2. MIAMI-DADE TPO TARC MEETING SEPTEMBER 16, 2020
RULES OF ENGAGEMENT 2
Rules of Engagement
• This is a public meeting and is being recorded.
• If you experience technical difficulties, please contact Lisa Juan at 954-716-8823 or at lisa.juan@kimley-horn.com so that a
member of our technical support team may assist you.
• Public participants:
• Will remain muted throughout the duration of this meeting except for the Public Comment period.
• If you wish to provide a comment, please use the “Raise Hand” button at the bottom of your Zoom panel so the
meeting organizer can unmute your microphone. If you are calling in, the organizer will automatically unmute your
microphone when the Public Comment period begins. Please proceed by first providing your full name and home
address followed by your comment.
• Committee members:
• If you wish to provide a comment, please use the “Raise Hand” button at the bottom of your Zoom panel. Wait to be
recognized by the Chair. Once recognized by the Chair, please provide your name and question/comment.
• Committee members are encouraged to enable their web cameras and mute their microphones when not speaking.
• To move or amend a motion, unmute your microphone, clearly state your name for the record, and propose or second
the motion. The TARC Coordinator will record the action and verbally confirm your name.
• Open votes such, as Approval of Agenda, will be conducted by calling dissenting votes only. Committee members in
opposition shall state their names and say “nay”. Resolutions and other important votes will be conducted via roll call.
3. TARC Agenda
I. Introduction
A. Approval of Agenda
B. Approval of Minutes
II. Action Items
A. Dadeland South Intermodal Project
III. Information Items
A. Golden Glades Multimodal Transportation Facility
B. TARC Attendance Sheet/Vacancy Report
IV. Reports
A. Member Reports
B. Staff Reports
V. New Business
A. Upcoming TARC Meetings
VI. Public Comment
VII. Adjournment
10. 10
MIAMI-DADE TPO TARC MEETING SEPTEMBER 16, 2020
Dadeland South Intermodal
Project
II.A.
ACTION ITEMS
11. Department of Transportation and Public Works
CIP 207: Dadeland South Intermodal Station Project
Prepared for: The Miami-Dade County Technical Aesthetics Review
Project Presentation
September 16, 2020
12. 1. Introductions
2. Project Delivery Method
3. Project Schedule
4. Project Scope
a. Architectural Elements
b. Structural Elements
5. Permitting Considerations
Presentation Agenda
14. • Design-Build
• Design Criteria Package
• Narrative (defines design and construction criteria)
• Attachments (Design-Build Firm must adhere to)
• Reference Documents (for informational purposes only)
• Funded by County’s PTP
Project Delivery Method
15. • Advertisement (Step 1): late September 2020
• Short List (Step 2): late November 2020
• Bid Opening: early February 2021
• Design-Build Firm selection: early September 2021
• Project NTP: early October 2021
• Duration – approximately 2 years
• Substantial Completion/Revenue Service
• Final Acceptance
Schedule Milestones
16. • Elevated Bus Rapid Transit (BRT) platform
• BRT Platform Canopy
• Metrorail Canopy Extension
• Canopy over vertical circulation at north entrance
• Canopy over walkway to connect kiss-and-ride to north entrance
• Passenger connectivity to/from Metrorail platform via a track grade
pedestrian crossing and an inclined walkway
• Operator Relief Station (BRT and Train)
• Transit Supervisor Booths (Bus, BRT and Train)
Project Scope
30. • Additional station improvements
• facility technologies
• bicycle facilities
• lighting
• landscape and hardscape elements
• wayfinding signage and station identification pylon
• tile flooring replacement
• Climate control systems
• Spot diffusers
• Vertical circulation elements
• Emergency egress stairways from BRT platform
• New elevator
Project Scope (continued)
39. • Site and Roadway Improvements
• Milling and resurfacing (M&R) of adjacent roadways
• Bus only lane on Dadeland Boulevard
• Signalization improvements
• Pick-up/drop-off area reconfiguration
• M&R of park-and-ride surface lot
Project Scope (continued)