SlideShare a Scribd company logo
Crashing Example: The network and durations given below shows the normal schedule for a
project. You can decrease (crash) the durations at an additional expense. The Table given
below summarizes the time-cost information for the activities. The owner wants you to you
to finish the project in 110 days. Find the minimum possible cost for the project if you want to
finish it on 110 days. (Assume that for each activity there is a single linear, continuous
function between the crash duration and normal duration points).
Activity
Normal
duration
(days)
Crash
Duration
(days)
Normal
Cost
Crash
Cost
A 120 100 12000 14000
B 20 15 1800 2800
C 40 30 16000 22000
D 30 20 1400 2000
E 50 40 3600 4800
F 60 45 13500 18000
Solution:
Assume that the duration-cost relationship for each activity is a single linear, continuous
function between the crash duration and normal duration points. Using the normal duration
(ND), crash duration (CD), normal cost (NC), and crash cost (CC), the crash cost slope for
each activity can be determined as follows;
CD
ND
NC
CC
SA
−
−
=
day
SA /
100
$
100
120
12000
14000
=
−
−
=
SB = $200/day
SC = $600/day
SD = $60/day
SE = $120/day
SF = $300/day
A
120
B
20
C D E
F
40 30 50
60
1 2 3 4 5
The normal cost for the project is the sum of a normal cost for each activity. The normal cost
for the project is $48300 and the normal duration is 140 days. The activity which should be
crashed is the one on the critical path which will add the least amount to the overall project
cost. This will be the activity with the flattest or least-cost slope. The duration can be reduced
as long as the critical path is not changed or a new critical path is created. In addition, the
activity duration cannot be less than the crash duration.
SD = $60/day (least-cost slope) Maximum of 10 days can be cut from this schedule by
reducing the duration of activity D to the crash duration of 20 days.
Overall duration is 130 days and there are multiple critical paths (B-F-E and B-C-D-E). Total
project cost at this duration is the normal cost of $48300 plus the cost of crashing the activity
D by 10 days (60 * 10 = $600) for a total of $48900.
The next activity to be crashed would be the activity E, since it has the least-cost slope ($120
per day) of any of the activities on the critical path. Activity E can be crashed by a total of 10
days. Crashing the activity E by 10 days will cost an additional $120 per day or $1200.
The project duration is now 120 days and the total project cost is $50100. There are now three
critical paths (A, B-C-D-E, and B-F-E). The next stage of crashing requires a more through
analysis since it is impossible to crash one activity alone and achieve a reduction in the
overall project duration. Activity A is paired with each of the other activities to determine
which has the least overall cost slope for those activities which have remaining days to be
crashed.
Activity A ($100) + activity B ($200)
Activity A ($100) + activity C ($600) + activity F ($300)
A
120
B
20
C D E
F
40 30 50
20 40
60
1 2 3 4 5
A
120
B
20
C D E
F
40 30 50
20
60
1 2 3 4 5
The least-cost slope will be activity A + activity B for a cost increase of $300 per day.
Reducing the project duration by 5 days will add 5*300 = $1500 dollar crashing cost and the
total project cost would be $51600. Activity B can not be crashed any more.
Final step in crashing the project to 110 days would be accomplished by reducing the duration
of activity A by 5 days to 110 days, reducing activity C by 5 days to 35 days, and reducing
activity F by 5 days to 55 days. The combined cost slope for the simultaneous reduction of
activity A, activity C, and activity F would be $1000 per day. For 5 days of reduction this
would be an additional $5000 in total project cost. The total project cost for the crashed
schedule to 110 days of duration would be $56600.
A
120
B
20
C D E
F
40 30 50
20 40
60
15
115
55
110
35
1 2 3 4 5
A
120
B
20
C D E
F
40 30 50
20 40
60
15
115
1 2 3 4 5

More Related Content

What's hot

Project and organizational structure
Project and organizational structureProject and organizational structure
Project and organizational structure
Sawal Maskey
 

What's hot (20)

Scope management
Scope managementScope management
Scope management
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
Project Execution PowerPoint Presentation Slides
Project Execution PowerPoint Presentation SlidesProject Execution PowerPoint Presentation Slides
Project Execution PowerPoint Presentation Slides
 
Project Quality Management | Project Quality Control | Edureka
Project Quality Management | Project Quality Control | EdurekaProject Quality Management | Project Quality Control | Edureka
Project Quality Management | Project Quality Control | Edureka
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
Basis of Estimate Processes
Basis of Estimate ProcessesBasis of Estimate Processes
Basis of Estimate Processes
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slides
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
 
Project portfolio management
Project portfolio managementProject portfolio management
Project portfolio management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project Monitoring And Controlling
Project Monitoring And ControllingProject Monitoring And Controlling
Project Monitoring And Controlling
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
 
Project and organizational structure
Project and organizational structureProject and organizational structure
Project and organizational structure
 
6.3 Sequence Activities
6.3 Sequence Activities6.3 Sequence Activities
6.3 Sequence Activities
 
Project Management Steps And Process Powerpoint Presentation Slide
Project Management Steps And Process Powerpoint Presentation SlideProject Management Steps And Process Powerpoint Presentation Slide
Project Management Steps And Process Powerpoint Presentation Slide
 
Project cost control techniques
Project cost control techniquesProject cost control techniques
Project cost control techniques
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP Workgroup
 
Pmp sample qa3
Pmp sample qa3Pmp sample qa3
Pmp sample qa3
 

Similar to Cpm crashing example

Running Head DIRECT COST .docx
 Running Head DIRECT COST                                        .docx Running Head DIRECT COST                                        .docx
Running Head DIRECT COST .docx
aryan532920
 
crashing-1 Cons Increases Direct Costs Increased Management Time May Increa...
crashing-1 Cons Increases Direct  Costs Increased  Management Time May Increa...crashing-1 Cons Increases Direct  Costs Increased  Management Time May Increa...
crashing-1 Cons Increases Direct Costs Increased Management Time May Increa...
MuhammadSeyam
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpm
Kinshook Chaturvedi
 

Similar to Cpm crashing example (20)

Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Lecture7_2021_v2.pdf
Lecture7_2021_v2.pdfLecture7_2021_v2.pdf
Lecture7_2021_v2.pdf
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريع
 
MODULE 8 NOTES CEM (1).pdf
MODULE 8 NOTES CEM (1).pdfMODULE 8 NOTES CEM (1).pdf
MODULE 8 NOTES CEM (1).pdf
 
Pert Analysis
Pert AnalysisPert Analysis
Pert Analysis
 
Running Head DIRECT COST .docx
 Running Head DIRECT COST                                        .docx Running Head DIRECT COST                                        .docx
Running Head DIRECT COST .docx
 
Crashing
CrashingCrashing
Crashing
 
Crash management
Crash managementCrash management
Crash management
 
construction resource optimization 1.pptx
construction resource optimization 1.pptxconstruction resource optimization 1.pptx
construction resource optimization 1.pptx
 
Crashing in Project Management
Crashing in Project ManagementCrashing in Project Management
Crashing in Project Management
 
CPM-PERT-Examples .pptx
CPM-PERT-Examples .pptxCPM-PERT-Examples .pptx
CPM-PERT-Examples .pptx
 
Time cost optimisation
Time cost optimisationTime cost optimisation
Time cost optimisation
 
Ise 307- chapter 9
Ise 307- chapter 9 Ise 307- chapter 9
Ise 307- chapter 9
 
ACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptx
 
Crashing and cost plan-cpm
Crashing and cost plan-cpmCrashing and cost plan-cpm
Crashing and cost plan-cpm
 
economy Chapter2_by louy Al hami
economy Chapter2_by louy Al hami economy Chapter2_by louy Al hami
economy Chapter2_by louy Al hami
 
cost of capital .....ch ...of financial management ..solution by MIAN MOHSIN ...
cost of capital .....ch ...of financial management ..solution by MIAN MOHSIN ...cost of capital .....ch ...of financial management ..solution by MIAN MOHSIN ...
cost of capital .....ch ...of financial management ..solution by MIAN MOHSIN ...
 
crashing-1 Cons Increases Direct Costs Increased Management Time May Increa...
crashing-1 Cons Increases Direct  Costs Increased  Management Time May Increa...crashing-1 Cons Increases Direct  Costs Increased  Management Time May Increa...
crashing-1 Cons Increases Direct Costs Increased Management Time May Increa...
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpm
 
Ch2(2011
Ch2(2011Ch2(2011
Ch2(2011
 

Recently uploaded

Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
Kamal Acharya
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
Kamal Acharya
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
Kamal Acharya
 

Recently uploaded (20)

RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
 
Peek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfPeek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Furniture showroom management system project.pdf
Furniture showroom management system project.pdfFurniture showroom management system project.pdf
Furniture showroom management system project.pdf
 
fluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerfluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answer
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdf
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 
IT-601 Lecture Notes-UNIT-2.pdf Data Analysis
IT-601 Lecture Notes-UNIT-2.pdf Data AnalysisIT-601 Lecture Notes-UNIT-2.pdf Data Analysis
IT-601 Lecture Notes-UNIT-2.pdf Data Analysis
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltage
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
fundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionfundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projection
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
 
Pharmacy management system project report..pdf
Pharmacy management system project report..pdfPharmacy management system project report..pdf
Pharmacy management system project report..pdf
 
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data StreamKIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
 

Cpm crashing example

  • 1. Crashing Example: The network and durations given below shows the normal schedule for a project. You can decrease (crash) the durations at an additional expense. The Table given below summarizes the time-cost information for the activities. The owner wants you to you to finish the project in 110 days. Find the minimum possible cost for the project if you want to finish it on 110 days. (Assume that for each activity there is a single linear, continuous function between the crash duration and normal duration points). Activity Normal duration (days) Crash Duration (days) Normal Cost Crash Cost A 120 100 12000 14000 B 20 15 1800 2800 C 40 30 16000 22000 D 30 20 1400 2000 E 50 40 3600 4800 F 60 45 13500 18000 Solution: Assume that the duration-cost relationship for each activity is a single linear, continuous function between the crash duration and normal duration points. Using the normal duration (ND), crash duration (CD), normal cost (NC), and crash cost (CC), the crash cost slope for each activity can be determined as follows; CD ND NC CC SA − − = day SA / 100 $ 100 120 12000 14000 = − − = SB = $200/day SC = $600/day SD = $60/day SE = $120/day SF = $300/day A 120 B 20 C D E F 40 30 50 60 1 2 3 4 5
  • 2. The normal cost for the project is the sum of a normal cost for each activity. The normal cost for the project is $48300 and the normal duration is 140 days. The activity which should be crashed is the one on the critical path which will add the least amount to the overall project cost. This will be the activity with the flattest or least-cost slope. The duration can be reduced as long as the critical path is not changed or a new critical path is created. In addition, the activity duration cannot be less than the crash duration. SD = $60/day (least-cost slope) Maximum of 10 days can be cut from this schedule by reducing the duration of activity D to the crash duration of 20 days. Overall duration is 130 days and there are multiple critical paths (B-F-E and B-C-D-E). Total project cost at this duration is the normal cost of $48300 plus the cost of crashing the activity D by 10 days (60 * 10 = $600) for a total of $48900. The next activity to be crashed would be the activity E, since it has the least-cost slope ($120 per day) of any of the activities on the critical path. Activity E can be crashed by a total of 10 days. Crashing the activity E by 10 days will cost an additional $120 per day or $1200. The project duration is now 120 days and the total project cost is $50100. There are now three critical paths (A, B-C-D-E, and B-F-E). The next stage of crashing requires a more through analysis since it is impossible to crash one activity alone and achieve a reduction in the overall project duration. Activity A is paired with each of the other activities to determine which has the least overall cost slope for those activities which have remaining days to be crashed. Activity A ($100) + activity B ($200) Activity A ($100) + activity C ($600) + activity F ($300) A 120 B 20 C D E F 40 30 50 20 40 60 1 2 3 4 5 A 120 B 20 C D E F 40 30 50 20 60 1 2 3 4 5
  • 3. The least-cost slope will be activity A + activity B for a cost increase of $300 per day. Reducing the project duration by 5 days will add 5*300 = $1500 dollar crashing cost and the total project cost would be $51600. Activity B can not be crashed any more. Final step in crashing the project to 110 days would be accomplished by reducing the duration of activity A by 5 days to 110 days, reducing activity C by 5 days to 35 days, and reducing activity F by 5 days to 55 days. The combined cost slope for the simultaneous reduction of activity A, activity C, and activity F would be $1000 per day. For 5 days of reduction this would be an additional $5000 in total project cost. The total project cost for the crashed schedule to 110 days of duration would be $56600. A 120 B 20 C D E F 40 30 50 20 40 60 15 115 55 110 35 1 2 3 4 5 A 120 B 20 C D E F 40 30 50 20 40 60 15 115 1 2 3 4 5