SCHEDULING COMMUNITY OF PRACTICE




                    Scheduling Excellence Initiative
                                        Featuring
    SEI
Scheduling
Excellence
                       Early Completion Schedules
 Initiative

                                          Chris Carson, PSP
                                  Corporate Director of Project Controls
                                           Alpha Corporation
                                  Chris.carson@alphacorporation.com
                                             757-342-5524
SEI Update
   SCHEDULING COMMUNITY OF PRACTICE



                • Best Practices & Guidelines for Scheduling
                    – Releasing first draft to start peer review
                    – Available at 2011 Annual Meeting
                    – Goal is to complete by end of 2011
    SEI
Scheduling      • Best Practices & Guidelines for Schedule
Excellence        Impact Analysis, Volume 1
 Initiative         – Producing work product
                    – Need volunteers to help develop topics
                    – Goal is to release peer review draft end of 2012
                • Joint Collaborative Project with AACEi
                    – Developing study - Quality Control Metrics
                          Percentage of CP activities, Ratio of relationships to
                          activities, etc.                 PMI College of Scheduling
                              “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                                                                                                       2
SEI Update
   SCHEDULING COMMUNITY OF PRACTICE



                • Best Practices & Guidelines for Scheduling
                    – Copy of Table of Contents available on SCoP
                      website – “Share – Documents – Document
                      Exchange – Documents – SEI – SM”
    SEI             – “2010-06-04 BPG Volume 1 Final Outline”
Scheduling
Excellence
                • Best Practices & Guidelines for Schedule
 Initiative       Impact Analysis
                    – Copy of Table of Contents available on SCoP
                      website – “Share – Documents – Document
                      Exchange – Documents – SEI – SIA”
                    – “2008-03-01 SIA Outline – Volume I”
                    – “2008-04-30 SIA Outline – Volume II” (future effort)

                                                           PMI College of Scheduling
                              “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                                                                                                       3
SEI Publications
   SCHEDULING COMMUNITY OF PRACTICE

                     PMI College of Scheduling


                    Best Practices
                    & Guidelines



                     Volume I
                     Project Planning
    SEI              And Scheduling

Scheduling
Excellence
 Initiative
Best Practices & Guidelines
   SCHEDULING COMMUNITY OF PRACTICE



                • Topic authors and reviewers must answer six
                  basic questions about each topic:
                    – Definition
                          What is it?
    SEI             – Purpose
Scheduling
                          Why is it used?
Excellence
 Initiative         – Default Condition
                          When & under what conditions is it used?
                    – Best Practices
                          What are acceptable implementations?
                    – Recommended Practice
                          Is there a preferred implementation?
                    – Admonitions & Advisories
                          What should be avoided?                    5
SEI Update
   SCHEDULING COMMUNITY OF PRACTICE



                • SEI Core Team
                    – Chris Carson, Managing Director, SEI
                    – Pete Oakander, Deputy Director, SEI
                    – Craig Relyea, Editorial Team Leader, SEI
    SEI
Scheduling      • Best Practices & Guidelines for Scheduling
Excellence          – Laura Williams, Volume Manager
 Initiative         – Recipient of the 2011 award for “Contribution to
                      College of Scheduling/SCoP”
                • Best Practices and Guidelines for Schedule
                  Impact Analysis
                    – Mark Sanders, Volume Co-Manager
                    – Mark Nagata, Volume Co-Manager
                                                           PMI College of Scheduling
                              “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                                                                                                       6
Early Completion Schedules
   SCHEDULING COMMUNITY OF PRACTICE



                   Copies of the Early Completion Schedules
                   draft documents available on website
                      “Share – Documents – Document Exchange – Documents –
                      SEI Webinar BPG Topics

    SEI            Early Completion Schedules
Scheduling            Defined as submission of an as-planned schedule
Excellence            showing earlier completion than contractually
 Initiative
                      mandated
                   Early Completion Schedules
                      Inadvertent
                      Intentional



                                                           PMI College of Scheduling
                              “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                                                                                                       7
Early Completion Schedules
   SCHEDULING COMMUNITY OF PRACTICE



                      Inadvertent Early Completion Schedules
                          Usually not done intentionally
                          May be missing scope
                          May be rushed and just not finished
    SEI                   May not have involved full PM team
Scheduling                Not done for a specific reason
Excellence
 Initiative           Intentional Early Completion Schedules
                          Developed to minimize time on project
                          Developed to provide a “buffer” for completion
                          Expects to be allowed to complete early
                          Expects to be paid extended GC for owner delays
                          from early date, not just contract completion date
                          May or may not provide notification of intent to finish
                          early
                                                           PMI College of Scheduling
                              “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                                                                                                       8
Early Completion Schedules
   SCHEDULING COMMUNITY OF PRACTICE



                   Inadvertent Early Completion Schedules
                      Owner perspective
                        Should prompt careful review
                              Verify reasonableness
    SEI                       Verify full scope of work
Scheduling                    Verify inclusion of all non-work activities that might
Excellence                    drive the schedule
 Initiative                   Determine if schedule represents full PM team
                              participation
                              Verify resource planning and logic/sequencing
                              Verify inclusion of reasonable weather planning
                              Determine use of risk management
                              Review coordination and owner-responsible activities
                              carefully


                                                           PMI College of Scheduling
                              “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                                                                                                       9
Early Completion Schedules
   SCHEDULING COMMUNITY OF PRACTICE



                   Inadvertent Early Completion Schedules
                      Owner perspective
                        Share review results with contractor
                        Recommend revision to accommodate missing
    SEI                 items
Scheduling
                        Once contractor has verified quality control and
Excellence
 Initiative             reasonable schedule, resubmission still
                        requires careful secondary review
                        Generally when owner questions contractor’s
                        schedule, providing feedback in detail, revised
                        schedule consumes more of the project
                        duration


                                                           PMI College of Scheduling
                              “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                                                                                                       10
Early Completion Schedules
   SCHEDULING COMMUNITY OF PRACTICE



                   Inadvertent Early Completion Schedules
                      Contractor perspective
                         Should prompt careful QC review
                              Verify resource planning and logic/sequencing
    SEI                       Verify inclusion of reasonable weather planning
Scheduling                    Ensure use of risk management, particularly
Excellence                    identifying high risk activities and processes
 Initiative                   Provide careful Written Narrative to ensure that all
                              assumptions and requirements of the owner are
                              identified
                          Schedule should provide reasonable expectation of
                          meeting project milestones, not overly optimistic or
                          pessimistic
                          Revise as necessary and submit

                                                           PMI College of Scheduling
                              “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                                                                                                       11
Early Completion Schedules
   SCHEDULING COMMUNITY OF PRACTICE



                   Intentional Early Completion Schedules
                      Owner perspective
                        Proactive steps
                              Address in contract documents
    SEI                                    Require as-planned schedule shows contractual
Scheduling                                 completion
Excellence                                 Require constraint on contractual milestones
 Initiative                                Forbid float in as-planned schedule
                                           Simply state that early completion schedules will
                                           not be accepted
                                           Provide change order to reduce the contractual
                                           completion to the early completion date
                                           Allow a contingency activity prior to Substantial
                                           Completion – mandate joint ownership of
                                           contingency time (float)
                                           Provide incentive contingency activity
                                                           PMI College of Scheduling         12
                              “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Early Completion Schedules
   SCHEDULING COMMUNITY OF PRACTICE



                   Intentional Early Completion Schedules
                      Owner perspective
                        Raises specific risks
                              Check to see that schedule does not impose
    SEI                       additional requirements on owner
                                           Short review times
Scheduling
                                           Early equipment delivery
Excellence
                                           Other project coordination issues
 Initiative
                              Owner will pick up maintenance and operating
                              charges from early completion date
                              End user might have to occupy early
                              Salaries will start early
                              Third party coordination may be more difficult
                              If the early completion schedule is too aggressive,
                              there is uncertainty in completion predictions

                                                           PMI College of Scheduling
                              “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                                                                                                       13
Early Completion Schedules
   SCHEDULING COMMUNITY OF PRACTICE



                   Intentional Early Completion Schedules
                      Owner perspective
                        Legal risks may occur
                              Failure to notify and/or spec language
    SEI                       precluding early completion may not be an
Scheduling                    absolute bar to damages recovery when owner
Excellence                    causes delays
 Initiative




                                                           PMI College of Scheduling
                              “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                                                                                                       14
Early Completion Schedules
   SCHEDULING COMMUNITY OF PRACTICE



                   Intentional Early Completion Schedules
                      Contractor perspective
                         Contractor needs to identify true need for early
                         completion schedule
    SEI                       Due to limited general conditions costs, should
Scheduling                    document and follow early completion requirements
Excellence                    Due to attempt to limit risk of late completion, should
 Initiative                   discuss with owner and negotiate some buffer solution
                              Due to limited resource availability, verify and choose
                              solution to support the risk
                          With true need identified, contractor can take
                          measures to limit risks




                                                           PMI College of Scheduling
                              “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                                                                                                       15
Early Completion Schedules
   SCHEDULING COMMUNITY OF PRACTICE



                   Intentional Early Completion Schedules
                      Contractor perspective
                         Owner ability to simply move completion date to
                         early completion schedule date could result in
    SEI                  liquidated damages based on early date
Scheduling               Float will likely still belong to project so owner-
Excellence               responsible changes might use up float
 Initiative
                              Contractor could be required to stay on project beyond
                              early completion date to handle changes with no
                              additional general conditions costs
                          This is still a risk with good production when the
                          project is ahead of schedule – owner changes could
                          still force contractor to remain on job
                              But bid would have included full term GC costs

                                                           PMI College of Scheduling
                              “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                                                                                                       16
Early Completion Schedules
   SCHEDULING COMMUNITY OF PRACTICE



                   Intentional Early Completion Schedules
                      Contractor perspective
                         In order to recover damages from delayed early
                         completion, contractor must show:
    SEI                       Always intended to finish early
Scheduling                    Had the ability to finish early
Excellence                    Would have finished early but for owner actions
 Initiative               Without these conditions, contractor likely will not
                          prevail with an early completion claim in litigation
                          Could also notify owner that project was bid with only
                          general conditions for the early completion duration
                          Jurisdictional differences in litigation make resolution
                          uncertain for both parties
                          Ownership of float could be problematic if owner
                          attempts to retain
                                                           PMI College of Scheduling
                              “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                                                                                                       17
Early Completion Schedules
   SCHEDULING COMMUNITY OF PRACTICE



                   Intentional Early Completion Schedules
                      General recommendations
                          Quality of as-planned schedule must be validated
                          before deciding on ability to finish early
    SEI                   Risk management should be incorporated into
Scheduling                schedule to raise the probability of meeting
Excellence                scheduled completion
 Initiative               Both parties should negotiate early completion
                              Look at contingency options to provide some
                              protection
                              Adjust contractual completion date
                                           If conditions work for owner, agree, and adjust
                                           contractual completion to early date
                                           If contractor is comfortable about schedule predictions,
                                           agree to adjust contractual completion


                                                           PMI College of Scheduling
                              “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                                                                                                       18
SEI Best Practices and
                             Guidelines for Scheduling
   SCHEDULING COMMUNITY OF PRACTICE



                • Plans for published volume
                    – Working to get universities that provide CM
                      education involved with peer review
                    – Plan to get copies into CM education departments
    SEI               as reference book
Scheduling          – Goal is to have volume reviewed, correlated, and
Excellence            published by 2012
 Initiative
                • Opportunities for volunteers
                    – BP&G for Scheduling
                          Develop remaining work product
                          Opportunities for peer review
                    – BP&G for Schedule Impact Analysis
                          Develop primary work product
                          Influence best practice recommendations    19
Early Completion Schedules
   SCHEDULING COMMUNITY OF PRACTICE



                                                        Questions?

                                       Recommendations?
    SEI
Scheduling                                           War Stories?
Excellence
 Initiative
                                                               Gripes?




                                                           PMI College of Scheduling
                              “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                                                                                                       20
SCHEDULING COMMUNITY OF PRACTICE


                              BP&G for Scheduling
                        Early Completion Schedules
    SEI
Scheduling                                                Chris Carson, PSP
Excellence                         Corporate Director of Project Controls
 Initiative                                 Alpha Corporation
                                    101 West Main Street, Suite 7100
                                            Norfolk, VA 23510
                                           757-533-9368 Office
                                           757-342-5524 Mobile
                                   Chris.carson@alphacorporation.com


                                                           PMI College of Scheduling
                              “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
                                                                                                                       21

Early Completion Schedules

  • 1.
    SCHEDULING COMMUNITY OFPRACTICE Scheduling Excellence Initiative Featuring SEI Scheduling Excellence Early Completion Schedules Initiative Chris Carson, PSP Corporate Director of Project Controls Alpha Corporation Chris.carson@alphacorporation.com 757-342-5524
  • 2.
    SEI Update SCHEDULING COMMUNITY OF PRACTICE • Best Practices & Guidelines for Scheduling – Releasing first draft to start peer review – Available at 2011 Annual Meeting – Goal is to complete by end of 2011 SEI Scheduling • Best Practices & Guidelines for Schedule Excellence Impact Analysis, Volume 1 Initiative – Producing work product – Need volunteers to help develop topics – Goal is to release peer review draft end of 2012 • Joint Collaborative Project with AACEi – Developing study - Quality Control Metrics Percentage of CP activities, Ratio of relationships to activities, etc. PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc. 2
  • 3.
    SEI Update SCHEDULING COMMUNITY OF PRACTICE • Best Practices & Guidelines for Scheduling – Copy of Table of Contents available on SCoP website – “Share – Documents – Document Exchange – Documents – SEI – SM” SEI – “2010-06-04 BPG Volume 1 Final Outline” Scheduling Excellence • Best Practices & Guidelines for Schedule Initiative Impact Analysis – Copy of Table of Contents available on SCoP website – “Share – Documents – Document Exchange – Documents – SEI – SIA” – “2008-03-01 SIA Outline – Volume I” – “2008-04-30 SIA Outline – Volume II” (future effort) PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc. 3
  • 4.
    SEI Publications SCHEDULING COMMUNITY OF PRACTICE PMI College of Scheduling Best Practices & Guidelines Volume I Project Planning SEI And Scheduling Scheduling Excellence Initiative
  • 5.
    Best Practices &Guidelines SCHEDULING COMMUNITY OF PRACTICE • Topic authors and reviewers must answer six basic questions about each topic: – Definition What is it? SEI – Purpose Scheduling Why is it used? Excellence Initiative – Default Condition When & under what conditions is it used? – Best Practices What are acceptable implementations? – Recommended Practice Is there a preferred implementation? – Admonitions & Advisories What should be avoided? 5
  • 6.
    SEI Update SCHEDULING COMMUNITY OF PRACTICE • SEI Core Team – Chris Carson, Managing Director, SEI – Pete Oakander, Deputy Director, SEI – Craig Relyea, Editorial Team Leader, SEI SEI Scheduling • Best Practices & Guidelines for Scheduling Excellence – Laura Williams, Volume Manager Initiative – Recipient of the 2011 award for “Contribution to College of Scheduling/SCoP” • Best Practices and Guidelines for Schedule Impact Analysis – Mark Sanders, Volume Co-Manager – Mark Nagata, Volume Co-Manager PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc. 6
  • 7.
    Early Completion Schedules SCHEDULING COMMUNITY OF PRACTICE Copies of the Early Completion Schedules draft documents available on website “Share – Documents – Document Exchange – Documents – SEI Webinar BPG Topics SEI Early Completion Schedules Scheduling Defined as submission of an as-planned schedule Excellence showing earlier completion than contractually Initiative mandated Early Completion Schedules Inadvertent Intentional PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc. 7
  • 8.
    Early Completion Schedules SCHEDULING COMMUNITY OF PRACTICE Inadvertent Early Completion Schedules Usually not done intentionally May be missing scope May be rushed and just not finished SEI May not have involved full PM team Scheduling Not done for a specific reason Excellence Initiative Intentional Early Completion Schedules Developed to minimize time on project Developed to provide a “buffer” for completion Expects to be allowed to complete early Expects to be paid extended GC for owner delays from early date, not just contract completion date May or may not provide notification of intent to finish early PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc. 8
  • 9.
    Early Completion Schedules SCHEDULING COMMUNITY OF PRACTICE Inadvertent Early Completion Schedules Owner perspective Should prompt careful review Verify reasonableness SEI Verify full scope of work Scheduling Verify inclusion of all non-work activities that might Excellence drive the schedule Initiative Determine if schedule represents full PM team participation Verify resource planning and logic/sequencing Verify inclusion of reasonable weather planning Determine use of risk management Review coordination and owner-responsible activities carefully PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc. 9
  • 10.
    Early Completion Schedules SCHEDULING COMMUNITY OF PRACTICE Inadvertent Early Completion Schedules Owner perspective Share review results with contractor Recommend revision to accommodate missing SEI items Scheduling Once contractor has verified quality control and Excellence Initiative reasonable schedule, resubmission still requires careful secondary review Generally when owner questions contractor’s schedule, providing feedback in detail, revised schedule consumes more of the project duration PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc. 10
  • 11.
    Early Completion Schedules SCHEDULING COMMUNITY OF PRACTICE Inadvertent Early Completion Schedules Contractor perspective Should prompt careful QC review Verify resource planning and logic/sequencing SEI Verify inclusion of reasonable weather planning Scheduling Ensure use of risk management, particularly Excellence identifying high risk activities and processes Initiative Provide careful Written Narrative to ensure that all assumptions and requirements of the owner are identified Schedule should provide reasonable expectation of meeting project milestones, not overly optimistic or pessimistic Revise as necessary and submit PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc. 11
  • 12.
    Early Completion Schedules SCHEDULING COMMUNITY OF PRACTICE Intentional Early Completion Schedules Owner perspective Proactive steps Address in contract documents SEI Require as-planned schedule shows contractual Scheduling completion Excellence Require constraint on contractual milestones Initiative Forbid float in as-planned schedule Simply state that early completion schedules will not be accepted Provide change order to reduce the contractual completion to the early completion date Allow a contingency activity prior to Substantial Completion – mandate joint ownership of contingency time (float) Provide incentive contingency activity PMI College of Scheduling 12 “PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 13.
    Early Completion Schedules SCHEDULING COMMUNITY OF PRACTICE Intentional Early Completion Schedules Owner perspective Raises specific risks Check to see that schedule does not impose SEI additional requirements on owner Short review times Scheduling Early equipment delivery Excellence Other project coordination issues Initiative Owner will pick up maintenance and operating charges from early completion date End user might have to occupy early Salaries will start early Third party coordination may be more difficult If the early completion schedule is too aggressive, there is uncertainty in completion predictions PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc. 13
  • 14.
    Early Completion Schedules SCHEDULING COMMUNITY OF PRACTICE Intentional Early Completion Schedules Owner perspective Legal risks may occur Failure to notify and/or spec language SEI precluding early completion may not be an Scheduling absolute bar to damages recovery when owner Excellence causes delays Initiative PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc. 14
  • 15.
    Early Completion Schedules SCHEDULING COMMUNITY OF PRACTICE Intentional Early Completion Schedules Contractor perspective Contractor needs to identify true need for early completion schedule SEI Due to limited general conditions costs, should Scheduling document and follow early completion requirements Excellence Due to attempt to limit risk of late completion, should Initiative discuss with owner and negotiate some buffer solution Due to limited resource availability, verify and choose solution to support the risk With true need identified, contractor can take measures to limit risks PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc. 15
  • 16.
    Early Completion Schedules SCHEDULING COMMUNITY OF PRACTICE Intentional Early Completion Schedules Contractor perspective Owner ability to simply move completion date to early completion schedule date could result in SEI liquidated damages based on early date Scheduling Float will likely still belong to project so owner- Excellence responsible changes might use up float Initiative Contractor could be required to stay on project beyond early completion date to handle changes with no additional general conditions costs This is still a risk with good production when the project is ahead of schedule – owner changes could still force contractor to remain on job But bid would have included full term GC costs PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc. 16
  • 17.
    Early Completion Schedules SCHEDULING COMMUNITY OF PRACTICE Intentional Early Completion Schedules Contractor perspective In order to recover damages from delayed early completion, contractor must show: SEI Always intended to finish early Scheduling Had the ability to finish early Excellence Would have finished early but for owner actions Initiative Without these conditions, contractor likely will not prevail with an early completion claim in litigation Could also notify owner that project was bid with only general conditions for the early completion duration Jurisdictional differences in litigation make resolution uncertain for both parties Ownership of float could be problematic if owner attempts to retain PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc. 17
  • 18.
    Early Completion Schedules SCHEDULING COMMUNITY OF PRACTICE Intentional Early Completion Schedules General recommendations Quality of as-planned schedule must be validated before deciding on ability to finish early SEI Risk management should be incorporated into Scheduling schedule to raise the probability of meeting Excellence scheduled completion Initiative Both parties should negotiate early completion Look at contingency options to provide some protection Adjust contractual completion date If conditions work for owner, agree, and adjust contractual completion to early date If contractor is comfortable about schedule predictions, agree to adjust contractual completion PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc. 18
  • 19.
    SEI Best Practicesand Guidelines for Scheduling SCHEDULING COMMUNITY OF PRACTICE • Plans for published volume – Working to get universities that provide CM education involved with peer review – Plan to get copies into CM education departments SEI as reference book Scheduling – Goal is to have volume reviewed, correlated, and Excellence published by 2012 Initiative • Opportunities for volunteers – BP&G for Scheduling Develop remaining work product Opportunities for peer review – BP&G for Schedule Impact Analysis Develop primary work product Influence best practice recommendations 19
  • 20.
    Early Completion Schedules SCHEDULING COMMUNITY OF PRACTICE Questions? Recommendations? SEI Scheduling War Stories? Excellence Initiative Gripes? PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc. 20
  • 21.
    SCHEDULING COMMUNITY OFPRACTICE BP&G for Scheduling Early Completion Schedules SEI Scheduling Chris Carson, PSP Excellence Corporate Director of Project Controls Initiative Alpha Corporation 101 West Main Street, Suite 7100 Norfolk, VA 23510 757-533-9368 Office 757-342-5524 Mobile Chris.carson@alphacorporation.com PMI College of Scheduling “PMI” is a registered trade and service mark of the Project Management Institute, Inc. 21