MITIGATION OF RISKS IN USING
PARALLEL PROJECT SCHEDULES
Patrick M. Kelly, PSP
• Degree:
   – B.S. Ocean Engineering (1996)
• University:
   – US Naval Academy
• Years of Experience:
   – 11 (incl. Civil Engineer Corps)
• Professional Field:
   – Contracting, Project Manager, Project Controls Manager (Scheduling,
     Claims & Disputes Resolution). Managed aviation, industrial, commercial,
     infrastructure and critical structures assignments, and other projects nationwide, providing
     construction and contract management, schedule analysis, impact analysis, cost evaluation,
     entitlement analysis, and other claims and dispute resolution services.

• Something you do not know about me:
Chris Carson, PSP, PMP, CCM
• Corporate Director of Project Controls, Alpha Corporation
   –   Responsible for standards, processes, and procedures for a team of schedulers, analysts,
       and project managers in multiple office locations
   –   Provided seminars for hundreds of scheduling professionals in CPM scheduling
       methodologies, and manages the in-house training program at Alpha
• Certifications: PSP, CCM (Certified Construction Manager - CMAA)
• University: University of Virginia, Mechanical Engineering, 1972
• Professional Field: 37 years of experience in Construction
  Management, CM Services especially Scheduling, Estimating,
  Claims
• Active in PMI College of Scheduling
   –   Managing Director for SEI (Scheduling Excellence Initiative) writing Best Practices and
       Guidelines for Scheduling and Schedule Impact Analysis
• Active in CMAA (Construction Management Association of America
   –   Served on 9 person committee revising the Time Management Chapter of the CMAA’s CM
       Standards of Practice
• Something you do not know about me:
   –   I am a proud grandfather of two girls and a boy
   –   I was given an award for “Significant Contributions to the Scheduling Industry” at the 2009
       CoS national conference




                                                                                                     3
Overview
Overview
• Dual schedule use rarely occurs, but there are
  occasions where a general or prime contractor may
  desire or need to run a separate schedule.
• This usually is the case when the contractor feels
  that there are significant risks to completion, such
  as risks associated with subcontractor performance,
  but the contractor does not wish or may not have
  the ability to run any type of formal risk analysis for
  uncertain durations.
Overview
• This presentation discusses the use of dual parallel
  project schedules, examines the risks and provides
  recommendations when dual schedules are used.
  – Many general contractors (GC) create these "production” schedules,
    separate from the “contract” schedules, which support the contractual
    relationship between the GC and the subcontractors, showing
    aggressive production rates in efforts to reduce late completion risks.
  – The paper identifies the problems created by the existence of the
    "production” schedules including contractual difficulties for all parties,
    increased managerial duties for the GC, constructive acceleration risks,
    and confusion in forensic analysis.
  – We recommend steps to handle this through risk analysis, in creating
    the schedules through a risk management process, including the use of
    global changes and only editing logic when it is "preferential" or
    resource-driven.
Overview
• Recommendations maximize the utility when it is
  necessary to use parallel schedules while
  minimizing problems created by their existence.
• This is not a discussion of “early completion”
  schedules.
  Note that it is preferable to only have one project schedule that is used
                 for both management and analysis of delays.

                  In the rare cases when it is necessary, or when the
                  contractor insists on the use of dual schedules, there
                  are some guidelines that should be followed.

                  These guidelines primarily revolve around the use of
                  informal risk adjustment to provide some level of
                  protection for a contractor while allowing him to pursue
                  an aggressive schedule that is not highly likely to be
                  achieved.
Definitions
Definitions
• The Contract Schedule represents the minimum, or
  most likely, means and methods necessary to
  complete the project within the contractual time
  frame.
  – It represents the commitments made in the prime contract between the
    Owner and the Prime Contractor.
  – For calculation of activity durations, in terms of a three-point estimate
    method for determining activity duration, the Contract Schedule would
    use the “most likely” duration estimate, as shown in the figure below:
Definitions
• In terms of the logic assignment, the Contract
  Schedule would use all the hard logic constraints,
  but would also use a maximum amount of
  preferential logic constraints, particularly those
  which represent resource logic.
• From RP 24R-03 “Developing Activity Logic”:
  – “Activities can be linked with hard logic (i.e., sequence of each activity
    is predetermined, such as footing A before footing B), or soft logic
    wherein related activities may be combined and accomplished in a
    different order as determined at the time of execution. There are also
    physical hard logic relationships where soft logic does not normally
    apply, such as footing formwork must be in place before concrete can
    be placed.”
Definitions
• The Contract Schedule therefore represents the
  minimal, most likely duration plan and resources to
  meet contract time.
  – Note that this is not risk-adjusted in that there is no three-point analysis
    done by repeated iterations using the three duration estimates
  – It is a single deterministic schedule produced by choosing the
    contractor determined and calculated most likely durations for
    individual activities.
Definitions
• The Production Schedule represents the optimistic
  means and methods which the Prime Contractor
  intends to employ during project execution to
  complete early.
  – It should represent the commitments made between the Prime
    Contractor and his subcontractors in the various subcontract
    agreements.
  – In terms of a three-point estimate for activity durations, the Production
    Schedule would use the “optimistic” duration estimates of individual
    activities.
  – In terms of the logic assignments, the Production Schedule would use
    all the hard logic constraints, but would minimize the use of preferential
    logic constraints.
• The Production Schedule therefore represents the
  most aggressive and optimistic plan to complete the
  project early.
Benefits

Why use dual project schedules?
Benefits –Contractual Relationships
• The Contract Schedule represents the commitments
  that the prime contractor has made to the Owner.
   – Overall duration is governed by the prime contract.
• The Production Schedule represents the
  commitments that the prime contractor is requiring
  of the Subcontractors.
   – It is ideal for the subcontractors’ contracts have language which ties
     each Subcontractor’s performance period to the performance period
     shown in the Production Schedule.
• One of the primary benefits of using dual project
  schedules is the ability of the prime contractor to
  manage performance in all of the contractual
  relationships that exist on a project.
Benefits – Early Completion
• There are occasions when the Contract Schedule
  may not be able to represent the contractor’s actual
  plan because of stringent requirements in a
  schedule specification.
  – For instance, schedule specifications often limit a contractor’s ability to
    show early completion.
  – This creates a problem for contractors who have a contract with
    excessively long contract duration.
  – Long contract durations force a contractor to show unrealistically long
    activity durations with production rates lower than anticipated, and
    unless the contractor has the option of showing an early completion
    schedule, he will be unable to account for any delays or disruptions
    caused by the Owner or third parties.
Benefits – Right to Finish Early
• Production Schedules may help support the
  contractor’s right to finish early position.
  – In making such a claim, the use of this schedule could show how his
    aggressive plan was impacted by the Owner’s action or inaction.
  – Supported with the appropriate bid information, the use of this schedule
    might aid in the proof of such a claim.
  – The contractor may not be able to get extended general conditions,
    because it might not show the Critical Path delay in terms of the actual
    Contract Schedule, but it could help prove disruption that prevented the
    contractor from finishing as early as possible.
Benefits - Contingency
• A contractor might want to use this approach in an informal
  attempt to create contingency for risks associated with
  subcontractor performance, particularly in cases where there
  are unfamiliar or untested subcontractors working on a
  complicated project.
• Analysis of update data for subcontractors will reveal
  weaknesses in performance, and help direct the project
  manager’s attention to areas that require his assistance.
• Owner is likely to see this use as the contractor
  inappropriately capturing float.
Benefits – Risk Management
• Accounting for risks to completion:
  – Weather Planning. The Production Schedule may plan for optimistic
    weather, or, alternately, minimizing performance periods of
    subcontractors in order to plan for worse weather than shown in
    Contract Schedule.
  – Work Exclusion Periods. Many contracts contain major exclusion
    periods to accommodate environmental restrictions. These restrictions
    can magnify the effect of a delay. Finishing work early before the onset
    of environmental restriction periods, in order to minimize the risk of
    individual delay events having their effects magnified by the restriction,
    is a reason why the prime contractor would try to drive subcontractors
    to meet optimistic duration estimates.
Benefits – Risk Management
• Accounting for risks to completion:
  – Owner or Third Party Risks. Minimizing the potential impacts of third
    party risks, or planning for Owner caused risks (“predictable
    unforseens”). For example, a common unforeseen condition in
    transportation work is utility conflicts, which, though predictable, are
    also often unavoidable and have a detrimental effect on contractor
    production.
  – Liquidated Damages. A prime contractor is likely to drive the project
    towards optimistic performance when liquidated damages are very high,
    in order to minimize his exposure.
Costs

What are the risks associated with using dual
             project schedules?
Cost – Risk in Perception
• Using a separate, more aggressive schedule can
  tend to generate confusion in the relationship
  between the Owner and the Prime Contractor.
• Owners will often see the Production Schedule as
  the “real” plan, and the Contract Schedule as a way
  to sequester float.
Cost – Risk in Proof of Delay
• The primary problem with dual schedule use occurs
  when the Contractor tries to prove Critical Path
  delay that exists on the Contract Schedule, which
  does not exist on the Production Schedule, when
  the Contractor is actively working means and
  methods as represented in the Production Schedule.
  – When delays are analyzed using the benchmark of the Contract
    Schedule, delays are much more likely to result in time extensions from
    the Owner.
  – In a litigation situation, there is a risk that the triers-of-fact might decide
    that the Production Schedules should have been the baseline for
    analyzing the ramifications of delay, or that the difference is float.
  – The Owner will likely feel this way during the project as well, and it
    promotes the unhealthy attitude of “wait and see” to find out if the
    predicted delays do in fact create a late condition.
Cost – Risk to Management
• Communications get complicated with dual
  schedules.
  – The PM team is always trying to figure out which schedule is under
    discussion, and even if the subcontractors know about the two
    schedules, when they are exposed to them on the project, it will cause
    alarm and a feeling of being constructively accelerated for no reason.
  – When a subcontractor is put on notice of lack of production, since that
    measurement is from the tighter Production Schedule, that
    subcontractor could take the position that there was more float in the
    project than admitted in the Production Schedule, justifying more time
    for performance, and this could result in actual constructive
    acceleration claims from subcontractors.
Creation and Maintenance

What is the best way to create and maintain a
          dual series of schedules?
Creation
• It is preferable to only have one project schedule
  that is used for both management and analysis of
  delays.
• However, should the conditions exist which make
  the use of dual schedules beneficial, there are some
  general precepts which should be followed.
Creation – Schedule Shell
• Steps:
   – Create the schedule “shell;” that is, the activity code structure, work
     breakdown structure, and calendars. This shell will be used for both the
     Production Schedule and Contract Schedule.
   – Create the list of activities. This activity list, developed to the
     appropriate level of detail (as determined by contract specifications, the
     needs of project management, etc.), will be used in both the Production
     Schedule and the Contract Schedule.
   – Develop the hard logic. Again, since this is logic representing physical
     constraints which are inviolable, these logic ties should be common
     between the two schedules.
• At this point, the scheduler should be ready to develop the
  aspects of the Production Schedule and Contract Schedule
  which will be different from one another.
Creation – Production Schedule
• The first schedule developed should be the Production
  Schedule.
   – This schedule is produced using the optimistic estimate of durations for Prime
     Contractor activities, and should also take into account subcontractor input for
     activity durations.
   – The Production Schedule differences may be limited to a single trade or
     discipline; for instance, the Production Schedule may aggressively prosecute the
     building shell to achieve early dry-in.
   – There should be little or no contingency built into the activity durations at this
     point.
• Once this schedule is developed, it can be compared to the
  contractual project duration to see if it already consumes the
  contractually allowed time, and if so, it will be necessary to
  abandon the dual schedule concept.
Creation – Production Schedule
• The Production Schedules should be explained to the
  subcontractors, showing them that it does contain their
  supplied durations, logic, and dates. The subcontracts
  should reference this schedule as the only project schedule
  used for the subcontracts.
Creation – Contract Schedule
• The development of the Contract Schedule should
  involve reassignment of activity durations to allow
  for the most likely duration estimate, and should add
  additional preferential logic to show the most likely
  level of resources.
  – The differences between activity durations and preferential logic should
    be clearly recorded in strong schedule basis documentation that shows
    the basis of all durations, logic, and resource plans.
  – This information will be essential during the progress of the project to
    understand the dual schedules and their relationship.
Creation – Schedule Updates
• Development of the schedule updates can begin with the
  statusing of either the Contract or the Production Schedule.
  Progress is only a series of facts about status of activities at a
  given point.
   – There should be no difference between the statuses of the two schedules.
   – Since activities and activity IDs are consistent between the two schedules,
     progress input into one schedule can be easily exported, then imported into the
     other.
• Recalculation as of the common data date will show how the
  Prime Contractor is matching both the plans.
• There may be benefit to recalculating the Contract Schedule
  on “Progress Override” as an analysis method, in order to
  review the two schedules’ Critical Paths; however, in general,
  we recommend the use of “Retained Logic” and implementing
  network revisions to account for any out-of-sequence work.
Creation – Schedule Updates
• Schedulers should perform an analysis of both the
  schedules in order to determine how well
  subcontractors are performing.
  – Review of subcontractor Time Performance Ratio (Actual Duration /
    Original Duration) will show whether they are meeting the aggressive
    Production Schedule durations, or even the less optimistic Contract
    Schedule durations.
  – Schedulers should develop comparison layouts to show the two
    schedules’ plans for the next period.
Creation – Schedule Updates
• It is advisable to change the logic/durations in the
  Contract Schedule for the next update period to
  match those in the Production Schedule.
• If the project is progressing well, each update
  should bring the two schedules closer together as
  the Contract Schedule is predicting improved
  completion.
Risk Management

What techniques should contractors use to
          minimize these risks?
Risk Management
• The use of best-case scenario estimates means that
  a strong qualitative risk management plan is that
  much more essential.
  – Since risk management should be incorporated into the project
    schedule, any attempt to use dual schedules is likely to reduce the
    chances of completing on time.
  – Risk processes should be applied to the only schedule on the project,
    used for construction.
  – Risk management should also be transparent and reviewed each update,
    and this process makes at least some of the risk actions hidden.
Risk Management
• The Production Schedule does not make any
  allowance for trade to trade coordination or
  mobilization and demobilization, and assumes that
  there is no lost time for additional cleanup or
  materials delivery or racking.
  – This produces a schedule that represents the minimal time frame for
    construction, and leaves the contractor responsible for a high risk of
    performance.
  – The superintendent will need to use this schedule carefully and motivate
    the subcontractors and workers to meet the dates and milestones in this
    schedule.
Risk Management
• Once the Production Schedule is developed and
  checked, the project management team should run a
  risk management assessment on the project, and
  identify all risks to performance.
  – Weather
  – High-risk subcontractors
  – Mobilization and Rework Time
Risk Management
• The appropriate way to deal with this situation is to
  tell the Owner up front how the schedule is being
  developed, and explain the situation.
• Attempt to get agreement that any time saved by the
  production time will be to the contractor’s benefit
  and will not accrue to float for the project, except as
  the contractual schedule gains time and adds float
  to the schedule.
Conclusion
Conclusion
• It is preferable to only have one project schedule that is used
  for both management and analysis of delays.
• In the rare cases when it is necessary, or when the contractor
  insists on the use of dual schedules, there are some
  guidelines that should be followed.
• The guidelines primarily revolve around the use of informal
  risk adjustment to provide some level of protection for a
  contractor while allowing him to pursue an aggressive
  schedule that is not highly likely to be achieved.
MITIGATION OF RISKS IN USING
        PARALLEL PROJECT
           SCHEDULES

                              Questions?
    Chris Carson, PSP, PMP, CCM                Patrick M. Kelly, PSP
Corporate Director of Project Controls      Project Controls Manager


Chris.Carson@alphacorporation.com        Patrick.Kelly@alphacorporation.com
  (O) 757-533-9368   (M) 757-342-5524    (O) 757-533-9368   (M) 757-217-6820
41

More Related Content

What's hot

Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - AirportChris Carson
 
CPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryCPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryMichael Pink
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact AnalysisChris Carson
 
DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.Chris Carson
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule RevisionsChris Carson
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminChris Carson
 
Schedule Design AACE
Schedule Design AACESchedule Design AACE
Schedule Design AACEChris Carson
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2Chris Carson
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMIChris Carson
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2Abdelhay Ghanem
 
Project Scheduling and Control Projects
Project Scheduling and Control ProjectsProject Scheduling and Control Projects
Project Scheduling and Control Projectsharoldtaylor1113
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1Chris Carson
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
 

What's hot (19)

Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Claims Triage
Claims TriageClaims Triage
Claims Triage
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - Airport
 
CPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryCPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction Indistry
 
Schedule Review
Schedule ReviewSchedule Review
Schedule Review
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract Admin
 
Schedule Design AACE
Schedule Design AACESchedule Design AACE
Schedule Design AACE
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
 
Project Scheduling and Control Projects
Project Scheduling and Control ProjectsProject Scheduling and Control Projects
Project Scheduling and Control Projects
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 

Viewers also liked

Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion SchedulesChris Carson
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueChris Carson
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationChris Carson
 
Managing construction risks robert epstein, greenberg traurig
Managing construction risks   robert epstein, greenberg traurigManaging construction risks   robert epstein, greenberg traurig
Managing construction risks robert epstein, greenberg traurigfrancistoriaga
 
PROJ 420 Course Project
PROJ 420 Course ProjectPROJ 420 Course Project
PROJ 420 Course Projectgsb100
 
Subcontractor default insurance thomas tripodianos & anthony carlucci -...
Subcontractor default insurance   thomas tripodianos & anthony carlucci -...Subcontractor default insurance   thomas tripodianos & anthony carlucci -...
Subcontractor default insurance thomas tripodianos & anthony carlucci -...francistoriaga
 
Different types of glasses
Different types of glassesDifferent types of glasses
Different types of glassesKrishna Sahit
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsHamdija Velagic
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building ConstructionHamdija Velagic
 

Viewers also liked (11)

Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion Schedules
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan Presentation
 
Managing construction risks robert epstein, greenberg traurig
Managing construction risks   robert epstein, greenberg traurigManaging construction risks   robert epstein, greenberg traurig
Managing construction risks robert epstein, greenberg traurig
 
PROJ 420 Course Project
PROJ 420 Course ProjectPROJ 420 Course Project
PROJ 420 Course Project
 
Subcontractor default insurance thomas tripodianos & anthony carlucci -...
Subcontractor default insurance   thomas tripodianos & anthony carlucci -...Subcontractor default insurance   thomas tripodianos & anthony carlucci -...
Subcontractor default insurance thomas tripodianos & anthony carlucci -...
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Different types of glasses
Different types of glassesDifferent types of glasses
Different types of glasses
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building Construction
 

Similar to Mitigation of Risk in Dual Schedules

Top 3 Challenges in Managing Triple Constraint
Top 3 Challenges in Managing Triple ConstraintTop 3 Challenges in Managing Triple Constraint
Top 3 Challenges in Managing Triple ConstraintSunil Guglani
 
A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning Olivia Wilson
 
Trade-off Analysis in a Project EnvironmentWhen we try .docx
Trade-off Analysis in a Project EnvironmentWhen we try .docxTrade-off Analysis in a Project EnvironmentWhen we try .docx
Trade-off Analysis in a Project EnvironmentWhen we try .docxturveycharlyn
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
Transitioning from Project to Operations in CSG to LNG
Transitioning from Project to Operations in CSG to LNGTransitioning from Project to Operations in CSG to LNG
Transitioning from Project to Operations in CSG to LNGKai Eberspaecher
 
J.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of scheduleJ.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of scheduleJ.S. Daniel
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project managementChris Hattingh
 
Major Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperMajor Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperIan Heptinstall
 
Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview WorkshopRae Davies
 
D22MB040_Unit_6.pptx
D22MB040_Unit_6.pptxD22MB040_Unit_6.pptx
D22MB040_Unit_6.pptxkiranroy6777
 
CPM Consultants Delaware
CPM Consultants DelawareCPM Consultants Delaware
CPM Consultants DelawareWilliam Brooks
 
Calculation of the construction time systematic management of project uncert...
Calculation of the construction time  systematic management of project uncert...Calculation of the construction time  systematic management of project uncert...
Calculation of the construction time systematic management of project uncert...eSAT Journals
 
Dealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration MegaprojectsDealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration MegaprojectsJeremie Averous
 
independent scheduling consultants
independent scheduling consultants independent scheduling consultants
independent scheduling consultants William Brooks
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1reddvise
 

Similar to Mitigation of Risk in Dual Schedules (20)

Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)
 
Top 3 Challenges in Managing Triple Constraint
Top 3 Challenges in Managing Triple ConstraintTop 3 Challenges in Managing Triple Constraint
Top 3 Challenges in Managing Triple Constraint
 
A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning
 
Trade-off Analysis in a Project EnvironmentWhen we try .docx
Trade-off Analysis in a Project EnvironmentWhen we try .docxTrade-off Analysis in a Project EnvironmentWhen we try .docx
Trade-off Analysis in a Project EnvironmentWhen we try .docx
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Transitioning from Project to Operations in CSG to LNG
Transitioning from Project to Operations in CSG to LNGTransitioning from Project to Operations in CSG to LNG
Transitioning from Project to Operations in CSG to LNG
 
J.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of scheduleJ.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of schedule
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project management
 
Major Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperMajor Projects - Faster Better Cheaper
Major Projects - Faster Better Cheaper
 
Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview Workshop
 
D22MB040_Unit_6.pptx
D22MB040_Unit_6.pptxD22MB040_Unit_6.pptx
D22MB040_Unit_6.pptx
 
CPM Consultants Delaware
CPM Consultants DelawareCPM Consultants Delaware
CPM Consultants Delaware
 
ch09s.ppt
ch09s.pptch09s.ppt
ch09s.ppt
 
Calculation of the construction time systematic management of project uncert...
Calculation of the construction time  systematic management of project uncert...Calculation of the construction time  systematic management of project uncert...
Calculation of the construction time systematic management of project uncert...
 
Dealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration MegaprojectsDealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration Megaprojects
 
independent scheduling consultants
independent scheduling consultants independent scheduling consultants
independent scheduling consultants
 
construction project planing
 construction project planing construction project planing
construction project planing
 
CSC-1986.original
CSC-1986.originalCSC-1986.original
CSC-1986.original
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1
 

More from Chris Carson

Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpChris Carson
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry SchedulingChris Carson
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotChris Carson
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesChris Carson
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful MediationChris Carson
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex ProjectChris Carson
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony MistakesChris Carson
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule DevelopmentChris Carson
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor SchedulingChris Carson
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMIChris Carson
 

More from Chris Carson (10)

Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls Pp
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry Scheduling
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does Not
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel Schedules
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful Mediation
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex Project
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony Mistakes
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor Scheduling
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMI
 

Mitigation of Risk in Dual Schedules

  • 1. MITIGATION OF RISKS IN USING PARALLEL PROJECT SCHEDULES
  • 2. Patrick M. Kelly, PSP • Degree: – B.S. Ocean Engineering (1996) • University: – US Naval Academy • Years of Experience: – 11 (incl. Civil Engineer Corps) • Professional Field: – Contracting, Project Manager, Project Controls Manager (Scheduling, Claims & Disputes Resolution). Managed aviation, industrial, commercial, infrastructure and critical structures assignments, and other projects nationwide, providing construction and contract management, schedule analysis, impact analysis, cost evaluation, entitlement analysis, and other claims and dispute resolution services. • Something you do not know about me:
  • 3. Chris Carson, PSP, PMP, CCM • Corporate Director of Project Controls, Alpha Corporation – Responsible for standards, processes, and procedures for a team of schedulers, analysts, and project managers in multiple office locations – Provided seminars for hundreds of scheduling professionals in CPM scheduling methodologies, and manages the in-house training program at Alpha • Certifications: PSP, CCM (Certified Construction Manager - CMAA) • University: University of Virginia, Mechanical Engineering, 1972 • Professional Field: 37 years of experience in Construction Management, CM Services especially Scheduling, Estimating, Claims • Active in PMI College of Scheduling – Managing Director for SEI (Scheduling Excellence Initiative) writing Best Practices and Guidelines for Scheduling and Schedule Impact Analysis • Active in CMAA (Construction Management Association of America – Served on 9 person committee revising the Time Management Chapter of the CMAA’s CM Standards of Practice • Something you do not know about me: – I am a proud grandfather of two girls and a boy – I was given an award for “Significant Contributions to the Scheduling Industry” at the 2009 CoS national conference 3
  • 5. Overview • Dual schedule use rarely occurs, but there are occasions where a general or prime contractor may desire or need to run a separate schedule. • This usually is the case when the contractor feels that there are significant risks to completion, such as risks associated with subcontractor performance, but the contractor does not wish or may not have the ability to run any type of formal risk analysis for uncertain durations.
  • 6. Overview • This presentation discusses the use of dual parallel project schedules, examines the risks and provides recommendations when dual schedules are used. – Many general contractors (GC) create these "production” schedules, separate from the “contract” schedules, which support the contractual relationship between the GC and the subcontractors, showing aggressive production rates in efforts to reduce late completion risks. – The paper identifies the problems created by the existence of the "production” schedules including contractual difficulties for all parties, increased managerial duties for the GC, constructive acceleration risks, and confusion in forensic analysis. – We recommend steps to handle this through risk analysis, in creating the schedules through a risk management process, including the use of global changes and only editing logic when it is "preferential" or resource-driven.
  • 7. Overview • Recommendations maximize the utility when it is necessary to use parallel schedules while minimizing problems created by their existence. • This is not a discussion of “early completion” schedules. Note that it is preferable to only have one project schedule that is used for both management and analysis of delays. In the rare cases when it is necessary, or when the contractor insists on the use of dual schedules, there are some guidelines that should be followed. These guidelines primarily revolve around the use of informal risk adjustment to provide some level of protection for a contractor while allowing him to pursue an aggressive schedule that is not highly likely to be achieved.
  • 9. Definitions • The Contract Schedule represents the minimum, or most likely, means and methods necessary to complete the project within the contractual time frame. – It represents the commitments made in the prime contract between the Owner and the Prime Contractor. – For calculation of activity durations, in terms of a three-point estimate method for determining activity duration, the Contract Schedule would use the “most likely” duration estimate, as shown in the figure below:
  • 10. Definitions • In terms of the logic assignment, the Contract Schedule would use all the hard logic constraints, but would also use a maximum amount of preferential logic constraints, particularly those which represent resource logic. • From RP 24R-03 “Developing Activity Logic”: – “Activities can be linked with hard logic (i.e., sequence of each activity is predetermined, such as footing A before footing B), or soft logic wherein related activities may be combined and accomplished in a different order as determined at the time of execution. There are also physical hard logic relationships where soft logic does not normally apply, such as footing formwork must be in place before concrete can be placed.”
  • 11. Definitions • The Contract Schedule therefore represents the minimal, most likely duration plan and resources to meet contract time. – Note that this is not risk-adjusted in that there is no three-point analysis done by repeated iterations using the three duration estimates – It is a single deterministic schedule produced by choosing the contractor determined and calculated most likely durations for individual activities.
  • 12. Definitions • The Production Schedule represents the optimistic means and methods which the Prime Contractor intends to employ during project execution to complete early. – It should represent the commitments made between the Prime Contractor and his subcontractors in the various subcontract agreements. – In terms of a three-point estimate for activity durations, the Production Schedule would use the “optimistic” duration estimates of individual activities. – In terms of the logic assignments, the Production Schedule would use all the hard logic constraints, but would minimize the use of preferential logic constraints. • The Production Schedule therefore represents the most aggressive and optimistic plan to complete the project early.
  • 13. Benefits Why use dual project schedules?
  • 14. Benefits –Contractual Relationships • The Contract Schedule represents the commitments that the prime contractor has made to the Owner. – Overall duration is governed by the prime contract. • The Production Schedule represents the commitments that the prime contractor is requiring of the Subcontractors. – It is ideal for the subcontractors’ contracts have language which ties each Subcontractor’s performance period to the performance period shown in the Production Schedule. • One of the primary benefits of using dual project schedules is the ability of the prime contractor to manage performance in all of the contractual relationships that exist on a project.
  • 15. Benefits – Early Completion • There are occasions when the Contract Schedule may not be able to represent the contractor’s actual plan because of stringent requirements in a schedule specification. – For instance, schedule specifications often limit a contractor’s ability to show early completion. – This creates a problem for contractors who have a contract with excessively long contract duration. – Long contract durations force a contractor to show unrealistically long activity durations with production rates lower than anticipated, and unless the contractor has the option of showing an early completion schedule, he will be unable to account for any delays or disruptions caused by the Owner or third parties.
  • 16. Benefits – Right to Finish Early • Production Schedules may help support the contractor’s right to finish early position. – In making such a claim, the use of this schedule could show how his aggressive plan was impacted by the Owner’s action or inaction. – Supported with the appropriate bid information, the use of this schedule might aid in the proof of such a claim. – The contractor may not be able to get extended general conditions, because it might not show the Critical Path delay in terms of the actual Contract Schedule, but it could help prove disruption that prevented the contractor from finishing as early as possible.
  • 17. Benefits - Contingency • A contractor might want to use this approach in an informal attempt to create contingency for risks associated with subcontractor performance, particularly in cases where there are unfamiliar or untested subcontractors working on a complicated project. • Analysis of update data for subcontractors will reveal weaknesses in performance, and help direct the project manager’s attention to areas that require his assistance. • Owner is likely to see this use as the contractor inappropriately capturing float.
  • 18. Benefits – Risk Management • Accounting for risks to completion: – Weather Planning. The Production Schedule may plan for optimistic weather, or, alternately, minimizing performance periods of subcontractors in order to plan for worse weather than shown in Contract Schedule. – Work Exclusion Periods. Many contracts contain major exclusion periods to accommodate environmental restrictions. These restrictions can magnify the effect of a delay. Finishing work early before the onset of environmental restriction periods, in order to minimize the risk of individual delay events having their effects magnified by the restriction, is a reason why the prime contractor would try to drive subcontractors to meet optimistic duration estimates.
  • 19. Benefits – Risk Management • Accounting for risks to completion: – Owner or Third Party Risks. Minimizing the potential impacts of third party risks, or planning for Owner caused risks (“predictable unforseens”). For example, a common unforeseen condition in transportation work is utility conflicts, which, though predictable, are also often unavoidable and have a detrimental effect on contractor production. – Liquidated Damages. A prime contractor is likely to drive the project towards optimistic performance when liquidated damages are very high, in order to minimize his exposure.
  • 20. Costs What are the risks associated with using dual project schedules?
  • 21. Cost – Risk in Perception • Using a separate, more aggressive schedule can tend to generate confusion in the relationship between the Owner and the Prime Contractor. • Owners will often see the Production Schedule as the “real” plan, and the Contract Schedule as a way to sequester float.
  • 22. Cost – Risk in Proof of Delay • The primary problem with dual schedule use occurs when the Contractor tries to prove Critical Path delay that exists on the Contract Schedule, which does not exist on the Production Schedule, when the Contractor is actively working means and methods as represented in the Production Schedule. – When delays are analyzed using the benchmark of the Contract Schedule, delays are much more likely to result in time extensions from the Owner. – In a litigation situation, there is a risk that the triers-of-fact might decide that the Production Schedules should have been the baseline for analyzing the ramifications of delay, or that the difference is float. – The Owner will likely feel this way during the project as well, and it promotes the unhealthy attitude of “wait and see” to find out if the predicted delays do in fact create a late condition.
  • 23. Cost – Risk to Management • Communications get complicated with dual schedules. – The PM team is always trying to figure out which schedule is under discussion, and even if the subcontractors know about the two schedules, when they are exposed to them on the project, it will cause alarm and a feeling of being constructively accelerated for no reason. – When a subcontractor is put on notice of lack of production, since that measurement is from the tighter Production Schedule, that subcontractor could take the position that there was more float in the project than admitted in the Production Schedule, justifying more time for performance, and this could result in actual constructive acceleration claims from subcontractors.
  • 24. Creation and Maintenance What is the best way to create and maintain a dual series of schedules?
  • 25. Creation • It is preferable to only have one project schedule that is used for both management and analysis of delays. • However, should the conditions exist which make the use of dual schedules beneficial, there are some general precepts which should be followed.
  • 26. Creation – Schedule Shell • Steps: – Create the schedule “shell;” that is, the activity code structure, work breakdown structure, and calendars. This shell will be used for both the Production Schedule and Contract Schedule. – Create the list of activities. This activity list, developed to the appropriate level of detail (as determined by contract specifications, the needs of project management, etc.), will be used in both the Production Schedule and the Contract Schedule. – Develop the hard logic. Again, since this is logic representing physical constraints which are inviolable, these logic ties should be common between the two schedules. • At this point, the scheduler should be ready to develop the aspects of the Production Schedule and Contract Schedule which will be different from one another.
  • 27. Creation – Production Schedule • The first schedule developed should be the Production Schedule. – This schedule is produced using the optimistic estimate of durations for Prime Contractor activities, and should also take into account subcontractor input for activity durations. – The Production Schedule differences may be limited to a single trade or discipline; for instance, the Production Schedule may aggressively prosecute the building shell to achieve early dry-in. – There should be little or no contingency built into the activity durations at this point. • Once this schedule is developed, it can be compared to the contractual project duration to see if it already consumes the contractually allowed time, and if so, it will be necessary to abandon the dual schedule concept.
  • 28. Creation – Production Schedule • The Production Schedules should be explained to the subcontractors, showing them that it does contain their supplied durations, logic, and dates. The subcontracts should reference this schedule as the only project schedule used for the subcontracts.
  • 29. Creation – Contract Schedule • The development of the Contract Schedule should involve reassignment of activity durations to allow for the most likely duration estimate, and should add additional preferential logic to show the most likely level of resources. – The differences between activity durations and preferential logic should be clearly recorded in strong schedule basis documentation that shows the basis of all durations, logic, and resource plans. – This information will be essential during the progress of the project to understand the dual schedules and their relationship.
  • 30. Creation – Schedule Updates • Development of the schedule updates can begin with the statusing of either the Contract or the Production Schedule. Progress is only a series of facts about status of activities at a given point. – There should be no difference between the statuses of the two schedules. – Since activities and activity IDs are consistent between the two schedules, progress input into one schedule can be easily exported, then imported into the other. • Recalculation as of the common data date will show how the Prime Contractor is matching both the plans. • There may be benefit to recalculating the Contract Schedule on “Progress Override” as an analysis method, in order to review the two schedules’ Critical Paths; however, in general, we recommend the use of “Retained Logic” and implementing network revisions to account for any out-of-sequence work.
  • 31. Creation – Schedule Updates • Schedulers should perform an analysis of both the schedules in order to determine how well subcontractors are performing. – Review of subcontractor Time Performance Ratio (Actual Duration / Original Duration) will show whether they are meeting the aggressive Production Schedule durations, or even the less optimistic Contract Schedule durations. – Schedulers should develop comparison layouts to show the two schedules’ plans for the next period.
  • 32. Creation – Schedule Updates • It is advisable to change the logic/durations in the Contract Schedule for the next update period to match those in the Production Schedule. • If the project is progressing well, each update should bring the two schedules closer together as the Contract Schedule is predicting improved completion.
  • 33. Risk Management What techniques should contractors use to minimize these risks?
  • 34. Risk Management • The use of best-case scenario estimates means that a strong qualitative risk management plan is that much more essential. – Since risk management should be incorporated into the project schedule, any attempt to use dual schedules is likely to reduce the chances of completing on time. – Risk processes should be applied to the only schedule on the project, used for construction. – Risk management should also be transparent and reviewed each update, and this process makes at least some of the risk actions hidden.
  • 35. Risk Management • The Production Schedule does not make any allowance for trade to trade coordination or mobilization and demobilization, and assumes that there is no lost time for additional cleanup or materials delivery or racking. – This produces a schedule that represents the minimal time frame for construction, and leaves the contractor responsible for a high risk of performance. – The superintendent will need to use this schedule carefully and motivate the subcontractors and workers to meet the dates and milestones in this schedule.
  • 36. Risk Management • Once the Production Schedule is developed and checked, the project management team should run a risk management assessment on the project, and identify all risks to performance. – Weather – High-risk subcontractors – Mobilization and Rework Time
  • 37. Risk Management • The appropriate way to deal with this situation is to tell the Owner up front how the schedule is being developed, and explain the situation. • Attempt to get agreement that any time saved by the production time will be to the contractor’s benefit and will not accrue to float for the project, except as the contractual schedule gains time and adds float to the schedule.
  • 39. Conclusion • It is preferable to only have one project schedule that is used for both management and analysis of delays. • In the rare cases when it is necessary, or when the contractor insists on the use of dual schedules, there are some guidelines that should be followed. • The guidelines primarily revolve around the use of informal risk adjustment to provide some level of protection for a contractor while allowing him to pursue an aggressive schedule that is not highly likely to be achieved.
  • 40. MITIGATION OF RISKS IN USING PARALLEL PROJECT SCHEDULES Questions? Chris Carson, PSP, PMP, CCM Patrick M. Kelly, PSP Corporate Director of Project Controls Project Controls Manager Chris.Carson@alphacorporation.com Patrick.Kelly@alphacorporation.com (O) 757-533-9368 (M) 757-342-5524 (O) 757-533-9368 (M) 757-217-6820
  • 41. 41