SlideShare a Scribd company logo
TOTAL
           PRODUCTIVE
           MAINTENANCE
                            Collected by
                      Dr. K. BARANIDHARAN
                  Asst. Prof in Management Studies
                 Sri Sairam Institute of Technology
                                Chennai



09/20/12     SRI SAIRAM INSTITUTE OF TECHNOLOGY &     1
                              SIMS
TPM
           TOTAL PRODUCTIVE MAINTENANCE ….

           GOAL
 Increase production
   while,    at    the
   same          time,
   increasing
   employee     morale
   and             job
   satisfaction.


                             MKS/TPM/RKFL/01-2008
                  SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                                 2
                                   SIMS
TOTAL PRODUCTIVE MAINTENANCE ….

  TPM
Why we need TPM ?
The major objectives of the TPM are listed as
   under :

1. Avoid wastage in quickly changing
   environment.
2. Reduce Cost of Manufacturing.
3. Produce a low batch quantity at the
   earliest possible time.
4. Goods send to Customers must be “
   non – defective”

09/20/12      SRI SAIRAM INSTITUTE OF
                      MKS/TPM/RKFL/01-2008   3
                TECHNOLOGY & SIMS
Introduction
   Total    productive
    maintenance  (TPM ) originated in Japan
    in 1971 as a method for improved
    machine availability through better
    utilization of maintenance and production
    resources.
   TPM is a maintenance process developed
    for improving productivity by making
    processes more reliable and less
    wasteful.TPM is an extension of
    TQM(Total Quality Management)
09/20/12       SRI SAIRAM INSTITUTE OF TECHNOLOGY &
                                SIMS
                                                      4
Why TPM ?
  • TPM was introduced to achieve the following
    objectives. The important ones are listed below.
     – Avoid wastage in a quickly changing
       economic environment.
     – Producing goods without reducing product
       quality.
     – Reduce cost.
     – Produce a low batch quantity at the earliest
       possible time.
     – Goods send to the customers must be non
       defective.
                    SRI SAIRAM INSTITUTE OF
09/20/12              TECHNOLOGY & SIMS            5
What is TPM?

           “Strategy of TPM is to change the attitude
           from “I use, You maintain” to “I use, I
           maintain”.
           Think about how to Increase production
           and reduced cost by reducing or
           eliminating loss, and this is the TPM.



09/20/12           SRI SAIRAM INSTITUTE OF TECHNOLOGY & SIMS   6
Objectives of TPM
  • To improve equipment effectiveness
     – TPM examines the effectiveness of facilities by
       identifying and examining all loses.
     Example: Downtime loses, Speed loses, and defect
       loses.
  • To achieve autonomous Maintenance
     – TPM allows the people who operate equipment to
       take responsibility of the maintenance tasks.
  • To train all staff in relevant maintenance skills
     – TPM places a heavy emphasis on appropriate and
       continuous training to all operating and maintenance
       staffs
                    SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                                   7
                                     SIMS
Objectives of TPM
   To plan maintenance
           – TPM has a systematic approach to all
             maintenance activities.
   To achieve early equipment management
           – TPM aims to move towards zero
             maintenance through “Maintenance
             Prevention”.



                         SRI SAIRAM INSTITUTE OF
09/20/12                   TECHNOLOGY & SIMS        8
MAINTENANCE




            SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                           9
                             SIMS
MAINTENANCE….
MAINTENANCE
The Management, control, execution and
  quality assurance of activities which
  ensure the achievement of optimum
  availability and performance of a
  plant in order to meet business
  objectives.




  09/20/12    SRI SAIRAM INSTITUTE OF
                  MKS/TPM/RKFL/01-2008    10
                 TECHNOLOGY & SIMS
Maintenance –
 Objectives :
 •   To enable product and service quality, and customer satisfaction
     through healthy equipments

 •   Maximize useful life of the equipments

 •   Prevent unsafe working

 •   Minimize process variability

 •   Reduce the operational attributable to the equipments

 •   Minimize frequency and severity of equipment interruptions

 •   Maximize the productiveSAIRAM INSTITUTE OF TECHNOLOGY &
                              capacity of the equipment resources
                          SRI
 09/20/12                                                               11
                                      SIMS
Why Maintenance is critical ?

   Operational cost is one of the key differentiators
   Machine would work only if people work
   Ever increasing dependence on technology and
    machines due to higher levels of automation
   Specialized technology calls for specialized
    maintenance skills
   A good maintenance system can result into an effective
    inventory control for spare parts
   Maintenance is no longer viewed as reaction to
    machine breakdowns, the role is to participate in
    quality and productivity enhancement
                        SRI SAIRAM INSTITUTE OF
 09/20/12                 TECHNOLOGY & SIMS              12
Types (Phases) of Maintenance –
   Breakdown Maintenance (Pre 1950s) – to set the
    machine right when in trouble
   Preventive Maintenance (1950s) – establish a
    maintenance system to improve machine
    performance
   Productive Maintenance (1960s) – recognizing
    importance of maintenance (1960s), reliability
    (1962), maintainability engineering (1962) and
    economic efficiency (engineering economy)
   Total Productive Maintenance (1970s) – productive
    maintenance efficiency through a comprehensive
    system based on respect on INSTITUTE OF
                         SRI SAIRAM individuals or total
        09/20/12           TECHNOLOGY & SIMS             13
    employee participation
Maintenance Decisions –
 • Centralized vs. Decentralized Departmentalization
   – general or specific skills, physical location, etc.

 • In House vs. Outsourced System – cost factors,
   convenience, skill required, etc.

 • Standby Equipments – cost of maintenance (of the
   main as well as stand by), time for maintenance,
   need for reliability, etc.

 • Repair vs. Replacement – cost factors,
   performance assurance, etc.

       09/20/12        SRI SAIRAM INSTITUTE OF             14
                          TECHNOLOGY & SIMS
The Evolution of Maintenance




                   SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                                  15
                                    SIMS
Pillars of TPM




           SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                          16
                            SIMS
Pillars of TPM
    PILLAR 1 - Autonomous
     Maintenance
       A collaborative team activity involving production,
        maintenance, and engineering
       Maintaining Basic conditions on shop floor & in Machines.

       All over participation through TPM Circles.

      Example: 5 S’, JH ZEN ( Autonomous maintenance ), etc.,
       An approach that
              Develops operating and maintenance skills
              Strengthens communication and cooperation



                             SRI SAIRAM INSTITUTE OF
09/20/12                       TECHNOLOGY & SIMS                    17
Steps in JH ZEN :
     Conduct initial cleaning/inspection
     Eliminate sources of contamination
     Establish provisional standards
     Develop general inspection training
     Conduct general inspections
     Improve workplace management and control
     Participate in advanced improvement
      activities
09/20/12           SRI SAIRAM INSTITUTE OF       18
                     TECHNOLOGY & SIMS
Steps in JISHU HOZEN:




               SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                              19
                                SIMS
Pillars of TPM
• PILLAR 2 - Focused
  Improvement
   • Improvement on every one’s activity.
   • Improvement is to eliminate Production losses
     and cost reduction.
   • Improvement in Reliability, Maintainability, and
     cost.




09/20/12         SRI SAIRAM INSTITUTE OF           20
                   TECHNOLOGY & SIMS
Pillars of TPM
  •   PILLAR 3 - Planned Maintenance
       – Logical analysis “Real causes for real counter measures”.
       – Focus on Prevention.
       – It is aimed to have trouble free machines and equipments producing
          defect free products for total customer satisfaction.
       Example: Preventive Maintenance, Breakdown Maintenance, etc.,
  •   Six steps in Planned maintenance :
       – Equipment evaluation and recoding present status.
       – Restore deterioration and improve weakness.
       – Building up information management system.
       – Prepare time based information system, select equipment, parts and
          members and map out plan.
       – Prepare predictive maintenance system by introducing equipment
          diagnostic techniques.
       – Evaluation of planned maintenance.
                          SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                                                  21
                                           SIMS
SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                          22
                            SIMS
Pillars of TPM

           PILLAR 4 - Quality Maintenance
             Developing perfect machine for perfect Quality.
             Eliminating In – Process defects and custom complaints.

           Policy :
             Defect free conditions and control of equipments.
             QM activities to support quality assurance.
             Focus of prevention of defects at source
             Focus on POKA-YOKE. ( fool proof system )
             In-line detection and segregation of defects.
             Effective implementation of operator quality assurance.

09/20/12             SRI SAIRAM INSTITUTE OF TECHNOLOGY & SIMS   23
Pillars of TPM
  • PILLAR 5 - Education & Training
           – Skills development for uniformity of work practices on machines.
           – Skills for Zero defects, Zero breakdowns & Zero accidents.
           – Multi Skilled employees in all departments
  • Steps in Educating and training activities :
           – Setting policies and priorities and checking present status of education and
             training.
           – Establish of training system for operation and maintenance skill up
             gradation.
           – Training the employees for upgrading the operation and maintenance skills.
           – Preparation of training calendar.
           – Kick-off of the system for training.
           – Evaluation of activities and study of future approach.
           – A clear understanding of the criteria for judging normal and abnormal
             conditions
           – The ability to quickly respond to any and all abnormalities
                                SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                                                            24
                                                 SIMS
Pillars of TPM
  • Four Levels of Skills
           – Level 1: Lack both theoretical and practical ability (needs to be
             taught)
           – Level 2: Knows theory but not in practice
           – Level 3: Has mastered practice but not theory
           – Level 4: Mastered both practice and theory




                                SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                                                         25
                                                 SIMS
Pillar s of TPM
 PILLAR 6 - Development Management
    Developing machines for “high equipment effectiveness”.
    Quick process for developing new products.
   Example: KAIZEN
 Kaizen Policy :
    Practice concepts of zero losses in every sphere of activity.
    relentless pursuit to achieve cost reduction targets in all
     resources.
    Relentless pursuit to improve over all plant equipment
     effectiveness.
    Extensive use of PM analysis as a tool for eliminating losses.
    Focus of easy handling of operators.
 09/20/12               SRI SAIRAM INSTITUTE OF                   26
                          TECHNOLOGY & SIMS
Pillars of TPM

 PILLAR 7 - Safety, Health &
  Environment
   Zero accidents and Zero hazards at
    works.
   Zero Pollution at Plant and
    Environment.




09/20/12      SRI SAIRAM INSTITUTE OF    27
                TECHNOLOGY & SIMS
Pillars of TPM
 • PILLAR 8 - Office TPM
       – Office TPM must be followed to improve productivity, efficiency in the
         administrative functions and identify and eliminate losses. This includes
         analyzing processes and procedures towards increased office
         automation
       – Plans & Guidelines:
       – Providing awareness about office TPM to all support departments
       – Helping them to identify P, Q, C, D, S, M in each function in relation to
         plant performance
       – Identify the scope for improvement in each function
       – Collect relevant data
       – Help them to solve problems in their circles
       – Make up an activity board where progress is monitored on both sides -
         results and actions along with Kaizens.
       – Fan out to cover all employees and circles in all functions.
                            SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                                                       28
                                             SIMS
Pillars of TPM
  •   P Q C D S M in Office TPM :
       – P - Production output lost due to Material, Manpower productivity,
          Production output lost due to want of tools.
       – Q - Mistakes in preparation of cheques, bills, invoices, payroll,
          Customer returns/warranty attributable to BOPs, Rejection/rework in
          BOP's/job work, Office area rework.
       – C - Buying cost/unit produced, Cost of logistics - inbound/outbound,
          Cost of carrying inventory, Cost of communication, Demurrage costs.
       – D - Logistics losses (Delay in loading/unloading)
               • Delay in delivery due to any of the support functions
               • Delay in payments to suppliers
               • Delay in information
           – S - Safety in material handling/stores/logistics, Safety of soft and hard
             data.
           – M - Number of Kaizens in office areas

                                 SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                                                            29
                                                  SIMS
Steps in introduction of TPM in a organization
Stage                            Step (Nakajima’s 12 Steps)
        Preparation Stage        Step 1:Announce top management’s decision to introduce
                                 TPM
                                 Step 2:Introductory education campaign
                                 Step 3:TPM Promotion
                                 Step 4:Establish basic TPM policies and goals
                                 Step 5: Preparation and Formulation of a master plan
Preliminary Implementation Stage Step 6:TPM kick-off


   TPM Implementation Stage      Step 7:Develop an equipment management program
                                 Step 8:Develop a planned maintenance program
                                 Step 9:Develop a autonomous maintenance program
                                 Step 10:Increase skills of production and maintenance
                                 personnel
                               SRI SAIRAM INSTITUTE OF TECHNOLOGY &
    09/20/12                      Step 11:Develop early equipment
                                                SIMS
                                                                      management program
                                                                                     30
Implementation of TPM




               SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                              31
                                SIMS
Steps in introduction of TPM in
            a organization
   Step    1: Announce top
      management’s decision to
      introduce TPM
           – State TPM objectives in a company
             newsletter
           – Place articles on TPM in the company
             newspaper



                         SRI SAIRAM INSTITUTE OF
09/20/12                   TECHNOLOGY & SIMS        32
Steps in introduction of TPM in
a organization
   Step 2: Introductory education
    campaign
       Seminars for managers
       Slide presentations for all employees




                       SRI SAIRAM INSTITUTE OF
    09/20/12             TECHNOLOGY & SIMS       33
Steps in introduction of TPM in
            a organization
   Step         3:TPM Promotion
           – Special committees at every level to promote
             TPM
           – Establish an organizational structure
           – Newsletters
           – Articles
           – Videos
           – Posters

                          SRI SAIRAM INSTITUTE OF
09/20/12                    TECHNOLOGY & SIMS           34
Steps in introduction of TPM in
           a organization
    Step 4: Establish basic TPM
     policies and goals
          Analyze existing conditions
          Set goals
          Goals that are Result oriented, Specific,
           Measurable, Attainable and Realistic
          Predict
          TPM policies and goals should be very much
           clear to everyone involved in TPM
           implementation results. OF
                        SRI SAIRAM INSTITUTE
09/20/12               TECHNOLOGY & SIMS            35
Steps in introduction of TPM in a organization
  • Step 5: Preparation and Formulation of a
    master plan
           – A master plan lays out your goals, what you will do to
             achieve them and when you will achieve them
           – Detailed plans for each pillar have to be prepared
           – This activity can be carried out by a consultant, plant
             personnel, or both.
           – Consultant involvement typically begins with a plant
             visit to observe production operations, learn about
             the equipment (type, function, condition, problems
             and losses etc.), study maintenance operations
             (structure, size and tasks etc.), gauge orderliness and
             cleanliness in the plant, and talk to employees to
             determine their motivation and attitude
                           SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                                          36
                                            SIMS
Program Development Master
                      Plan




                  SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                                 37
                                   SIMS
Steps in introduction of TPM in a
organization
 Step 6: TPM kick-off
   The main kick-off to TPM should take
    the form of a formal presentation
    (feasible study Report)with all
    the employees attending
   This opportunity can be used to gain
    the full support of the employees
   Invite external customers, affiliated
    and subcontracting companies

09/20/12       SRI SAIRAM INSTITUTE OF      38
                 TECHNOLOGY & SIMS
Steps in introduction of TPM in a organization
  •   Step 7: Develop an equipment management program
       – The tools of total quality management and continuous improvement are
          applied to the management and improvement of equipment
       – Form project teams
       – Select model equipment
          - Identify equipment problems
          - Analyze equipment problems
          - Develop solutions and proposals for improvement
       – Typical membership of a team
          - Five to seven operators
          - A maintenance person
          - A technical expert
       – Tools
          - Pareto
          - Cause & effect
          - Root cause
          - Methods analysis
                          SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                                                    39
                                           SIMS
Steps in introduction of TPM in a
                organization
  • Step 8: Develop a planned maintenance
    program
           – Set up plans and schedules to carry out work on
             equipment before it breaks down, in order to
             extend the life of the equipment
           – Include periodic and predictive maintenance
           – Include management of spare parts and tools



                         SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                                        40
                                          SIMS
Steps in introduction of TPM in a
                organization
  • Step 9: Develop a autonomous maintenance
    program
           – A handing-over of maintenance tasks from
             specialized maintenance personnel to production
             operators
           – Tasks to hand over
             - Cleaning
             - Lubricating
             - Inspecting
             - Set-up and adjustment
                        SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                                       41
                                         SIMS
A Chart for Autonomous Maintenance




            SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                           42
                             SIMS
Steps in introduction of TPM in a
                organization
  • Step 10: Increase skills of production and
    maintenance personnel
           – The training sessions must be planned shortly
             after the kick-off presentation
           – 2 major components
             - soft skills training
             - technical training
           – Train leaders together
           – Have leaders share information with group
             members
                         SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                                        43
                                          SIMS
Training Skill Development Matrix




              SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                             44
                               SIMS
Steps in introduction of TPM in a organization
  • Step 11: Develop early equipment management program
     – The principle of designing for maintenance prevention can be
       applied to new products, and to new and existing machines
     – New products must be designed so that they can be easily
       produced on new or existing machines
     – New machines must be designed for easier operations,
       changeover and maintenance
     – Existing machines:
       - analyze historical records for
          - trends of types of failures
          - frequency of component failures
          - root causes of failures
       - determine how to eliminate the problem and reduce
       maintenance through an equipment design change or by
       changing the process
                       SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                                              45
                                        SIMS
Steps in introduction of TPM in a
                organization
  • Step 12: Perfect TPM implementation and raise TPM levels
           – Evaluate for the PM Award: The Japanese Institute for Productive
             Maintenance runs the annual PM Excellence Award. They provide a
             checklist for companies applying for the award
           – Set higher goals




                             SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                                                  46
                                              SIMS
6 Big Loses
  Six Big Loss   Loss Category                  Examples            Comment
  Category
  Breakdowns         Down Time Loss             Tooling Failures   There is flexibility
                                                Unplanned          on where to set the
                                                Maintenance        threshold between
                                                General            a Breakdown
                                                Breakdowns         (Down Time Loss)
                                                Equipment Failure  and a Small Stop
                                                                   (Speed Loss).
   Setup and         Down Time Loss             Setup/Changeover This loss is often
  Adjustments                                   Material Shortages addressed through
                                                Operator Shortages setup time
                                                Major Adjustments reduction
                                                Warm-Up Time       programs.


                            SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                                                            47
                                             SIMS
6 Big Loses
  Six Big Loss   Loss Category                  Examples             Comment
  Category
   Small Stops          Speed Loss              Obstructed Product   Typically only
                                                Flow                 includes stops that
                                                Component Jams       are under five
                                                Misfeeds             minutes and that
                                                Sensor Blocked       do not require
                                                Delivery Blocked     maintenance
                                                Cleaning/Checking    personnel.
     Reduced            Speed Loss              Rough Running        Anything that
      Speed                                     Under Nameplate      keeps the process
                                                Capacity             from running at its
                                                Under Design         theoretical
                                                Capacity             maximum speed
                                                Equipment Wear       (a.k.a. Ideal Run
                                                Operator             Rate or Nameplate
                                                Inefficiency         Capacity).
                            SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                                                              48
                                             SIMS
6 Big Loses
  Six Big Loss   Loss Category                  Examples             Comment
  Category
     Startup           Quality Loss             Scrap                Rejects during
     Rejects                                    Rework               warm-up, startup
                                                In-Process Damage    or other early
                                                In-Process           production. May be
                                                Expiration           due to improper
                                                Incorrect Assembly   setup, warm-up
                                                                     period, etc.
   Production          Quality Loss             Scrap                Rejects during
     Rejects                                    Rework               steady-state
                                                In-Process Damage    production.
                                                In-Process
                                                Expiration
                                                Incorrect Assembly

                            SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                                                            49
                                             SIMS
Benefits of TPM
• The properly implemented TPM has made excellent progress
  in a number of areas. These include;
• Increased equipment productivity
• Improved equipment reliability
• Reduced equipment downtime
• Increased plant capacity
• Extended machine line
• Lower maintenance and production costs
• Approaching zero equipment-caused defects
• Improved team work between operators and maintenance
  people
• Enhanced job satisfaction
• Improved return on investment
• Improved safety

                   SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                                     50
                                    SIMS
Thank you

                      Collected by
                 Dr. K. BARANIDHARAN
           Asst. Prof in Management Studies
           Sri Sairam Institute of Technology
                         Chennai



               SRI SAIRAM INSTITUTE OF TECHNOLOGY &
09/20/12                                              51
                                SIMS

More Related Content

What's hot

Total productive maintenance
Total productive maintenanceTotal productive maintenance
Total productive maintenance
ManishaHalai1
 
Maintenance Autonomous
Maintenance AutonomousMaintenance Autonomous
Maintenance Autonomous
Ravi Kumar
 
TPM For lean manufacturing chp3 | kobetsu kaizen for production efficiency...
TPM For lean manufacturing  chp3 |   kobetsu kaizen for production efficiency...TPM For lean manufacturing  chp3 |   kobetsu kaizen for production efficiency...
TPM For lean manufacturing chp3 | kobetsu kaizen for production efficiency...
博行 門眞
 
Total productive maintenance(TPM)
Total productive maintenance(TPM)Total productive maintenance(TPM)
Total productive maintenance(TPM)
Md.Muzahid Khan
 
Total Productive Maintenance
Total Productive Maintenance Total Productive Maintenance
Total Productive Maintenance
Ashik Takvir
 
Autonomous maintenance Jishu Hozen
Autonomous maintenance Jishu HozenAutonomous maintenance Jishu Hozen
Autonomous maintenance Jishu Hozen
ChetanMehta39
 
16 major losses tng
16 major losses tng16 major losses tng
16 major losses tng
Rajasekaran Murugan
 
Autonomous Maintenance (AM)
Autonomous Maintenance (AM)Autonomous Maintenance (AM)
Autonomous Maintenance (AM)
Pramod A
 
My machine camp
My machine campMy machine camp
My machine camp
Jitesh Gaurav
 
TPM for lean manufacturing | lean tools
 TPM  for lean manufacturing |  lean tools	 TPM  for lean manufacturing |  lean tools
TPM for lean manufacturing | lean tools
博行 門眞
 
Tpm total productive maintenance
Tpm  total productive maintenanceTpm  total productive maintenance
Tpm total productive maintenance
KULDEEP MATHUR
 
Abnomality and jishu hozen
Abnomality and jishu hozenAbnomality and jishu hozen
Abnomality and jishu hozen
Rajasekaran Murugan
 
TPM Overview and AM Workshop
TPM Overview and AM WorkshopTPM Overview and AM Workshop
TPM Overview and AM Workshop
John Gabrielle Cabradilla
 
TPM: Autonomous Maintenance
TPM: Autonomous MaintenanceTPM: Autonomous Maintenance
TPM: Autonomous Maintenance
Operational Excellence Consulting
 
Aim of tpm 16 losses/7 Steps of Jhisu Hozen
Aim of tpm 16 losses/7 Steps of Jhisu HozenAim of tpm 16 losses/7 Steps of Jhisu Hozen
Aim of tpm 16 losses/7 Steps of Jhisu Hozen
avijit biswas
 
What is total productive maintenance?
What is total productive maintenance?What is total productive maintenance?
What is total productive maintenance?
ThreadSol
 
Autonomous maintenance ppt
Autonomous maintenance pptAutonomous maintenance ppt
Autonomous maintenance ppt
Suraj1911
 

What's hot (20)

Total productive maintenance
Total productive maintenanceTotal productive maintenance
Total productive maintenance
 
Maintenance Autonomous
Maintenance AutonomousMaintenance Autonomous
Maintenance Autonomous
 
TPM For lean manufacturing chp3 | kobetsu kaizen for production efficiency...
TPM For lean manufacturing  chp3 |   kobetsu kaizen for production efficiency...TPM For lean manufacturing  chp3 |   kobetsu kaizen for production efficiency...
TPM For lean manufacturing chp3 | kobetsu kaizen for production efficiency...
 
Total productive maintenance(TPM)
Total productive maintenance(TPM)Total productive maintenance(TPM)
Total productive maintenance(TPM)
 
Total Productive Maintenance
Total Productive Maintenance Total Productive Maintenance
Total Productive Maintenance
 
TPM Activity
TPM ActivityTPM Activity
TPM Activity
 
Autonomous maintenance Jishu Hozen
Autonomous maintenance Jishu HozenAutonomous maintenance Jishu Hozen
Autonomous maintenance Jishu Hozen
 
16 major losses tng
16 major losses tng16 major losses tng
16 major losses tng
 
Autonomous Maintenance (AM)
Autonomous Maintenance (AM)Autonomous Maintenance (AM)
Autonomous Maintenance (AM)
 
My machine camp
My machine campMy machine camp
My machine camp
 
TPM for lean manufacturing | lean tools
 TPM  for lean manufacturing |  lean tools	 TPM  for lean manufacturing |  lean tools
TPM for lean manufacturing | lean tools
 
Tpm total productive maintenance
Tpm  total productive maintenanceTpm  total productive maintenance
Tpm total productive maintenance
 
Abnomality and jishu hozen
Abnomality and jishu hozenAbnomality and jishu hozen
Abnomality and jishu hozen
 
TPM Overview and AM Workshop
TPM Overview and AM WorkshopTPM Overview and AM Workshop
TPM Overview and AM Workshop
 
Tpm
TpmTpm
Tpm
 
TPM: Autonomous Maintenance
TPM: Autonomous MaintenanceTPM: Autonomous Maintenance
TPM: Autonomous Maintenance
 
Tpm training
Tpm trainingTpm training
Tpm training
 
Aim of tpm 16 losses/7 Steps of Jhisu Hozen
Aim of tpm 16 losses/7 Steps of Jhisu HozenAim of tpm 16 losses/7 Steps of Jhisu Hozen
Aim of tpm 16 losses/7 Steps of Jhisu Hozen
 
What is total productive maintenance?
What is total productive maintenance?What is total productive maintenance?
What is total productive maintenance?
 
Autonomous maintenance ppt
Autonomous maintenance pptAutonomous maintenance ppt
Autonomous maintenance ppt
 

Viewers also liked

Iso
IsoIso
Total Quality Management
Total Quality Management Total Quality Management
Total Quality Management
Aneel Raza
 
Reliability Centred Maintenance Presentation
Reliability Centred Maintenance PresentationReliability Centred Maintenance Presentation
Reliability Centred Maintenance Presentation
Andy_Watson_Sim
 
FMEA 4th Edition for Beginer
FMEA 4th Edition for BeginerFMEA 4th Edition for Beginer
FMEA 4th Edition for BeginerNukool Thanuanram
 
F.M.E.C.A pdf
F.M.E.C.A pdfF.M.E.C.A pdf
F.M.E.C.A pdf
Aon Ali Jaffery
 
failure modes and effects analysis (fmea)
failure modes and effects analysis (fmea)failure modes and effects analysis (fmea)
failure modes and effects analysis (fmea)
palanivendhan
 
Fmea Handbook V4.1[1][1]
Fmea Handbook V4.1[1][1]Fmea Handbook V4.1[1][1]
Fmea Handbook V4.1[1][1]
ExerciseLeanLLC
 
Reliability centred maintenance
Reliability centred maintenanceReliability centred maintenance
Reliability centred maintenanceSHIVAJI CHOUDHURY
 
FMEA - Failure mode and effects analysis
FMEA - Failure mode and effects analysisFMEA - Failure mode and effects analysis
FMEA - Failure mode and effects analysis
Soumyajit Bhuin
 
Failure Mode & Effect Analysis
Failure Mode & Effect AnalysisFailure Mode & Effect Analysis
Failure Mode & Effect AnalysisECC International
 
Reliability centered maintenance
Reliability centered maintenanceReliability centered maintenance
Reliability centered maintenance
Rodolfo Stonner, PMP, RMP
 
An introduction to total productive maintenance (tpm
An introduction to total productive maintenance (tpmAn introduction to total productive maintenance (tpm
An introduction to total productive maintenance (tpmarpitmishra
 
Failure Modes and Effect Analysis (FMEA)
Failure Modes and Effect Analysis (FMEA)Failure Modes and Effect Analysis (FMEA)
Failure Modes and Effect Analysis (FMEA)
Mohammed Hamed Ahmed Soliman
 
Failure Mode Effect Analysis (FMEA)
Failure Mode Effect Analysis (FMEA)Failure Mode Effect Analysis (FMEA)
Failure Mode Effect Analysis (FMEA)Abou Ibri
 
Tqm fmea
Tqm fmeaTqm fmea
Tqm fmea
ANNA UNIVERSITY
 
Deming’s 14 Points on Total Quality Management - TQM - W. Edwards Deming
Deming’s 14 Points on Total Quality Management - TQM - W. Edwards DemingDeming’s 14 Points on Total Quality Management - TQM - W. Edwards Deming
Deming’s 14 Points on Total Quality Management - TQM - W. Edwards Deming
M Obai Seif Kılıç
 
FMEA and FMECA
FMEA and FMECAFMEA and FMECA
FMEA and FMECA
Sjur
 
Introduction to FMEA/FMECA
Introduction to FMEA/FMECAIntroduction to FMEA/FMECA
Introduction to FMEA/FMECA
Michael Herman
 

Viewers also liked (20)

Elements of TQM
Elements of TQMElements of TQM
Elements of TQM
 
Iso
IsoIso
Iso
 
Total Quality Management
Total Quality Management Total Quality Management
Total Quality Management
 
Jurans triology ppt
Jurans triology pptJurans triology ppt
Jurans triology ppt
 
Reliability Centred Maintenance Presentation
Reliability Centred Maintenance PresentationReliability Centred Maintenance Presentation
Reliability Centred Maintenance Presentation
 
FMEA 4th Edition for Beginer
FMEA 4th Edition for BeginerFMEA 4th Edition for Beginer
FMEA 4th Edition for Beginer
 
F.M.E.C.A pdf
F.M.E.C.A pdfF.M.E.C.A pdf
F.M.E.C.A pdf
 
failure modes and effects analysis (fmea)
failure modes and effects analysis (fmea)failure modes and effects analysis (fmea)
failure modes and effects analysis (fmea)
 
Fmea Handbook V4.1[1][1]
Fmea Handbook V4.1[1][1]Fmea Handbook V4.1[1][1]
Fmea Handbook V4.1[1][1]
 
Reliability centred maintenance
Reliability centred maintenanceReliability centred maintenance
Reliability centred maintenance
 
FMEA - Failure mode and effects analysis
FMEA - Failure mode and effects analysisFMEA - Failure mode and effects analysis
FMEA - Failure mode and effects analysis
 
Failure Mode & Effect Analysis
Failure Mode & Effect AnalysisFailure Mode & Effect Analysis
Failure Mode & Effect Analysis
 
Reliability centered maintenance
Reliability centered maintenanceReliability centered maintenance
Reliability centered maintenance
 
An introduction to total productive maintenance (tpm
An introduction to total productive maintenance (tpmAn introduction to total productive maintenance (tpm
An introduction to total productive maintenance (tpm
 
Failure Modes and Effect Analysis (FMEA)
Failure Modes and Effect Analysis (FMEA)Failure Modes and Effect Analysis (FMEA)
Failure Modes and Effect Analysis (FMEA)
 
Failure Mode Effect Analysis (FMEA)
Failure Mode Effect Analysis (FMEA)Failure Mode Effect Analysis (FMEA)
Failure Mode Effect Analysis (FMEA)
 
Tqm fmea
Tqm fmeaTqm fmea
Tqm fmea
 
Deming’s 14 Points on Total Quality Management - TQM - W. Edwards Deming
Deming’s 14 Points on Total Quality Management - TQM - W. Edwards DemingDeming’s 14 Points on Total Quality Management - TQM - W. Edwards Deming
Deming’s 14 Points on Total Quality Management - TQM - W. Edwards Deming
 
FMEA and FMECA
FMEA and FMECAFMEA and FMECA
FMEA and FMECA
 
Introduction to FMEA/FMECA
Introduction to FMEA/FMECAIntroduction to FMEA/FMECA
Introduction to FMEA/FMECA
 

Similar to TPM. DR. K. BARANIDHARAN

Srj tpm
Srj tpmSrj tpm
Reliability-centered maintenance (RCM) & Total Productive Maintenance (TPM).pptx
Reliability-centered maintenance (RCM) & Total Productive Maintenance (TPM).pptxReliability-centered maintenance (RCM) & Total Productive Maintenance (TPM).pptx
Reliability-centered maintenance (RCM) & Total Productive Maintenance (TPM).pptx
Samuel Gher
 
Total Productive Maintenance (TPM) for EVERTS 20Aug2018
Total Productive Maintenance (TPM) for EVERTS  20Aug2018Total Productive Maintenance (TPM) for EVERTS  20Aug2018
Total Productive Maintenance (TPM) for EVERTS 20Aug2018
Timothy Wooi
 
Maintenance engineering
Maintenance engineeringMaintenance engineering
Maintenance engineering
Anirudh Goyal
 
tpm tracking for machine shope--by ganesh kadam
tpm tracking for machine shope--by ganesh kadamtpm tracking for machine shope--by ganesh kadam
tpm tracking for machine shope--by ganesh kadam
JABIL circuit india pvt ltd pune
 
IRJET - Implementation of TPM Philosophy on Critical Paint Shop Machine
IRJET - Implementation of TPM Philosophy on Critical Paint Shop MachineIRJET - Implementation of TPM Philosophy on Critical Paint Shop Machine
IRJET - Implementation of TPM Philosophy on Critical Paint Shop Machine
IRJET Journal
 
Presentation on Total Productive Maintenance
Presentation on Total Productive MaintenancePresentation on Total Productive Maintenance
Presentation on Total Productive Maintenance
Mahendra K SHUKLA
 
Methodology used for improving overall equipment effectiveness by Implementi...
Methodology used for improving overall equipment effectiveness  by Implementi...Methodology used for improving overall equipment effectiveness  by Implementi...
Methodology used for improving overall equipment effectiveness by Implementi...
IJMER
 
Ranveer yadav 2013 14
Ranveer yadav 2013 14Ranveer yadav 2013 14
Ranveer yadav 2013 14ranviry49
 
2022 Consortium for Self-Aware Machining and Metrology
2022 Consortium for Self-Aware Machining and Metrology 2022 Consortium for Self-Aware Machining and Metrology
2022 Consortium for Self-Aware Machining and Metrology
Pure Precision
 
Introduction to Reliability Centered Maintenance
Introduction to Reliability Centered MaintenanceIntroduction to Reliability Centered Maintenance
Introduction to Reliability Centered Maintenance
Dibyendu De
 
Tpm how it_can_work
Tpm how it_can_workTpm how it_can_work
Tpm how it_can_work
arshad1001
 
Total Productivity Management (TPM)
Total Productivity Management (TPM)Total Productivity Management (TPM)
Total Productivity Management (TPM)
theglobalist2003
 
Total productive maintenance (tpm)
Total productive maintenance (tpm)Total productive maintenance (tpm)
Total productive maintenance (tpm)
ranviry49
 
TPM Total Productive Maintenance Workshop for Quarry Plant (1) 09Oct16
TPM Total Productive Maintenance Workshop for Quarry Plant (1) 09Oct16TPM Total Productive Maintenance Workshop for Quarry Plant (1) 09Oct16
TPM Total Productive Maintenance Workshop for Quarry Plant (1) 09Oct16
Timothy Wooi
 
Total productive maintance (tpm)
Total productive maintance (tpm)Total productive maintance (tpm)
Total productive maintance (tpm)
Ankur Kumar
 
12 Benefits of using CMMS - computerized maintenance management system
12 Benefits of using CMMS - computerized maintenance management system12 Benefits of using CMMS - computerized maintenance management system
12 Benefits of using CMMS - computerized maintenance management system
Andriy Popov
 
Introduction To TPM by Ashish Trivedi.pptx
Introduction To TPM by Ashish Trivedi.pptxIntroduction To TPM by Ashish Trivedi.pptx
Introduction To TPM by Ashish Trivedi.pptx
AshishTrivedi65
 
Presentation maintenence management
Presentation maintenence managementPresentation maintenence management
Presentation maintenence management
Vaisakh S Babu
 
TPM: Planned Maintenance
TPM: Planned MaintenanceTPM: Planned Maintenance
TPM: Planned Maintenance
Operational Excellence Consulting
 

Similar to TPM. DR. K. BARANIDHARAN (20)

Srj tpm
Srj tpmSrj tpm
Srj tpm
 
Reliability-centered maintenance (RCM) & Total Productive Maintenance (TPM).pptx
Reliability-centered maintenance (RCM) & Total Productive Maintenance (TPM).pptxReliability-centered maintenance (RCM) & Total Productive Maintenance (TPM).pptx
Reliability-centered maintenance (RCM) & Total Productive Maintenance (TPM).pptx
 
Total Productive Maintenance (TPM) for EVERTS 20Aug2018
Total Productive Maintenance (TPM) for EVERTS  20Aug2018Total Productive Maintenance (TPM) for EVERTS  20Aug2018
Total Productive Maintenance (TPM) for EVERTS 20Aug2018
 
Maintenance engineering
Maintenance engineeringMaintenance engineering
Maintenance engineering
 
tpm tracking for machine shope--by ganesh kadam
tpm tracking for machine shope--by ganesh kadamtpm tracking for machine shope--by ganesh kadam
tpm tracking for machine shope--by ganesh kadam
 
IRJET - Implementation of TPM Philosophy on Critical Paint Shop Machine
IRJET - Implementation of TPM Philosophy on Critical Paint Shop MachineIRJET - Implementation of TPM Philosophy on Critical Paint Shop Machine
IRJET - Implementation of TPM Philosophy on Critical Paint Shop Machine
 
Presentation on Total Productive Maintenance
Presentation on Total Productive MaintenancePresentation on Total Productive Maintenance
Presentation on Total Productive Maintenance
 
Methodology used for improving overall equipment effectiveness by Implementi...
Methodology used for improving overall equipment effectiveness  by Implementi...Methodology used for improving overall equipment effectiveness  by Implementi...
Methodology used for improving overall equipment effectiveness by Implementi...
 
Ranveer yadav 2013 14
Ranveer yadav 2013 14Ranveer yadav 2013 14
Ranveer yadav 2013 14
 
2022 Consortium for Self-Aware Machining and Metrology
2022 Consortium for Self-Aware Machining and Metrology 2022 Consortium for Self-Aware Machining and Metrology
2022 Consortium for Self-Aware Machining and Metrology
 
Introduction to Reliability Centered Maintenance
Introduction to Reliability Centered MaintenanceIntroduction to Reliability Centered Maintenance
Introduction to Reliability Centered Maintenance
 
Tpm how it_can_work
Tpm how it_can_workTpm how it_can_work
Tpm how it_can_work
 
Total Productivity Management (TPM)
Total Productivity Management (TPM)Total Productivity Management (TPM)
Total Productivity Management (TPM)
 
Total productive maintenance (tpm)
Total productive maintenance (tpm)Total productive maintenance (tpm)
Total productive maintenance (tpm)
 
TPM Total Productive Maintenance Workshop for Quarry Plant (1) 09Oct16
TPM Total Productive Maintenance Workshop for Quarry Plant (1) 09Oct16TPM Total Productive Maintenance Workshop for Quarry Plant (1) 09Oct16
TPM Total Productive Maintenance Workshop for Quarry Plant (1) 09Oct16
 
Total productive maintance (tpm)
Total productive maintance (tpm)Total productive maintance (tpm)
Total productive maintance (tpm)
 
12 Benefits of using CMMS - computerized maintenance management system
12 Benefits of using CMMS - computerized maintenance management system12 Benefits of using CMMS - computerized maintenance management system
12 Benefits of using CMMS - computerized maintenance management system
 
Introduction To TPM by Ashish Trivedi.pptx
Introduction To TPM by Ashish Trivedi.pptxIntroduction To TPM by Ashish Trivedi.pptx
Introduction To TPM by Ashish Trivedi.pptx
 
Presentation maintenence management
Presentation maintenence managementPresentation maintenence management
Presentation maintenence management
 
TPM: Planned Maintenance
TPM: Planned MaintenanceTPM: Planned Maintenance
TPM: Planned Maintenance
 

More from SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI

Decision making model - Dr.K.Baranidharan, Sri Sairam Institute of Technology...
Decision making model - Dr.K.Baranidharan, Sri Sairam Institute of Technology...Decision making model - Dr.K.Baranidharan, Sri Sairam Institute of Technology...
Decision making model - Dr.K.Baranidharan, Sri Sairam Institute of Technology...
SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI
 
Incon invitation dec 2013
Incon invitation dec 2013Incon invitation dec 2013
SS&FA/C - Equilibrium in the short period - FINAL YEAR CS/IT - SRI SAIRAM IN...
SS&FA/C - Equilibrium in the  short period - FINAL YEAR CS/IT - SRI SAIRAM IN...SS&FA/C - Equilibrium in the  short period - FINAL YEAR CS/IT - SRI SAIRAM IN...
SS&FA/C - Equilibrium in the short period - FINAL YEAR CS/IT - SRI SAIRAM IN...
SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI
 
SS&FA/C - Equilibrium in the very short period - FINAL YEAR CS/IT - SRI SAIRA...
SS&FA/C - Equilibrium in the very short period - FINAL YEAR CS/IT - SRI SAIRA...SS&FA/C - Equilibrium in the very short period - FINAL YEAR CS/IT - SRI SAIRA...
SS&FA/C - Equilibrium in the very short period - FINAL YEAR CS/IT - SRI SAIRA...
SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI
 
EE&FA/C - SHIFT IN DEMAND AND SUPPLY CURVES - FINAL YEAR CS/3RD YEAR IT - SRI...
EE&FA/C - SHIFT IN DEMAND AND SUPPLY CURVES - FINAL YEAR CS/3RD YEAR IT - SRI...EE&FA/C - SHIFT IN DEMAND AND SUPPLY CURVES - FINAL YEAR CS/3RD YEAR IT - SRI...
EE&FA/C - SHIFT IN DEMAND AND SUPPLY CURVES - FINAL YEAR CS/3RD YEAR IT - SRI...
SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI
 
TQM - RECOGNITION, REWARD, PERFORMANCE APPRAISAL - FINAL YEAR ECE - SRI SAIRA...
TQM - RECOGNITION, REWARD, PERFORMANCE APPRAISAL - FINAL YEAR ECE - SRI SAIRA...TQM - RECOGNITION, REWARD, PERFORMANCE APPRAISAL - FINAL YEAR ECE - SRI SAIRA...
TQM - RECOGNITION, REWARD, PERFORMANCE APPRAISAL - FINAL YEAR ECE - SRI SAIRA...
SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI
 
EE&FA/C - ECONOMICS OF SCALE - FINAL YEAR CS/ 3RD YEAR IT - SRI SAIRAM INSTIT...
EE&FA/C - ECONOMICS OF SCALE - FINAL YEAR CS/ 3RD YEAR IT - SRI SAIRAM INSTIT...EE&FA/C - ECONOMICS OF SCALE - FINAL YEAR CS/ 3RD YEAR IT - SRI SAIRAM INSTIT...
EE&FA/C - ECONOMICS OF SCALE - FINAL YEAR CS/ 3RD YEAR IT - SRI SAIRAM INSTIT...
SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI
 
TQM - RECOGNITION, REWARD, PERFORMANCE APPRAISAL - FINAL YEAR ECE - SRI SAIRA...
TQM - RECOGNITION, REWARD, PERFORMANCE APPRAISAL - FINAL YEAR ECE - SRI SAIRA...TQM - RECOGNITION, REWARD, PERFORMANCE APPRAISAL - FINAL YEAR ECE - SRI SAIRA...
TQM - RECOGNITION, REWARD, PERFORMANCE APPRAISAL - FINAL YEAR ECE - SRI SAIRA...
SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI
 
TQM - 7 NEW TOOLS - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHEN...
TQM - 7 NEW TOOLS - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHEN...TQM - 7 NEW TOOLS - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHEN...
TQM - 7 NEW TOOLS - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHEN...
SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI
 
TQM - 5' S - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI - D...
TQM - 5' S - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI - D...TQM - 5' S - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI - D...
TQM - 5' S - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI - D...
SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI
 
TQM - Six sigma - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNA...
TQM - Six sigma - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNA...TQM - Six sigma - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNA...
TQM - Six sigma - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNA...
SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI
 
EEFA - LAW OF SUPPLY - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY...
EEFA - LAW OF SUPPLY  - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY...EEFA - LAW OF SUPPLY  - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY...
EEFA - LAW OF SUPPLY - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY...
SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI
 
EEFA - ISOQUANT - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR...
EEFA - ISOQUANT  - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR...EEFA - ISOQUANT  - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR...
EEFA - ISOQUANT - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR...
SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI
 
EEFA - RETURN TO FACTOR - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOL...
EEFA - RETURN TO FACTOR  - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOL...EEFA - RETURN TO FACTOR  - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOL...
EEFA - RETURN TO FACTOR - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOL...
SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI
 
EEFA - FACTORS AFFECTING ELESTICITY OF SUPPLY - FINAL YEAR CS/IT - SRI SAIRA...
EEFA - FACTORS AFFECTING ELESTICITY OF SUPPLY  - FINAL YEAR CS/IT - SRI SAIRA...EEFA - FACTORS AFFECTING ELESTICITY OF SUPPLY  - FINAL YEAR CS/IT - SRI SAIRA...
EEFA - FACTORS AFFECTING ELESTICITY OF SUPPLY - FINAL YEAR CS/IT - SRI SAIRA...
SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI
 
EEFA - SUPPLY FUNCTION - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOG...
EEFA - SUPPLY FUNCTION - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOG...EEFA - SUPPLY FUNCTION - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOG...
EEFA - SUPPLY FUNCTION - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOG...
SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI
 
EEFA - DETERMINANT OF SUPPLY - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TEC...
EEFA - DETERMINANT OF SUPPLY - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TEC...EEFA - DETERMINANT OF SUPPLY - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TEC...
EEFA - DETERMINANT OF SUPPLY - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TEC...
SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI
 
EEFA - SUPPLY - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR,K,...
EEFA - SUPPLY - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR,K,...EEFA - SUPPLY - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR,K,...
EEFA - SUPPLY - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR,K,...
SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI
 
TQM - KANO MODEL - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR...
TQM - KANO MODEL - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR...TQM - KANO MODEL - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR...
TQM - KANO MODEL - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR...
SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI
 

More from SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI (20)

Decision making model - Dr.K.Baranidharan, Sri Sairam Institute of Technology...
Decision making model - Dr.K.Baranidharan, Sri Sairam Institute of Technology...Decision making model - Dr.K.Baranidharan, Sri Sairam Institute of Technology...
Decision making model - Dr.K.Baranidharan, Sri Sairam Institute of Technology...
 
Incon invitation dec 2013
Incon invitation dec 2013Incon invitation dec 2013
Incon invitation dec 2013
 
SS&FA/C - Equilibrium in the short period - FINAL YEAR CS/IT - SRI SAIRAM IN...
SS&FA/C - Equilibrium in the  short period - FINAL YEAR CS/IT - SRI SAIRAM IN...SS&FA/C - Equilibrium in the  short period - FINAL YEAR CS/IT - SRI SAIRAM IN...
SS&FA/C - Equilibrium in the short period - FINAL YEAR CS/IT - SRI SAIRAM IN...
 
SS&FA/C - Equilibrium in the very short period - FINAL YEAR CS/IT - SRI SAIRA...
SS&FA/C - Equilibrium in the very short period - FINAL YEAR CS/IT - SRI SAIRA...SS&FA/C - Equilibrium in the very short period - FINAL YEAR CS/IT - SRI SAIRA...
SS&FA/C - Equilibrium in the very short period - FINAL YEAR CS/IT - SRI SAIRA...
 
EE&FA/C - SHIFT IN DEMAND AND SUPPLY CURVES - FINAL YEAR CS/3RD YEAR IT - SRI...
EE&FA/C - SHIFT IN DEMAND AND SUPPLY CURVES - FINAL YEAR CS/3RD YEAR IT - SRI...EE&FA/C - SHIFT IN DEMAND AND SUPPLY CURVES - FINAL YEAR CS/3RD YEAR IT - SRI...
EE&FA/C - SHIFT IN DEMAND AND SUPPLY CURVES - FINAL YEAR CS/3RD YEAR IT - SRI...
 
TQM - RECOGNITION, REWARD, PERFORMANCE APPRAISAL - FINAL YEAR ECE - SRI SAIRA...
TQM - RECOGNITION, REWARD, PERFORMANCE APPRAISAL - FINAL YEAR ECE - SRI SAIRA...TQM - RECOGNITION, REWARD, PERFORMANCE APPRAISAL - FINAL YEAR ECE - SRI SAIRA...
TQM - RECOGNITION, REWARD, PERFORMANCE APPRAISAL - FINAL YEAR ECE - SRI SAIRA...
 
EE&FA/C - ECONOMICS OF SCALE - FINAL YEAR CS/ 3RD YEAR IT - SRI SAIRAM INSTIT...
EE&FA/C - ECONOMICS OF SCALE - FINAL YEAR CS/ 3RD YEAR IT - SRI SAIRAM INSTIT...EE&FA/C - ECONOMICS OF SCALE - FINAL YEAR CS/ 3RD YEAR IT - SRI SAIRAM INSTIT...
EE&FA/C - ECONOMICS OF SCALE - FINAL YEAR CS/ 3RD YEAR IT - SRI SAIRAM INSTIT...
 
TQM - RECOGNITION, REWARD, PERFORMANCE APPRAISAL - FINAL YEAR ECE - SRI SAIRA...
TQM - RECOGNITION, REWARD, PERFORMANCE APPRAISAL - FINAL YEAR ECE - SRI SAIRA...TQM - RECOGNITION, REWARD, PERFORMANCE APPRAISAL - FINAL YEAR ECE - SRI SAIRA...
TQM - RECOGNITION, REWARD, PERFORMANCE APPRAISAL - FINAL YEAR ECE - SRI SAIRA...
 
TQM - 7 NEW TOOLS - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHEN...
TQM - 7 NEW TOOLS - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHEN...TQM - 7 NEW TOOLS - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHEN...
TQM - 7 NEW TOOLS - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHEN...
 
TQM - 5' S - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI - D...
TQM - 5' S - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI - D...TQM - 5' S - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI - D...
TQM - 5' S - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNAI - D...
 
TQM - Six sigma - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNA...
TQM - Six sigma - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNA...TQM - Six sigma - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNA...
TQM - Six sigma - FINAL YEAR ECE - SRI SAIRAM INSTITUTE OF TECHNOLOGY, CHENNA...
 
EEFA - LAW OF SUPPLY - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY...
EEFA - LAW OF SUPPLY  - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY...EEFA - LAW OF SUPPLY  - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY...
EEFA - LAW OF SUPPLY - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY...
 
EEFA - ISOQUANT - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR...
EEFA - ISOQUANT  - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR...EEFA - ISOQUANT  - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR...
EEFA - ISOQUANT - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR...
 
Isocost.2
Isocost.2Isocost.2
Isocost.2
 
EEFA - RETURN TO FACTOR - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOL...
EEFA - RETURN TO FACTOR  - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOL...EEFA - RETURN TO FACTOR  - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOL...
EEFA - RETURN TO FACTOR - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOL...
 
EEFA - FACTORS AFFECTING ELESTICITY OF SUPPLY - FINAL YEAR CS/IT - SRI SAIRA...
EEFA - FACTORS AFFECTING ELESTICITY OF SUPPLY  - FINAL YEAR CS/IT - SRI SAIRA...EEFA - FACTORS AFFECTING ELESTICITY OF SUPPLY  - FINAL YEAR CS/IT - SRI SAIRA...
EEFA - FACTORS AFFECTING ELESTICITY OF SUPPLY - FINAL YEAR CS/IT - SRI SAIRA...
 
EEFA - SUPPLY FUNCTION - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOG...
EEFA - SUPPLY FUNCTION - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOG...EEFA - SUPPLY FUNCTION - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOG...
EEFA - SUPPLY FUNCTION - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOG...
 
EEFA - DETERMINANT OF SUPPLY - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TEC...
EEFA - DETERMINANT OF SUPPLY - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TEC...EEFA - DETERMINANT OF SUPPLY - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TEC...
EEFA - DETERMINANT OF SUPPLY - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TEC...
 
EEFA - SUPPLY - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR,K,...
EEFA - SUPPLY - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR,K,...EEFA - SUPPLY - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR,K,...
EEFA - SUPPLY - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR,K,...
 
TQM - KANO MODEL - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR...
TQM - KANO MODEL - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR...TQM - KANO MODEL - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR...
TQM - KANO MODEL - FINAL YEAR CS/IT - SRI SAIRAM INSTITUTE OF TECHNOLOGY - DR...
 

Recently uploaded

Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
Thiyagu K
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
SACHIN R KONDAGURI
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
Vikramjit Singh
 
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th SemesterGuidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Atul Kumar Singh
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
DhatriParmar
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
BhavyaRajput3
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
Jisc
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
Levi Shapiro
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
Anna Sz.
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
DeeptiGupta154
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
Honest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptxHonest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptx
timhan337
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 

Recently uploaded (20)

Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
 
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th SemesterGuidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th Semester
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
Honest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptxHonest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptx
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 

TPM. DR. K. BARANIDHARAN

  • 1. TOTAL PRODUCTIVE MAINTENANCE Collected by Dr. K. BARANIDHARAN Asst. Prof in Management Studies Sri Sairam Institute of Technology Chennai 09/20/12 SRI SAIRAM INSTITUTE OF TECHNOLOGY & 1 SIMS
  • 2. TPM TOTAL PRODUCTIVE MAINTENANCE …. GOAL Increase production while, at the same time, increasing employee morale and job satisfaction. MKS/TPM/RKFL/01-2008 SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 2 SIMS
  • 3. TOTAL PRODUCTIVE MAINTENANCE …. TPM Why we need TPM ? The major objectives of the TPM are listed as under : 1. Avoid wastage in quickly changing environment. 2. Reduce Cost of Manufacturing. 3. Produce a low batch quantity at the earliest possible time. 4. Goods send to Customers must be “ non – defective” 09/20/12 SRI SAIRAM INSTITUTE OF MKS/TPM/RKFL/01-2008 3 TECHNOLOGY & SIMS
  • 4. Introduction  Total productive maintenance  (TPM ) originated in Japan in 1971 as a method for improved machine availability through better utilization of maintenance and production resources.  TPM is a maintenance process developed for improving productivity by making processes more reliable and less wasteful.TPM is an extension of TQM(Total Quality Management) 09/20/12 SRI SAIRAM INSTITUTE OF TECHNOLOGY & SIMS 4
  • 5. Why TPM ? • TPM was introduced to achieve the following objectives. The important ones are listed below. – Avoid wastage in a quickly changing economic environment. – Producing goods without reducing product quality. – Reduce cost. – Produce a low batch quantity at the earliest possible time. – Goods send to the customers must be non defective. SRI SAIRAM INSTITUTE OF 09/20/12 TECHNOLOGY & SIMS 5
  • 6. What is TPM? “Strategy of TPM is to change the attitude from “I use, You maintain” to “I use, I maintain”. Think about how to Increase production and reduced cost by reducing or eliminating loss, and this is the TPM. 09/20/12 SRI SAIRAM INSTITUTE OF TECHNOLOGY & SIMS 6
  • 7. Objectives of TPM • To improve equipment effectiveness – TPM examines the effectiveness of facilities by identifying and examining all loses. Example: Downtime loses, Speed loses, and defect loses. • To achieve autonomous Maintenance – TPM allows the people who operate equipment to take responsibility of the maintenance tasks. • To train all staff in relevant maintenance skills – TPM places a heavy emphasis on appropriate and continuous training to all operating and maintenance staffs SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 7 SIMS
  • 8. Objectives of TPM  To plan maintenance – TPM has a systematic approach to all maintenance activities.  To achieve early equipment management – TPM aims to move towards zero maintenance through “Maintenance Prevention”. SRI SAIRAM INSTITUTE OF 09/20/12 TECHNOLOGY & SIMS 8
  • 9. MAINTENANCE SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 9 SIMS
  • 10. MAINTENANCE…. MAINTENANCE The Management, control, execution and quality assurance of activities which ensure the achievement of optimum availability and performance of a plant in order to meet business objectives. 09/20/12 SRI SAIRAM INSTITUTE OF MKS/TPM/RKFL/01-2008 10 TECHNOLOGY & SIMS
  • 11. Maintenance – Objectives : • To enable product and service quality, and customer satisfaction through healthy equipments • Maximize useful life of the equipments • Prevent unsafe working • Minimize process variability • Reduce the operational attributable to the equipments • Minimize frequency and severity of equipment interruptions • Maximize the productiveSAIRAM INSTITUTE OF TECHNOLOGY & capacity of the equipment resources SRI 09/20/12 11 SIMS
  • 12. Why Maintenance is critical ?  Operational cost is one of the key differentiators  Machine would work only if people work  Ever increasing dependence on technology and machines due to higher levels of automation  Specialized technology calls for specialized maintenance skills  A good maintenance system can result into an effective inventory control for spare parts  Maintenance is no longer viewed as reaction to machine breakdowns, the role is to participate in quality and productivity enhancement SRI SAIRAM INSTITUTE OF 09/20/12 TECHNOLOGY & SIMS 12
  • 13. Types (Phases) of Maintenance –  Breakdown Maintenance (Pre 1950s) – to set the machine right when in trouble  Preventive Maintenance (1950s) – establish a maintenance system to improve machine performance  Productive Maintenance (1960s) – recognizing importance of maintenance (1960s), reliability (1962), maintainability engineering (1962) and economic efficiency (engineering economy)  Total Productive Maintenance (1970s) – productive maintenance efficiency through a comprehensive system based on respect on INSTITUTE OF SRI SAIRAM individuals or total 09/20/12 TECHNOLOGY & SIMS 13 employee participation
  • 14. Maintenance Decisions – • Centralized vs. Decentralized Departmentalization – general or specific skills, physical location, etc. • In House vs. Outsourced System – cost factors, convenience, skill required, etc. • Standby Equipments – cost of maintenance (of the main as well as stand by), time for maintenance, need for reliability, etc. • Repair vs. Replacement – cost factors, performance assurance, etc. 09/20/12 SRI SAIRAM INSTITUTE OF 14 TECHNOLOGY & SIMS
  • 15. The Evolution of Maintenance SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 15 SIMS
  • 16. Pillars of TPM SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 16 SIMS
  • 17. Pillars of TPM  PILLAR 1 - Autonomous Maintenance  A collaborative team activity involving production, maintenance, and engineering  Maintaining Basic conditions on shop floor & in Machines.  All over participation through TPM Circles. Example: 5 S’, JH ZEN ( Autonomous maintenance ), etc.,  An approach that  Develops operating and maintenance skills  Strengthens communication and cooperation SRI SAIRAM INSTITUTE OF 09/20/12 TECHNOLOGY & SIMS 17
  • 18. Steps in JH ZEN :  Conduct initial cleaning/inspection  Eliminate sources of contamination  Establish provisional standards  Develop general inspection training  Conduct general inspections  Improve workplace management and control  Participate in advanced improvement activities 09/20/12 SRI SAIRAM INSTITUTE OF 18 TECHNOLOGY & SIMS
  • 19. Steps in JISHU HOZEN: SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 19 SIMS
  • 20. Pillars of TPM • PILLAR 2 - Focused Improvement • Improvement on every one’s activity. • Improvement is to eliminate Production losses and cost reduction. • Improvement in Reliability, Maintainability, and cost. 09/20/12 SRI SAIRAM INSTITUTE OF 20 TECHNOLOGY & SIMS
  • 21. Pillars of TPM • PILLAR 3 - Planned Maintenance – Logical analysis “Real causes for real counter measures”. – Focus on Prevention. – It is aimed to have trouble free machines and equipments producing defect free products for total customer satisfaction. Example: Preventive Maintenance, Breakdown Maintenance, etc., • Six steps in Planned maintenance : – Equipment evaluation and recoding present status. – Restore deterioration and improve weakness. – Building up information management system. – Prepare time based information system, select equipment, parts and members and map out plan. – Prepare predictive maintenance system by introducing equipment diagnostic techniques. – Evaluation of planned maintenance. SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 21 SIMS
  • 22. SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 22 SIMS
  • 23. Pillars of TPM PILLAR 4 - Quality Maintenance Developing perfect machine for perfect Quality. Eliminating In – Process defects and custom complaints. Policy : Defect free conditions and control of equipments. QM activities to support quality assurance. Focus of prevention of defects at source Focus on POKA-YOKE. ( fool proof system ) In-line detection and segregation of defects. Effective implementation of operator quality assurance. 09/20/12 SRI SAIRAM INSTITUTE OF TECHNOLOGY & SIMS 23
  • 24. Pillars of TPM • PILLAR 5 - Education & Training – Skills development for uniformity of work practices on machines. – Skills for Zero defects, Zero breakdowns & Zero accidents. – Multi Skilled employees in all departments • Steps in Educating and training activities : – Setting policies and priorities and checking present status of education and training. – Establish of training system for operation and maintenance skill up gradation. – Training the employees for upgrading the operation and maintenance skills. – Preparation of training calendar. – Kick-off of the system for training. – Evaluation of activities and study of future approach. – A clear understanding of the criteria for judging normal and abnormal conditions – The ability to quickly respond to any and all abnormalities SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 24 SIMS
  • 25. Pillars of TPM • Four Levels of Skills – Level 1: Lack both theoretical and practical ability (needs to be taught) – Level 2: Knows theory but not in practice – Level 3: Has mastered practice but not theory – Level 4: Mastered both practice and theory SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 25 SIMS
  • 26. Pillar s of TPM  PILLAR 6 - Development Management  Developing machines for “high equipment effectiveness”.  Quick process for developing new products. Example: KAIZEN  Kaizen Policy :  Practice concepts of zero losses in every sphere of activity.  relentless pursuit to achieve cost reduction targets in all resources.  Relentless pursuit to improve over all plant equipment effectiveness.  Extensive use of PM analysis as a tool for eliminating losses.  Focus of easy handling of operators. 09/20/12 SRI SAIRAM INSTITUTE OF 26 TECHNOLOGY & SIMS
  • 27. Pillars of TPM  PILLAR 7 - Safety, Health & Environment  Zero accidents and Zero hazards at works.  Zero Pollution at Plant and Environment. 09/20/12 SRI SAIRAM INSTITUTE OF 27 TECHNOLOGY & SIMS
  • 28. Pillars of TPM • PILLAR 8 - Office TPM – Office TPM must be followed to improve productivity, efficiency in the administrative functions and identify and eliminate losses. This includes analyzing processes and procedures towards increased office automation – Plans & Guidelines: – Providing awareness about office TPM to all support departments – Helping them to identify P, Q, C, D, S, M in each function in relation to plant performance – Identify the scope for improvement in each function – Collect relevant data – Help them to solve problems in their circles – Make up an activity board where progress is monitored on both sides - results and actions along with Kaizens. – Fan out to cover all employees and circles in all functions. SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 28 SIMS
  • 29. Pillars of TPM • P Q C D S M in Office TPM : – P - Production output lost due to Material, Manpower productivity, Production output lost due to want of tools. – Q - Mistakes in preparation of cheques, bills, invoices, payroll, Customer returns/warranty attributable to BOPs, Rejection/rework in BOP's/job work, Office area rework. – C - Buying cost/unit produced, Cost of logistics - inbound/outbound, Cost of carrying inventory, Cost of communication, Demurrage costs. – D - Logistics losses (Delay in loading/unloading) • Delay in delivery due to any of the support functions • Delay in payments to suppliers • Delay in information – S - Safety in material handling/stores/logistics, Safety of soft and hard data. – M - Number of Kaizens in office areas SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 29 SIMS
  • 30. Steps in introduction of TPM in a organization Stage Step (Nakajima’s 12 Steps) Preparation Stage Step 1:Announce top management’s decision to introduce TPM Step 2:Introductory education campaign Step 3:TPM Promotion Step 4:Establish basic TPM policies and goals Step 5: Preparation and Formulation of a master plan Preliminary Implementation Stage Step 6:TPM kick-off TPM Implementation Stage Step 7:Develop an equipment management program Step 8:Develop a planned maintenance program Step 9:Develop a autonomous maintenance program Step 10:Increase skills of production and maintenance personnel SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 Step 11:Develop early equipment SIMS management program 30
  • 31. Implementation of TPM SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 31 SIMS
  • 32. Steps in introduction of TPM in a organization  Step 1: Announce top management’s decision to introduce TPM – State TPM objectives in a company newsletter – Place articles on TPM in the company newspaper SRI SAIRAM INSTITUTE OF 09/20/12 TECHNOLOGY & SIMS 32
  • 33. Steps in introduction of TPM in a organization  Step 2: Introductory education campaign  Seminars for managers  Slide presentations for all employees SRI SAIRAM INSTITUTE OF 09/20/12 TECHNOLOGY & SIMS 33
  • 34. Steps in introduction of TPM in a organization  Step 3:TPM Promotion – Special committees at every level to promote TPM – Establish an organizational structure – Newsletters – Articles – Videos – Posters SRI SAIRAM INSTITUTE OF 09/20/12 TECHNOLOGY & SIMS 34
  • 35. Steps in introduction of TPM in a organization  Step 4: Establish basic TPM policies and goals  Analyze existing conditions  Set goals  Goals that are Result oriented, Specific, Measurable, Attainable and Realistic  Predict  TPM policies and goals should be very much clear to everyone involved in TPM implementation results. OF SRI SAIRAM INSTITUTE 09/20/12 TECHNOLOGY & SIMS 35
  • 36. Steps in introduction of TPM in a organization • Step 5: Preparation and Formulation of a master plan – A master plan lays out your goals, what you will do to achieve them and when you will achieve them – Detailed plans for each pillar have to be prepared – This activity can be carried out by a consultant, plant personnel, or both. – Consultant involvement typically begins with a plant visit to observe production operations, learn about the equipment (type, function, condition, problems and losses etc.), study maintenance operations (structure, size and tasks etc.), gauge orderliness and cleanliness in the plant, and talk to employees to determine their motivation and attitude SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 36 SIMS
  • 37. Program Development Master Plan SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 37 SIMS
  • 38. Steps in introduction of TPM in a organization  Step 6: TPM kick-off  The main kick-off to TPM should take the form of a formal presentation (feasible study Report)with all the employees attending  This opportunity can be used to gain the full support of the employees  Invite external customers, affiliated and subcontracting companies 09/20/12 SRI SAIRAM INSTITUTE OF 38 TECHNOLOGY & SIMS
  • 39. Steps in introduction of TPM in a organization • Step 7: Develop an equipment management program – The tools of total quality management and continuous improvement are applied to the management and improvement of equipment – Form project teams – Select model equipment - Identify equipment problems - Analyze equipment problems - Develop solutions and proposals for improvement – Typical membership of a team - Five to seven operators - A maintenance person - A technical expert – Tools - Pareto - Cause & effect - Root cause - Methods analysis SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 39 SIMS
  • 40. Steps in introduction of TPM in a organization • Step 8: Develop a planned maintenance program – Set up plans and schedules to carry out work on equipment before it breaks down, in order to extend the life of the equipment – Include periodic and predictive maintenance – Include management of spare parts and tools SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 40 SIMS
  • 41. Steps in introduction of TPM in a organization • Step 9: Develop a autonomous maintenance program – A handing-over of maintenance tasks from specialized maintenance personnel to production operators – Tasks to hand over - Cleaning - Lubricating - Inspecting - Set-up and adjustment SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 41 SIMS
  • 42. A Chart for Autonomous Maintenance SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 42 SIMS
  • 43. Steps in introduction of TPM in a organization • Step 10: Increase skills of production and maintenance personnel – The training sessions must be planned shortly after the kick-off presentation – 2 major components - soft skills training - technical training – Train leaders together – Have leaders share information with group members SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 43 SIMS
  • 44. Training Skill Development Matrix SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 44 SIMS
  • 45. Steps in introduction of TPM in a organization • Step 11: Develop early equipment management program – The principle of designing for maintenance prevention can be applied to new products, and to new and existing machines – New products must be designed so that they can be easily produced on new or existing machines – New machines must be designed for easier operations, changeover and maintenance – Existing machines: - analyze historical records for - trends of types of failures - frequency of component failures - root causes of failures - determine how to eliminate the problem and reduce maintenance through an equipment design change or by changing the process SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 45 SIMS
  • 46. Steps in introduction of TPM in a organization • Step 12: Perfect TPM implementation and raise TPM levels – Evaluate for the PM Award: The Japanese Institute for Productive Maintenance runs the annual PM Excellence Award. They provide a checklist for companies applying for the award – Set higher goals SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 46 SIMS
  • 47. 6 Big Loses Six Big Loss Loss Category Examples Comment Category Breakdowns Down Time Loss Tooling Failures There is flexibility Unplanned on where to set the Maintenance threshold between General a Breakdown Breakdowns (Down Time Loss) Equipment Failure and a Small Stop (Speed Loss). Setup and Down Time Loss Setup/Changeover This loss is often Adjustments Material Shortages addressed through Operator Shortages setup time Major Adjustments reduction Warm-Up Time programs. SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 47 SIMS
  • 48. 6 Big Loses Six Big Loss Loss Category Examples Comment Category Small Stops Speed Loss Obstructed Product Typically only Flow includes stops that Component Jams are under five Misfeeds minutes and that Sensor Blocked do not require Delivery Blocked maintenance Cleaning/Checking personnel. Reduced Speed Loss Rough Running Anything that Speed Under Nameplate keeps the process Capacity from running at its Under Design theoretical Capacity maximum speed Equipment Wear (a.k.a. Ideal Run Operator Rate or Nameplate Inefficiency Capacity). SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 48 SIMS
  • 49. 6 Big Loses Six Big Loss Loss Category Examples Comment Category Startup Quality Loss Scrap Rejects during Rejects Rework warm-up, startup In-Process Damage or other early In-Process production. May be Expiration due to improper Incorrect Assembly setup, warm-up period, etc. Production Quality Loss Scrap Rejects during Rejects Rework steady-state In-Process Damage production. In-Process Expiration Incorrect Assembly SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 49 SIMS
  • 50. Benefits of TPM • The properly implemented TPM has made excellent progress in a number of areas. These include; • Increased equipment productivity • Improved equipment reliability • Reduced equipment downtime • Increased plant capacity • Extended machine line • Lower maintenance and production costs • Approaching zero equipment-caused defects • Improved team work between operators and maintenance people • Enhanced job satisfaction • Improved return on investment • Improved safety SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 50 SIMS
  • 51. Thank you Collected by Dr. K. BARANIDHARAN Asst. Prof in Management Studies Sri Sairam Institute of Technology Chennai SRI SAIRAM INSTITUTE OF TECHNOLOGY & 09/20/12 51 SIMS