SlideShare a Scribd company logo
REMINDER
Check in on the
COLLABORATE mobile app
30% 60% 90% IFC Engineering
What is the Project Progress
Prepared by:
Trevor Watt
Project Controls Specialist
EPCM Solutions
Using P6 to Decipher
Session ID#: 15412
Introduction
Rules of Credit
■ Document Count
▪ Very accurate during drawing phase
▪ Lacks ability to progress 3d model / calculations
▪ Hard to identify analysis and design changes
— They don’t affect the document count
■ Review package 30 – 60 – 90 – IFC
▪ Inaccurate
▪ Leaves a lot of interpretation to the discipline lead engineers
▪ Hard to identify change
Rules of Credit
■ Activity Based
▪ Very Accurate through all phases
▪ Easily identifies changes and slippage in schedule
▪ Provides more insight to resource loading
▪ Can provide detailed historical information for future estimates
▪ Can be used for “What If” scenarios
▪ Clear defined information as to what will be provided and
expected in each review package
▪ Can provide cost, hour and schedule alignment.
What is required?
■ Level of completion of review packages
▪ A document specifying what deliverables are to be included, and
at what level are they to be completed too.
■ WBS that aligns with the Level of completion document
▪ Each deliverable has its own deliverable number
▪ This forms the bottom level of the WBS.
▪ The deliverable will be broken down further via activities
■ CBS which mimics the WBS
Level of Completion Document
■ Define the Detailed Engineering review stage gates
■ Define the required disciplines to complete the package
■ Define the Deliverables that are to be part of the complete
package
▪ Define the level of completion of each deliverable for each
review package
Defining the WBS
■ After the deliverables are defined a coding structure and
system needs to be derived
■ Typical structure for an engineering project would look like so:
▪ Project / Phase / Area / Sub Area / CWP Package / EWP
Package / Discipline / Deliverable / Activity
▪ Project to CWP section should be defined by owner / client
▪ The EWP to Activity should be defined by Engineering company
▪ Next the codes should be defined for each level of the skeleton
structure.
▪ Should be consistent through the project right through till the
end of construction.
WBS / CBS alignment
■ In the previous example the CBS or cost code used in the
financial system ends up as:
▪ 4.311.900.100
▪ 4 – Current Project (PS4) added to the CBS but is basically the
project schedule name, so not included in project WBS
▪ 3 – Detailed Design
▪ 1 – Area (W)
▪ 1 – Package
▪ 190 – Process
▪ 300 – Control Narrative
P6 Typical Settings
■ Fixed Durations and Units
■ Auto compute Actuals – Off
■ Calculate cost from Units – Off
■ Physical % Complete
■ Budgeted Values with planned dates
■ Recalculate Actual units and cost when duration % changes –
Off
■ Link Actual and Actual This period Units and Cost
■ P6 V7 requires costs to be loaded for performance %
complete to calculate.
■ Activity % complete should be used under Earned Value in
the Admin preferences.
Planning
■ After the structure is defined and entered within the schedule
activities can then be created
▪ The most important ones to identify first are the outside client
deliverables that will be required from the client.
▪ Then the internal discipline to discipline deliverables.
▪ These should all be presented as milestones within the
schedule.
■ Each discipline lead should be brought in to help define/plan
there own individual scope.
▪ I have seen mass planning sessions, and these do not work.
▪ Start with each discipline individually then work with the group
as whole to define interdisciplinary logic.
Planning
■ Define the activities within each WBS or deliverable bucket
▪ Define durations and Budgeted labour units for each activity
▪ Most logic within a particular bucket is FS
▪ Try to keep activities within a 10 day duration.
▪ And keep in mind the milestones deliverables that were defined.
■ Define the logic between the buckets
■ Define the logic from the outside deliverables client or
external discipline deliverable.
■ Review as a project team.
Planning
■ Check resource curves to make sure project is feasible.
■ Level as necessary.
■ Check early and late curves.
■ Add in any schedule risk required.
■ Verify the critical path.
▪ In engineering projects, the critical path can easily be defined
usually by the client and inter-discipline deliverables.
▪ If one deliverable isn’t met the particular discipline usually can’t
get much traction on the beginning of their design.
▪ Eg. Oil and gas pipeline detailed design
— Transients to stress to structural. (could be multiple iterations)
Loading Budgets
■ Once the schedule is fully activity loaded
▪ Budgets can be loaded via an excel import
▪ Important that all resources have calculate cost from units
turned off.
▪ Export Project to excel selecting Resource Assignments check
box
▪ Select Budgeted Units and Budgeted Cost
▪ Multiply your units by your wage rate within excel, and re-import
to P6.
Place holders for Actuals
■ Since we are not coding to the activity level we need to add in
place holders for uploading the actuals from the financial
system.
▪ Can be WBS summary or LOE activity type.
▪ Activtity ID must match the CBS code from the cost system.
▪ Assign applicable resource with no budgeted units or cost.
▪ One is required for each WBS bucket.
Progressing the schedule
■ What questions to ask?
▪ Actual Start?
▪ Actual Finish?
▪ Remaining Labour units
▪ Remaining Duration
■ Make a global change to calculate Physical % complete, The
calculation is as below, but UDF must be used to represent
this caluclation
▪ Physical % complete = (budget – remaining) / budget
■ Essentially the above formula will calculate the earned labour
units.
Uploading Actuals
■ Export to excel using resource assignments.
▪ Select Actual Units and Actual Costs columns
▪ Delete all activities that do not have an activity ID that is a CBS
code.
▪ Use Vlookup or some other format to populate excel sheet
▪ Reimport into P6.
What info does all this give you?
■ With this setup you now can apply all EV columns to your
layout.
■ The progress is measured at the individual activity level to
provide overall progress.
■ Full resource curves and leveling are available if required.
■ Cashflows can be represented in either excel or P6.
■ Changes are easily identified by the team during progress
meetings.
■ Most importantly you will not over claim progress.
Rolled up Earned Value from P6
Detailed view at WBS Level
Stacked Histogram from P6
Over Allocation represented in P6
S-Curve generated from P6 dump into Excel
Performance Indices from P6 Dump into
Excel
Earned Schedule from P6 Dump into Excel
Variances from P6 Dump into Excel
Summation
■ There are multiple ways to progress engineering, but the only
unit that really matters is hours.
■ Identification of changes is crucial to success
▪ This is achieved by a detailed schedule
■ With a proper set-up, execution and management of
resources becomes easier and more accurate
■ The bottom line is what ever happens during the engineering
phase, can affect construction two fold.
Please complete the session
evaluation
We appreciate your feedback and insight
You may complete the session evaluation either
on paper or online via the mobile app

More Related Content

What's hot

Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
PMI Chennai Chapter
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendations
ubk1411
 
Workshop on Plant Commissioning and Seamless Startup final.pdf
Workshop on Plant Commissioning and Seamless Startup final.pdfWorkshop on Plant Commissioning and Seamless Startup final.pdf
Workshop on Plant Commissioning and Seamless Startup final.pdf
HIMADRI BANERJI
 
Commissioning of Offshore Installations
Commissioning of Offshore InstallationsCommissioning of Offshore Installations
Commissioning of Offshore Installations
wan saiful arini
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping station
Harish Mahavar
 

What's hot (20)

Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
 
Epc projects and cad tools
Epc projects and cad toolsEpc projects and cad tools
Epc projects and cad tools
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promo
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
 
Pid.pdf
Pid.pdfPid.pdf
Pid.pdf
 
Milestone checklist
Milestone checklist   Milestone checklist
Milestone checklist
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promo
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendations
 
Basic engineering_Checklist
Basic engineering_ChecklistBasic engineering_Checklist
Basic engineering_Checklist
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draft
 
Workshop on Plant Commissioning and Seamless Startup final.pdf
Workshop on Plant Commissioning and Seamless Startup final.pdfWorkshop on Plant Commissioning and Seamless Startup final.pdf
Workshop on Plant Commissioning and Seamless Startup final.pdf
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution Plan
 
Commissioning of Offshore Installations
Commissioning of Offshore InstallationsCommissioning of Offshore Installations
Commissioning of Offshore Installations
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping station
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
Advanced Work Packaging in Construction: An Introduction
Advanced Work Packaging in Construction: An IntroductionAdvanced Work Packaging in Construction: An Introduction
Advanced Work Packaging in Construction: An Introduction
 

Viewers also liked

30 60 90 Business Plan
30 60 90 Business Plan30 60 90 Business Plan
30 60 90 Business Plan
jfreshour
 
30 60 90 Day Sales Plan
30 60 90 Day Sales Plan30 60 90 Day Sales Plan
30 60 90 Day Sales Plan
natevans65
 
Bcg Consultants Love Life
Bcg  Consultants Love LifeBcg  Consultants Love Life
Bcg Consultants Love Life
nitinagarwalin
 

Viewers also liked (18)

30 , 60, 90 Days Plan To Meet Goals For New Organization
30 , 60, 90 Days Plan To Meet Goals For New Organization30 , 60, 90 Days Plan To Meet Goals For New Organization
30 , 60, 90 Days Plan To Meet Goals For New Organization
 
YOUR 30-, 60-, AND 90-DAY GAME PLAN FOR CAREER SUCCESS IN TODAY’S LEANER WORK...
YOUR 30-, 60-, AND 90-DAY GAME PLAN FOR CAREER SUCCESS IN TODAY’S LEANER WORK...YOUR 30-, 60-, AND 90-DAY GAME PLAN FOR CAREER SUCCESS IN TODAY’S LEANER WORK...
YOUR 30-, 60-, AND 90-DAY GAME PLAN FOR CAREER SUCCESS IN TODAY’S LEANER WORK...
 
LeadingAST.com - Sample 90 day leadership plan
LeadingAST.com - Sample 90 day leadership planLeadingAST.com - Sample 90 day leadership plan
LeadingAST.com - Sample 90 day leadership plan
 
The First 90 days
The First 90 daysThe First 90 days
The First 90 days
 
Highlight Report - Project Management template
Highlight Report - Project Management template Highlight Report - Project Management template
Highlight Report - Project Management template
 
Design Checklist-Instrumentation & Control Systems (typical / guideline)
Design Checklist-Instrumentation & Control Systems (typical / guideline)Design Checklist-Instrumentation & Control Systems (typical / guideline)
Design Checklist-Instrumentation & Control Systems (typical / guideline)
 
Programme or project plan on a single slide (with RAG status)
Programme or project plan on a single slide (with RAG status)Programme or project plan on a single slide (with RAG status)
Programme or project plan on a single slide (with RAG status)
 
90 day plan
90 day plan90 day plan
90 day plan
 
30 60-90
30 60-9030 60-90
30 60-90
 
Managing multiple projects
Managing multiple projectsManaging multiple projects
Managing multiple projects
 
SharePoint User Experience Design Project Plan v1.0
SharePoint User Experience Design Project Plan v1.0SharePoint User Experience Design Project Plan v1.0
SharePoint User Experience Design Project Plan v1.0
 
30 60 90 Business Plan
30 60 90 Business Plan30 60 90 Business Plan
30 60 90 Business Plan
 
30 60 90 day plan
30 60 90 day plan30 60 90 day plan
30 60 90 day plan
 
My First 90 Days - Strategies for Success
My First 90 Days - Strategies for SuccessMy First 90 Days - Strategies for Success
My First 90 Days - Strategies for Success
 
10 tips for building a 30 60-90 plan
10 tips for building a 30 60-90 plan10 tips for building a 30 60-90 plan
10 tips for building a 30 60-90 plan
 
30 60 90 Day Sales Plan
30 60 90 Day Sales Plan30 60 90 Day Sales Plan
30 60 90 Day Sales Plan
 
Top 16 ways to make money online forever
Top 16 ways to make money online foreverTop 16 ways to make money online forever
Top 16 ways to make money online forever
 
Bcg Consultants Love Life
Bcg  Consultants Love LifeBcg  Consultants Love Life
Bcg Consultants Love Life
 

Similar to 30 60 90 percent ifc engineering what is the project progress - Oracle Primavera P6 Collaborate 14

Project management
Project managementProject management
Project management
ervinod
 

Similar to 30 60 90 percent ifc engineering what is the project progress - Oracle Primavera P6 Collaborate 14 (20)

Earned value and P6 - Oracle Primavera P6 Collaborate 14
Earned value and P6 - Oracle Primavera P6 Collaborate 14Earned value and P6 - Oracle Primavera P6 Collaborate 14
Earned value and P6 - Oracle Primavera P6 Collaborate 14
 
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systems
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Dashboard / Digest / Compliance reporting of key performance, quality and oth...
Dashboard / Digest / Compliance reporting of key performance, quality and oth...Dashboard / Digest / Compliance reporting of key performance, quality and oth...
Dashboard / Digest / Compliance reporting of key performance, quality and oth...
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
 
Project management
Project managementProject management
Project management
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
ATCO Engineering - Process Evaluation
ATCO Engineering - Process EvaluationATCO Engineering - Process Evaluation
ATCO Engineering - Process Evaluation
 
JDE Projects Month End Course - Work Orders
JDE Projects Month End Course - Work OrdersJDE Projects Month End Course - Work Orders
JDE Projects Month End Course - Work Orders
 
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
Implementation review eppm p6 8.2 at a major utility - Oracle Primavera P6 Co...
 
SAP PS overview
SAP PS overviewSAP PS overview
SAP PS overview
 
134 work break break down structure
134 work break break down structure134 work break break down structure
134 work break break down structure
 
cutoverstrategy.ppt
cutoverstrategy.pptcutoverstrategy.ppt
cutoverstrategy.ppt
 
cutoverstrategy - Copy.ppt
cutoverstrategy - Copy.pptcutoverstrategy - Copy.ppt
cutoverstrategy - Copy.ppt
 
(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...
 

More from p6academy

20160405 How to Install Primavera P6 16.1 Professional desktop
20160405 How to Install Primavera P6 16.1 Professional desktop20160405 How to Install Primavera P6 16.1 Professional desktop
20160405 How to Install Primavera P6 16.1 Professional desktop
p6academy
 

More from p6academy (20)

Oracle OpenWorld 2015
Oracle OpenWorld 2015Oracle OpenWorld 2015
Oracle OpenWorld 2015
 
Plan and Execute the Right Projects— Easily and Affordably
Plan and Execute the Right Projects—  Easily and AffordablyPlan and Execute the Right Projects—  Easily and Affordably
Plan and Execute the Right Projects— Easily and Affordably
 
What's New In Primavera P6 EPPM 17.1
What's New In Primavera P6 EPPM 17.1What's New In Primavera P6 EPPM 17.1
What's New In Primavera P6 EPPM 17.1
 
Oracle Primavera Unifier What's New in Release 16.2
Oracle Primavera Unifier What's New in Release 16.2Oracle Primavera Unifier What's New in Release 16.2
Oracle Primavera Unifier What's New in Release 16.2
 
Oracle What's New In Primavera P6 16.2
Oracle What's New In Primavera P6 16.2Oracle What's New In Primavera P6 16.2
Oracle What's New In Primavera P6 16.2
 
What's New in Primavera Prime 16.1
What's New in Primavera Prime 16.1What's New in Primavera Prime 16.1
What's New in Primavera Prime 16.1
 
What's New in Primavera Gateway 16.1
What's New in Primavera Gateway 16.1What's New in Primavera Gateway 16.1
What's New in Primavera Gateway 16.1
 
What's New In Primavera Analytics 16.1
What's New In Primavera Analytics 16.1What's New In Primavera Analytics 16.1
What's New In Primavera Analytics 16.1
 
What's New in Unifier 16.1
What's New in Unifier 16.1What's New in Unifier 16.1
What's New in Unifier 16.1
 
20160405 How to Install Primavera P6 16.1 Professional desktop
20160405 How to Install Primavera P6 16.1 Professional desktop20160405 How to Install Primavera P6 16.1 Professional desktop
20160405 How to Install Primavera P6 16.1 Professional desktop
 
Oracle Primavera P6 16.1 Announced
Oracle Primavera P6 16.1 AnnouncedOracle Primavera P6 16.1 Announced
Oracle Primavera P6 16.1 Announced
 
Oracle Primavera Unifier 16.1
Oracle Primavera Unifier 16.1Oracle Primavera Unifier 16.1
Oracle Primavera Unifier 16.1
 
P6 Release 8 Application Considerations Overview
P6 Release 8 Application Considerations OverviewP6 Release 8 Application Considerations Overview
P6 Release 8 Application Considerations Overview
 
Administering Users, Access and Views in P6 EPPM (Web) Release 8 and later
Administering Users, Access and Views in P6 EPPM  (Web) Release 8 and laterAdministering Users, Access and Views in P6 EPPM  (Web) Release 8 and later
Administering Users, Access and Views in P6 EPPM (Web) Release 8 and later
 
P6 Release 8 Installation Orientation
P6 Release 8 Installation OrientationP6 Release 8 Installation Orientation
P6 Release 8 Installation Orientation
 
Oracle Primavera P6 R8 Release Value Proposition
Oracle Primavera P6 R8 Release Value PropositionOracle Primavera P6 R8 Release Value Proposition
Oracle Primavera P6 R8 Release Value Proposition
 
Oracle Primavera P6 v7 Release Value Proposition
Oracle Primavera P6 v7 Release Value Proposition Oracle Primavera P6 v7 Release Value Proposition
Oracle Primavera P6 v7 Release Value Proposition
 
Oracle Primavera P6 Release Content Document (RCD)
Oracle Primavera P6 Release Content Document (RCD)Oracle Primavera P6 Release Content Document (RCD)
Oracle Primavera P6 Release Content Document (RCD)
 
Oracle Support Accreditation – Level 1 Study Guide
Oracle Support Accreditation – Level 1 Study GuideOracle Support Accreditation – Level 1 Study Guide
Oracle Support Accreditation – Level 1 Study Guide
 
Oracle Primavera Support Accreditation Study Guide
Oracle Primavera Support Accreditation Study GuideOracle Primavera Support Accreditation Study Guide
Oracle Primavera Support Accreditation Study Guide
 

Recently uploaded

anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 
NewBase 24 May 2024 Energy News issue - 1727 by Khaled Al Awadi_compresse...
NewBase   24 May  2024  Energy News issue - 1727 by Khaled Al Awadi_compresse...NewBase   24 May  2024  Energy News issue - 1727 by Khaled Al Awadi_compresse...
NewBase 24 May 2024 Energy News issue - 1727 by Khaled Al Awadi_compresse...
Khaled Al Awadi
 

Recently uploaded (20)

anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
HR and Employment law update: May 2024.
HR and Employment law update:  May 2024.HR and Employment law update:  May 2024.
HR and Employment law update: May 2024.
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
State of D2C in India: A Logistics Update
State of D2C in India: A Logistics UpdateState of D2C in India: A Logistics Update
State of D2C in India: A Logistics Update
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
Falcon Invoice Discounting Setup for Small Businesses
Falcon Invoice Discounting Setup for Small BusinessesFalcon Invoice Discounting Setup for Small Businesses
Falcon Invoice Discounting Setup for Small Businesses
 
Evolution and Growth of Supply chain.pdf
Evolution and Growth of Supply chain.pdfEvolution and Growth of Supply chain.pdf
Evolution and Growth of Supply chain.pdf
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 
LinkedIn Masterclass Techweek 2024 v4.1.pptx
LinkedIn Masterclass Techweek 2024 v4.1.pptxLinkedIn Masterclass Techweek 2024 v4.1.pptx
LinkedIn Masterclass Techweek 2024 v4.1.pptx
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
 
TriStar Gold Corporate Presentation May 2024
TriStar Gold Corporate Presentation May 2024TriStar Gold Corporate Presentation May 2024
TriStar Gold Corporate Presentation May 2024
 
Using Generative AI for Content Marketing
Using Generative AI for Content MarketingUsing Generative AI for Content Marketing
Using Generative AI for Content Marketing
 
Luxury Artificial Plants Dubai | Plants in KSA, UAE | Shajara
Luxury Artificial Plants Dubai | Plants in KSA, UAE | ShajaraLuxury Artificial Plants Dubai | Plants in KSA, UAE | Shajara
Luxury Artificial Plants Dubai | Plants in KSA, UAE | Shajara
 
Hyundai capital 2024 1quarter Earnings release
Hyundai capital 2024 1quarter Earnings releaseHyundai capital 2024 1quarter Earnings release
Hyundai capital 2024 1quarter Earnings release
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
 
How to Maintain Healthy Life style.pptx
How to Maintain  Healthy Life style.pptxHow to Maintain  Healthy Life style.pptx
How to Maintain Healthy Life style.pptx
 
Equinox Gold Corporate Deck May 24th 2024
Equinox Gold Corporate Deck May 24th 2024Equinox Gold Corporate Deck May 24th 2024
Equinox Gold Corporate Deck May 24th 2024
 
NewBase 24 May 2024 Energy News issue - 1727 by Khaled Al Awadi_compresse...
NewBase   24 May  2024  Energy News issue - 1727 by Khaled Al Awadi_compresse...NewBase   24 May  2024  Energy News issue - 1727 by Khaled Al Awadi_compresse...
NewBase 24 May 2024 Energy News issue - 1727 by Khaled Al Awadi_compresse...
 

30 60 90 percent ifc engineering what is the project progress - Oracle Primavera P6 Collaborate 14

  • 1. REMINDER Check in on the COLLABORATE mobile app 30% 60% 90% IFC Engineering What is the Project Progress Prepared by: Trevor Watt Project Controls Specialist EPCM Solutions Using P6 to Decipher Session ID#: 15412
  • 3. Rules of Credit ■ Document Count ▪ Very accurate during drawing phase ▪ Lacks ability to progress 3d model / calculations ▪ Hard to identify analysis and design changes — They don’t affect the document count ■ Review package 30 – 60 – 90 – IFC ▪ Inaccurate ▪ Leaves a lot of interpretation to the discipline lead engineers ▪ Hard to identify change
  • 4. Rules of Credit ■ Activity Based ▪ Very Accurate through all phases ▪ Easily identifies changes and slippage in schedule ▪ Provides more insight to resource loading ▪ Can provide detailed historical information for future estimates ▪ Can be used for “What If” scenarios ▪ Clear defined information as to what will be provided and expected in each review package ▪ Can provide cost, hour and schedule alignment.
  • 5. What is required? ■ Level of completion of review packages ▪ A document specifying what deliverables are to be included, and at what level are they to be completed too. ■ WBS that aligns with the Level of completion document ▪ Each deliverable has its own deliverable number ▪ This forms the bottom level of the WBS. ▪ The deliverable will be broken down further via activities ■ CBS which mimics the WBS
  • 6. Level of Completion Document ■ Define the Detailed Engineering review stage gates ■ Define the required disciplines to complete the package ■ Define the Deliverables that are to be part of the complete package ▪ Define the level of completion of each deliverable for each review package
  • 7.
  • 8.
  • 9. Defining the WBS ■ After the deliverables are defined a coding structure and system needs to be derived ■ Typical structure for an engineering project would look like so: ▪ Project / Phase / Area / Sub Area / CWP Package / EWP Package / Discipline / Deliverable / Activity ▪ Project to CWP section should be defined by owner / client ▪ The EWP to Activity should be defined by Engineering company ▪ Next the codes should be defined for each level of the skeleton structure. ▪ Should be consistent through the project right through till the end of construction.
  • 10.
  • 11. WBS / CBS alignment ■ In the previous example the CBS or cost code used in the financial system ends up as: ▪ 4.311.900.100 ▪ 4 – Current Project (PS4) added to the CBS but is basically the project schedule name, so not included in project WBS ▪ 3 – Detailed Design ▪ 1 – Area (W) ▪ 1 – Package ▪ 190 – Process ▪ 300 – Control Narrative
  • 12. P6 Typical Settings ■ Fixed Durations and Units ■ Auto compute Actuals – Off ■ Calculate cost from Units – Off ■ Physical % Complete ■ Budgeted Values with planned dates ■ Recalculate Actual units and cost when duration % changes – Off ■ Link Actual and Actual This period Units and Cost ■ P6 V7 requires costs to be loaded for performance % complete to calculate. ■ Activity % complete should be used under Earned Value in the Admin preferences.
  • 13. Planning ■ After the structure is defined and entered within the schedule activities can then be created ▪ The most important ones to identify first are the outside client deliverables that will be required from the client. ▪ Then the internal discipline to discipline deliverables. ▪ These should all be presented as milestones within the schedule. ■ Each discipline lead should be brought in to help define/plan there own individual scope. ▪ I have seen mass planning sessions, and these do not work. ▪ Start with each discipline individually then work with the group as whole to define interdisciplinary logic.
  • 14. Planning ■ Define the activities within each WBS or deliverable bucket ▪ Define durations and Budgeted labour units for each activity ▪ Most logic within a particular bucket is FS ▪ Try to keep activities within a 10 day duration. ▪ And keep in mind the milestones deliverables that were defined. ■ Define the logic between the buckets ■ Define the logic from the outside deliverables client or external discipline deliverable. ■ Review as a project team.
  • 15. Planning ■ Check resource curves to make sure project is feasible. ■ Level as necessary. ■ Check early and late curves. ■ Add in any schedule risk required. ■ Verify the critical path. ▪ In engineering projects, the critical path can easily be defined usually by the client and inter-discipline deliverables. ▪ If one deliverable isn’t met the particular discipline usually can’t get much traction on the beginning of their design. ▪ Eg. Oil and gas pipeline detailed design — Transients to stress to structural. (could be multiple iterations)
  • 16. Loading Budgets ■ Once the schedule is fully activity loaded ▪ Budgets can be loaded via an excel import ▪ Important that all resources have calculate cost from units turned off. ▪ Export Project to excel selecting Resource Assignments check box ▪ Select Budgeted Units and Budgeted Cost ▪ Multiply your units by your wage rate within excel, and re-import to P6.
  • 17. Place holders for Actuals ■ Since we are not coding to the activity level we need to add in place holders for uploading the actuals from the financial system. ▪ Can be WBS summary or LOE activity type. ▪ Activtity ID must match the CBS code from the cost system. ▪ Assign applicable resource with no budgeted units or cost. ▪ One is required for each WBS bucket.
  • 18.
  • 19. Progressing the schedule ■ What questions to ask? ▪ Actual Start? ▪ Actual Finish? ▪ Remaining Labour units ▪ Remaining Duration ■ Make a global change to calculate Physical % complete, The calculation is as below, but UDF must be used to represent this caluclation ▪ Physical % complete = (budget – remaining) / budget ■ Essentially the above formula will calculate the earned labour units.
  • 20.
  • 21. Uploading Actuals ■ Export to excel using resource assignments. ▪ Select Actual Units and Actual Costs columns ▪ Delete all activities that do not have an activity ID that is a CBS code. ▪ Use Vlookup or some other format to populate excel sheet ▪ Reimport into P6.
  • 22. What info does all this give you? ■ With this setup you now can apply all EV columns to your layout. ■ The progress is measured at the individual activity level to provide overall progress. ■ Full resource curves and leveling are available if required. ■ Cashflows can be represented in either excel or P6. ■ Changes are easily identified by the team during progress meetings. ■ Most importantly you will not over claim progress.
  • 23. Rolled up Earned Value from P6
  • 24. Detailed view at WBS Level
  • 27. S-Curve generated from P6 dump into Excel
  • 28. Performance Indices from P6 Dump into Excel
  • 29. Earned Schedule from P6 Dump into Excel
  • 30. Variances from P6 Dump into Excel
  • 31. Summation ■ There are multiple ways to progress engineering, but the only unit that really matters is hours. ■ Identification of changes is crucial to success ▪ This is achieved by a detailed schedule ■ With a proper set-up, execution and management of resources becomes easier and more accurate ■ The bottom line is what ever happens during the engineering phase, can affect construction two fold.
  • 32. Please complete the session evaluation We appreciate your feedback and insight You may complete the session evaluation either on paper or online via the mobile app