General Estimation & Abstract Sheet of Royal City
Shaikh Ajim1, Raut Vishwajit2, Shah Tajmmul3, Pawar Ganesh4, Pathan Alim5, Shejwal Yogesh6
1Guide. Department Of Civil Engineering, Ashok Polytechnic, Maharashtra, India
2,3,4,5,6Student. Department Of Civil Engineering, Ashok Polytechnic, Maharashtra, India
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract – The estimating and costing means technique of the calculating the various quantities of executed work and then
determining their cost known as costing
The costing is mainly done by abstract sheet which is seen as follows
Also it is use to determine the cost and labors for the work and in this rates of DSR is use the rates given in the DSR arerevised
every year, also the rates given in DSR includes 10% contractor’s profit
(Key words : estimating, costing, cost, abstract sheet, labors, 10% contractor’s profit)
1. INTRODUCTION
This project is under guidance of prof. shaikh A. S of General estimation of the city which has name as royal city, in which
includes hospital (G+1), hostel (G), school (G+2), collage (G+2), 3bhk rowhouses,3bhk apartments,1bhk apartmentsandmall.
And also abstract sheet is done after calculating the quantities of each building
2. APPROXIMATE ESTIMATE
Approximate estimate means the preliminary estimate , because it is also use full forgettingadministrativeapproval .alsofor
it site plans and layout plans are required
Purposes of approximate estimate
1. It gives rough idea about the cost which is required for the project or work which will be executed
2. Easy to check feasibility of project
3. It is also helpful to administrative approval and technical sanction
Comes here Conclusion content comes here Conclusion content comes here Conclusion content comes here
4. sample calculations
Measurement sheet
SR.NO DESCRIPTION NOS LENGTH BREADH HEIGTH QUANTITY
1. EXCAVATION
Excavation in soft murum in foundation with
lead & lift etc. complete.
17 1.2 1.2 1.5 17.13
2. PCC
Pcc bed below the foundation in proportion
with providing & laying , compacting , curing
etc. complete.
17 1.2 1.2 0.2 4.89
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 03 | Mar -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 817
Abstract sheet
S.NO DESCRIPTION SPECIFICATION UNIT
QUN
TITY
COMPLETED
RATE PER
UNIT
AMOUNT
LABO
UR
RATE
PER
UNIT
AMOUN
T
1
EXCAVATION-
Excavation For
Foundation In Earth ,soil
of all types
,sand,gravel,and soft
murum including
removing the excavated
material up to a distance
of 50 m
Beyond the building area
and stacking and
spreading as directed
,dewatering preparing
the bed for the
foundation and
necessary back filling
ramming, watering
including shoring and
strutting etc. complete
.with lift up to 1.50 m
a.hard murum
lift up to 1.50 m
Spec.no.Bd.A.2
Page no.259
Cubic
meter
36.7
2
118 4332.96 118 4332.96
2
PCC-
Providing and laying in
situ,cement concrete M-
15/1:2:4 of
trap/granite/quartzite/g
neiss metal for
foundation and bedding
including bailing-out
water manually
formwork, compacting
covering newly laid
concrete by gunny bag,
plastic tarpaulin curing
etc. complete
Spec.no.Bd
E.1
Page no.287/is-
456-2000
Cubic
meter
4.89 3823 18694.47 380 1858.2
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 03 | Mar -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 818
there are various of approximate estimating and costing like
1. plinth area method
2. cubical content method
3. service unit method
4. typical bay method
5. approximate quantity method
and also methods to calculating quantities are
1. PWD(Long wall Short wall)method
2. Centerline method
1. PWD(Long wall Short wall)method : in this method the longer wall in the building are consider as long
wall .this wall are measured from out to out . the shorter wall are perpendicular to the long wall are
measured from in to in of length long walls are considered as short wall
Length of long wall = center to center length of long wall + width ofitem
Length of long wall = center to center length of long wall - width ofitem
Fig. No 1:Plan of royal city, Shrirampur
Centerline method:
 Draw centerline plan
 Calculate total length of center line
 Calculate no of T junction
 Take no of junction for walls meeting for three directions =1
 No of junction for walls meeting from 4directions = 2
 Calculate length of item as
L=total c/c length – (1/2) x no of junction x width of item
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 04 Issue: 03 | Mar -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 819
Hence total completed rate = 23027.43
Total labour rate = 6191.16
Total amount for this item = labour rate+
completed rate
Total amount for this item = 29218.59
Like this
Building name Amount for built with
contractor’s profit
1compartment of
3BHK
5545345 /-
compartment of
1BHK
5045565 /-
Hospital 565765 /-
School 7245435 /-
Collage 177342 /-
1 row house 312053.7 /-
Hostel 1022343 /-
mall 55454342 /-
5. CONCLUSION
Due to this we can publish also tender notices and
also an importance of this project is that it is helpful to
fixation to tax, also for the valuation it is very important
Du to this also we can know the cost of our
construction to do financial arrangements and the
arrangements of labors and materials for project
6. ACKNOWLEDGEMENT
It has been a privilege for me to be associated with
Prof.shaikh.A.S my guide during this dissertation work. I
have been greatly benefited by their valuable suggestions
and ideas
Finally, I would like to express my deep,
incomparable appreciation and gratitude to my family
members for their constant spiritual support and
encouragement to pursue the higher technical education.
REFERENCES
1. Estimating And Costing, Author :Kavita L. Bavdekar
2. BUILDING BY LOWS BY govt.of india
3. Www. Estimating And Costing. Wikipedia the free
encyclopedia .in
4. District schedule rate of Nasik division(by PWD)
BIOGRAPHIES
Shaikh Ajim
Guide. Department Of Civil Engineering,
Ashok Polytechnic, Maharashtra, India
Raut Vishwajit
Student. Department Of Civil
Engineering, Ashok Polytechnic,
Maharashtra, India
Shah Tajmmul
Student. Department Of Civil
Engineering, Ashok Polytechnic,
Maharashtra, India
Pawar Ganesh
Student. Department Of Civil
Engineering, Ashok Polytechnic,
Maharashtra, India
Pathan Alim
Student. Department Of Civil
Engineering, Ashok Polytechnic,
Maharashtra, India
Shejwal Yogesh
Student. Department Of Civil
Engineering, Ashok Polytechnic,
Maharashtra, India

More Related Content

What's hot

Job Layout
Job LayoutJob Layout
Job Layout
Bahzad5
 
LOW COST HOUSING
LOW COST HOUSINGLOW COST HOUSING
LOW COST HOUSING
SUJEESH A S
 
Rate analysis brief
Rate analysis briefRate analysis brief
Rate analysis brief
sonali parashar
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
Simarpreet Singh
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
Ganesh Tatikonda
 
Pavement design
Pavement designPavement design
Pavement design
Garvit Goyal
 
PREPARE RATE ANALYSIS OF PAINTING WORK USING OBD , PLASTIC EMULSION OIL PAINT...
PREPARE RATE ANALYSIS OF PAINTING WORK USING OBD , PLASTIC EMULSION OIL PAINT...PREPARE RATE ANALYSIS OF PAINTING WORK USING OBD , PLASTIC EMULSION OIL PAINT...
PREPARE RATE ANALYSIS OF PAINTING WORK USING OBD , PLASTIC EMULSION OIL PAINT...
ssuser217c6f
 
Low cost housing
Low cost housingLow cost housing
Low cost housing
SAI KIRAN
 
1. i Highway Planning.pdf
1. i  Highway Planning.pdf1. i  Highway Planning.pdf
1. i Highway Planning.pdf
Er. Bam Bhandari
 
Mivan Construction Techinique
Mivan Construction TechiniqueMivan Construction Techinique
Mivan Construction Techinique
ASHISH singh
 
Seal coat,prime coat and tack coat
Seal coat,prime coat and tack coatSeal coat,prime coat and tack coat
Seal coat,prime coat and tack coat
MuhammadArif856
 
Highway engineering PPT
Highway engineering PPTHighway engineering PPT
Highway engineering PPT
Kavin Raval
 
Construction of metro station
Construction of metro stationConstruction of metro station
Construction of metro station
Amit Kumar Tiwari
 
Stabilization of Black Cotton Soil with Lime and Geo-grid
Stabilization of Black Cotton Soil with Lime and Geo-gridStabilization of Black Cotton Soil with Lime and Geo-grid
Stabilization of Black Cotton Soil with Lime and Geo-grid
AM Publications
 
Hudco Construction Techniques
Hudco Construction TechniquesHudco Construction Techniques
Hudco Construction TechniquesUday Yadav
 
Automated highway systems
Automated highway systemsAutomated highway systems
Automated highway systems
Aglaia Connect
 
6-Cross Section Elements ( Transportation and Traffic Engineering Dr. Sheriff...
6-Cross Section Elements ( Transportation and Traffic Engineering Dr. Sheriff...6-Cross Section Elements ( Transportation and Traffic Engineering Dr. Sheriff...
6-Cross Section Elements ( Transportation and Traffic Engineering Dr. Sheriff...
Hossam Shafiq I
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
Prasad Manerikar
 
Chapter 13 ( valuation)
Chapter 13 ( valuation)Chapter 13 ( valuation)
Chapter 13 ( valuation)
umes manandhar
 
Railway track construction, drainage & maintenence
Railway track  construction, drainage & maintenenceRailway track  construction, drainage & maintenence
Railway track construction, drainage & maintenence
Ghanashyam Prajapati
 

What's hot (20)

Job Layout
Job LayoutJob Layout
Job Layout
 
LOW COST HOUSING
LOW COST HOUSINGLOW COST HOUSING
LOW COST HOUSING
 
Rate analysis brief
Rate analysis briefRate analysis brief
Rate analysis brief
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Pavement design
Pavement designPavement design
Pavement design
 
PREPARE RATE ANALYSIS OF PAINTING WORK USING OBD , PLASTIC EMULSION OIL PAINT...
PREPARE RATE ANALYSIS OF PAINTING WORK USING OBD , PLASTIC EMULSION OIL PAINT...PREPARE RATE ANALYSIS OF PAINTING WORK USING OBD , PLASTIC EMULSION OIL PAINT...
PREPARE RATE ANALYSIS OF PAINTING WORK USING OBD , PLASTIC EMULSION OIL PAINT...
 
Low cost housing
Low cost housingLow cost housing
Low cost housing
 
1. i Highway Planning.pdf
1. i  Highway Planning.pdf1. i  Highway Planning.pdf
1. i Highway Planning.pdf
 
Mivan Construction Techinique
Mivan Construction TechiniqueMivan Construction Techinique
Mivan Construction Techinique
 
Seal coat,prime coat and tack coat
Seal coat,prime coat and tack coatSeal coat,prime coat and tack coat
Seal coat,prime coat and tack coat
 
Highway engineering PPT
Highway engineering PPTHighway engineering PPT
Highway engineering PPT
 
Construction of metro station
Construction of metro stationConstruction of metro station
Construction of metro station
 
Stabilization of Black Cotton Soil with Lime and Geo-grid
Stabilization of Black Cotton Soil with Lime and Geo-gridStabilization of Black Cotton Soil with Lime and Geo-grid
Stabilization of Black Cotton Soil with Lime and Geo-grid
 
Hudco Construction Techniques
Hudco Construction TechniquesHudco Construction Techniques
Hudco Construction Techniques
 
Automated highway systems
Automated highway systemsAutomated highway systems
Automated highway systems
 
6-Cross Section Elements ( Transportation and Traffic Engineering Dr. Sheriff...
6-Cross Section Elements ( Transportation and Traffic Engineering Dr. Sheriff...6-Cross Section Elements ( Transportation and Traffic Engineering Dr. Sheriff...
6-Cross Section Elements ( Transportation and Traffic Engineering Dr. Sheriff...
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Chapter 13 ( valuation)
Chapter 13 ( valuation)Chapter 13 ( valuation)
Chapter 13 ( valuation)
 
Railway track construction, drainage & maintenence
Railway track  construction, drainage & maintenenceRailway track  construction, drainage & maintenence
Railway track construction, drainage & maintenence
 

Similar to General Estimation & Abstract Sheet of Royal City

IRJET- Critical Chain Project Management in Construction Projects
IRJET- Critical Chain Project Management in Construction ProjectsIRJET- Critical Chain Project Management in Construction Projects
IRJET- Critical Chain Project Management in Construction Projects
IRJET Journal
 
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
IRJET Journal
 
The Study of Measurement of Over-Engineering in Construction Project
The Study of Measurement of Over-Engineering in Construction ProjectThe Study of Measurement of Over-Engineering in Construction Project
The Study of Measurement of Over-Engineering in Construction Project
IRJET Journal
 
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPCOMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
IRJET Journal
 
Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...
IRJET Journal
 
Management For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of DelayManagement For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of Delay
IRJET Journal
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
IRJET Journal
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
lckr117
 
Design and Development of Dynamo Testing Machine
Design and Development of Dynamo Testing MachineDesign and Development of Dynamo Testing Machine
Design and Development of Dynamo Testing Machine
IRJET Journal
 
Manufacturing of Toggle Jack
Manufacturing of Toggle JackManufacturing of Toggle Jack
Manufacturing of Toggle Jack
IRJET Journal
 
IRJET- Optimization of Mechanical Pencil by using Value Engineering
IRJET- Optimization of Mechanical Pencil by using Value EngineeringIRJET- Optimization of Mechanical Pencil by using Value Engineering
IRJET- Optimization of Mechanical Pencil by using Value Engineering
IRJET Journal
 
To develop a statement of work for the designing and fabrication of a solar w...
To develop a statement of work for the designing and fabrication of a solar w...To develop a statement of work for the designing and fabrication of a solar w...
To develop a statement of work for the designing and fabrication of a solar w...
Peachy Essay
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
TauheedKhan45
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
Vijay325
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&t
Nishant Pandey
 
IRJET- Value Analysis of Inward Curve Basin for a GVHT
IRJET-  	  Value Analysis of Inward Curve Basin for a GVHTIRJET-  	  Value Analysis of Inward Curve Basin for a GVHT
IRJET- Value Analysis of Inward Curve Basin for a GVHT
IRJET Journal
 
Impact of delayness on construction projects
Impact of delayness on construction projectsImpact of delayness on construction projects
Impact of delayness on construction projects
IRJET Journal
 
Building a comissioning guideline
Building a comissioning guidelineBuilding a comissioning guideline
Building a comissioning guideline
Zuzi Evangelista
 
IRJET- Course outcome Attainment Estimation System
IRJET-  	  Course outcome Attainment Estimation SystemIRJET-  	  Course outcome Attainment Estimation System
IRJET- Course outcome Attainment Estimation System
IRJET Journal
 
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET Journal
 

Similar to General Estimation & Abstract Sheet of Royal City (20)

IRJET- Critical Chain Project Management in Construction Projects
IRJET- Critical Chain Project Management in Construction ProjectsIRJET- Critical Chain Project Management in Construction Projects
IRJET- Critical Chain Project Management in Construction Projects
 
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
 
The Study of Measurement of Over-Engineering in Construction Project
The Study of Measurement of Over-Engineering in Construction ProjectThe Study of Measurement of Over-Engineering in Construction Project
The Study of Measurement of Over-Engineering in Construction Project
 
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPCOMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
 
Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...
 
Management For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of DelayManagement For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of Delay
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
Design and Development of Dynamo Testing Machine
Design and Development of Dynamo Testing MachineDesign and Development of Dynamo Testing Machine
Design and Development of Dynamo Testing Machine
 
Manufacturing of Toggle Jack
Manufacturing of Toggle JackManufacturing of Toggle Jack
Manufacturing of Toggle Jack
 
IRJET- Optimization of Mechanical Pencil by using Value Engineering
IRJET- Optimization of Mechanical Pencil by using Value EngineeringIRJET- Optimization of Mechanical Pencil by using Value Engineering
IRJET- Optimization of Mechanical Pencil by using Value Engineering
 
To develop a statement of work for the designing and fabrication of a solar w...
To develop a statement of work for the designing and fabrication of a solar w...To develop a statement of work for the designing and fabrication of a solar w...
To develop a statement of work for the designing and fabrication of a solar w...
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&t
 
IRJET- Value Analysis of Inward Curve Basin for a GVHT
IRJET-  	  Value Analysis of Inward Curve Basin for a GVHTIRJET-  	  Value Analysis of Inward Curve Basin for a GVHT
IRJET- Value Analysis of Inward Curve Basin for a GVHT
 
Impact of delayness on construction projects
Impact of delayness on construction projectsImpact of delayness on construction projects
Impact of delayness on construction projects
 
Building a comissioning guideline
Building a comissioning guidelineBuilding a comissioning guideline
Building a comissioning guideline
 
IRJET- Course outcome Attainment Estimation System
IRJET-  	  Course outcome Attainment Estimation SystemIRJET-  	  Course outcome Attainment Estimation System
IRJET- Course outcome Attainment Estimation System
 
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
IRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
IRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
IRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
IRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
IRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
IRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
IRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 

Recently uploaded (20)

TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 

General Estimation & Abstract Sheet of Royal City

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 03 | Mar -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 816 General Estimation & Abstract Sheet of Royal City Shaikh Ajim1, Raut Vishwajit2, Shah Tajmmul3, Pawar Ganesh4, Pathan Alim5, Shejwal Yogesh6 1Guide. Department Of Civil Engineering, Ashok Polytechnic, Maharashtra, India 2,3,4,5,6Student. Department Of Civil Engineering, Ashok Polytechnic, Maharashtra, India ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract – The estimating and costing means technique of the calculating the various quantities of executed work and then determining their cost known as costing The costing is mainly done by abstract sheet which is seen as follows Also it is use to determine the cost and labors for the work and in this rates of DSR is use the rates given in the DSR arerevised every year, also the rates given in DSR includes 10% contractor’s profit (Key words : estimating, costing, cost, abstract sheet, labors, 10% contractor’s profit) 1. INTRODUCTION This project is under guidance of prof. shaikh A. S of General estimation of the city which has name as royal city, in which includes hospital (G+1), hostel (G), school (G+2), collage (G+2), 3bhk rowhouses,3bhk apartments,1bhk apartmentsandmall. And also abstract sheet is done after calculating the quantities of each building 2. APPROXIMATE ESTIMATE Approximate estimate means the preliminary estimate , because it is also use full forgettingadministrativeapproval .alsofor it site plans and layout plans are required Purposes of approximate estimate 1. It gives rough idea about the cost which is required for the project or work which will be executed 2. Easy to check feasibility of project 3. It is also helpful to administrative approval and technical sanction Comes here Conclusion content comes here Conclusion content comes here Conclusion content comes here 4. sample calculations Measurement sheet SR.NO DESCRIPTION NOS LENGTH BREADH HEIGTH QUANTITY 1. EXCAVATION Excavation in soft murum in foundation with lead & lift etc. complete. 17 1.2 1.2 1.5 17.13 2. PCC Pcc bed below the foundation in proportion with providing & laying , compacting , curing etc. complete. 17 1.2 1.2 0.2 4.89
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 03 | Mar -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 817 Abstract sheet S.NO DESCRIPTION SPECIFICATION UNIT QUN TITY COMPLETED RATE PER UNIT AMOUNT LABO UR RATE PER UNIT AMOUN T 1 EXCAVATION- Excavation For Foundation In Earth ,soil of all types ,sand,gravel,and soft murum including removing the excavated material up to a distance of 50 m Beyond the building area and stacking and spreading as directed ,dewatering preparing the bed for the foundation and necessary back filling ramming, watering including shoring and strutting etc. complete .with lift up to 1.50 m a.hard murum lift up to 1.50 m Spec.no.Bd.A.2 Page no.259 Cubic meter 36.7 2 118 4332.96 118 4332.96 2 PCC- Providing and laying in situ,cement concrete M- 15/1:2:4 of trap/granite/quartzite/g neiss metal for foundation and bedding including bailing-out water manually formwork, compacting covering newly laid concrete by gunny bag, plastic tarpaulin curing etc. complete Spec.no.Bd E.1 Page no.287/is- 456-2000 Cubic meter 4.89 3823 18694.47 380 1858.2
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 03 | Mar -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 818 there are various of approximate estimating and costing like 1. plinth area method 2. cubical content method 3. service unit method 4. typical bay method 5. approximate quantity method and also methods to calculating quantities are 1. PWD(Long wall Short wall)method 2. Centerline method 1. PWD(Long wall Short wall)method : in this method the longer wall in the building are consider as long wall .this wall are measured from out to out . the shorter wall are perpendicular to the long wall are measured from in to in of length long walls are considered as short wall Length of long wall = center to center length of long wall + width ofitem Length of long wall = center to center length of long wall - width ofitem Fig. No 1:Plan of royal city, Shrirampur Centerline method:  Draw centerline plan  Calculate total length of center line  Calculate no of T junction  Take no of junction for walls meeting for three directions =1  No of junction for walls meeting from 4directions = 2  Calculate length of item as L=total c/c length – (1/2) x no of junction x width of item
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 04 Issue: 03 | Mar -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 819 Hence total completed rate = 23027.43 Total labour rate = 6191.16 Total amount for this item = labour rate+ completed rate Total amount for this item = 29218.59 Like this Building name Amount for built with contractor’s profit 1compartment of 3BHK 5545345 /- compartment of 1BHK 5045565 /- Hospital 565765 /- School 7245435 /- Collage 177342 /- 1 row house 312053.7 /- Hostel 1022343 /- mall 55454342 /- 5. CONCLUSION Due to this we can publish also tender notices and also an importance of this project is that it is helpful to fixation to tax, also for the valuation it is very important Du to this also we can know the cost of our construction to do financial arrangements and the arrangements of labors and materials for project 6. ACKNOWLEDGEMENT It has been a privilege for me to be associated with Prof.shaikh.A.S my guide during this dissertation work. I have been greatly benefited by their valuable suggestions and ideas Finally, I would like to express my deep, incomparable appreciation and gratitude to my family members for their constant spiritual support and encouragement to pursue the higher technical education. REFERENCES 1. Estimating And Costing, Author :Kavita L. Bavdekar 2. BUILDING BY LOWS BY govt.of india 3. Www. Estimating And Costing. Wikipedia the free encyclopedia .in 4. District schedule rate of Nasik division(by PWD) BIOGRAPHIES Shaikh Ajim Guide. Department Of Civil Engineering, Ashok Polytechnic, Maharashtra, India Raut Vishwajit Student. Department Of Civil Engineering, Ashok Polytechnic, Maharashtra, India Shah Tajmmul Student. Department Of Civil Engineering, Ashok Polytechnic, Maharashtra, India Pawar Ganesh Student. Department Of Civil Engineering, Ashok Polytechnic, Maharashtra, India Pathan Alim Student. Department Of Civil Engineering, Ashok Polytechnic, Maharashtra, India Shejwal Yogesh Student. Department Of Civil Engineering, Ashok Polytechnic, Maharashtra, India