SlideShare a Scribd company logo
ASME SECTION VIII DIV 1
UG-77 Material Identification
• On completed vessel, original identification markings,
or transferred markings or coded markings (traceable
to original) shall be visible on each vessel part
• Any marking method which is acceptable to inspector
• When service conditions prohibit die-stamping, any
method with positive identification may be adopted
• When original markings are unavoidably cut, coded
markings may be adopted which shall be described in
QC system
UG-78 Repair of defects in materials
• Method & extent of repair shall be acceptable to
inspector
• Defective material that cannot be satisfactorily
repaired shall be rejected
UG-84 Charpy Impact Tests
• Production Test Coupons
– Test plate shall be from one of heats of vessel
– For category A joint, test plate shall, where
practicable, be welded as an extension to end of
production joint
– For category B joint (welded using different welding
procedure than used on category A joints, test plate
shall be welded under production welding
conditions used for vessel, using same type of
equipment and at same location and using same
procedures as used for joint and it shall be welded
concurrently with production welds or as closed to
start of production welding as practicable
UG-84 Charpy Impact Tests
• Production Test Coupon
– One test plate for each welding procedure for
categories A & B
– For automatic or semi automatic welding, one test
plate in each position
– For manual welding, vertical upward welded test
plate qualify for all position.
– If PTC fails to meet the impact requirements, welds
represented shall be unacceptable. Reheat treatment
and retesting or retesting only are permitted.
UW-3 Weld joint category
• Defines the location of a joint in a vessel
• Established for use in specifying joint type and degree
of inspection
• Based on service, material and thickness, special
requirements are specified in code
– Category A
– Category B
– Category C
– Category D
UW-3 Weld joint category
UW-11 Radiographic & Ultrasonic Examination
• Full radiography
– All butt welds in shell and heads of lethal service
vessels
– All butt welds with nominal thickness of weld
exceeds 38 mm or thickness specified elsewhere in
code. Category B & C butt welds in nozzles that
neither exceeds 10” size nor 29 mm wall thickness
do not require radiography
UW-11 Radiographic & Ultrasonic Examination
• Spot Radiography
– Butt welds of type 1 or 2 of table UW-12 which are
not required to be fully radiographed
– If spot radiography is specified for the entire vessel,
RT is not required for category B & C welds in
nozzles or communicating chamber that neither
exceeds NPS 10 nor 29 mm wall thickness
• No Radiography
– No radiography is required when the vessel or vessel
part is designed for external pressure only or when
the joint design complies with UW-12(C)
UW-26 General
• All welding shall be performed in accordance with
Manufacturer’s WPS in accordance with the
requirements of Sec IX
• All welders shall be qualified by Manufacturer in
accordance with the requirements of Sec IX
• Assign welder identification symbol
UW-32 Cleaning of surfaces to be welded
• Surfaces shall be clean and free of scale, rust, oil,
grease, slag, detrimental oxides and other deleterious
foreign material
• When metal is to be deposited over a previously welded
surface, all slag shall be removed by a roughing tool,
chisel, chipping hammer or other suitable means
UW-33 Alignment tolerances
• Alignment of sections at edges shall be such that
maximum offset is not greater than limit given in Table
UW-33
• Allowable offset shall be faired at a 3:1 taper over
width of finished weld, or if necessary, by adding
additional weld metal
UW-35 Finished Long & Circ Joints
UW-37 Miscellaneous Welding Requirements
• Welder & welding operator identification
– Stamp identifying number, letter or symbol on or
adjacent to and at intervals of not more than 1 m
along the welds in steel plates >= 6 mm and for non
ferrous plates >= 13 mm in thickness
– Stencil or other marking in welds in steel plates < 6
mm and for non ferrous plates < 13 mm in
thickness
– Record of welders / WOs employed on each joints
shall be kept
– For multiple welds, tube to tube sheet welds, QA
system shall have a procedure to identify welders or
welding operators
• Imperfections are unacceptable under following
condition
– Any crack or incomplete fusion or penetration
– Any elongated indication which has length greater
than
• 6 mm for t upto 19 mm
• 1/3t for t from 19 mm to 57 mm
• 19 mm for t over 57 mm
UW-51 Radiographic Examination of Welded Joints
UW-52 Spot Examination of Welded Joints
• One spot shall be examined for each 15 m increment
• Sufficient number of spot radiographs shall be taken to
examine welding of each welder or welding operator
• Location of spot shall be chosen by the Inspector
• Radiographs required at specific locations to satisfy
rules of other paragraphs shall not be used to satisfy
the requirements of spot radiography
• Minimum length of spot shall be 6 inch
UW-52 Spot Examination of Welded Joints
• Any crack or lack of fusion/penetration is unacceptable
• Any slag inclusions or cavities
– with length more than 2/3t shall be unacceptable
– If several indications within above limitations are in
line, weld is acceptable if sum of the longest
dimensions of all such indication is not more than t
in length of 6t and if longest indications considered
are separated by at least 3L where L is length of
longest indication
– Max. length of longest indication shall be 19 mm
– Less than 6 mm shall be acceptable
UCS-57 Radiographic Examination
• In addition to UW-11, RT is required for butt welds
which exceed thickness limit specified in Table UCS-57
App 6 - MPE & App 8 - LPE
• Acceptance standard
– All surfaces to be examined shall be free of
• Relevant linear indications
• Relevant rounded indications greater than 5 mm
• Four or more relevant rounded indication in a
line separated by 1.5 mm or less, edge to edge
Appendix 12 Ultrasonic Examination of welds
• Indications characterized as cracks, lack of fusion or
incomplete penetration are unacceptable regardless of
length
• Other imperfections are unacceptable if indications
exceed reference level amplitude and have lengths
which exceed
– 6 mm for t upto 19 mm
– 1/3t for t from 19 mm to 57 mm
– 19 mm for t over 57 mm

More Related Content

What's hot

ASME BOILER & PRESSURE SECTION VIII.ppt
ASME BOILER & PRESSURE SECTION VIII.pptASME BOILER & PRESSURE SECTION VIII.ppt
ASME BOILER & PRESSURE SECTION VIII.ppt
hesham ismail
 
Asme viii Div. 1 presentation rev.0
Asme viii Div. 1  presentation   rev.0Asme viii Div. 1  presentation   rev.0
Asme viii Div. 1 presentation rev.0
Mohammad Mahrous
 
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Varun Patel
 
Asme sec viii div 1 icb
Asme sec viii div 1 icbAsme sec viii div 1 icb
Asme sec viii div 1 icb
Praj Industries Ltd.
 
Inspection manual for piping
Inspection manual for pipingInspection manual for piping
Inspection manual for piping
Khiem Vo Duy
 
How to produce PQR
How to produce PQRHow to produce PQR
How to produce PQR
Mohamed Farouk
 
Procedure qualification
Procedure qualificationProcedure qualification
Procedure qualification
vaasuBandaru
 
Methods of examination of joints(RT) - API 650 Tanks
Methods of examination of joints(RT) - API 650 TanksMethods of examination of joints(RT) - API 650 Tanks
Methods of examination of joints(RT) - API 650 Tanks
RajSamy
 
How to review wps part 1 (mau company)
How to review wps part 1 (mau company)How to review wps part 1 (mau company)
How to review wps part 1 (mau company)
Mohamed Farouk
 
ASME Section VIII Div 1. design training
ASME Section VIII Div 1.  design trainingASME Section VIII Div 1.  design training
ASME Section VIII Div 1. design training
Sam Jose
 
criteria of weld defects
criteria of weld defects criteria of weld defects
criteria of weld defects
Saqib Rasool
 
Presentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptxPresentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptx
hesham ismail
 
Saes w-011-welding on plot ( process ) piping
Saes w-011-welding on plot ( process ) pipingSaes w-011-welding on plot ( process ) piping
Saes w-011-welding on plot ( process ) piping
abhi10apr
 
Asme sec. ix bkr - 051010
Asme sec. ix   bkr - 051010Asme sec. ix   bkr - 051010
Asme sec. ix bkr - 051010
Jithu John
 
Piping components, materials, codes and standards part 1- pipe
Piping components, materials, codes and standards   part 1- pipePiping components, materials, codes and standards   part 1- pipe
Piping components, materials, codes and standards part 1- pipe
Alireza Niakani
 

What's hot (20)

ASME BOILER & PRESSURE SECTION VIII.ppt
ASME BOILER & PRESSURE SECTION VIII.pptASME BOILER & PRESSURE SECTION VIII.ppt
ASME BOILER & PRESSURE SECTION VIII.ppt
 
API_510_for_Exam.pdf
API_510_for_Exam.pdfAPI_510_for_Exam.pdf
API_510_for_Exam.pdf
 
Presentation on SECVIII
Presentation on SECVIIIPresentation on SECVIII
Presentation on SECVIII
 
Asme viii Div. 1 presentation rev.0
Asme viii Div. 1  presentation   rev.0Asme viii Div. 1  presentation   rev.0
Asme viii Div. 1 presentation rev.0
 
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
 
Asme sec viii div 1 icb
Asme sec viii div 1 icbAsme sec viii div 1 icb
Asme sec viii div 1 icb
 
Inspection manual for piping
Inspection manual for pipingInspection manual for piping
Inspection manual for piping
 
How to produce PQR
How to produce PQRHow to produce PQR
How to produce PQR
 
Question bank
Question bankQuestion bank
Question bank
 
Procedure qualification
Procedure qualificationProcedure qualification
Procedure qualification
 
Methods of examination of joints(RT) - API 650 Tanks
Methods of examination of joints(RT) - API 650 TanksMethods of examination of joints(RT) - API 650 Tanks
Methods of examination of joints(RT) - API 650 Tanks
 
How to review wps part 1 (mau company)
How to review wps part 1 (mau company)How to review wps part 1 (mau company)
How to review wps part 1 (mau company)
 
ASME Section VIII Div 1. design training
ASME Section VIII Div 1.  design trainingASME Section VIII Div 1.  design training
ASME Section VIII Div 1. design training
 
Shell rolling procedure
Shell rolling procedureShell rolling procedure
Shell rolling procedure
 
Welder qualification
Welder qualificationWelder qualification
Welder qualification
 
criteria of weld defects
criteria of weld defects criteria of weld defects
criteria of weld defects
 
Presentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptxPresentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptx
 
Saes w-011-welding on plot ( process ) piping
Saes w-011-welding on plot ( process ) pipingSaes w-011-welding on plot ( process ) piping
Saes w-011-welding on plot ( process ) piping
 
Asme sec. ix bkr - 051010
Asme sec. ix   bkr - 051010Asme sec. ix   bkr - 051010
Asme sec. ix bkr - 051010
 
Piping components, materials, codes and standards part 1- pipe
Piping components, materials, codes and standards   part 1- pipePiping components, materials, codes and standards   part 1- pipe
Piping components, materials, codes and standards part 1- pipe
 

Viewers also liked

Pressure vessel manufacturing
Pressure vessel manufacturingPressure vessel manufacturing
Pressure vessel manufacturingphysics101
 
Pressure vessel types
Pressure vessel typesPressure vessel types
Pressure vessel types
Fawadulhasnain
 
Pressure vessels
Pressure vessels  Pressure vessels
Pressure vessels GPTraining
 
Vessel fabrication sequence
Vessel fabrication sequenceVessel fabrication sequence
Vessel fabrication sequence
Cameron
 
Radiographic interpretation
Radiographic interpretationRadiographic interpretation
Radiographic interpretation
moix rafiq
 
Weld ability of the new generation stainless steels
Weld ability of the new generation stainless steelsWeld ability of the new generation stainless steels
Weld ability of the new generation stainless steelsJithu John
 
Design by Analysis - A general guideline for pressure vessel
Design by Analysis - A general guideline for pressure vesselDesign by Analysis - A general guideline for pressure vessel
Design by Analysis - A general guideline for pressure vessel
AnalyzeForSafety
 

Viewers also liked (9)

Pressure vessels
Pressure vesselsPressure vessels
Pressure vessels
 
Pressure vessel manufacturing
Pressure vessel manufacturingPressure vessel manufacturing
Pressure vessel manufacturing
 
Pressure vessel types
Pressure vessel typesPressure vessel types
Pressure vessel types
 
Pressure vessels
Pressure vessels  Pressure vessels
Pressure vessels
 
Vessel fabrication sequence
Vessel fabrication sequenceVessel fabrication sequence
Vessel fabrication sequence
 
Radiographic interpretation
Radiographic interpretationRadiographic interpretation
Radiographic interpretation
 
Weld ability of the new generation stainless steels
Weld ability of the new generation stainless steelsWeld ability of the new generation stainless steels
Weld ability of the new generation stainless steels
 
Rt Acceptance
Rt AcceptanceRt Acceptance
Rt Acceptance
 
Design by Analysis - A general guideline for pressure vessel
Design by Analysis - A general guideline for pressure vesselDesign by Analysis - A general guideline for pressure vessel
Design by Analysis - A general guideline for pressure vessel
 

Similar to Asme sec viii div 1 s

asmesecviiidiv2-140726082839-phpapp01.pdf
asmesecviiidiv2-140726082839-phpapp01.pdfasmesecviiidiv2-140726082839-phpapp01.pdf
asmesecviiidiv2-140726082839-phpapp01.pdf
NithinGanesh3
 
WELDING PROCEDURES and WELDERS QUALIFICATION .ppt
WELDING PROCEDURES and WELDERS QUALIFICATION .pptWELDING PROCEDURES and WELDERS QUALIFICATION .ppt
WELDING PROCEDURES and WELDERS QUALIFICATION .ppt
mohammed194284
 
86177188-Wps-Pqr-Guide.ppt
86177188-Wps-Pqr-Guide.ppt86177188-Wps-Pqr-Guide.ppt
86177188-Wps-Pqr-Guide.ppt
peter770054
 
WPS -PQR - Welder Qualifications .pdf
WPS -PQR - Welder Qualifications .pdfWPS -PQR - Welder Qualifications .pdf
WPS -PQR - Welder Qualifications .pdf
mounirbonnois
 
Piping bv
Piping bvPiping bv
Piping bv
Lorena Barros
 
Important qualification ranges must know about welder performance
Important qualification ranges must know about welder performanceImportant qualification ranges must know about welder performance
Important qualification ranges must know about welder performance
Weld Maniac
 
Welding works in steel piping
Welding works in steel pipingWelding works in steel piping
Welding works in steel piping
Akshay Toraskar
 
Good practices in PSC work.ppt
Good practices in PSC work.pptGood practices in PSC work.ppt
Good practices in PSC work.ppt
ssusercaf1a41
 
Pipe wizard olympus
Pipe wizard olympusPipe wizard olympus
Pipe wizard olympus
Sungsoo Han
 
DP acco. to DS1-converti.pptx
DP acco. to DS1-converti.pptxDP acco. to DS1-converti.pptx
DP acco. to DS1-converti.pptx
majdijerbi3
 
Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
MOHAMMAD ATIF ALI
 
Methodology Of Fabrication_R4_19.08.16.pptx
Methodology Of Fabrication_R4_19.08.16.pptxMethodology Of Fabrication_R4_19.08.16.pptx
Methodology Of Fabrication_R4_19.08.16.pptx
harmanpnrgroup
 
Weld Defects
Weld DefectsWeld Defects
Weld Defectsadminn2
 
Welding — arc stud welding of metallic
Welding — arc stud welding of metallicWelding — arc stud welding of metallic
Welding — arc stud welding of metallic
sai anjaneya
 
Asmesectionix
Asmesectionix Asmesectionix
Asmesectionix
Nuri Cesur
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976
Southern Railway
 
Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...
Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...
Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...
Thorne & Derrick International
 
ASTM E190
ASTM E190ASTM E190
ASTM E190
Manthan Chavda
 
Mast testing ppt
Mast testing pptMast testing ppt
Mast testing ppt
ROHIT RANJAN
 

Similar to Asme sec viii div 1 s (20)

asmesecviiidiv2-140726082839-phpapp01.pdf
asmesecviiidiv2-140726082839-phpapp01.pdfasmesecviiidiv2-140726082839-phpapp01.pdf
asmesecviiidiv2-140726082839-phpapp01.pdf
 
WELDING PROCEDURES and WELDERS QUALIFICATION .ppt
WELDING PROCEDURES and WELDERS QUALIFICATION .pptWELDING PROCEDURES and WELDERS QUALIFICATION .ppt
WELDING PROCEDURES and WELDERS QUALIFICATION .ppt
 
86177188-Wps-Pqr-Guide.ppt
86177188-Wps-Pqr-Guide.ppt86177188-Wps-Pqr-Guide.ppt
86177188-Wps-Pqr-Guide.ppt
 
WPS -PQR - Welder Qualifications .pdf
WPS -PQR - Welder Qualifications .pdfWPS -PQR - Welder Qualifications .pdf
WPS -PQR - Welder Qualifications .pdf
 
Piping bv
Piping bvPiping bv
Piping bv
 
Important qualification ranges must know about welder performance
Important qualification ranges must know about welder performanceImportant qualification ranges must know about welder performance
Important qualification ranges must know about welder performance
 
Welding works in steel piping
Welding works in steel pipingWelding works in steel piping
Welding works in steel piping
 
Good practices in PSC work.ppt
Good practices in PSC work.pptGood practices in PSC work.ppt
Good practices in PSC work.ppt
 
Pipe wizard olympus
Pipe wizard olympusPipe wizard olympus
Pipe wizard olympus
 
DP acco. to DS1-converti.pptx
DP acco. to DS1-converti.pptxDP acco. to DS1-converti.pptx
DP acco. to DS1-converti.pptx
 
Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
 
Methodology Of Fabrication_R4_19.08.16.pptx
Methodology Of Fabrication_R4_19.08.16.pptxMethodology Of Fabrication_R4_19.08.16.pptx
Methodology Of Fabrication_R4_19.08.16.pptx
 
Weld Defects
Weld DefectsWeld Defects
Weld Defects
 
Welding — arc stud welding of metallic
Welding — arc stud welding of metallicWelding — arc stud welding of metallic
Welding — arc stud welding of metallic
 
Asmesectionix
Asmesectionix Asmesectionix
Asmesectionix
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976
 
Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...
Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...
Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...
 
ASTM E190
ASTM E190ASTM E190
ASTM E190
 
Mast testing ppt
Mast testing pptMast testing ppt
Mast testing ppt
 
Module 5
Module 5Module 5
Module 5
 

More from Jithu John

2. Pharmacokinetics and dynamics - KK.pptx
2. Pharmacokinetics and dynamics - KK.pptx2. Pharmacokinetics and dynamics - KK.pptx
2. Pharmacokinetics and dynamics - KK.pptx
Jithu John
 
my ppt.pptx
my ppt.pptxmy ppt.pptx
my ppt.pptx
Jithu John
 
9 belzona-2 - compliant repairs
9 belzona-2 - compliant repairs9 belzona-2 - compliant repairs
9 belzona-2 - compliant repairs
Jithu John
 
2 eliminate hidden riskof cui
2 eliminate hidden riskof cui2 eliminate hidden riskof cui
2 eliminate hidden riskof cui
Jithu John
 
Oil refinery processes
Oil refinery processesOil refinery processes
Oil refinery processes
Jithu John
 
Asme section ii c new
Asme section ii c newAsme section ii c new
Asme section ii c new
Jithu John
 
Saudi aramco standards
Saudi aramco standardsSaudi aramco standards
Saudi aramco standards
Jithu John
 
Alignment
AlignmentAlignment
Alignment
Jithu John
 
100661266 cswip-3-1-2009
100661266 cswip-3-1-2009100661266 cswip-3-1-2009
100661266 cswip-3-1-2009
Jithu John
 
61769477 welding-inspection-cswip-gud
61769477 welding-inspection-cswip-gud61769477 welding-inspection-cswip-gud
61769477 welding-inspection-cswip-gud
Jithu John
 
Welding qualification a
Welding qualification aWelding qualification a
Welding qualification aJithu John
 

More from Jithu John (12)

2. Pharmacokinetics and dynamics - KK.pptx
2. Pharmacokinetics and dynamics - KK.pptx2. Pharmacokinetics and dynamics - KK.pptx
2. Pharmacokinetics and dynamics - KK.pptx
 
my ppt.pptx
my ppt.pptxmy ppt.pptx
my ppt.pptx
 
9 belzona-2 - compliant repairs
9 belzona-2 - compliant repairs9 belzona-2 - compliant repairs
9 belzona-2 - compliant repairs
 
2 eliminate hidden riskof cui
2 eliminate hidden riskof cui2 eliminate hidden riskof cui
2 eliminate hidden riskof cui
 
Oil refinery processes
Oil refinery processesOil refinery processes
Oil refinery processes
 
Asme section ii c new
Asme section ii c newAsme section ii c new
Asme section ii c new
 
Saudi aramco standards
Saudi aramco standardsSaudi aramco standards
Saudi aramco standards
 
Alignment
AlignmentAlignment
Alignment
 
100661266 cswip-3-1-2009
100661266 cswip-3-1-2009100661266 cswip-3-1-2009
100661266 cswip-3-1-2009
 
61769477 welding-inspection-cswip-gud
61769477 welding-inspection-cswip-gud61769477 welding-inspection-cswip-gud
61769477 welding-inspection-cswip-gud
 
Weld defects
Weld defectsWeld defects
Weld defects
 
Welding qualification a
Welding qualification aWelding qualification a
Welding qualification a
 

Recently uploaded

LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 

Recently uploaded (20)

LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 

Asme sec viii div 1 s

  • 2. UG-77 Material Identification • On completed vessel, original identification markings, or transferred markings or coded markings (traceable to original) shall be visible on each vessel part • Any marking method which is acceptable to inspector • When service conditions prohibit die-stamping, any method with positive identification may be adopted • When original markings are unavoidably cut, coded markings may be adopted which shall be described in QC system
  • 3. UG-78 Repair of defects in materials • Method & extent of repair shall be acceptable to inspector • Defective material that cannot be satisfactorily repaired shall be rejected
  • 4. UG-84 Charpy Impact Tests • Production Test Coupons – Test plate shall be from one of heats of vessel – For category A joint, test plate shall, where practicable, be welded as an extension to end of production joint – For category B joint (welded using different welding procedure than used on category A joints, test plate shall be welded under production welding conditions used for vessel, using same type of equipment and at same location and using same procedures as used for joint and it shall be welded concurrently with production welds or as closed to start of production welding as practicable
  • 5. UG-84 Charpy Impact Tests • Production Test Coupon – One test plate for each welding procedure for categories A & B – For automatic or semi automatic welding, one test plate in each position – For manual welding, vertical upward welded test plate qualify for all position. – If PTC fails to meet the impact requirements, welds represented shall be unacceptable. Reheat treatment and retesting or retesting only are permitted.
  • 6. UW-3 Weld joint category • Defines the location of a joint in a vessel • Established for use in specifying joint type and degree of inspection • Based on service, material and thickness, special requirements are specified in code – Category A – Category B – Category C – Category D
  • 7. UW-3 Weld joint category
  • 8. UW-11 Radiographic & Ultrasonic Examination • Full radiography – All butt welds in shell and heads of lethal service vessels – All butt welds with nominal thickness of weld exceeds 38 mm or thickness specified elsewhere in code. Category B & C butt welds in nozzles that neither exceeds 10” size nor 29 mm wall thickness do not require radiography
  • 9. UW-11 Radiographic & Ultrasonic Examination • Spot Radiography – Butt welds of type 1 or 2 of table UW-12 which are not required to be fully radiographed – If spot radiography is specified for the entire vessel, RT is not required for category B & C welds in nozzles or communicating chamber that neither exceeds NPS 10 nor 29 mm wall thickness • No Radiography – No radiography is required when the vessel or vessel part is designed for external pressure only or when the joint design complies with UW-12(C)
  • 10. UW-26 General • All welding shall be performed in accordance with Manufacturer’s WPS in accordance with the requirements of Sec IX • All welders shall be qualified by Manufacturer in accordance with the requirements of Sec IX • Assign welder identification symbol
  • 11. UW-32 Cleaning of surfaces to be welded • Surfaces shall be clean and free of scale, rust, oil, grease, slag, detrimental oxides and other deleterious foreign material • When metal is to be deposited over a previously welded surface, all slag shall be removed by a roughing tool, chisel, chipping hammer or other suitable means
  • 12. UW-33 Alignment tolerances • Alignment of sections at edges shall be such that maximum offset is not greater than limit given in Table UW-33 • Allowable offset shall be faired at a 3:1 taper over width of finished weld, or if necessary, by adding additional weld metal
  • 13. UW-35 Finished Long & Circ Joints
  • 14. UW-37 Miscellaneous Welding Requirements • Welder & welding operator identification – Stamp identifying number, letter or symbol on or adjacent to and at intervals of not more than 1 m along the welds in steel plates >= 6 mm and for non ferrous plates >= 13 mm in thickness – Stencil or other marking in welds in steel plates < 6 mm and for non ferrous plates < 13 mm in thickness – Record of welders / WOs employed on each joints shall be kept – For multiple welds, tube to tube sheet welds, QA system shall have a procedure to identify welders or welding operators
  • 15. • Imperfections are unacceptable under following condition – Any crack or incomplete fusion or penetration – Any elongated indication which has length greater than • 6 mm for t upto 19 mm • 1/3t for t from 19 mm to 57 mm • 19 mm for t over 57 mm UW-51 Radiographic Examination of Welded Joints
  • 16. UW-52 Spot Examination of Welded Joints • One spot shall be examined for each 15 m increment • Sufficient number of spot radiographs shall be taken to examine welding of each welder or welding operator • Location of spot shall be chosen by the Inspector • Radiographs required at specific locations to satisfy rules of other paragraphs shall not be used to satisfy the requirements of spot radiography • Minimum length of spot shall be 6 inch
  • 17. UW-52 Spot Examination of Welded Joints • Any crack or lack of fusion/penetration is unacceptable • Any slag inclusions or cavities – with length more than 2/3t shall be unacceptable – If several indications within above limitations are in line, weld is acceptable if sum of the longest dimensions of all such indication is not more than t in length of 6t and if longest indications considered are separated by at least 3L where L is length of longest indication – Max. length of longest indication shall be 19 mm – Less than 6 mm shall be acceptable
  • 18. UCS-57 Radiographic Examination • In addition to UW-11, RT is required for butt welds which exceed thickness limit specified in Table UCS-57
  • 19. App 6 - MPE & App 8 - LPE • Acceptance standard – All surfaces to be examined shall be free of • Relevant linear indications • Relevant rounded indications greater than 5 mm • Four or more relevant rounded indication in a line separated by 1.5 mm or less, edge to edge
  • 20. Appendix 12 Ultrasonic Examination of welds • Indications characterized as cracks, lack of fusion or incomplete penetration are unacceptable regardless of length • Other imperfections are unacceptable if indications exceed reference level amplitude and have lengths which exceed – 6 mm for t upto 19 mm – 1/3t for t from 19 mm to 57 mm – 19 mm for t over 57 mm