This document provides steps for crashing a project schedule to reduce its duration. It begins by explaining the two types of activity durations: normal and crash. It then outlines 9 steps to determine the maximum possible time reduction for a project: 1) draw the network diagram, 2) find the critical path using normal durations, 3) find the critical path using crash durations, 4) calculate the difference in critical paths, 5) calculate the slope for each activity, 6) select the activity with the lowest slope for crashing, 7) calculate the possible crash amount, 8) redraw the network and recalculate duration and cost, 9) compare to crashed critical path and repeat steps if different. It provides two notes: the critical path may change between