SlideShare a Scribd company logo
Prof. Tatikonda G. S.
 The determination of rate per unit of a
particular item of work, from the cost of
quantities of materials, the cost of laborers
and other miscellaneous petty expenses
required for its completion is known as the
Analysis of Rates.
 The rates of materials and labor vary from
place to place and hence the rates of
different items of works also vary from
place to place.
 To work out the actual cost of per unit of the
items.
 To work out the economical use of materials
and processes in completing the particulars
item.
 To work out the cost of extra items which are
not provided in the contract bond, but are to
be done as per the directions of the client.
 To revise the schedule of rates due to increase
in the cost of material and labour or due to
change in technique
 Details of all operations involved in carrying
out the work
 The quantities of materials and their costs
 The number of different categories of
laborers required, their working capacity
and daily wages.
1. Major Factors :-
a) Material
b) Labour
2. Minor Factors : -
a) Special Equipment
b) Place of work
c) Nature of work
d) Conditions of Contract
e) Profit of the contractor
f) Specification
g) Site Condition
h) Miscellaneous
 Lead: The horizontal distance between the
trench pit and the place where excavated
earth is placed is called as lead. The unit of
lead is 50 m for a distance up to 500 m, 500 m
for a distance exceeding 500 m up to 5 km and
1 km for distance exceeds 5 km.
 Lift: It is the depth of excavation or the
vertical movement of material. Generally
lift is taken as 1.5 m below ground level. Extra
lift shall be measured in unit of 1.5 m or part
thereof.
The capacity of a skilled labour to do the
quantity of work per day called task work. Task work
is depends on the nature, size, height, situation, location,
climate condition, techniques adopted, wages paid.
Factors Affecting Task Work:-
 Out turn of skilled labour depends on the nature, size,
height, situation, location, Climatic condition, technique
adopted, wages paid etc.
 Availability of skilled labour.
 A well-organized work increases the out turn of labour.
 Job satisfaction and working condition may increase the
out turn work. If the work is allotted on piece work
basis then the daily wages output of labour increases.
 ANALYSIS OF RATES
The analysis of rates is worked out for the unit payment of
the particular item of work under two heads.
 Materials
 Labour
 Material Cost + Labour Cost = Cost of Items of Work
Other items included are:
 Tools and Plants ( T & P ) = 2.5 to 3 % of the labour cost
 Transportation cost more than 8 km is considered
 Water charges = 1.5 to 2 % 0f total cost
 Contractor ‘ s profit = 10 %
rate analysis

More Related Content

What's hot

Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing bookThomas Britto
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
Simarpreet Singh
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
Aishwarya Deopujari
 
Estimating & Costing - I
Estimating & Costing - IEstimating & Costing - I
Estimating & Costing - I
anbukkarasi dhuraisamy
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specifications
Simran Vats
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
gayu pandian
 
Rate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisRate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate Analyisis
Japtyesh Singh
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
AshwiniChaudhari13
 
Earthwork and excavation
Earthwork  and  excavationEarthwork  and  excavation
Earthwork and excavation
Krishna Spoorthy Rachamalla
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
Vijay325
 
District schedule rates (DSR), specification of items of work as per PWD
District schedule rates (DSR), specification of items of work as per PWDDistrict schedule rates (DSR), specification of items of work as per PWD
District schedule rates (DSR), specification of items of work as per PWD
AshwiniChaudhari13
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
Ganesh Murugan
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and Arbitration
JIT KUMAR GUPTA
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
Prasad Manerikar
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-I
Kishor Ade
 
Valuation part of Building
Valuation part of Building Valuation part of Building
Valuation part of Building
RAMPRASAD KUMAWAT
 
Terminology used in estimating and costing
Terminology used in estimating and costingTerminology used in estimating and costing
Terminology used in estimating and costing
Janak Mehta
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
srinivas2036
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & Equipments
GAURAV. H .TANDON
 

What's hot (20)

Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
 
Estimating & Costing - I
Estimating & Costing - IEstimating & Costing - I
Estimating & Costing - I
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specifications
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
Rate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisRate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate Analyisis
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
 
Earthwork and excavation
Earthwork  and  excavationEarthwork  and  excavation
Earthwork and excavation
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
 
District schedule rates (DSR), specification of items of work as per PWD
District schedule rates (DSR), specification of items of work as per PWDDistrict schedule rates (DSR), specification of items of work as per PWD
District schedule rates (DSR), specification of items of work as per PWD
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and Arbitration
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-I
 
Valuation part of Building
Valuation part of Building Valuation part of Building
Valuation part of Building
 
Terminology used in estimating and costing
Terminology used in estimating and costingTerminology used in estimating and costing
Terminology used in estimating and costing
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & Equipments
 

Similar to rate analysis

UNIT 2.pptx
UNIT 2.pptxUNIT 2.pptx
UNIT 2.pptx
AkashM725543
 
Rate analysis vansheika
Rate analysis   vansheikaRate analysis   vansheika
Rate analysis vansheika
VansheikaThakur
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
NaumanIjaz12
 
chapter3-210122050220.pdf
chapter3-210122050220.pdfchapter3-210122050220.pdf
chapter3-210122050220.pdf
Deepak37004
 
Estimating and Costing
Estimating and CostingEstimating and Costing
Estimating and Costing
Ganesh Tatikonda
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
hatim ahmed
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
vikrant prajapati
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
TauheedKhan45
 
Estimate and Valuation by Aman Kumar
Estimate and Valuation by Aman KumarEstimate and Valuation by Aman Kumar
Estimate and Valuation by Aman Kumar
aman kumar
 
Lec.2 binifits of estamations...Types of Estimation
Lec.2  binifits of estamations...Types of EstimationLec.2  binifits of estamations...Types of Estimation
Lec.2 binifits of estamations...Types of Estimation
Muthanna Abbu
 
Analyis of Rate MODULE VI October 2022.pptx
Analyis of Rate  MODULE VI October 2022.pptxAnalyis of Rate  MODULE VI October 2022.pptx
Analyis of Rate MODULE VI October 2022.pptx
rekhat26
 
Cost Classification in Management Accountingx
Cost Classification in Management AccountingxCost Classification in Management Accountingx
Cost Classification in Management Accountingx
ChamodiBandara1
 
E.c.v Introduction
E.c.v IntroductionE.c.v Introduction
E.c.v Introduction
Yusuf Challawala
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
SHAZEBALIKHAN1
 
3.estimating
3.estimating3.estimating
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
DhavalMithaiwala
 
Mca i fma u 4.2 marginal costing
Mca i fma u 4.2 marginal costingMca i fma u 4.2 marginal costing
Mca i fma u 4.2 marginal costing
Rai University
 
Theory of Production and Cost, Break-even Analysis
Theory of Production and Cost, Break-even AnalysisTheory of Production and Cost, Break-even Analysis
Theory of Production and Cost, Break-even Analysis
Kumar Pawar
 
Basics of estimation
Basics of estimation Basics of estimation
Basics of estimation
ddscte
 

Similar to rate analysis (20)

UNIT 2.pptx
UNIT 2.pptxUNIT 2.pptx
UNIT 2.pptx
 
Rate analysis vansheika
Rate analysis   vansheikaRate analysis   vansheika
Rate analysis vansheika
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
 
chapter3-210122050220.pdf
chapter3-210122050220.pdfchapter3-210122050220.pdf
chapter3-210122050220.pdf
 
Estimating and Costing
Estimating and CostingEstimating and Costing
Estimating and Costing
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
 
Estimate and Valuation by Aman Kumar
Estimate and Valuation by Aman KumarEstimate and Valuation by Aman Kumar
Estimate and Valuation by Aman Kumar
 
Lec.2 binifits of estamations...Types of Estimation
Lec.2  binifits of estamations...Types of EstimationLec.2  binifits of estamations...Types of Estimation
Lec.2 binifits of estamations...Types of Estimation
 
Analyis of Rate MODULE VI October 2022.pptx
Analyis of Rate  MODULE VI October 2022.pptxAnalyis of Rate  MODULE VI October 2022.pptx
Analyis of Rate MODULE VI October 2022.pptx
 
Cost Classification in Management Accountingx
Cost Classification in Management AccountingxCost Classification in Management Accountingx
Cost Classification in Management Accountingx
 
E.c.v Introduction
E.c.v IntroductionE.c.v Introduction
E.c.v Introduction
 
Ecv
EcvEcv
Ecv
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
 
3.estimating
3.estimating3.estimating
3.estimating
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
Mca i fma u 4.2 marginal costing
Mca i fma u 4.2 marginal costingMca i fma u 4.2 marginal costing
Mca i fma u 4.2 marginal costing
 
Theory of Production and Cost, Break-even Analysis
Theory of Production and Cost, Break-even AnalysisTheory of Production and Cost, Break-even Analysis
Theory of Production and Cost, Break-even Analysis
 
Basics of estimation
Basics of estimation Basics of estimation
Basics of estimation
 

Recently uploaded

English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 

Recently uploaded (20)

English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 

rate analysis

  • 2.  The determination of rate per unit of a particular item of work, from the cost of quantities of materials, the cost of laborers and other miscellaneous petty expenses required for its completion is known as the Analysis of Rates.  The rates of materials and labor vary from place to place and hence the rates of different items of works also vary from place to place.
  • 3.  To work out the actual cost of per unit of the items.  To work out the economical use of materials and processes in completing the particulars item.  To work out the cost of extra items which are not provided in the contract bond, but are to be done as per the directions of the client.  To revise the schedule of rates due to increase in the cost of material and labour or due to change in technique
  • 4.  Details of all operations involved in carrying out the work  The quantities of materials and their costs  The number of different categories of laborers required, their working capacity and daily wages.
  • 5. 1. Major Factors :- a) Material b) Labour 2. Minor Factors : - a) Special Equipment b) Place of work c) Nature of work d) Conditions of Contract e) Profit of the contractor f) Specification g) Site Condition h) Miscellaneous
  • 6.  Lead: The horizontal distance between the trench pit and the place where excavated earth is placed is called as lead. The unit of lead is 50 m for a distance up to 500 m, 500 m for a distance exceeding 500 m up to 5 km and 1 km for distance exceeds 5 km.  Lift: It is the depth of excavation or the vertical movement of material. Generally lift is taken as 1.5 m below ground level. Extra lift shall be measured in unit of 1.5 m or part thereof.
  • 7. The capacity of a skilled labour to do the quantity of work per day called task work. Task work is depends on the nature, size, height, situation, location, climate condition, techniques adopted, wages paid. Factors Affecting Task Work:-  Out turn of skilled labour depends on the nature, size, height, situation, location, Climatic condition, technique adopted, wages paid etc.  Availability of skilled labour.  A well-organized work increases the out turn of labour.  Job satisfaction and working condition may increase the out turn work. If the work is allotted on piece work basis then the daily wages output of labour increases.
  • 8.
  • 9.
  • 10.  ANALYSIS OF RATES The analysis of rates is worked out for the unit payment of the particular item of work under two heads.  Materials  Labour  Material Cost + Labour Cost = Cost of Items of Work Other items included are:  Tools and Plants ( T & P ) = 2.5 to 3 % of the labour cost  Transportation cost more than 8 km is considered  Water charges = 1.5 to 2 % 0f total cost  Contractor ‘ s profit = 10 %