Realization on Construction management of residential
apartments
Ashfaq Ahmed
(M.tech), School of Civil Engineering, HINDUSTAN university, chennai - 603103, Tamil Nadu, India;
Abstract: Proper planning and scheduling is very important in construction projects for reducing and controlling
delays of the project. Substantial amounts of time, money, resources are wasted each year in a construction industry
due to improper planning and scheduling. With globalization the construction projects have become vast and
complex. Planning of such projects requires huge amount of paperwork, which can be reduced with the help of project
planning software. Providing good planning, proper organization, sufficient flow of resources to a project cannot
automatically achieve desired result. A warning mechanism must be present which can alert the organization about
its possible success and failures throughout the project. The main objectives of this study are to plan, schedule a
Residential project with help of primavera software, study the results generated, it is possible to suggest which
method is suitable for the selected residential Building project. Also to recommend measures to the organization for
enhancing their project planning skills for similar projects in future and provide them with technical problems
encountered in their process. This study is mainly done using Primavera P6, project management software. All
activities and their sequence of occurrence, duration, resources required and costs involved are studied. The
organizational breakdown structure of company and work breakdown structure of the project are noted. This gives an
idea about the resources involved and financial aspect of the completed work.“Project management is the application
of knowledge, skills, tools and techniques to project activities to meet the project Requirements
Keywords: Planning, Scheduling, budgeting, Project Planning Software, Primavera
I. Introduction
Construction industry is an integral component of a nation’s infrastructure and industrial growth.
Even though construction industry is the second largest industry in India, the growth of this industry has been
differential across the nation. The rural regions need tools for economic development, land use and
environment planning to cope with the status of development in urban areas. The time available to achieve this
goal is shrinking. Here arises the need for effective project management. Many issues are being faced by
construction industry that must be taken care of. They include time and cost overruns due to inadequate
project formulation, poor planning for implementation, lack of proper contract planning and management and
lack of proper management during execution. It has been estimated by analysts that average cost of a project
goes up by 30 percentage compared to the budgeted cost. Observations show that proper skilful management
is imperative for the timely completion of the project within estimated budget and with allocated resources.
Projects with good planning, adequate organizational machinery and sufficient flow of resources cannot
automatically achieve the desired result.
There must be some warning mechanism, which can alert the organization about its possible success
and failures, off and on. Project monitoring is the process of collecting, recording, and reporting information
concerning project performance that project manager and others wish to know. Monitoring involves watching
the progress of the project against time, resources and performance schedule during execution of the project
and identifying lagging areas requiring timely attention and action whereas project controlling uses data from
monitor activity to bring actual performance to planned performance.
The main objectives of this study are:
1. To suggest the importance and purpose of Planning the construction work.
2. To suggest guidelines to contractors for Scheduling the project.
3. To reduce ideal in construction process of residential building.
4. To suggest a layout for updating the schedule.
5. To suggest effective budgeting method.
This study is mainly done using Primavera P6, project management software. All activities and their
sequence of occurrence, duration, resources required and costs involved are studied. The organizational
breakdown structure of company and work breakdown structure of the project are noted. This gives an idea
about the resources involved and financial aspect of the completed work.“Project management is the application
of knowledge, skills, tools and techniques to project activities to meet the project Requirements.
Realization on Construction management of residential apartments
DOI: 10.9790/1684-1303024956 www.iosrjournals.org 50 | Page
Plan.-During the planning stage of a project schedule, thecontractor lays out all project elements to create a
time-based graphical representation of the project scope. The planning stage includes:
• Defining objectives and scope of work.
• Identifying milestones (contractual dates, benchmarks).
• Developing work breakdown structures (what and where).
• Developing an organization breakdown structure (who).
• Creating activities (when and where).
• Creating relationships (interfaces, dependencies, network).
• Identifying a critical path.
• Assigning resources (personnel, equipment, or material).
• Performing risk analysis.
• Refining schedule as needed.
• Establishing the baseline schedule.
Perform. This state occurs after the schedule has been planned,adopted, and executed. The perform stage
includes:
• Updating the schedule on a regular basis.
• Updating progress.
• Incorporating updates or revisions, including project delays.
• Communicating status to team and management.
Monitor. During this stage, the schedule is most beneficial topredict the outcome of the project. Monitor
(also referred to as controlling) includes:
• Regularly analyzing the schedule based on special provisions and Standard Specifications requirements.
• Analyzing resource productivity.
• Analyzing cost usage.
• Analyze time extensions.
• Comparing different schedules to find changes to key elements such as:
▫ Planned duration versus actual duration
▫ Remaining duration
▫ As-built dates (start and finish)
▫ Descriptions
▫ Changes to logical relationships
• Evaluating performance (earned value techniques).
• Identifying trends.
• Developing forecasts.
Modify. This stage includes:
• Incorporating approved change orders.
• Performing time impact analysis for delays.
• Identifying recovery plan (fast-tracking, modifying logic).
• Communicating new direction to team and management.
II. Methodology
The scope of work was divided into the following steps:
 Study areacharacteristics.
 Preparing actual schedule for the project in primavera.
 Identifyingtheconstraintsinthatproject.
 Reducing the constraints which causes delay and prepare new schedule.
 Optimize the labour resources to reduce the cost of theproject.
Preparing Actual Schedule forthe Project in Primavera
Actual schedule preparation process starts with the collection of data like project start date, activities
involved in the construction of a G+7 apartment with stilt, activities sequences, duration taken for each
and every activities, resources needed for each and every activities and its amount, cost spent for each and
every activities. The collected data are entered in the software and the relations between the activities are given
as per its sequence ofactivities collected.The process ofscheduling in primavera for the actual progress of work
Realization on Construction management of residential apartments
DOI: 10.9790/1684-1303024956 www.iosrjournals.org 51 | Page
is shown in Figure 1, 2, 3, 4 .This actual schedule and report is considered as a base schedule for this project.
Figure 1. Actual Schedule Part(i).
Figure 2. Actual Schedule Part (ii).
Figure 3. Actual Schedule Part (iii).
Realization on Construction management of residential apartments
DOI: 10.9790/1684-1303024956 www.iosrjournals.org 52 | Page
Figure 4. Actual Schedule Part (iv).
The root causes for the long durationare,
 No parallel activities were done.
 Longest criticalpath.
 Lackofresources.
These three are the reasons for the delay of the project and due to the interdependencies of time and
cost; these causes are also responsible for the cost overrun of the project.
Measures Taken to Reduce the Time Constraints
Constraints causing the time delay have to be reduced. The techniques used to reduce these constraints
are,
• Interconnecting activities properly.
• Increasing the resources.
Budgeting the project
A budget is a quantitative expression of a plan for defined period of time. It may include planned sales
volumes and revenues, resource quantities, costs and expenses, assets, liabilities and cash flows. It expresses
strategic plans of business units, organizations, activities or events in measurable terms.
Budget helps to aid the planning of actual operations by forcing managers to consider how the
conditions might change and what steps should be taken now and by encouraging managers to consider
problems before they arise. It also helps co-ordinate the activities of the organization by compelling managers to
examine relationships between their own operation and those of other departments
III. Results and Discussions
Modified Schedule 1 -Interconnecting Activities Properly
The connection of the activities plays a major role in the time controlling of the project. Connecting
activities should be carefully done which is considerably resulting in the project success. The constraints of
having longest critical path can be reduced by means of doing activities parallel. These parallel activities can be
done in the prima- vera software by differentiating relationship between the activities.
Report obtained from the modified schedule 1 gives the result of interconnecting activities properly.
This interconnecting activity shows a considerable result in the time taken for completion of the project. The
time dif- ference taken for the completion of the project between the original schedule and modified schedule
1 is five months.
Modified Schedule 2 Increasing Resources
For doing every activity in the construction process, sufficient amount of resources is required.
Resourcesplaya vital role in the project for the successful completion of all the activities on time. Time delay caused
in a single activity will be carried over to the subsequent activities. This delay of each activity is due to the
insufficient resources. Therefore, it is necessary to provide sufficient amount of resources like men, material and
equipment to reducethe time taken for the construction of the project.
In this residential apartment, the shuttering material and workmen are insufficient. Therefore the activities of con-
structing structural elements of columns in each floor take four sets of activities. Single set of activities consists of
rein- forcing, shuttering, concreting and de-shuttering. Therefore increasing the resources will result in reducing the
Realization on Construction management of residential apartments
DOI: 10.9790/1684-1303024956 www.iosrjournals.org 53 | Page
repetition of that sets of activities, which results in reducing the delay in the project. In this, the resources have
been increased twice and the schedule was prepared in the primavera.
These two measures can be done by means of proper planning and scheduling of the project. The
corrective measures of proper interconnecting activities and increas- ing the resources is incorporated in the new
schedule of that residential project.
The schedule made by increasing the resources twice with the interconnection of activities properly
completes two months before from the project completion time of the modified schedule 1 and it completes
seven months before from the original schedule of the residential apartment project.
Figure 5. S-curve analysis.
Lower productivity of machinery
Productivity is an average measure of the efficiency of production. It can be expressed as the ratio of output to
inputs used in the production process, i.e. output per unit of input. When all outputs and inputs are included in the
productivity measure it is called total productivity. Outputs and inputs are defined in the total productivity measure as
their economic values. The value of outputs minus the value of inputs is a measure of the income generated in a
production process. It is a measure of total efficiency of a production process and as such the objective to be
maximized in production process
Figure 6. running hours for equipments
0 5000 10000 15000
1
2
3
4
Running Hours
Actual
Running Hours
Planned
Realization on Construction management of residential apartments
DOI: 10.9790/1684-1303024956 www.iosrjournals.org 54 | Page
Figure 7. total machine months variation.
Figure 8.variation for equipment
Figure 9.. comparison of equipments running hours
0 20 40 60
Diesel
Generator (1)
BOBCAT
Effeciency (2)
AIR Compressor
(3)
Concrete Pump
(4)
Total Machine
Month Actual
Total Machine
Month Planned
Total Machine Month
Diesel
Generator (1)
BOBCAT
Effeciency (2)
AIR
Compressor
(3)
Concrete
Pump (4)
Running Hours
1 2
3 4
Realization on Construction management of residential apartments
DOI: 10.9790/1684-1303024956 www.iosrjournals.org 55 | Page
Figure 10. amount for each equipment
Figure 11. comparison of rate of diesel
Figure 12. milage for each equipment
Figure 13. cumulative hours comparision for equipments
IV. Conclusion
Schedule made by using techniques that reduce the constraints helps for the project to complete
earlier of five to seven months from the actual base schedule of the project and thereby increase the
profit outcome from the project. Further, with the management on the labour resource of skilled, unskilled
male worker and unskilled female worker in the construction activities, the cost spent on the labour resources
reduces by 5% of the actual cost spent on the labour resources. Using a soft- ware helps to manage the work
easily and it reduces the information constraints between the management and the site members which greatly
contribute to the project success.
This study concludes that by using the Primavera a time period of 4 months from the actual base
schedule of the project was saved and also helps to prevent the cost overrun, thereby ensuring the successful
completion of the project. It helps to manage the work easily and also helps to avoid constraints or risks that will
delay the project by interconnecting and parallelizing the activities and mobilization of the resources from time
to time for successful completion of the project within the estimated time
Amount
1
2
3
4
Rate of Diesel (Rs.)
1
2
3
4
Litres/hr
1
2
3
Actual Cum/hr
1
2
3
Realization on Construction management of residential apartments
DOI: 10.9790/1684-1303024956 www.iosrjournals.org 56 | Page
Budget is prepared for each and every activity by allocating the resources to the activities. Budgeted
project labor, Non labor, Expense, Material and total cost of all theactivities are calculated. The total budgeted
cost of the project was Rs16, 556,504.80.
Activities are to be tracked as per the project duration from January 1st to April 4nd and actual costs
for all the activities in that duration are updated. Total actual cost within this duration was Rs.21,02,789.39.
References
[1]. Subramani.T and Chinnadurai.K (2015), Construction Management and Scheduling of Residential Building Using Primavera,International
JournalofApplication or Innovation in Engineering & Management (IJAIEM), 4(5), 188-198.
[2]. Prabhat Kumar Sinha, Abusalah Mohamed Alakhdar Abdlaziz, R.K. Pandey, Ashok Tripathi and Anshuman(2013), Time and
schedule management using Primavera, International journal of Civil engineering and technology (IJCIET), 4(5), 78-87.
[3]. Satinder Chopra and Arvind Dewangan (2014), Time and schedule management by using primavera P6: Significance of activity ID and
description, International Journal of Innovative Research in Science, Engineering and Technology, 3(7), 15022-15027.
[4]. X. Regina Mary and V. Rathinakumar (2015), Reducing Construction Constraints using Primavera, Indian Journal of Science and
Technology, 8(14), 1-7.
[5]. Unmesh. Y. Polekar and Rohit. R. Salgude (2015), Planning, Scheduling and Tracking of a residential Project using Primavera Software,
International Journal of Advance Research in Computer Science and Management Studies, 3(5), 227-236.
[6]. A.A.Lakade, A.K.Gupta and D.B.Desai (2010), A Project Management Approach Using Primavera In Construction Industry, Journal of
Mechanical and Civil Engineering, 15(2), 21-24
[7]. Pethe Sarang S and Pramila Adavi (2012), Application of primavera in construction industry, International Journal of Advanced
Technology in Civil Engineering, 1(3), 16-17.
[8]. Andrew Fernans Tom and Sachin Paul (2013), Project Monitoring and Control using Primavera, International Journal of Innovative
Research in Science, Engineering and Technology, 2(3), 762-771.
[9]. Reddy. B. S. K, Nagaraju SK, Salman. MD (2015), Astudy on optimisation of resources for multiple projects by using primavera, Journal
of Engineering Science and Technology, 10(2), 235-248.

More Related Content

What's hot

Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Managementsrinivas2036
 
Project implimentation
Project implimentationProject implimentation
Project implimentationMazhar Poohlah
 
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...IRJET Journal
 
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...IRJET Journal
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
Project management and control
Project management and controlProject management and control
Project management and controlShruti Pendharkar
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniquesguestc8140fe
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project managementKabilan Kabi
 
Construction planning_Construction Management (2180611) (Semester-8), Civil E...
Construction planning_Construction Management (2180611) (Semester-8), Civil E...Construction planning_Construction Management (2180611) (Semester-8), Civil E...
Construction planning_Construction Management (2180611) (Semester-8), Civil E...A Makwana
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & managementManit Agarwal
 
Project management
Project managementProject management
Project managementAhmed Said
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and schedulingadeel hamid
 
Project management tools and techniques- tutorsindia.com
Project management tools and techniques- tutorsindia.comProject management tools and techniques- tutorsindia.com
Project management tools and techniques- tutorsindia.comTutors India
 
Project Management Notes 3
Project Management Notes 3Project Management Notes 3
Project Management Notes 3Golam Bitonsir
 

What's hot (20)

Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Construction Management - New Trends
Construction Management - New TrendsConstruction Management - New Trends
Construction Management - New Trends
 
Project implimentation
Project implimentationProject implimentation
Project implimentation
 
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...
 
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
 
105 project time management
105 project time management105 project time management
105 project time management
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Project management and control
Project management and controlProject management and control
Project management and control
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
Construction planning_Construction Management (2180611) (Semester-8), Civil E...
Construction planning_Construction Management (2180611) (Semester-8), Civil E...Construction planning_Construction Management (2180611) (Semester-8), Civil E...
Construction planning_Construction Management (2180611) (Semester-8), Civil E...
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
Chapter 3
Chapter 3Chapter 3
Chapter 3
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
Project management
Project managementProject management
Project management
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
Project management tools and techniques- tutorsindia.com
Project management tools and techniques- tutorsindia.comProject management tools and techniques- tutorsindia.com
Project management tools and techniques- tutorsindia.com
 
Project Management Notes 3
Project Management Notes 3Project Management Notes 3
Project Management Notes 3
 

Viewers also liked

NDL-MSL-RPT-005 - Capstone Design Project II Final Report Eric(Sungcheol) Cho...
NDL-MSL-RPT-005 - Capstone Design Project II Final Report Eric(Sungcheol) Cho...NDL-MSL-RPT-005 - Capstone Design Project II Final Report Eric(Sungcheol) Cho...
NDL-MSL-RPT-005 - Capstone Design Project II Final Report Eric(Sungcheol) Cho...Eric Choi
 
Technologie de pointe intégrant des données de trafic et de la cartographie d...
Technologie de pointe intégrant des données de trafic et de la cartographie d...Technologie de pointe intégrant des données de trafic et de la cartographie d...
Technologie de pointe intégrant des données de trafic et de la cartographie d...Intelli³
 
ALM for Project Managers: Kanban, Dashboards & Reports, Traceability
ALM for Project Managers: Kanban, Dashboards & Reports, TraceabilityALM for Project Managers: Kanban, Dashboards & Reports, Traceability
ALM for Project Managers: Kanban, Dashboards & Reports, TraceabilityIntland Software GmbH
 
Webinar - Risky Business: How to Balance Innovation & Risk in Big Data
Webinar - Risky Business: How to Balance Innovation & Risk in Big DataWebinar - Risky Business: How to Balance Innovation & Risk in Big Data
Webinar - Risky Business: How to Balance Innovation & Risk in Big DataZaloni
 
P6 analytics producing meaningful results in P6 analytics - Oracle Primavera...
P6 analytics producing meaningful results in P6 analytics  - Oracle Primavera...P6 analytics producing meaningful results in P6 analytics  - Oracle Primavera...
P6 analytics producing meaningful results in P6 analytics - Oracle Primavera...p6academy
 
4.4 yasal haklar, kamu
4.4 yasal haklar, kamu4.4 yasal haklar, kamu
4.4 yasal haklar, kamueabdep
 
1.2.2 sınıflandırma
1.2.2 sınıflandırma1.2.2 sınıflandırma
1.2.2 sınıflandırmaeabdep
 
6.4.4.problem davranışların azaltılması
6.4.4.problem davranışların azaltılması6.4.4.problem davranışların azaltılması
6.4.4.problem davranışların azaltılmasıeabdep
 
Software Proposal Portal Inc.
Software Proposal Portal Inc.Software Proposal Portal Inc.
Software Proposal Portal Inc.swproposal
 
An Improved Phase Disposition Pulse Width Modulation (PDPWM) For a Modular Mu...
An Improved Phase Disposition Pulse Width Modulation (PDPWM) For a Modular Mu...An Improved Phase Disposition Pulse Width Modulation (PDPWM) For a Modular Mu...
An Improved Phase Disposition Pulse Width Modulation (PDPWM) For a Modular Mu...IOSR Journals
 

Viewers also liked (20)

NDL-MSL-RPT-005 - Capstone Design Project II Final Report Eric(Sungcheol) Cho...
NDL-MSL-RPT-005 - Capstone Design Project II Final Report Eric(Sungcheol) Cho...NDL-MSL-RPT-005 - Capstone Design Project II Final Report Eric(Sungcheol) Cho...
NDL-MSL-RPT-005 - Capstone Design Project II Final Report Eric(Sungcheol) Cho...
 
SH_InfoSolution_Bro
SH_InfoSolution_BroSH_InfoSolution_Bro
SH_InfoSolution_Bro
 
Technologie de pointe intégrant des données de trafic et de la cartographie d...
Technologie de pointe intégrant des données de trafic et de la cartographie d...Technologie de pointe intégrant des données de trafic et de la cartographie d...
Technologie de pointe intégrant des données de trafic et de la cartographie d...
 
творче портфоліо
творче портфоліотворче портфоліо
творче портфоліо
 
ALM for Project Managers: Kanban, Dashboards & Reports, Traceability
ALM for Project Managers: Kanban, Dashboards & Reports, TraceabilityALM for Project Managers: Kanban, Dashboards & Reports, Traceability
ALM for Project Managers: Kanban, Dashboards & Reports, Traceability
 
Webinar - Risky Business: How to Balance Innovation & Risk in Big Data
Webinar - Risky Business: How to Balance Innovation & Risk in Big DataWebinar - Risky Business: How to Balance Innovation & Risk in Big Data
Webinar - Risky Business: How to Balance Innovation & Risk in Big Data
 
P6 analytics producing meaningful results in P6 analytics - Oracle Primavera...
P6 analytics producing meaningful results in P6 analytics  - Oracle Primavera...P6 analytics producing meaningful results in P6 analytics  - Oracle Primavera...
P6 analytics producing meaningful results in P6 analytics - Oracle Primavera...
 
4.4 yasal haklar, kamu
4.4 yasal haklar, kamu4.4 yasal haklar, kamu
4.4 yasal haklar, kamu
 
1.2.2 sınıflandırma
1.2.2 sınıflandırma1.2.2 sınıflandırma
1.2.2 sınıflandırma
 
6.4.4.problem davranışların azaltılması
6.4.4.problem davranışların azaltılması6.4.4.problem davranışların azaltılması
6.4.4.problem davranışların azaltılması
 
Software Proposal Portal Inc.
Software Proposal Portal Inc.Software Proposal Portal Inc.
Software Proposal Portal Inc.
 
J1103035766
J1103035766J1103035766
J1103035766
 
G013144149
G013144149G013144149
G013144149
 
C013112225
C013112225C013112225
C013112225
 
D017612529
D017612529D017612529
D017612529
 
I01245562
I01245562I01245562
I01245562
 
Y01226152157
Y01226152157Y01226152157
Y01226152157
 
H1103034350
H1103034350H1103034350
H1103034350
 
B1802030511
B1802030511B1802030511
B1802030511
 
An Improved Phase Disposition Pulse Width Modulation (PDPWM) For a Modular Mu...
An Improved Phase Disposition Pulse Width Modulation (PDPWM) For a Modular Mu...An Improved Phase Disposition Pulse Width Modulation (PDPWM) For a Modular Mu...
An Improved Phase Disposition Pulse Width Modulation (PDPWM) For a Modular Mu...
 

Similar to H1303024956

Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...IJSRD
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3POOJA UDAYAN
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET Journal
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Schedulingijtsrd
 
76 s201905
76 s20190576 s201905
76 s201905IJRAT
 
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...IRJET Journal
 
Project Management Skills unit-4 Notes
Project Management Skills unit-4 NotesProject Management Skills unit-4 Notes
Project Management Skills unit-4 NotesSamarthVarpe
 
Efficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential ProjectEfficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential ProjectIJERA Editor
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
 
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...IRJET Journal
 
Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...write31
 
Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...write4
 
Running Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docx
Running Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docxRunning Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docx
Running Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docxtodd581
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.pptDejeneTsegaye6
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptpisal3
 
Project mangement part 1
Project mangement part 1Project mangement part 1
Project mangement part 1ghulam MUSTAFA
 
1-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp011-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp01Amy Roman
 
1.7 project management
1.7 project management1.7 project management
1.7 project managementexemplar2401
 
Good scheduling practice
Good scheduling practiceGood scheduling practice
Good scheduling practicekrunalchem
 

Similar to H1303024956 (20)

Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Scheduling
 
76 s201905
76 s20190576 s201905
76 s201905
 
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
 
Project Management Skills unit-4 Notes
Project Management Skills unit-4 NotesProject Management Skills unit-4 Notes
Project Management Skills unit-4 Notes
 
Efficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential ProjectEfficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential Project
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
 
Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...
 
Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...Harvard University Theories Tools and Techiques in Project Managagement Prese...
Harvard University Theories Tools and Techiques in Project Managagement Prese...
 
Running Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docx
Running Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docxRunning Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docx
Running Head PROJECT MANAGEMENT METHODOLOGIES & TOOLS1PROJE.docx
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.ppt
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
 
Project mangement part 1
Project mangement part 1Project mangement part 1
Project mangement part 1
 
1-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp011-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp01
 
1.7 project management
1.7 project management1.7 project management
1.7 project management
 
Project Management
Project ManagementProject Management
Project Management
 
Good scheduling practice
Good scheduling practiceGood scheduling practice
Good scheduling practice
 

More from IOSR Journals (20)

A011140104
A011140104A011140104
A011140104
 
M0111397100
M0111397100M0111397100
M0111397100
 
L011138596
L011138596L011138596
L011138596
 
K011138084
K011138084K011138084
K011138084
 
J011137479
J011137479J011137479
J011137479
 
I011136673
I011136673I011136673
I011136673
 
G011134454
G011134454G011134454
G011134454
 
H011135565
H011135565H011135565
H011135565
 
F011134043
F011134043F011134043
F011134043
 
E011133639
E011133639E011133639
E011133639
 
D011132635
D011132635D011132635
D011132635
 
C011131925
C011131925C011131925
C011131925
 
B011130918
B011130918B011130918
B011130918
 
A011130108
A011130108A011130108
A011130108
 
I011125160
I011125160I011125160
I011125160
 
H011124050
H011124050H011124050
H011124050
 
G011123539
G011123539G011123539
G011123539
 
F011123134
F011123134F011123134
F011123134
 
E011122530
E011122530E011122530
E011122530
 
D011121524
D011121524D011121524
D011121524
 

Recently uploaded

SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Scott Keck-Warren
 
Snow Chain-Integrated Tire for a Safe Drive on Winter Roads
Snow Chain-Integrated Tire for a Safe Drive on Winter RoadsSnow Chain-Integrated Tire for a Safe Drive on Winter Roads
Snow Chain-Integrated Tire for a Safe Drive on Winter RoadsHyundai Motor Group
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphNeo4j
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxMaking_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxnull - The Open Security Community
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?XfilesPro
 

Recently uploaded (20)

SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food Manufacturing
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024
 
Snow Chain-Integrated Tire for a Safe Drive on Winter Roads
Snow Chain-Integrated Tire for a Safe Drive on Winter RoadsSnow Chain-Integrated Tire for a Safe Drive on Winter Roads
Snow Chain-Integrated Tire for a Safe Drive on Winter Roads
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxMaking_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?
 

H1303024956

  • 1. IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 13, Issue 3, Ver. II (May- Jun. 2016), PP 49-56 www.iosrjournals.org DOI: 10.9790/1684-1303024956 www.iosrjournals.org 49 | Page Realization on Construction management of residential apartments Ashfaq Ahmed (M.tech), School of Civil Engineering, HINDUSTAN university, chennai - 603103, Tamil Nadu, India; Abstract: Proper planning and scheduling is very important in construction projects for reducing and controlling delays of the project. Substantial amounts of time, money, resources are wasted each year in a construction industry due to improper planning and scheduling. With globalization the construction projects have become vast and complex. Planning of such projects requires huge amount of paperwork, which can be reduced with the help of project planning software. Providing good planning, proper organization, sufficient flow of resources to a project cannot automatically achieve desired result. A warning mechanism must be present which can alert the organization about its possible success and failures throughout the project. The main objectives of this study are to plan, schedule a Residential project with help of primavera software, study the results generated, it is possible to suggest which method is suitable for the selected residential Building project. Also to recommend measures to the organization for enhancing their project planning skills for similar projects in future and provide them with technical problems encountered in their process. This study is mainly done using Primavera P6, project management software. All activities and their sequence of occurrence, duration, resources required and costs involved are studied. The organizational breakdown structure of company and work breakdown structure of the project are noted. This gives an idea about the resources involved and financial aspect of the completed work.“Project management is the application of knowledge, skills, tools and techniques to project activities to meet the project Requirements Keywords: Planning, Scheduling, budgeting, Project Planning Software, Primavera I. Introduction Construction industry is an integral component of a nation’s infrastructure and industrial growth. Even though construction industry is the second largest industry in India, the growth of this industry has been differential across the nation. The rural regions need tools for economic development, land use and environment planning to cope with the status of development in urban areas. The time available to achieve this goal is shrinking. Here arises the need for effective project management. Many issues are being faced by construction industry that must be taken care of. They include time and cost overruns due to inadequate project formulation, poor planning for implementation, lack of proper contract planning and management and lack of proper management during execution. It has been estimated by analysts that average cost of a project goes up by 30 percentage compared to the budgeted cost. Observations show that proper skilful management is imperative for the timely completion of the project within estimated budget and with allocated resources. Projects with good planning, adequate organizational machinery and sufficient flow of resources cannot automatically achieve the desired result. There must be some warning mechanism, which can alert the organization about its possible success and failures, off and on. Project monitoring is the process of collecting, recording, and reporting information concerning project performance that project manager and others wish to know. Monitoring involves watching the progress of the project against time, resources and performance schedule during execution of the project and identifying lagging areas requiring timely attention and action whereas project controlling uses data from monitor activity to bring actual performance to planned performance. The main objectives of this study are: 1. To suggest the importance and purpose of Planning the construction work. 2. To suggest guidelines to contractors for Scheduling the project. 3. To reduce ideal in construction process of residential building. 4. To suggest a layout for updating the schedule. 5. To suggest effective budgeting method. This study is mainly done using Primavera P6, project management software. All activities and their sequence of occurrence, duration, resources required and costs involved are studied. The organizational breakdown structure of company and work breakdown structure of the project are noted. This gives an idea about the resources involved and financial aspect of the completed work.“Project management is the application of knowledge, skills, tools and techniques to project activities to meet the project Requirements.
  • 2. Realization on Construction management of residential apartments DOI: 10.9790/1684-1303024956 www.iosrjournals.org 50 | Page Plan.-During the planning stage of a project schedule, thecontractor lays out all project elements to create a time-based graphical representation of the project scope. The planning stage includes: • Defining objectives and scope of work. • Identifying milestones (contractual dates, benchmarks). • Developing work breakdown structures (what and where). • Developing an organization breakdown structure (who). • Creating activities (when and where). • Creating relationships (interfaces, dependencies, network). • Identifying a critical path. • Assigning resources (personnel, equipment, or material). • Performing risk analysis. • Refining schedule as needed. • Establishing the baseline schedule. Perform. This state occurs after the schedule has been planned,adopted, and executed. The perform stage includes: • Updating the schedule on a regular basis. • Updating progress. • Incorporating updates or revisions, including project delays. • Communicating status to team and management. Monitor. During this stage, the schedule is most beneficial topredict the outcome of the project. Monitor (also referred to as controlling) includes: • Regularly analyzing the schedule based on special provisions and Standard Specifications requirements. • Analyzing resource productivity. • Analyzing cost usage. • Analyze time extensions. • Comparing different schedules to find changes to key elements such as: ▫ Planned duration versus actual duration ▫ Remaining duration ▫ As-built dates (start and finish) ▫ Descriptions ▫ Changes to logical relationships • Evaluating performance (earned value techniques). • Identifying trends. • Developing forecasts. Modify. This stage includes: • Incorporating approved change orders. • Performing time impact analysis for delays. • Identifying recovery plan (fast-tracking, modifying logic). • Communicating new direction to team and management. II. Methodology The scope of work was divided into the following steps:  Study areacharacteristics.  Preparing actual schedule for the project in primavera.  Identifyingtheconstraintsinthatproject.  Reducing the constraints which causes delay and prepare new schedule.  Optimize the labour resources to reduce the cost of theproject. Preparing Actual Schedule forthe Project in Primavera Actual schedule preparation process starts with the collection of data like project start date, activities involved in the construction of a G+7 apartment with stilt, activities sequences, duration taken for each and every activities, resources needed for each and every activities and its amount, cost spent for each and every activities. The collected data are entered in the software and the relations between the activities are given as per its sequence ofactivities collected.The process ofscheduling in primavera for the actual progress of work
  • 3. Realization on Construction management of residential apartments DOI: 10.9790/1684-1303024956 www.iosrjournals.org 51 | Page is shown in Figure 1, 2, 3, 4 .This actual schedule and report is considered as a base schedule for this project. Figure 1. Actual Schedule Part(i). Figure 2. Actual Schedule Part (ii). Figure 3. Actual Schedule Part (iii).
  • 4. Realization on Construction management of residential apartments DOI: 10.9790/1684-1303024956 www.iosrjournals.org 52 | Page Figure 4. Actual Schedule Part (iv). The root causes for the long durationare,  No parallel activities were done.  Longest criticalpath.  Lackofresources. These three are the reasons for the delay of the project and due to the interdependencies of time and cost; these causes are also responsible for the cost overrun of the project. Measures Taken to Reduce the Time Constraints Constraints causing the time delay have to be reduced. The techniques used to reduce these constraints are, • Interconnecting activities properly. • Increasing the resources. Budgeting the project A budget is a quantitative expression of a plan for defined period of time. It may include planned sales volumes and revenues, resource quantities, costs and expenses, assets, liabilities and cash flows. It expresses strategic plans of business units, organizations, activities or events in measurable terms. Budget helps to aid the planning of actual operations by forcing managers to consider how the conditions might change and what steps should be taken now and by encouraging managers to consider problems before they arise. It also helps co-ordinate the activities of the organization by compelling managers to examine relationships between their own operation and those of other departments III. Results and Discussions Modified Schedule 1 -Interconnecting Activities Properly The connection of the activities plays a major role in the time controlling of the project. Connecting activities should be carefully done which is considerably resulting in the project success. The constraints of having longest critical path can be reduced by means of doing activities parallel. These parallel activities can be done in the prima- vera software by differentiating relationship between the activities. Report obtained from the modified schedule 1 gives the result of interconnecting activities properly. This interconnecting activity shows a considerable result in the time taken for completion of the project. The time dif- ference taken for the completion of the project between the original schedule and modified schedule 1 is five months. Modified Schedule 2 Increasing Resources For doing every activity in the construction process, sufficient amount of resources is required. Resourcesplaya vital role in the project for the successful completion of all the activities on time. Time delay caused in a single activity will be carried over to the subsequent activities. This delay of each activity is due to the insufficient resources. Therefore, it is necessary to provide sufficient amount of resources like men, material and equipment to reducethe time taken for the construction of the project. In this residential apartment, the shuttering material and workmen are insufficient. Therefore the activities of con- structing structural elements of columns in each floor take four sets of activities. Single set of activities consists of rein- forcing, shuttering, concreting and de-shuttering. Therefore increasing the resources will result in reducing the
  • 5. Realization on Construction management of residential apartments DOI: 10.9790/1684-1303024956 www.iosrjournals.org 53 | Page repetition of that sets of activities, which results in reducing the delay in the project. In this, the resources have been increased twice and the schedule was prepared in the primavera. These two measures can be done by means of proper planning and scheduling of the project. The corrective measures of proper interconnecting activities and increas- ing the resources is incorporated in the new schedule of that residential project. The schedule made by increasing the resources twice with the interconnection of activities properly completes two months before from the project completion time of the modified schedule 1 and it completes seven months before from the original schedule of the residential apartment project. Figure 5. S-curve analysis. Lower productivity of machinery Productivity is an average measure of the efficiency of production. It can be expressed as the ratio of output to inputs used in the production process, i.e. output per unit of input. When all outputs and inputs are included in the productivity measure it is called total productivity. Outputs and inputs are defined in the total productivity measure as their economic values. The value of outputs minus the value of inputs is a measure of the income generated in a production process. It is a measure of total efficiency of a production process and as such the objective to be maximized in production process Figure 6. running hours for equipments 0 5000 10000 15000 1 2 3 4 Running Hours Actual Running Hours Planned
  • 6. Realization on Construction management of residential apartments DOI: 10.9790/1684-1303024956 www.iosrjournals.org 54 | Page Figure 7. total machine months variation. Figure 8.variation for equipment Figure 9.. comparison of equipments running hours 0 20 40 60 Diesel Generator (1) BOBCAT Effeciency (2) AIR Compressor (3) Concrete Pump (4) Total Machine Month Actual Total Machine Month Planned Total Machine Month Diesel Generator (1) BOBCAT Effeciency (2) AIR Compressor (3) Concrete Pump (4) Running Hours 1 2 3 4
  • 7. Realization on Construction management of residential apartments DOI: 10.9790/1684-1303024956 www.iosrjournals.org 55 | Page Figure 10. amount for each equipment Figure 11. comparison of rate of diesel Figure 12. milage for each equipment Figure 13. cumulative hours comparision for equipments IV. Conclusion Schedule made by using techniques that reduce the constraints helps for the project to complete earlier of five to seven months from the actual base schedule of the project and thereby increase the profit outcome from the project. Further, with the management on the labour resource of skilled, unskilled male worker and unskilled female worker in the construction activities, the cost spent on the labour resources reduces by 5% of the actual cost spent on the labour resources. Using a soft- ware helps to manage the work easily and it reduces the information constraints between the management and the site members which greatly contribute to the project success. This study concludes that by using the Primavera a time period of 4 months from the actual base schedule of the project was saved and also helps to prevent the cost overrun, thereby ensuring the successful completion of the project. It helps to manage the work easily and also helps to avoid constraints or risks that will delay the project by interconnecting and parallelizing the activities and mobilization of the resources from time to time for successful completion of the project within the estimated time Amount 1 2 3 4 Rate of Diesel (Rs.) 1 2 3 4 Litres/hr 1 2 3 Actual Cum/hr 1 2 3
  • 8. Realization on Construction management of residential apartments DOI: 10.9790/1684-1303024956 www.iosrjournals.org 56 | Page Budget is prepared for each and every activity by allocating the resources to the activities. Budgeted project labor, Non labor, Expense, Material and total cost of all theactivities are calculated. The total budgeted cost of the project was Rs16, 556,504.80. Activities are to be tracked as per the project duration from January 1st to April 4nd and actual costs for all the activities in that duration are updated. Total actual cost within this duration was Rs.21,02,789.39. References [1]. Subramani.T and Chinnadurai.K (2015), Construction Management and Scheduling of Residential Building Using Primavera,International JournalofApplication or Innovation in Engineering & Management (IJAIEM), 4(5), 188-198. [2]. Prabhat Kumar Sinha, Abusalah Mohamed Alakhdar Abdlaziz, R.K. Pandey, Ashok Tripathi and Anshuman(2013), Time and schedule management using Primavera, International journal of Civil engineering and technology (IJCIET), 4(5), 78-87. [3]. Satinder Chopra and Arvind Dewangan (2014), Time and schedule management by using primavera P6: Significance of activity ID and description, International Journal of Innovative Research in Science, Engineering and Technology, 3(7), 15022-15027. [4]. X. Regina Mary and V. Rathinakumar (2015), Reducing Construction Constraints using Primavera, Indian Journal of Science and Technology, 8(14), 1-7. [5]. Unmesh. Y. Polekar and Rohit. R. Salgude (2015), Planning, Scheduling and Tracking of a residential Project using Primavera Software, International Journal of Advance Research in Computer Science and Management Studies, 3(5), 227-236. [6]. A.A.Lakade, A.K.Gupta and D.B.Desai (2010), A Project Management Approach Using Primavera In Construction Industry, Journal of Mechanical and Civil Engineering, 15(2), 21-24 [7]. Pethe Sarang S and Pramila Adavi (2012), Application of primavera in construction industry, International Journal of Advanced Technology in Civil Engineering, 1(3), 16-17. [8]. Andrew Fernans Tom and Sachin Paul (2013), Project Monitoring and Control using Primavera, International Journal of Innovative Research in Science, Engineering and Technology, 2(3), 762-771. [9]. Reddy. B. S. K, Nagaraju SK, Salman. MD (2015), Astudy on optimisation of resources for multiple projects by using primavera, Journal of Engineering Science and Technology, 10(2), 235-248.