SlideShare a Scribd company logo
Proposal: Solar Grant Final  Project: MSE 567 & 467 Huidong Jonathan Mary Sabina Younes
Outline 1. Site Selection 2. Load Profile 3. System Availability 4. Photovoltaic Array Sizing 5. Battery Sizing 6. Power Conditioning Unit ( inverters, fuses, wiring,….) 7. Cost Breakdown
Heavily forested area at Tanzania Typical village house Village People
Economic consideration in site selection: Cost of site preparation Cost of access to the site
The Project Provide PV power at -3.61, 37.37 for 10 yrs 100 small homes ~60ftx60ft 20° slopes Surrounded by 75ft trees 3 month rainy season (spring: Aug – Oct) Random twice a week sun Remainder of year is sunny
Parts/Labor Reliability PV 40 yrs Power electronics 5 yrs Batteries 3 yrs Cleaning every 3 months Cost - $/h $5 for laborer $10 for electrical installer $30 for engineer/system designer 5 ton truck $2/mile
Mombasa Port
Route From Moshi
 Cleaned Road
Work Load Lights 25W*10lamps*12h/day = 3kWh/day Refrigerator 700kWh/yr*yr/365days = 1.91781kWh/day Television 125W*5h/day + 15W*19h/day = 0.91kWh/day Air Conditioner 750W*24h/day = 18kWh/day Computer 200W*5h/day + 10W*19h/day = 1.19kWh/day Washing Machine 0.25kWh/wk*wk/7days = 0.03572kWh/day Total = 25.05353kWh/day/house
Components Panels China, GOD company, mono-crystalline 180W, 16% efficiency, 36 Vpm, 1580*808*35 (mm), $283 Batteries Shenzhen Haonaite Power Co, 12V*200AH, 522*238*218 (mm), $168 Inverter/Charge controller Shanghai Jinxian Solar Tech Co, 220V 50Hz 3kW, 1*1*2 (m), $1,757 Wire Shanghai Yingqiang Electronic Co, TIN PLATED COPPER WIRE, $0.805/m
Array Sizing
Average PV System Component Efficiencies PV array                                                   80-85% Inverter                                                     80-90% Wire                                                          97-98% Disconnects, fuses98-99% Total grid-tied PV system efficiency	60-75% New batteries (roundtrip efficiency)	65-75% Total off-grid PV system efficiency (AC)	40-56%
Array/Battery Sizing 25.05353kWh/(4.55*0.18*0.4) = 76.476 77 Panels 77 panels insufficient to recharge battery bank Increased to 78 1653.53kWh/(200Ah*12V*0.8*0.001) = 861.214 batteries Used 862
Array/Battery Sizing
Facility Layout
Battery Storage
Cost Panels – $2,210,230 7,800 panels Controller/Inverter – $358,428 204units Batteries – $14,481,600 86,200 batteries (worst case/times # by 3) Wire – $4025 5000m Site Clearance – $25,000 (minus lumber sales) Battery storage – $60,000 Hole & Material
Cost Shipping Truck – $516,600 1300 trips/2$ per mile/ 216 miles Ship – $51,460 $630 per container/ 80containers Installation Laborers – $24,480 Engineer – $58,320 Training Labor – $10,800 Engineer – $7,200 Cleaning – $146,000 Total – $17,954,143
Younes Sina

More Related Content

What's hot

Presentation on a grid connected Solar PV system
Presentation on a grid connected Solar PV systemPresentation on a grid connected Solar PV system
Presentation on a grid connected Solar PV system
ashmomio
 
Design Aspect of Standalone PV system
Design Aspect of Standalone PV systemDesign Aspect of Standalone PV system
Design Aspect of Standalone PV system
Malik Sameeullah
 
Pv Solar Grid Connect Solar Design
Pv Solar Grid Connect Solar DesignPv Solar Grid Connect Solar Design
Pv Solar Grid Connect Solar Design
Optimus Energy Philippines
 
SYKES TIMBER CASE STUDY
SYKES TIMBER CASE STUDYSYKES TIMBER CASE STUDY
Renewable energy course#03
Renewable energy course#03Renewable energy course#03
Renewable energy course#03
Syed_Sajjad_Raza
 
A Report on solar power plant installation
A Report on solar power plant installationA Report on solar power plant installation
A Report on solar power plant installation
Amitesh Kumar
 
PV Project MENA (2)
PV Project MENA (2)PV Project MENA (2)
PV Project MENA (2)
Hamid Nawaz
 
Grid connected rooftop solar power plant at silicon
Grid connected rooftop solar power plant at siliconGrid connected rooftop solar power plant at silicon
Grid connected rooftop solar power plant at silicon
Navneet Das
 
Yunasko cologne 6_oct2016_fin
Yunasko cologne 6_oct2016_finYunasko cologne 6_oct2016_fin
Yunasko cologne 6_oct2016_fin
Yunasko
 
Design and performance analysis of 500 KWp on-grid solar PV system
Design and performance analysis of 500 KWp on-grid solar PV systemDesign and performance analysis of 500 KWp on-grid solar PV system
Design and performance analysis of 500 KWp on-grid solar PV system
AmroSadulQuddus
 
Yunasko expo2017 astana
Yunasko expo2017 astanaYunasko expo2017 astana
Yunasko expo2017 astana
Yunasko
 
Solar power plant catalogue
Solar power plant  catalogueSolar power plant  catalogue
Solar power plant catalogue
KONDAASAutomation
 
Study of grid connected pv system based on current source inverter
Study of grid connected pv system based on current source inverterStudy of grid connected pv system based on current source inverter
Study of grid connected pv system based on current source inverter
IAEME Publication
 
Photovoltaics Case Study
Photovoltaics Case StudyPhotovoltaics Case Study
Photovoltaics Case Study
Leonardo ENERGY
 
Powerpoint
PowerpointPowerpoint
Powerpoint
temosa10
 
mohan.final
mohan.finalmohan.final
On-Site Renewables in a Post-Subsidy Landscape
On-Site Renewables in a Post-Subsidy LandscapeOn-Site Renewables in a Post-Subsidy Landscape
On-Site Renewables in a Post-Subsidy Landscape
EMEX
 
Bulk Solar Power Generation :CSP and CPV technologies
Bulk Solar Power Generation :CSP and CPV technologiesBulk Solar Power Generation :CSP and CPV technologies
Bulk Solar Power Generation :CSP and CPV technologies
Leonardo ENERGY
 
Kiet pv presentation
Kiet pv presentationKiet pv presentation
Kiet pv presentation
capricorn_ktl
 
Electricity measi correction
Electricity measi correctionElectricity measi correction
Electricity measi correction
consumeractiongroup
 

What's hot (20)

Presentation on a grid connected Solar PV system
Presentation on a grid connected Solar PV systemPresentation on a grid connected Solar PV system
Presentation on a grid connected Solar PV system
 
Design Aspect of Standalone PV system
Design Aspect of Standalone PV systemDesign Aspect of Standalone PV system
Design Aspect of Standalone PV system
 
Pv Solar Grid Connect Solar Design
Pv Solar Grid Connect Solar DesignPv Solar Grid Connect Solar Design
Pv Solar Grid Connect Solar Design
 
SYKES TIMBER CASE STUDY
SYKES TIMBER CASE STUDYSYKES TIMBER CASE STUDY
SYKES TIMBER CASE STUDY
 
Renewable energy course#03
Renewable energy course#03Renewable energy course#03
Renewable energy course#03
 
A Report on solar power plant installation
A Report on solar power plant installationA Report on solar power plant installation
A Report on solar power plant installation
 
PV Project MENA (2)
PV Project MENA (2)PV Project MENA (2)
PV Project MENA (2)
 
Grid connected rooftop solar power plant at silicon
Grid connected rooftop solar power plant at siliconGrid connected rooftop solar power plant at silicon
Grid connected rooftop solar power plant at silicon
 
Yunasko cologne 6_oct2016_fin
Yunasko cologne 6_oct2016_finYunasko cologne 6_oct2016_fin
Yunasko cologne 6_oct2016_fin
 
Design and performance analysis of 500 KWp on-grid solar PV system
Design and performance analysis of 500 KWp on-grid solar PV systemDesign and performance analysis of 500 KWp on-grid solar PV system
Design and performance analysis of 500 KWp on-grid solar PV system
 
Yunasko expo2017 astana
Yunasko expo2017 astanaYunasko expo2017 astana
Yunasko expo2017 astana
 
Solar power plant catalogue
Solar power plant  catalogueSolar power plant  catalogue
Solar power plant catalogue
 
Study of grid connected pv system based on current source inverter
Study of grid connected pv system based on current source inverterStudy of grid connected pv system based on current source inverter
Study of grid connected pv system based on current source inverter
 
Photovoltaics Case Study
Photovoltaics Case StudyPhotovoltaics Case Study
Photovoltaics Case Study
 
Powerpoint
PowerpointPowerpoint
Powerpoint
 
mohan.final
mohan.finalmohan.final
mohan.final
 
On-Site Renewables in a Post-Subsidy Landscape
On-Site Renewables in a Post-Subsidy LandscapeOn-Site Renewables in a Post-Subsidy Landscape
On-Site Renewables in a Post-Subsidy Landscape
 
Bulk Solar Power Generation :CSP and CPV technologies
Bulk Solar Power Generation :CSP and CPV technologiesBulk Solar Power Generation :CSP and CPV technologies
Bulk Solar Power Generation :CSP and CPV technologies
 
Kiet pv presentation
Kiet pv presentationKiet pv presentation
Kiet pv presentation
 
Electricity measi correction
Electricity measi correctionElectricity measi correction
Electricity measi correction
 

Viewers also liked

Proposals
ProposalsProposals
Proposals
Somi Kashif
 
AdaptiveCluster_proposal_CityLabfall11_FINAL[1]
AdaptiveCluster_proposal_CityLabfall11_FINAL[1]AdaptiveCluster_proposal_CityLabfall11_FINAL[1]
AdaptiveCluster_proposal_CityLabfall11_FINAL[1]
John Kostak
 
Grant Proposal Final
Grant Proposal FinalGrant Proposal Final
Grant Proposal Final
Devon Rhodes
 
Final
FinalFinal
Final Grant & Proposal (1)
Final Grant & Proposal (1)Final Grant & Proposal (1)
Final Grant & Proposal (1)
Emma Herschman
 
Research Grant Proposal Final version
Research Grant Proposal Final versionResearch Grant Proposal Final version
Research Grant Proposal Final version
Jordan Lubbers
 
Final Grant Proposal
Final Grant ProposalFinal Grant Proposal
Final Grant Proposal
Samantha Petersen
 
Volunteer with Ignite Adaptive Sports!
Volunteer with Ignite Adaptive Sports!Volunteer with Ignite Adaptive Sports!
Volunteer with Ignite Adaptive Sports!
Orri Jonsson
 
Grant Presentation
Grant PresentationGrant Presentation
Grant Presentation
Alyssa Seipel
 
Grant proposal
Grant proposalGrant proposal
Grant proposal
Fran McKain
 
Hawaii homeless shelter RFP 2017 award listing
Hawaii homeless shelter RFP 2017 award listingHawaii homeless shelter RFP 2017 award listing
Hawaii homeless shelter RFP 2017 award listing
Honolulu Civil Beat
 
Grant proposal final
Grant proposal final Grant proposal final
Grant proposal final
Sarah Barnett
 
Pepsi RefreshEverything Multitouch Grant Proposal
Pepsi RefreshEverything Multitouch Grant ProposalPepsi RefreshEverything Multitouch Grant Proposal
Pepsi RefreshEverything Multitouch Grant Proposal
prosper50
 
Ora1120 Budget and Proposal Prep Mod1
Ora1120 Budget and Proposal Prep Mod1Ora1120 Budget and Proposal Prep Mod1
Ora1120 Budget and Proposal Prep Mod1
chris shaw
 
Community Foundation Grant Proposal Final Draft
Community Foundation Grant Proposal Final DraftCommunity Foundation Grant Proposal Final Draft
Community Foundation Grant Proposal Final Draft
molliefoust
 
Writing the Budget for a Grant Proposal
Writing the Budget for a Grant ProposalWriting the Budget for a Grant Proposal
Writing the Budget for a Grant Proposal
Dierdre McKee
 
Logic Models For Grant Writing
Logic Models For Grant WritingLogic Models For Grant Writing
Logic Models For Grant Writing
Dierdre McKee
 
Summer camp proposal
Summer camp proposalSummer camp proposal

Viewers also liked (18)

Proposals
ProposalsProposals
Proposals
 
AdaptiveCluster_proposal_CityLabfall11_FINAL[1]
AdaptiveCluster_proposal_CityLabfall11_FINAL[1]AdaptiveCluster_proposal_CityLabfall11_FINAL[1]
AdaptiveCluster_proposal_CityLabfall11_FINAL[1]
 
Grant Proposal Final
Grant Proposal FinalGrant Proposal Final
Grant Proposal Final
 
Final
FinalFinal
Final
 
Final Grant & Proposal (1)
Final Grant & Proposal (1)Final Grant & Proposal (1)
Final Grant & Proposal (1)
 
Research Grant Proposal Final version
Research Grant Proposal Final versionResearch Grant Proposal Final version
Research Grant Proposal Final version
 
Final Grant Proposal
Final Grant ProposalFinal Grant Proposal
Final Grant Proposal
 
Volunteer with Ignite Adaptive Sports!
Volunteer with Ignite Adaptive Sports!Volunteer with Ignite Adaptive Sports!
Volunteer with Ignite Adaptive Sports!
 
Grant Presentation
Grant PresentationGrant Presentation
Grant Presentation
 
Grant proposal
Grant proposalGrant proposal
Grant proposal
 
Hawaii homeless shelter RFP 2017 award listing
Hawaii homeless shelter RFP 2017 award listingHawaii homeless shelter RFP 2017 award listing
Hawaii homeless shelter RFP 2017 award listing
 
Grant proposal final
Grant proposal final Grant proposal final
Grant proposal final
 
Pepsi RefreshEverything Multitouch Grant Proposal
Pepsi RefreshEverything Multitouch Grant ProposalPepsi RefreshEverything Multitouch Grant Proposal
Pepsi RefreshEverything Multitouch Grant Proposal
 
Ora1120 Budget and Proposal Prep Mod1
Ora1120 Budget and Proposal Prep Mod1Ora1120 Budget and Proposal Prep Mod1
Ora1120 Budget and Proposal Prep Mod1
 
Community Foundation Grant Proposal Final Draft
Community Foundation Grant Proposal Final DraftCommunity Foundation Grant Proposal Final Draft
Community Foundation Grant Proposal Final Draft
 
Writing the Budget for a Grant Proposal
Writing the Budget for a Grant ProposalWriting the Budget for a Grant Proposal
Writing the Budget for a Grant Proposal
 
Logic Models For Grant Writing
Logic Models For Grant WritingLogic Models For Grant Writing
Logic Models For Grant Writing
 
Summer camp proposal
Summer camp proposalSummer camp proposal
Summer camp proposal
 

Similar to Younes Sina

Design and Development of 5MW Solar PV Grid Connected Power Plant using PVsyst
Design and Development of 5MW Solar PV Grid Connected Power Plant using PVsystDesign and Development of 5MW Solar PV Grid Connected Power Plant using PVsyst
Design and Development of 5MW Solar PV Grid Connected Power Plant using PVsyst
IRJET Journal
 
Solar PPt.pptx
Solar PPt.pptxSolar PPt.pptx
Solar PPt.pptx
MissSeptember1
 
5.5 off main-grid technologies for power generation in rural contexts
5.5 off main-grid technologies for power generation in rural contexts5.5 off main-grid technologies for power generation in rural contexts
5.5 off main-grid technologies for power generation in rural contexts
LeNS_slide
 
Solar Training 20100208
Solar Training 20100208Solar Training 20100208
Solar Training 20100208
Syed Khurram Iqbal
 
Proposal for a 2MW fspv system and e-transport
Proposal for a 2MW fspv system and e-transportProposal for a 2MW fspv system and e-transport
Proposal for a 2MW fspv system and e-transport
Ankit Singh
 
Solar integrated EV bus
Solar integrated EV busSolar integrated EV bus
Solar integrated EV bus
Prabhakar Prabhu
 
EE494_SENIOR_DESIGN_PRESENTATION_2015_V3
EE494_SENIOR_DESIGN_PRESENTATION_2015_V3EE494_SENIOR_DESIGN_PRESENTATION_2015_V3
EE494_SENIOR_DESIGN_PRESENTATION_2015_V3
Jürgen Andrés Sawatzki Chaw
 
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWPIRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET Journal
 
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWPIRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET Journal
 
Solar Energy Generation Potential on National Highways
Solar Energy Generation Potential on National HighwaysSolar Energy Generation Potential on National Highways
Solar Energy Generation Potential on National Highways
IRJET Journal
 
Off Grid PV System
Off Grid PV SystemOff Grid PV System
Off Grid PV System
Dilawez Alam
 
PROPOSAL
PROPOSALPROPOSAL
1 KW Solar Photovoltaic System
1 KW Solar Photovoltaic System1 KW Solar Photovoltaic System
1 KW Solar Photovoltaic System
Manthan Thakkar
 
5 .Solar Energy and Battery--_--_+_+_-_--_+_+_+_+
5 .Solar Energy and Battery--_--_+_+_-_--_+_+_+_+5 .Solar Energy and Battery--_--_+_+_-_--_+_+_+_+
5 .Solar Energy and Battery--_--_+_+_-_--_+_+_+_+
sidhantkumarpdt
 
Alternative Energy: The time is Nigh
Alternative Energy: The time is NighAlternative Energy: The time is Nigh
Alternative Energy: The time is Nigh
TiE Bangalore
 
Solar Barge
Solar BargeSolar Barge
Solar Barge
lgthucabee
 
12522494 (1).ppt
12522494 (1).ppt12522494 (1).ppt
12522494 (1).ppt
SourabhNagwanshi3
 
Solar Installation and Design: Dos and Don'ts
Solar Installation and Design: Dos and Don'tsSolar Installation and Design: Dos and Don'ts
Solar Installation and Design: Dos and Don'ts
Dr. Tajudeen Humble Sikiru
 
Renewable energy considerations for the Bahamas
Renewable energy considerations for the BahamasRenewable energy considerations for the Bahamas
Renewable energy considerations for the Bahamas
Charvari Watson
 
Ugsolar太阳能
Ugsolar太阳能Ugsolar太阳能
Ugsolar太阳能
Dr. Tan Boon Siong
 

Similar to Younes Sina (20)

Design and Development of 5MW Solar PV Grid Connected Power Plant using PVsyst
Design and Development of 5MW Solar PV Grid Connected Power Plant using PVsystDesign and Development of 5MW Solar PV Grid Connected Power Plant using PVsyst
Design and Development of 5MW Solar PV Grid Connected Power Plant using PVsyst
 
Solar PPt.pptx
Solar PPt.pptxSolar PPt.pptx
Solar PPt.pptx
 
5.5 off main-grid technologies for power generation in rural contexts
5.5 off main-grid technologies for power generation in rural contexts5.5 off main-grid technologies for power generation in rural contexts
5.5 off main-grid technologies for power generation in rural contexts
 
Solar Training 20100208
Solar Training 20100208Solar Training 20100208
Solar Training 20100208
 
Proposal for a 2MW fspv system and e-transport
Proposal for a 2MW fspv system and e-transportProposal for a 2MW fspv system and e-transport
Proposal for a 2MW fspv system and e-transport
 
Solar integrated EV bus
Solar integrated EV busSolar integrated EV bus
Solar integrated EV bus
 
EE494_SENIOR_DESIGN_PRESENTATION_2015_V3
EE494_SENIOR_DESIGN_PRESENTATION_2015_V3EE494_SENIOR_DESIGN_PRESENTATION_2015_V3
EE494_SENIOR_DESIGN_PRESENTATION_2015_V3
 
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWPIRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
 
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWPIRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
 
Solar Energy Generation Potential on National Highways
Solar Energy Generation Potential on National HighwaysSolar Energy Generation Potential on National Highways
Solar Energy Generation Potential on National Highways
 
Off Grid PV System
Off Grid PV SystemOff Grid PV System
Off Grid PV System
 
PROPOSAL
PROPOSALPROPOSAL
PROPOSAL
 
1 KW Solar Photovoltaic System
1 KW Solar Photovoltaic System1 KW Solar Photovoltaic System
1 KW Solar Photovoltaic System
 
5 .Solar Energy and Battery--_--_+_+_-_--_+_+_+_+
5 .Solar Energy and Battery--_--_+_+_-_--_+_+_+_+5 .Solar Energy and Battery--_--_+_+_-_--_+_+_+_+
5 .Solar Energy and Battery--_--_+_+_-_--_+_+_+_+
 
Alternative Energy: The time is Nigh
Alternative Energy: The time is NighAlternative Energy: The time is Nigh
Alternative Energy: The time is Nigh
 
Solar Barge
Solar BargeSolar Barge
Solar Barge
 
12522494 (1).ppt
12522494 (1).ppt12522494 (1).ppt
12522494 (1).ppt
 
Solar Installation and Design: Dos and Don'ts
Solar Installation and Design: Dos and Don'tsSolar Installation and Design: Dos and Don'ts
Solar Installation and Design: Dos and Don'ts
 
Renewable energy considerations for the Bahamas
Renewable energy considerations for the BahamasRenewable energy considerations for the Bahamas
Renewable energy considerations for the Bahamas
 
Ugsolar太阳能
Ugsolar太阳能Ugsolar太阳能
Ugsolar太阳能
 

More from Younes Sina

Physics by Younes Sina
Physics by Younes SinaPhysics by Younes Sina
Physics by Younes Sina
Younes Sina
 
Chapter 14
Chapter 14Chapter 14
Chapter 14
Younes Sina
 
Chapter 12
Chapter 12Chapter 12
Chapter 12
Younes Sina
 
Chapter 11
Chapter 11Chapter 11
Chapter 11
Younes Sina
 
Chapter 10
Chapter 10Chapter 10
Chapter 10
Younes Sina
 
Chapter 9
Chapter 9Chapter 9
Chapter 9
Younes Sina
 
Chapter 8
Chapter 8Chapter 8
Chapter 8
Younes Sina
 
Chapter 7
Chapter 7Chapter 7
Chapter 7
Younes Sina
 
Chapter 6
Chapter 6Chapter 6
Chapter 6
Younes Sina
 
Chapter 5
Chapter 5Chapter 5
Chapter 5
Younes Sina
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
Younes Sina
 
Chapter 3
Chapter 3Chapter 3
Chapter 3
Younes Sina
 
Chapter 2
Chapter 2Chapter 2
Chapter 2
Younes Sina
 
Chapter 1
Chapter 1Chapter 1
Chapter 1
Younes Sina
 
ICDIM 2012 presentation
ICDIM 2012 presentationICDIM 2012 presentation
ICDIM 2012 presentation
Younes Sina
 
Phase Diagram, ZrO2 and Al2O3 System
Phase Diagram, ZrO2 and Al2O3 SystemPhase Diagram, ZrO2 and Al2O3 System
Phase Diagram, ZrO2 and Al2O3 System
Younes Sina
 
Electron irradiation effect on Al2O3
Electron irradiation effect on Al2O3Electron irradiation effect on Al2O3
Electron irradiation effect on Al2O3
Younes Sina
 
Line Spectra (Rydberg’s Constant)
Line Spectra (Rydberg’s Constant)Line Spectra (Rydberg’s Constant)
Line Spectra (Rydberg’s Constant)
Younes Sina
 
توسعه روش شكست سنجي براي تعيين درصد
توسعه روش شكست سنجي براي تعيين درصدتوسعه روش شكست سنجي براي تعيين درصد
توسعه روش شكست سنجي براي تعيين درصدYounes Sina
 
Nuclear Radiation, the chart of nuclides
Nuclear Radiation, the chart of nuclidesNuclear Radiation, the chart of nuclides
Nuclear Radiation, the chart of nuclides
Younes Sina
 

More from Younes Sina (20)

Physics by Younes Sina
Physics by Younes SinaPhysics by Younes Sina
Physics by Younes Sina
 
Chapter 14
Chapter 14Chapter 14
Chapter 14
 
Chapter 12
Chapter 12Chapter 12
Chapter 12
 
Chapter 11
Chapter 11Chapter 11
Chapter 11
 
Chapter 10
Chapter 10Chapter 10
Chapter 10
 
Chapter 9
Chapter 9Chapter 9
Chapter 9
 
Chapter 8
Chapter 8Chapter 8
Chapter 8
 
Chapter 7
Chapter 7Chapter 7
Chapter 7
 
Chapter 6
Chapter 6Chapter 6
Chapter 6
 
Chapter 5
Chapter 5Chapter 5
Chapter 5
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
Chapter 3
Chapter 3Chapter 3
Chapter 3
 
Chapter 2
Chapter 2Chapter 2
Chapter 2
 
Chapter 1
Chapter 1Chapter 1
Chapter 1
 
ICDIM 2012 presentation
ICDIM 2012 presentationICDIM 2012 presentation
ICDIM 2012 presentation
 
Phase Diagram, ZrO2 and Al2O3 System
Phase Diagram, ZrO2 and Al2O3 SystemPhase Diagram, ZrO2 and Al2O3 System
Phase Diagram, ZrO2 and Al2O3 System
 
Electron irradiation effect on Al2O3
Electron irradiation effect on Al2O3Electron irradiation effect on Al2O3
Electron irradiation effect on Al2O3
 
Line Spectra (Rydberg’s Constant)
Line Spectra (Rydberg’s Constant)Line Spectra (Rydberg’s Constant)
Line Spectra (Rydberg’s Constant)
 
توسعه روش شكست سنجي براي تعيين درصد
توسعه روش شكست سنجي براي تعيين درصدتوسعه روش شكست سنجي براي تعيين درصد
توسعه روش شكست سنجي براي تعيين درصد
 
Nuclear Radiation, the chart of nuclides
Nuclear Radiation, the chart of nuclidesNuclear Radiation, the chart of nuclides
Nuclear Radiation, the chart of nuclides
 

Recently uploaded

Video Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the FutureVideo Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the Future
Alpen-Adria-Universität
 
How to use Firebase Data Connect For Flutter
How to use Firebase Data Connect For FlutterHow to use Firebase Data Connect For Flutter
How to use Firebase Data Connect For Flutter
Daiki Mogmet Ito
 
Generating privacy-protected synthetic data using Secludy and Milvus
Generating privacy-protected synthetic data using Secludy and MilvusGenerating privacy-protected synthetic data using Secludy and Milvus
Generating privacy-protected synthetic data using Secludy and Milvus
Zilliz
 
HCL Notes and Domino License Cost Reduction in the World of DLAU
HCL Notes and Domino License Cost Reduction in the World of DLAUHCL Notes and Domino License Cost Reduction in the World of DLAU
HCL Notes and Domino License Cost Reduction in the World of DLAU
panagenda
 
Taking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdfTaking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdf
ssuserfac0301
 
Ocean lotus Threat actors project by John Sitima 2024 (1).pptx
Ocean lotus Threat actors project by John Sitima 2024 (1).pptxOcean lotus Threat actors project by John Sitima 2024 (1).pptx
Ocean lotus Threat actors project by John Sitima 2024 (1).pptx
SitimaJohn
 
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
名前 です男
 
Driving Business Innovation: Latest Generative AI Advancements & Success Story
Driving Business Innovation: Latest Generative AI Advancements & Success StoryDriving Business Innovation: Latest Generative AI Advancements & Success Story
Driving Business Innovation: Latest Generative AI Advancements & Success Story
Safe Software
 
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAUHCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
panagenda
 
Presentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of GermanyPresentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of Germany
innovationoecd
 
Artificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopmentArtificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopment
Octavian Nadolu
 
Building Production Ready Search Pipelines with Spark and Milvus
Building Production Ready Search Pipelines with Spark and MilvusBuilding Production Ready Search Pipelines with Spark and Milvus
Building Production Ready Search Pipelines with Spark and Milvus
Zilliz
 
Microsoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdfMicrosoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdf
Uni Systems S.M.S.A.
 
UI5 Controls simplified - UI5con2024 presentation
UI5 Controls simplified - UI5con2024 presentationUI5 Controls simplified - UI5con2024 presentation
UI5 Controls simplified - UI5con2024 presentation
Wouter Lemaire
 
How to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptxHow to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptx
danishmna97
 
June Patch Tuesday
June Patch TuesdayJune Patch Tuesday
June Patch Tuesday
Ivanti
 
CAKE: Sharing Slices of Confidential Data on Blockchain
CAKE: Sharing Slices of Confidential Data on BlockchainCAKE: Sharing Slices of Confidential Data on Blockchain
CAKE: Sharing Slices of Confidential Data on Blockchain
Claudio Di Ciccio
 
20240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 202420240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 2024
Matthew Sinclair
 
Infrastructure Challenges in Scaling RAG with Custom AI models
Infrastructure Challenges in Scaling RAG with Custom AI modelsInfrastructure Challenges in Scaling RAG with Custom AI models
Infrastructure Challenges in Scaling RAG with Custom AI models
Zilliz
 
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdfUnlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Malak Abu Hammad
 

Recently uploaded (20)

Video Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the FutureVideo Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the Future
 
How to use Firebase Data Connect For Flutter
How to use Firebase Data Connect For FlutterHow to use Firebase Data Connect For Flutter
How to use Firebase Data Connect For Flutter
 
Generating privacy-protected synthetic data using Secludy and Milvus
Generating privacy-protected synthetic data using Secludy and MilvusGenerating privacy-protected synthetic data using Secludy and Milvus
Generating privacy-protected synthetic data using Secludy and Milvus
 
HCL Notes and Domino License Cost Reduction in the World of DLAU
HCL Notes and Domino License Cost Reduction in the World of DLAUHCL Notes and Domino License Cost Reduction in the World of DLAU
HCL Notes and Domino License Cost Reduction in the World of DLAU
 
Taking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdfTaking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdf
 
Ocean lotus Threat actors project by John Sitima 2024 (1).pptx
Ocean lotus Threat actors project by John Sitima 2024 (1).pptxOcean lotus Threat actors project by John Sitima 2024 (1).pptx
Ocean lotus Threat actors project by John Sitima 2024 (1).pptx
 
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
 
Driving Business Innovation: Latest Generative AI Advancements & Success Story
Driving Business Innovation: Latest Generative AI Advancements & Success StoryDriving Business Innovation: Latest Generative AI Advancements & Success Story
Driving Business Innovation: Latest Generative AI Advancements & Success Story
 
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAUHCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
 
Presentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of GermanyPresentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of Germany
 
Artificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopmentArtificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopment
 
Building Production Ready Search Pipelines with Spark and Milvus
Building Production Ready Search Pipelines with Spark and MilvusBuilding Production Ready Search Pipelines with Spark and Milvus
Building Production Ready Search Pipelines with Spark and Milvus
 
Microsoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdfMicrosoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdf
 
UI5 Controls simplified - UI5con2024 presentation
UI5 Controls simplified - UI5con2024 presentationUI5 Controls simplified - UI5con2024 presentation
UI5 Controls simplified - UI5con2024 presentation
 
How to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptxHow to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptx
 
June Patch Tuesday
June Patch TuesdayJune Patch Tuesday
June Patch Tuesday
 
CAKE: Sharing Slices of Confidential Data on Blockchain
CAKE: Sharing Slices of Confidential Data on BlockchainCAKE: Sharing Slices of Confidential Data on Blockchain
CAKE: Sharing Slices of Confidential Data on Blockchain
 
20240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 202420240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 2024
 
Infrastructure Challenges in Scaling RAG with Custom AI models
Infrastructure Challenges in Scaling RAG with Custom AI modelsInfrastructure Challenges in Scaling RAG with Custom AI models
Infrastructure Challenges in Scaling RAG with Custom AI models
 
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdfUnlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
 

Younes Sina

  • 1. Proposal: Solar Grant Final Project: MSE 567 & 467 Huidong Jonathan Mary Sabina Younes
  • 2. Outline 1. Site Selection 2. Load Profile 3. System Availability 4. Photovoltaic Array Sizing 5. Battery Sizing 6. Power Conditioning Unit ( inverters, fuses, wiring,….) 7. Cost Breakdown
  • 3. Heavily forested area at Tanzania Typical village house Village People
  • 4. Economic consideration in site selection: Cost of site preparation Cost of access to the site
  • 5. The Project Provide PV power at -3.61, 37.37 for 10 yrs 100 small homes ~60ftx60ft 20° slopes Surrounded by 75ft trees 3 month rainy season (spring: Aug – Oct) Random twice a week sun Remainder of year is sunny
  • 6. Parts/Labor Reliability PV 40 yrs Power electronics 5 yrs Batteries 3 yrs Cleaning every 3 months Cost - $/h $5 for laborer $10 for electrical installer $30 for engineer/system designer 5 ton truck $2/mile
  • 7.
  • 11. Work Load Lights 25W*10lamps*12h/day = 3kWh/day Refrigerator 700kWh/yr*yr/365days = 1.91781kWh/day Television 125W*5h/day + 15W*19h/day = 0.91kWh/day Air Conditioner 750W*24h/day = 18kWh/day Computer 200W*5h/day + 10W*19h/day = 1.19kWh/day Washing Machine 0.25kWh/wk*wk/7days = 0.03572kWh/day Total = 25.05353kWh/day/house
  • 12. Components Panels China, GOD company, mono-crystalline 180W, 16% efficiency, 36 Vpm, 1580*808*35 (mm), $283 Batteries Shenzhen Haonaite Power Co, 12V*200AH, 522*238*218 (mm), $168 Inverter/Charge controller Shanghai Jinxian Solar Tech Co, 220V 50Hz 3kW, 1*1*2 (m), $1,757 Wire Shanghai Yingqiang Electronic Co, TIN PLATED COPPER WIRE, $0.805/m
  • 14. Average PV System Component Efficiencies PV array 80-85% Inverter 80-90% Wire 97-98% Disconnects, fuses98-99% Total grid-tied PV system efficiency 60-75% New batteries (roundtrip efficiency) 65-75% Total off-grid PV system efficiency (AC) 40-56%
  • 15. Array/Battery Sizing 25.05353kWh/(4.55*0.18*0.4) = 76.476 77 Panels 77 panels insufficient to recharge battery bank Increased to 78 1653.53kWh/(200Ah*12V*0.8*0.001) = 861.214 batteries Used 862
  • 19. Cost Panels – $2,210,230 7,800 panels Controller/Inverter – $358,428 204units Batteries – $14,481,600 86,200 batteries (worst case/times # by 3) Wire – $4025 5000m Site Clearance – $25,000 (minus lumber sales) Battery storage – $60,000 Hole & Material
  • 20.
  • 21.
  • 22.
  • 23.
  • 24. Cost Shipping Truck – $516,600 1300 trips/2$ per mile/ 216 miles Ship – $51,460 $630 per container/ 80containers Installation Laborers – $24,480 Engineer – $58,320 Training Labor – $10,800 Engineer – $7,200 Cleaning – $146,000 Total – $17,954,143