SlideShare a Scribd company logo
EPC Project Rule Of Credit
and
Progress measurement
Click here to purchase or visit www.ignitetribes.com
Level 1 - WBS
WBS DESCRIPTION
WEIGHTAGE
BASIS
COST (RM)
WEIGHT
FACTOR
ENG ENGINEERING Manhour 1,862,010 0.064
PRC PROCUREMENT Cost 6,499,944 0.223
CM CONSTRUCTION Cost 19,770,791 0.679
CON COMMISIONING Cost 967,255 0.032
Total Cost 2,9100,000
Weight Factor = Cost
Total cost
Level 2 - WBS
BASIS COST (RM)
WEIGHT
FACTOR
ENGINEERING (TOTAL COST) $1,862,010.00
CIVIL & STRUCTURE Manhour $380,890.00 20.46%
PROCESS
Manhour
$207,710.00 11.16%
MECHANICAL
Manhour
$260,160.00 13.97%
GENERAL
Manhour
$140,580.00 7.55%
PIPING
Manhour
$376,430.00 20.22%
ELECTRICAL
Manhour
$296,200.00 15.91%
INSTRUMENTATION
Manhour
$200,040.00 10.74%
Weight Factor = Discipline Cost
Engineering Total cost
Engineering Work Category Breakdown
Level 4 - WBS
ENGINEERING (Weightage)
( Option 1)
Proposed Weightage
( Option 2)
Proposed Weightage
Study & Design Preparation 40 %
Issued for Approval 40%
Client Comment -
Incorporate Client Comment -
Issued for Construction 20%
Issue for review (IFR) 10%
Issue for approval (IFA) 20%
Issue for construction (IFC) 30%
Approved for construction 40%
Level 4 - WBS
Study and
Design
Preparation
IFR IFA IFC AFC
Progress (%
Complete)
Weight
Progress
Document Title Category Discipline
Budgeted
Man Hour
Weight
Factor
5% 15% 20% 25% 35%
Tie In Plan Dwg Piping 300 0.05484 100.0% 100.0% 100.0% 100.0% 33.0% 76.6% 4.2%
Piping GA Dwg Piping 400 0.07313 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 7.3%
Tie In Isometric Dwg Piping 350 0.06399 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 6.4%
Standard Pipe Support Dwg Piping 450 0.08227 100.0% 100.0% 100.0% 100.0% 33.0% 76.6% 6.3%
Demolition Dwg Piping 350 0.06399 100.0% 100.0% 100.0% 75.0% 0.0% 58.8% 3.8%
Tie In List Doc Piping 550 0.10055 100.0% 55.5% 0.0% 0.0% 0.0% 13.3% 1.3%
Critical Line List Doc Piping 600 0.10969 100.0% 55.5% 0.0% 0.0% 0.0% 13.3% 1.5%
Stress Analysis Report Doc Piping 800 0.14625229 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
Coating Specs Doc Piping 850 0.15539305 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
Piping class Doc Piping 820 0.14990859 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
GRAND TOTAL 5470 1.0000 30.8%
% Complete= (5% x 100%) + (15% x 100%) + (20% x 100%) +(25% x 100%)+( 35% x 33.0%)
Weight factor = 0.0584 * 76.6 %Progress tracking Excel sheet available for download in ignite.com
Engineering
Step Rule of Credit Increment % Cumulative %
1 Study and design preparation 5% 5%
2 Issue for review (IFR) 10% 15%
3 Issue for approval (IFA) 20% 35%
4 Issue for construction (IFC) 30% 65%
5 Approved for construction 35% 100%
Engineering
Step Rule of Credit Increment % Cumulative %
1 Study and design preparation 10% 10%
2 Issue to client 30% 40%
3 Approval by client 35% 75%
4 Issue for construction / purchasing 25% 100%
Instruments & Valves
Step Rule of Credit Increment % Cumulative %
1 Document Started, Format Accepted, TOC Complete 25% 25%
2
Write-up Complete, Dept Sign-off, Issue for Review / Issue for
Client Approval
25% 50%
3 Code 3 – Rejected, Revise & Re-Submit 10% 60%
4
Code 2 – Approved with Comments, Revise & Re-Submit &
Proceed with Construction
20% 80%
5 Code 1 – Approved without Comments 10% 90%
6 Final Issue / Upload in SAP / Issue for Construction (IFC) 10% 100%
Piping Modeling
Step Rule of Credit Increment % Cumulative %
1
Preliminary : modeled point to point, branch fittings modeled,
pipe support location shown, critical line issued for stressing
20% 20%
2
Detailed : line modeled with valves, fittings and instruments, ISO
generating free of errors
25% 45%
3
Checking : Clash free, physical supports modeled, conforms to
stress analysis,, extracted for checking
30% 75%
4 Code 3 – Rejected, Revise & Re-Submit 0% 75%
5
Code 2 – Approved with Comments, Revise & Re-Submit &
Proceed with Construction
10% 85%
6
Code 1 – Approved without Comments, Final Issue / Release into
SAP
15% 100%
Piping Calculation
Step Rule of Credit Increment % Cumulative %
1 Initiate Pipe Stress Calcs/Issue Deliverables to Mech Eng 20% 20%
2 Prepare / Issue for Client Approval 55% 75%
3 Release / Approved for Construction 25% 100%
Click here to purchase or visit www.ignitetribes.com
Piping Drawing
Step Rule of Credit Increment % Cumulative %
1 Document Started, Format Accepted, TOC Complete 25% 25%
2 Issue for Review / Issue for Client Approval 25% 50%
3 Code 3 – Rejected, Revise & Re-Submit 10% 60%
4
Code 2 – Approved with Comments, Revise & Re-Submit &
Proceed with Construction
20% 80%
5 Code 1 – Approved without Comments 10% 90%
6 Final Issue / Upload in SAP 10% 100%
Procurement - Subcontract
Step Rule of Credit Increment % Cumulative %
1 RFQ issued to subcontractor 10% 10%
2 Technical Bid Evaluation (TBE) 5% 15%
3 Cost Bid Evaluation (CBE) 5% 20%
4 Purchasing Request (PR) 10% 30%
5 PO issued 30% 60%
6 Site mobilization 40% 100%
Procurement - Subcontract
Step Rule of Credit Increment % Cumulative %
1 RFQ issued to subcontractor 10% 10%
2 Tender evaluation done 5% 15%
3 PO placed to vendor 10% 25%
4 Received key vendor drawings 5% 30%
5 Approved key vendor drawing 5% 35%
6 Fabrication 50% 85%
7 Final inspection finished 5% 90%
8 Ex-Work 5% 95%
9 Delivery at site 5% 100%
Procurement – Valves, Bulk Materials
Step Rule of Credit Increment % Cumulative %
1 Issued RFQ 10% 10%
2 Technical Bid Evaluation 10% 20%
3 P.O. Issued 15% 35%
4 Receipt of Major Materials 10% 45%
5 Function Testing 25% 70%
6 Final Inspection 15% 85%
7 Inco Term Delivery Complete 10% 95%
8 PO invoice close out 5% 100%
Procurement – Vessel Standalone
Step Rule of Credit Increment % Cumulative %
1 Issued RFQ 10% 10%
2 Technical Bid Evaluation 10% 20%
3 P.O. Issued 15% 35%
4 Commencement of Fabrication 10% 45%
5 Hydro Static testing 25% 70%
6 Final Inspection 15% 85%
7 Inco Term Delivery Complete 10% 95%
8 PO invoice close out 5% 100%
Fabrication of Equipment Erection
Step Activities Increment % Cumulative %
Equipment Erection
1 Chipping & Padding 5% 5%
2 Lifting & rigging 40% 45%
3 Levelling & grouting 15% 60%
4 Preliminary alignment 20% 80%
5 Final alignment 10% 90%
6 Clear punch list 10% 100%
Fabrication of Piping Erection
Step Activities Increment % Cumulative %
Piping Erection
1 Material at site 5% 5%
2 Pipe laying 20% 25%
3 Preparation 20% 45%
4 Full welding execution 35% 80%
5 NDT 5% 85%
6 Pipe support erection 10% 95%
7 Final inspection 5% 100%
Fabrication of Piping
Step Activities Increment % Cumulative %
Piping Fabrication
1 Weld map drawing preparation 4% 4%
2 Withdrew material 3% 7%
3 Welding preparation 20% 27%
4 Spool assemble and tack weld 25% 52%
5 Full welding execution 20% 72%
6 Non Destructive Test (NDT) 6% 78%
7 Surface preparation and coating 15% 93%
8 Final Inspection 4% 97%
9 Deliver at Site 3% 100%
Tie-In work
Step Activities Increment % Cumulative %
Tie-in Work
1 Preparation done 10% 10%
2 Tagging done 10% 20%
3 Tie-in work 70% 90%
4 Final inspection 10% 100%
Hydrotest
Step Activities Increment % Cumulative %
Hydrotest
1 Preparation done 20% 20%
2 Testing 45% 65%
3 Reinstated 25% 90%
4 Punchlist cleared 10% 100%
Fabrication of Vessel
Step Activities Increment % Cumulative % WBS Weight
Fabricate Nozzles 5%
1 Weld/Fabricate nozzles 50% 50%
2 Completed NDE 50% 100%
Fabricate section number head 5%
1 Layout, cut holes prep 30% 30%
2 Fit/Weld nozzles/compensation pads 70% 100%
Fabricate Section Number 20%
1 Bevel, square, roll vessel 10% 10%
2 Weld long seams / re-roll 15% 25%
3 Layout, cut holes prep 10% 35%
4 Fit/weld nozzles/compensation pads 10% 45%
5 Build/install internal pads and external (trial fit) 55% 100%
Complete vessel / pressure envelope 55%
1 Fit Sections and Weld Circ Seams 25% 25%
2 Local PWHT with Overlap 10% 35%
3 Complete Internal / External Attachments 50% 85%
4 Hydrotest Vessel 15% 100%
Fabrication of Vessel
Step Activities Increment % Cumulative % WBS Weight
Paint 15%
1 Blasting 20%
2 Painting 40%
3 Lining & Acceptable Holiday (Spark) Testing 25%
4 Release 15%
Mechanical Work – Rotating Equipment
Step Activities Increment % Cumulative %
Rotating Equipment
1 Receive material 15% 15%
2 Rough, set. And prelim alignment 20% 35%
3 Level & grout 10% 45%
4 Final alignment 15% 60%
5 Run in 20% 80%
6 Clear punch list 20% 100%
Civil Work – Foundation & Concrete Paving
Step Activities Increment % Cumulative %
Foundation
1 Excavation 10%
2 Rebar 30%
3 Formwork 10%
4 Pouring concrete 15%
5 Strip & finishing 10%
6 Backfilling & compaction 15%
7 Clear punch list 10%
Civil Work – Cable Trench
Step Activities Increment % Cumulative %
Cable Trench
1 Excavation 35% 35%
2 Pre-cast concrete 25% 70%
3 Installation of concrete 25% 95%
4 Clear punch list 5% 100%
Civil Work – RCC Structure
Step Activities Increment % Cumulative %
Cable Trench
1 Excavation/PCC 10% 10%
2 Raft concrete 15% 25%
3 Super structure wall 40% 65%
4 Slab and backfilling 35% 100%
Electrical Cabling
Step Activities Increment % Cumulative %
Electrical cabling
1 Transportation to site 10% 10%
2 Tray erection 30% 40%
3 Cable laying 40% 80%
4 Cable connection 10% 90%
5 Testing 10% 100%
Electrical Fittings
Step Activities Increment % Cumulative %
Cable Trench
1 Installation 50% 50%
2 Cable connection 10% 60%
3 Testing 40% 100%
Fabrication of Piping
Progress tracking Excel sheet available for download in ignite.com
Fabrication of Piping
Click here to purchase
or visit
www.ignitetribes.com
Fabrication of Jacket and Topside
Click here to purchase
or visit
www.ignitetribes.com
Available progress sheet to view and download
Fabrication of Vessel
Click here to purchase
or visit
www.ignitetribes.com
Downstream Progress Weightage Sample
Click here to purchase
or visit
www.ignitetribes.com
Downstream Progress Weightage Sample
Click here to purchase
or visit
www.ignitetribes.com
Downstream Progress Weightage Sample
Click here to purchase or visit
www.ignitetribes.com
Click here to purchase or visit
www.ignitetribes.com
Click here to
purchase or visit
www.ignitetribes.c
om
Thank You …

More Related Content

What's hot

Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
ignitetribes
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
PMI Chennai Chapter
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promo
ignitetribes
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt
TecnicoItca
 
Pid.pdf
Pid.pdfPid.pdf
Pid.pdf
ssuserfc98db
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draft
ignitetribes
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Michael Pink
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendations
ubk1411
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
ADITYA GHUMARE
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
Chris Carson
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
katrin enders
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
McLachlan Lister Pty Limited
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
McLachlan Lister Pty Limited
 
Process Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by TechnipProcess Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by Technip
ignitetribes
 
KSI Presentation Expediting 2014
KSI Presentation Expediting 2014KSI Presentation Expediting 2014
KSI Presentation Expediting 2014
Samanta Ribeiro
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
jmd2011
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
Chris Carson
 
Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
raghunathan janarthanan
 

What's hot (20)

Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promo
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt
 
Pid.pdf
Pid.pdfPid.pdf
Pid.pdf
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draft
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendations
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
Process Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by TechnipProcess Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by Technip
 
KSI Presentation Expediting 2014
KSI Presentation Expediting 2014KSI Presentation Expediting 2014
KSI Presentation Expediting 2014
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
 

Similar to Second edition epc project rule of credit and progress measurement promo

Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.
Mourad Iskandar
 
Rehoboth Beach, DE - Funding the Ocean Outfall Project
Rehoboth Beach, DE - Funding the Ocean Outfall ProjectRehoboth Beach, DE - Funding the Ocean Outfall Project
Rehoboth Beach, DE - Funding the Ocean Outfall Project
rehobothbeachde
 
De assignment
De assignmentDe assignment
De assignment
Lwj Welson
 
Water pipe Lines Progress Planned Vs actual.pptx
Water pipe Lines  Progress Planned Vs actual.pptxWater pipe Lines  Progress Planned Vs actual.pptx
Water pipe Lines Progress Planned Vs actual.pptx
DILIP KUMAR M.Tech (ACT)
 
QAQC Presentation for project startup .pptx
QAQC Presentation for project startup .pptxQAQC Presentation for project startup .pptx
QAQC Presentation for project startup .pptx
AliIrfan66
 
30 bruce valpy - bvg associates
30   bruce valpy - bvg associates30   bruce valpy - bvg associates
30 bruce valpy - bvg associates
johannaparans
 
BENCHMARK PROJECT ALLOCATION
BENCHMARK PROJECT ALLOCATIONBENCHMARK PROJECT ALLOCATION
BENCHMARK PROJECT ALLOCATION
ahmong4
 
Project Quality control Progress .pptx
Project Quality control  Progress .pptxProject Quality control  Progress .pptx
Project Quality control Progress .pptx
DILIP KUMAR M.Tech (ACT)
 
10 DTL flow rate and tank volume calculation.pptx
10 DTL flow rate and tank volume calculation.pptx10 DTL flow rate and tank volume calculation.pptx
10 DTL flow rate and tank volume calculation.pptx
HusseinJabbar6
 
Offshore Cost of Energy NREL WESE Workship Bruce Valpy 14 Jan 2015
Offshore Cost of Energy NREL WESE Workship Bruce Valpy 14 Jan 2015Offshore Cost of Energy NREL WESE Workship Bruce Valpy 14 Jan 2015
Offshore Cost of Energy NREL WESE Workship Bruce Valpy 14 Jan 2015
BVG Associates
 
VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.EngVOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
Julian Kalac P.Eng
 
Monthly report march, 2020(word)
Monthly report march, 2020(word)Monthly report march, 2020(word)
Monthly report march, 2020(word)
thomas victor
 
Schedule of Works Cost Summary Report
Schedule of Works Cost Summary ReportSchedule of Works Cost Summary Report
Schedule of Works Cost Summary Report
Natalie Reid
 
Offshore renewables minimising OPEX Bruce Valpy Nantes 21 May 2015
Offshore renewables  minimising OPEX Bruce Valpy Nantes 21 May 2015Offshore renewables  minimising OPEX Bruce Valpy Nantes 21 May 2015
Offshore renewables minimising OPEX Bruce Valpy Nantes 21 May 2015
BVG Associates
 
JTP - EV Presentation
JTP - EV PresentationJTP - EV Presentation
JTP - EV Presentation
Stanley Taylor
 
WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25
Tofik Nazirov, B.Sc., PhD
 
Destin brass
Destin brass Destin brass
Destin brass
Harshit Goyal
 
Diesel Production: Cost Estimation
Diesel Production: Cost EstimationDiesel Production: Cost Estimation
Diesel Production: Cost Estimation
Pratik Patel
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakhar
Mohammad IFTAKHAR
 
M&E Key Performance Indicators 2016
M&E Key Performance Indicators 2016M&E Key Performance Indicators 2016
M&E Key Performance Indicators 2016
Nerissa Delos Santos
 

Similar to Second edition epc project rule of credit and progress measurement promo (20)

Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.
 
Rehoboth Beach, DE - Funding the Ocean Outfall Project
Rehoboth Beach, DE - Funding the Ocean Outfall ProjectRehoboth Beach, DE - Funding the Ocean Outfall Project
Rehoboth Beach, DE - Funding the Ocean Outfall Project
 
De assignment
De assignmentDe assignment
De assignment
 
Water pipe Lines Progress Planned Vs actual.pptx
Water pipe Lines  Progress Planned Vs actual.pptxWater pipe Lines  Progress Planned Vs actual.pptx
Water pipe Lines Progress Planned Vs actual.pptx
 
QAQC Presentation for project startup .pptx
QAQC Presentation for project startup .pptxQAQC Presentation for project startup .pptx
QAQC Presentation for project startup .pptx
 
30 bruce valpy - bvg associates
30   bruce valpy - bvg associates30   bruce valpy - bvg associates
30 bruce valpy - bvg associates
 
BENCHMARK PROJECT ALLOCATION
BENCHMARK PROJECT ALLOCATIONBENCHMARK PROJECT ALLOCATION
BENCHMARK PROJECT ALLOCATION
 
Project Quality control Progress .pptx
Project Quality control  Progress .pptxProject Quality control  Progress .pptx
Project Quality control Progress .pptx
 
10 DTL flow rate and tank volume calculation.pptx
10 DTL flow rate and tank volume calculation.pptx10 DTL flow rate and tank volume calculation.pptx
10 DTL flow rate and tank volume calculation.pptx
 
Offshore Cost of Energy NREL WESE Workship Bruce Valpy 14 Jan 2015
Offshore Cost of Energy NREL WESE Workship Bruce Valpy 14 Jan 2015Offshore Cost of Energy NREL WESE Workship Bruce Valpy 14 Jan 2015
Offshore Cost of Energy NREL WESE Workship Bruce Valpy 14 Jan 2015
 
VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.EngVOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
 
Monthly report march, 2020(word)
Monthly report march, 2020(word)Monthly report march, 2020(word)
Monthly report march, 2020(word)
 
Schedule of Works Cost Summary Report
Schedule of Works Cost Summary ReportSchedule of Works Cost Summary Report
Schedule of Works Cost Summary Report
 
Offshore renewables minimising OPEX Bruce Valpy Nantes 21 May 2015
Offshore renewables  minimising OPEX Bruce Valpy Nantes 21 May 2015Offshore renewables  minimising OPEX Bruce Valpy Nantes 21 May 2015
Offshore renewables minimising OPEX Bruce Valpy Nantes 21 May 2015
 
JTP - EV Presentation
JTP - EV PresentationJTP - EV Presentation
JTP - EV Presentation
 
WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25
 
Destin brass
Destin brass Destin brass
Destin brass
 
Diesel Production: Cost Estimation
Diesel Production: Cost EstimationDiesel Production: Cost Estimation
Diesel Production: Cost Estimation
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakhar
 
M&E Key Performance Indicators 2016
M&E Key Performance Indicators 2016M&E Key Performance Indicators 2016
M&E Key Performance Indicators 2016
 

More from ignitetribes

Primavera Activity ID Coding
Primavera Activity ID CodingPrimavera Activity ID Coding
Primavera Activity ID Coding
ignitetribes
 
Headed Towards Burnout
Headed Towards BurnoutHeaded Towards Burnout
Headed Towards Burnout
ignitetribes
 
The Leadership Qualities of Elon Musk
The Leadership Qualities of Elon MuskThe Leadership Qualities of Elon Musk
The Leadership Qualities of Elon Musk
ignitetribes
 
Improving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dunganImproving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dungan
ignitetribes
 
101 toughest interviews_questions
101 toughest interviews_questions101 toughest interviews_questions
101 toughest interviews_questions
ignitetribes
 
Technip case study
Technip case studyTechnip case study
Technip case study
ignitetribes
 
Project planning and control training with lego
Project planning and control training with legoProject planning and control training with lego
Project planning and control training with lego
ignitetribes
 

More from ignitetribes (7)

Primavera Activity ID Coding
Primavera Activity ID CodingPrimavera Activity ID Coding
Primavera Activity ID Coding
 
Headed Towards Burnout
Headed Towards BurnoutHeaded Towards Burnout
Headed Towards Burnout
 
The Leadership Qualities of Elon Musk
The Leadership Qualities of Elon MuskThe Leadership Qualities of Elon Musk
The Leadership Qualities of Elon Musk
 
Improving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dunganImproving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dungan
 
101 toughest interviews_questions
101 toughest interviews_questions101 toughest interviews_questions
101 toughest interviews_questions
 
Technip case study
Technip case studyTechnip case study
Technip case study
 
Project planning and control training with lego
Project planning and control training with legoProject planning and control training with lego
Project planning and control training with lego
 

Recently uploaded

ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
PECB
 
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
imrankhan141184
 
Electric Fetus - Record Store Scavenger Hunt
Electric Fetus - Record Store Scavenger HuntElectric Fetus - Record Store Scavenger Hunt
Electric Fetus - Record Store Scavenger Hunt
RamseyBerglund
 
The basics of sentences session 7pptx.pptx
The basics of sentences session 7pptx.pptxThe basics of sentences session 7pptx.pptx
The basics of sentences session 7pptx.pptx
heathfieldcps1
 
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptxPengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Fajar Baskoro
 
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptxBIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
RidwanHassanYusuf
 
Standardized tool for Intelligence test.
Standardized tool for Intelligence test.Standardized tool for Intelligence test.
Standardized tool for Intelligence test.
deepaannamalai16
 
How to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 InventoryHow to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 Inventory
Celine George
 
Benner "Expanding Pathways to Publishing Careers"
Benner "Expanding Pathways to Publishing Careers"Benner "Expanding Pathways to Publishing Careers"
Benner "Expanding Pathways to Publishing Careers"
National Information Standards Organization (NISO)
 
Walmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdfWalmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdf
TechSoup
 
BBR 2024 Summer Sessions Interview Training
BBR  2024 Summer Sessions Interview TrainingBBR  2024 Summer Sessions Interview Training
BBR 2024 Summer Sessions Interview Training
Katrina Pritchard
 
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDFLifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
Vivekanand Anglo Vedic Academy
 
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
mulvey2
 
Haunted Houses by H W Longfellow for class 10
Haunted Houses by H W Longfellow for class 10Haunted Houses by H W Longfellow for class 10
Haunted Houses by H W Longfellow for class 10
nitinpv4ai
 
A Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two HeartsA Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two Hearts
Steve Thomason
 
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptxChapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Denish Jangid
 
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptxNEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
iammrhaywood
 
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdfREASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
giancarloi8888
 
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
EduSkills OECD
 
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
Himanshu Rai
 

Recently uploaded (20)

ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
 
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
 
Electric Fetus - Record Store Scavenger Hunt
Electric Fetus - Record Store Scavenger HuntElectric Fetus - Record Store Scavenger Hunt
Electric Fetus - Record Store Scavenger Hunt
 
The basics of sentences session 7pptx.pptx
The basics of sentences session 7pptx.pptxThe basics of sentences session 7pptx.pptx
The basics of sentences session 7pptx.pptx
 
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptxPengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptx
 
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptxBIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
BIOLOGY NATIONAL EXAMINATION COUNCIL (NECO) 2024 PRACTICAL MANUAL.pptx
 
Standardized tool for Intelligence test.
Standardized tool for Intelligence test.Standardized tool for Intelligence test.
Standardized tool for Intelligence test.
 
How to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 InventoryHow to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 Inventory
 
Benner "Expanding Pathways to Publishing Careers"
Benner "Expanding Pathways to Publishing Careers"Benner "Expanding Pathways to Publishing Careers"
Benner "Expanding Pathways to Publishing Careers"
 
Walmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdfWalmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdf
 
BBR 2024 Summer Sessions Interview Training
BBR  2024 Summer Sessions Interview TrainingBBR  2024 Summer Sessions Interview Training
BBR 2024 Summer Sessions Interview Training
 
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDFLifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
 
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
 
Haunted Houses by H W Longfellow for class 10
Haunted Houses by H W Longfellow for class 10Haunted Houses by H W Longfellow for class 10
Haunted Houses by H W Longfellow for class 10
 
A Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two HeartsA Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two Hearts
 
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptxChapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptx
 
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptxNEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
 
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdfREASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
 
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
 
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
 

Second edition epc project rule of credit and progress measurement promo

  • 1. EPC Project Rule Of Credit and Progress measurement Click here to purchase or visit www.ignitetribes.com
  • 2. Level 1 - WBS WBS DESCRIPTION WEIGHTAGE BASIS COST (RM) WEIGHT FACTOR ENG ENGINEERING Manhour 1,862,010 0.064 PRC PROCUREMENT Cost 6,499,944 0.223 CM CONSTRUCTION Cost 19,770,791 0.679 CON COMMISIONING Cost 967,255 0.032 Total Cost 2,9100,000 Weight Factor = Cost Total cost
  • 3. Level 2 - WBS BASIS COST (RM) WEIGHT FACTOR ENGINEERING (TOTAL COST) $1,862,010.00 CIVIL & STRUCTURE Manhour $380,890.00 20.46% PROCESS Manhour $207,710.00 11.16% MECHANICAL Manhour $260,160.00 13.97% GENERAL Manhour $140,580.00 7.55% PIPING Manhour $376,430.00 20.22% ELECTRICAL Manhour $296,200.00 15.91% INSTRUMENTATION Manhour $200,040.00 10.74% Weight Factor = Discipline Cost Engineering Total cost Engineering Work Category Breakdown
  • 4. Level 4 - WBS ENGINEERING (Weightage) ( Option 1) Proposed Weightage ( Option 2) Proposed Weightage Study & Design Preparation 40 % Issued for Approval 40% Client Comment - Incorporate Client Comment - Issued for Construction 20% Issue for review (IFR) 10% Issue for approval (IFA) 20% Issue for construction (IFC) 30% Approved for construction 40%
  • 5. Level 4 - WBS Study and Design Preparation IFR IFA IFC AFC Progress (% Complete) Weight Progress Document Title Category Discipline Budgeted Man Hour Weight Factor 5% 15% 20% 25% 35% Tie In Plan Dwg Piping 300 0.05484 100.0% 100.0% 100.0% 100.0% 33.0% 76.6% 4.2% Piping GA Dwg Piping 400 0.07313 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 7.3% Tie In Isometric Dwg Piping 350 0.06399 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 6.4% Standard Pipe Support Dwg Piping 450 0.08227 100.0% 100.0% 100.0% 100.0% 33.0% 76.6% 6.3% Demolition Dwg Piping 350 0.06399 100.0% 100.0% 100.0% 75.0% 0.0% 58.8% 3.8% Tie In List Doc Piping 550 0.10055 100.0% 55.5% 0.0% 0.0% 0.0% 13.3% 1.3% Critical Line List Doc Piping 600 0.10969 100.0% 55.5% 0.0% 0.0% 0.0% 13.3% 1.5% Stress Analysis Report Doc Piping 800 0.14625229 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Coating Specs Doc Piping 850 0.15539305 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Piping class Doc Piping 820 0.14990859 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% GRAND TOTAL 5470 1.0000 30.8% % Complete= (5% x 100%) + (15% x 100%) + (20% x 100%) +(25% x 100%)+( 35% x 33.0%) Weight factor = 0.0584 * 76.6 %Progress tracking Excel sheet available for download in ignite.com
  • 6. Engineering Step Rule of Credit Increment % Cumulative % 1 Study and design preparation 5% 5% 2 Issue for review (IFR) 10% 15% 3 Issue for approval (IFA) 20% 35% 4 Issue for construction (IFC) 30% 65% 5 Approved for construction 35% 100%
  • 7. Engineering Step Rule of Credit Increment % Cumulative % 1 Study and design preparation 10% 10% 2 Issue to client 30% 40% 3 Approval by client 35% 75% 4 Issue for construction / purchasing 25% 100%
  • 8. Instruments & Valves Step Rule of Credit Increment % Cumulative % 1 Document Started, Format Accepted, TOC Complete 25% 25% 2 Write-up Complete, Dept Sign-off, Issue for Review / Issue for Client Approval 25% 50% 3 Code 3 – Rejected, Revise & Re-Submit 10% 60% 4 Code 2 – Approved with Comments, Revise & Re-Submit & Proceed with Construction 20% 80% 5 Code 1 – Approved without Comments 10% 90% 6 Final Issue / Upload in SAP / Issue for Construction (IFC) 10% 100%
  • 9. Piping Modeling Step Rule of Credit Increment % Cumulative % 1 Preliminary : modeled point to point, branch fittings modeled, pipe support location shown, critical line issued for stressing 20% 20% 2 Detailed : line modeled with valves, fittings and instruments, ISO generating free of errors 25% 45% 3 Checking : Clash free, physical supports modeled, conforms to stress analysis,, extracted for checking 30% 75% 4 Code 3 – Rejected, Revise & Re-Submit 0% 75% 5 Code 2 – Approved with Comments, Revise & Re-Submit & Proceed with Construction 10% 85% 6 Code 1 – Approved without Comments, Final Issue / Release into SAP 15% 100%
  • 10. Piping Calculation Step Rule of Credit Increment % Cumulative % 1 Initiate Pipe Stress Calcs/Issue Deliverables to Mech Eng 20% 20% 2 Prepare / Issue for Client Approval 55% 75% 3 Release / Approved for Construction 25% 100% Click here to purchase or visit www.ignitetribes.com
  • 11. Piping Drawing Step Rule of Credit Increment % Cumulative % 1 Document Started, Format Accepted, TOC Complete 25% 25% 2 Issue for Review / Issue for Client Approval 25% 50% 3 Code 3 – Rejected, Revise & Re-Submit 10% 60% 4 Code 2 – Approved with Comments, Revise & Re-Submit & Proceed with Construction 20% 80% 5 Code 1 – Approved without Comments 10% 90% 6 Final Issue / Upload in SAP 10% 100%
  • 12. Procurement - Subcontract Step Rule of Credit Increment % Cumulative % 1 RFQ issued to subcontractor 10% 10% 2 Technical Bid Evaluation (TBE) 5% 15% 3 Cost Bid Evaluation (CBE) 5% 20% 4 Purchasing Request (PR) 10% 30% 5 PO issued 30% 60% 6 Site mobilization 40% 100%
  • 13. Procurement - Subcontract Step Rule of Credit Increment % Cumulative % 1 RFQ issued to subcontractor 10% 10% 2 Tender evaluation done 5% 15% 3 PO placed to vendor 10% 25% 4 Received key vendor drawings 5% 30% 5 Approved key vendor drawing 5% 35% 6 Fabrication 50% 85% 7 Final inspection finished 5% 90% 8 Ex-Work 5% 95% 9 Delivery at site 5% 100%
  • 14. Procurement – Valves, Bulk Materials Step Rule of Credit Increment % Cumulative % 1 Issued RFQ 10% 10% 2 Technical Bid Evaluation 10% 20% 3 P.O. Issued 15% 35% 4 Receipt of Major Materials 10% 45% 5 Function Testing 25% 70% 6 Final Inspection 15% 85% 7 Inco Term Delivery Complete 10% 95% 8 PO invoice close out 5% 100%
  • 15. Procurement – Vessel Standalone Step Rule of Credit Increment % Cumulative % 1 Issued RFQ 10% 10% 2 Technical Bid Evaluation 10% 20% 3 P.O. Issued 15% 35% 4 Commencement of Fabrication 10% 45% 5 Hydro Static testing 25% 70% 6 Final Inspection 15% 85% 7 Inco Term Delivery Complete 10% 95% 8 PO invoice close out 5% 100%
  • 16. Fabrication of Equipment Erection Step Activities Increment % Cumulative % Equipment Erection 1 Chipping & Padding 5% 5% 2 Lifting & rigging 40% 45% 3 Levelling & grouting 15% 60% 4 Preliminary alignment 20% 80% 5 Final alignment 10% 90% 6 Clear punch list 10% 100%
  • 17. Fabrication of Piping Erection Step Activities Increment % Cumulative % Piping Erection 1 Material at site 5% 5% 2 Pipe laying 20% 25% 3 Preparation 20% 45% 4 Full welding execution 35% 80% 5 NDT 5% 85% 6 Pipe support erection 10% 95% 7 Final inspection 5% 100%
  • 18. Fabrication of Piping Step Activities Increment % Cumulative % Piping Fabrication 1 Weld map drawing preparation 4% 4% 2 Withdrew material 3% 7% 3 Welding preparation 20% 27% 4 Spool assemble and tack weld 25% 52% 5 Full welding execution 20% 72% 6 Non Destructive Test (NDT) 6% 78% 7 Surface preparation and coating 15% 93% 8 Final Inspection 4% 97% 9 Deliver at Site 3% 100%
  • 19. Tie-In work Step Activities Increment % Cumulative % Tie-in Work 1 Preparation done 10% 10% 2 Tagging done 10% 20% 3 Tie-in work 70% 90% 4 Final inspection 10% 100%
  • 20. Hydrotest Step Activities Increment % Cumulative % Hydrotest 1 Preparation done 20% 20% 2 Testing 45% 65% 3 Reinstated 25% 90% 4 Punchlist cleared 10% 100%
  • 21. Fabrication of Vessel Step Activities Increment % Cumulative % WBS Weight Fabricate Nozzles 5% 1 Weld/Fabricate nozzles 50% 50% 2 Completed NDE 50% 100% Fabricate section number head 5% 1 Layout, cut holes prep 30% 30% 2 Fit/Weld nozzles/compensation pads 70% 100% Fabricate Section Number 20% 1 Bevel, square, roll vessel 10% 10% 2 Weld long seams / re-roll 15% 25% 3 Layout, cut holes prep 10% 35% 4 Fit/weld nozzles/compensation pads 10% 45% 5 Build/install internal pads and external (trial fit) 55% 100% Complete vessel / pressure envelope 55% 1 Fit Sections and Weld Circ Seams 25% 25% 2 Local PWHT with Overlap 10% 35% 3 Complete Internal / External Attachments 50% 85% 4 Hydrotest Vessel 15% 100%
  • 22. Fabrication of Vessel Step Activities Increment % Cumulative % WBS Weight Paint 15% 1 Blasting 20% 2 Painting 40% 3 Lining & Acceptable Holiday (Spark) Testing 25% 4 Release 15%
  • 23. Mechanical Work – Rotating Equipment Step Activities Increment % Cumulative % Rotating Equipment 1 Receive material 15% 15% 2 Rough, set. And prelim alignment 20% 35% 3 Level & grout 10% 45% 4 Final alignment 15% 60% 5 Run in 20% 80% 6 Clear punch list 20% 100%
  • 24. Civil Work – Foundation & Concrete Paving Step Activities Increment % Cumulative % Foundation 1 Excavation 10% 2 Rebar 30% 3 Formwork 10% 4 Pouring concrete 15% 5 Strip & finishing 10% 6 Backfilling & compaction 15% 7 Clear punch list 10%
  • 25. Civil Work – Cable Trench Step Activities Increment % Cumulative % Cable Trench 1 Excavation 35% 35% 2 Pre-cast concrete 25% 70% 3 Installation of concrete 25% 95% 4 Clear punch list 5% 100%
  • 26. Civil Work – RCC Structure Step Activities Increment % Cumulative % Cable Trench 1 Excavation/PCC 10% 10% 2 Raft concrete 15% 25% 3 Super structure wall 40% 65% 4 Slab and backfilling 35% 100%
  • 27. Electrical Cabling Step Activities Increment % Cumulative % Electrical cabling 1 Transportation to site 10% 10% 2 Tray erection 30% 40% 3 Cable laying 40% 80% 4 Cable connection 10% 90% 5 Testing 10% 100%
  • 28. Electrical Fittings Step Activities Increment % Cumulative % Cable Trench 1 Installation 50% 50% 2 Cable connection 10% 60% 3 Testing 40% 100%
  • 29. Fabrication of Piping Progress tracking Excel sheet available for download in ignite.com
  • 30. Fabrication of Piping Click here to purchase or visit www.ignitetribes.com
  • 31. Fabrication of Jacket and Topside Click here to purchase or visit www.ignitetribes.com Available progress sheet to view and download
  • 32. Fabrication of Vessel Click here to purchase or visit www.ignitetribes.com
  • 33. Downstream Progress Weightage Sample Click here to purchase or visit www.ignitetribes.com
  • 34. Downstream Progress Weightage Sample Click here to purchase or visit www.ignitetribes.com
  • 35. Downstream Progress Weightage Sample Click here to purchase or visit www.ignitetribes.com Click here to purchase or visit www.ignitetribes.com Click here to purchase or visit www.ignitetribes.c om