SlideShare a Scribd company logo
Quantity Surveyor
INTRODUCTION TO CONSTRUCTION INDUSTRY
+
INTRODUCTION TO DRAWING
GROUP:
• CH’NG PHEI WOON(LEADER)
• CHRISTINA CHUA
• BOON LI YING
• ALISON TANG
• CHONG YI HUI
ASSIGNMENT 1
Mind Map
Definition of Quantity Surveyor
• Providing advices on
procurement, contracts and
project cost management.
• Work as consultants or be
employed by a contractor or sub-
contractor.
Quantity Surveyor Certified board
• The Board of Quantity Surveyors Malaysia was set up by an Act of
Parliament, i.e. Quantity Surveyors Act 1967 (revised 2002). The Board
consists of a President, a Registrar and sixteen (16) members appointed by
the Minister of Works, Malaysia.
• to approve or reject applications for registration or approval to practise
under this Act or to approve any such application subject to such conditions
or restrictions as it may deem fit to impose
• to order the issuance of a written warning or reprimand, the imposition of a
fine, suspension, cancellation, removal or reinstatement in accordance with
Part III and IV Quantity Surveyors Act
Scope of Work Handled by 

Quantity Surveyors
• Cost Planning
• To help the design team to
keep within the budget from
start to the end of the project
• Preliminary Cost Advice
•Give practical advice on
comparative costs of alternative
layouts, materials, components
& methods of construction.
•Contractual Methods
• Advise on the best form of contract
for a specific project.
•Tendering
•Calculating the cost and risk to
tender for the project.
• Choice of Contractor
• Quantity surveyor makes recommendation
of contractors base on past performances
to the employers.
•Valuation of Construction Work
•Quantity surveyor evaluates work
carried out before making certified
payment.
•Increase Efficiency
•Making sure that fairness
exists between employer
and contractors to make
work smoother and easier.
Responsibilities & Tasks at
Different Stages of Construction
• Monitor cost at different stages of project.
• Certify payment and invoices.
• Negotiating disputes.
• Advising on budgets and costs.
• Giving advice for disputes on contracts.
Daily Activities
Construction starts…
• Feasibility studies of a project
• Roughly estimate what’s involve in the project
(Measurement of Sketches)
• Study architects’ and engineers’ plans
• Identify cost and overall budget
(Value Engineering)
• Final detailed estimate is prepared by Quantity
Surveyor and Architect
•During Construction…
• Provide flow of cash data
• Can access cost effects when change of project occur
•After Construction…
•Quantity Surveyor prepare
statement of final account
(Records actual cost for all
sections of job)
Stages that involve in cost planning during
design and construction
Tender
Reconciliation
Comparing tender price
with final cost
Post-Contract Cost
Control
Controlling cost at different
stages of construction
Preliminary Estimate
Using research market price to
estimate
Cost Plan
Calculating project cost
according to elemental
analysis
Cost Check
Evaluating the work
done according to
cost
TYPE

OF
Preliminary Drawing
DRAWING
Tender Drawing
Contract
Drawing
AS-Built
Drawing
Preliminary Drawing
• A rough design with less detail
• Estimate the budget of a project
• Can be used to prepared cost plan
Tender Drawing
• A complete design with full details by Architects
and Structural engineer
• Comprise of architectural and structural drawings
• Can be used to prepare Bills of Quantities
STRUCTURAL DRAWING
By Structural Engineer
Column
Beam
• Between 2 column
Slab
(Floor)
Structural Drawing by Structural Engineer
Architectural Drawingby Architect
Description &
material
rate
Measurement
Quantity
Total Cost
EXAMPLE OF BILLS OF QUANTITIES
Quantity Surveyors ‘Bible book’

SMM2
• Latest edition : SMM2
• SMM 1 Slightly different from
SMM2
• This book is guide for calculation
and format of BILLS OF
QUANTITIES
Contract Drawing
• Same drawing as tender drawings
Contract Drawing = Construction Drawing
Used to prepare contract document
Construction Drawing
As-Built Drawing
• A finalise drawing
Any changes in example Type of tile ,paint
Commonly by Clients or Architects

More Related Content

What's hot

Persons involved in tenders and contract
Persons involved in tenders and contractPersons involved in tenders and contract
Persons involved in tenders and contract
shiva prakash
 
Types of contract
Types of contractTypes of contract
Types of contract
HarshalNarkhede7
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture)
Muhammad Aljalali
 
Quantity Surveyor presentation
Quantity Surveyor presentationQuantity Surveyor presentation
Quantity Surveyor presentation
cynfang Fong
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
Dr K M SONI
 
Quantity Surveyors (Practice)
Quantity Surveyors (Practice)Quantity Surveyors (Practice)
Quantity Surveyors (Practice)
Unais Mohamed Aliyar
 
Quantity take off
Quantity take offQuantity take off
Quantity take off
Jawad Ahmad Baig
 
Construction Documents
Construction DocumentsConstruction Documents
Construction DocumentsAllan Berry
 
Measure And Pay Contract
Measure And Pay Contract Measure And Pay Contract
Measure And Pay Contract
Venuri Lakshani
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
srinivas2036
 
site report
site reportsite report
site report
dhirazain
 
Process of Building Construction
Process of Building ConstructionProcess of Building Construction
Process of Building Construction
AyushHajare
 
Tenders for construction
Tenders for constructionTenders for construction
Tenders for construction
gandrajuadityavarmagav
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in construction
MahSobeh
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise Building
David H Moloney
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction Contract
Avinash Kumar Gupta
 
Contracts
ContractsContracts
Contracts
krrish706
 
Construction phases
Construction phasesConstruction phases
Construction phases
Meesum Zaidi
 

What's hot (20)

Persons involved in tenders and contract
Persons involved in tenders and contractPersons involved in tenders and contract
Persons involved in tenders and contract
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture)
 
Quantity Surveyor presentation
Quantity Surveyor presentationQuantity Surveyor presentation
Quantity Surveyor presentation
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
 
Quantity Surveyors (Practice)
Quantity Surveyors (Practice)Quantity Surveyors (Practice)
Quantity Surveyors (Practice)
 
Quantity take off
Quantity take offQuantity take off
Quantity take off
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
Measure And Pay Contract
Measure And Pay Contract Measure And Pay Contract
Measure And Pay Contract
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
ACH 231 Lecture 07 (Contract Documents) Part 1
ACH 231 Lecture 07 (Contract Documents) Part 1ACH 231 Lecture 07 (Contract Documents) Part 1
ACH 231 Lecture 07 (Contract Documents) Part 1
 
site report
site reportsite report
site report
 
Process of Building Construction
Process of Building ConstructionProcess of Building Construction
Process of Building Construction
 
Tenders for construction
Tenders for constructionTenders for construction
Tenders for construction
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in construction
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise Building
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction Contract
 
Contracts
ContractsContracts
Contracts
 
Construction phases
Construction phasesConstruction phases
Construction phases
 

Similar to Quantity-Surveyor (ICI+ITD)-pdf.pdf

Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
LY97
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014
Felix Vong
 
Guc arct 702 legislations lecture 4 - project delivery process and business...
Guc arct 702 legislations   lecture 4 - project delivery process and business...Guc arct 702 legislations   lecture 4 - project delivery process and business...
Guc arct 702 legislations lecture 4 - project delivery process and business...
Galala University
 
Cjmconstructionconsultingpresentation 13086519950433-phpapp02-110621053129-ph...
Cjmconstructionconsultingpresentation 13086519950433-phpapp02-110621053129-ph...Cjmconstructionconsultingpresentation 13086519950433-phpapp02-110621053129-ph...
Cjmconstructionconsultingpresentation 13086519950433-phpapp02-110621053129-ph...
Neha V
 
QSS
QSSQSS
Qs(ici&itd) (1)
Qs(ici&itd) (1)Qs(ici&itd) (1)
Qs(ici&itd) (1)
Js Cheok
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
Jy Chong
 
Duties and job roles of QS.pptx
Duties and job roles of QS.pptxDuties and job roles of QS.pptx
Duties and job roles of QS.pptx
SagarKatole1
 
CJM Construction Consulting PowerPoint Presentation
CJM Construction Consulting PowerPoint PresentationCJM Construction Consulting PowerPoint Presentation
CJM Construction Consulting PowerPoint Presentation
Signature Paving & Sealcoating, Inc.
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
Sysy Jnthn
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
Timun Loh
 
FMA - 2_CM651_Group.pptx
FMA - 2_CM651_Group.pptxFMA - 2_CM651_Group.pptx
FMA - 2_CM651_Group.pptx
ArJayTambaoan
 
ITD Presentation
ITD PresentationITD Presentation
ITD Presentation
masonsth
 
Construction Stages and Construction Teams
Construction Stages and Construction TeamsConstruction Stages and Construction Teams
Construction Stages and Construction Teams
MOHDFIRRDHAUSBINMOHD
 
Ici itd qs project 1
Ici itd qs project 1Ici itd qs project 1
Ici itd qs project 1
Daniel Tan
 
ICI ITD QS PROJECT 1 (1).pptx
ICI ITD QS PROJECT 1 (1).pptxICI ITD QS PROJECT 1 (1).pptx
ICI ITD QS PROJECT 1 (1).pptxmkyong1996
 
CV Clive V2 180612 A
CV Clive V2 180612 ACV Clive V2 180612 A
CV Clive V2 180612 AClive Price
 

Similar to Quantity-Surveyor (ICI+ITD)-pdf.pdf (20)

Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014
 
Guc arct 702 legislations lecture 4 - project delivery process and business...
Guc arct 702 legislations   lecture 4 - project delivery process and business...Guc arct 702 legislations   lecture 4 - project delivery process and business...
Guc arct 702 legislations lecture 4 - project delivery process and business...
 
Cjmconstructionconsultingpresentation 13086519950433-phpapp02-110621053129-ph...
Cjmconstructionconsultingpresentation 13086519950433-phpapp02-110621053129-ph...Cjmconstructionconsultingpresentation 13086519950433-phpapp02-110621053129-ph...
Cjmconstructionconsultingpresentation 13086519950433-phpapp02-110621053129-ph...
 
QSS
QSSQSS
QSS
 
Qs(ici&itd) (1)
Qs(ici&itd) (1)Qs(ici&itd) (1)
Qs(ici&itd) (1)
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
 
Duties and job roles of QS.pptx
Duties and job roles of QS.pptxDuties and job roles of QS.pptx
Duties and job roles of QS.pptx
 
CJM Construction Consulting PowerPoint Presentation
CJM Construction Consulting PowerPoint PresentationCJM Construction Consulting PowerPoint Presentation
CJM Construction Consulting PowerPoint Presentation
 
Qsx
QsxQsx
Qsx
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
FMA - 2_CM651_Group.pptx
FMA - 2_CM651_Group.pptxFMA - 2_CM651_Group.pptx
FMA - 2_CM651_Group.pptx
 
ITD Presentation
ITD PresentationITD Presentation
ITD Presentation
 
The Architecture Profession
The Architecture ProfessionThe Architecture Profession
The Architecture Profession
 
Construction Stages and Construction Teams
Construction Stages and Construction TeamsConstruction Stages and Construction Teams
Construction Stages and Construction Teams
 
Ici itd qs project 1
Ici itd qs project 1Ici itd qs project 1
Ici itd qs project 1
 
ICI ITD QS PROJECT 1 (1).pptx
ICI ITD QS PROJECT 1 (1).pptxICI ITD QS PROJECT 1 (1).pptx
ICI ITD QS PROJECT 1 (1).pptx
 
CV Clive V2 180612 A
CV Clive V2 180612 ACV Clive V2 180612 A
CV Clive V2 180612 A
 
SANPPT
SANPPTSANPPT
SANPPT
 

More from Chong Yi Hui

btechcompiled.pdf
btechcompiled.pdfbtechcompiled.pdf
btechcompiled.pdf
Chong Yi Hui
 
BSCIENCE_REPORT_yihui-a4.pdf
BSCIENCE_REPORT_yihui-a4.pdfBSCIENCE_REPORT_yihui-a4.pdf
BSCIENCE_REPORT_yihui-a4.pdf
Chong Yi Hui
 
Comparative Analysis Essay Yi Hui.pdf
Comparative Analysis Essay Yi Hui.pdfComparative Analysis Essay Yi Hui.pdf
Comparative Analysis Essay Yi Hui.pdf
Chong Yi Hui
 
THEORIES_YIHUI.pdf
THEORIES_YIHUI.pdfTHEORIES_YIHUI.pdf
THEORIES_YIHUI.pdf
Chong Yi Hui
 
Yihui's pm final
Yihui's pm finalYihui's pm final
Yihui's pm final
Chong Yi Hui
 
Btechii-project2
Btechii-project2Btechii-project2
Btechii-project2
Chong Yi Hui
 
Btechii
BtechiiBtechii
Btechii
Chong Yi Hui
 
Studio report
Studio reportStudio report
Studio report
Chong Yi Hui
 
Slides for bscience ii
Slides for bscience iiSlides for bscience ii
Slides for bscience ii
Chong Yi Hui
 
Building science 2 report
Building science 2 reportBuilding science 2 report
Building science 2 report
Chong Yi Hui
 
Building technology report
Building technology reportBuilding technology report
Building technology report
Chong Yi Hui
 
ARC2625 REPORT FILE ChongYiHui0324404
ARC2625 REPORT FILE ChongYiHui0324404ARC2625 REPORT FILE ChongYiHui0324404
ARC2625 REPORT FILE ChongYiHui0324404
Chong Yi Hui
 
Building construction report
Building construction reportBuilding construction report
Building construction report
Chong Yi Hui
 
Final report
Final reportFinal report
Final report
Chong Yi Hui
 
Culture project-ii-finalized
Culture project-ii-finalizedCulture project-ii-finalized
Culture project-ii-finalized
Chong Yi Hui
 
Statitics
StatiticsStatitics
Statitics
Chong Yi Hui
 
English report
English report English report
English report
Chong Yi Hui
 
Social psychology project ii(comic)
Social psychology project ii(comic)Social psychology project ii(comic)
Social psychology project ii(comic)
Chong Yi Hui
 
Account assignment report finale(1)
Account assignment report finale(1)Account assignment report finale(1)
Account assignment report finale(1)
Chong Yi Hui
 

More from Chong Yi Hui (20)

btechcompiled.pdf
btechcompiled.pdfbtechcompiled.pdf
btechcompiled.pdf
 
BSCIENCE_REPORT_yihui-a4.pdf
BSCIENCE_REPORT_yihui-a4.pdfBSCIENCE_REPORT_yihui-a4.pdf
BSCIENCE_REPORT_yihui-a4.pdf
 
Comparative Analysis Essay Yi Hui.pdf
Comparative Analysis Essay Yi Hui.pdfComparative Analysis Essay Yi Hui.pdf
Comparative Analysis Essay Yi Hui.pdf
 
THEORIES_YIHUI.pdf
THEORIES_YIHUI.pdfTHEORIES_YIHUI.pdf
THEORIES_YIHUI.pdf
 
Yihui's pm final
Yihui's pm finalYihui's pm final
Yihui's pm final
 
Pm final
Pm finalPm final
Pm final
 
Btechii-project2
Btechii-project2Btechii-project2
Btechii-project2
 
Btechii
BtechiiBtechii
Btechii
 
Studio report
Studio reportStudio report
Studio report
 
Slides for bscience ii
Slides for bscience iiSlides for bscience ii
Slides for bscience ii
 
Building science 2 report
Building science 2 reportBuilding science 2 report
Building science 2 report
 
Building technology report
Building technology reportBuilding technology report
Building technology report
 
ARC2625 REPORT FILE ChongYiHui0324404
ARC2625 REPORT FILE ChongYiHui0324404ARC2625 REPORT FILE ChongYiHui0324404
ARC2625 REPORT FILE ChongYiHui0324404
 
Building construction report
Building construction reportBuilding construction report
Building construction report
 
Final report
Final reportFinal report
Final report
 
Culture project-ii-finalized
Culture project-ii-finalizedCulture project-ii-finalized
Culture project-ii-finalized
 
Statitics
StatiticsStatitics
Statitics
 
English report
English report English report
English report
 
Social psychology project ii(comic)
Social psychology project ii(comic)Social psychology project ii(comic)
Social psychology project ii(comic)
 
Account assignment report finale(1)
Account assignment report finale(1)Account assignment report finale(1)
Account assignment report finale(1)
 

Quantity-Surveyor (ICI+ITD)-pdf.pdf

  • 1. Quantity Surveyor INTRODUCTION TO CONSTRUCTION INDUSTRY + INTRODUCTION TO DRAWING GROUP: • CH’NG PHEI WOON(LEADER) • CHRISTINA CHUA • BOON LI YING • ALISON TANG • CHONG YI HUI ASSIGNMENT 1
  • 3. Definition of Quantity Surveyor • Providing advices on procurement, contracts and project cost management. • Work as consultants or be employed by a contractor or sub- contractor.
  • 4. Quantity Surveyor Certified board • The Board of Quantity Surveyors Malaysia was set up by an Act of Parliament, i.e. Quantity Surveyors Act 1967 (revised 2002). The Board consists of a President, a Registrar and sixteen (16) members appointed by the Minister of Works, Malaysia. • to approve or reject applications for registration or approval to practise under this Act or to approve any such application subject to such conditions or restrictions as it may deem fit to impose • to order the issuance of a written warning or reprimand, the imposition of a fine, suspension, cancellation, removal or reinstatement in accordance with Part III and IV Quantity Surveyors Act
  • 5. Scope of Work Handled by 
 Quantity Surveyors • Cost Planning • To help the design team to keep within the budget from start to the end of the project • Preliminary Cost Advice •Give practical advice on comparative costs of alternative layouts, materials, components & methods of construction.
  • 6. •Contractual Methods • Advise on the best form of contract for a specific project. •Tendering •Calculating the cost and risk to tender for the project.
  • 7. • Choice of Contractor • Quantity surveyor makes recommendation of contractors base on past performances to the employers. •Valuation of Construction Work •Quantity surveyor evaluates work carried out before making certified payment.
  • 8. •Increase Efficiency •Making sure that fairness exists between employer and contractors to make work smoother and easier.
  • 9. Responsibilities & Tasks at Different Stages of Construction • Monitor cost at different stages of project. • Certify payment and invoices. • Negotiating disputes. • Advising on budgets and costs. • Giving advice for disputes on contracts.
  • 10. Daily Activities Construction starts… • Feasibility studies of a project • Roughly estimate what’s involve in the project (Measurement of Sketches) • Study architects’ and engineers’ plans • Identify cost and overall budget (Value Engineering) • Final detailed estimate is prepared by Quantity Surveyor and Architect
  • 11. •During Construction… • Provide flow of cash data • Can access cost effects when change of project occur •After Construction… •Quantity Surveyor prepare statement of final account (Records actual cost for all sections of job)
  • 12. Stages that involve in cost planning during design and construction Tender Reconciliation Comparing tender price with final cost Post-Contract Cost Control Controlling cost at different stages of construction Preliminary Estimate Using research market price to estimate Cost Plan Calculating project cost according to elemental analysis Cost Check Evaluating the work done according to cost
  • 14. Preliminary Drawing • A rough design with less detail • Estimate the budget of a project • Can be used to prepared cost plan
  • 15. Tender Drawing • A complete design with full details by Architects and Structural engineer • Comprise of architectural and structural drawings • Can be used to prepare Bills of Quantities
  • 16. STRUCTURAL DRAWING By Structural Engineer Column Beam • Between 2 column Slab (Floor)
  • 17. Structural Drawing by Structural Engineer
  • 20. Quantity Surveyors ‘Bible book’
 SMM2 • Latest edition : SMM2 • SMM 1 Slightly different from SMM2 • This book is guide for calculation and format of BILLS OF QUANTITIES
  • 21. Contract Drawing • Same drawing as tender drawings Contract Drawing = Construction Drawing Used to prepare contract document
  • 23. As-Built Drawing • A finalise drawing Any changes in example Type of tile ,paint Commonly by Clients or Architects