ESTIMATING
Introduction to The Principle of Estimating
&
Project Cost Estimating
Darren Tan Quan Wen
Lim Hong Wei
Loo Siah Mong
Pui Chun Shian
Ranee Leow Kai Yen
Soo Yon Li
0322662
0322741
0321995
0323470
0328173
0322821
Importance of estimating at ...
Pre-contract stageObtain
competitive
prices
Cost control
Compile
quotations
➔ Provide clients a clearer
picture of the costs
involved, helping them
to plan and budget
accordingly.
➔ Enable material procured/
design to be finalised
within the budget.
➔ Enable planning for
budget allocation
➔ Ensure that the
successful contractor’s
tender does not exceed
the client’s budget.
Importance of estimating at ...
Pre-tender stageAssurance in
project Value
sub-contractor
Budget
confirmation
➔ Provide the company a
figure which they are
capable in tendering the
project value
➔ Estimated value allows
subcontractor to know
whether they are willing or
able to submit tender to
the contractor.
➔ Ensure client knows that
the sufficient funds are
available before
committing to seeking
tenders.
Importance of estimating at ...
Post-contract stageTender sum =
Final account
Cash flow control
Control
contingency sum
➔ Making sure the final
account statement is
close to the amount
estimated initially ➔ Realistic monthly
assessment of preliminaries
➔ Increased costs kept up to
date in monthly valuations
➔ Daywork sheets
completed and cleared
for monthly payment
➔ Ensure majority of it is to
cover cost of extra work
that could not be
reasonably foreseen
➔ Ensure probable cost of
all variations to be
computed before issue
of variation orders.
Estimating Measurement Tendering
➔ Uses estimator
building’s knowledge
and skills to estimate
a rough figure on a
particular project
➔ Uses SMM2 as a
guideline to calculate
a more accurate figure
of the project
➔ Price offer to do a
construction building
➔ Based on past
building construction
price
➔ Based on current
market price
➔ Inviting subcontractor
to bid and evaluating
the bids during tender
stage
➔ No profit made ➔ No profit made ➔ Done with profit
What are preliminaries items ?
Temporary works which are required by main
contractor during the contract, but do not form any
of work packages required by the contract.
Occupational Health and
Safety Officer
Internet Access Portable Toilets
Site Office Temporary Roads

Estimating presentation 1

  • 1.
    ESTIMATING Introduction to ThePrinciple of Estimating & Project Cost Estimating Darren Tan Quan Wen Lim Hong Wei Loo Siah Mong Pui Chun Shian Ranee Leow Kai Yen Soo Yon Li 0322662 0322741 0321995 0323470 0328173 0322821
  • 2.
    Importance of estimatingat ... Pre-contract stageObtain competitive prices Cost control Compile quotations ➔ Provide clients a clearer picture of the costs involved, helping them to plan and budget accordingly. ➔ Enable material procured/ design to be finalised within the budget. ➔ Enable planning for budget allocation ➔ Ensure that the successful contractor’s tender does not exceed the client’s budget.
  • 3.
    Importance of estimatingat ... Pre-tender stageAssurance in project Value sub-contractor Budget confirmation ➔ Provide the company a figure which they are capable in tendering the project value ➔ Estimated value allows subcontractor to know whether they are willing or able to submit tender to the contractor. ➔ Ensure client knows that the sufficient funds are available before committing to seeking tenders.
  • 4.
    Importance of estimatingat ... Post-contract stageTender sum = Final account Cash flow control Control contingency sum ➔ Making sure the final account statement is close to the amount estimated initially ➔ Realistic monthly assessment of preliminaries ➔ Increased costs kept up to date in monthly valuations ➔ Daywork sheets completed and cleared for monthly payment ➔ Ensure majority of it is to cover cost of extra work that could not be reasonably foreseen ➔ Ensure probable cost of all variations to be computed before issue of variation orders.
  • 5.
    Estimating Measurement Tendering ➔Uses estimator building’s knowledge and skills to estimate a rough figure on a particular project ➔ Uses SMM2 as a guideline to calculate a more accurate figure of the project ➔ Price offer to do a construction building ➔ Based on past building construction price ➔ Based on current market price ➔ Inviting subcontractor to bid and evaluating the bids during tender stage ➔ No profit made ➔ No profit made ➔ Done with profit
  • 6.
    What are preliminariesitems ? Temporary works which are required by main contractor during the contract, but do not form any of work packages required by the contract. Occupational Health and Safety Officer Internet Access Portable Toilets
  • 7.

Editor's Notes

  • #3 1a. Pre-contract Obtaining competitive prices from a number of selected contractors to provide clients with a clearer picture of the costs involved, helping them to plan and budget accordingly Making sure the material procure can be fall within the budget, enable design to be finalised analyse and compare quotations for compilation of tender/bid offer submissions
  • #4  Pre-Tender To ensure that the company is capable in tendering the project value Ensure tender figure is as close as possible to estimated figure It is important to know that the sub contractor is willing to submit tender as well. Enables client to confirm that sufficient funds are available before committing to seeking tenders
  • #5  Post-contract Making sure the final account statement tally with the amount estimated. prepare and agreeing payments applications, so that payment is received in accordance with the terms of the contract conditions Maintaining logs for claims and thereby agreeing variations
  • #7 scaffolding they must be removed after the construction to prevent obstruction. Site office Site office is a temporary place for the construction professions who work at the site to conduct meetings, discussions, a place for shelter and so on Internet To research on different types problems faced, or anything that needs the internet to complete the tasks. Temporary road For heavy plants to transport heavy materials such as concrete, water, steel reinforcement bars and so on. Safety equipments To prevent from trespassers interrupting the construction work and make sure that there is no loss in materials so that there is no extra cost for the construction. Portable Toilet provide sanitation needs prevent workers from wandering off site