SlideShare a Scribd company logo
OFFSHORE WIND CABLES
June 2012
Key industry players, cable cost breakdown, economical and technical drivers,
challenges and key innovations
Table of Contents
01 Introduction to offshore wind cables
02 Key industry players
03 Cost breakdown
04 Economical and technical drivers
05 Cable challenges
06 Demand for cost reductions
07 Key innovations
08 Remarks
09 Perspectives
4
6
7
8
9
10
11
12
13
Foreword
This insight provides an introduction to offshore wind cables and the key
industry players.
The cost structure of cables, the demand for cost reductions, as well as
the economical and technical drivers are examined.
Furthermore, the major challenges within the cable industry and key
innovations in recent projects and those under development are studied.
Page 3
The insight has been
developed in close
collaboration with Catalyst
Strategy Consulting, an
international consultancy,
which operates in the nexus
of technology and business,
and holds ample experience
and specialization in
especially the Maritime,
Energy & Offshore, and
Cleantech industries
Medium voltage array cables interconnect the turbines and the substation, high voltage
export cables connect the offshore substation to onshore and subsea cable burial is the
current best practice to ensure cable protection
Page 4
INTRODUCTION TO OFFSHORE WIND CABLES
Source: MEC Intelligence analysis
Array/infield/collection grid cables – interconnecting turbines to substation
• Transformers at each wind turbine, usually in the base of the tower, are used to step up from the generation voltage, typically 690 volts (V), to a
medium voltage of typically 25–40 kilovolts (kV)
• This voltage range seems to be preferred because standardized equipment is available at competitive prices and because higher voltage transformers
would be too big to fit readily into the tower cross sections
• A grid of medium-voltage submarine cables, typically buried 1–2 meters (m) deep in the seabed, is used to connect the wind turbines to an offshore
substation
Transmission/export cables – connecting offshore substation to onshore substation
• The transmission system begins at the offshore substation, which steps up the voltage to a transmission voltage of 130–150 kV, the highest voltages in
use today for AC submarine cables. This higher voltage allows a much smaller diameter and lower cost submarine cables to be used for the long run to
shore
• There are two technology options available for the transmission system associated with offshore wind power:
• HVAC (high voltage alternating current)
• HVDC (high voltage direct current)
• HVAC is generally thought to be the most economical for distances shorter than 50 km
• Between 50 km and 80 km HVAC and HVDC are expected to be similar in costs
• Above 80 km HVDC will likely be the economically most attractive solution
• This is mainly due to the effective capacity of a given HVAC drops with distance due to capacitive and inductive characteristics of the cable and
their associated line losses (~10% loss)
• HVDC avoids these line losses completely and is therefore the preferred technology for long distance.
Cable installation
• Subsea cable burial ensures cable protection in distribution systems worldwide and is widespread best practice in the telecoms industry. Left
unprotected, power cable, fiber optic telephone cable and oil and gas pipe is vulnerable to damage from ship anchors, fishing activity and other threats.
INDICATIVE
A number of different methods for cable installation exist but the most common is to
simultaneously lay and bury the cable using a plough
Page 5
CABLE INSTALLATION
Source: MEC Intelligence analysis
Simultaneous lay and bury using plough
• A plough is pulled by a cable laying vessel/barge and the cable is laid by a turntable on the vessel
• The plough buries the cable in a trench of approx. 2 m deep using a high pressure water jet
• The water jet fluidizes the sand/mud and the cable sinks into the trench
• Most common method for cable installation especially for export cables
• Cables are stretched to ensure a
high tension when put in the
trench using a control system on a
barge
• Important to minimize tension at
turning points to ensure cable stays
in the trench
• Diver is used to confirm the
touchdown of the cable in the
trench and to carry out post-lay
inspection of the array cables
• Inflated airbags are used to pull-in
the export cable onto the shore
• Inter-array cables are pulled-in
from the substation to the
foundations fed up through J-tubes
inside the foundations
INDICATIVE
1
2
3
4
5
Simultaneous lay and bury using ROV
• Similar to abovementioned method but utilizes a ROV instead of a plough
• The ROV carries the cable in a spool which limits is use to inner-array cables
• The preferred installation method when using the turbine installation vessel for cable installation
Pre-excavate
• A backhoe dredge is used to pre-excavate a trench
• A cable laying vessel lays the cable in the trench and the trench is filled using the dredge
• The method may also utilize floating cables over the trench via airbags
• Used for both array and export cable installation
Lay and trench
• A cable laying vessel lays the cables on the seabed and a trench is made using a ROV
• This method has been used for both array and export cables
Pull and trench
• Cables are pulled among turbines using a winch and later on they are buried with a ROV or plough
• Only useful for inner-array connections
Installation methods General
The offshore wind cable industry is relatively fragmented in cables, consolidated in
equipment, populated by 4-5 key players in cable installation
Page 6
KEY INDUSTRY PLAYERS
Source: MEC Intelligence analysis
• Nexans (FR)
• ABB Submarine Cables (SE)
• LS Cable and System (KR)
• JDR Cable Systems (UK)
• NKT Cables Group (DE)
• NSW/Corning (DE)
• Prysmian Cables and Systems (Draka
Offshore) (IT)
• Siemens (DE)
• ZTT Group (CN)
• Borealis Group (AT)
INDICATIVE
• Pharos Offshore Group (UK)
• SMD (UK)
• CTC Marine (UK)
• JD-Contractor (DK)
• Global Marine Systems (UK)
• VSMC (DE)
• S.B. Submarine Systems Co.
Ltd. (CN)
• Beluga Shipping (DE)
• Modus Seabed Intervention
(UK)
Cable manufacturers Equipment manufacturers Cable installers
The general trend shows a decreasing cost pr. installed MW offshore – however, the value mix is
changing, as logistics and installations costs are taking a larger share of the value compared to
traditional cost components - e.g. the turbine – Cable cost is expected to grow along with distance
to shore and effective load increase
Page 7Source: MEC Intelligence analysis
Logistics
and
Installation
21%
Other
5%
Project
Mgmt and
Permits
6%
Electrical
infrastructure
& cables
14%
Foundation
19%
Turbine
35%
Total
installation
100%
Total
100%
Logistics
28%
Installation
72%
Tower
17%
Blade
25%
Foundation
35%
Total
100%
Cables
2%
Substation
4%
Hub
8%
Nacelle
9%
Capital Cost Breakdown (% per MW) Installation & Logistics
(% per MW)
Installation* (% per MW)
Logistics (% per MW)
Foundation
33%
Total
100%
Cables
33%
Substation
8%
Hub
7%
Nacelle
7%
Tower
7%
Blade
7%
Turbine
Unit cost trend compared relatively to peers
COST BREAKDOWN
*Note on installation split of turbine – split will vary
• Nacelle and hubs are joined at the port along with 2 blades = one unit
• Tower is one unit
• The third blade is one unit
INDICATIVE
The primary economical and technological drivers are related to the installation and
burial of subsea cables and ~70% of insurance claims from offshore wind farm
operations relate to cable damage
Page 8
ECONOMICAL AND TECHNICAL DRIVERS
Source: MEC Intelligence analysis
• Installation of subsea cables has been characterized
by cost overruns and cable damage in a number of
cases
• Subsea cables have been the largest source of
insurance claims in offshore wind to date
• It has been estimated that subsea cable laying
accounts for between 5-10% of the capital cost of
the wind farm development but ~70% of insurance
claims from wind farm operations relate to cable
damage
INDICATIVE
• Technology development has a key role to play in
impacting costs
• As offshore wind farms are located further from
shore, point-to-point HVDC systems will prove more
cost effective than HVAC
Economical Drivers Technical Drivers
Poor understanding of environmental conditions, poor planning regarding cable
installation and risk of shortage of high-voltage cables and trained workers pose the
primary cable challenges
Page 9
CABLE CHALLENGES
Source: MEC Intelligence analysis
• Poor understanding of weather and
marine environment
• Access difficulties due to unexpectedly
severe weather conditions
• Harder or softer ground being
encountered impeding burial machinery
• Unexpected topography e.g. slopes and
holes
• Poor definition of environmental risks
leading to tight permitting windows
• Poor appreciation of the wave/tidal
environment leading to tight operational
windows
• Poor understanding of marine
environment leading to excessive
weather delays
EXAMPLE
• Lack of consultation with cable
manufacturers / marine contractors
regarding the practicalities of
installation
• Lack of quality in cable route survey
definition and data interpretation for
the cable route
• Developers accepted consent
conditions that are unrealistic or
impractical
• Poor understanding of impacts of
construction
• Unrealistic permit conditions being
passed on to contractors to implement
• Risk of a high-voltage subsea cable
shortage in the next few years as
well as a possible shortage of trained
workers
• The supply base is currently limited
to a number of companies and time
to establish new production facilities
is significant depending on
competition from other energy
infrastructure projects
Risk of shortage of high-voltage subsea
cables and possibly trained workers
Poor planning regarding cable installationPoor understanding of environmental
conditions
The major offshore wind expansion plans on the horizon drives the demand for cable
cost and insurance claims reduction
Page 10
DEMAND FOR CABLE COST REDUCTIONS
Source: MEC Intelligence analysis
EXAMPLES
• With major industry expansion plans on the horizon, there has never been a greater
need for the industry to come together and develop a coordinated approach to the
challenges it faces going forward.
Major offshore wind expansion plans
• The installation and burial processes currently being used have resulted in many
insurance claims being made by offshore developers to cover the costs of damage to
cables.
Substantial insurance claims due to cable damage
Key innovations in order to drive cost down on cables include cable installation and
maintenance robots, alternative HVDC cable technologies, AC/DC rectifier technology
development and new types of submarine cables
Page 11
KEY INNOVATIONS
Source: MEC Intelligence analysis
EXAMPLES
• Underwater robot developed for subsea cable burial
• Provides more scheduling flexibility
• Inter-array cables can be installed more quickly
• Less need for expensive diving activities
• Cable maintenance robot
• More cost-efficient measure of maintenance
Cable installation
• HVDC Plus (Siemens technology)
• Modular multilevel voltage-sourced converters
• Preferred solution where shortage of space is a criterion
• Improves the performance of the transmission grid with
regard to system security
• Will be used for the world’s longest HVDC submarine grid
connecting England and Scotland (420 km)
• HVDC Light (ABB technology)
• Increases the reliability of power grids
• Upper range: 1,200 MW and ±500 kV.
Cable technology
• Mercury arc valves
• Thyristor converters
AC/DC rectifier technology development
• Mass-impregnated cables
• Self-contained fluid-filled cables
• Extruded insulation cables
Types of submarine cables used
Findings
Page 12
REMARKS
VII
VIII
VI
IIII
V
III
I
II
Medium voltage array cables interconnect the turbines and the substation, high voltage export cables connect the
offshore substation to onshore and subsea cable burial is the current best practice to ensure cable protection
A number of different methods for cable installation exist but the most common is to simultaneously lay and bury the
cable using a plough
The offshore wind cable industry is dominated by a limited number of players on the cable and equipment side and 4-
5 key players on the cable installation side
Cables account for ~14% of the balance of plant with export cables accounting for ~75% and array cables accounting
for ~25%, and cables account for ~33% of installation and commissioning costs which is a significant share
The primary economic and technological drivers are related to the installation and burial of subsea cables and ~70%
of insurance claims from offshore wind farm operations relate to cable damage
Poor understanding of environmental conditions, poor planning regarding cable installation and risk of shortage of
high-voltage cables and trained workers pose the primary cable challenges
The major offshore wind expansion plans on the horizon and the many economic and technical challenges currently
facing the offshore wind cable industry drives the demand for cable cost reductions
Key innovations in order to drive cost down on cables include cable installation and maintenance robots, alternative
HVDC cable technologies, AC/DC rectifier technology development and new types of submarine cables
Source: MEC Intelligence Analysis
Perspectives
Page 13
REMARKS
Source: MEC Intelligence Analysis
Considering the ambition to reduce the cost of offshore wind energy – would innovations in logistics and supply chain,
be able to stand up to the requirements? Which areas are likely to become bottlenecks?
With the value split in the offshore wind changing rapidly, which are the key stakeholders who are positioned to win
and lose market share in the future offshore wind energy market?
What does the emergence of markets and industries across the globe mean, in the context of the contemporary
suppliers?
Considering supply constraints, and the need to build operational excellence and flexibility - are there business models
and/or innovative port infrastructure configurations, which yield competitive advantage?
With the offshore wind market rapidly becoming global - which local rules, policies, and various stakeholder decision
making criteria, are essential to know to grow and sustain markets?
Considering the requirement of local content in the markets, how should companies organize to branch-out
internationally?
About MEC Intelligence
MEC Intelligence supports growth strategies in the Maritime, Energy, and
Cleantech Industries by offering high quality analysis of the clients’ growth
questions – bringing together in-depth understanding of industry dynamics and
fact driven, global, and independent market research.
We create insights that are real, actionable, and integrate seamlessly into the
clients’ decision process by working in a one-to-one relationship with clients.
We have a strategic partnership with Catalyst Strategy Consulting to bring
synergistic advisory expertise.
Catalyst Strategy Consulting is one of Europe’s leading strategy consultancies
with focus on the Maritime, Energy, and Cleantech sectors. The company
advises global top companies and leading private equity funds on business
model innovation and growth strategies.
Please visit Catalyst Strategy Consulting for more information.
Page 14
Knowledge support for
effective decisions aimed at
anticipating and winning the
right growth opportunities
Sample Publications in Offshore Wind
MEC Intelligence has conducted a vast range of bespoke researched studies for
leading international companies in the areas of Maritime, Energy and Cleantech
– along with authoring a range of free and commercial insights and reports
within our focal domains
Publications and Credentials
Offshore Wind Foundation
October 2011
Offshore Wind Cables
June 2012
Offshore Wind Logistics
July 2012
Offshore wind market in China
August 2012
Sample Publications in Marine and Cleantech
LNG as Propulsion Fuel
October 2011
Electric Vehicles
December 2011
MEC Intelligence holds ample experience and expertise
within market forecasting and analysis, project cost
benchmarking in e.g. sourcing, best practice studies etc.
We leverage an extensive network of experts and
professionals, to provide bespoke research and analysis,
catering to your specific needs – contact us directly to
receive an individual quote to your specific research needs
MEC Intelligence India
MEC Consulting Pvt. Ltd.
Levels 5, 6 and 7
JMD Regent Square
Mehrauli-Gurgaon Road
Gurgaon
India
Tel: +91 9810 53 3550
Email: India@mecintelligence.com
MEC Intelligence Denmark
Nordre Fasanvej 113,2;
2000 Frederiksberg.
Copenhagen
Denmark
Tel: +45 3543 3277
Email: Europe@mecintelligence.com
The information in this document has been obtained from sources believed to be reliable. MEC Intelligence disclaim all warranties as to the accuracy, completeness or adequacy of such information.
We shall have no liability for errors or inadequacies in the information contained herein or for interpretations thereof.
This document is protected by copyright. Republication, reproduction or commercial use of the glossary and artwork, in whole or in part, is prohibited without the written permission of MEC
Intelligence. © MEC Intelligence

More Related Content

What's hot

Micro grid
Micro gridMicro grid
Micro grid
Nadeem Rana
 
Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...
Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...
Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...Aodhgan Gleeson
 
Power System Control
Power System ControlPower System Control
Power System Control
Ridwanul Hoque
 
Présentation d'un guide d'une etude solaire
Présentation d'un guide d'une etude solairePrésentation d'un guide d'une etude solaire
Présentation d'un guide d'une etude solaire
RabbazMohssine
 
Microgrid management
Microgrid managementMicrogrid management
Séminaire Smart-Grid | TECHNIFUTUR
Séminaire Smart-Grid | TECHNIFUTURSéminaire Smart-Grid | TECHNIFUTUR
Séminaire Smart-Grid | TECHNIFUTUR
Cluster TWEED
 
Electronique de puissance cours complet www.cours-online.com
Electronique de puissance cours complet  www.cours-online.comElectronique de puissance cours complet  www.cours-online.com
Electronique de puissance cours complet www.cours-online.com
morin moli
 
Relay coordination
Relay coordinationRelay coordination
Relay coordination
D Målîk
 
Microgrid tecnology
Microgrid tecnologyMicrogrid tecnology
Microgrid tecnology
Akash Bhat
 
Introduction to Microgrid
Introduction to Microgrid Introduction to Microgrid
Breakdown due to Internal Discharges and Surface Breakdown
Breakdown due to Internal Discharges and Surface BreakdownBreakdown due to Internal Discharges and Surface Breakdown
Breakdown due to Internal Discharges and Surface Breakdown
Asim Raza
 
Vaccum Circuit Breaker
Vaccum Circuit BreakerVaccum Circuit Breaker
Vaccum Circuit BreakerRAHUL-GOPU
 
Hybrid AC/DC microgrid and Electric Vehicles
Hybrid AC/DC microgrid and Electric VehiclesHybrid AC/DC microgrid and Electric Vehicles
Hybrid AC/DC microgrid and Electric VehiclesMd Shamiur Rahman
 
Overcurrent and Distance Protection in DigSilent PowerFactory
Overcurrent and Distance Protection in DigSilent PowerFactoryOvercurrent and Distance Protection in DigSilent PowerFactory
Overcurrent and Distance Protection in DigSilent PowerFactory
Areeb Abdullah
 
Droop control approach for power sharing in AC microgrid
Droop control approach for power sharing in AC microgrid Droop control approach for power sharing in AC microgrid
Droop control approach for power sharing in AC microgrid
Siksha 'O' Anusandhan (Deemed to be University )
 
switching substation, plcc and scada
switching substation, plcc and scadaswitching substation, plcc and scada
switching substation, plcc and scada
Hemendra Kumar Rajput
 
Guide Energie éolienne - ademe
Guide Energie éolienne - ademe Guide Energie éolienne - ademe
Guide Energie éolienne - ademe
Build Green
 
Power Systems analysis with MATPOWER and Simscape Electrical (MATLAB/Simulink)
Power Systems analysis with MATPOWER and Simscape Electrical (MATLAB/Simulink) Power Systems analysis with MATPOWER and Simscape Electrical (MATLAB/Simulink)
Power Systems analysis with MATPOWER and Simscape Electrical (MATLAB/Simulink)
Bilal Amjad
 
Cours du réseau électrique
Cours du réseau électriqueCours du réseau électrique
Cours du réseau électrique
AbdelazizELGhzizal
 
Presentation on Power Transformer
Presentation on Power TransformerPresentation on Power Transformer
Presentation on Power Transformer
Ajay Maurya
 

What's hot (20)

Micro grid
Micro gridMicro grid
Micro grid
 
Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...
Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...
Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...
 
Power System Control
Power System ControlPower System Control
Power System Control
 
Présentation d'un guide d'une etude solaire
Présentation d'un guide d'une etude solairePrésentation d'un guide d'une etude solaire
Présentation d'un guide d'une etude solaire
 
Microgrid management
Microgrid managementMicrogrid management
Microgrid management
 
Séminaire Smart-Grid | TECHNIFUTUR
Séminaire Smart-Grid | TECHNIFUTURSéminaire Smart-Grid | TECHNIFUTUR
Séminaire Smart-Grid | TECHNIFUTUR
 
Electronique de puissance cours complet www.cours-online.com
Electronique de puissance cours complet  www.cours-online.comElectronique de puissance cours complet  www.cours-online.com
Electronique de puissance cours complet www.cours-online.com
 
Relay coordination
Relay coordinationRelay coordination
Relay coordination
 
Microgrid tecnology
Microgrid tecnologyMicrogrid tecnology
Microgrid tecnology
 
Introduction to Microgrid
Introduction to Microgrid Introduction to Microgrid
Introduction to Microgrid
 
Breakdown due to Internal Discharges and Surface Breakdown
Breakdown due to Internal Discharges and Surface BreakdownBreakdown due to Internal Discharges and Surface Breakdown
Breakdown due to Internal Discharges and Surface Breakdown
 
Vaccum Circuit Breaker
Vaccum Circuit BreakerVaccum Circuit Breaker
Vaccum Circuit Breaker
 
Hybrid AC/DC microgrid and Electric Vehicles
Hybrid AC/DC microgrid and Electric VehiclesHybrid AC/DC microgrid and Electric Vehicles
Hybrid AC/DC microgrid and Electric Vehicles
 
Overcurrent and Distance Protection in DigSilent PowerFactory
Overcurrent and Distance Protection in DigSilent PowerFactoryOvercurrent and Distance Protection in DigSilent PowerFactory
Overcurrent and Distance Protection in DigSilent PowerFactory
 
Droop control approach for power sharing in AC microgrid
Droop control approach for power sharing in AC microgrid Droop control approach for power sharing in AC microgrid
Droop control approach for power sharing in AC microgrid
 
switching substation, plcc and scada
switching substation, plcc and scadaswitching substation, plcc and scada
switching substation, plcc and scada
 
Guide Energie éolienne - ademe
Guide Energie éolienne - ademe Guide Energie éolienne - ademe
Guide Energie éolienne - ademe
 
Power Systems analysis with MATPOWER and Simscape Electrical (MATLAB/Simulink)
Power Systems analysis with MATPOWER and Simscape Electrical (MATLAB/Simulink) Power Systems analysis with MATPOWER and Simscape Electrical (MATLAB/Simulink)
Power Systems analysis with MATPOWER and Simscape Electrical (MATLAB/Simulink)
 
Cours du réseau électrique
Cours du réseau électriqueCours du réseau électrique
Cours du réseau électrique
 
Presentation on Power Transformer
Presentation on Power TransformerPresentation on Power Transformer
Presentation on Power Transformer
 

Similar to 2012 offshore wind cables

Wind farm planning and commissioning
Wind farm planning and commissioningWind farm planning and commissioning
Wind farm planning and commissioning
Preet_patel
 
Nexans LV-HV Wind Farm Cables Catalogue
Nexans LV-HV Wind Farm Cables CatalogueNexans LV-HV Wind Farm Cables Catalogue
Nexans LV-HV Wind Farm Cables Catalogue
Thorne & Derrick International
 
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Ivan Rojas Soliz
 
Functional bonding and shielding of Profibus and Profinet - Peter Thomas
Functional bonding and shielding of Profibus and Profinet - Peter ThomasFunctional bonding and shielding of Profibus and Profinet - Peter Thomas
Functional bonding and shielding of Profibus and Profinet - Peter Thomas
PROFIBUS and PROFINET InternationaI - PI UK
 
Wind Power Plant Planning And Commisioning
Wind Power Plant  Planning  And CommisioningWind Power Plant  Planning  And Commisioning
Wind Power Plant Planning And Commisioning
Suraj Naik
 
Future Offshore Wind Energy Technology
Future Offshore Wind Energy TechnologyFuture Offshore Wind Energy Technology
Future Offshore Wind Energy Technology
Philip Totaro
 
Submarine cable
Submarine cableSubmarine cable
Submarine cable
Subrata Kumer Paul
 
C5 wimes and spd, david bray
C5 wimes and spd, david brayC5 wimes and spd, david bray
C5 wimes and spd, david bray
PROFIBUS and PROFINET InternationaI - PI UK
 
Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission line
Fazlur Rahman
 
Oil pipiline stress monitoring
Oil pipiline  stress monitoringOil pipiline  stress monitoring
Oil pipiline stress monitoring
Juan David Betancur
 
Jacobs Recent changes to transmission line design standards and the impact on...
Jacobs Recent changes to transmission line design standards and the impact on...Jacobs Recent changes to transmission line design standards and the impact on...
Jacobs Recent changes to transmission line design standards and the impact on...Engineers Australia
 
3.chapter 1 ohtl vs cables
3.chapter 1 ohtl vs cables3.chapter 1 ohtl vs cables
3.chapter 1 ohtl vs cables
ssuser30d0c22
 
Multi Cable Transit Devices: Applications & Design Methods, PCIC Middle East...
Multi Cable Transit Devices:  Applications & Design Methods, PCIC Middle East...Multi Cable Transit Devices:  Applications & Design Methods, PCIC Middle East...
Multi Cable Transit Devices: Applications & Design Methods, PCIC Middle East...
Allen Gibson
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15John Grover
 
Power Cables Operation, Maintenance, Location and Fault Detection
Power Cables Operation, Maintenance, Location and Fault DetectionPower Cables Operation, Maintenance, Location and Fault Detection
Power Cables Operation, Maintenance, Location and Fault Detection
Living Online
 
Offshore wind resource assessment
Offshore wind resource assessmentOffshore wind resource assessment
Offshore wind resource assessment
Dileep V Raj
 
Supply system (Electrical Power System)
Supply system (Electrical Power System)Supply system (Electrical Power System)
Supply system (Electrical Power System)
Abhishek Choksi
 
wireless Communication Underwater(Ocean)
wireless Communication Underwater(Ocean)wireless Communication Underwater(Ocean)
wireless Communication Underwater(Ocean)
tanveer alam
 
Unit V - Instruments Design and Manufacturing1.pptx
Unit V - Instruments Design and Manufacturing1.pptxUnit V - Instruments Design and Manufacturing1.pptx
Unit V - Instruments Design and Manufacturing1.pptx
ssuserb3e5bb
 
Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2
Jerry Brown
 

Similar to 2012 offshore wind cables (20)

Wind farm planning and commissioning
Wind farm planning and commissioningWind farm planning and commissioning
Wind farm planning and commissioning
 
Nexans LV-HV Wind Farm Cables Catalogue
Nexans LV-HV Wind Farm Cables CatalogueNexans LV-HV Wind Farm Cables Catalogue
Nexans LV-HV Wind Farm Cables Catalogue
 
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
 
Functional bonding and shielding of Profibus and Profinet - Peter Thomas
Functional bonding and shielding of Profibus and Profinet - Peter ThomasFunctional bonding and shielding of Profibus and Profinet - Peter Thomas
Functional bonding and shielding of Profibus and Profinet - Peter Thomas
 
Wind Power Plant Planning And Commisioning
Wind Power Plant  Planning  And CommisioningWind Power Plant  Planning  And Commisioning
Wind Power Plant Planning And Commisioning
 
Future Offshore Wind Energy Technology
Future Offshore Wind Energy TechnologyFuture Offshore Wind Energy Technology
Future Offshore Wind Energy Technology
 
Submarine cable
Submarine cableSubmarine cable
Submarine cable
 
C5 wimes and spd, david bray
C5 wimes and spd, david brayC5 wimes and spd, david bray
C5 wimes and spd, david bray
 
Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission line
 
Oil pipiline stress monitoring
Oil pipiline  stress monitoringOil pipiline  stress monitoring
Oil pipiline stress monitoring
 
Jacobs Recent changes to transmission line design standards and the impact on...
Jacobs Recent changes to transmission line design standards and the impact on...Jacobs Recent changes to transmission line design standards and the impact on...
Jacobs Recent changes to transmission line design standards and the impact on...
 
3.chapter 1 ohtl vs cables
3.chapter 1 ohtl vs cables3.chapter 1 ohtl vs cables
3.chapter 1 ohtl vs cables
 
Multi Cable Transit Devices: Applications & Design Methods, PCIC Middle East...
Multi Cable Transit Devices:  Applications & Design Methods, PCIC Middle East...Multi Cable Transit Devices:  Applications & Design Methods, PCIC Middle East...
Multi Cable Transit Devices: Applications & Design Methods, PCIC Middle East...
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15
 
Power Cables Operation, Maintenance, Location and Fault Detection
Power Cables Operation, Maintenance, Location and Fault DetectionPower Cables Operation, Maintenance, Location and Fault Detection
Power Cables Operation, Maintenance, Location and Fault Detection
 
Offshore wind resource assessment
Offshore wind resource assessmentOffshore wind resource assessment
Offshore wind resource assessment
 
Supply system (Electrical Power System)
Supply system (Electrical Power System)Supply system (Electrical Power System)
Supply system (Electrical Power System)
 
wireless Communication Underwater(Ocean)
wireless Communication Underwater(Ocean)wireless Communication Underwater(Ocean)
wireless Communication Underwater(Ocean)
 
Unit V - Instruments Design and Manufacturing1.pptx
Unit V - Instruments Design and Manufacturing1.pptxUnit V - Instruments Design and Manufacturing1.pptx
Unit V - Instruments Design and Manufacturing1.pptx
 
Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2
 

More from MEC Intelligence

MEC+ World Food Programme Contribution
MEC+ World Food Programme ContributionMEC+ World Food Programme Contribution
MEC+ World Food Programme Contribution
MEC Intelligence
 
Floating Offshore Wind-Ready for commercialization?
Floating Offshore Wind-Ready for commercialization?Floating Offshore Wind-Ready for commercialization?
Floating Offshore Wind-Ready for commercialization?
MEC Intelligence
 
Next generation opportunities in utility scale solar
Next generation opportunities in utility scale solarNext generation opportunities in utility scale solar
Next generation opportunities in utility scale solar
MEC Intelligence
 
Emergence of-hybrid-renewable-energy-systems
Emergence of-hybrid-renewable-energy-systemsEmergence of-hybrid-renewable-energy-systems
Emergence of-hybrid-renewable-energy-systems
MEC Intelligence
 
2015 Foundations for larger and deeper Offshore Wind
2015 Foundations for larger and deeper Offshore Wind 2015 Foundations for larger and deeper Offshore Wind
2015 Foundations for larger and deeper Offshore Wind
MEC Intelligence
 
2014 Perspective on US Offshore Wind
2014 Perspective on US Offshore Wind2014 Perspective on US Offshore Wind
2014 Perspective on US Offshore Wind
MEC Intelligence
 
2013 Offshore Wind China
2013 Offshore Wind China2013 Offshore Wind China
2013 Offshore Wind China
MEC Intelligence
 
2011 electric vehicles market study
2011 electric vehicles market study2011 electric vehicles market study
2011 electric vehicles market study
MEC Intelligence
 
2011 LNG AS PROPULSION FUEL
2011 LNG AS PROPULSION FUEL2011 LNG AS PROPULSION FUEL
2011 LNG AS PROPULSION FUEL
MEC Intelligence
 

More from MEC Intelligence (9)

MEC+ World Food Programme Contribution
MEC+ World Food Programme ContributionMEC+ World Food Programme Contribution
MEC+ World Food Programme Contribution
 
Floating Offshore Wind-Ready for commercialization?
Floating Offshore Wind-Ready for commercialization?Floating Offshore Wind-Ready for commercialization?
Floating Offshore Wind-Ready for commercialization?
 
Next generation opportunities in utility scale solar
Next generation opportunities in utility scale solarNext generation opportunities in utility scale solar
Next generation opportunities in utility scale solar
 
Emergence of-hybrid-renewable-energy-systems
Emergence of-hybrid-renewable-energy-systemsEmergence of-hybrid-renewable-energy-systems
Emergence of-hybrid-renewable-energy-systems
 
2015 Foundations for larger and deeper Offshore Wind
2015 Foundations for larger and deeper Offshore Wind 2015 Foundations for larger and deeper Offshore Wind
2015 Foundations for larger and deeper Offshore Wind
 
2014 Perspective on US Offshore Wind
2014 Perspective on US Offshore Wind2014 Perspective on US Offshore Wind
2014 Perspective on US Offshore Wind
 
2013 Offshore Wind China
2013 Offshore Wind China2013 Offshore Wind China
2013 Offshore Wind China
 
2011 electric vehicles market study
2011 electric vehicles market study2011 electric vehicles market study
2011 electric vehicles market study
 
2011 LNG AS PROPULSION FUEL
2011 LNG AS PROPULSION FUEL2011 LNG AS PROPULSION FUEL
2011 LNG AS PROPULSION FUEL
 

Recently uploaded

ppt on beauty of the nature by Palak.pptx
ppt on  beauty of the nature by Palak.pptxppt on  beauty of the nature by Palak.pptx
ppt on beauty of the nature by Palak.pptx
RaniJaiswal16
 
Sustainable Rain water harvesting in india.ppt
Sustainable Rain water harvesting in india.pptSustainable Rain water harvesting in india.ppt
Sustainable Rain water harvesting in india.ppt
chaitaliambole
 
UNDERSTANDING WHAT GREEN WASHING IS!.pdf
UNDERSTANDING WHAT GREEN WASHING IS!.pdfUNDERSTANDING WHAT GREEN WASHING IS!.pdf
UNDERSTANDING WHAT GREEN WASHING IS!.pdf
JulietMogola
 
Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024
punit537210
 
International+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shopInternational+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shop
laozhuseo02
 
Natural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptxNatural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptx
sidjena70
 
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptxAGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
BanitaDsouza
 
growbilliontrees.com-Trees for Granddaughter (1).pdf
growbilliontrees.com-Trees for Granddaughter (1).pdfgrowbilliontrees.com-Trees for Granddaughter (1).pdf
growbilliontrees.com-Trees for Granddaughter (1).pdf
yadavakashagra
 
Q&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service PlaybookQ&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service Playbook
World Resources Institute (WRI)
 
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business VenturesWillie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
greendigital
 
Sustainable farming practices in India .pptx
Sustainable farming  practices in India .pptxSustainable farming  practices in India .pptx
Sustainable farming practices in India .pptx
chaitaliambole
 
Navigating the complex landscape of AI governance
Navigating the complex landscape of AI governanceNavigating the complex landscape of AI governance
Navigating the complex landscape of AI governance
Piermenotti Mauro
 
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdfPresentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Innovation and Technology for Development Centre
 
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian AmazonAlert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
CIFOR-ICRAF
 
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for..."Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
MMariSelvam4
 
Summary of the Climate and Energy Policy of Australia
Summary of the Climate and Energy Policy of AustraliaSummary of the Climate and Energy Policy of Australia
Summary of the Climate and Energy Policy of Australia
yasmindemoraes1
 
Celebrating World-environment-day-2024.pdf
Celebrating  World-environment-day-2024.pdfCelebrating  World-environment-day-2024.pdf
Celebrating World-environment-day-2024.pdf
rohankumarsinghrore1
 
Environmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. SinghEnvironmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. Singh
AhmadKhan917612
 
Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...
Open Access Research Paper
 
NRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation StrategyNRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation Strategy
Robin Grant
 

Recently uploaded (20)

ppt on beauty of the nature by Palak.pptx
ppt on  beauty of the nature by Palak.pptxppt on  beauty of the nature by Palak.pptx
ppt on beauty of the nature by Palak.pptx
 
Sustainable Rain water harvesting in india.ppt
Sustainable Rain water harvesting in india.pptSustainable Rain water harvesting in india.ppt
Sustainable Rain water harvesting in india.ppt
 
UNDERSTANDING WHAT GREEN WASHING IS!.pdf
UNDERSTANDING WHAT GREEN WASHING IS!.pdfUNDERSTANDING WHAT GREEN WASHING IS!.pdf
UNDERSTANDING WHAT GREEN WASHING IS!.pdf
 
Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024
 
International+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shopInternational+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shop
 
Natural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptxNatural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptx
 
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptxAGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
 
growbilliontrees.com-Trees for Granddaughter (1).pdf
growbilliontrees.com-Trees for Granddaughter (1).pdfgrowbilliontrees.com-Trees for Granddaughter (1).pdf
growbilliontrees.com-Trees for Granddaughter (1).pdf
 
Q&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service PlaybookQ&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service Playbook
 
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business VenturesWillie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
 
Sustainable farming practices in India .pptx
Sustainable farming  practices in India .pptxSustainable farming  practices in India .pptx
Sustainable farming practices in India .pptx
 
Navigating the complex landscape of AI governance
Navigating the complex landscape of AI governanceNavigating the complex landscape of AI governance
Navigating the complex landscape of AI governance
 
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdfPresentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
 
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian AmazonAlert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
 
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for..."Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
 
Summary of the Climate and Energy Policy of Australia
Summary of the Climate and Energy Policy of AustraliaSummary of the Climate and Energy Policy of Australia
Summary of the Climate and Energy Policy of Australia
 
Celebrating World-environment-day-2024.pdf
Celebrating  World-environment-day-2024.pdfCelebrating  World-environment-day-2024.pdf
Celebrating World-environment-day-2024.pdf
 
Environmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. SinghEnvironmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. Singh
 
Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...
 
NRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation StrategyNRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation Strategy
 

2012 offshore wind cables

  • 1. OFFSHORE WIND CABLES June 2012 Key industry players, cable cost breakdown, economical and technical drivers, challenges and key innovations
  • 2. Table of Contents 01 Introduction to offshore wind cables 02 Key industry players 03 Cost breakdown 04 Economical and technical drivers 05 Cable challenges 06 Demand for cost reductions 07 Key innovations 08 Remarks 09 Perspectives 4 6 7 8 9 10 11 12 13
  • 3. Foreword This insight provides an introduction to offshore wind cables and the key industry players. The cost structure of cables, the demand for cost reductions, as well as the economical and technical drivers are examined. Furthermore, the major challenges within the cable industry and key innovations in recent projects and those under development are studied. Page 3 The insight has been developed in close collaboration with Catalyst Strategy Consulting, an international consultancy, which operates in the nexus of technology and business, and holds ample experience and specialization in especially the Maritime, Energy & Offshore, and Cleantech industries
  • 4. Medium voltage array cables interconnect the turbines and the substation, high voltage export cables connect the offshore substation to onshore and subsea cable burial is the current best practice to ensure cable protection Page 4 INTRODUCTION TO OFFSHORE WIND CABLES Source: MEC Intelligence analysis Array/infield/collection grid cables – interconnecting turbines to substation • Transformers at each wind turbine, usually in the base of the tower, are used to step up from the generation voltage, typically 690 volts (V), to a medium voltage of typically 25–40 kilovolts (kV) • This voltage range seems to be preferred because standardized equipment is available at competitive prices and because higher voltage transformers would be too big to fit readily into the tower cross sections • A grid of medium-voltage submarine cables, typically buried 1–2 meters (m) deep in the seabed, is used to connect the wind turbines to an offshore substation Transmission/export cables – connecting offshore substation to onshore substation • The transmission system begins at the offshore substation, which steps up the voltage to a transmission voltage of 130–150 kV, the highest voltages in use today for AC submarine cables. This higher voltage allows a much smaller diameter and lower cost submarine cables to be used for the long run to shore • There are two technology options available for the transmission system associated with offshore wind power: • HVAC (high voltage alternating current) • HVDC (high voltage direct current) • HVAC is generally thought to be the most economical for distances shorter than 50 km • Between 50 km and 80 km HVAC and HVDC are expected to be similar in costs • Above 80 km HVDC will likely be the economically most attractive solution • This is mainly due to the effective capacity of a given HVAC drops with distance due to capacitive and inductive characteristics of the cable and their associated line losses (~10% loss) • HVDC avoids these line losses completely and is therefore the preferred technology for long distance. Cable installation • Subsea cable burial ensures cable protection in distribution systems worldwide and is widespread best practice in the telecoms industry. Left unprotected, power cable, fiber optic telephone cable and oil and gas pipe is vulnerable to damage from ship anchors, fishing activity and other threats. INDICATIVE
  • 5. A number of different methods for cable installation exist but the most common is to simultaneously lay and bury the cable using a plough Page 5 CABLE INSTALLATION Source: MEC Intelligence analysis Simultaneous lay and bury using plough • A plough is pulled by a cable laying vessel/barge and the cable is laid by a turntable on the vessel • The plough buries the cable in a trench of approx. 2 m deep using a high pressure water jet • The water jet fluidizes the sand/mud and the cable sinks into the trench • Most common method for cable installation especially for export cables • Cables are stretched to ensure a high tension when put in the trench using a control system on a barge • Important to minimize tension at turning points to ensure cable stays in the trench • Diver is used to confirm the touchdown of the cable in the trench and to carry out post-lay inspection of the array cables • Inflated airbags are used to pull-in the export cable onto the shore • Inter-array cables are pulled-in from the substation to the foundations fed up through J-tubes inside the foundations INDICATIVE 1 2 3 4 5 Simultaneous lay and bury using ROV • Similar to abovementioned method but utilizes a ROV instead of a plough • The ROV carries the cable in a spool which limits is use to inner-array cables • The preferred installation method when using the turbine installation vessel for cable installation Pre-excavate • A backhoe dredge is used to pre-excavate a trench • A cable laying vessel lays the cable in the trench and the trench is filled using the dredge • The method may also utilize floating cables over the trench via airbags • Used for both array and export cable installation Lay and trench • A cable laying vessel lays the cables on the seabed and a trench is made using a ROV • This method has been used for both array and export cables Pull and trench • Cables are pulled among turbines using a winch and later on they are buried with a ROV or plough • Only useful for inner-array connections Installation methods General
  • 6. The offshore wind cable industry is relatively fragmented in cables, consolidated in equipment, populated by 4-5 key players in cable installation Page 6 KEY INDUSTRY PLAYERS Source: MEC Intelligence analysis • Nexans (FR) • ABB Submarine Cables (SE) • LS Cable and System (KR) • JDR Cable Systems (UK) • NKT Cables Group (DE) • NSW/Corning (DE) • Prysmian Cables and Systems (Draka Offshore) (IT) • Siemens (DE) • ZTT Group (CN) • Borealis Group (AT) INDICATIVE • Pharos Offshore Group (UK) • SMD (UK) • CTC Marine (UK) • JD-Contractor (DK) • Global Marine Systems (UK) • VSMC (DE) • S.B. Submarine Systems Co. Ltd. (CN) • Beluga Shipping (DE) • Modus Seabed Intervention (UK) Cable manufacturers Equipment manufacturers Cable installers
  • 7. The general trend shows a decreasing cost pr. installed MW offshore – however, the value mix is changing, as logistics and installations costs are taking a larger share of the value compared to traditional cost components - e.g. the turbine – Cable cost is expected to grow along with distance to shore and effective load increase Page 7Source: MEC Intelligence analysis Logistics and Installation 21% Other 5% Project Mgmt and Permits 6% Electrical infrastructure & cables 14% Foundation 19% Turbine 35% Total installation 100% Total 100% Logistics 28% Installation 72% Tower 17% Blade 25% Foundation 35% Total 100% Cables 2% Substation 4% Hub 8% Nacelle 9% Capital Cost Breakdown (% per MW) Installation & Logistics (% per MW) Installation* (% per MW) Logistics (% per MW) Foundation 33% Total 100% Cables 33% Substation 8% Hub 7% Nacelle 7% Tower 7% Blade 7% Turbine Unit cost trend compared relatively to peers COST BREAKDOWN *Note on installation split of turbine – split will vary • Nacelle and hubs are joined at the port along with 2 blades = one unit • Tower is one unit • The third blade is one unit INDICATIVE
  • 8. The primary economical and technological drivers are related to the installation and burial of subsea cables and ~70% of insurance claims from offshore wind farm operations relate to cable damage Page 8 ECONOMICAL AND TECHNICAL DRIVERS Source: MEC Intelligence analysis • Installation of subsea cables has been characterized by cost overruns and cable damage in a number of cases • Subsea cables have been the largest source of insurance claims in offshore wind to date • It has been estimated that subsea cable laying accounts for between 5-10% of the capital cost of the wind farm development but ~70% of insurance claims from wind farm operations relate to cable damage INDICATIVE • Technology development has a key role to play in impacting costs • As offshore wind farms are located further from shore, point-to-point HVDC systems will prove more cost effective than HVAC Economical Drivers Technical Drivers
  • 9. Poor understanding of environmental conditions, poor planning regarding cable installation and risk of shortage of high-voltage cables and trained workers pose the primary cable challenges Page 9 CABLE CHALLENGES Source: MEC Intelligence analysis • Poor understanding of weather and marine environment • Access difficulties due to unexpectedly severe weather conditions • Harder or softer ground being encountered impeding burial machinery • Unexpected topography e.g. slopes and holes • Poor definition of environmental risks leading to tight permitting windows • Poor appreciation of the wave/tidal environment leading to tight operational windows • Poor understanding of marine environment leading to excessive weather delays EXAMPLE • Lack of consultation with cable manufacturers / marine contractors regarding the practicalities of installation • Lack of quality in cable route survey definition and data interpretation for the cable route • Developers accepted consent conditions that are unrealistic or impractical • Poor understanding of impacts of construction • Unrealistic permit conditions being passed on to contractors to implement • Risk of a high-voltage subsea cable shortage in the next few years as well as a possible shortage of trained workers • The supply base is currently limited to a number of companies and time to establish new production facilities is significant depending on competition from other energy infrastructure projects Risk of shortage of high-voltage subsea cables and possibly trained workers Poor planning regarding cable installationPoor understanding of environmental conditions
  • 10. The major offshore wind expansion plans on the horizon drives the demand for cable cost and insurance claims reduction Page 10 DEMAND FOR CABLE COST REDUCTIONS Source: MEC Intelligence analysis EXAMPLES • With major industry expansion plans on the horizon, there has never been a greater need for the industry to come together and develop a coordinated approach to the challenges it faces going forward. Major offshore wind expansion plans • The installation and burial processes currently being used have resulted in many insurance claims being made by offshore developers to cover the costs of damage to cables. Substantial insurance claims due to cable damage
  • 11. Key innovations in order to drive cost down on cables include cable installation and maintenance robots, alternative HVDC cable technologies, AC/DC rectifier technology development and new types of submarine cables Page 11 KEY INNOVATIONS Source: MEC Intelligence analysis EXAMPLES • Underwater robot developed for subsea cable burial • Provides more scheduling flexibility • Inter-array cables can be installed more quickly • Less need for expensive diving activities • Cable maintenance robot • More cost-efficient measure of maintenance Cable installation • HVDC Plus (Siemens technology) • Modular multilevel voltage-sourced converters • Preferred solution where shortage of space is a criterion • Improves the performance of the transmission grid with regard to system security • Will be used for the world’s longest HVDC submarine grid connecting England and Scotland (420 km) • HVDC Light (ABB technology) • Increases the reliability of power grids • Upper range: 1,200 MW and ±500 kV. Cable technology • Mercury arc valves • Thyristor converters AC/DC rectifier technology development • Mass-impregnated cables • Self-contained fluid-filled cables • Extruded insulation cables Types of submarine cables used
  • 12. Findings Page 12 REMARKS VII VIII VI IIII V III I II Medium voltage array cables interconnect the turbines and the substation, high voltage export cables connect the offshore substation to onshore and subsea cable burial is the current best practice to ensure cable protection A number of different methods for cable installation exist but the most common is to simultaneously lay and bury the cable using a plough The offshore wind cable industry is dominated by a limited number of players on the cable and equipment side and 4- 5 key players on the cable installation side Cables account for ~14% of the balance of plant with export cables accounting for ~75% and array cables accounting for ~25%, and cables account for ~33% of installation and commissioning costs which is a significant share The primary economic and technological drivers are related to the installation and burial of subsea cables and ~70% of insurance claims from offshore wind farm operations relate to cable damage Poor understanding of environmental conditions, poor planning regarding cable installation and risk of shortage of high-voltage cables and trained workers pose the primary cable challenges The major offshore wind expansion plans on the horizon and the many economic and technical challenges currently facing the offshore wind cable industry drives the demand for cable cost reductions Key innovations in order to drive cost down on cables include cable installation and maintenance robots, alternative HVDC cable technologies, AC/DC rectifier technology development and new types of submarine cables Source: MEC Intelligence Analysis
  • 13. Perspectives Page 13 REMARKS Source: MEC Intelligence Analysis Considering the ambition to reduce the cost of offshore wind energy – would innovations in logistics and supply chain, be able to stand up to the requirements? Which areas are likely to become bottlenecks? With the value split in the offshore wind changing rapidly, which are the key stakeholders who are positioned to win and lose market share in the future offshore wind energy market? What does the emergence of markets and industries across the globe mean, in the context of the contemporary suppliers? Considering supply constraints, and the need to build operational excellence and flexibility - are there business models and/or innovative port infrastructure configurations, which yield competitive advantage? With the offshore wind market rapidly becoming global - which local rules, policies, and various stakeholder decision making criteria, are essential to know to grow and sustain markets? Considering the requirement of local content in the markets, how should companies organize to branch-out internationally?
  • 14. About MEC Intelligence MEC Intelligence supports growth strategies in the Maritime, Energy, and Cleantech Industries by offering high quality analysis of the clients’ growth questions – bringing together in-depth understanding of industry dynamics and fact driven, global, and independent market research. We create insights that are real, actionable, and integrate seamlessly into the clients’ decision process by working in a one-to-one relationship with clients. We have a strategic partnership with Catalyst Strategy Consulting to bring synergistic advisory expertise. Catalyst Strategy Consulting is one of Europe’s leading strategy consultancies with focus on the Maritime, Energy, and Cleantech sectors. The company advises global top companies and leading private equity funds on business model innovation and growth strategies. Please visit Catalyst Strategy Consulting for more information. Page 14 Knowledge support for effective decisions aimed at anticipating and winning the right growth opportunities
  • 15. Sample Publications in Offshore Wind MEC Intelligence has conducted a vast range of bespoke researched studies for leading international companies in the areas of Maritime, Energy and Cleantech – along with authoring a range of free and commercial insights and reports within our focal domains Publications and Credentials Offshore Wind Foundation October 2011 Offshore Wind Cables June 2012 Offshore Wind Logistics July 2012 Offshore wind market in China August 2012 Sample Publications in Marine and Cleantech LNG as Propulsion Fuel October 2011 Electric Vehicles December 2011 MEC Intelligence holds ample experience and expertise within market forecasting and analysis, project cost benchmarking in e.g. sourcing, best practice studies etc. We leverage an extensive network of experts and professionals, to provide bespoke research and analysis, catering to your specific needs – contact us directly to receive an individual quote to your specific research needs
  • 16. MEC Intelligence India MEC Consulting Pvt. Ltd. Levels 5, 6 and 7 JMD Regent Square Mehrauli-Gurgaon Road Gurgaon India Tel: +91 9810 53 3550 Email: India@mecintelligence.com MEC Intelligence Denmark Nordre Fasanvej 113,2; 2000 Frederiksberg. Copenhagen Denmark Tel: +45 3543 3277 Email: Europe@mecintelligence.com The information in this document has been obtained from sources believed to be reliable. MEC Intelligence disclaim all warranties as to the accuracy, completeness or adequacy of such information. We shall have no liability for errors or inadequacies in the information contained herein or for interpretations thereof. This document is protected by copyright. Republication, reproduction or commercial use of the glossary and artwork, in whole or in part, is prohibited without the written permission of MEC Intelligence. © MEC Intelligence