Introduction to Cost Management and Professional Certificates
محتوى المحاضرة:
●عناصر التكلفة الرئيسية للمشاريع.
●طرق ومستويات تقدير التكاليف.
●القيمة المكتسبة والتحكم في التكاليف.
●المؤثرات المختلفة على التكاليف.
●أهم الشهادات الاحترافية في إدارة التكاليف.
●فكرة عن شهادة CCP وكيفية الحصول عليها.
Construction Contracts Management based on UK common law using more than 40 cases of law with references from the UK, USA regulations, and international rules plus some examples from standard forms of construction contracts such as JCT, NEC & FIDIC.
إدارة التخطيط والبرامج الزمنية
فيديو المحاضرة: https://www.youtube.com/watch?v=HiGNZeLQ9Po
Content:
1- Planning and scheduling
2- Time schedule development
3- Resource and cost loading
4- Time schedule submittal
5- Review and approval
6- Update and reporting
7- Delay quantification approaches
8- Mitigation and action plans
On 23 May 2012, McLachlan Lister's Anamaria Popescu made a presentation on "Extensions of Time - Avoiding the Traps or Taking Advantage of Them" in conjunction with well-known Australian law firm Holding Redlich
تصنيف أنواع العقود في مجال الانشاءات
دورة مجانية في: https://www.udemy.com/contracts-arabic/
الدورة الكاملة: prof.planner.teachable.com/p/contract-management/
Introduction to Cost Management and Professional Certificates
محتوى المحاضرة:
●عناصر التكلفة الرئيسية للمشاريع.
●طرق ومستويات تقدير التكاليف.
●القيمة المكتسبة والتحكم في التكاليف.
●المؤثرات المختلفة على التكاليف.
●أهم الشهادات الاحترافية في إدارة التكاليف.
●فكرة عن شهادة CCP وكيفية الحصول عليها.
Construction Contracts Management based on UK common law using more than 40 cases of law with references from the UK, USA regulations, and international rules plus some examples from standard forms of construction contracts such as JCT, NEC & FIDIC.
إدارة التخطيط والبرامج الزمنية
فيديو المحاضرة: https://www.youtube.com/watch?v=HiGNZeLQ9Po
Content:
1- Planning and scheduling
2- Time schedule development
3- Resource and cost loading
4- Time schedule submittal
5- Review and approval
6- Update and reporting
7- Delay quantification approaches
8- Mitigation and action plans
On 23 May 2012, McLachlan Lister's Anamaria Popescu made a presentation on "Extensions of Time - Avoiding the Traps or Taking Advantage of Them" in conjunction with well-known Australian law firm Holding Redlich
تصنيف أنواع العقود في مجال الانشاءات
دورة مجانية في: https://www.udemy.com/contracts-arabic/
الدورة الكاملة: prof.planner.teachable.com/p/contract-management/
مقارنة بين ثلاثة من الصيغ النموذجية البريطانية والدولية مع فكرة عن نموذج رابع أمريكي
FIDIC - JCT - NEC - AIA
محاضرة الشرح: https://www.youtube.com/watch?v=fVpeut_-9-0
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
Presentation from a Town Hall session to discuss favorite forensic schedule analysis methodologies, based on the Forensic Analysis Recommended Practice from AACE International. The Best Practices and Guidelines for Schedule Impact Analysis project is discussing methods.
الاصدار الثاني من الأسس الخمسين لإدارة عقود التشييد والمقاولات
الشرح مع أمثلة من القانون والحالات القضائية والصيغ النموذجية للعقود كالفيديك وغيره موجود على: https://www.luqmanacademy.com/course?course=_525sl60348e7e6d487
مقدمة في إدارة العقود الهندسية
The lecture includes:
- 5/50 Questions of Contract Fundamentals
- 3 Suites of Standard Forms of Contracts
- 5 Examples of Case Law
- 1 Sub-clause of FIDIC Red Book 2017
Video: https://youtu.be/2vrYi0PxpYg
مراجعة كاملة وشاملة لشهادة محترف ادارة المشاريع
دورة محاضرات فيديو مع اسئلة: http://prof.planner.teachable.com/courses/pmp-arabic/
على قناة اليوتيوب الفيديو: https://www.youtube.com/playlist?list=PL9HqmhqTzU-UkDJ6GANiBffjTHBgfY_Gu
The Second Edition of the Rainbow Suite is considerably longer, more detailed. The update addresses issues raised by users over the past 18 years and reflects current international best practice. The presentation analysis changes in Yellow & Silver Books as they apply to EPC & PPP Contracts from the perspectives of Public Entities, Contractors and Lenders.
إدارة القيمة المكتسبة مفيدة ومخادعة في التحكم في المشروعات
فيديو دورة الأساسيات: http://prof.planner.teachable.com/p/evm-basics/
دورة المستوى المتقدم: http://www.slideshare.net/MohamedMaged8/contracts-classification
للمزيد: https://www.facebook.com/groups/prof.cost.engineers/
Earned schedule role in performance reporting and other important delay indicators.
Video: https://www.youtube.com/watch?v=FbA6RWB1gDM&feature=youtu.be
The full course: https://www.luqmanacademy.com/course?course=project-control-using-evm_399sl6015424f8aba9
Video: https://twitter.com/magedkom/status/1354678096683618305?s=20
Quantify Construction Damages related to Delay, disruption, and inefficienciesMichael Pink
Learn how to quantify damages related to delay, disruption and inefficiencies on Construction projects. Convert your delays and impacts into cost claims with this proven process.
مقارنة بين ثلاثة من الصيغ النموذجية البريطانية والدولية مع فكرة عن نموذج رابع أمريكي
FIDIC - JCT - NEC - AIA
محاضرة الشرح: https://www.youtube.com/watch?v=fVpeut_-9-0
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
Presentation from a Town Hall session to discuss favorite forensic schedule analysis methodologies, based on the Forensic Analysis Recommended Practice from AACE International. The Best Practices and Guidelines for Schedule Impact Analysis project is discussing methods.
الاصدار الثاني من الأسس الخمسين لإدارة عقود التشييد والمقاولات
الشرح مع أمثلة من القانون والحالات القضائية والصيغ النموذجية للعقود كالفيديك وغيره موجود على: https://www.luqmanacademy.com/course?course=_525sl60348e7e6d487
مقدمة في إدارة العقود الهندسية
The lecture includes:
- 5/50 Questions of Contract Fundamentals
- 3 Suites of Standard Forms of Contracts
- 5 Examples of Case Law
- 1 Sub-clause of FIDIC Red Book 2017
Video: https://youtu.be/2vrYi0PxpYg
مراجعة كاملة وشاملة لشهادة محترف ادارة المشاريع
دورة محاضرات فيديو مع اسئلة: http://prof.planner.teachable.com/courses/pmp-arabic/
على قناة اليوتيوب الفيديو: https://www.youtube.com/playlist?list=PL9HqmhqTzU-UkDJ6GANiBffjTHBgfY_Gu
The Second Edition of the Rainbow Suite is considerably longer, more detailed. The update addresses issues raised by users over the past 18 years and reflects current international best practice. The presentation analysis changes in Yellow & Silver Books as they apply to EPC & PPP Contracts from the perspectives of Public Entities, Contractors and Lenders.
إدارة القيمة المكتسبة مفيدة ومخادعة في التحكم في المشروعات
فيديو دورة الأساسيات: http://prof.planner.teachable.com/p/evm-basics/
دورة المستوى المتقدم: http://www.slideshare.net/MohamedMaged8/contracts-classification
للمزيد: https://www.facebook.com/groups/prof.cost.engineers/
Earned schedule role in performance reporting and other important delay indicators.
Video: https://www.youtube.com/watch?v=FbA6RWB1gDM&feature=youtu.be
The full course: https://www.luqmanacademy.com/course?course=project-control-using-evm_399sl6015424f8aba9
Video: https://twitter.com/magedkom/status/1354678096683618305?s=20
Quantify Construction Damages related to Delay, disruption, and inefficienciesMichael Pink
Learn how to quantify damages related to delay, disruption and inefficiencies on Construction projects. Convert your delays and impacts into cost claims with this proven process.
Sustainability as a city identity الاستدامة كهوية للمدينةEman Elmazek
Sustainability as a city identity is a public awareness presentation. The presentation shows the importance of shaping a solid city identity, how sustainability is a demanding trend in the global market and how some cities make it part of its identity. Sustainability had helped in shaping Middle East cities' identity facing the challenge of globalization.
The Principle in short :
"10% of our life depends on what happens to us"...
"90% of our life depends on how we react to it...."
I re edit New version of easy Learning for youth .
3d, 4d, 5d and 6d bim provide exceptional results for building construction!bimservicesindia1
BIM Services India is an eminent Architectural and Engineering consulting company provides all round solutions such as site analysis, CAD Services, planning, 3D 4D & 5D BIM Architectural and Engineering designs and other relevant consulting services to the clients from Architectural, Mechanical and Structural spheres at highly competitive cost with promising prompt delivery.
website:www.bimservicesindia.com
Indian Contract system has become a complex system mainly plagued by legal discrepancies. This has resulted in companies/organization spending their valuable time and monetary resources in fighting and hence proving their respective arguments in arbitrational councils or court of law. Many ways can be adopted so that organization conducting business transactions do not have to opt to arbitration. However, despite severe measures taken by organization there may be situation arising where both parties have to opt for arbitrational procedure. This paper underlines the key aspects that are needed to win an arbitrational procedure with proper planning, presentation and approach
Dear students get fully solved assignments
Send your semester & Specialization name to our mail id :
“ help.mbaassignments@gmail.com ”
or
Call us at : 08263069601
(Prefer mailing. Call in emergency )
We are delighted to welcome you to the first edition of Systech
Insights in which we share our expertise and opinions on a range of topical issues.
Stephen Rayment and Mark Woodward-Smith
Group Managing Directors
The Principle of Cost Follows the event in Commercial ArbitrationOluwaseyi Bamigboye
The general principle and practice of ‘cost follows the event’ in arbitration is that the unsuccessful party in an arbitral proceedings shall pay all or substantial part of the arbitration and legal cost to the successful party as calculated by the arbitrator. This publication attempts a review of this principle and concludes with an outline of situations when cost will not necessarily follow the event.
Time Bars and their enforceability in English law EPC contractsEversheds Sutherland
The use of time bar clauses in standard form EPC contracts is common. How effective a tool are such clauses for managing contractors’ claims for extensions of time and additional payment, and what challenges will there be in enforcing a time bar clause?
10 Essentials For An Effective Construction ContractSarah Fox
An overview of the 10 aspects every contract for a construction works package (however large or small) needs to include to make it an effective tool.
These 10 essentials are the foundation to the 500-Word Contract (TM), developed as a basis for construction contracts in England/Wales. They are also a checklist for your own terms and conditions.
For more information go to www.500words.co.uk or send Sarah an email sarah@500words.co.uk
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Dr.Costas Sachpazis
Terzaghi's soil bearing capacity theory, developed by Karl Terzaghi, is a fundamental principle in geotechnical engineering used to determine the bearing capacity of shallow foundations. This theory provides a method to calculate the ultimate bearing capacity of soil, which is the maximum load per unit area that the soil can support without undergoing shear failure. The Calculation HTML Code included.
Overview of the fundamental roles in Hydropower generation and the components involved in wider Electrical Engineering.
This paper presents the design and construction of hydroelectric dams from the hydrologist’s survey of the valley before construction, all aspects and involved disciplines, fluid dynamics, structural engineering, generation and mains frequency regulation to the very transmission of power through the network in the United Kingdom.
Author: Robbie Edward Sayers
Collaborators and co editors: Charlie Sims and Connor Healey.
(C) 2024 Robbie E. Sayers
Student information management system project report ii.pdfKamal Acharya
Our project explains about the student management. This project mainly explains the various actions related to student details. This project shows some ease in adding, editing and deleting the student details. It also provides a less time consuming process for viewing, adding, editing and deleting the marks of the students.
Explore the innovative world of trenchless pipe repair with our comprehensive guide, "The Benefits and Techniques of Trenchless Pipe Repair." This document delves into the modern methods of repairing underground pipes without the need for extensive excavation, highlighting the numerous advantages and the latest techniques used in the industry.
Learn about the cost savings, reduced environmental impact, and minimal disruption associated with trenchless technology. Discover detailed explanations of popular techniques such as pipe bursting, cured-in-place pipe (CIPP) lining, and directional drilling. Understand how these methods can be applied to various types of infrastructure, from residential plumbing to large-scale municipal systems.
Ideal for homeowners, contractors, engineers, and anyone interested in modern plumbing solutions, this guide provides valuable insights into why trenchless pipe repair is becoming the preferred choice for pipe rehabilitation. Stay informed about the latest advancements and best practices in the field.
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
2. Lecture Contents
Types of Contracts.
FIDIC Claims, Dispute and Arbitration.
Types of Claims.
Claims Life Cycle.
Claim Analysis
Case Study
3.
4. CONSTRUCTION CONTRACTS
Classified by Method of Evaluating Contract Cost.
(التكلفة تقٌٌم حسب تصنٌف)
Classified by Method of Bidding.
(الطرح طرٌقة حسب تقٌٌم)
Special Contracts
5. Contract types according to
Contract Cost
1. Fixed Price Contracts الثابت السعر عقود
a) Lump Sum / Stipulated Price
b) Unit Price / Bill of Quantity (BOQ)
c) Fixed Price with Escalation / Price Adjustable
Day one Dollar one Escalation (Inflation)
Significant Increase Escalation
Delay Escalation
Escalation can be measured by
Index formula
Percentage
6. Contract types according to
Contract Cost
2. Cost Reimbursement Contracts المستردة التكلفة عقود
Sometimes called Cost Plus or Prim Cost
a) Cost Plus Fee
b) Cost Plus Percentage
c) Cost Plus percentage with guaranteed maximum
d) Cost plus percentage with guaranteed. max. with
bonus
e) Cost Plus target
7. Contract types according to
Method of Bidding
Competitive Contracts
Negotiated Contracts
Combination between Comptetivness and Negotiation
34. Life cycle of construction claims
1. Claim identification
2. Claim notification
3. Claim examination
4. Claim documentation
5. Claim presentation
6. Claim negotiation
35. Claim Identification
Construction claim identification involves the accurate
detection of a construction claim in time. This is the
critical and important stage of the claim process.
For example, some very strong deserved construction
claims are lost solely due to failure of identifying them.
36. Claim Notification
Construction claim notification means alerting the
other party of a potential problem in a manner that is
non adversarial.
This alert (notification) must be done with the Time
limit that is mentioned in the contract.
37. Claim Examination
Construction claim examination means to establish
the legal and factual basis on which the claim is to be
developed.
This stage involves also an accurate estimation of the
potential recovery.
This action has to be investigated by interviewing the
staff who will be working in the project. The primary
sources for claim examination could deal with project
files, video footage, memos, etc., that must be used to
prove the time and cost elements of the claim.
38. Claim Documentation
Construction claim documentation is the collection of
the hard facts that give the actual history of a
construction claim. A well-prepared defendant quickly
demolishes evidence and claim costs that are not
supported by accurate records.
The documented facts are the clue that holds the legal
framework together. If these are insufficient the claim
will not stick.
39. Claim Presentation
Construction claim presentation should be logically built
up, well organized, and factually convincing. Thus, a claim
should be written in a format that emphasizes the fact that
a contract requirement is breached.
A contractor must then demonstrate the resulting harms
which are caused by the owners’ acts. (Cox 1997) has
fittingly said that presentation preferred to be separated
into two, the entitlement and the quantum.
The former section should have the legal and factual basis
while the later should provide the estimated recovery of the
claim.
40. Claim Negotiation
According to (Easton 1989) a structured and proper
negotiation preparation includes:
ascertaining that all information is current and complete;
minimizing the scope of negotiation beforehand so that
insignificant points should not precipitate a violent argument
and disrupt progress;
knowing one’s weaknesses and trying to utilize weak points
by conceding them in return from the other party;
foreseeing problems; and
Anticipating the opposition’s next move.
There is a saying that ‘‘it is more important to be prepared
than to be right”
47. As-Planned versus As-Built
This method aims to compare the duration of an as-
planned activity on the program with the as-built duration
for that same activities on the as-built program. The
difference in time between these durations is taken as the
period of delay to which a Contractor is entitled to an
Extension of Time as a result of an excusable delay event.
Dr. Hesham Abdelkhalek 47
48. Selecting the suitable analysis method
Dr. Hesham Abdelkhalek 48
Accurate baseline
Accurate As-built
49. Selecting the suitable analysis method
Dr. Hesham Abdelkhalek 49
Accurate baseline
and Updates
Accurate baseline
and As-built
50.
51. PEC-EG-11012 51
THERMAL POWER PLANT
UNITS 6&7 - 2X650 MW GAS/OIL FIRED UNITS
INTAKE, DISCHARGE AND RELATED WORKS
POSITION PAPER
In respect of
THE ENTITLEMENT FOR EXTENSION OF TIME
52. no Event start
1 Site Mobilization Allocation and bechmarks 5-Oct-09
2 Re-rout of gas pipelines 6-Sep-09
3 Providing Offshore permit 6-Sep-09
4 Off Site Area 30-Dec-09
5 protection plane approval for Dewatering 16-Mar-10
6 permanent cofferdam soil investigation 30-Jun-10
7 Excavation of Intake Pipes 12-Jul-10
8 Stopping work due to Petroleum company helicopter runway 29-Sep-10
9 25 Jan force majour 28-Jan-11
10 Fuel Shortage (May 2011) 11-May-11
11 Site Close Off 15-Jun-11
12 Contaminated Discharge Water 21-Jul-11
13 Intake Filling Delay 18-Aug-11
14 Disturbance of off-shore works 27-Aug-11
15 Bad Weather Conditions 10-Dec-11
16 Fuel Shortage (Jan 2012) 22-Jan-12
17 CP-102 Caused Delays fragmented
18 Truck Drivers Strike 9 Dec 11
PEC-EG-11012 52
Major Events
New events marked
54. Off-site area delivery
Activities
Affected
Affect directly on delivery of RCC pipes activity (SUBMT00020
& SUBMT00030) which effect directly on Installing of
Discharge pipes (1000001681) in discharge area and Start
Construction of intake basin & inlet pipes (1000000530) in54PEC-EG-11012
55. Re-rout of gas pipelines
Activities Affected Earth work for rough grading activity (SPECS00250)
that leads to channel (1-4) diversion activities and
cause delay of discharge and intake area. 55
16” gas pipeline
24” gas pipeline
PEC-EG-11012
57. protection plan approval for Dewatering
Activities Affected Mobilization of dewatering equipment activity
(1000000900) which is the first activity in Diversion
Channel (1-4) on critical path. 57PEC-EG-11012
58. Stoppage due to petroleum company helicopter runway
• Affect directly on the
production all discharge
structure activities that starts in
(Start Const. of the new Disch
& Seal Well) milestone
(1000000460).
• After the stoppage ends
WDEPC Project instructed AC
should reduce its working
hours from (63-hours per week)
to (31 hours per week) from
(Saturday to Thursday).
• Accordingly, AC worked on reduced productivity, based on the
work was not continuous.
58PEC-EG-11012
59. 25th January force Majeure.
Full Stoppage:
The work at job site was completely suspended from 28th of
Jan 2011 till 16th of Feb 2011.
This suspension affected All in progress activities in February
update.
Curfew Effect:
The curfew was imposed by the supreme council of the
military after the uprising event.
Impact on supplies: The delivery of earth products as sand,
gravel, stones….etc. are usually taken place from late evening
to early morning hours.
Curfew Impact from 16 Feb till end of June that made
disruption of work
59PEC-EG-11012
61. W1 start W1 PCD W1 imp PCD
EOT
Entitlement = 47 days
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 6-Sep-09 18-Mar-11
Window
End W2 17-Jan-10 28-Jun-10
Impacted
Programme
(W1 with events – DD is
as W1) 6-Sep-09 4-May-11
47 0 7
Events:
• Off-site area delivery
• Re-rout of gas pipelines
• Providing Offshore permit
• Providing site benchmark
• Site Mobilization allocation
Project
Duration
Period 1: from Sep 2009 (project start) to Jan 2010
Site Mobilization allocation
61
EOT Entailment = W1 Impacted PCD
- W1 PCD
Mitigation= W1 Impacted PCD – W2
PCD
Non Progress = W2 PCD - W1
Impacted PCD
62. W1 start W1 imp PCD
Non-Progress= 7
days
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 6-Sep-09 18-Mar-11
Window
End W2 17-Jan-10 28-Jun-10
Impacted
Programme
(W1 with events – DD is
as W1) 6-Sep-09 4-May-11
47 0 7
Events:
• Off-site area delivery
• Re-rout of gas pipelines
• Providing Offshore permit
• Providing site benchmark
• Site Mobilization allocation
Project
Duration
Period 1: from Sep 2009 (project start) to Jan 2010
W2 PCD
Site Mobilization allocation
62
EOT Entailment = W1 Impacted PCD
- W1 PCD
Mitigation= W1 Impacted PCD – W2
PCD
Non Progress = W2 PCD - W1
Impacted PCD
63. W1 start W1 PCD W1 imp PCD
EOT
Entitlement = 10
days
Events:
• Off-site area delivery
• Re-rout of gas pipelines
• Providing offshore permit
Project
Duration
Period 2: from Jan 2010 to Feb 2010
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 17-Jan-10 11-May-11
Window
End W2 7-Feb-10 1-Jun-11
Impacted
Programme
(W1 with events – DD is
as W1) 17-Jan-10 21-May-11 10 0 11
Re-rout of gas pipeline
63
EOT Entailment = W1 Impacted PCD
- W1 PCD
Mitigation= W1 Impacted PCD – W2
PCD
Non Progress = W2 PCD - W1
Impacted PCD
64. Events:
• Off-site area delivery
• Re-rout of gas pipelines
• Providing offshore permit
Period 2: from Jan 2010 to Feb 2010
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 17-Jan-10 11-May-11
Window
End W2 7-Feb-10 1-Jun-11
Impacted
Programme
(W1 with events – DD is
as W1) 17-Jan-10 21-May-11 10 0 11
W1 start W1 imp PCD
Non-Progress= 11
days
Project
Duration
W2 PCD
Re-rout of gas pipeline
64
65. W1 start
W1 PCD
W1 imp PCD
EOT
Entitlement = 0
days
Events:
• Off-site area delivery
• Re-rout of gas pipelines
• Providing offshore permit
Project
Duration
Period 3: from Feb 2010 to Mar 2010
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 7-Feb-10 1-Jun-11
Window
End W2 7-Mar-10 18-May-11
Impacted
Programme
(W1 with events – DD is
as W1) 7-Feb-10 1-Jun-11 0 14 0
65
66. Events:
• Off-site area delivery
• Re-rout of gas pipelines
• Providing offshore permit
Period 3: from Feb 2010 to Mar 2010
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 7-Feb-10 1-Jun-11
Window
End W2 7-Mar-10 18-May-11
Impacted
Programme
(W1 with events – DD is
as W1) 7-Feb-10 1-Jun-11 0 14 0
W1 start W1 PCD
Mitigation= 14
days
Project
Duration
W2 PCD
66
EOT Entailment = W1 Impacted PCD
- W1 PCD
Mitigation= W1 Impacted PCD – W2
PCD
Non Progress = W2 PCD - W1
Impacted PCD
67. W1 start
W1 PCD
W1 imp PCD
EOT
Entitlement = 0
days
Events:
• Off-site area delivery
• protection plan approval for
Dewatering
Project
Duration
Period 4: from Mar 2010 to Apr 2010
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 7-Mar-10 18-May-11
Window
End W2 11-Apr-10 11-Jun-11
Impacted
Programme
(W1 with events – DD is
as W1) 7-Mar-10 18-May-11 0 0 24
67
68. Events:
• Off-site area delivery
• protection plan approval for
Dewatering
Period 4: from Mar 2010 to Apr 2010
W1 start W1 PCD
Non-progress = 24
days
Project
Duration
W2 PCD
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 7-Mar-10 18-May-11
Window
End W2 11-Apr-10 11-Jun-11
Impacted
Programme
(W1 with events – DD is
as W1) 7-Mar-10 18-May-11 0 0 24
68
69. W1 start W1 PCD W1 imp PCD
EOT
Entitlement = 27
days
Events:
• protection plan approval for
Dewatering
Project
Duration
Period 5: from Apr 2010 to Jun 2010
protection plan approval
for Dewatering
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 11-Apr-10 11-Jun-11
Window
End W2 6-Jun-10 28-May-11
Impacted
Programme
(W1 with events – DD is
as W1) 11-Apr-10 8-Jul-11 27 41 0
69
70. Events:
• protection plan approval for
Dewatering
Period 5: from Apr 2010 to Jun 2010
W1 start W1 imp PCD
Mitigation= 41
days
Project
Duration
W2 PCD
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 11-Apr-10 11-Jun-11
Window
End W2 6-Jun-10 28-May-11
Impacted
Programme
(W1 with events – DD is
as W1) 11-Apr-10 8-Jul-11 27 41 0
protection plan approval
for Dewatering
70
71. W1 start
W1 PCD
W1 imp PCD
EOT
Entitlement = 0
days
Events:
• protection plan approval for
Dewatering
Project
Duration
Period 6: from Jun 2010 to July 2010
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 6-Jun-10 28-May-11
Window
End W2 4-Jul-10 13-Jun-11
Impacted
Programme
(W1 with events – DD is
as W1) 6-Jun-10 28-May-11 0 0 16
71
72. Events:
• protection plan approval for
Dewatering
Period 6: from Jun 2010 to July 2010
W1 start W1 PCD
Non-progress = 16
days
Project
Duration
W2 PCD
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 6-Jun-10 28-May-11
Window
End W2 4-Jul-10 13-Jun-11
Impacted
Programme
(W1 with events – DD is
as W1) 6-Jun-10 28-May-11 0 0 16
72
73. Events:
• protection plan approval for
Dewatering
• Excavation of Intake Pipes
Period 7: from July 2010 to Aug 2010
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 4-Jul-10 13-Jun-11
Window
End W2 1-Aug-10 19-Jun-11
Impacted
Programme
(W1 with events – DD is
as W1) 4-Jul-10 13-Jun-11 0 0 6
73
W1 start W1 imp PCD
EOT= 6 days
Project
Duration
W2 PCD
Excavation of Intake Pipes
74. Events:
• protection plan approval for
Dewatering
• Excavation of Intake Pipes
Period 7: from July 2010 to Aug 2010
W1 start W1 PCD
Non-progress = 6
days
Project
Duration
W2 PCD
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 4-Jul-10 13-Jun-11
Window
End W2 1-Aug-10 19-Jun-11
Impacted
Programme
(W1 with events – DD is
as W1) 4-Jul-10 13-Jun-11 0 0 6
74
75. W1 start W1 PCD W1 imp PCD
EOT
Entitlement = 19
days
Events:
• protection plan approval for
Dewatering
• Stoppage due to petroleum
company helicopter runway
Project
Duration
Period 8: from Aug 2010 to Sep 2010
protection plan approval
for Dewatering
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 1-Aug-10 19-Jun-11
Window
End W2 19-Sep-10 24-Jul-11
Impacted
Programme
(W1 with events – DD is
as W1) 1-Aug-10 8-Jul-11 19 0 16
75
76. Events:
• protection plan approval for
Dewatering
• Stoppage due to petroleum
company helicopter runway
Period 8: from Aug 2010 to Sep 2010
W1 start W1 imp PCD
Non-Progress= 16
days
Project
Duration
W2 PCD
protection plan approval
for Dewatering
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 1-Aug-10 19-Jun-11
Window
End W2 19-Sep-10 24-Jul-11
Impacted
Programme
(W1 with events – DD is
as W1) 1-Aug-10 8-Jul-11 19 0 16
76
77. Events:
• Complete work suspension
from 28th of January to 16th
Feb
• Curfew Impact from 16 Feb till
end of June
• Fuel Shortage (May 2011)
• Site Close Off
Period 9: from Jan 2011 to Jun 2011
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 28-Jan-11 26-May-12
Window
End W2 30-Jun-11 11-May-12
Impacted
Programme
(W1 with events – DD is
as W1) 28-Jan-11 24-Jul-12 59 74 0
77
W1 start W1 imp PCD
Project
Duration
Complete work suspension
from 28th of January to 16th
Feb Curfew Impact from
16 Feb till end of June
EOT =59 days
W2 PCD
Fuel Shortage (May 2011)
Site Close Off
78. Events:
• Complete work suspension
from 28th of January to 16th
Feb
• Curfew Impact from 16 Feb till
end of June
• Fuel Shortage (May 2011)
• Site Close Off
Period 9: from Jan 2011 to Jun 2011
W1 start W1 imp PCD
Project
Duration
Complete work suspension
from 28th of January to 16th
Feb Curfew Impact from
16 Feb till end of June
Mitigation =74
W2 PCD
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 28-Jan-11 26-May-12
Window
End W2 30-Jun-11 11-May-12
Impacted
Programme
(W1 with events – DD is
as W1) 28-Jan-11 24-Jul-12 59 74 0
78
Fuel Shortage (May 2011)
Site Close Off
79. Events:
• Contaminated Discharge
Water
• Intake Filling Delay
• Disturbance of off-shore works
• CP-102 Caused Delays
• Truck Drivers Strike
Period 10: from Jun 2011 to Oct 2011
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 30-June-11 11-May-12
Window
End W2 30-Oct-11 15-Jul-12
Impacted
Programme
(W1 with events – DD is
as W1) 30-June-11 11-May-12 0 0 65
79
W1 start W1 imp PCD
Project
Duration
EOT =32 days
W2 PCD
• Intake Filling Delay
• CP-102 Caused Delays
• Disturbance of off-shore works
• Contaminated Discharge Water
• Truck Drivers Strike
80. Period 10: from Jun 2011 to Oct 2011
W1 start W1 PCD
Non-progress = 12
W2 PCD
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 30-June-11 11-May-12
Window
End W2 30-Oct-11 15-Jul-12
Impacted
Programme
(W1 with events – DD is
as W1) 30-June-11 11-May-12 0 0 65
80
Events:
• Contaminated Discharge
Water
• Intake Filling Delay
• Disturbance of off-shore works
• CP-102 Caused Delays
• Truck Drivers Strike
• Intake Filling Delay
• CP-102 Caused Delays
• Disturbance of off-shore works
• Contaminated Discharge Water
• Truck Drivers Strike
81. Period 11: from Oct 2011 to Mar 2011
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 30-June-11 11-May-12
Window
End W2 30-Oct-11 15-Jul-12
Impacted
Programme
(W1 with events – DD is
as W1) 30-June-11 11-May-12 0 0 65
81
W1 start W1 imp PCD
Project
Duration
EOT =12days
W2 PCD
Events:
• Bad Weather Conditions
• Fuel Shortage (Jan 2012)
• Fuel Shortage (Jan 2012)
• Bad Weather Conditions
82. W1 start W1 PCD
Non-progress = 12
days
W2 PCD
Programmes
DATA
DATE PCD
EOT
Entailment Mitigation
Non
Progress
Window
Start W1 30-June-11 11-May-12
Window
End W2 30-Oct-11 15-Jul-12
Impacted
Programme
(W1 with events – DD is
as W1) 30-June-11 11-May-12 0 0 65
82
Events:
• Bad Weather Conditions
• Fuel Shortage (Jan 2012)
Period 11: from Oct 2011 to Mar 2011
• Fuel Shortage (Jan 2012)
• Bad Weather Conditions
83. 83
Total EOT Entitlement
Stage Period
EOT
Mitigation
Non
ProgressEntailment
One
1 47 0 7
2 10 0 11
3 0 14 0
4 0 0 24
5 27 41 0
6 0 0 16
7 0 0 6
8 19 0 16
Two
9 59 74 0
10 0 0 65
Sum 162 129 145