SlideShare a Scribd company logo
Time Management
Problem-Set-1
Dr. Syed Amir Iqbal.
Produce a network diagram using the data below, identify the critical
path and record the project duration.
Task Duration Predecessor
A 5 Start
B 8 A
C 3 B
D 4 A
E 5 C
F 7 C
G 6 D,E
H 8 F
I 6 G
J 5 H,I
Task Duration Predecessor
A 1
B 8 A
C 4 A
P 7 A
L 2 B
M 4 C
Q 4 P,C
N 9 P
Y 5 L,Q
F 10 M
J 2 Q
S 2 N
V 5 Y,F,J
Z 1 V,S
• Construct a
precedence diagram.
• On the diagram,
compute the four
schedule times for
each activity.
• Identify the critical
path
An automobile
manufacturer is
developing a new
model of car, and the
following table shows
some of the
information relating to
the major activities
involved in this project:
For the following table of information,
1. Draw the network diagram
2. List the network paths
3. Determine the critical path(s)
4. Determine the float for each activity
For the following table of information,
1. Draw the network diagram 3. Determine the critical path(s)
2. List the network paths 4. Determine the float for each activity
Task Duration Predecessor
Start 0
A 5 Start
B 2 Start
C 3 A, B
D 5 Start
E 6 Start
F 4 D, E
G 2 C, F
H 5 G
I 7 G
J 3 H
Finish 0 I, J
Perform a Forward Pass and a Backward Pass of the network
diagram given and identify critical path?
For the information given find:
a) Critical Path
b) Cost of completing the project 3 weeks earlier.
Activity Precedence Time (Weeks) Cost ($)
Normal Crash Normal Crash
A - 4 2 10000 11000
B A 3 2 6000 9000
C A 2 1 4000 6000
D B 5 3 14000 18000
E B,C 1 1 9000 9000
F C 3 2 7000 8000
G E,F 4 2 13000 25000
H D,E 4 1 11000 18000
I H,G 6 5 20000 29000
Activity Precedence Time (Weeks) Cost ($) Cost/Week Weeks to Compress
Normal Crash Normal Crash
A - 4 2 10000 11000 500 2
B A 3 2 6000 9000 3000 1
C A 2 1 4000 6000 2000 1
D B 5 3 14000 18000 2000 2
E B,C 1 1 9000 9000 0 0
F C 3 2 7000 8000 1000 1
G E,F 4 2 13000 25000 6000 2
H D,E 4 1 11000 18000 2333 3
I H,G 6 5 20000 29000 9000 1
A=4
B=3
E=1
F=3
G=4
I=6
H=4
D=5
C=2
A-B-D-H-I = 22
A-B-E-H-I = 18
A-B-E-G-I = 18
A-C-E-H-I = 17
A-C-E-G-I = 17
A-C-F-G-I = 19
Activity Precedence Time (Weeks) Cost ($) Cost ($) /Week Weeks to Compress
Normal Crash Normal Crash
A - 4 2 10000 11000 500 2
B A 3 2 6000 9000 3000 1
C A 2 1 4000 6000 2000 1
D B 5 3 14000 18000 2000 2
E B,C 1 1 9000 9000 0 0
F C 3 2 7000 8000 1000 1
G E,F 4 2 13000 25000 6000 2
H D,E 4 1 11000 18000 2333 3
I H,G 6 5 20000 29000 9000 1
A-B-D-H-I = 22
A-B-E-H-I = 18
A-B-E-G-I = 18
A-C-E-H-I = 17
A-C-E-G-I = 17
A-C-F-G-I = 19
A=4
B=3
E=1
F=3
G=4
I=6
H=4
D=5
C=2
For Week-1
• Reduce activity A to 3 weeks and additional cost will be $500.
• Now path A-B-D-H-I will be 21 weeks and is still the critical path.
For Week-2
• Activity A still have 1 week cushion for time reduction. So Reduce
activity A to one more week. So current duration of activity A is 2
weeks with additional cost of $500.
• New duration of path A-B-D-H-I is 20 weeks and it is still the
critical path. Activity A is now exhausted and further reduction in
this activity is not possible.
For Week-3
• Now among activities B-D-H-I, activity D has the lowest reduction
cost/week. So reduce activity D by one week with additional cost
of $ 2000. New duration of activity D is 4 weeks. The total
duration of A-B-D-H-I is 19 weeks.
• Now the project duration is reduced from 22 weeks to 19 weeks
and the project has two critical paths A-B-D-H-I & A-C-F-G-I.
A None 7
B A 3
C A 4
D B,C 5
E D 2
F D 4
G E,F 5
Act. Imed. Pred. Time
A(7)
B(3)
C(4)
D(5)
E(2)
F(4)
G(5)
Time – Cost Analysis
Crashing the Project (Crash 4 days)
Activity Normal
Time
Crash
Time
Normal
Cost
Crash
Cost
Cost/Day
A 7 6 $7,000 $8,000 $1,000
B 3 2 5,000 7,000 2,000
C 4 3 9,000 10,200 1,200
D 5 4 3,000 4,500 1,500
E 2 1 2,000 3,000 1,000
F 4 2 4,000 7,000 1,500
G 5 4 5,000 8,000 3,000
17
For the data given in the table, Compute critical
path using PERT technique.
Activity Predecessor
Time
Te S.D.
To Tm Tp
A - 2 4 6 4 0.667
B A 8 11 20 12 2.000
C A 10 15 20 15 1.667
D B 12 18 24 18 2.000
E C 8 13 24 14 2.667
F C 4 7 16 8 2.000
G D,F 14 18 28 19 2.333
H E 10 12 14 12 0.667
I G,H 7 10 19 11 2.000
For the data given in the table,
Compute critical path using PERT
technique.
Activity Predecessor
Time
Te S.D.
To Tm Tp
A - 12 14 22 15 1.667
B - 16 17 24 18 1.333
C A 14 15 16 15 0.333
D A 13 18 23 18 1.667
E B 16 18 20 18 0.667
F D,E 13 14 21 15 1.333
G C,F 6 8 10 8 0.667

More Related Content

What's hot

Sujets de preparation bac tp (sayari)
Sujets de preparation bac tp (sayari)Sujets de preparation bac tp (sayari)
Sujets de preparation bac tp (sayari)mohamed_SAYARI
 
Rappel eb8
Rappel eb8Rappel eb8
Rappel eb8
zeinabze
 
Green Building And Low Carbon Building in Malaysia
Green Building And Low Carbon Building in MalaysiaGreen Building And Low Carbon Building in Malaysia
Green Building And Low Carbon Building in Malaysia
Steve Lojuntin
 
Chapter 17 after-tax economic analysis
Chapter 17   after-tax economic analysisChapter 17   after-tax economic analysis
Chapter 17 after-tax economic analysis
Bich Lien Pham
 
Les algorithmes d’approximation
Les algorithmes d’approximationLes algorithmes d’approximation
Les algorithmes d’approximationWael Ismail
 
Chapter 13 green building
Chapter 13 green buildingChapter 13 green building
Chapter 13 green building
KHUSHBU SHAH
 
P2 ch03 2
P2 ch03 2P2 ch03 2
P2 ch03 2
alhaashem
 
Quantitative Management - Ch 11 Network Models
Quantitative Management -  Ch 11 Network ModelsQuantitative Management -  Ch 11 Network Models
Quantitative Management - Ch 11 Network Models
Agnes Puspita
 
GBI: Role of BS
GBI: Role of BSGBI: Role of BS
GBI: Role of BS
Adiirfan Che-ani
 
Operations research : Assignment problem (One's method) presentation
Operations research : Assignment problem (One's method) presentationOperations research : Assignment problem (One's method) presentation
Operations research : Assignment problem (One's method) presentation
Pankaj Kumar
 
Operation Research Techniques in Transportation
Operation Research Techniques in Transportation Operation Research Techniques in Transportation
Quantitative Analysis For Management 11th Edition Render Solutions Manual
Quantitative Analysis For Management 11th Edition Render Solutions ManualQuantitative Analysis For Management 11th Edition Render Solutions Manual
Quantitative Analysis For Management 11th Edition Render Solutions Manual
Shermanne
 
Lpp formulations - 2018 - 1
Lpp  formulations  - 2018 - 1Lpp  formulations  - 2018 - 1
Lpp formulations - 2018 - 1
Utshav Chaudhary
 
Vital Vitamins Facility Planning & Designing
Vital Vitamins Facility  Planning & DesigningVital Vitamins Facility  Planning & Designing
Vital Vitamins Facility Planning & Designing
usamaashfaq12
 
Network diagram problems
Network diagram problemsNetwork diagram problems
Network diagram problems
Subhra Mishra
 
LEED GA Exam Prep
LEED GA Exam PrepLEED GA Exam Prep
LEED GA Exam Prep
G Communications 360
 
Report of Measured Drawing - Lorong Ikan, Penang
Report of Measured Drawing - Lorong Ikan, PenangReport of Measured Drawing - Lorong Ikan, Penang
Report of Measured Drawing - Lorong Ikan, Penang
jernjack
 
Td logique
Td logiqueTd logique
Green Building Construction: Case study on Green Building
Green Building Construction: Case study on Green BuildingGreen Building Construction: Case study on Green Building
Green Building Construction: Case study on Green Building
KetulKhatri
 
Problems W7.ppt
Problems W7.pptProblems W7.ppt
Problems W7.ppt
Annisa600151
 

What's hot (20)

Sujets de preparation bac tp (sayari)
Sujets de preparation bac tp (sayari)Sujets de preparation bac tp (sayari)
Sujets de preparation bac tp (sayari)
 
Rappel eb8
Rappel eb8Rappel eb8
Rappel eb8
 
Green Building And Low Carbon Building in Malaysia
Green Building And Low Carbon Building in MalaysiaGreen Building And Low Carbon Building in Malaysia
Green Building And Low Carbon Building in Malaysia
 
Chapter 17 after-tax economic analysis
Chapter 17   after-tax economic analysisChapter 17   after-tax economic analysis
Chapter 17 after-tax economic analysis
 
Les algorithmes d’approximation
Les algorithmes d’approximationLes algorithmes d’approximation
Les algorithmes d’approximation
 
Chapter 13 green building
Chapter 13 green buildingChapter 13 green building
Chapter 13 green building
 
P2 ch03 2
P2 ch03 2P2 ch03 2
P2 ch03 2
 
Quantitative Management - Ch 11 Network Models
Quantitative Management -  Ch 11 Network ModelsQuantitative Management -  Ch 11 Network Models
Quantitative Management - Ch 11 Network Models
 
GBI: Role of BS
GBI: Role of BSGBI: Role of BS
GBI: Role of BS
 
Operations research : Assignment problem (One's method) presentation
Operations research : Assignment problem (One's method) presentationOperations research : Assignment problem (One's method) presentation
Operations research : Assignment problem (One's method) presentation
 
Operation Research Techniques in Transportation
Operation Research Techniques in Transportation Operation Research Techniques in Transportation
Operation Research Techniques in Transportation
 
Quantitative Analysis For Management 11th Edition Render Solutions Manual
Quantitative Analysis For Management 11th Edition Render Solutions ManualQuantitative Analysis For Management 11th Edition Render Solutions Manual
Quantitative Analysis For Management 11th Edition Render Solutions Manual
 
Lpp formulations - 2018 - 1
Lpp  formulations  - 2018 - 1Lpp  formulations  - 2018 - 1
Lpp formulations - 2018 - 1
 
Vital Vitamins Facility Planning & Designing
Vital Vitamins Facility  Planning & DesigningVital Vitamins Facility  Planning & Designing
Vital Vitamins Facility Planning & Designing
 
Network diagram problems
Network diagram problemsNetwork diagram problems
Network diagram problems
 
LEED GA Exam Prep
LEED GA Exam PrepLEED GA Exam Prep
LEED GA Exam Prep
 
Report of Measured Drawing - Lorong Ikan, Penang
Report of Measured Drawing - Lorong Ikan, PenangReport of Measured Drawing - Lorong Ikan, Penang
Report of Measured Drawing - Lorong Ikan, Penang
 
Td logique
Td logiqueTd logique
Td logique
 
Green Building Construction: Case study on Green Building
Green Building Construction: Case study on Green BuildingGreen Building Construction: Case study on Green Building
Green Building Construction: Case study on Green Building
 
Problems W7.ppt
Problems W7.pptProblems W7.ppt
Problems W7.ppt
 

Similar to CPM-PERT-Examples .pptx

UNIT-2.pptx
UNIT-2.pptxUNIT-2.pptx
UNIT-2.pptx
Raja Manyam
 
Pma individual assignment ii
Pma  individual assignment iiPma  individual assignment ii
Pma individual assignment ii
chandraswami
 
Project management
Project managementProject management
Project management
Anurag Srivastava
 
UNIT-2.pptx
UNIT-2.pptxUNIT-2.pptx
UNIT-2.pptx
Raja Manyam
 
Devry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newDevry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 new
uopassignment
 
Project management
Project managementProject management
Project management
Trade Expert
 
Lecture7_2021_v2.pdf
Lecture7_2021_v2.pdfLecture7_2021_v2.pdf
Lecture7_2021_v2.pdf
ssuserc9da59
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpm
Kinshook Chaturvedi
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
Chandi Mohanty
 
Consider the following resource loading table. Assume that we canno.docx
Consider the following resource loading table.  Assume that we canno.docxConsider the following resource loading table.  Assume that we canno.docx
Consider the following resource loading table. Assume that we canno.docx
donnajames55
 
Quantitative Techniques
Quantitative TechniquesQuantitative Techniques
Quantitative Techniques
SanaRiaz789
 
Time-Cost Tradeoff by Examples
Time-Cost Tradeoff by ExamplesTime-Cost Tradeoff by Examples
Time-Cost Tradeoff by Examples
Chachrist Srisuwanrat
 
Crashing and cost plan-cpm
Crashing and cost plan-cpmCrashing and cost plan-cpm
Crashing and cost plan-cpm
Julius Cuaresma
 
Cpm crashing example
Cpm crashing exampleCpm crashing example
Cpm crashing example
Monalisha Shenoy
 
Crashing
CrashingCrashing
Assignment 101
Assignment 101Assignment 101
Assignment 101
Sisira Kumara
 
MODULE 8 NOTES CEM (1).pdf
MODULE 8 NOTES CEM (1).pdfMODULE 8 NOTES CEM (1).pdf
MODULE 8 NOTES CEM (1).pdf
AbhishekKumar393017
 
1 For PE 17-6A, part a, the Ratio of Fixed Assets to Long-Term Li.docx
1 For PE 17-6A, part a, the Ratio of Fixed Assets to Long-Term Li.docx1 For PE 17-6A, part a, the Ratio of Fixed Assets to Long-Term Li.docx
1 For PE 17-6A, part a, the Ratio of Fixed Assets to Long-Term Li.docx
mercysuttle
 
Crashing
CrashingCrashing
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
Nikka Lopez
 

Similar to CPM-PERT-Examples .pptx (20)

UNIT-2.pptx
UNIT-2.pptxUNIT-2.pptx
UNIT-2.pptx
 
Pma individual assignment ii
Pma  individual assignment iiPma  individual assignment ii
Pma individual assignment ii
 
Project management
Project managementProject management
Project management
 
UNIT-2.pptx
UNIT-2.pptxUNIT-2.pptx
UNIT-2.pptx
 
Devry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newDevry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 new
 
Project management
Project managementProject management
Project management
 
Lecture7_2021_v2.pdf
Lecture7_2021_v2.pdfLecture7_2021_v2.pdf
Lecture7_2021_v2.pdf
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpm
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Consider the following resource loading table. Assume that we canno.docx
Consider the following resource loading table.  Assume that we canno.docxConsider the following resource loading table.  Assume that we canno.docx
Consider the following resource loading table. Assume that we canno.docx
 
Quantitative Techniques
Quantitative TechniquesQuantitative Techniques
Quantitative Techniques
 
Time-Cost Tradeoff by Examples
Time-Cost Tradeoff by ExamplesTime-Cost Tradeoff by Examples
Time-Cost Tradeoff by Examples
 
Crashing and cost plan-cpm
Crashing and cost plan-cpmCrashing and cost plan-cpm
Crashing and cost plan-cpm
 
Cpm crashing example
Cpm crashing exampleCpm crashing example
Cpm crashing example
 
Crashing
CrashingCrashing
Crashing
 
Assignment 101
Assignment 101Assignment 101
Assignment 101
 
MODULE 8 NOTES CEM (1).pdf
MODULE 8 NOTES CEM (1).pdfMODULE 8 NOTES CEM (1).pdf
MODULE 8 NOTES CEM (1).pdf
 
1 For PE 17-6A, part a, the Ratio of Fixed Assets to Long-Term Li.docx
1 For PE 17-6A, part a, the Ratio of Fixed Assets to Long-Term Li.docx1 For PE 17-6A, part a, the Ratio of Fixed Assets to Long-Term Li.docx
1 For PE 17-6A, part a, the Ratio of Fixed Assets to Long-Term Li.docx
 
Crashing
CrashingCrashing
Crashing
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 

Recently uploaded

Risk-Management-presentation for cooperatives
Risk-Management-presentation for cooperativesRisk-Management-presentation for cooperatives
Risk-Management-presentation for cooperatives
bernanbumatay1
 
Make it or Break it - Insights for achieving Product-market fit .pdf
Make it or Break it - Insights for achieving Product-market fit .pdfMake it or Break it - Insights for achieving Product-market fit .pdf
Make it or Break it - Insights for achieving Product-market fit .pdf
Resonate Digital
 
Conflict resololution,role of hr in resolution
Conflict resololution,role of hr in resolutionConflict resololution,role of hr in resolution
Conflict resololution,role of hr in resolution
Dr. Christine Ngari ,Ph.D (HRM)
 
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
William (Bill) H. Bender, FCSI
 
Credit-Management seminar for cooperative power point presentation
Credit-Management seminar for cooperative power point presentationCredit-Management seminar for cooperative power point presentation
Credit-Management seminar for cooperative power point presentation
bernanbumatay1
 
The Management Guide: From Projects to Portfolio
The Management Guide: From Projects to PortfolioThe Management Guide: From Projects to Portfolio
The Management Guide: From Projects to Portfolio
Ahmed AbdelMoneim
 
Comparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile SystemsComparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile Systems
Rob Healy
 
Integrity in leadership builds trust by ensuring consistency between words an...
Integrity in leadership builds trust by ensuring consistency between words an...Integrity in leadership builds trust by ensuring consistency between words an...
Integrity in leadership builds trust by ensuring consistency between words an...
Ram V Chary
 
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
Dr. Nazrul Islam
 
Credit Management training seminar power point presentation
Credit Management training seminar power point presentationCredit Management training seminar power point presentation
Credit Management training seminar power point presentation
bernanbumatay1
 
20240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 202420240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 2024
Matthew Sinclair
 
Enriching engagement with ethical review processes
Enriching engagement with ethical review processesEnriching engagement with ethical review processes
Enriching engagement with ethical review processes
strikingabalance
 
Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™
Alexey Krivitsky
 
Sethurathnam Ravi: A Legacy in Finance and Leadership
Sethurathnam Ravi: A Legacy in Finance and LeadershipSethurathnam Ravi: A Legacy in Finance and Leadership
Sethurathnam Ravi: A Legacy in Finance and Leadership
Anjana Josie
 
innovation in nursing practice, education and management.pptx
innovation in nursing practice, education and management.pptxinnovation in nursing practice, education and management.pptx
innovation in nursing practice, education and management.pptx
TulsiDhidhi1
 
一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理
8p28uk6g
 
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
tdt5v4b
 
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
dsnow9802
 
Public Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdfPublic Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdf
Pinta Partners
 
Strategy for E-Types - Strategy Formulation.pptx
Strategy for E-Types - Strategy Formulation.pptxStrategy for E-Types - Strategy Formulation.pptx
Strategy for E-Types - Strategy Formulation.pptx
KarthikRaghu8
 

Recently uploaded (20)

Risk-Management-presentation for cooperatives
Risk-Management-presentation for cooperativesRisk-Management-presentation for cooperatives
Risk-Management-presentation for cooperatives
 
Make it or Break it - Insights for achieving Product-market fit .pdf
Make it or Break it - Insights for achieving Product-market fit .pdfMake it or Break it - Insights for achieving Product-market fit .pdf
Make it or Break it - Insights for achieving Product-market fit .pdf
 
Conflict resololution,role of hr in resolution
Conflict resololution,role of hr in resolutionConflict resololution,role of hr in resolution
Conflict resololution,role of hr in resolution
 
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
 
Credit-Management seminar for cooperative power point presentation
Credit-Management seminar for cooperative power point presentationCredit-Management seminar for cooperative power point presentation
Credit-Management seminar for cooperative power point presentation
 
The Management Guide: From Projects to Portfolio
The Management Guide: From Projects to PortfolioThe Management Guide: From Projects to Portfolio
The Management Guide: From Projects to Portfolio
 
Comparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile SystemsComparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile Systems
 
Integrity in leadership builds trust by ensuring consistency between words an...
Integrity in leadership builds trust by ensuring consistency between words an...Integrity in leadership builds trust by ensuring consistency between words an...
Integrity in leadership builds trust by ensuring consistency between words an...
 
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
Impact of Effective Performance Appraisal Systems on Employee Motivation and ...
 
Credit Management training seminar power point presentation
Credit Management training seminar power point presentationCredit Management training seminar power point presentation
Credit Management training seminar power point presentation
 
20240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 202420240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 2024
 
Enriching engagement with ethical review processes
Enriching engagement with ethical review processesEnriching engagement with ethical review processes
Enriching engagement with ethical review processes
 
Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™
 
Sethurathnam Ravi: A Legacy in Finance and Leadership
Sethurathnam Ravi: A Legacy in Finance and LeadershipSethurathnam Ravi: A Legacy in Finance and Leadership
Sethurathnam Ravi: A Legacy in Finance and Leadership
 
innovation in nursing practice, education and management.pptx
innovation in nursing practice, education and management.pptxinnovation in nursing practice, education and management.pptx
innovation in nursing practice, education and management.pptx
 
一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理一比一原版(QU毕业证)皇后大学毕业证如何办理
一比一原版(QU毕业证)皇后大学毕业证如何办理
 
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
 
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...
 
Public Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdfPublic Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdf
 
Strategy for E-Types - Strategy Formulation.pptx
Strategy for E-Types - Strategy Formulation.pptxStrategy for E-Types - Strategy Formulation.pptx
Strategy for E-Types - Strategy Formulation.pptx
 

CPM-PERT-Examples .pptx

  • 2. Produce a network diagram using the data below, identify the critical path and record the project duration. Task Duration Predecessor A 5 Start B 8 A C 3 B D 4 A E 5 C F 7 C G 6 D,E H 8 F I 6 G J 5 H,I
  • 3.
  • 4. Task Duration Predecessor A 1 B 8 A C 4 A P 7 A L 2 B M 4 C Q 4 P,C N 9 P Y 5 L,Q F 10 M J 2 Q S 2 N V 5 Y,F,J Z 1 V,S • Construct a precedence diagram. • On the diagram, compute the four schedule times for each activity. • Identify the critical path
  • 5. An automobile manufacturer is developing a new model of car, and the following table shows some of the information relating to the major activities involved in this project:
  • 6. For the following table of information, 1. Draw the network diagram 2. List the network paths 3. Determine the critical path(s) 4. Determine the float for each activity
  • 7.
  • 8. For the following table of information, 1. Draw the network diagram 3. Determine the critical path(s) 2. List the network paths 4. Determine the float for each activity Task Duration Predecessor Start 0 A 5 Start B 2 Start C 3 A, B D 5 Start E 6 Start F 4 D, E G 2 C, F H 5 G I 7 G J 3 H Finish 0 I, J
  • 9.
  • 10. Perform a Forward Pass and a Backward Pass of the network diagram given and identify critical path?
  • 11. For the information given find: a) Critical Path b) Cost of completing the project 3 weeks earlier. Activity Precedence Time (Weeks) Cost ($) Normal Crash Normal Crash A - 4 2 10000 11000 B A 3 2 6000 9000 C A 2 1 4000 6000 D B 5 3 14000 18000 E B,C 1 1 9000 9000 F C 3 2 7000 8000 G E,F 4 2 13000 25000 H D,E 4 1 11000 18000 I H,G 6 5 20000 29000
  • 12. Activity Precedence Time (Weeks) Cost ($) Cost/Week Weeks to Compress Normal Crash Normal Crash A - 4 2 10000 11000 500 2 B A 3 2 6000 9000 3000 1 C A 2 1 4000 6000 2000 1 D B 5 3 14000 18000 2000 2 E B,C 1 1 9000 9000 0 0 F C 3 2 7000 8000 1000 1 G E,F 4 2 13000 25000 6000 2 H D,E 4 1 11000 18000 2333 3 I H,G 6 5 20000 29000 9000 1
  • 13. A=4 B=3 E=1 F=3 G=4 I=6 H=4 D=5 C=2 A-B-D-H-I = 22 A-B-E-H-I = 18 A-B-E-G-I = 18 A-C-E-H-I = 17 A-C-E-G-I = 17 A-C-F-G-I = 19
  • 14. Activity Precedence Time (Weeks) Cost ($) Cost ($) /Week Weeks to Compress Normal Crash Normal Crash A - 4 2 10000 11000 500 2 B A 3 2 6000 9000 3000 1 C A 2 1 4000 6000 2000 1 D B 5 3 14000 18000 2000 2 E B,C 1 1 9000 9000 0 0 F C 3 2 7000 8000 1000 1 G E,F 4 2 13000 25000 6000 2 H D,E 4 1 11000 18000 2333 3 I H,G 6 5 20000 29000 9000 1
  • 15. A-B-D-H-I = 22 A-B-E-H-I = 18 A-B-E-G-I = 18 A-C-E-H-I = 17 A-C-E-G-I = 17 A-C-F-G-I = 19 A=4 B=3 E=1 F=3 G=4 I=6 H=4 D=5 C=2 For Week-1 • Reduce activity A to 3 weeks and additional cost will be $500. • Now path A-B-D-H-I will be 21 weeks and is still the critical path. For Week-2 • Activity A still have 1 week cushion for time reduction. So Reduce activity A to one more week. So current duration of activity A is 2 weeks with additional cost of $500. • New duration of path A-B-D-H-I is 20 weeks and it is still the critical path. Activity A is now exhausted and further reduction in this activity is not possible. For Week-3 • Now among activities B-D-H-I, activity D has the lowest reduction cost/week. So reduce activity D by one week with additional cost of $ 2000. New duration of activity D is 4 weeks. The total duration of A-B-D-H-I is 19 weeks. • Now the project duration is reduced from 22 weeks to 19 weeks and the project has two critical paths A-B-D-H-I & A-C-F-G-I.
  • 16. A None 7 B A 3 C A 4 D B,C 5 E D 2 F D 4 G E,F 5 Act. Imed. Pred. Time A(7) B(3) C(4) D(5) E(2) F(4) G(5)
  • 17. Time – Cost Analysis Crashing the Project (Crash 4 days) Activity Normal Time Crash Time Normal Cost Crash Cost Cost/Day A 7 6 $7,000 $8,000 $1,000 B 3 2 5,000 7,000 2,000 C 4 3 9,000 10,200 1,200 D 5 4 3,000 4,500 1,500 E 2 1 2,000 3,000 1,000 F 4 2 4,000 7,000 1,500 G 5 4 5,000 8,000 3,000 17
  • 18. For the data given in the table, Compute critical path using PERT technique.
  • 19. Activity Predecessor Time Te S.D. To Tm Tp A - 2 4 6 4 0.667 B A 8 11 20 12 2.000 C A 10 15 20 15 1.667 D B 12 18 24 18 2.000 E C 8 13 24 14 2.667 F C 4 7 16 8 2.000 G D,F 14 18 28 19 2.333 H E 10 12 14 12 0.667 I G,H 7 10 19 11 2.000
  • 20. For the data given in the table, Compute critical path using PERT technique.
  • 21. Activity Predecessor Time Te S.D. To Tm Tp A - 12 14 22 15 1.667 B - 16 17 24 18 1.333 C A 14 15 16 15 0.333 D A 13 18 23 18 1.667 E B 16 18 20 18 0.667 F D,E 13 14 21 15 1.333 G C,F 6 8 10 8 0.667