste from a former uranium mill. Major long-term stewardship activities include monitoring the disposal cell, restricting access, inspecting fencing and signs, and monitoring groundwater. The 6-hectare site has been monitored since 1983, with disposal of approximately 15,300 cubic meters of waste in the cell. Annual costs average around $16,400, with higher costs every 5 years for groundwater monitoring. The site will remain under long-term stewardship by the DOE indefinitely to ensure the integrity of the disposal cell.
The document discusses modern practices for underground mine planning and design. It covers key topics like mine lifecycles, success factors, planning processes and tools, and expected future developments. Underground mining trends include deeper deposits, higher costs, and increased focus on underground operations. Mine planning requires quality inputs, experienced teams, and software tools to develop designs, schedules, and reports. Factors like orebody geometry, geotechnical conditions, and required production influence the selection of mining methods.
Exploration and analysis of oil and gas field ( 3D seismic survey)Apurva Mittal
This document discusses different types of seismic surveys used in oil and gas exploration and production. It describes 2D seismic surveys, which are inexpensive but provide lower quality data. 3D seismic surveys acquire more detailed data in three dimensions and are more effective for mapping anomalies. 4D seismic surveys involve repeat 3D surveys over time to monitor reservoir performance and locate remaining resources as extraction progresses. Factors like vessel configuration, line orientation, and marine life can impact survey quality and efficiency.
Sedimentation assessment of a small reservoir at afaka forest reserve, kaduna...Alexander Decker
This document summarizes a study assessing sedimentation of a small reservoir in Afaka Forest Reserve, Kaduna, Nigeria. The key findings are:
1. Bathymetric surveys from 2004-2013 showed the reservoir's storage capacity decreased from its initial design capacity of 16,400m3 to 10,665m3, a storage loss of about 35%.
2. A linear relationship between reservoir storage capacity and age established a sedimentation rate of 221m3 per year, meaning the reservoir's storage capacity would be eliminated in 76.5 years without dredging.
3. For economic viability, the study recommends desilting the reservoir every 15 years to remove 3,280m3 of sediment and
This document discusses the role of seismic surveys in establishing oil and gas fields. It describes the various steps involved in seismic data acquisition, including planning, preparation, field operations such as drilling shot holes or operating vibrators, recording seismic data, and processing the data. The objectives of seismic surveys are listed as regional exploration, prospect delineation, and field development. Key factors in planning a survey include the targeted geological features, available budgets and data, and parameter selection for recording seismic signals.
This document summarizes the use of satellite radar techniques to monitor peatland degradation and recovery in the Irish Midlands. It shows that Interferometric Synthetic Aperture Radar (InSAR) can now monitor peatlands continuously over large areas. The study analyzed surface motion in three peat bogs between 2002-2009 and 2015-2016. Clara Bog showed sustained subsidence turning to uplift, indicating stabilization. Abbeyleix Bog uplifted after drain blocking. Knockahaw Bog uplifted in areas with minimal drainage changes, demonstrating water retention influences uplift. InSAR allows revising peatland restoration strategies based on continuous monitoring.
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...Christian Olele
- The document discusses a geotechnical site investigation conducted for the Lekki Toll Road infrastructure project in Lagos, Nigeria.
- The investigation included boreholes, standard penetration tests, and laboratory tests to characterize the soil conditions along the route.
- At the proposed Admiralty Toll Plaza site, the subsurface profile consisted of loose to medium dense lagoonal sands, with the water table located between 0.5-2.4m below ground surface. Founding structures on shallow foundations bearing in the sands was recommended.
The document summarizes the results of a geophysical investigation using vertical electrical soundings around Makiyaye village in Nigeria. 18 vertical electrical soundings were conducted and analyzed. The subsurface was found to consist of 4 main layers - a topsoil layer, a weathered basement layer, a partly weathered/fractured basement layer, and a fresh basement layer. Resistivity values and thicknesses of the layers varied across the study area. The geoelectric sections revealed dips and a synclinal structure in the subsurface. Based on the resistivity values, the subsurface material up to 20m depth was found to be competent with high load-bearing capacity, though some low resistivity zones indicated high clay content
TOTAL EARTH SOLUTIONS OIL AND GAS SERVICESBrett Johnson
Total Earth Solutions Pty Ltd (TES) is a specialist aviation, geological, geophysical and geospatial consulting firm providing services to the petroleum and mining industries.
TES provides a range of technical services related to the acquisition, processing and interpretation of geoscientific and geospatial data collected from space, aircraft, UAV’s and ground vehicles.
We aim to offer a complete turnkey service where we can plan and manage surveys all the way through to interpreting the data to create highly detailed analyses of petroleum basins and mining regions.
We differentiate ourselves by employing a strong focus on the geological interpretation of geophysical and geospatial data, but also by having enormous experience in the effective and safe management of airborne and ground survey operations.
Aviation
TES has qualified commercial pilots on its staff, with years of experience in low level survey operations around the world.
Qualified safety auditor.
Sourcing of survey aircraft.
Sourcing of survey pilots.
Development of aviation procedures and management of compliance.
Provision of survey equipment including – magnetic, radiometric, gravity, LIDAR, aerial photography.
Construction and installation of survey systems.
Planning and management of airborne operations.
UAV
TES is at the forefront of development and utilisation of Unmanned Aerial Vehicles (UAV’s) carrying hi-tech payloads such as LIDAR, thermal imaging and geophysical systems, applied to exploration, development, infrastructure mapping and monitoring.
Data Collection
TES can identify, source and interpret the best data for the issue at hand. We have enormous experience in data acquired from a range of platforms, from satellites, aircraft, UAVs, ships through to ground acquisition. We can examine the problem and develop the most cost effective combination of data to meet the needs of the client.
The document provides information on the Crescent Mine located in the Coeur d'Alene Mining District of North Idaho. It summarizes the mine's history of production under Bunker Hill ownership from 1917-1981, including that 25 million ounces of silver were produced at an average grade of 27 oz/ton. It also describes recent exploration work by SNS Silver Corp from 2007-2008 that identified indicated resources of 6.1 million ounces and inferred resources of 4.1 million ounces of silver. The document proposes a joint venture between SNS and Syringa Exploration Inc., who plan to bring the mine back into production and further explore its resources, which have the potential for a 20-30 year mine life.
The document summarizes a project to modify Dike 5 at Folsom Lake through partial removal of the downstream face and construction of new sand and gravel drains to control internal erosion. Key aspects of the project included excavating 40,000 cubic yards of the existing downstream face, installing 1,500 feet of 15-inch toe drain pipe, and placing 18,000 cubic yards of fine sand filter and 2,500 cubic yards of coarse gravel filter. The work was performed between September 2008 and February 2009 using conventional earthmoving equipment as well as a specialized material delivery system to precisely place construction materials.
The document provides information on two sites in Pennsylvania - the Burrell Site and the Canonsburg Site. For the Burrell Site, it summarizes that the major activities are disposal cell and groundwater monitoring with access restrictions. The site size is 28 hectares and the estimated annual cost from 2000-2006 was $51,600. For the Canonsburg Site, it summarizes the major activities are disposal cell monitoring, groundwater and surface water monitoring, and access restrictions, with a site size of 14 hectares and estimated annual cost from 2000-2006 of $148,000.
Björn Jóhann Björnsson is a geological engineer with over 35 years of experience. He has a M.Sc. in Geological Engineering from the University of Idaho and a B.Sc. in Geology from the University of Iceland. He has extensive experience in dam construction, geotechnical engineering, environmental impact assessments, and other areas of geology and engineering. He is currently a consulting engineer and owner of Stuðull Consulting.
This document discusses an experiment analyzing wave loadings on a Seawave Slot-cone Generator (SSG), a wave energy converter. Regular wave tests were conducted in a wave flume on a 1:66 scale model of the SSG located on a sloped "focuser" to increase wave run-up. Pressure transducers measured wave pressures at different heights on the SSG during 31 wave trains with varying heights and periods. The results were used to develop predictive methods for estimating peak wave pressures and rise times on the SSG under different conditions. These predictions will help with structural design of full-scale SSG devices.
This document summarizes a field program conducted in March 2007 by the Geological Survey of Canada to address gaps in baseline environmental data between Fort Good Hope and Norman Wells in the Northwest Territories. Nine sites were selected along different terrain and vegetation conditions. Boreholes up to 20 meters deep were drilled to characterize subsurface materials and ground ice conditions. Eleven boreholes were instrumented with temperature cables to monitor ground thermal regimes over time. This data collection helps characterize current permafrost conditions and will facilitate detection of future changes to inform northern development and environmental assessments.
The document discusses the dredging process and its effects. It provides an overview of different types of dredgers including mechanical dredgers like bucket ladder dredgers and grab dredgers, and hydraulic dredgers like suction hopper dredgers and cutter suction dredgers. It also discusses site investigation processes, soil classification, dredger selection, dumping grounds, effectiveness, impacts, and environmental effects of dredging. Dredging is necessary for activities like creating harbors and maintaining waterways, but can impact the environment through disturbed sediments and potential contamination. Careful planning is required to select the appropriate dredger and minimize negative impacts.
The North Carolina General Assembly requested a coastal wind energy study. The University of North Carolina at Chapel Hill was designated to conduct the study, examining the Pamlico and Albemarle Sounds for offshore wind development over waters less than 30 meters deep. The study evaluated the wind resource, ecological impacts, utility infrastructure, and preliminary economic analysis. It identified large areas offshore with potential for wind farms, which could meet 20% of North Carolina's power demand. A potential turbine demonstration site was identified in the Pamlico Sound.
This document provides guidance for students on conducting fieldwork for the iGCSE Geography exam. It outlines the steps of the enquiry process, including planning, data collection, presentation, analysis and evaluation. It then describes various fieldwork opportunities organized by topic area and exam unit. For each opportunity, it provides details on skills needed, aims, location, hypotheses, data collection techniques, risks, and potential exam questions. The document aims to help students plan and carry out fieldwork investigations that meet the requirements of the iGCSE Geography exam.
Igcse geography coastal environments fieldworkWill Williams
The document provides information about a fieldwork investigation into coastal environments at Shoreham, England. It discusses:
1) Two themes for the fieldwork - measuring beach profiles and material to analyze the impact of coastal protection structures, and conducting a survey to understand local residents' views on coastal management.
2) Background context on the regeneration plans for Shoreham and the need to protect the coastline given new development.
3) Details on the coastal protection methods used, including groynes, seawalls, and beach nourishment.
4) An overview of the fieldwork process, from formulating aims and hypotheses to collecting and analyzing data and drawing conclusions.
5) Instructions for tasks to measure
This document discusses land surface modeling in weather and climate models. It describes the role of land surface models in providing surface boundary conditions, such as heat and water fluxes. It outlines the requirements for land models, including atmospheric forcing data, appropriate physical representations, land cover and soil data, and initial land states. It then covers applications for weather and climate modeling, validation of land models, ongoing work to improve them, and their expanding role within Earth system modeling.
The Parkersburg Site in West Virginia contains an engineered disposal cell for radioactive waste from a former uranium mill. Major long-term stewardship activities include monitoring the disposal cell, restricting access, inspecting fencing and signs, and monitoring groundwater. The 6-hectare site has been monitored since 1983, with disposal of approximately 15,300 cubic meters of waste in the cell. Annual costs average around $16,400, with higher costs every 5 years for groundwater monitoring. The site will remain under long-term stewardship by the DOE indefinitely to ensure the integrity of the disposal cell.
The document discusses modern practices for underground mine planning and design. It covers key topics like mine lifecycles, success factors, planning processes and tools, and expected future developments. Underground mining trends include deeper deposits, higher costs, and increased focus on underground operations. Mine planning requires quality inputs, experienced teams, and software tools to develop designs, schedules, and reports. Factors like orebody geometry, geotechnical conditions, and required production influence the selection of mining methods.
Exploration and analysis of oil and gas field ( 3D seismic survey)Apurva Mittal
This document discusses different types of seismic surveys used in oil and gas exploration and production. It describes 2D seismic surveys, which are inexpensive but provide lower quality data. 3D seismic surveys acquire more detailed data in three dimensions and are more effective for mapping anomalies. 4D seismic surveys involve repeat 3D surveys over time to monitor reservoir performance and locate remaining resources as extraction progresses. Factors like vessel configuration, line orientation, and marine life can impact survey quality and efficiency.
Sedimentation assessment of a small reservoir at afaka forest reserve, kaduna...Alexander Decker
This document summarizes a study assessing sedimentation of a small reservoir in Afaka Forest Reserve, Kaduna, Nigeria. The key findings are:
1. Bathymetric surveys from 2004-2013 showed the reservoir's storage capacity decreased from its initial design capacity of 16,400m3 to 10,665m3, a storage loss of about 35%.
2. A linear relationship between reservoir storage capacity and age established a sedimentation rate of 221m3 per year, meaning the reservoir's storage capacity would be eliminated in 76.5 years without dredging.
3. For economic viability, the study recommends desilting the reservoir every 15 years to remove 3,280m3 of sediment and
This document discusses the role of seismic surveys in establishing oil and gas fields. It describes the various steps involved in seismic data acquisition, including planning, preparation, field operations such as drilling shot holes or operating vibrators, recording seismic data, and processing the data. The objectives of seismic surveys are listed as regional exploration, prospect delineation, and field development. Key factors in planning a survey include the targeted geological features, available budgets and data, and parameter selection for recording seismic signals.
This document summarizes the use of satellite radar techniques to monitor peatland degradation and recovery in the Irish Midlands. It shows that Interferometric Synthetic Aperture Radar (InSAR) can now monitor peatlands continuously over large areas. The study analyzed surface motion in three peat bogs between 2002-2009 and 2015-2016. Clara Bog showed sustained subsidence turning to uplift, indicating stabilization. Abbeyleix Bog uplifted after drain blocking. Knockahaw Bog uplifted in areas with minimal drainage changes, demonstrating water retention influences uplift. InSAR allows revising peatland restoration strategies based on continuous monitoring.
The Role of Geotechnical Site Investigations of Lekki Toll Road Infrastructur...Christian Olele
- The document discusses a geotechnical site investigation conducted for the Lekki Toll Road infrastructure project in Lagos, Nigeria.
- The investigation included boreholes, standard penetration tests, and laboratory tests to characterize the soil conditions along the route.
- At the proposed Admiralty Toll Plaza site, the subsurface profile consisted of loose to medium dense lagoonal sands, with the water table located between 0.5-2.4m below ground surface. Founding structures on shallow foundations bearing in the sands was recommended.
The document summarizes the results of a geophysical investigation using vertical electrical soundings around Makiyaye village in Nigeria. 18 vertical electrical soundings were conducted and analyzed. The subsurface was found to consist of 4 main layers - a topsoil layer, a weathered basement layer, a partly weathered/fractured basement layer, and a fresh basement layer. Resistivity values and thicknesses of the layers varied across the study area. The geoelectric sections revealed dips and a synclinal structure in the subsurface. Based on the resistivity values, the subsurface material up to 20m depth was found to be competent with high load-bearing capacity, though some low resistivity zones indicated high clay content
TOTAL EARTH SOLUTIONS OIL AND GAS SERVICESBrett Johnson
Total Earth Solutions Pty Ltd (TES) is a specialist aviation, geological, geophysical and geospatial consulting firm providing services to the petroleum and mining industries.
TES provides a range of technical services related to the acquisition, processing and interpretation of geoscientific and geospatial data collected from space, aircraft, UAV’s and ground vehicles.
We aim to offer a complete turnkey service where we can plan and manage surveys all the way through to interpreting the data to create highly detailed analyses of petroleum basins and mining regions.
We differentiate ourselves by employing a strong focus on the geological interpretation of geophysical and geospatial data, but also by having enormous experience in the effective and safe management of airborne and ground survey operations.
Aviation
TES has qualified commercial pilots on its staff, with years of experience in low level survey operations around the world.
Qualified safety auditor.
Sourcing of survey aircraft.
Sourcing of survey pilots.
Development of aviation procedures and management of compliance.
Provision of survey equipment including – magnetic, radiometric, gravity, LIDAR, aerial photography.
Construction and installation of survey systems.
Planning and management of airborne operations.
UAV
TES is at the forefront of development and utilisation of Unmanned Aerial Vehicles (UAV’s) carrying hi-tech payloads such as LIDAR, thermal imaging and geophysical systems, applied to exploration, development, infrastructure mapping and monitoring.
Data Collection
TES can identify, source and interpret the best data for the issue at hand. We have enormous experience in data acquired from a range of platforms, from satellites, aircraft, UAVs, ships through to ground acquisition. We can examine the problem and develop the most cost effective combination of data to meet the needs of the client.
The document provides information on the Crescent Mine located in the Coeur d'Alene Mining District of North Idaho. It summarizes the mine's history of production under Bunker Hill ownership from 1917-1981, including that 25 million ounces of silver were produced at an average grade of 27 oz/ton. It also describes recent exploration work by SNS Silver Corp from 2007-2008 that identified indicated resources of 6.1 million ounces and inferred resources of 4.1 million ounces of silver. The document proposes a joint venture between SNS and Syringa Exploration Inc., who plan to bring the mine back into production and further explore its resources, which have the potential for a 20-30 year mine life.
The document summarizes a project to modify Dike 5 at Folsom Lake through partial removal of the downstream face and construction of new sand and gravel drains to control internal erosion. Key aspects of the project included excavating 40,000 cubic yards of the existing downstream face, installing 1,500 feet of 15-inch toe drain pipe, and placing 18,000 cubic yards of fine sand filter and 2,500 cubic yards of coarse gravel filter. The work was performed between September 2008 and February 2009 using conventional earthmoving equipment as well as a specialized material delivery system to precisely place construction materials.
The document provides information on two sites in Pennsylvania - the Burrell Site and the Canonsburg Site. For the Burrell Site, it summarizes that the major activities are disposal cell and groundwater monitoring with access restrictions. The site size is 28 hectares and the estimated annual cost from 2000-2006 was $51,600. For the Canonsburg Site, it summarizes the major activities are disposal cell monitoring, groundwater and surface water monitoring, and access restrictions, with a site size of 14 hectares and estimated annual cost from 2000-2006 of $148,000.
Björn Jóhann Björnsson is a geological engineer with over 35 years of experience. He has a M.Sc. in Geological Engineering from the University of Idaho and a B.Sc. in Geology from the University of Iceland. He has extensive experience in dam construction, geotechnical engineering, environmental impact assessments, and other areas of geology and engineering. He is currently a consulting engineer and owner of Stuðull Consulting.
This document discusses an experiment analyzing wave loadings on a Seawave Slot-cone Generator (SSG), a wave energy converter. Regular wave tests were conducted in a wave flume on a 1:66 scale model of the SSG located on a sloped "focuser" to increase wave run-up. Pressure transducers measured wave pressures at different heights on the SSG during 31 wave trains with varying heights and periods. The results were used to develop predictive methods for estimating peak wave pressures and rise times on the SSG under different conditions. These predictions will help with structural design of full-scale SSG devices.
This document summarizes a field program conducted in March 2007 by the Geological Survey of Canada to address gaps in baseline environmental data between Fort Good Hope and Norman Wells in the Northwest Territories. Nine sites were selected along different terrain and vegetation conditions. Boreholes up to 20 meters deep were drilled to characterize subsurface materials and ground ice conditions. Eleven boreholes were instrumented with temperature cables to monitor ground thermal regimes over time. This data collection helps characterize current permafrost conditions and will facilitate detection of future changes to inform northern development and environmental assessments.
The document discusses the dredging process and its effects. It provides an overview of different types of dredgers including mechanical dredgers like bucket ladder dredgers and grab dredgers, and hydraulic dredgers like suction hopper dredgers and cutter suction dredgers. It also discusses site investigation processes, soil classification, dredger selection, dumping grounds, effectiveness, impacts, and environmental effects of dredging. Dredging is necessary for activities like creating harbors and maintaining waterways, but can impact the environment through disturbed sediments and potential contamination. Careful planning is required to select the appropriate dredger and minimize negative impacts.
This document discusses ground investigation for tunnelling projects. It covers objectives of ground investigation planning including suitability assessment, design, construction planning and environmental impact determination. Key risks like water ingress, ground collapse and obstructions are highlighted. Common ground conditions like dykes, wedges and timber piles are shown. Strategies and techniques for ground investigation planning, during design and construction stages are outlined. Methods for different ground types like soft ground, hard rock and karst deposits are also described. The document emphasizes comprehensive planning and supervision of ground investigation works for tunnelling projects.
Monitoring measuring and verification, Gonzalo Zambrano, University of AlbertaGlobal CCS Institute
This document summarizes Gonzalo Zambrano's presentation on monitoring, measuring and verification (MMV) for CO2 storage projects. It discusses the Aquistore project, which aims to demonstrate safe CO2 storage in deep saline formations in Alberta, Canada. The Aquistore project involves injecting CO2 into a saline formation over 3 km underground and uses various surface and downhole techniques to monitor the CO2 plume and ensure containment. These include 3D and time-lapse seismic surveys, a permanent seismic array, tiltmeters, GPS, and soil gas and groundwater monitoring.
This document provides an overview of drilling engineering. It discusses the history of drilling beginning in the 1840s using percussion drilling. It describes how rotary drilling was developed to allow for offshore drilling. The document outlines the infrastructure and processes involved in drilling, including offshore and onshore structures, load considerations, drilling rigs, bits, pipes, fluids, cementing, directional drilling, kicks, blowout preventers, completions, wellheads, manifolds, and abandonment. Key aspects driving infrastructure decisions are the economic viability and technical requirements of the reservoir and installation.
The document discusses various aspects of conducting a risk assessment for a proposed industrial project, including defining key terms, evaluating hazards and risks, developing emergency response plans, and communication measures. It outlines how environmental impacts will be assessed, hazardous materials will be handled safely, and external agencies will be notified in the event needs arise beyond internal capabilities.
Distribution of petroleum product within the oil rich Niger Delta area of Nigeria is a daunting
task because of its deltaic nature. To solve this challenge, fixed fuel dispensing stations will be built in the
coastal environment to receive and make supplies available to fishermen and marine transporters. Building of
such fuel stations require proper foundation design. Soil test results of the region was obtained and a foundation
design was made to ascertain the number of piles pile depth, pile spacing, skin friction, lateral load bearing
capacity and end bearing capacity. API codes where used to check and ensure that the results obtained are
within safety limits. This will ensure that the offshore structure completes it intended and designed life span.
The document summarizes the presentation "CCS Risk Analysis" given by Neil Wildgust of the Global CCS Institute. The presentation covered risks associated with various aspects of carbon capture and storage (CCS), including capture, transport, and geological storage of CO2. It discussed approaches to assessing and modeling risks, using natural analogs to understand potential impacts, and monitoring and mitigation strategies. The goal of the risk analysis is to evaluate CCS projects and ensure 99% of stored CO2 remains contained for 1,000 years with 80% confidence.
This document proposes a 4th year project on deepwater offshore wind installations. It provides background on the student's interests and family connections to the offshore oil and gas industry. It discusses the growth of offshore wind power, particularly moving into deeper waters. The objectives of the project are to analyze floating platform concepts and installation methods for turbines in deepwater. The methodology will involve researching spar buoys, tension leg platforms, and buoyancy stabilized concepts over the course of an academic year. The student also proposes a relevant summer internship at Allseas to learn about subsea engineering and offshore installation from a leading industry player.
Dust monitoring and control in metal MinesAdil Mathew
This document discusses dust monitoring and control in opencast metal mines. It begins by defining particulate matter and dust, then discusses major sources of dust generation at mines including mining faces, haul roads, crushing plants, and waste dumps. It outlines standards for dust monitoring at work zones and ambient air quality. Monitoring methods like gravimetric sampling are described. The document discusses health effects of dust inhalation and various dust control methods that can be generalized to all mining operations or specialized to specific processes like drilling, blasting, and in-pit crushing. It provides a case study on dust control practices in iron ore mines in Eastern India.
This document provides information about the environmental impacts of various energy sources including wind power, solar power, geothermal energy, and their life cycle emissions. It discusses the land use, wildlife impacts, noise, and other environmental effects of wind turbines. For solar power, it covers land use, water use, and hazardous materials used in manufacturing. The document also outlines the water quality, use, and air emissions related to geothermal energy production.
This document summarizes the key findings and recommendations from a research project on design methods for offshore wind turbines installed at exposed sites. The project involved detailed measurements and analysis of environmental conditions and structural loads on a turbine in the Blyth offshore wind farm. Key findings include: waves in shallow water require non-linear modeling; site-specific wave and wind data should be used; design tools were enhanced and validated; foundation models need to account for soil properties; hydrodynamic loading models were evaluated. Recommendations include: revising certification rules to specify wave modeling and extreme loads; developing standard machinery designs while customizing support structures; accounting for water depth and non-linear waves in design.
Several European offshore wind farm projects have faced high costs and challenges due to complex seabed geology with shallow bedrock. Alternative foundation designs that do not require piling, such as gravity bases and suction caissons, could help reduce costs by simplifying installation processes. For the nascent North American offshore wind industry to be cost-competitive, it will be important to develop foundation technologies suited for local hard soil and bedrock conditions that minimize the need for piling.
Presentation - Case Study on Site Investigation Plan at Chek.pptxolaboughannam1
The document summarizes a case study on the site investigation plan for the construction of the Chek Lap Kok Airport in Hong Kong. An extensive two-part geotechnical program was conducted: (1) detailed site investigation through boreholes, piezocone tests, and laboratory testing revealed up to 20m of very soft marine mud, and (2) a large instrumented test fill evaluated reclamation feasibility and drain configurations. Results showed alidrains accelerated consolidation more than sand drains. The test demonstrated controlled filling and vertical drains could successfully reclaim the soft seabed, avoiding mudwaves with a 1.5m alidrain spacing and 12-month consolidation period.
Presentation - Case Study on Site Investigation Plan at Chek.pptxolaboughannam1
The document summarizes a case study on the site investigation plan for the construction of the Chek Lap Kok Airport in Hong Kong. An extensive two-part geotechnical program was conducted: (1) detailed site investigation through boreholes, piezocone tests, and laboratory testing revealed up to 20m of very soft marine mud, and (2) a large instrumented test fill evaluated reclamation feasibility and drain configurations. Results showed alidrains accelerated consolidation more than sand drains. The test demonstrated controlled filling and vertical drains could successfully reclaim the soft seabed, avoiding mudwaves with a 1.5m alidrain spacing and 12-month consolidation period.
The importance of geohazards for safety, rig/well integrity & drilling. It includes real incidents & worst case scenarios. Pressure concepts, seismic and diagrams are utilized to explain given examples.
The document provides information on Fugro Airborne Surveys' DIGHEM electromagnetic system for near-surface mapping. DIGHEM can be used from both fixed-wing aircraft and helicopters for applications such as mineral and aggregate exploration, groundwater mapping, contaminant mapping, bathymetry, and infrastructure mapping. It describes the DIGHEM system, presents case studies demonstrating its use, and compares it to other airborne electromagnetic systems.
Managing carbon geological storage and natural resources in sedimentary basinsGlobal CCS Institute
To highlight the research and achievements of Australian researchers, the Global CCS Institute, together with Australian National Low Emissions Coal Research and Development (ANLEC R&D), will hold a series of webinars throughout 2017. Each webinar will highlight a specific ANLEC R&D research project and the relevant report found on the Institute’s website.
This is the eighth webinar of the series and will present on basin resource management and carbon storage. With the ongoing deployment of CCS facilities globally, the pore space - the voids in the rock deep in sedimentary basins – are now a commercial resource. This is a relatively new concept with only a few industries utilising that pore space to date.
This webinar presented a framework for the management of basin resources including carbon storage. Prospective sites for geological storage of carbon dioxide target largely sedimentary basins since these provide the most suitable geological settings for safe, long-term storage of greenhouse gases. Sedimentary basins can host different natural resources that may occur in isolated pockets, across widely dispersed regions, in multiple locations, within a single layer of strata or at various depths.
In Australia, the primary basin resources are groundwater, oil and gas, unconventional gas, coal and geothermal energy. Understanding the nature of how these resources are distributed in the subsurface is fundamental to managing basin resource development and carbon dioxide storage. Natural resources can overlap laterally or with depth and have been developed successfully for decades. Geological storage of carbon dioxide is another basin resource that must be considered in developing a basin-scale resource management system to ensure that multiple uses of the subsurface can sustainably and pragmatically co-exist.
This webinar was presented by Karsten Michael, Research Team Leader, CSIRO Energy.
This document discusses the challenges of tunnel design and construction in the GCC (Gulf Cooperation Council) region. It outlines several ongoing and future major tunneling projects in GCC countries like Qatar, Saudi Arabia, and Oman. Key challenges include weak rock formations, karstic features, high groundwater, and tight project timelines. Solutions proposed include using closed-face TBMs, detailed risk analysis to estimate machine advance rates, grouting programs for karst, and steel fiber-reinforced concrete tunnel linings to resist aggressive groundwater. Overall, the large scale of projects in challenging geotechnical conditions requires innovative design and construction approaches.
Introduction first starts by explaining sedimentation of reservoir rocks. Then it moves on to trap elements and responsibilities of a reservoir engineer.
A saturated set of slides that talk about multiple drilling equipment processes & aspects. Examples: rig types, systems, drilling mud, bits, pipes & etc.
Özüllər və qazma qurğuları, sistemləri, qazma baltaları və daha bir çox avadanlıq və proses barədə məlumat. Ən sonda istifadə olunan terminlərin ingiliscə tərcüməsi verilmişdir.
The slide-pack covers a large variety of artificial lift methods. Explanations are supported by breakdown of pros and cons, calculations and questions. Questions will shed light of roughly how to decide which method(s) to use in a specific case.
The slides cover reservoir/fluid properties and production parameters of the Zhetybay oil and gas field located in Khazakstan. Information about geology, porosity-permeability, production and injection allow you to get an idea about drive mechanisms in the field.
Drilling operations can encounter various problems related to geological uncertainties, wellbore stability issues, and depletion effects. Some key risks include uncertainties in pore pressure-fracture gradient measurements, mud volcanoes causing landslides or weak formations, fault zones providing pathways for fluid flow, and maintaining wellbore integrity in low-pressure depleted zones. Operators address these challenges through careful planning, identifying potential hazard areas using seismic data, selecting appropriate drilling fluid properties, and employing wellbore strengthening techniques and lost circulation materials when needed to prevent fluid losses and wellbore collapse.
Abstracts are saturated summary of a research work and is part of academics writing. When applying for conferences, neat structure of an abstract can guarantee admission.
The extensive slide-pack starts with introducing physics and basics on geomechanics. A lot of stress and rock strength concepts are explored. Then it moves on to explain the importance of the discipline for drilling, injection, sanding. Apart from giving theory to understand more difficult content that follow, it throws in practical application and prepares good ground for further study of geomechanical literature.
The content defines geophysics and focuses on roles of seismic on exploration, well planning. It provides insights on integration of various disciplines.
Global warming concerns leading to decarbonization is shifting energy from fossil fuels to renewable energy. The slides briefly touch on different ways of decarbonizing & alternative energy resources.
Exploring formation pressures based on Chapter 5 of Heriot-Watt Drilling Engineering book. Pressure prediction, well planning, well bore stability aspects are also covered in the slide-pack.
Farida Ismayilova has over 3 years of experience working for BP in drilling geohazards and PPFG specialization. She has a Bachelor's and Master's degree in Petroleum Engineering from Azerbaijan State Oil and Industry University. The presentation provides an overview of PPFG terms and principles, and the role of PPFG in well planning. It discusses basics like pore pressure, fracture gradient, and the PPFG window. It also explains how a PPFG specialist incorporates data from nearby wells to estimate high, base, and low cases for safe well design and mud weight selection.
Skin effekti - quyuətrafı zonada müxtəlif səbəblərdən keçiriciliyin dəyişməsi
Təqdimat skin anlayışı, onun səbəbləri, növləri barədə informasiya verir.
Təqdimatda animasiya olduğu üçün təqdimatı yükləyib baxın.
Təqdimat qazma qurğularının növləri, komponentləri,qazma məhlulunun sirkulyasiyası və təmizlənməsi prosesi və avadanlıqları və s. barədə qısa məlumat verir.
Understanding Inductive Bias in Machine LearningSUTEJAS
This presentation explores the concept of inductive bias in machine learning. It explains how algorithms come with built-in assumptions and preferences that guide the learning process. You'll learn about the different types of inductive bias and how they can impact the performance and generalizability of machine learning models.
The presentation also covers the positive and negative aspects of inductive bias, along with strategies for mitigating potential drawbacks. We'll explore examples of how bias manifests in algorithms like neural networks and decision trees.
By understanding inductive bias, you can gain valuable insights into how machine learning models work and make informed decisions when building and deploying them.
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...IJECEIAES
Climate change's impact on the planet forced the United Nations and governments to promote green energies and electric transportation. The deployments of photovoltaic (PV) and electric vehicle (EV) systems gained stronger momentum due to their numerous advantages over fossil fuel types. The advantages go beyond sustainability to reach financial support and stability. The work in this paper introduces the hybrid system between PV and EV to support industrial and commercial plants. This paper covers the theoretical framework of the proposed hybrid system including the required equation to complete the cost analysis when PV and EV are present. In addition, the proposed design diagram which sets the priorities and requirements of the system is presented. The proposed approach allows setup to advance their power stability, especially during power outages. The presented information supports researchers and plant owners to complete the necessary analysis while promoting the deployment of clean energy. The result of a case study that represents a dairy milk farmer supports the theoretical works and highlights its advanced benefits to existing plants. The short return on investment of the proposed approach supports the paper's novelty approach for the sustainable electrical system. In addition, the proposed system allows for an isolated power setup without the need for a transmission line which enhances the safety of the electrical network
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTjpsjournal1
The rivalry between prominent international actors for dominance over Central Asia's hydrocarbon
reserves and the ancient silk trade route, along with China's diplomatic endeavours in the area, has been
referred to as the "New Great Game." This research centres on the power struggle, considering
geopolitical, geostrategic, and geoeconomic variables. Topics including trade, political hegemony, oil
politics, and conventional and nontraditional security are all explored and explained by the researcher.
Using Mackinder's Heartland, Spykman Rimland, and Hegemonic Stability theories, examines China's role
in Central Asia. This study adheres to the empirical epistemological method and has taken care of
objectivity. This study analyze primary and secondary research documents critically to elaborate role of
china’s geo economic outreach in central Asian countries and its future prospect. China is thriving in trade,
pipeline politics, and winning states, according to this study, thanks to important instruments like the
Shanghai Cooperation Organisation and the Belt and Road Economic Initiative. According to this study,
China is seeing significant success in commerce, pipeline politics, and gaining influence on other
governments. This success may be attributed to the effective utilisation of key tools such as the Shanghai
Cooperation Organisation and the Belt and Road Economic Initiative.
International Conference on NLP, Artificial Intelligence, Machine Learning an...gerogepatton
International Conference on NLP, Artificial Intelligence, Machine Learning and Applications (NLAIM 2024) offers a premier global platform for exchanging insights and findings in the theory, methodology, and applications of NLP, Artificial Intelligence, Machine Learning, and their applications. The conference seeks substantial contributions across all key domains of NLP, Artificial Intelligence, Machine Learning, and their practical applications, aiming to foster both theoretical advancements and real-world implementations. With a focus on facilitating collaboration between researchers and practitioners from academia and industry, the conference serves as a nexus for sharing the latest developments in the field.
Embedded machine learning-based road conditions and driving behavior monitoringIJECEIAES
Car accident rates have increased in recent years, resulting in losses in human lives, properties, and other financial costs. An embedded machine learning-based system is developed to address this critical issue. The system can monitor road conditions, detect driving patterns, and identify aggressive driving behaviors. The system is based on neural networks trained on a comprehensive dataset of driving events, driving styles, and road conditions. The system effectively detects potential risks and helps mitigate the frequency and impact of accidents. The primary goal is to ensure the safety of drivers and vehicles. Collecting data involved gathering information on three key road events: normal street and normal drive, speed bumps, circular yellow speed bumps, and three aggressive driving actions: sudden start, sudden stop, and sudden entry. The gathered data is processed and analyzed using a machine learning system designed for limited power and memory devices. The developed system resulted in 91.9% accuracy, 93.6% precision, and 92% recall. The achieved inference time on an Arduino Nano 33 BLE Sense with a 32-bit CPU running at 64 MHz is 34 ms and requires 2.6 kB peak RAM and 139.9 kB program flash memory, making it suitable for resource-constrained embedded systems.
ACEP Magazine edition 4th launched on 05.06.2024Rahul
This document provides information about the third edition of the magazine "Sthapatya" published by the Association of Civil Engineers (Practicing) Aurangabad. It includes messages from current and past presidents of ACEP, memories and photos from past ACEP events, information on life time achievement awards given by ACEP, and a technical article on concrete maintenance, repairs and strengthening. The document highlights activities of ACEP and provides a technical educational article for members.
2. About myself
Farida Ismayilova
>3 years experience as Drilling Geohazards Specialist
Graduate of Azerbaijan State Oil and Industry University
Master’s & Bachelor’s degree in Petroleum Engineering
8. • The Paris Agreement is a legally binding international
treaty on climate change.
• It was initially adopted by 196 parties in Paris -
effective since 2016.
• Its goal is to limit global warming to well below 2,
preferably to 1.5 degrees Celsius, compared to pre-
industrial levels.
• The aim is reducing greenhouse gas emissions as soon
as possible to achieve a climate neutral world by 2050.
Paris agreement
9.
10. Energy business is changing - decarbonization
COST
ENERGY
produced
CO2
emission
COST
ENERGY
produced
Before Becoming
Note: in the future additional cost/tax will be implemented for amount of emissions
11. Energy transition
The Rapid Transition Scenario (Rapid) posits a
series of policy measures, led by a
significant increase in carbon prices.
The Net Zero Scenario (Net Zero) assumes that
the policy measures embodied in Rapid are
both added to and reinforced by significant shifts
in societal behavior and preferences.
15. CCUS requirements
• Demand – a nearby business producing a lot of greenhouse
gasses that is ready to pay for injection
• Government support – regulations, lower taxes to make it
profitable and attractive for investors
• Finding a reservoir with a seal on top to inject – good
parameters, away from highly-populated areas for safety
• Drilling wells to inject, predicting fluids behavior and
contacts through time
geoscience, drilling, completion, reservoir engineering
18. Onshore vs offshore
Average capex costs in 2016-19 for :
• onshore wind farms - £1.61 million per MW,
• offshore wind - £4.49 million per MW (including transmission)
Traditionally onshore turbines have dominated the wind market,
with the first turbine constructed in the late 1800’s.
The first offshore wind project went into effect in the early 1990’s
near Denmark.
Denmark is receiving over 40 percent of their electricity from wind
and 75 percent of that comes from onshore turbines.
19. Advantages of Offshore Wind
• Doesn’t interfere with land use – housing, farming
• Offshore wind speeds are higher
• Wind direction varies less
• More efficient - less turbines provide the same energy as onshore ones
20. Disadvantages of Offshore wind
• Energy transmission to the land is expensive
• More wear & tear of turbines due to high wind speed
• Offshore turbines are harder to install & fix due to distance
• Potential noise pollution and threat to birds
21. Geoscience in offshore wind energy
• Geoscience in determining where to put wind farms
• Gas risk – no shallow gas below or near
• Slope stability
• Soil properties
Similar to assessments prior to platform installation
25. Why so many surveys?
• Geohazard and Archaeological clearance for
permitting and safety of construction and
installation
• Lease Area
• Export Cable Routes
• Geotechnical soil properties for detailed
engineering and design of
• Offshore Wind Turbines
• Offshore Sub-Stations
• Inter-Array Cables
• Export Cables
• Development of Ground Model
• Defining baseline soil parameters &
seabed/subsurface conditions
26. Bathymetry
Bathymetry – using echosounder (sonar) to map seabed morphology. It
reveals slopes, pockmarks, seabed depressions, faulting reaching to
seabed & etc. It is fed into a ground model.
27. Bathymetry example
“Pockmarks” are deep depressions
in the sediments created by
escaping gas. It indicates presence of
shallow gas & can possess risk.
A trough is a linear structural
depression that extends laterally
over a distance.
Sometimes it represents fault
reaching to the surface which can
act as a conduit in case of gas
presence.
28. High-resolution seismic
Conventional seismic ~50Hz frequency used mainly for exploration that
allows imaging several kilometers depth. It won’t suit in case of wind
turbine installation feasibility studies as higher resolution is required.
High-resolution (HR) seismic ~120-200Hz frequency that allows resolving
5-15m thickness. Can be suitable for shallow depth analysis.
Ultra-high-resolution (UHR) ~600Hz frequency can resolve a few meters
thickness but is more expensive and not always necessary.
Note: Higher frequency, better resolutions but less depth coverage of imaging.
32. Geotechnical data: in-situ tests
Drilling geotechnical boreholes for in-situ testing and
taking core samples for laboratory tests.
During in-situ Cone Penetration Test (CPT) the forces on
the cone and the friction sleeve are measured.
Based on that undrained shear strength, relative density,
load bearing capacity are calculated.
33. Geotechnical data: lab tests
Soil samples are taken to the lab for thorough
analysis
For soil classification - defining moisture content,
specific gravity, particle distribution & etc
For determining the aggressiveness of groundwater
to concrete & steel structures - chemical analysis of
groundwater (pH value, sulphate content and
chloride content tests)
34. Soil strength and deformation
Unconfined compression strength (UCS) - determination of the
unconfined compressive strength of cohesive soil of the axial load.
Consolidation test (1D) - consolidation of soils are used to
estimate the magnitude and rate of settlement of a structure.
Consolidated undrained triaxial compression test (3D) -
determination of strength and stress-strain relationships of
cohesive soil. Used to predict how the material will behave in a
larger-scale geotechnical engineering applications.
An example would be to predict the stability of the soil on a slope.
Unconfined compression
strength (UCS)
36. Where would you put a
wind turbine? (geophysics)
• Away from shallow gas & pockmarks
• On a stable slope, not at the base of a
seabed slump
• In soils with sufficient soil strength to
withstand the weight
37. C o n c l u s i o n
Geoscience and Geophysical skills have a place in the future:
• Shallow depth analysis for Renewables – Offshore Wind
• Deep analysis for Carbon Capture & Underground Storage
38. Denmark Technical University –
• Wind energy
• Introduction to solar cells
• Organic Solar Cells - Theory and Practice
Open resources