SlideShare a Scribd company logo
Recent changes to transmission line design
standards and the impact on new construction and
ageing assets in the Pilbara
ENGINEERS
AUSTRALIA
ASIF BHANGOR, PRINCIPAL ENGINEER
AARON HAMILTON, SENIOR ELECTRICAL ENGINEER
What will we cover in this presentation?
1. Introduction
2. The Pilbara, where are we?
3. AS/NZS 7000:2010 key differences amongst others
4. Tower testing
5. Aged transmission lines, what do we do in case of failures?
6. Helicopter stringing
7. Current industry practice in tower installation
8. New method of tower installation
9. Recognitions/Awards
The Pilbara, where are we?
• Region D with cyclonic wind speeds
• Return periods for transmission lines generally 200+ years
whilst distribution lines typically 50/100 years
• Regional wind speed for say 200 years return is 72m/s
• Indigenous heritage sites, priority ecological areas & rivers
• Access constraints
• Crossing 3rd party infrastructure sensitive to shutdowns
– Mining company railways
– Mining or Industry distribution and transmission lines
– Highways
AS/NZS 7000:2010 key differences amongst others
Wind load
• No need to apply 10% amplification to the wind speeds in
AS/NZS 7000:2010
• No need to apply downdraft (high intensity winds) for regions C
and D
AS/NZS 7000:2010 key differences amongst others
Wind load
AS/NZS 7000:2010 key differences amongst others
Insulator swing
• High wind in insulator swing calculations has been typically
mentioned as 500 Pa for power frequency clearance of 500mm
AS/ NZS 7000:2010 key differences amongst others
Insulator swing
• Low wind and moderate wind is 100 Pa and 300 Pa
• Some utilities have used 240 Pa as moderate wind
AS/ NZS 7000:2010 key differences amongst others
Insulator swing
• Blowout calculation is linked to the serviceability wind but
insulator swing talks about high wind (limiting to 500 Pa only)
• If we apply maximum wind of the Pilbara, we get large swing
angles which lead to bracket extensions for clearances
AS/ NZS 7000:2010 key differences amongst others
Insulator swing
AS/ NZS 7000:2010 key differences amongst others
Insulator swing … suggested approach…
• The wind speed derived should be adjusted for the
terrain, height multipliers from AS1170.2 and considering
a drag factor of 1.2
• In addition, the wind speed is reduced for the effect of
span reduction factors which takes into account the
spatial characteristics of wind gusts and inertia offered by
the conductors. See figure B5 in AS1170.2 Page 129
• For easement calculations, refer to item R4 in AS7000
and Cb1 2006 table 10.3 for the 5 – 10 minutes averaging
period conversion which converts it to a serviceability
wind for checking the easement
AS/NZS 7000:2010 key differences amongst others
Conductor assessment (strength and serviceability limits)
• The below table highlights the factored approach in
conductor assessment
AS/NZS 7000:2010 key differences amongst others
Comparison of Cb1 and AS7000 (for conductors in the Pilbara region)
Wind Speeds up to 90m/sec for conductor selection (including height multipliers)
Conductor type UTS (kN) Ft, MWT (kN) Ruling span (m)
Special Diving ACSR (30/6/3.5+1/3.65) 146.0 119.4 470.0
AAAC Sapphire (37/3.75) 115.0 81.1 341.0
AACSR/AC/1120 (42/19/3.25) 264.5 145.0 360.0
Criteria/ Cb1
Conductor type 0.7UTS 1.5Ft
Special Diving ACSR (30/6/3.5+1/3.65) 102.2 179.0 Conductor fails
AAAC Sapphire (37/3.75) 80.5 121.6 Conductor fails
AACSR/AC/1120 (42/19/3.25) 185.2 217.5 Conductor fails
Criteria/(Failure/ Strength) AS7000
Conductor type 0.9UTS 1.25Ft
Special Diving ACSR (30/6/3.5+1/3.65) 131.4 149.2 Conductor fails
AAAC Sapphire (37/3.75) 103.5 101.3 OK
AACSR/AC/1120 (42/19/3.25) 238.1 181.3 OK
Criteria/(Damage/ Serviceability) Non Linear AS7000
Conductor type 0.7UTS 1.00Ft
Special Diving ACSR (30/6/3.5+1/3.65) 102.2 119.4 Conductor fails
AAAC Sapphire (37/3.75) 80.5 81.1 Conductor fails
AACSR/AC/1120 (42/19/3.25) 185.2 145.0 OK
Criteria/ (Damage/ Serviceability) Linear AS7000
Conductor type 0.5UTS 1.00Ft
Special Diving ACSR (30/6/3.5+1/3.65) 73.0 119.4 Conductor fails
AAAC Sapphire (37/3.75) 57.5 81.1 Conductor fails
AACSR/AC/1120 (42/19/3.25) 132.3 145.0 Conductor fails
Conductor
assessment
AS/NZS 7000:2010 key differences amongst others
Pole foundation assessment
• In the past utilities have used C(b)1 suggested empirical
assessment of L/10+0.6 for foundation depths – having
no interaction with soil data
• Historically, utilities have deemed this acceptable for
wood poles in region A where wind speeds are around 39
– 43m/s
• However, in the Pilbara where cyclonic wind speeds are
present due care has to be considered for poles carrying
mine load thus requiring higher reliability (basically no
foundation failures acceptable)
AS/NZS 7000:2010 key differences amongst others
Pole foundation assessment
• Mindset exists that “We have done this in the past using
L/10+0.6m so why increase the embedment depth now?”
• More recently, utilities have moved away from L/10+0.6m
embedment with proper soil interaction methods such as
Broms, Brinch & Hansen etc.
• Essential Energy, Electranet, Powerlink, Energy Australia
design standards all refer to Brinch & Hansen now
• Please refer to Table 9.7 of handbook HB331 which
states disadvantages of the L/10+0.6(0.8) formula
AS/NZS 7000:2010 key differences amongst others
Pole foundation assessment
AS/NZS 7000:2010 key differences amongst others
Pole foundation assessment
Tower Testing
Tower Testing
• Failures exhibit load sharing
issues in lattice steel
• Important to understand tower
failures are catastrophic in
nature
• Hence the need to test towers
and eliminate any issues in load
sharing between members,
plates, bolts etc.
• Leg loads for cyclonic wind
regions reach to around 2000kN
per leg
Aged transmission lines
What do we do in case of failures?
• Gradual ageing of steel structures exposed to extreme
weather events exposes owners to high cost of
refurbishment, let alone lost time of production if local
generation does not exist
• Generally utilities have dealt with this problem using
emergency response structures (i.e. Lindsey Guyed
Masts)
• The network in the Pilbara is at risk…failures mean
complete shutdown…
Aged transmission lines
What do we do in case of failures?
• There is a need to consider design of transmission lines
with higher reliability (i.e. 500 years return wind speeds)
and a high degree of accuracy when it comes to detailing
and fabrication of steel for new projects
• For ageing projects, there is a need to frequently check
and maintain/ replace the ageing towers, conductors, and
insulators using effective maintenance plans
Aged transmission lines
What do we do in case of failures?
• Wednesday 28th September TransGrid had a failure on
the 220kV line from Darlington Point to Buronga
• The failure was at tower 557 and 558, approximately 30
kms east of Balranald (“in the middle of nowhere” was
the first description). The cause was a high wind event
• 3 towers have been damaged. Initially, towers 557 and
558 failed on the Wednesday night
• On the morning of Friday 30th September, leg buckling
on Tower 556 was observed
• The line has been restored using timber pole
emergency structures – 4 structures have been used
Aged transmission lines
What do we do in case of failures?
• Tower 558 has failed in the “classical” manner of
compression failure in the legs and has fallen at 90 deg
to the line direction
• The foundation shows obvious signs of severe corrosion
of the reinforcement and necking of the remaining reo at
failure
• Some analysis needed to check the reo and concrete to
determine the cause and age of the corrosion (an old
construction joint? locally aggressive soil?)
Aged transmission lines
TransGrid Failure Event
28/09/2011 220kV Line
from Darlington Point to
Buronga, NSW
• Region A7 Downdraft
winds (high intensity
winds)
• Zone II, Span reduction
factor = 1.0 (0-200m
spans)
• Wind speeds up to
43m/s (1.1kPA)
Aged transmission lines
TransGrid Failure Event
28/09/2011 220kV Line
from Darlington Point to
Buronga
Aged transmission lines
TransGrid Failure Event
28/09/2011 220kV Line
from Darlington Point to
Buronga
Aged transmission lines
Leigh Creek to Davenport 132kV line experienced a cyclone
in SA
Helicopter stringing in the Pilbara
Some recent challenges experienced
• Access constraints
• Cultural heritage sites
• River crossings
• Priority ecological areas
• Crossing 3rd party infrastructure sensitive to shutdowns
• Mining company railways
• Mining or Industry distribution and transmission lines
• Highways
Helicopter stringing in the Pilbara
YM-CL 220kV Stringing Detail
• Helicopter fitted with side
pull rather than belly hook
• Side pull is a customised
piece of equipment designed
specifically for stringing
transmission lines
• Side pull increases the
helicopter fuel efficiency
over a belly hook
• Pilots prefer side pull as
complete assembly is visible
Helicopter stringing in the Pilbara
YM-CL 220kV Stringing Detail
• Helicopter pulls the cable
out sideways, to ensure
vision can be maintained in
the direction of travel and
the direction of load
Helicopter stringing in the Pilbara
YM-CL 220kV Stringing Detail
• Pulling order planned to
ensure that cables already
strung are in front of or
below the height of the
aircraft rotor system
• At no point should cables be
behind the aircraft at the
same height as the one
being pulled
Helicopter stringing in the Pilbara
YM-CL 220kV Stringing Detail
• Stringing broken in to 13 pulls
• 7 of the 13 pulls involved 5 towers
or fewer
• Generally helicopter pulled draw
wire for phase conductors and
Earthwire and OPGW direct
• Direct pulls need to be done under
tension to keep off ground
• Phase conductors are generally not
pulled direct due to the weight,
distance from the ground
• Helicopter used to pull all
conductors direct for rail and line
crossings (due to outage limitations)
Helicopter stringing in the Pilbara
Advantages
• Schedule improvement
• 4.5km drawwire pull takes approximately 45 minutes
• 12km OHEW or OPGW pull under tension takes approximately 3
hours
• Critical path moves to linesmen sagging and terminating
• Low impact on heritage sites (line crosses directly over 18)
• Simplified stringing over heavily vegetated river crossing (620m)
• Simplified, faster stringing over existing 132kV transmission lines
• Simplified, faster stringing over rail
Helicopter stringing in the Pilbara
Current industry practice in tower installation
Current industry practice in tower installation
Current industry practice in tower installation
Current industry practice in tower installation
Current industry practice in tower installation
Changing the way we do things? Counter arguments by stakeholders
• Crane rated 10 times higher than load
• Load calculations done for all critical lifts
• Lift plans reviewed and signed off by engineer
• Crane inspected at regular intervals
• Crane operator is very experienced and has worked with rigging team for a
long time
• Rigging equipment rated 5 times higher than load
• Rigging equipment inspected daily by crew as well as monthly inspections by
accredited third party inspectors.
• Rigging crew is well trained and very experienced in tower construction
• Verification of competence of all riggers and crane operator
• PPE inspected daily including safety harnesses, ropes etc.
• Very quick installation reducing riggers time spent on the tower and risk of fall
Current industry practice in tower installation
• Incidents reported in failures
Current industry practice in tower installation
• Incidents reported in failures
• Close Call for Big Truck Mount
01/17/14
• Newcastle, Australia
• A 54 meter truck mounted lift lost
balance near Newcastle, Australia
when the ground gave way under one
of its outriggers.
• Fortunately the boom came to rest
against the pylons of the high tension
power line that it was helping to install
– no one was injured or hurt in the
incident
Current industry practice in tower installation
New method of tower installation
“Safety guide” design
This allows crane operators to lower the top section without manual
intervention
of crew
• Once the lower portion of the tower is installed on the ground and fitted with
the foundation base, it is fitted at the connection point to the top structure
with the safety bracket
• The top superstructure is suspended by the crane operator and lowered
into the safety bracket, landing the top superstructure inside the bracket.
The load of the top superstructure is relieved by the crane operator as the
weight of the top does not rest on the steel itself
• The rigging personnel can then go to the top section and connect the
relevant bolts to the holes of the relevant plates and release the safety
bracket. This enables them to work without being under suspended load
New method of tower installation
New method of tower installation
New method of tower installation
Site Construction Team developed option which included:
• Purpose-made temporary “docking brackets” to be installed at the fixing
positions to ease “landing” of the suspended structures onto their bases,
without the need for riggers to be under the suspended loads.
• Installation of temporary brackets to guide sections in to place isn’t new, but
their use has to date been limited to helicopter based tower construction.
• Spacing the splice plates of the suspended structure sections (mid sections), to
gape open, thus easing the landing of those structures through carefully
lowering, with control provided by tag lines with the riggers safely away from
danger.
New method of tower installation
New method of tower installation
New method of tower installation
New method of tower installation
New method of tower installation
Achievement of outcomes
• Eliminated the need for riggers to work under suspended loads or manually
move the sections into place risking injury.
• Riggers are no longer exposed to the swinging momentum of the tower
sections.
• Does not require additional brackets to be installed or design modifications
for the most part and the changes were mostly procedural. Existing splice
plates join the adjacent sections, which is easy to implement.
• Developed new, safer site construction methodology that involves sections
of the tower being landed onto the bottom sections with the combined use
of brackets, guide ropes and or other equipment and material already
available on site.
New method of tower installation
Longer splice plates significantly improves landing of the superstructure
Recognitions/Awards
Recognition in the Australian Industry to promote safety and innovation
in current practices for Tower Design and Installation

More Related Content

What's hot

Design of Transmission Tower
Design of Transmission TowerDesign of Transmission Tower
Design of Transmission Tower
Abhijit Kumar
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & Parts
Power System Operation
 
Sp34 str detailing
Sp34     str detailingSp34     str detailing
Sp34 str detailingMohd Danish
 
Poles and towers
Poles and towersPoles and towers
Poles and towers
Gas & Oil Pakistan Ltd.
 
Design and analasys of a g+2 residential building
Design and analasys of a g+2 residential building Design and analasys of a g+2 residential building
Design and analasys of a g+2 residential building
=> No nEEd FoH WoRk , Um gOod cOnsUMer oF PArentx MOnEy
 
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contentsANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
ila vamsi krishna
 
Anchor bolt design
Anchor bolt designAnchor bolt design
Anchor bolt design
Varadaraj Ck
 
Part 3 Guy Tower Structure
Part 3 Guy Tower Structure Part 3 Guy Tower Structure
Part 3 Guy Tower Structure
Fred Teichman
 
A brief introduction on Modelling of Truss Bridge in CSI bridge
A brief introduction onModelling of Truss Bridge in CSI bridgeA brief introduction onModelling of Truss Bridge in CSI bridge
A brief introduction on Modelling of Truss Bridge in CSI bridge
suvendu parida
 
An Overview On Box Girder Bridges
An Overview On Box Girder BridgesAn Overview On Box Girder Bridges
An Overview On Box Girder Bridges
IRJET Journal
 
Indian standard: IS808 DIMENSIONS FOR HOT ROLLED STEEL
Indian standard: IS808 DIMENSIONS FOR HOT ROLLED STEEL Indian standard: IS808 DIMENSIONS FOR HOT ROLLED STEEL
Indian standard: IS808 DIMENSIONS FOR HOT ROLLED STEEL
D&H Engineers
 
Water tank 1
Water tank 1Water tank 1
Water tank 1
SachinThakre10
 
400kv gis substation erection sequence
400kv gis substation erection sequence400kv gis substation erection sequence
400kv gis substation erection sequence
Anbarasu Balakrishnan
 
Transformers in Power Distribution Networks
Transformers in Power Distribution NetworksTransformers in Power Distribution Networks
Transformers in Power Distribution Networks
Leonardo ENERGY
 
analysis and design of telecommunication tower
analysis and design of telecommunication toweranalysis and design of telecommunication tower
analysis and design of telecommunication tower
Rohithasangaraju
 
Fabrication of steel plate girder r
Fabrication of steel plate girder rFabrication of steel plate girder r
Fabrication of steel plate girder rVISHAL SINGH
 
2.2 Professionalism and Codes of Ethics (April 2020)
2.2  Professionalism and Codes of Ethics (April 2020) 2.2  Professionalism and Codes of Ethics (April 2020)
2.2 Professionalism and Codes of Ethics (April 2020)
Bulan Abdullah (Ir)(Dr.)
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
Rajesh Prasad
 
M.Tech Structural Engineering Project on Voided and Cellular Bridge introduction
M.Tech Structural Engineering Project on Voided and Cellular Bridge introductionM.Tech Structural Engineering Project on Voided and Cellular Bridge introduction
M.Tech Structural Engineering Project on Voided and Cellular Bridge introduction
vaignan
 
building consturction training report at cpwd (MNIT)
building consturction training report at cpwd (MNIT)building consturction training report at cpwd (MNIT)
building consturction training report at cpwd (MNIT)
rahul jangid
 

What's hot (20)

Design of Transmission Tower
Design of Transmission TowerDesign of Transmission Tower
Design of Transmission Tower
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & Parts
 
Sp34 str detailing
Sp34     str detailingSp34     str detailing
Sp34 str detailing
 
Poles and towers
Poles and towersPoles and towers
Poles and towers
 
Design and analasys of a g+2 residential building
Design and analasys of a g+2 residential building Design and analasys of a g+2 residential building
Design and analasys of a g+2 residential building
 
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contentsANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
ANALYSIS AND DESIGN OF G+4 RESIDENTIAL BUILDING contents
 
Anchor bolt design
Anchor bolt designAnchor bolt design
Anchor bolt design
 
Part 3 Guy Tower Structure
Part 3 Guy Tower Structure Part 3 Guy Tower Structure
Part 3 Guy Tower Structure
 
A brief introduction on Modelling of Truss Bridge in CSI bridge
A brief introduction onModelling of Truss Bridge in CSI bridgeA brief introduction onModelling of Truss Bridge in CSI bridge
A brief introduction on Modelling of Truss Bridge in CSI bridge
 
An Overview On Box Girder Bridges
An Overview On Box Girder BridgesAn Overview On Box Girder Bridges
An Overview On Box Girder Bridges
 
Indian standard: IS808 DIMENSIONS FOR HOT ROLLED STEEL
Indian standard: IS808 DIMENSIONS FOR HOT ROLLED STEEL Indian standard: IS808 DIMENSIONS FOR HOT ROLLED STEEL
Indian standard: IS808 DIMENSIONS FOR HOT ROLLED STEEL
 
Water tank 1
Water tank 1Water tank 1
Water tank 1
 
400kv gis substation erection sequence
400kv gis substation erection sequence400kv gis substation erection sequence
400kv gis substation erection sequence
 
Transformers in Power Distribution Networks
Transformers in Power Distribution NetworksTransformers in Power Distribution Networks
Transformers in Power Distribution Networks
 
analysis and design of telecommunication tower
analysis and design of telecommunication toweranalysis and design of telecommunication tower
analysis and design of telecommunication tower
 
Fabrication of steel plate girder r
Fabrication of steel plate girder rFabrication of steel plate girder r
Fabrication of steel plate girder r
 
2.2 Professionalism and Codes of Ethics (April 2020)
2.2  Professionalism and Codes of Ethics (April 2020) 2.2  Professionalism and Codes of Ethics (April 2020)
2.2 Professionalism and Codes of Ethics (April 2020)
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
M.Tech Structural Engineering Project on Voided and Cellular Bridge introduction
M.Tech Structural Engineering Project on Voided and Cellular Bridge introductionM.Tech Structural Engineering Project on Voided and Cellular Bridge introduction
M.Tech Structural Engineering Project on Voided and Cellular Bridge introduction
 
building consturction training report at cpwd (MNIT)
building consturction training report at cpwd (MNIT)building consturction training report at cpwd (MNIT)
building consturction training report at cpwd (MNIT)
 

Viewers also liked

transmission line
transmission line transmission line
transmission line
singh1515
 
Where to From Here - Oil and Gas in WA
Where to From Here - Oil and Gas in WAWhere to From Here - Oil and Gas in WA
Where to From Here - Oil and Gas in WA
Engineers Australia
 
Method statement for transmission line (lanco)
Method statement for transmission line (lanco)Method statement for transmission line (lanco)
Method statement for transmission line (lanco)Praveen Kumar
 
Electrical transmission line
Electrical transmission lineElectrical transmission line
Electrical transmission line
Dhananjay Jha
 
ICWES15 - Reclamation of Oilfield Produced Water using Hydrophilic Pervaporat...
ICWES15 - Reclamation of Oilfield Produced Water using Hydrophilic Pervaporat...ICWES15 - Reclamation of Oilfield Produced Water using Hydrophilic Pervaporat...
ICWES15 - Reclamation of Oilfield Produced Water using Hydrophilic Pervaporat...Engineers Australia
 
Connecting to the future: how transport will shape the City of Fremantle
Connecting to the future: how transport will shape the City of FremantleConnecting to the future: how transport will shape the City of Fremantle
Connecting to the future: how transport will shape the City of Fremantle
Engineers Australia
 
Arc flash August 2012 IE Aust JEEP
Arc flash  August 2012   IE Aust JEEPArc flash  August 2012   IE Aust JEEP
Arc flash August 2012 IE Aust JEEPEngineers Australia
 
121108 MD smart grid and renewable energy integration 1
121108 MD smart grid and renewable energy integration 1121108 MD smart grid and renewable energy integration 1
121108 MD smart grid and renewable energy integration 1Engineers Australia
 
EHS plan for Transmission Line Survey Work
EHS plan for Transmission Line Survey WorkEHS plan for Transmission Line Survey Work
EHS plan for Transmission Line Survey Work
Praveen Kumar
 
Cyber supply chain risk management ASDE
Cyber supply chain risk management   ASDECyber supply chain risk management   ASDE
Cyber supply chain risk management ASDEEngineers Australia
 
Pilbara rfa ea presentation v3.2 1
Pilbara rfa ea presentation v3.2 1Pilbara rfa ea presentation v3.2 1
Pilbara rfa ea presentation v3.2 1Engineers Australia
 
Calculation up to 100; NIED Okahandja - Advisory teachers - October 2013
Calculation up to 100; NIED Okahandja - Advisory teachers - October 2013Calculation up to 100; NIED Okahandja - Advisory teachers - October 2013
Calculation up to 100; NIED Okahandja - Advisory teachers - October 2013
jdewaard
 
Telecommunication Tower
Telecommunication TowerTelecommunication Tower
Telecommunication Tower
ayishairshad
 
Aluminium ladders
Aluminium laddersAluminium ladders
Aluminium ladders
Dyan UkaUka
 
Revised intensity frequency-duration (ifd) design rainfalls estimates for wa ...
Revised intensity frequency-duration (ifd) design rainfalls estimates for wa ...Revised intensity frequency-duration (ifd) design rainfalls estimates for wa ...
Revised intensity frequency-duration (ifd) design rainfalls estimates for wa ...Engineers Australia
 
Pavement materials and design in western australia by geoffrey cocks
Pavement materials and design in western australia by geoffrey cocksPavement materials and design in western australia by geoffrey cocks
Pavement materials and design in western australia by geoffrey cocksEngineers Australia
 
Smart grid - Do they fit into real networks ver 1
Smart grid  - Do they fit into real networks ver 1Smart grid  - Do they fit into real networks ver 1
Smart grid - Do they fit into real networks ver 1Engineers Australia
 

Viewers also liked (20)

transmission line
transmission line transmission line
transmission line
 
Swing angle
Swing angleSwing angle
Swing angle
 
Where to From Here - Oil and Gas in WA
Where to From Here - Oil and Gas in WAWhere to From Here - Oil and Gas in WA
Where to From Here - Oil and Gas in WA
 
Method statement for transmission line (lanco)
Method statement for transmission line (lanco)Method statement for transmission line (lanco)
Method statement for transmission line (lanco)
 
Electrical transmission line
Electrical transmission lineElectrical transmission line
Electrical transmission line
 
ICWES15 - Reclamation of Oilfield Produced Water using Hydrophilic Pervaporat...
ICWES15 - Reclamation of Oilfield Produced Water using Hydrophilic Pervaporat...ICWES15 - Reclamation of Oilfield Produced Water using Hydrophilic Pervaporat...
ICWES15 - Reclamation of Oilfield Produced Water using Hydrophilic Pervaporat...
 
Connecting to the future: how transport will shape the City of Fremantle
Connecting to the future: how transport will shape the City of FremantleConnecting to the future: how transport will shape the City of Fremantle
Connecting to the future: how transport will shape the City of Fremantle
 
Arc flash August 2012 IE Aust JEEP
Arc flash  August 2012   IE Aust JEEPArc flash  August 2012   IE Aust JEEP
Arc flash August 2012 IE Aust JEEP
 
121108 MD smart grid and renewable energy integration 1
121108 MD smart grid and renewable energy integration 1121108 MD smart grid and renewable energy integration 1
121108 MD smart grid and renewable energy integration 1
 
EHS plan for Transmission Line Survey Work
EHS plan for Transmission Line Survey WorkEHS plan for Transmission Line Survey Work
EHS plan for Transmission Line Survey Work
 
Cyber supply chain risk management ASDE
Cyber supply chain risk management   ASDECyber supply chain risk management   ASDE
Cyber supply chain risk management ASDE
 
Pilbara rfa ea presentation v3.2 1
Pilbara rfa ea presentation v3.2 1Pilbara rfa ea presentation v3.2 1
Pilbara rfa ea presentation v3.2 1
 
Calculation up to 100; NIED Okahandja - Advisory teachers - October 2013
Calculation up to 100; NIED Okahandja - Advisory teachers - October 2013Calculation up to 100; NIED Okahandja - Advisory teachers - October 2013
Calculation up to 100; NIED Okahandja - Advisory teachers - October 2013
 
Height work permit
Height work permitHeight work permit
Height work permit
 
Telecommunication Tower
Telecommunication TowerTelecommunication Tower
Telecommunication Tower
 
Aluminium ladders
Aluminium laddersAluminium ladders
Aluminium ladders
 
Delcast Egaf6
Delcast Egaf6Delcast Egaf6
Delcast Egaf6
 
Revised intensity frequency-duration (ifd) design rainfalls estimates for wa ...
Revised intensity frequency-duration (ifd) design rainfalls estimates for wa ...Revised intensity frequency-duration (ifd) design rainfalls estimates for wa ...
Revised intensity frequency-duration (ifd) design rainfalls estimates for wa ...
 
Pavement materials and design in western australia by geoffrey cocks
Pavement materials and design in western australia by geoffrey cocksPavement materials and design in western australia by geoffrey cocks
Pavement materials and design in western australia by geoffrey cocks
 
Smart grid - Do they fit into real networks ver 1
Smart grid  - Do they fit into real networks ver 1Smart grid  - Do they fit into real networks ver 1
Smart grid - Do they fit into real networks ver 1
 

Similar to Jacobs Recent changes to transmission line design standards and the impact on new construction and ageing assets in the Pilbara

Power system slide notes
Power system slide notesPower system slide notes
Power system slide notes
michaeljmack
 
GIS 400kv substation
GIS  400kv substationGIS  400kv substation
GIS 400kv substation
Anbarasu Balakrishnan
 
Wind farm planning and commissioning
Wind farm planning and commissioningWind farm planning and commissioning
Wind farm planning and commissioning
Preet_patel
 
2012 offshore wind cables
2012 offshore wind cables2012 offshore wind cables
2012 offshore wind cables
MEC Intelligence
 
Wind Power Plant Planning And Commisioning
Wind Power Plant  Planning  And CommisioningWind Power Plant  Planning  And Commisioning
Wind Power Plant Planning And Commisioning
Suraj Naik
 
AME POWER PLANT REFERENCES
AME POWER PLANT REFERENCESAME POWER PLANT REFERENCES
AME POWER PLANT REFERENCESCarlo Avanzini
 
Conductix Wampfler Product Overview Cables
Conductix Wampfler Product Overview CablesConductix Wampfler Product Overview Cables
Conductix Wampfler Product Overview Cables
Thorne & Derrick International
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976
Southern Railway
 
Gas insulated substation 1
Gas insulated substation 1Gas insulated substation 1
Gas insulated substation 1
Ronal Parmar
 
Elastimold - Cable Connectors, Joints, Terminations Catalogue
Elastimold - Cable Connectors, Joints, Terminations CatalogueElastimold - Cable Connectors, Joints, Terminations Catalogue
Elastimold - Cable Connectors, Joints, Terminations Catalogue
Thorne & Derrick International
 
Electrical safety presentation by jmv railway and invitation ireee2019 at ...
Electrical safety  presentation by jmv   railway and invitation ireee2019 at ...Electrical safety  presentation by jmv   railway and invitation ireee2019 at ...
Electrical safety presentation by jmv railway and invitation ireee2019 at ...
Mahesh Chandra Manav
 
Metal enclosed busduct
Metal enclosed busductMetal enclosed busduct
Metal enclosed busduct
Amit Agrawal
 
Chapter 4 mechanical design of transmission lines
Chapter 4  mechanical design of transmission linesChapter 4  mechanical design of transmission lines
Chapter 4 mechanical design of transmission lines
firaoltemesgen1
 
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs) Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Audubon Engineering Company
 
Case study sterlite deadend grip
Case study  sterlite deadend gripCase study  sterlite deadend grip
Case study sterlite deadend grip
Harish Agarwal
 
Reel and Umbilical Training for Subsea Hose Reels and Umbilicals
Reel and Umbilical Training for Subsea Hose Reels and UmbilicalsReel and Umbilical Training for Subsea Hose Reels and Umbilicals
Reel and Umbilical Training for Subsea Hose Reels and Umbilicals
wevans1
 
Aerial cables
Aerial cablesAerial cables
Aerial cables
Sandeep Bhowmick
 
ga-gae system
ga-gae systemga-gae system
ga-gae system
Ormazabal
 
Asce 7 10 presentation on seismic bracing for mep systems
Asce 7 10 presentation on seismic bracing for mep systemsAsce 7 10 presentation on seismic bracing for mep systems
Asce 7 10 presentation on seismic bracing for mep systems
michaeljmack
 
Metalclad switchgear
Metalclad switchgearMetalclad switchgear
Metalclad switchgear
Sayandeep Dasgupta
 

Similar to Jacobs Recent changes to transmission line design standards and the impact on new construction and ageing assets in the Pilbara (20)

Power system slide notes
Power system slide notesPower system slide notes
Power system slide notes
 
GIS 400kv substation
GIS  400kv substationGIS  400kv substation
GIS 400kv substation
 
Wind farm planning and commissioning
Wind farm planning and commissioningWind farm planning and commissioning
Wind farm planning and commissioning
 
2012 offshore wind cables
2012 offshore wind cables2012 offshore wind cables
2012 offshore wind cables
 
Wind Power Plant Planning And Commisioning
Wind Power Plant  Planning  And CommisioningWind Power Plant  Planning  And Commisioning
Wind Power Plant Planning And Commisioning
 
AME POWER PLANT REFERENCES
AME POWER PLANT REFERENCESAME POWER PLANT REFERENCES
AME POWER PLANT REFERENCES
 
Conductix Wampfler Product Overview Cables
Conductix Wampfler Product Overview CablesConductix Wampfler Product Overview Cables
Conductix Wampfler Product Overview Cables
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976
 
Gas insulated substation 1
Gas insulated substation 1Gas insulated substation 1
Gas insulated substation 1
 
Elastimold - Cable Connectors, Joints, Terminations Catalogue
Elastimold - Cable Connectors, Joints, Terminations CatalogueElastimold - Cable Connectors, Joints, Terminations Catalogue
Elastimold - Cable Connectors, Joints, Terminations Catalogue
 
Electrical safety presentation by jmv railway and invitation ireee2019 at ...
Electrical safety  presentation by jmv   railway and invitation ireee2019 at ...Electrical safety  presentation by jmv   railway and invitation ireee2019 at ...
Electrical safety presentation by jmv railway and invitation ireee2019 at ...
 
Metal enclosed busduct
Metal enclosed busductMetal enclosed busduct
Metal enclosed busduct
 
Chapter 4 mechanical design of transmission lines
Chapter 4  mechanical design of transmission linesChapter 4  mechanical design of transmission lines
Chapter 4 mechanical design of transmission lines
 
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs) Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
 
Case study sterlite deadend grip
Case study  sterlite deadend gripCase study  sterlite deadend grip
Case study sterlite deadend grip
 
Reel and Umbilical Training for Subsea Hose Reels and Umbilicals
Reel and Umbilical Training for Subsea Hose Reels and UmbilicalsReel and Umbilical Training for Subsea Hose Reels and Umbilicals
Reel and Umbilical Training for Subsea Hose Reels and Umbilicals
 
Aerial cables
Aerial cablesAerial cables
Aerial cables
 
ga-gae system
ga-gae systemga-gae system
ga-gae system
 
Asce 7 10 presentation on seismic bracing for mep systems
Asce 7 10 presentation on seismic bracing for mep systemsAsce 7 10 presentation on seismic bracing for mep systems
Asce 7 10 presentation on seismic bracing for mep systems
 
Metalclad switchgear
Metalclad switchgearMetalclad switchgear
Metalclad switchgear
 

More from Engineers Australia

Timber Connections reduced by Geoff Boughton
Timber Connections reduced by Geoff BoughtonTimber Connections reduced by Geoff Boughton
Timber Connections reduced by Geoff BoughtonEngineers Australia
 
Green schemes 2012_npe_eo_y lecture perth v9
Green schemes 2012_npe_eo_y lecture perth v9Green schemes 2012_npe_eo_y lecture perth v9
Green schemes 2012_npe_eo_y lecture perth v9Engineers Australia
 
Design and Analysis of Floating Production Systems
Design and Analysis of Floating Production Systems Design and Analysis of Floating Production Systems
Design and Analysis of Floating Production Systems
Engineers Australia
 
The EPCM of writing tenders: How engineers can successfully build compelling ...
The EPCM of writing tenders: How engineers can successfully build compelling ...The EPCM of writing tenders: How engineers can successfully build compelling ...
The EPCM of writing tenders: How engineers can successfully build compelling ...
Engineers Australia
 
Bid write presentation engineers australia & spe 7 feb12-1
Bid write presentation   engineers australia & spe 7 feb12-1Bid write presentation   engineers australia & spe 7 feb12-1
Bid write presentation engineers australia & spe 7 feb12-1Engineers Australia
 
EA / ATSE joint seminar Engineering for Extreme Natural Events
EA / ATSE joint seminar Engineering for Extreme Natural EventsEA / ATSE joint seminar Engineering for Extreme Natural Events
EA / ATSE joint seminar Engineering for Extreme Natural EventsEngineers Australia
 
Freight and public transport planning initiatives conference 24 november 2011
Freight and public transport planning initiatives conference 24 november 2011Freight and public transport planning initiatives conference 24 november 2011
Freight and public transport planning initiatives conference 24 november 2011Engineers Australia
 
How to write a research paper. By Gareth Forbes, Curtin University and Engine...
How to write a research paper. By Gareth Forbes, Curtin University and Engine...How to write a research paper. By Gareth Forbes, Curtin University and Engine...
How to write a research paper. By Gareth Forbes, Curtin University and Engine...
Engineers Australia
 
How to write a research paper. By Mark Bush
How to write a research paper. By Mark BushHow to write a research paper. By Mark Bush
How to write a research paper. By Mark Bush
Engineers Australia
 
How to write a research paper. By Prof A (Tony) D Lucey, Curtin University an...
How to write a research paper. By Prof A (Tony) D Lucey, Curtin University an...How to write a research paper. By Prof A (Tony) D Lucey, Curtin University an...
How to write a research paper. By Prof A (Tony) D Lucey, Curtin University an...
Engineers Australia
 
Ausimm engineers aust presentation 040811 (97-2003 version)
Ausimm engineers aust  presentation 040811 (97-2003 version) Ausimm engineers aust  presentation 040811 (97-2003 version)
Ausimm engineers aust presentation 040811 (97-2003 version) Engineers Australia
 
ICWES15 - Support for elementary School Science Teachers. Presented by Valeri...
ICWES15 - Support for elementary School Science Teachers. Presented by Valeri...ICWES15 - Support for elementary School Science Teachers. Presented by Valeri...
ICWES15 - Support for elementary School Science Teachers. Presented by Valeri...Engineers Australia
 
ICWES15 - Women in Engineering: Are we reinventing the Wheel? Presented by A/P
ICWES15 - Women in Engineering: Are we reinventing the Wheel?  Presented by A/PICWES15 - Women in Engineering: Are we reinventing the Wheel?  Presented by A/P
ICWES15 - Women in Engineering: Are we reinventing the Wheel? Presented by A/PEngineers Australia
 
ICWES15 - An Opportunity for Change. Presented by Angela E Hili, AUST
ICWES15 - An Opportunity for Change. Presented by Angela E Hili, AUSTICWES15 - An Opportunity for Change. Presented by Angela E Hili, AUST
ICWES15 - An Opportunity for Change. Presented by Angela E Hili, AUSTEngineers Australia
 
ICWES15 - A Digital Future and Resource Depletion. Presented by Jackie M Carp...
ICWES15 - A Digital Future and Resource Depletion. Presented by Jackie M Carp...ICWES15 - A Digital Future and Resource Depletion. Presented by Jackie M Carp...
ICWES15 - A Digital Future and Resource Depletion. Presented by Jackie M Carp...Engineers Australia
 
ICWES15 - System Fix: Transforming Education and Recruitment of Engineers by ...
ICWES15 - System Fix: Transforming Education and Recruitment of Engineers by ...ICWES15 - System Fix: Transforming Education and Recruitment of Engineers by ...
ICWES15 - System Fix: Transforming Education and Recruitment of Engineers by ...Engineers Australia
 
ICWES15 - Being a Femaile Engineer and Role Model - a Personal Perspective. ...
ICWES15 - Being a Femaile Engineer and Role Model - a Personal Perspective.  ...ICWES15 - Being a Femaile Engineer and Role Model - a Personal Perspective.  ...
ICWES15 - Being a Femaile Engineer and Role Model - a Personal Perspective. ...Engineers Australia
 
ICWES15 - The Formation of Women in Engineering: Townsville. Presented by Kel...
ICWES15 - The Formation of Women in Engineering: Townsville. Presented by Kel...ICWES15 - The Formation of Women in Engineering: Townsville. Presented by Kel...
ICWES15 - The Formation of Women in Engineering: Townsville. Presented by Kel...Engineers Australia
 

More from Engineers Australia (20)

Timber Connections reduced by Geoff Boughton
Timber Connections reduced by Geoff BoughtonTimber Connections reduced by Geoff Boughton
Timber Connections reduced by Geoff Boughton
 
Green schemes 2012_npe_eo_y lecture perth v9
Green schemes 2012_npe_eo_y lecture perth v9Green schemes 2012_npe_eo_y lecture perth v9
Green schemes 2012_npe_eo_y lecture perth v9
 
Design and Analysis of Floating Production Systems
Design and Analysis of Floating Production Systems Design and Analysis of Floating Production Systems
Design and Analysis of Floating Production Systems
 
The EPCM of writing tenders: How engineers can successfully build compelling ...
The EPCM of writing tenders: How engineers can successfully build compelling ...The EPCM of writing tenders: How engineers can successfully build compelling ...
The EPCM of writing tenders: How engineers can successfully build compelling ...
 
Bid write presentation engineers australia & spe 7 feb12-1
Bid write presentation   engineers australia & spe 7 feb12-1Bid write presentation   engineers australia & spe 7 feb12-1
Bid write presentation engineers australia & spe 7 feb12-1
 
111125 IChemE Palmer
111125 IChemE Palmer111125 IChemE Palmer
111125 IChemE Palmer
 
EA / ATSE joint seminar Engineering for Extreme Natural Events
EA / ATSE joint seminar Engineering for Extreme Natural EventsEA / ATSE joint seminar Engineering for Extreme Natural Events
EA / ATSE joint seminar Engineering for Extreme Natural Events
 
Freight and public transport planning initiatives conference 24 november 2011
Freight and public transport planning initiatives conference 24 november 2011Freight and public transport planning initiatives conference 24 november 2011
Freight and public transport planning initiatives conference 24 november 2011
 
How to write a research paper. By Gareth Forbes, Curtin University and Engine...
How to write a research paper. By Gareth Forbes, Curtin University and Engine...How to write a research paper. By Gareth Forbes, Curtin University and Engine...
How to write a research paper. By Gareth Forbes, Curtin University and Engine...
 
How to write a research paper. By Mark Bush
How to write a research paper. By Mark BushHow to write a research paper. By Mark Bush
How to write a research paper. By Mark Bush
 
How to write a research paper. By Prof A (Tony) D Lucey, Curtin University an...
How to write a research paper. By Prof A (Tony) D Lucey, Curtin University an...How to write a research paper. By Prof A (Tony) D Lucey, Curtin University an...
How to write a research paper. By Prof A (Tony) D Lucey, Curtin University an...
 
Ausimm engineers aust presentation 040811 (97-2003 version)
Ausimm engineers aust  presentation 040811 (97-2003 version) Ausimm engineers aust  presentation 040811 (97-2003 version)
Ausimm engineers aust presentation 040811 (97-2003 version)
 
2011 mar kalgoorlie_ieaust_
2011 mar kalgoorlie_ieaust_2011 mar kalgoorlie_ieaust_
2011 mar kalgoorlie_ieaust_
 
ICWES15 - Support for elementary School Science Teachers. Presented by Valeri...
ICWES15 - Support for elementary School Science Teachers. Presented by Valeri...ICWES15 - Support for elementary School Science Teachers. Presented by Valeri...
ICWES15 - Support for elementary School Science Teachers. Presented by Valeri...
 
ICWES15 - Women in Engineering: Are we reinventing the Wheel? Presented by A/P
ICWES15 - Women in Engineering: Are we reinventing the Wheel?  Presented by A/PICWES15 - Women in Engineering: Are we reinventing the Wheel?  Presented by A/P
ICWES15 - Women in Engineering: Are we reinventing the Wheel? Presented by A/P
 
ICWES15 - An Opportunity for Change. Presented by Angela E Hili, AUST
ICWES15 - An Opportunity for Change. Presented by Angela E Hili, AUSTICWES15 - An Opportunity for Change. Presented by Angela E Hili, AUST
ICWES15 - An Opportunity for Change. Presented by Angela E Hili, AUST
 
ICWES15 - A Digital Future and Resource Depletion. Presented by Jackie M Carp...
ICWES15 - A Digital Future and Resource Depletion. Presented by Jackie M Carp...ICWES15 - A Digital Future and Resource Depletion. Presented by Jackie M Carp...
ICWES15 - A Digital Future and Resource Depletion. Presented by Jackie M Carp...
 
ICWES15 - System Fix: Transforming Education and Recruitment of Engineers by ...
ICWES15 - System Fix: Transforming Education and Recruitment of Engineers by ...ICWES15 - System Fix: Transforming Education and Recruitment of Engineers by ...
ICWES15 - System Fix: Transforming Education and Recruitment of Engineers by ...
 
ICWES15 - Being a Femaile Engineer and Role Model - a Personal Perspective. ...
ICWES15 - Being a Femaile Engineer and Role Model - a Personal Perspective.  ...ICWES15 - Being a Femaile Engineer and Role Model - a Personal Perspective.  ...
ICWES15 - Being a Femaile Engineer and Role Model - a Personal Perspective. ...
 
ICWES15 - The Formation of Women in Engineering: Townsville. Presented by Kel...
ICWES15 - The Formation of Women in Engineering: Townsville. Presented by Kel...ICWES15 - The Formation of Women in Engineering: Townsville. Presented by Kel...
ICWES15 - The Formation of Women in Engineering: Townsville. Presented by Kel...
 

Recently uploaded

Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABSDESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
itech2017
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
ambekarshweta25
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 

Recently uploaded (20)

Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABSDESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 

Jacobs Recent changes to transmission line design standards and the impact on new construction and ageing assets in the Pilbara

  • 1. Recent changes to transmission line design standards and the impact on new construction and ageing assets in the Pilbara ENGINEERS AUSTRALIA ASIF BHANGOR, PRINCIPAL ENGINEER AARON HAMILTON, SENIOR ELECTRICAL ENGINEER
  • 2. What will we cover in this presentation? 1. Introduction 2. The Pilbara, where are we? 3. AS/NZS 7000:2010 key differences amongst others 4. Tower testing 5. Aged transmission lines, what do we do in case of failures? 6. Helicopter stringing 7. Current industry practice in tower installation 8. New method of tower installation 9. Recognitions/Awards
  • 3. The Pilbara, where are we? • Region D with cyclonic wind speeds • Return periods for transmission lines generally 200+ years whilst distribution lines typically 50/100 years • Regional wind speed for say 200 years return is 72m/s • Indigenous heritage sites, priority ecological areas & rivers • Access constraints • Crossing 3rd party infrastructure sensitive to shutdowns – Mining company railways – Mining or Industry distribution and transmission lines – Highways
  • 4. AS/NZS 7000:2010 key differences amongst others Wind load • No need to apply 10% amplification to the wind speeds in AS/NZS 7000:2010 • No need to apply downdraft (high intensity winds) for regions C and D
  • 5. AS/NZS 7000:2010 key differences amongst others Wind load
  • 6. AS/NZS 7000:2010 key differences amongst others Insulator swing • High wind in insulator swing calculations has been typically mentioned as 500 Pa for power frequency clearance of 500mm
  • 7. AS/ NZS 7000:2010 key differences amongst others Insulator swing • Low wind and moderate wind is 100 Pa and 300 Pa • Some utilities have used 240 Pa as moderate wind
  • 8. AS/ NZS 7000:2010 key differences amongst others Insulator swing • Blowout calculation is linked to the serviceability wind but insulator swing talks about high wind (limiting to 500 Pa only) • If we apply maximum wind of the Pilbara, we get large swing angles which lead to bracket extensions for clearances
  • 9. AS/ NZS 7000:2010 key differences amongst others Insulator swing
  • 10. AS/ NZS 7000:2010 key differences amongst others Insulator swing … suggested approach… • The wind speed derived should be adjusted for the terrain, height multipliers from AS1170.2 and considering a drag factor of 1.2 • In addition, the wind speed is reduced for the effect of span reduction factors which takes into account the spatial characteristics of wind gusts and inertia offered by the conductors. See figure B5 in AS1170.2 Page 129 • For easement calculations, refer to item R4 in AS7000 and Cb1 2006 table 10.3 for the 5 – 10 minutes averaging period conversion which converts it to a serviceability wind for checking the easement
  • 11. AS/NZS 7000:2010 key differences amongst others Conductor assessment (strength and serviceability limits) • The below table highlights the factored approach in conductor assessment
  • 12. AS/NZS 7000:2010 key differences amongst others Comparison of Cb1 and AS7000 (for conductors in the Pilbara region) Wind Speeds up to 90m/sec for conductor selection (including height multipliers) Conductor type UTS (kN) Ft, MWT (kN) Ruling span (m) Special Diving ACSR (30/6/3.5+1/3.65) 146.0 119.4 470.0 AAAC Sapphire (37/3.75) 115.0 81.1 341.0 AACSR/AC/1120 (42/19/3.25) 264.5 145.0 360.0 Criteria/ Cb1 Conductor type 0.7UTS 1.5Ft Special Diving ACSR (30/6/3.5+1/3.65) 102.2 179.0 Conductor fails AAAC Sapphire (37/3.75) 80.5 121.6 Conductor fails AACSR/AC/1120 (42/19/3.25) 185.2 217.5 Conductor fails Criteria/(Failure/ Strength) AS7000 Conductor type 0.9UTS 1.25Ft Special Diving ACSR (30/6/3.5+1/3.65) 131.4 149.2 Conductor fails AAAC Sapphire (37/3.75) 103.5 101.3 OK AACSR/AC/1120 (42/19/3.25) 238.1 181.3 OK Criteria/(Damage/ Serviceability) Non Linear AS7000 Conductor type 0.7UTS 1.00Ft Special Diving ACSR (30/6/3.5+1/3.65) 102.2 119.4 Conductor fails AAAC Sapphire (37/3.75) 80.5 81.1 Conductor fails AACSR/AC/1120 (42/19/3.25) 185.2 145.0 OK Criteria/ (Damage/ Serviceability) Linear AS7000 Conductor type 0.5UTS 1.00Ft Special Diving ACSR (30/6/3.5+1/3.65) 73.0 119.4 Conductor fails AAAC Sapphire (37/3.75) 57.5 81.1 Conductor fails AACSR/AC/1120 (42/19/3.25) 132.3 145.0 Conductor fails Conductor assessment
  • 13. AS/NZS 7000:2010 key differences amongst others Pole foundation assessment • In the past utilities have used C(b)1 suggested empirical assessment of L/10+0.6 for foundation depths – having no interaction with soil data • Historically, utilities have deemed this acceptable for wood poles in region A where wind speeds are around 39 – 43m/s • However, in the Pilbara where cyclonic wind speeds are present due care has to be considered for poles carrying mine load thus requiring higher reliability (basically no foundation failures acceptable)
  • 14. AS/NZS 7000:2010 key differences amongst others Pole foundation assessment • Mindset exists that “We have done this in the past using L/10+0.6m so why increase the embedment depth now?” • More recently, utilities have moved away from L/10+0.6m embedment with proper soil interaction methods such as Broms, Brinch & Hansen etc. • Essential Energy, Electranet, Powerlink, Energy Australia design standards all refer to Brinch & Hansen now • Please refer to Table 9.7 of handbook HB331 which states disadvantages of the L/10+0.6(0.8) formula
  • 15. AS/NZS 7000:2010 key differences amongst others Pole foundation assessment
  • 16. AS/NZS 7000:2010 key differences amongst others Pole foundation assessment
  • 17. Tower Testing Tower Testing • Failures exhibit load sharing issues in lattice steel • Important to understand tower failures are catastrophic in nature • Hence the need to test towers and eliminate any issues in load sharing between members, plates, bolts etc. • Leg loads for cyclonic wind regions reach to around 2000kN per leg
  • 18. Aged transmission lines What do we do in case of failures? • Gradual ageing of steel structures exposed to extreme weather events exposes owners to high cost of refurbishment, let alone lost time of production if local generation does not exist • Generally utilities have dealt with this problem using emergency response structures (i.e. Lindsey Guyed Masts) • The network in the Pilbara is at risk…failures mean complete shutdown…
  • 19. Aged transmission lines What do we do in case of failures? • There is a need to consider design of transmission lines with higher reliability (i.e. 500 years return wind speeds) and a high degree of accuracy when it comes to detailing and fabrication of steel for new projects • For ageing projects, there is a need to frequently check and maintain/ replace the ageing towers, conductors, and insulators using effective maintenance plans
  • 20. Aged transmission lines What do we do in case of failures? • Wednesday 28th September TransGrid had a failure on the 220kV line from Darlington Point to Buronga • The failure was at tower 557 and 558, approximately 30 kms east of Balranald (“in the middle of nowhere” was the first description). The cause was a high wind event • 3 towers have been damaged. Initially, towers 557 and 558 failed on the Wednesday night • On the morning of Friday 30th September, leg buckling on Tower 556 was observed • The line has been restored using timber pole emergency structures – 4 structures have been used
  • 21. Aged transmission lines What do we do in case of failures? • Tower 558 has failed in the “classical” manner of compression failure in the legs and has fallen at 90 deg to the line direction • The foundation shows obvious signs of severe corrosion of the reinforcement and necking of the remaining reo at failure • Some analysis needed to check the reo and concrete to determine the cause and age of the corrosion (an old construction joint? locally aggressive soil?)
  • 22. Aged transmission lines TransGrid Failure Event 28/09/2011 220kV Line from Darlington Point to Buronga, NSW • Region A7 Downdraft winds (high intensity winds) • Zone II, Span reduction factor = 1.0 (0-200m spans) • Wind speeds up to 43m/s (1.1kPA)
  • 23. Aged transmission lines TransGrid Failure Event 28/09/2011 220kV Line from Darlington Point to Buronga
  • 24. Aged transmission lines TransGrid Failure Event 28/09/2011 220kV Line from Darlington Point to Buronga
  • 25. Aged transmission lines Leigh Creek to Davenport 132kV line experienced a cyclone in SA
  • 26. Helicopter stringing in the Pilbara Some recent challenges experienced • Access constraints • Cultural heritage sites • River crossings • Priority ecological areas • Crossing 3rd party infrastructure sensitive to shutdowns • Mining company railways • Mining or Industry distribution and transmission lines • Highways
  • 27. Helicopter stringing in the Pilbara YM-CL 220kV Stringing Detail • Helicopter fitted with side pull rather than belly hook • Side pull is a customised piece of equipment designed specifically for stringing transmission lines • Side pull increases the helicopter fuel efficiency over a belly hook • Pilots prefer side pull as complete assembly is visible
  • 28. Helicopter stringing in the Pilbara YM-CL 220kV Stringing Detail • Helicopter pulls the cable out sideways, to ensure vision can be maintained in the direction of travel and the direction of load
  • 29. Helicopter stringing in the Pilbara YM-CL 220kV Stringing Detail • Pulling order planned to ensure that cables already strung are in front of or below the height of the aircraft rotor system • At no point should cables be behind the aircraft at the same height as the one being pulled
  • 30. Helicopter stringing in the Pilbara YM-CL 220kV Stringing Detail • Stringing broken in to 13 pulls • 7 of the 13 pulls involved 5 towers or fewer • Generally helicopter pulled draw wire for phase conductors and Earthwire and OPGW direct • Direct pulls need to be done under tension to keep off ground • Phase conductors are generally not pulled direct due to the weight, distance from the ground • Helicopter used to pull all conductors direct for rail and line crossings (due to outage limitations)
  • 31. Helicopter stringing in the Pilbara Advantages • Schedule improvement • 4.5km drawwire pull takes approximately 45 minutes • 12km OHEW or OPGW pull under tension takes approximately 3 hours • Critical path moves to linesmen sagging and terminating • Low impact on heritage sites (line crosses directly over 18) • Simplified stringing over heavily vegetated river crossing (620m) • Simplified, faster stringing over existing 132kV transmission lines • Simplified, faster stringing over rail
  • 32. Helicopter stringing in the Pilbara
  • 33. Current industry practice in tower installation
  • 34. Current industry practice in tower installation
  • 35. Current industry practice in tower installation
  • 36. Current industry practice in tower installation
  • 37. Current industry practice in tower installation Changing the way we do things? Counter arguments by stakeholders • Crane rated 10 times higher than load • Load calculations done for all critical lifts • Lift plans reviewed and signed off by engineer • Crane inspected at regular intervals • Crane operator is very experienced and has worked with rigging team for a long time • Rigging equipment rated 5 times higher than load • Rigging equipment inspected daily by crew as well as monthly inspections by accredited third party inspectors. • Rigging crew is well trained and very experienced in tower construction • Verification of competence of all riggers and crane operator • PPE inspected daily including safety harnesses, ropes etc. • Very quick installation reducing riggers time spent on the tower and risk of fall
  • 38. Current industry practice in tower installation • Incidents reported in failures
  • 39. Current industry practice in tower installation • Incidents reported in failures • Close Call for Big Truck Mount 01/17/14 • Newcastle, Australia • A 54 meter truck mounted lift lost balance near Newcastle, Australia when the ground gave way under one of its outriggers. • Fortunately the boom came to rest against the pylons of the high tension power line that it was helping to install – no one was injured or hurt in the incident
  • 40. Current industry practice in tower installation
  • 41. New method of tower installation “Safety guide” design This allows crane operators to lower the top section without manual intervention of crew • Once the lower portion of the tower is installed on the ground and fitted with the foundation base, it is fitted at the connection point to the top structure with the safety bracket • The top superstructure is suspended by the crane operator and lowered into the safety bracket, landing the top superstructure inside the bracket. The load of the top superstructure is relieved by the crane operator as the weight of the top does not rest on the steel itself • The rigging personnel can then go to the top section and connect the relevant bolts to the holes of the relevant plates and release the safety bracket. This enables them to work without being under suspended load
  • 42. New method of tower installation
  • 43. New method of tower installation
  • 44. New method of tower installation Site Construction Team developed option which included: • Purpose-made temporary “docking brackets” to be installed at the fixing positions to ease “landing” of the suspended structures onto their bases, without the need for riggers to be under the suspended loads. • Installation of temporary brackets to guide sections in to place isn’t new, but their use has to date been limited to helicopter based tower construction. • Spacing the splice plates of the suspended structure sections (mid sections), to gape open, thus easing the landing of those structures through carefully lowering, with control provided by tag lines with the riggers safely away from danger.
  • 45. New method of tower installation
  • 46. New method of tower installation
  • 47. New method of tower installation
  • 48. New method of tower installation
  • 49. New method of tower installation Achievement of outcomes • Eliminated the need for riggers to work under suspended loads or manually move the sections into place risking injury. • Riggers are no longer exposed to the swinging momentum of the tower sections. • Does not require additional brackets to be installed or design modifications for the most part and the changes were mostly procedural. Existing splice plates join the adjacent sections, which is easy to implement. • Developed new, safer site construction methodology that involves sections of the tower being landed onto the bottom sections with the combined use of brackets, guide ropes and or other equipment and material already available on site.
  • 50. New method of tower installation Longer splice plates significantly improves landing of the superstructure
  • 51. Recognitions/Awards Recognition in the Australian Industry to promote safety and innovation in current practices for Tower Design and Installation