SlideShare a Scribd company logo
1 of 18
Case Study on Site Investigation
Plan at Chek Lap Kok, Hong Kong
O. BOU GHANAM, C. TANISSA
DEPARTMENT OF CIVIL & ENVIRONMENTAL
ENGINEERING, UNIVERSITY OF ILLINOIS
URBANA-CHAMPAIGN
Project Description
 Construction of Hong Kong replacement airport by
levelling the island of Chek Lap Kok and Lam Chau
and Reclaiming almost 600 Ha of land
 Preliminary offshore site investigation (1973-1978)
revealed the presence of
 Up to 20 m of very soft marine mud forming the
seabed around the islands.
 Additional cohesive sediments, somewhat stronger
and less compressible, sporadically indicated at
greater depths.
 Anticipated Construction problems due to large
settlements/ differential settlements and large
mudwaves.
Wu et al. (2020).
O. BOU GHANAM & C. TANISSA 2/18
CEE - Geotech
Project: Geotechnical Risks and Constraints
.
Stability
• Embankment Stability
• Bearing Capacity
Failures
• Mud Waves
Settlements
• Excessive Total
Settlements
• Intolerable Differential
Settlements
Seawalls
• Stability of Seawalls
• Excessive deformation
Cost and Time
• Decide on most
efficient construction/
ground improvement
solution
O. BOU GHANAM & C. TANISSA 3/18
CEE - Geotech
Geotechnical Program
 Purpose of Geo-technical Program:
 Fully defining the problems;
 Assessing the viability of using vertical drains and careful filling techniques to allow successful
construction over the mud, eliminating the need to excavate and replace.
Two parts:
 Part I: Extensive site investigation to provide detailed data regarding the foundation soils at the site.
 Part II: The construction of a heavily instrumented large test fill into the sea from Chek Lap Kok to
evaluate feasibility of reclamations and staged construction works with various vertical drain
configurations
O. BOU GHANAM & C. TANISSA 4/18
CEE - Geotech
Part I: Site Investigation
 77 marine boreholes, drilled from floating barges using land drilling
equipment with good sampling procedures (drilling mud, casing, fixed
piston and shelby sampling)
 93 piezocone penetration soundings, 60° conical piezocone tip,
projected area of 15 cm2, sleeve area of 200 cm2, porous piezometer
element located midway between the tip and the base, rate 2cm/sec
 95 pore pressure dissipation tests;
 Extensive field vane testing; 65-mm x 130-mm field vane tip was used
in the soft marine mud, while a 55-mm x 110-mm vane tip was used in
the stiffer clays. performed at a rate of rotation of 6°/min to develop the
peak (undisturbed) strength, after which 10 time rotation and a second
shear test performed at 6°/min
 In-situ variable head permeability tests using Geonor Piezometers
 Marine geophysical studies
 Extensive laboratory testing program including both routine and
specialized tests
O. BOU GHANAM & C. TANISSA 5/18
CEE - Geotech
Subsurface Stratigraphy
 [0 -15m]: Upper Marine Clay: Very soft and
compressible Seabed Mud
[15 – 23m]: Upper Alluvium: Very stiff
desiccated and fissured clay with frequent
dense sand lenses [OCR 4-8]
[23 – 38m]: Lower Marine Clay: Medium stiff
light marine clay [OCR 2-3]
[38 – 48m]: Lower Alluvium: Very dense coarse
to fine sand, becomes very silty, with occasional
lenses of hard clay, frequently grades into
gravels and cobbles.
[48 – End]: Completely Decomposed Granite
(CDG) overlaying Granite Bedrock
O. BOU GHANAM & C. TANISSA 6/18
CEE - Geotech
Piezocone-Borehole Correlations
O. BOU GHANAM & C. TANISSA 7/18
CEE - Geotech
Upper Marine Clay

Lower Marine Clay
O. BOU GHANAM & C. TANISSA 8/18
CEE - Geotech
Properties of Upper/Lower Marine Clay
Upper Marine Clay Lower Marine Clay
Classification High Plastic Clay - CH Medium to High Plasticity CL/CH
Plasticity Index 45-65% 20-40%
Water Content MC > LL 30-60%
OCR 1.5 to 2.0 4.0 to 7.0
Normalized Shear Strength
from FVS: su/σ’vo
0.42 0.4 to 0.6
Cc 0.3 to 0.5 0.15 to 0.35
Cr 5 to 10% Cc 0.02 to 0.06
Cv 1.3 ± 0.5 m2/yr 2.0 ± 1 m2/yr
Ch 4 m2/yr
O. BOU GHANAM & C. TANISSA 9/18
CEE - Geotech
Part II: Test Fill - Objectives
 Objective:
 Development of in-situ information regarding the
consolidation characteristic of the seabed mud layer
Development of in-situ information regrading
embankment stability
Assessing the viability of staged reclamation and the
applicable rates of constructions
Assessing the feasibility of multiple vertical drain
configurations ( Sand Drains Vs at various diameters/
spacing) in speeding consolidation settlements
Test Fill Construction: (a) March, 1982, Seawall Coming
above Water; (b) April, 1982, Drain Installation in Main Test
Area, Haul Road on Left; (c) July, 1982, Completed Test Fill
O. BOU GHANAM & C. TANISSA 10/18
CEE - Geotech
Part II: Test Fill – Construction Details
 Located 200 m offshore, 100 m square of plan
 Built over a soil profile consisting of:
 4 m of sea water to reach the seabed
 7 m of fairly uniform mud,
 5-6 m of upper alluvial crust deposits,
 3-8 m of lower marine clay deposits,
 7-13 m of lower alluvial deposits,
 CDG residual Soils
 Four Quadrants:
 Control Area - No treatment
 500-mm diameter displacement sand drains at 3.0 m
triangular spacings
 Plastic band Alidrain at 1.5 and 3.0 meters triangular
spacing in the remaining twi quadrants
Plan of Test Fill
O. BOU GHANAM & C. TANISSA 11/18
CEE - Geotech
Part II: Test Fill – Instrumentation
Instrument Measured Parameters Installed
to June, 1982
Operational
Nov., 1982
Pneumatic piezometer
Porewater pressure
63 63
Hydraulic piezometer 13 13
Settlement plate Surface settlement and
groundwater level
58 57
Settlement profile pipe Surface settlement profiles 19 5
Pneumatic settlement gauge Subsurface settlement 10 ?
Inclinometer Subsurface lateral
movement
9 7
Subsurface settlement
anchors/Inclinometer
Subsurface settlement
and lateral movement
12 10
Surface movement
point
Surface settlement and
horizontal movement
54 54
O. BOU GHANAM & C. TANISSA 12/18
CEE - Geotech
Part II: Test Fill –Measurements & Constraints
 Measurements of :
◦ Consolidation and settlement of the
subsurface soils;
◦ lateral movement in the fill and
subsurface soils;
◦ pore pressure generation and
dissipation; and
◦ Embankment filling.
• Use of instrumentation
specifically designed to
accommodate large
strains.
Instrumentation
to accommodate
large
movements
• Duplication of instruments to allow for
loss of some installations.
• Duplication of the method of
measurement by using two or more
different instrument types
• Extensive protection measures,
especially
Anticipated large
damage rate due
to ongoing
construction
activities
O. BOU GHANAM & C. TANISSA 13/18
CEE - Geotech
Part II: Main Test Fill – Results and Interpretations
Settlement profiles (one-dimensional/ Uniform) observed via a pipe installed at the end of the
Construction Stage 4 across the 1.5-m Alidrain and 3-m sand drain quadrants
O. BOU GHANAM & C. TANISSA 14/18
CEE - Geotech
Part II: Main Test Fill – Results and Interpretations
Settlements of Upper Marine Clay in Main Test Area
 The inclusion of Alidrains accelerated the
consolidation process;
 Closer spacing of the Alidrains resulted in
faster settlement.
 The effectiveness of the sand drains, on the
other hand, appears to be limited
 Estimated Settlements appeared reasonable
when compared to measured values
O. BOU GHANAM & C. TANISSA 15/18
CEE - Geotech
Part II: Main Test Fill – Results and Interpretations
 Data from permanent Piezometers and
Piezo-profile tests
 Pore pressures were extrapolated from
Pore pressure isochrones and Coefficients of
Consolidations of soils were back-calculated:
Estimated Cv for Soft mud of 2.9 m2/ yr,
higher than the the value estimated from
testing program ( 1.3 m2/yr)
Effective Vertical paths were estimated for
each quadrant
Distribution of Excess Pore Pressures with Depth-
Main Test Area
O. BOU GHANAM & C. TANISSA 16/18
CEE - Geotech
Part II: Main Test Fill – Conclusions
 The test fill successfully demonstrated the viability of building the Chek Lap Kok Airport
reclamation over the soft seabed mud
The development of mudwaves could be avoided by controlled filling in layers
Vertical band drains could be used to accelerate consolidation of the mud
Displacement sand drains were not successful
Alidrains tested were found to be very effective despite the large vertical strains experienced
 Solution: Install Alidrain or an equivalent product at 1.5-m spacing and with a 12-month
consolidation period, with 25% Preload
O. BOU GHANAM & C. TANISSA 17/18
CEE - Geotech
Performance: Settlement
Measurements -Multi-temporal InSAR
(a) Estimated overall settlement velocity over the two decades. (b)-
(g) Time series of settlements of six selected points estimated from
MT-InSAR (blue triangles) and the settlement model (curves)
 Significant settlement since its operation in
1998 due mainly to consolidation of the
materials used in the land reclamation and
underlaying mud deposits;
 Settlement Measurements using Interferometric
Synthetic Aperture Radar (InSAR)
 The results reveal both spatial and temporal
variations of the land settlement, accumulating
to over 40 cm over two Decades
 The results are validated through cross-
validation between the datasets and with
leveling and GPS measurements on the Airport
platform.
O. BOU GHANAM & C. TANISSA 18/18
CEE - Geotech

More Related Content

Similar to Presentation - Case Study on Site Investigation Plan at Chek.pptx

(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...Michal Krzeminski
 
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...Michal Krzeminski
 
Miraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground ImprovementMiraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground ImprovementADFIAP
 
Miraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground ImprovementMiraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground ImprovementADFIAP
 
IJSRED-V2I3P89
IJSRED-V2I3P89IJSRED-V2I3P89
IJSRED-V2I3P89IJSRED
 
IJSRED-V2I3P89
IJSRED-V2I3P89IJSRED-V2I3P89
IJSRED-V2I3P89IJSRED
 
IJSRED-V2I3P89
IJSRED-V2I3P89IJSRED-V2I3P89
IJSRED-V2I3P89IJSRED
 
IJSRED-V2I3P89
IJSRED-V2I3P89IJSRED-V2I3P89
IJSRED-V2I3P89IJSRED
 
Overview of High Vacuum Densification Method (HVDM) for soft soils Improvement
Overview of High Vacuum Densification Method (HVDM) for soft soils Improvement Overview of High Vacuum Densification Method (HVDM) for soft soils Improvement
Overview of High Vacuum Densification Method (HVDM) for soft soils Improvement Ripon Chandra Malo
 
Overview of High Vacuum Densification Method (HVDM) for soft soils Improvement
Overview of High Vacuum Densification Method (HVDM) for soft soils Improvement Overview of High Vacuum Densification Method (HVDM) for soft soils Improvement
Overview of High Vacuum Densification Method (HVDM) for soft soils Improvement Ripon Chandra Malo
 
Pradipta Banik- Buet 1204012- thesis presentation
Pradipta Banik- Buet 1204012- thesis presentationPradipta Banik- Buet 1204012- thesis presentation
Pradipta Banik- Buet 1204012- thesis presentationPradipta Banik
 
Pradipta Banik- Buet 1204012- thesis presentation
Pradipta Banik- Buet 1204012- thesis presentationPradipta Banik- Buet 1204012- thesis presentation
Pradipta Banik- Buet 1204012- thesis presentationPradipta Banik
 
Applicability, quality control and quality assurance in
Applicability, quality control and quality assurance inApplicability, quality control and quality assurance in
Applicability, quality control and quality assurance inKulbir Singh gill
 
Applicability, quality control and quality assurance in
Applicability, quality control and quality assurance inApplicability, quality control and quality assurance in
Applicability, quality control and quality assurance inKulbir Singh gill
 
Compaction and Drainability 01
Compaction and Drainability 01Compaction and Drainability 01
Compaction and Drainability 01Muhammad Faisal
 
Compaction and Drainability 01
Compaction and Drainability 01Compaction and Drainability 01
Compaction and Drainability 01Muhammad Faisal
 
Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Angelo Indelicato
 
Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Angelo Indelicato
 

Similar to Presentation - Case Study on Site Investigation Plan at Chek.pptx (20)

Gq3311661169
Gq3311661169Gq3311661169
Gq3311661169
 
Gq3311661169
Gq3311661169Gq3311661169
Gq3311661169
 
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
 
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
 
Miraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground ImprovementMiraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground Improvement
 
Miraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground ImprovementMiraculous Solution to Asia Pacific Soft Ground Improvement
Miraculous Solution to Asia Pacific Soft Ground Improvement
 
IJSRED-V2I3P89
IJSRED-V2I3P89IJSRED-V2I3P89
IJSRED-V2I3P89
 
IJSRED-V2I3P89
IJSRED-V2I3P89IJSRED-V2I3P89
IJSRED-V2I3P89
 
IJSRED-V2I3P89
IJSRED-V2I3P89IJSRED-V2I3P89
IJSRED-V2I3P89
 
IJSRED-V2I3P89
IJSRED-V2I3P89IJSRED-V2I3P89
IJSRED-V2I3P89
 
Overview of High Vacuum Densification Method (HVDM) for soft soils Improvement
Overview of High Vacuum Densification Method (HVDM) for soft soils Improvement Overview of High Vacuum Densification Method (HVDM) for soft soils Improvement
Overview of High Vacuum Densification Method (HVDM) for soft soils Improvement
 
Overview of High Vacuum Densification Method (HVDM) for soft soils Improvement
Overview of High Vacuum Densification Method (HVDM) for soft soils Improvement Overview of High Vacuum Densification Method (HVDM) for soft soils Improvement
Overview of High Vacuum Densification Method (HVDM) for soft soils Improvement
 
Pradipta Banik- Buet 1204012- thesis presentation
Pradipta Banik- Buet 1204012- thesis presentationPradipta Banik- Buet 1204012- thesis presentation
Pradipta Banik- Buet 1204012- thesis presentation
 
Pradipta Banik- Buet 1204012- thesis presentation
Pradipta Banik- Buet 1204012- thesis presentationPradipta Banik- Buet 1204012- thesis presentation
Pradipta Banik- Buet 1204012- thesis presentation
 
Applicability, quality control and quality assurance in
Applicability, quality control and quality assurance inApplicability, quality control and quality assurance in
Applicability, quality control and quality assurance in
 
Applicability, quality control and quality assurance in
Applicability, quality control and quality assurance inApplicability, quality control and quality assurance in
Applicability, quality control and quality assurance in
 
Compaction and Drainability 01
Compaction and Drainability 01Compaction and Drainability 01
Compaction and Drainability 01
 
Compaction and Drainability 01
Compaction and Drainability 01Compaction and Drainability 01
Compaction and Drainability 01
 
Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...
 
Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...
 

Recently uploaded

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 

Recently uploaded (20)

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 

Presentation - Case Study on Site Investigation Plan at Chek.pptx

  • 1. Case Study on Site Investigation Plan at Chek Lap Kok, Hong Kong O. BOU GHANAM, C. TANISSA DEPARTMENT OF CIVIL & ENVIRONMENTAL ENGINEERING, UNIVERSITY OF ILLINOIS URBANA-CHAMPAIGN
  • 2. Project Description  Construction of Hong Kong replacement airport by levelling the island of Chek Lap Kok and Lam Chau and Reclaiming almost 600 Ha of land  Preliminary offshore site investigation (1973-1978) revealed the presence of  Up to 20 m of very soft marine mud forming the seabed around the islands.  Additional cohesive sediments, somewhat stronger and less compressible, sporadically indicated at greater depths.  Anticipated Construction problems due to large settlements/ differential settlements and large mudwaves. Wu et al. (2020). O. BOU GHANAM & C. TANISSA 2/18 CEE - Geotech
  • 3. Project: Geotechnical Risks and Constraints . Stability • Embankment Stability • Bearing Capacity Failures • Mud Waves Settlements • Excessive Total Settlements • Intolerable Differential Settlements Seawalls • Stability of Seawalls • Excessive deformation Cost and Time • Decide on most efficient construction/ ground improvement solution O. BOU GHANAM & C. TANISSA 3/18 CEE - Geotech
  • 4. Geotechnical Program  Purpose of Geo-technical Program:  Fully defining the problems;  Assessing the viability of using vertical drains and careful filling techniques to allow successful construction over the mud, eliminating the need to excavate and replace. Two parts:  Part I: Extensive site investigation to provide detailed data regarding the foundation soils at the site.  Part II: The construction of a heavily instrumented large test fill into the sea from Chek Lap Kok to evaluate feasibility of reclamations and staged construction works with various vertical drain configurations O. BOU GHANAM & C. TANISSA 4/18 CEE - Geotech
  • 5. Part I: Site Investigation  77 marine boreholes, drilled from floating barges using land drilling equipment with good sampling procedures (drilling mud, casing, fixed piston and shelby sampling)  93 piezocone penetration soundings, 60° conical piezocone tip, projected area of 15 cm2, sleeve area of 200 cm2, porous piezometer element located midway between the tip and the base, rate 2cm/sec  95 pore pressure dissipation tests;  Extensive field vane testing; 65-mm x 130-mm field vane tip was used in the soft marine mud, while a 55-mm x 110-mm vane tip was used in the stiffer clays. performed at a rate of rotation of 6°/min to develop the peak (undisturbed) strength, after which 10 time rotation and a second shear test performed at 6°/min  In-situ variable head permeability tests using Geonor Piezometers  Marine geophysical studies  Extensive laboratory testing program including both routine and specialized tests O. BOU GHANAM & C. TANISSA 5/18 CEE - Geotech
  • 6. Subsurface Stratigraphy  [0 -15m]: Upper Marine Clay: Very soft and compressible Seabed Mud [15 – 23m]: Upper Alluvium: Very stiff desiccated and fissured clay with frequent dense sand lenses [OCR 4-8] [23 – 38m]: Lower Marine Clay: Medium stiff light marine clay [OCR 2-3] [38 – 48m]: Lower Alluvium: Very dense coarse to fine sand, becomes very silty, with occasional lenses of hard clay, frequently grades into gravels and cobbles. [48 – End]: Completely Decomposed Granite (CDG) overlaying Granite Bedrock O. BOU GHANAM & C. TANISSA 6/18 CEE - Geotech
  • 7. Piezocone-Borehole Correlations O. BOU GHANAM & C. TANISSA 7/18 CEE - Geotech
  • 8. Upper Marine Clay  Lower Marine Clay O. BOU GHANAM & C. TANISSA 8/18 CEE - Geotech
  • 9. Properties of Upper/Lower Marine Clay Upper Marine Clay Lower Marine Clay Classification High Plastic Clay - CH Medium to High Plasticity CL/CH Plasticity Index 45-65% 20-40% Water Content MC > LL 30-60% OCR 1.5 to 2.0 4.0 to 7.0 Normalized Shear Strength from FVS: su/σ’vo 0.42 0.4 to 0.6 Cc 0.3 to 0.5 0.15 to 0.35 Cr 5 to 10% Cc 0.02 to 0.06 Cv 1.3 ± 0.5 m2/yr 2.0 ± 1 m2/yr Ch 4 m2/yr O. BOU GHANAM & C. TANISSA 9/18 CEE - Geotech
  • 10. Part II: Test Fill - Objectives  Objective:  Development of in-situ information regarding the consolidation characteristic of the seabed mud layer Development of in-situ information regrading embankment stability Assessing the viability of staged reclamation and the applicable rates of constructions Assessing the feasibility of multiple vertical drain configurations ( Sand Drains Vs at various diameters/ spacing) in speeding consolidation settlements Test Fill Construction: (a) March, 1982, Seawall Coming above Water; (b) April, 1982, Drain Installation in Main Test Area, Haul Road on Left; (c) July, 1982, Completed Test Fill O. BOU GHANAM & C. TANISSA 10/18 CEE - Geotech
  • 11. Part II: Test Fill – Construction Details  Located 200 m offshore, 100 m square of plan  Built over a soil profile consisting of:  4 m of sea water to reach the seabed  7 m of fairly uniform mud,  5-6 m of upper alluvial crust deposits,  3-8 m of lower marine clay deposits,  7-13 m of lower alluvial deposits,  CDG residual Soils  Four Quadrants:  Control Area - No treatment  500-mm diameter displacement sand drains at 3.0 m triangular spacings  Plastic band Alidrain at 1.5 and 3.0 meters triangular spacing in the remaining twi quadrants Plan of Test Fill O. BOU GHANAM & C. TANISSA 11/18 CEE - Geotech
  • 12. Part II: Test Fill – Instrumentation Instrument Measured Parameters Installed to June, 1982 Operational Nov., 1982 Pneumatic piezometer Porewater pressure 63 63 Hydraulic piezometer 13 13 Settlement plate Surface settlement and groundwater level 58 57 Settlement profile pipe Surface settlement profiles 19 5 Pneumatic settlement gauge Subsurface settlement 10 ? Inclinometer Subsurface lateral movement 9 7 Subsurface settlement anchors/Inclinometer Subsurface settlement and lateral movement 12 10 Surface movement point Surface settlement and horizontal movement 54 54 O. BOU GHANAM & C. TANISSA 12/18 CEE - Geotech
  • 13. Part II: Test Fill –Measurements & Constraints  Measurements of : ◦ Consolidation and settlement of the subsurface soils; ◦ lateral movement in the fill and subsurface soils; ◦ pore pressure generation and dissipation; and ◦ Embankment filling. • Use of instrumentation specifically designed to accommodate large strains. Instrumentation to accommodate large movements • Duplication of instruments to allow for loss of some installations. • Duplication of the method of measurement by using two or more different instrument types • Extensive protection measures, especially Anticipated large damage rate due to ongoing construction activities O. BOU GHANAM & C. TANISSA 13/18 CEE - Geotech
  • 14. Part II: Main Test Fill – Results and Interpretations Settlement profiles (one-dimensional/ Uniform) observed via a pipe installed at the end of the Construction Stage 4 across the 1.5-m Alidrain and 3-m sand drain quadrants O. BOU GHANAM & C. TANISSA 14/18 CEE - Geotech
  • 15. Part II: Main Test Fill – Results and Interpretations Settlements of Upper Marine Clay in Main Test Area  The inclusion of Alidrains accelerated the consolidation process;  Closer spacing of the Alidrains resulted in faster settlement.  The effectiveness of the sand drains, on the other hand, appears to be limited  Estimated Settlements appeared reasonable when compared to measured values O. BOU GHANAM & C. TANISSA 15/18 CEE - Geotech
  • 16. Part II: Main Test Fill – Results and Interpretations  Data from permanent Piezometers and Piezo-profile tests  Pore pressures were extrapolated from Pore pressure isochrones and Coefficients of Consolidations of soils were back-calculated: Estimated Cv for Soft mud of 2.9 m2/ yr, higher than the the value estimated from testing program ( 1.3 m2/yr) Effective Vertical paths were estimated for each quadrant Distribution of Excess Pore Pressures with Depth- Main Test Area O. BOU GHANAM & C. TANISSA 16/18 CEE - Geotech
  • 17. Part II: Main Test Fill – Conclusions  The test fill successfully demonstrated the viability of building the Chek Lap Kok Airport reclamation over the soft seabed mud The development of mudwaves could be avoided by controlled filling in layers Vertical band drains could be used to accelerate consolidation of the mud Displacement sand drains were not successful Alidrains tested were found to be very effective despite the large vertical strains experienced  Solution: Install Alidrain or an equivalent product at 1.5-m spacing and with a 12-month consolidation period, with 25% Preload O. BOU GHANAM & C. TANISSA 17/18 CEE - Geotech
  • 18. Performance: Settlement Measurements -Multi-temporal InSAR (a) Estimated overall settlement velocity over the two decades. (b)- (g) Time series of settlements of six selected points estimated from MT-InSAR (blue triangles) and the settlement model (curves)  Significant settlement since its operation in 1998 due mainly to consolidation of the materials used in the land reclamation and underlaying mud deposits;  Settlement Measurements using Interferometric Synthetic Aperture Radar (InSAR)  The results reveal both spatial and temporal variations of the land settlement, accumulating to over 40 cm over two Decades  The results are validated through cross- validation between the datasets and with leveling and GPS measurements on the Airport platform. O. BOU GHANAM & C. TANISSA 18/18 CEE - Geotech