SlideShare a Scribd company logo
SETCORE
Introduction
DRILL PIPE STANDERS
DRILL
PIPE
NEW DRILL PIPE
USED DRILL PIPE
API
DS-1
Used Drill Stem
Elements
DS-1 3rd edition
DS-1
TH Hill
4th edition
DS-1 Volume 3 - 4th edition
Volume 3
Inspection of Drill String
Equipment
consisting of a single
piece with no component
pieces
Drill Pipe
Drill Collars
Subs
Pup Joints
What are the major enhancements for DS‐1®
Fourth Edition compared to Third
Edition?
Volume 3:
 Add procedures cover hard-banding
(re‐application and inspection) and tool
joint build up.
 Expand dimensional and visual inspection
procedures for new proprietary
connections.
 Move seven procedures covering Specialty
Tools to Volume 4.
Standard DS1:
■Standards for Inspection- Accepting &Rejecting
used drill Pipes.
■Drill Stem Inspection covering wide range of
components.
■ specific Procedures & Methodology.
■ Flexible options.
■ Training & Qualifications.
■ Calibration mandatory requirement.
■Quality Control measures outlined for equipment &
processes.
INTRODUCTION
Specifying the inspectionprogram
Inspection Procedures
DS-1 CONTENTS
Failure Analysis
Fitness for Purpose
List of Table
Drill Pipe Inspection
Recommended Inspection Programs for DP (Page
18).
The inspection program
defines:
(a)Which inspection methods will be applied to each
drill stem component.
(b)How each inspection method must be conducted
in a step-by-step procedure.
(c)What acceptance criteria will be in effect during
inspection -- that is, the user’s definition of “good”
and “bad”.
Features covered by Inspection
Drill Pipe
Inspection
5
4
DS-1
Category
2 3
1
TUBE
BODY
Visual Tube
OD Gauging
UT Wall Thickness
Checks
Electromagnetic
Scanning MPI /Slip
Area
UT Slip Area
TOOL
JOINT
Visual Connection
Fluorescent MPI of
connection Thread profiling
w/gauge OD/ID Gauging
Seal width/Condition
Shoulder width
Bevel Diameter
Seal Flatness
Counter-bore
depth
**DS1 Category 5 is intended for drill string
components that are to be used in extremely
adverse conditions where the potential cost of
failure is very large. DS1 Category 5 includes the
Ultrasonic End Area Inspection of Upset and Slip
areas of the Drill pipe, where the accumulated
fatigue at both the areas together contribute 96%
probability of failure.
Chapter 3: (Page 31)
(INSPECTION PROCEDURES)
3.4 Visual Tube Inspection
This procedure covers visual
examination of internal/external surfaces of drill
pipe.
-Apparatus:
Paint marker, Pit depth gage, ultrasonic gage,
Spot light
3.4.4 Procedure and acceptance criteria: (page32)
a.External Surface imperfection on pipe shall be measured and the
depth subtracted from average adjacent wall thickness to determine
the remaining wall thickness under the imperfection and compared to
acceptance criteria
listed in table 3.5.1 (Reject if found less than criteria)
b.Pipe with extensive raised metal in the slip area may be pulled out
without further inspection at the discretion of the inspection company
and customer.
c. Raised metal on the pipe may be removed if permitted by the
customer and the owner of the pipe.
d.The minimum illumination level shall be 50
foot-candles
e.ID pitting shall not exceed 1/8” in depth as
visually estimated for premium class NWDP.
For class 2 NWDP Pitting shall not exceed 3/16”
f.The tubes shall not be visibly crooked by more
than 3” over the entire length or 0.5” in first 5”
from either end.
-MPI shall be done on the straightened tube
section and 2 feet in either side.
g. The ID surface of internally coated pipe shall be
examined for signs of deterioration of the coating.
-Tubes with coating Reference condition 3 or 4
shall be rejected unless waived by the
customer.(Fig 3.4.1)
3.5 OD Gage TubeInspection (Page 33)
This procedure covers the full length mechanical gaging of the tube
for outside diameter variations.
-Apparatus:
Go-no-go type gages.
Any electronic, dial, or vernierdevice.
Fixed setting standards for fielduse.
-The OD gage calibration shall be verified at the applicable maximum
and minimum OD values given in table 3.6.1 & 3.6.2.
3.5.5 Procedure
a. The tube shall be gaged from upset to-
upset by dragging the gage along the tube
length while rotating the pipe.
- The pipe shall roll at least one revolution
for every 5 feet of length inspected.
b. Acceptance criteria found in Table3.6.1.
3.6 UT Wall thickness inspection (Page.34)
This procedure covers the UT measurement of
DP wall thickness of the tube near the center
of the tube and at points of obvious wear.
-Apparatus
Pulse-echo type
Separate transmit and received transducer
with no worn to degree that makes visible
gap.
b. The same couplant shall be used in both
calibration and gaging.
c. Reference stander properties
 -The same acoustic properties of pipe being
inspected
 Shall have two thicknesses that meet the
following
• Thick section= nominal wall, +0.100, -0”
• Thin section=70%of nominal, +0, -0.100”
d. Minimum and maximum values of thick and
thin section found at Table 3.6.1 & 3.6.2 .
3.6.4 Procedure:
a. Parting line
Line between transmit and receive elements on
the two element transducer, It shall be held
perpendicular to the longitudinal axis of the pipe.
b. Readings shall be taken within one foot of the
center on each tube.
c. Readings shall be taken within 1” radius at the
lowest reading area.
Acceptance criteria found at table 3.6.1 & 3.6.2.
Classification of used NWDP tube:
-Dimensional acceptance criteria for used NWDP tube meet
requirements of table 1A(3.6.1-DS-1).
CONDITION PREMIUM CLASS CLASS 2
Min. remaining WT ≤ 80% ≤ 70%
Slip cuts Depth ≥ 10% of Avg. adj. Wall ≥ 20% of Avg. adj. Wall
Diameter reduction ≥ 3 % of specified OD ≥ 4 % of specified OD
Diameter Increase ≥ 3 % of specified OD ≥ 4 % of specified OD
Cracks None None
3.7 Electromagnetic Inspection (EMI)(Page 35)
This procedure cover scanning for transverse
and 3D flaws using flux leakage detection
equipment.
Reference Stander
It shall be a through-wall drilled hole stander
prepared from the same nominal diameter as
the pipe to be inspected.
The hole size shall be 1/16”, +_1/64
The stander may have one hole for each
detector arranged in spiral
Standardization Of Flux Leakage Equipment
a.The reference amplitude shall be minimum 10 mm
from each detector.
b. Signal to noise ratio shall be 3 to1.
c.The reference stander shall be scanned four times
continually at the speed to be used for inspection.
d.Each signal channel must produce indication of at
least 80% of the reference amplitude.
e.Their shall not be any gap between detector and
pipe.
The unit Shall be re-standardized:
 At thestart of each job.
 After each 50 length.
 Each time the unit is turned on.
 When mechanical or electronic changes or adjustments
the mode.
 Upon completion of the job.
If previous standardization accuracy cannot be verified all
pipe run since the last one shall be re inspected after
correction.
Inspection Procedure:
 The permanent record should have serial number of
pipe and end from which scanning began.
 Each length shall be scanned from upset-to-upset.
 The head shall be propelled into the near end tool joint.
 The head turned around and propelled the full length
into the opposite tooljoint.
 The rate of scanning for EMI device shall be constant
for production and stander and for the entire length.
 Each indication exceeding 50% of the standerreference
shall be marked until a minimum of 10 area marked.
 How to prove up EMI Indication?
1. Visual mechanical measurements.
2. MPI
3. Ultrasonic (WT).
4. Other techniques as required toidentify.
 The threshold level for the flux leakage unit shall not be grater
than 80% of the reference level.
 The threshold level for thickness unit shall be the signal level
representing 85% of nominal wall thickness.
 Pipe with imperfection which don’t meet the
acceptance criteria shall be rejected.
 Areas in which flux leakage indication exceed
threshold but no imperfection can be found shall be re-
scanned and if found this shall be cause for rejection.
MPI Slip /Upset Inspection:
MPI Wet Fluorescent
Wet Non-Fluorescent
Dry Fluorescent
Dry Non-Fluorescent
 This procedure covers inspection of slip and upset
external surfaces of used DP for transfer and 3D flaws
using either dry magnetic particle with an active AC
field or wet fluorescent with an active DC field.
 The area to beinspected:
1. 36” on the tube side start from 35 or 18 pin tool joint taper.(+6”
in case of additional slip cut).
2. 48” on the tube side start from 18 Box tool joint taper.(+6” in
case of additional slip cut).
3. If this method is applied on HWDP, Center pad area includes
the first 12” of tube from intersection of the transition radius
and outside tube surface on either side of the center pad.
Fluorescent Inspection Requirements:
1. Petroleum based medium that exhibit natural fluorescent
under black light shall not be used. (Diesel and gasoline
are not acceptable).
2. Water base medium are acceptable if they wet the
surface.
3. Particle concentration shall range from 0.1 to 0.4 ml/100
ml when measure using ASTM 100 ml centrifuge.
4. The maximum pole spacing of AC yoke during
inspection shall not exceed the distance between the
poles when all segment of the yoke are perpendicular to
the grip.
5.The minimum pole spacing during inspection shall be
2”.
6.Black light intensity shall be measured with an
ultraviolet meter each time it turned on, after 8 hours of
operation. The minimum intensity shall be 1000
microwatt/cm2. at 15” from light source or at the
distance to be used in inspection.
7.Intensity of ambient visible light shall be 2 foot per
candles.(50 foot candles at dry non fluorescent
inspection)
8. Any crack is cause of rejection except the hairline
crack in hard-facing.(Grinding is not permitted).
Tool Joint Inspection
Connection Inspection
3.11 Visual Connection Inspection
This procedure used to:
1. Determine the pipe grade.
2. Evaluate the condition of the seal.
3. Evaluate the condition of the Thread.
4. Evaluate the condition of the hard-facing.
5. Evaluate the condition of the Bevel.
6. Look for evidence of box swell and pin stretch.
1. Weight and grade codes:
OD (in) Nom. Wt (lb/ft) Weight code
9.50 1
3 1/2" 13.30 (stander) 2
15.50 3
13.75 1
4 1/2" 16.60 (stander) 2
20.00 3
22.82 4
24.66 5
25.50 6
16.25 1
5"
19.50 (stander) 2
25.60 3
5 1/2" 19.20 1
21.90 2
24.70 3
Grade Grade code
E-75 E
X-95 X
G-195 G
S-135 S
DS-140 Z
DS-150 V
Acceptance Criteria:
a. The grade and weight stencil shall be marked either
the pin milled slot or the pin nick.
b. Hardbanding shall extend no more than 3/16”
above the tool joint surface with no broken or
missing areas larger than 1/8” cross the major
dimension.
c. All connection and tool joint shall be free of visible
cracks and heat checking.
d. The minimum illumination level at the inspection
surface shall be 50 foot candles.
e. The thread protector shall be applied and secured
with approximately 50-100 ft-lbs torque.
API and similar Non-Proprietary connection
Requirements:
a. Bevel Width: Anapproximate 45 degree OD bevel
at least 1/32” wide shall be present for the full
circumference.
b. Thread surfaces:
1. Thread root shall be free from any pitting.
2. Thread surfaces shall be free from imperfections that
penetrate below the thread root, occupy more than 1-
1/2” in length along the thread helix.
3. Shall be free from imperfection that exceed 1/16” in
depth or 1/8” in diameter.
c. Box swell: can be checked by:
1. Place a straightedge along the longitudinal axis of
box tool joint. If a visible gab exists, the OD must be
measured. Compare the OD at the bevel to the OD
2” (+-) ½” away from bevel.(no different more than
1/32”).
d. Seal Surfaces:
1. Shall be free of raised metal or corrosion.
2. Any pitting of the seal that estimated to exceed
1/32” in depth.
3. Any pitting occupy more than 20% of the seal width
at any given location.
e. Re-facing:
1. Re-facing limits are 1/32” on any removal.
2. 1/16”cumulatively.
f. Pin Thread Profile:
1. No visible gab between profile and thread root more than
1/16” on no more than two thread crests.(1/32” in 4
thread acco.to APIRP7G-2)
2. Uniform flank wear estimated to be to be less than 0.010”
is permissible.
3. No gap between the profile and thread flanks more than
1/64”
4. No stretch exceeding 0.006” in two inch measured by Pin
Lead.
I. Box Taper:
The box taper at the back of the thread shall be at an angle of
30o (+15, -0) .(Visually Inspected).
j. Shoulder Square-ness:
Benchmark is used to inspect if there is a possible lack of
alignment. That is visually estimated to exceed 1/64”, the
connection shall be reject.
k. Pitting in Pin ID:
Pitting at ID is visually measured to be deeper than 1/8” shall
be cause for Rejection.
l. Shoulder Flatness:
Place a straightedge across a diameter of the tool joint face and
rotating it at least 18 degree. Any visible gab shall be cause of
rejection.
Dimensional 2 Inspection
a. Box outside Diameter (OD):
1. Shall be measured 3/8” (+-1/8”) from the shoulder.
2. Two measurements shall be taken at 90 (+-10)
degrees.
3. Box shall meet the requirements of the table
2A.(3.7.1, 3.7.18, 3.7.19) at DS1.
b. Pin Inside Diameter:
1. Shall be measured under the last thread facing the
seal.(+- ¼”)
2. Shall meat the requirements of the table 2A.(3.7.1,
3.7.18, 3.7.19) at DS1.
c. Box Shoulder Width:
1. Shall be measured by placing the straightedge
longitudinally along the tool joint, extending past the
shoulder surface, and then measuring the shoulder
thickness from this extension to the counter-bore
(excluding ID and bevel).
2. It measure at the point of minimum thickness.
3. Shall meat the requirements of the table 2A.(3.7.1, 3.7.18,
3.7.19) at DS1.
d. Tong Space:
1. Shall measured from the bevel to the edge of hard-facing.
2. Shall meat the requirements of the table 2A.(3.7.1, 3.7.18,
3.7.19) at DS1.
e. Box Counter-bore Depth:
1. Depth Shall be measured (including any ID bevel)
2. Shall not be less than 9/16”.
f. Box counter-bore Diameter:
1. Shall be measured as near as possible to the
shoulder
2. Shall meat the requirements of the table 2A.(3.7.1,
3.7.18, 3.7.19) at DS1.
g. Bevel Diameter:
Outer Diameter of the contact face of the rotary shoulder
connection. It serve two purposes:
1. Protect the outer edge of the sealing face.
2. Increase the contact pressure on seal face to minimize
leaking and separation .
Shall meat the requirements of the table 2A.(3.7.1, 3.7.18,
3.7.19) at DS1.
g. Pin Neck length:
1. The distance from the 90 degree pin shoulder to the
intersection of the flank of the first full depth thread with
the pin neck (shall bemeasured).
2. Shall not exceed 9/16”.
i. Thread compound and protector:
1. Acceptable connection shall be compound overall thread.
2. Thread protector shall be applied with 50-100ft-lbs of
torque.
Inspection Tables
BEST WISHES
E-mail: soufien.ettayari@gmail.com
Mobile: 0021622055866

More Related Content

What's hot

API 653 TANK INSPECTION.pdf
API 653 TANK INSPECTION.pdfAPI 653 TANK INSPECTION.pdf
API Specification 6D Quality Specification Level (QSL)
API Specification 6D Quality Specification Level (QSL)API Specification 6D Quality Specification Level (QSL)
API Specification 6D Quality Specification Level (QSL)
Murdani Achmad Sirajo
 
Presentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptxPresentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptx
hesham ismail
 
Casing design
Casing designCasing design
Casing design
Angga Bayu
 
criteria of weld defects
criteria of weld defects criteria of weld defects
criteria of weld defects
Saqib Rasool
 
Api6 a trim_material_ratings
Api6 a trim_material_ratingsApi6 a trim_material_ratings
Api6 a trim_material_ratings
Ingeniero William Gomez
 
Installation procedures of wellhead
Installation procedures of wellheadInstallation procedures of wellhead
Installation procedures of wellhead
Elsayed Amer
 
Mudline Suspension (MLS)
Mudline Suspension (MLS)Mudline Suspension (MLS)
Mudline Suspension (MLS)
Hamidreza Shobeyri
 
3. sequances of drilling operations
3. sequances of drilling operations3. sequances of drilling operations
3. sequances of drilling operations
Elsayed Amer
 
Tech drilling-coil tubing
Tech drilling-coil tubingTech drilling-coil tubing
Tech drilling-coil tubingTito Pétro Fac
 
Well completion equipment 2. landing nipples
Well completion equipment  2. landing nipplesWell completion equipment  2. landing nipples
Well completion equipment 2. landing nipples
Elsayed Amer
 
Inspection manual for piping
Inspection manual for pipingInspection manual for piping
Inspection manual for piping
Khiem Vo Duy
 
PetroSync - IWCF Well Intervention Pressure Control Level 2
PetroSync - IWCF Well Intervention Pressure Control Level 2PetroSync - IWCF Well Intervention Pressure Control Level 2
PetroSync - IWCF Well Intervention Pressure Control Level 2
PetroSync
 
35 Insp, Ndt, Stat Reqmts Fope
35 Insp, Ndt, Stat Reqmts Fope35 Insp, Ndt, Stat Reqmts Fope
35 Insp, Ndt, Stat Reqmts Fopejubin
 
WELL COSTING
WELL COSTINGWELL COSTING
WELL COSTING
AFATous
 
Api 575 rev.2
Api 575 rev.2Api 575 rev.2
Api 575 rev.2
Ali Raheem
 
INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdf
INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdfINSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdf
INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdf
Teddy Setiady
 
Well Testing Surface safety Valve (SSV), Well Test Valves - WOM Group
Well Testing Surface safety Valve (SSV), Well Test Valves - WOM GroupWell Testing Surface safety Valve (SSV), Well Test Valves - WOM Group
Well Testing Surface safety Valve (SSV), Well Test Valves - WOM Group
womgroup
 
Tubing Landing nipples in petroleum industry
Tubing Landing nipples in petroleum industryTubing Landing nipples in petroleum industry
Tubing Landing nipples in petroleum industry
PE Mahmoud Jad
 

What's hot (20)

API 653 TANK INSPECTION.pdf
API 653 TANK INSPECTION.pdfAPI 653 TANK INSPECTION.pdf
API 653 TANK INSPECTION.pdf
 
API Specification 6D Quality Specification Level (QSL)
API Specification 6D Quality Specification Level (QSL)API Specification 6D Quality Specification Level (QSL)
API Specification 6D Quality Specification Level (QSL)
 
Presentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptxPresentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptx
 
Casing design
Casing designCasing design
Casing design
 
criteria of weld defects
criteria of weld defects criteria of weld defects
criteria of weld defects
 
Api6 a trim_material_ratings
Api6 a trim_material_ratingsApi6 a trim_material_ratings
Api6 a trim_material_ratings
 
Installation procedures of wellhead
Installation procedures of wellheadInstallation procedures of wellhead
Installation procedures of wellhead
 
Mudline Suspension (MLS)
Mudline Suspension (MLS)Mudline Suspension (MLS)
Mudline Suspension (MLS)
 
3. sequances of drilling operations
3. sequances of drilling operations3. sequances of drilling operations
3. sequances of drilling operations
 
Tech drilling-coil tubing
Tech drilling-coil tubingTech drilling-coil tubing
Tech drilling-coil tubing
 
Well completion equipment 2. landing nipples
Well completion equipment  2. landing nipplesWell completion equipment  2. landing nipples
Well completion equipment 2. landing nipples
 
Inspection manual for piping
Inspection manual for pipingInspection manual for piping
Inspection manual for piping
 
PetroSync - IWCF Well Intervention Pressure Control Level 2
PetroSync - IWCF Well Intervention Pressure Control Level 2PetroSync - IWCF Well Intervention Pressure Control Level 2
PetroSync - IWCF Well Intervention Pressure Control Level 2
 
35 Insp, Ndt, Stat Reqmts Fope
35 Insp, Ndt, Stat Reqmts Fope35 Insp, Ndt, Stat Reqmts Fope
35 Insp, Ndt, Stat Reqmts Fope
 
WELL COSTING
WELL COSTINGWELL COSTING
WELL COSTING
 
Api 575 rev.2
Api 575 rev.2Api 575 rev.2
Api 575 rev.2
 
INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdf
INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdfINSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdf
INSPECTION OF PRESSURE VESSELS TO ASME Section VIII Div. 1.pdf
 
Well Testing Surface safety Valve (SSV), Well Test Valves - WOM Group
Well Testing Surface safety Valve (SSV), Well Test Valves - WOM GroupWell Testing Surface safety Valve (SSV), Well Test Valves - WOM Group
Well Testing Surface safety Valve (SSV), Well Test Valves - WOM Group
 
Tubing Landing nipples in petroleum industry
Tubing Landing nipples in petroleum industryTubing Landing nipples in petroleum industry
Tubing Landing nipples in petroleum industry
 
Pigging In OIL INDUSTRY
Pigging In OIL INDUSTRY Pigging In OIL INDUSTRY
Pigging In OIL INDUSTRY
 

Similar to DP acco. to DS1-converti.pptx

Qualification of INFARED SPECTROSCOPY BY HIMAJA.D
Qualification of INFARED SPECTROSCOPY BY HIMAJA.DQualification of INFARED SPECTROSCOPY BY HIMAJA.D
Qualification of INFARED SPECTROSCOPY BY HIMAJA.D
himaja donthula
 
Edwards Signaling SD2W Installation Manual
Edwards Signaling SD2W Installation ManualEdwards Signaling SD2W Installation Manual
Edwards Signaling SD2W Installation Manual
JMAC Supply
 
What is Pile Integrity Test ?
What is Pile Integrity Test ?What is Pile Integrity Test ?
What is Pile Integrity Test ?
Hamed Layssi, PEng, PhD
 
10810 63 (smoke density)
10810 63 (smoke density)10810 63 (smoke density)
10810 63 (smoke density)
Samsher Singh
 
API 570 open book.pdf
API 570 open book.pdfAPI 570 open book.pdf
API 570 open book.pdf
EmmanuelMatutu
 
Pharmaceutical validation
Pharmaceutical validationPharmaceutical validation
Pharmaceutical validation
MohiniTawade
 
Liquid dye-penetrant-test-inspection-free-ndt-sample-procedure
Liquid dye-penetrant-test-inspection-free-ndt-sample-procedureLiquid dye-penetrant-test-inspection-free-ndt-sample-procedure
Liquid dye-penetrant-test-inspection-free-ndt-sample-procedure
Raznan Ramli
 
Qualification of analytical instruments
Qualification of analytical instruments Qualification of analytical instruments
Qualification of analytical instruments
PUNEET NIRMAL
 
liquid penetrant test and ultrasonic test
liquid penetrant test and ultrasonic testliquid penetrant test and ultrasonic test
liquid penetrant test and ultrasonic test
Jaya Teja
 
Qualification of GC & FTIR
Qualification of GC & FTIRQualification of GC & FTIR
Qualification of GC & FTIR
MehulJain143
 
How to interpretant leak testing specification
How to interpretant leak testing specificationHow to interpretant leak testing specification
How to interpretant leak testing specification
parham liyalestani
 
Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...
Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...
Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...
Rishabh Sirvaiya
 
stack new.pdf
stack new.pdfstack new.pdf
stack new.pdf
Athulkgopi1
 
CHEM 361 HPLC.pdf
CHEM 361 HPLC.pdfCHEM 361 HPLC.pdf
CHEM 361 HPLC.pdf
MichaelAtteh
 
Edwards Signaling SDSJ Installation Manual
Edwards Signaling SDSJ Installation ManualEdwards Signaling SDSJ Installation Manual
Edwards Signaling SDSJ Installation Manual
JMAC Supply
 
Tubular Non Destructive techniques (Remote field testing and Internal Rotary ...
Tubular Non Destructive techniques (Remote field testing and Internal Rotary ...Tubular Non Destructive techniques (Remote field testing and Internal Rotary ...
Tubular Non Destructive techniques (Remote field testing and Internal Rotary ...
Akshay Mistri
 
InspectionSamplingProceduresFineCoarseAggregates.pdf
InspectionSamplingProceduresFineCoarseAggregates.pdfInspectionSamplingProceduresFineCoarseAggregates.pdf
InspectionSamplingProceduresFineCoarseAggregates.pdf
RiSovannaphumi
 
Design and Fabrication of an In-Pipe Inspection Robot
Design and Fabrication of an In-Pipe Inspection RobotDesign and Fabrication of an In-Pipe Inspection Robot
Design and Fabrication of an In-Pipe Inspection Robot
paperpublications3
 
292751693 eddy-current-rft-procedure
292751693 eddy-current-rft-procedure292751693 eddy-current-rft-procedure
292751693 eddy-current-rft-procedure
shakeel Ahmad
 

Similar to DP acco. to DS1-converti.pptx (20)

Qualification of INFARED SPECTROSCOPY BY HIMAJA.D
Qualification of INFARED SPECTROSCOPY BY HIMAJA.DQualification of INFARED SPECTROSCOPY BY HIMAJA.D
Qualification of INFARED SPECTROSCOPY BY HIMAJA.D
 
Edwards Signaling SD2W Installation Manual
Edwards Signaling SD2W Installation ManualEdwards Signaling SD2W Installation Manual
Edwards Signaling SD2W Installation Manual
 
AMAN PPT 4985 Assignment-1.pptx
AMAN PPT 4985 Assignment-1.pptxAMAN PPT 4985 Assignment-1.pptx
AMAN PPT 4985 Assignment-1.pptx
 
What is Pile Integrity Test ?
What is Pile Integrity Test ?What is Pile Integrity Test ?
What is Pile Integrity Test ?
 
10810 63 (smoke density)
10810 63 (smoke density)10810 63 (smoke density)
10810 63 (smoke density)
 
API 570 open book.pdf
API 570 open book.pdfAPI 570 open book.pdf
API 570 open book.pdf
 
Pharmaceutical validation
Pharmaceutical validationPharmaceutical validation
Pharmaceutical validation
 
Liquid dye-penetrant-test-inspection-free-ndt-sample-procedure
Liquid dye-penetrant-test-inspection-free-ndt-sample-procedureLiquid dye-penetrant-test-inspection-free-ndt-sample-procedure
Liquid dye-penetrant-test-inspection-free-ndt-sample-procedure
 
Qualification of analytical instruments
Qualification of analytical instruments Qualification of analytical instruments
Qualification of analytical instruments
 
liquid penetrant test and ultrasonic test
liquid penetrant test and ultrasonic testliquid penetrant test and ultrasonic test
liquid penetrant test and ultrasonic test
 
Qualification of GC & FTIR
Qualification of GC & FTIRQualification of GC & FTIR
Qualification of GC & FTIR
 
How to interpretant leak testing specification
How to interpretant leak testing specificationHow to interpretant leak testing specification
How to interpretant leak testing specification
 
Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...
Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...
Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...
 
stack new.pdf
stack new.pdfstack new.pdf
stack new.pdf
 
CHEM 361 HPLC.pdf
CHEM 361 HPLC.pdfCHEM 361 HPLC.pdf
CHEM 361 HPLC.pdf
 
Edwards Signaling SDSJ Installation Manual
Edwards Signaling SDSJ Installation ManualEdwards Signaling SDSJ Installation Manual
Edwards Signaling SDSJ Installation Manual
 
Tubular Non Destructive techniques (Remote field testing and Internal Rotary ...
Tubular Non Destructive techniques (Remote field testing and Internal Rotary ...Tubular Non Destructive techniques (Remote field testing and Internal Rotary ...
Tubular Non Destructive techniques (Remote field testing and Internal Rotary ...
 
InspectionSamplingProceduresFineCoarseAggregates.pdf
InspectionSamplingProceduresFineCoarseAggregates.pdfInspectionSamplingProceduresFineCoarseAggregates.pdf
InspectionSamplingProceduresFineCoarseAggregates.pdf
 
Design and Fabrication of an In-Pipe Inspection Robot
Design and Fabrication of an In-Pipe Inspection RobotDesign and Fabrication of an In-Pipe Inspection Robot
Design and Fabrication of an In-Pipe Inspection Robot
 
292751693 eddy-current-rft-procedure
292751693 eddy-current-rft-procedure292751693 eddy-current-rft-procedure
292751693 eddy-current-rft-procedure
 

Recently uploaded

LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 

Recently uploaded (20)

LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 

DP acco. to DS1-converti.pptx

  • 3. DRILL PIPE STANDERS DRILL PIPE NEW DRILL PIPE USED DRILL PIPE API DS-1
  • 4. Used Drill Stem Elements DS-1 3rd edition DS-1 TH Hill 4th edition
  • 5. DS-1 Volume 3 - 4th edition Volume 3 Inspection of Drill String Equipment consisting of a single piece with no component pieces Drill Pipe Drill Collars Subs Pup Joints
  • 6. What are the major enhancements for DS‐1® Fourth Edition compared to Third Edition? Volume 3:  Add procedures cover hard-banding (re‐application and inspection) and tool joint build up.  Expand dimensional and visual inspection procedures for new proprietary connections.  Move seven procedures covering Specialty Tools to Volume 4.
  • 7. Standard DS1: ■Standards for Inspection- Accepting &Rejecting used drill Pipes. ■Drill Stem Inspection covering wide range of components. ■ specific Procedures & Methodology. ■ Flexible options. ■ Training & Qualifications. ■ Calibration mandatory requirement. ■Quality Control measures outlined for equipment & processes.
  • 8. INTRODUCTION Specifying the inspectionprogram Inspection Procedures DS-1 CONTENTS Failure Analysis Fitness for Purpose List of Table
  • 10. Recommended Inspection Programs for DP (Page 18). The inspection program defines: (a)Which inspection methods will be applied to each drill stem component. (b)How each inspection method must be conducted in a step-by-step procedure. (c)What acceptance criteria will be in effect during inspection -- that is, the user’s definition of “good” and “bad”. Features covered by Inspection
  • 11. Drill Pipe Inspection 5 4 DS-1 Category 2 3 1 TUBE BODY Visual Tube OD Gauging UT Wall Thickness Checks Electromagnetic Scanning MPI /Slip Area UT Slip Area TOOL JOINT Visual Connection Fluorescent MPI of connection Thread profiling w/gauge OD/ID Gauging Seal width/Condition Shoulder width Bevel Diameter Seal Flatness Counter-bore depth
  • 12. **DS1 Category 5 is intended for drill string components that are to be used in extremely adverse conditions where the potential cost of failure is very large. DS1 Category 5 includes the Ultrasonic End Area Inspection of Upset and Slip areas of the Drill pipe, where the accumulated fatigue at both the areas together contribute 96% probability of failure.
  • 13.
  • 14.
  • 15. Chapter 3: (Page 31) (INSPECTION PROCEDURES) 3.4 Visual Tube Inspection This procedure covers visual examination of internal/external surfaces of drill pipe. -Apparatus: Paint marker, Pit depth gage, ultrasonic gage, Spot light
  • 16. 3.4.4 Procedure and acceptance criteria: (page32) a.External Surface imperfection on pipe shall be measured and the depth subtracted from average adjacent wall thickness to determine the remaining wall thickness under the imperfection and compared to acceptance criteria listed in table 3.5.1 (Reject if found less than criteria) b.Pipe with extensive raised metal in the slip area may be pulled out without further inspection at the discretion of the inspection company and customer. c. Raised metal on the pipe may be removed if permitted by the customer and the owner of the pipe.
  • 17. d.The minimum illumination level shall be 50 foot-candles e.ID pitting shall not exceed 1/8” in depth as visually estimated for premium class NWDP. For class 2 NWDP Pitting shall not exceed 3/16” f.The tubes shall not be visibly crooked by more than 3” over the entire length or 0.5” in first 5” from either end.
  • 18. -MPI shall be done on the straightened tube section and 2 feet in either side. g. The ID surface of internally coated pipe shall be examined for signs of deterioration of the coating. -Tubes with coating Reference condition 3 or 4 shall be rejected unless waived by the customer.(Fig 3.4.1)
  • 19.
  • 20. 3.5 OD Gage TubeInspection (Page 33) This procedure covers the full length mechanical gaging of the tube for outside diameter variations. -Apparatus: Go-no-go type gages. Any electronic, dial, or vernierdevice. Fixed setting standards for fielduse. -The OD gage calibration shall be verified at the applicable maximum and minimum OD values given in table 3.6.1 & 3.6.2.
  • 21. 3.5.5 Procedure a. The tube shall be gaged from upset to- upset by dragging the gage along the tube length while rotating the pipe. - The pipe shall roll at least one revolution for every 5 feet of length inspected. b. Acceptance criteria found in Table3.6.1.
  • 22. 3.6 UT Wall thickness inspection (Page.34) This procedure covers the UT measurement of DP wall thickness of the tube near the center of the tube and at points of obvious wear. -Apparatus Pulse-echo type Separate transmit and received transducer with no worn to degree that makes visible gap.
  • 23. b. The same couplant shall be used in both calibration and gaging. c. Reference stander properties  -The same acoustic properties of pipe being inspected  Shall have two thicknesses that meet the following • Thick section= nominal wall, +0.100, -0” • Thin section=70%of nominal, +0, -0.100”
  • 24. d. Minimum and maximum values of thick and thin section found at Table 3.6.1 & 3.6.2 . 3.6.4 Procedure: a. Parting line Line between transmit and receive elements on the two element transducer, It shall be held perpendicular to the longitudinal axis of the pipe.
  • 25. b. Readings shall be taken within one foot of the center on each tube. c. Readings shall be taken within 1” radius at the lowest reading area. Acceptance criteria found at table 3.6.1 & 3.6.2.
  • 26. Classification of used NWDP tube: -Dimensional acceptance criteria for used NWDP tube meet requirements of table 1A(3.6.1-DS-1). CONDITION PREMIUM CLASS CLASS 2 Min. remaining WT ≤ 80% ≤ 70% Slip cuts Depth ≥ 10% of Avg. adj. Wall ≥ 20% of Avg. adj. Wall Diameter reduction ≥ 3 % of specified OD ≥ 4 % of specified OD Diameter Increase ≥ 3 % of specified OD ≥ 4 % of specified OD Cracks None None
  • 27. 3.7 Electromagnetic Inspection (EMI)(Page 35) This procedure cover scanning for transverse and 3D flaws using flux leakage detection equipment. Reference Stander It shall be a through-wall drilled hole stander prepared from the same nominal diameter as the pipe to be inspected. The hole size shall be 1/16”, +_1/64 The stander may have one hole for each detector arranged in spiral
  • 28. Standardization Of Flux Leakage Equipment a.The reference amplitude shall be minimum 10 mm from each detector. b. Signal to noise ratio shall be 3 to1. c.The reference stander shall be scanned four times continually at the speed to be used for inspection. d.Each signal channel must produce indication of at least 80% of the reference amplitude. e.Their shall not be any gap between detector and pipe.
  • 29. The unit Shall be re-standardized:  At thestart of each job.  After each 50 length.  Each time the unit is turned on.  When mechanical or electronic changes or adjustments the mode.  Upon completion of the job. If previous standardization accuracy cannot be verified all pipe run since the last one shall be re inspected after correction.
  • 30. Inspection Procedure:  The permanent record should have serial number of pipe and end from which scanning began.  Each length shall be scanned from upset-to-upset.  The head shall be propelled into the near end tool joint.  The head turned around and propelled the full length into the opposite tooljoint.  The rate of scanning for EMI device shall be constant for production and stander and for the entire length.  Each indication exceeding 50% of the standerreference shall be marked until a minimum of 10 area marked.
  • 31.  How to prove up EMI Indication? 1. Visual mechanical measurements. 2. MPI 3. Ultrasonic (WT). 4. Other techniques as required toidentify.  The threshold level for the flux leakage unit shall not be grater than 80% of the reference level.  The threshold level for thickness unit shall be the signal level representing 85% of nominal wall thickness.  Pipe with imperfection which don’t meet the acceptance criteria shall be rejected.  Areas in which flux leakage indication exceed threshold but no imperfection can be found shall be re- scanned and if found this shall be cause for rejection.
  • 32. MPI Slip /Upset Inspection: MPI Wet Fluorescent Wet Non-Fluorescent Dry Fluorescent Dry Non-Fluorescent
  • 33.  This procedure covers inspection of slip and upset external surfaces of used DP for transfer and 3D flaws using either dry magnetic particle with an active AC field or wet fluorescent with an active DC field.  The area to beinspected: 1. 36” on the tube side start from 35 or 18 pin tool joint taper.(+6” in case of additional slip cut). 2. 48” on the tube side start from 18 Box tool joint taper.(+6” in case of additional slip cut). 3. If this method is applied on HWDP, Center pad area includes the first 12” of tube from intersection of the transition radius and outside tube surface on either side of the center pad.
  • 34. Fluorescent Inspection Requirements: 1. Petroleum based medium that exhibit natural fluorescent under black light shall not be used. (Diesel and gasoline are not acceptable). 2. Water base medium are acceptable if they wet the surface. 3. Particle concentration shall range from 0.1 to 0.4 ml/100 ml when measure using ASTM 100 ml centrifuge. 4. The maximum pole spacing of AC yoke during inspection shall not exceed the distance between the poles when all segment of the yoke are perpendicular to the grip.
  • 35. 5.The minimum pole spacing during inspection shall be 2”. 6.Black light intensity shall be measured with an ultraviolet meter each time it turned on, after 8 hours of operation. The minimum intensity shall be 1000 microwatt/cm2. at 15” from light source or at the distance to be used in inspection. 7.Intensity of ambient visible light shall be 2 foot per candles.(50 foot candles at dry non fluorescent inspection) 8. Any crack is cause of rejection except the hairline crack in hard-facing.(Grinding is not permitted).
  • 37. Connection Inspection 3.11 Visual Connection Inspection This procedure used to: 1. Determine the pipe grade. 2. Evaluate the condition of the seal. 3. Evaluate the condition of the Thread. 4. Evaluate the condition of the hard-facing. 5. Evaluate the condition of the Bevel. 6. Look for evidence of box swell and pin stretch.
  • 38. 1. Weight and grade codes: OD (in) Nom. Wt (lb/ft) Weight code 9.50 1 3 1/2" 13.30 (stander) 2 15.50 3 13.75 1 4 1/2" 16.60 (stander) 2 20.00 3 22.82 4 24.66 5 25.50 6 16.25 1 5" 19.50 (stander) 2 25.60 3 5 1/2" 19.20 1 21.90 2 24.70 3
  • 39. Grade Grade code E-75 E X-95 X G-195 G S-135 S DS-140 Z DS-150 V
  • 40. Acceptance Criteria: a. The grade and weight stencil shall be marked either the pin milled slot or the pin nick. b. Hardbanding shall extend no more than 3/16” above the tool joint surface with no broken or missing areas larger than 1/8” cross the major dimension. c. All connection and tool joint shall be free of visible cracks and heat checking. d. The minimum illumination level at the inspection surface shall be 50 foot candles. e. The thread protector shall be applied and secured with approximately 50-100 ft-lbs torque.
  • 41. API and similar Non-Proprietary connection Requirements: a. Bevel Width: Anapproximate 45 degree OD bevel at least 1/32” wide shall be present for the full circumference. b. Thread surfaces: 1. Thread root shall be free from any pitting. 2. Thread surfaces shall be free from imperfections that penetrate below the thread root, occupy more than 1- 1/2” in length along the thread helix. 3. Shall be free from imperfection that exceed 1/16” in depth or 1/8” in diameter.
  • 42. c. Box swell: can be checked by: 1. Place a straightedge along the longitudinal axis of box tool joint. If a visible gab exists, the OD must be measured. Compare the OD at the bevel to the OD 2” (+-) ½” away from bevel.(no different more than 1/32”). d. Seal Surfaces: 1. Shall be free of raised metal or corrosion. 2. Any pitting of the seal that estimated to exceed 1/32” in depth. 3. Any pitting occupy more than 20% of the seal width at any given location.
  • 43. e. Re-facing: 1. Re-facing limits are 1/32” on any removal. 2. 1/16”cumulatively. f. Pin Thread Profile: 1. No visible gab between profile and thread root more than 1/16” on no more than two thread crests.(1/32” in 4 thread acco.to APIRP7G-2) 2. Uniform flank wear estimated to be to be less than 0.010” is permissible. 3. No gap between the profile and thread flanks more than 1/64” 4. No stretch exceeding 0.006” in two inch measured by Pin Lead.
  • 44. I. Box Taper: The box taper at the back of the thread shall be at an angle of 30o (+15, -0) .(Visually Inspected). j. Shoulder Square-ness: Benchmark is used to inspect if there is a possible lack of alignment. That is visually estimated to exceed 1/64”, the connection shall be reject. k. Pitting in Pin ID: Pitting at ID is visually measured to be deeper than 1/8” shall be cause for Rejection.
  • 45. l. Shoulder Flatness: Place a straightedge across a diameter of the tool joint face and rotating it at least 18 degree. Any visible gab shall be cause of rejection.
  • 47. a. Box outside Diameter (OD): 1. Shall be measured 3/8” (+-1/8”) from the shoulder. 2. Two measurements shall be taken at 90 (+-10) degrees. 3. Box shall meet the requirements of the table 2A.(3.7.1, 3.7.18, 3.7.19) at DS1. b. Pin Inside Diameter: 1. Shall be measured under the last thread facing the seal.(+- ¼”) 2. Shall meat the requirements of the table 2A.(3.7.1, 3.7.18, 3.7.19) at DS1.
  • 48. c. Box Shoulder Width: 1. Shall be measured by placing the straightedge longitudinally along the tool joint, extending past the shoulder surface, and then measuring the shoulder thickness from this extension to the counter-bore (excluding ID and bevel). 2. It measure at the point of minimum thickness. 3. Shall meat the requirements of the table 2A.(3.7.1, 3.7.18, 3.7.19) at DS1. d. Tong Space: 1. Shall measured from the bevel to the edge of hard-facing. 2. Shall meat the requirements of the table 2A.(3.7.1, 3.7.18, 3.7.19) at DS1.
  • 49. e. Box Counter-bore Depth: 1. Depth Shall be measured (including any ID bevel) 2. Shall not be less than 9/16”. f. Box counter-bore Diameter: 1. Shall be measured as near as possible to the shoulder 2. Shall meat the requirements of the table 2A.(3.7.1, 3.7.18, 3.7.19) at DS1.
  • 50. g. Bevel Diameter: Outer Diameter of the contact face of the rotary shoulder connection. It serve two purposes: 1. Protect the outer edge of the sealing face. 2. Increase the contact pressure on seal face to minimize leaking and separation . Shall meat the requirements of the table 2A.(3.7.1, 3.7.18, 3.7.19) at DS1. g. Pin Neck length: 1. The distance from the 90 degree pin shoulder to the intersection of the flank of the first full depth thread with the pin neck (shall bemeasured). 2. Shall not exceed 9/16”.
  • 51. i. Thread compound and protector: 1. Acceptable connection shall be compound overall thread. 2. Thread protector shall be applied with 50-100ft-lbs of torque.
  • 53.
  • 54.
  • 55.
  • 56.
  • 57.