SlideShare a Scribd company logo
1 of 15
Download to read offline
Crash
Activity Successor Normal
duration
Crash
duration
Normal
cost (LE)
Crash
Cost (LE)
Constraint
Z A 4 2 2660 2800 -
A B,D 10 7 5000 5750 -
B - 5 3 3500 4900 F4,D2A
D - 8 6 7150 8150 D3C,L4E
E D 10 6 2800 3200 D5X
X E 4 2 4000 4300 F5
Y C 5 5 5000 5000 F5
C D 7 4 5000 5600 -
A project has the following activities and relationships
Contract time 20 days, Penalty Value300 LE/Day, What is your
recommendation?
Finish
X
C
E
Y
AZ B
D
Start
4
0 5
5
0 5
10
10 20
7
5 12
0
0 0
4
0 4
10
4 14
5
16 21
8
16 24
0
24 24
F5
L4
D3
D5
D2
F5
Activity Successor
Z A
A B,D
B -
D -
E D
X E
Y C
C D
15
16
14
24
21
F4
If we don’t crash the project the total cost will be as following :
Total cost = Total normal cost + Penalty cost
Total normal cost = Ʃ Normal cost for each activity
=2660+5000+3500+7150+2800+4000+5000+5000= 35110 L.E.
Penalty cost = Penalty cost per month * No. of delayed month
= 300 * 4 = 1200 L.E.
Total cost = Total normal cost + Penalty cost
= 35110 + 1200 = 36310 L.E.
In This case total time of the project will be 24 w and Contractor will
deliver the project 4 month later than the time in the contract.
To avoid this delay the crash will be applied to this network to deliver
the project as possible as contract time.
The Crash rules :
1) Apply Crash only on activities which affect the total time.
2) Crash the least cost activity according to the least cost slope
Cost Slope =
𝑪𝒓𝒂𝒔𝒉𝒆𝒅 𝒄𝒐𝒔𝒕 𝑪.𝑪. −𝑵𝒐𝒓𝒎𝒂𝒍 𝑪𝒐𝒔𝒕(𝑵.𝑪.)
𝑵𝒐𝒓𝒎𝒂𝒍 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏 (𝑵.𝑫.) −𝑪𝒓𝒂𝒔𝒉𝒆𝒅 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏 (𝑪.𝑫.)
L.E  unite time
3) Activity will be crashed according to it’s crashability
Crashability = Normal Duration(N.D.) – Crash Duration (C.D.)
The Path which need to be crashed are the paths gives total time more
than contract time (20 w)
X E D (24w 20w)
2
500
4
100
Y C D
2
500
3
200
Z A D
2
500
3
250
2
70
(23 20)
(22 20)
Z A B
1
700
3
250
2
70
(21 20)
4E = 4*100 = 400 L.E.
3C = 3 * 200 = 600 L.E.
2Z = 2 * 70 = 140 L.E.
This path is already crashed 2Z from
the previous path (Z is Shared
activity in the two paths)
Total Crashed Cost = 600 + 400 + 140 = 1140 L.E.
Another Scenario to reach contract time 20 w
X E D (24 20)
2
500
4
100
Y C D
2
500
3
200
Z A D
2
500
3
250
2
70
(23 20)
(22 20)
Z A B
2
700
3
250
2
70
(21 20)
1C = 1 * 200 = 200 L.E.
NO need for crashing this path
1Z = 70 L.E.
2E = 2 * 100 = 200 L.E.
Act. D is
shared
Act.
2D =
2*500=
1000 L.E.
Total Crashed Cost for this scenario = 1000 + 400 + 200+70 = 1470 L.E.
X E D (24w 23w)
2
500
4
100
Y C D
2
500
3
200
Z A D
2
500
3
250
2
70
(23 23)
(22 23)
Z A B
1
700
3
250
2
70
(21 23)
Total Crashed Cost = 100 L.E.
1E = 1 * 100 = 100 L.E.
NO need for crashing this path
NO need for crashing this path
NO need for crashing this path
Scenario of ending the project with in 23 w
X E D (24w 22w)
2
500
4
100
Y C D
2
500
3
200
Z A D
2
500
3
250
2
70
(23 22)
(22 22)
Z A B
1
700
3
250
2
70
(21 22)
Total Crashed Cost = 200 + 200 = 400 L.E.
2E = 2 * 100 = 200 L.E.
1C = 200 L.E.
NO need for crashing this path
NO need for crashing this path
Scenario of ending the project with in 22 w
X E D (24w 21w)
2
500
4
100
Y C D
2
500
3
200
Z A D
2
500
3
250
2
70
(23 21)
(22 21)
Z A B
1
700
3
250
2
70
(21 21)
Total Crashed Cost = 300 + 400 + 70 = 770 L.E.
3E = 3* 100 = 300 L.E.
2C = 2 * 200 = 400 L.E.
1Z = 70 L.E.
NO need for crashing this path
Scenario of ending the project with in 21 w
Total time
Total
Normal
Cost
Total
crashed
cost
Total Penalty
Value
Total cost
24 35110 0 1200 36310
23 35110 100 900 36110
22 35110 400 600 36110
21 35110 770 300 36180
20 35110 1140 0 36250
Scenarios of the different completion time of the project can be
estimated according to this table:
Respect reputation and apply scenario 20 w
Finish
X
C
E
Y
AZ B
D
Start
4
0 5
5
0 5
10 16
4
5 9
0
0 0
2
0 2
10
2 12
5
14 19
8
12 20
0
20 20
F5
L4
D3
D5
D2
F5
12
12
12
20
19
F4
6
The final executed Network
UPDATE
Feedback form site at day 5 as following:
1) Activity C will start late by 2days
2) Activity A will finish late by 2 days
Finish
X
C
E
Y
AZ B
D
Start
4
0 5
5
0 5
10 16
4
7 11
0
0 0
2
0 2
10
2 14
5
16 21
8
14 22
0
22 22
F5
L4
D3
D5
D2
F5
14
12
14
22
21
F4
6
According to feedback at day 5 during construction
the project will finish in 22 day (2 days late from
contract time) , so we need to apply crash again but
take in your consideration :
1) The activities which have been finished.
Ex: Activity X,Y and Z finished before the feedback
date and Activity C not started yet according to
feedback (not allowed to be crashed) and Activity A
has been started but will finish late according to
feedback (allowed to be crashed if possible).
1) The activities which have been crashed before.
Ex: Activity E,C and Z
Y C D
2
500
0
200
Z A D
2
500
3
250
0
70
(22 20)
(22 20)
Z A B
1
700
3
250
0
70
(21 20)
2D = 2 * 500 = 1000 L.E.
This path is already crashed 2D from
the previous path (D is Shared
activity in the two paths)
1B = 1 * 700 = 700 L.E.
Total Crashed Cost = 1000 + 700 = 1700 L.E.
The network after update
Finish
X
C
E
Y
AZ B
D
Start
4
0 5
5
0 5
10 16
4
7 11
0
0 0
2
0 2
10
2 14
4
16 20
6
14 20
0
20 20
F5
L4
D3
D5
D2
F5
14
12
14
20
20
F4
6

More Related Content

What's hot

Fundamentos de programación
Fundamentos de programaciónFundamentos de programación
Fundamentos de programaciónDiego Garcia
 
26. composite l2qtouchpad
26. composite l2qtouchpad26. composite l2qtouchpad
26. composite l2qtouchpadMedia4math
 
Decimal arithematic operation
Decimal arithematic operationDecimal arithematic operation
Decimal arithematic operationPadmapriyaG
 
Applications of calculus in commerce and economics ii
Applications of calculus in commerce and economics ii Applications of calculus in commerce and economics ii
Applications of calculus in commerce and economics ii sumanmathews
 
Equations bingo (easy)
Equations bingo (easy)Equations bingo (easy)
Equations bingo (easy)harlie90
 
Lp simplex method example in construction managment
Lp simplex method example in construction managmentLp simplex method example in construction managment
Lp simplex method example in construction managmentNaghamNagham
 
App inventor独自カラー
App inventor独自カラーApp inventor独自カラー
App inventor独自カラーKenichi Yoshida
 
Engineering Graphics
Engineering Graphics Engineering Graphics
Engineering Graphics Nishit Karkar
 
คู่มือการใช้ Casiofx5800 p surveyingprograms
คู่มือการใช้ Casiofx5800 p surveyingprogramsคู่มือการใช้ Casiofx5800 p surveyingprograms
คู่มือการใช้ Casiofx5800 p surveyingprogramsTherdkeat Khuonhat
 
Metodo estatico equivalente jessica garcia
Metodo estatico equivalente jessica garciaMetodo estatico equivalente jessica garcia
Metodo estatico equivalente jessica garciaJESSICA GARCIA
 
Applications of calculus in commerce and economics
Applications of calculus in commerce and economicsApplications of calculus in commerce and economics
Applications of calculus in commerce and economicssumanmathews
 
Matlab Assignment JK Institute
Matlab Assignment JK InstituteMatlab Assignment JK Institute
Matlab Assignment JK InstituteOm Prakash
 
Calculus 45S Slides May 14, 2008
Calculus 45S Slides May 14, 2008Calculus 45S Slides May 14, 2008
Calculus 45S Slides May 14, 2008Darren Kuropatwa
 

What's hot (20)

Fundamentos de programación
Fundamentos de programaciónFundamentos de programación
Fundamentos de programación
 
K3+2.86
 K3+2.86 K3+2.86
K3+2.86
 
26. composite l2qtouchpad
26. composite l2qtouchpad26. composite l2qtouchpad
26. composite l2qtouchpad
 
Decimal arithematic operation
Decimal arithematic operationDecimal arithematic operation
Decimal arithematic operation
 
Bryan
BryanBryan
Bryan
 
c language programing
c language programing c language programing
c language programing
 
Applications of calculus in commerce and economics ii
Applications of calculus in commerce and economics ii Applications of calculus in commerce and economics ii
Applications of calculus in commerce and economics ii
 
Equations bingo (easy)
Equations bingo (easy)Equations bingo (easy)
Equations bingo (easy)
 
Lp simplex method example in construction managment
Lp simplex method example in construction managmentLp simplex method example in construction managment
Lp simplex method example in construction managment
 
App inventor独自カラー
App inventor独自カラーApp inventor独自カラー
App inventor独自カラー
 
q
qq
q
 
Engineering Graphics
Engineering Graphics Engineering Graphics
Engineering Graphics
 
คู่มือการใช้ Casiofx5800 p surveyingprograms
คู่มือการใช้ Casiofx5800 p surveyingprogramsคู่มือการใช้ Casiofx5800 p surveyingprograms
คู่มือการใช้ Casiofx5800 p surveyingprograms
 
Metodo estatico equivalente jessica garcia
Metodo estatico equivalente jessica garciaMetodo estatico equivalente jessica garcia
Metodo estatico equivalente jessica garcia
 
Figures
FiguresFigures
Figures
 
Applications of calculus in commerce and economics
Applications of calculus in commerce and economicsApplications of calculus in commerce and economics
Applications of calculus in commerce and economics
 
Matlab Assignment JK Institute
Matlab Assignment JK InstituteMatlab Assignment JK Institute
Matlab Assignment JK Institute
 
Bryan
BryanBryan
Bryan
 
Calculus 45S Slides May 14, 2008
Calculus 45S Slides May 14, 2008Calculus 45S Slides May 14, 2008
Calculus 45S Slides May 14, 2008
 
Vector processing example
Vector processing exampleVector processing example
Vector processing example
 

Similar to Crash management

Lecture7_2021_v2.pdf
Lecture7_2021_v2.pdfLecture7_2021_v2.pdf
Lecture7_2021_v2.pdfssuserc9da59
 
W ee network_theory_10-06-17_ls2-sol
W ee network_theory_10-06-17_ls2-solW ee network_theory_10-06-17_ls2-sol
W ee network_theory_10-06-17_ls2-solAnkit Chaurasia
 
Grade 9 Q4-W1_Uniformly Accelerated Motion.pptx
Grade 9 Q4-W1_Uniformly Accelerated Motion.pptxGrade 9 Q4-W1_Uniformly Accelerated Motion.pptx
Grade 9 Q4-W1_Uniformly Accelerated Motion.pptxMadenCrisostomo
 
Basement wall design
Basement wall designBasement wall design
Basement wall designCETCBIM
 
DESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDINGDESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDINGAnjneya Srivastava
 
Mmup questionnaire 4
Mmup questionnaire 4Mmup questionnaire 4
Mmup questionnaire 4Omar Selim
 
Design and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadDesign and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadgopichand's
 
Design and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadDesign and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadgopichand's
 
12b applications
12b applications12b applications
12b applicationslaiba javed
 
Gradually Varied Flow in Open Channel
Gradually Varied Flow in Open ChannelGradually Varied Flow in Open Channel
Gradually Varied Flow in Open ChannelAmro Elfeki
 
All fluids-assignments
All fluids-assignmentsAll fluids-assignments
All fluids-assignmentstelmanm
 
App2_Seismic Design for RC Building.pdf
App2_Seismic Design for RC Building.pdfApp2_Seismic Design for RC Building.pdf
App2_Seismic Design for RC Building.pdfpankajchandiramani3
 
Reflections in a cubic structure
Reflections in a cubic structureReflections in a cubic structure
Reflections in a cubic structureVishnuPullanikkat
 
Lecture 5 Well Tubulars Casing String 2015.ppt
Lecture 5 Well Tubulars Casing String 2015.pptLecture 5 Well Tubulars Casing String 2015.ppt
Lecture 5 Well Tubulars Casing String 2015.pptVikramKumar158086
 
Cee 311(5)
Cee 311(5)Cee 311(5)
Cee 311(5)apudgr8
 
5 10c exercise_index the aluminum tilt series_ex on saed do not know cell pars
5 10c exercise_index the aluminum tilt series_ex on saed do not know cell pars5 10c exercise_index the aluminum tilt series_ex on saed do not know cell pars
5 10c exercise_index the aluminum tilt series_ex on saed do not know cell parsJoke Hadermann
 

Similar to Crash management (20)

Lecture7_2021_v2.pdf
Lecture7_2021_v2.pdfLecture7_2021_v2.pdf
Lecture7_2021_v2.pdf
 
W ee network_theory_10-06-17_ls2-sol
W ee network_theory_10-06-17_ls2-solW ee network_theory_10-06-17_ls2-sol
W ee network_theory_10-06-17_ls2-sol
 
Cpm crashing example
Cpm crashing exampleCpm crashing example
Cpm crashing example
 
Grade 9 Q4-W1_Uniformly Accelerated Motion.pptx
Grade 9 Q4-W1_Uniformly Accelerated Motion.pptxGrade 9 Q4-W1_Uniformly Accelerated Motion.pptx
Grade 9 Q4-W1_Uniformly Accelerated Motion.pptx
 
MODULE 8 NOTES CEM (1).pdf
MODULE 8 NOTES CEM (1).pdfMODULE 8 NOTES CEM (1).pdf
MODULE 8 NOTES CEM (1).pdf
 
Basement wall design
Basement wall designBasement wall design
Basement wall design
 
DESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDINGDESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDING
 
Mmup questionnaire 4
Mmup questionnaire 4Mmup questionnaire 4
Mmup questionnaire 4
 
ppt.pptx
ppt.pptxppt.pptx
ppt.pptx
 
Design and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadDesign and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staad
 
Design and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staadDesign and analasys of a g+3 residential building using staad
Design and analasys of a g+3 residential building using staad
 
12b applications
12b applications12b applications
12b applications
 
Gradually Varied Flow in Open Channel
Gradually Varied Flow in Open ChannelGradually Varied Flow in Open Channel
Gradually Varied Flow in Open Channel
 
All fluids-assignments
All fluids-assignmentsAll fluids-assignments
All fluids-assignments
 
App2_Seismic Design for RC Building.pdf
App2_Seismic Design for RC Building.pdfApp2_Seismic Design for RC Building.pdf
App2_Seismic Design for RC Building.pdf
 
Reflections in a cubic structure
Reflections in a cubic structureReflections in a cubic structure
Reflections in a cubic structure
 
Lecture 5 Well Tubulars Casing String 2015.ppt
Lecture 5 Well Tubulars Casing String 2015.pptLecture 5 Well Tubulars Casing String 2015.ppt
Lecture 5 Well Tubulars Casing String 2015.ppt
 
Cee 311(5)
Cee 311(5)Cee 311(5)
Cee 311(5)
 
5 10c exercise_index the aluminum tilt series_ex on saed do not know cell pars
5 10c exercise_index the aluminum tilt series_ex on saed do not know cell pars5 10c exercise_index the aluminum tilt series_ex on saed do not know cell pars
5 10c exercise_index the aluminum tilt series_ex on saed do not know cell pars
 
G.p presentation
G.p presentationG.p presentation
G.p presentation
 

More from Ahmed Gamal

Graduation book - BFRP
Graduation book - BFRPGraduation book - BFRP
Graduation book - BFRPAhmed Gamal
 
hti traininig 2018
hti traininig 2018hti traininig 2018
hti traininig 2018Ahmed Gamal
 
Resource management
Resource managementResource management
Resource managementAhmed Gamal
 
Pert2 management
Pert2 managementPert2 management
Pert2 managementAhmed Gamal
 
Pert management
Pert management Pert management
Pert management Ahmed Gamal
 
Lec 2 construction management
Lec 2 construction managementLec 2 construction management
Lec 2 construction managementAhmed Gamal
 
Earned value management
Earned value managementEarned value management
Earned value managementAhmed Gamal
 
Cm ch4 scheduling
Cm ch4 schedulingCm ch4 scheduling
Cm ch4 schedulingAhmed Gamal
 
1- construction management
1-  construction management1-  construction management
1- construction managementAhmed Gamal
 
تدريب 2 التجمع الخامس و نادي مدينتي
تدريب 2 التجمع الخامس و نادي مدينتيتدريب 2 التجمع الخامس و نادي مدينتي
تدريب 2 التجمع الخامس و نادي مدينتيAhmed Gamal
 
01 introduction and layout of steel (1)
01 introduction and layout of steel (1)01 introduction and layout of steel (1)
01 introduction and layout of steel (1)Ahmed Gamal
 
الامن الصناعي
الامن الصناعيالامن الصناعي
الامن الصناعيAhmed Gamal
 
programming fortran 77 Slide02
programming fortran 77 Slide02programming fortran 77 Slide02
programming fortran 77 Slide02Ahmed Gamal
 
programming fortran 77 Slide01
programming fortran 77 Slide01programming fortran 77 Slide01
programming fortran 77 Slide01Ahmed Gamal
 

More from Ahmed Gamal (20)

Graduation book - BFRP
Graduation book - BFRPGraduation book - BFRP
Graduation book - BFRP
 
hti traininig 2018
hti traininig 2018hti traininig 2018
hti traininig 2018
 
Resource management
Resource managementResource management
Resource management
 
Pert2 management
Pert2 managementPert2 management
Pert2 management
 
Pert management
Pert management Pert management
Pert management
 
Lob management
Lob managementLob management
Lob management
 
Lec 2 construction management
Lec 2 construction managementLec 2 construction management
Lec 2 construction management
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Cm ch4 scheduling
Cm ch4 schedulingCm ch4 scheduling
Cm ch4 scheduling
 
1- construction management
1-  construction management1-  construction management
1- construction management
 
تدريب 2 التجمع الخامس و نادي مدينتي
تدريب 2 التجمع الخامس و نادي مدينتيتدريب 2 التجمع الخامس و نادي مدينتي
تدريب 2 التجمع الخامس و نادي مدينتي
 
01 introduction and layout of steel (1)
01 introduction and layout of steel (1)01 introduction and layout of steel (1)
01 introduction and layout of steel (1)
 
الامن الصناعي
الامن الصناعيالامن الصناعي
الامن الصناعي
 
programming fortran 77 Slide02
programming fortran 77 Slide02programming fortran 77 Slide02
programming fortran 77 Slide02
 
programming fortran 77 Slide01
programming fortran 77 Slide01programming fortran 77 Slide01
programming fortran 77 Slide01
 
7 fatigue
7  fatigue7  fatigue
7 fatigue
 
5 hardness
5  hardness5  hardness
5 hardness
 
4 static shear
4  static shear4  static shear
4 static shear
 
3 bending test
3  bending test3  bending test
3 bending test
 
2 compression
2  compression2  compression
2 compression
 

Recently uploaded

Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptxAss.Prof. Dr. Mogeeb Mosleh
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
Continuous Improvement Posters for Learning
Continuous Improvement Posters for LearningContinuous Improvement Posters for Learning
Continuous Improvement Posters for LearningCIToolkit
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningCIToolkit
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...Pooja Nehwal
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 

Recently uploaded (20)

Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdfImagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
 
Continuous Improvement Posters for Learning
Continuous Improvement Posters for LearningContinuous Improvement Posters for Learning
Continuous Improvement Posters for Learning
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for Learning
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 

Crash management

  • 1. Crash Activity Successor Normal duration Crash duration Normal cost (LE) Crash Cost (LE) Constraint Z A 4 2 2660 2800 - A B,D 10 7 5000 5750 - B - 5 3 3500 4900 F4,D2A D - 8 6 7150 8150 D3C,L4E E D 10 6 2800 3200 D5X X E 4 2 4000 4300 F5 Y C 5 5 5000 5000 F5 C D 7 4 5000 5600 - A project has the following activities and relationships Contract time 20 days, Penalty Value300 LE/Day, What is your recommendation?
  • 2. Finish X C E Y AZ B D Start 4 0 5 5 0 5 10 10 20 7 5 12 0 0 0 4 0 4 10 4 14 5 16 21 8 16 24 0 24 24 F5 L4 D3 D5 D2 F5 Activity Successor Z A A B,D B - D - E D X E Y C C D 15 16 14 24 21 F4
  • 3. If we don’t crash the project the total cost will be as following : Total cost = Total normal cost + Penalty cost Total normal cost = Ʃ Normal cost for each activity =2660+5000+3500+7150+2800+4000+5000+5000= 35110 L.E. Penalty cost = Penalty cost per month * No. of delayed month = 300 * 4 = 1200 L.E. Total cost = Total normal cost + Penalty cost = 35110 + 1200 = 36310 L.E. In This case total time of the project will be 24 w and Contractor will deliver the project 4 month later than the time in the contract. To avoid this delay the crash will be applied to this network to deliver the project as possible as contract time.
  • 4. The Crash rules : 1) Apply Crash only on activities which affect the total time. 2) Crash the least cost activity according to the least cost slope Cost Slope = 𝑪𝒓𝒂𝒔𝒉𝒆𝒅 𝒄𝒐𝒔𝒕 𝑪.𝑪. −𝑵𝒐𝒓𝒎𝒂𝒍 𝑪𝒐𝒔𝒕(𝑵.𝑪.) 𝑵𝒐𝒓𝒎𝒂𝒍 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏 (𝑵.𝑫.) −𝑪𝒓𝒂𝒔𝒉𝒆𝒅 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏 (𝑪.𝑫.) L.E unite time 3) Activity will be crashed according to it’s crashability Crashability = Normal Duration(N.D.) – Crash Duration (C.D.)
  • 5. The Path which need to be crashed are the paths gives total time more than contract time (20 w) X E D (24w 20w) 2 500 4 100 Y C D 2 500 3 200 Z A D 2 500 3 250 2 70 (23 20) (22 20) Z A B 1 700 3 250 2 70 (21 20) 4E = 4*100 = 400 L.E. 3C = 3 * 200 = 600 L.E. 2Z = 2 * 70 = 140 L.E. This path is already crashed 2Z from the previous path (Z is Shared activity in the two paths) Total Crashed Cost = 600 + 400 + 140 = 1140 L.E.
  • 6. Another Scenario to reach contract time 20 w X E D (24 20) 2 500 4 100 Y C D 2 500 3 200 Z A D 2 500 3 250 2 70 (23 20) (22 20) Z A B 2 700 3 250 2 70 (21 20) 1C = 1 * 200 = 200 L.E. NO need for crashing this path 1Z = 70 L.E. 2E = 2 * 100 = 200 L.E. Act. D is shared Act. 2D = 2*500= 1000 L.E. Total Crashed Cost for this scenario = 1000 + 400 + 200+70 = 1470 L.E.
  • 7. X E D (24w 23w) 2 500 4 100 Y C D 2 500 3 200 Z A D 2 500 3 250 2 70 (23 23) (22 23) Z A B 1 700 3 250 2 70 (21 23) Total Crashed Cost = 100 L.E. 1E = 1 * 100 = 100 L.E. NO need for crashing this path NO need for crashing this path NO need for crashing this path Scenario of ending the project with in 23 w
  • 8. X E D (24w 22w) 2 500 4 100 Y C D 2 500 3 200 Z A D 2 500 3 250 2 70 (23 22) (22 22) Z A B 1 700 3 250 2 70 (21 22) Total Crashed Cost = 200 + 200 = 400 L.E. 2E = 2 * 100 = 200 L.E. 1C = 200 L.E. NO need for crashing this path NO need for crashing this path Scenario of ending the project with in 22 w
  • 9. X E D (24w 21w) 2 500 4 100 Y C D 2 500 3 200 Z A D 2 500 3 250 2 70 (23 21) (22 21) Z A B 1 700 3 250 2 70 (21 21) Total Crashed Cost = 300 + 400 + 70 = 770 L.E. 3E = 3* 100 = 300 L.E. 2C = 2 * 200 = 400 L.E. 1Z = 70 L.E. NO need for crashing this path Scenario of ending the project with in 21 w
  • 10. Total time Total Normal Cost Total crashed cost Total Penalty Value Total cost 24 35110 0 1200 36310 23 35110 100 900 36110 22 35110 400 600 36110 21 35110 770 300 36180 20 35110 1140 0 36250 Scenarios of the different completion time of the project can be estimated according to this table: Respect reputation and apply scenario 20 w
  • 11. Finish X C E Y AZ B D Start 4 0 5 5 0 5 10 16 4 5 9 0 0 0 2 0 2 10 2 12 5 14 19 8 12 20 0 20 20 F5 L4 D3 D5 D2 F5 12 12 12 20 19 F4 6 The final executed Network
  • 12. UPDATE Feedback form site at day 5 as following: 1) Activity C will start late by 2days 2) Activity A will finish late by 2 days Finish X C E Y AZ B D Start 4 0 5 5 0 5 10 16 4 7 11 0 0 0 2 0 2 10 2 14 5 16 21 8 14 22 0 22 22 F5 L4 D3 D5 D2 F5 14 12 14 22 21 F4 6
  • 13. According to feedback at day 5 during construction the project will finish in 22 day (2 days late from contract time) , so we need to apply crash again but take in your consideration : 1) The activities which have been finished. Ex: Activity X,Y and Z finished before the feedback date and Activity C not started yet according to feedback (not allowed to be crashed) and Activity A has been started but will finish late according to feedback (allowed to be crashed if possible). 1) The activities which have been crashed before. Ex: Activity E,C and Z
  • 14. Y C D 2 500 0 200 Z A D 2 500 3 250 0 70 (22 20) (22 20) Z A B 1 700 3 250 0 70 (21 20) 2D = 2 * 500 = 1000 L.E. This path is already crashed 2D from the previous path (D is Shared activity in the two paths) 1B = 1 * 700 = 700 L.E. Total Crashed Cost = 1000 + 700 = 1700 L.E.
  • 15. The network after update Finish X C E Y AZ B D Start 4 0 5 5 0 5 10 16 4 7 11 0 0 0 2 0 2 10 2 14 4 16 20 6 14 20 0 20 20 F5 L4 D3 D5 D2 F5 14 12 14 20 20 F4 6