SlideShare a Scribd company logo
1 of 19
Download to read offline
DESIGN OF AN INTZE TANK
COURSE CODE: CE - 4102
COURSE TITLE: STRUCTURAL ANALYSIS AND DESIGN -III SESSIONAL
Designed By:
SUMAN JYOTI
Student Id: 191125
Department of Civil Engineering
Dedicated To:
TRIBHUVAN UNIVERSITY
Kritipur, Nepal
KATHMANDU UNIVERSITY
Banepa, Nepal
DEPARTMENT OF CIVIL ENGINEERING
DHAKA UNIVERSITY OF ENGINEERING & TECHNOLOGY, GAZIPUR
Design an Intze tank from following data:
Future population = 3175
Per capita demand = 130 litre/day
Height of the cylindrical wall = 11 ft.
Concrete strength, f´c = 5030 psi
Steel strength, fy = 60 ksi = 415
Mpa
Solution:
1. GEOMETRIC DESIGN:
Total quantity of water = 3175 × 130 = 412750 lit/day = 412.75 m3
/ day
= 14564.94 ft3
/ day
Let, the diameter of the tank = D in ft.
Now, the volume of the tank = capacity of the tank
 14564.94 =
𝜋𝐷2
4
× 11ft
 D = 41.56 ft ≈ 42 ft
1.1 Dimension and Illustration of Water Tank:
Figure: Dimension Proportioning of Intz Water Tank
2. STRUCTURAL DESIGN:
2.1 Materials Property:
2.1.1 Permissible concrete stresses to resistance to cracking:
Direct tension, fc = 5√𝑓′𝑐 psi = 5√5030 psi psi = 354.61 psi = 2.445 MPa
Tension due to bending, fc = 12√𝑓′𝑐 psi = 12√5030= 851.06 psi = 5.87 MPa
Shear = √f′c psi = 2√5030 psi =141.85 psi = 0.978 MPa
Direct compression, fc = 0.25 f ′c psi = 1257.5 psi = 8.67 MPa
Compression due to bending, fc = 0.45 fc’ psi = 2263.5 psi = 15.06 MPa
Modular ratio, n =
29∗106
57000√f′c
=
29∗106
57000√5030
= 7.17
2.1.2 Allowable tensile strength of reinforcement (According to BNBC):
fs= 0.4 fy = 0.4 × 60 = 24 ksi =165.5 Mpa
2.2 Design of Top Spherical Dome:
2.2.1 Allowable tensile strength of reinforcement (According to BNBC):
Radius of top spherical dome = R
Let, r be the radius of the dome
So, h (2r-h) = R2
or, 5.25 × (2r – 5.25) = 212
or, r = 44.625 ft = 13.6 m
Now, sin θ = 21/ 44.625
θ = 28.07 º < 51.8 º (so, compression dome)
cos θ = 0.882
2.2.2 Load calculation:
Let, the thickness of dome slab = 100 mm
Self-weight = 0.1 x 25 = 2.5 kN/m2
Live load = 1.5 kN/m2
So, Total Distributed Load, w = 4 kN/m2
r
r-h
R = 21ft
h = 5.25 ft
R
2.2.3 Check for stresses:
Let, the thickness of dome
Hoop stress at any angle θ, =
𝑤𝑟
𝑡
(
cos2 θ+cosθ−1
1+𝑐𝑜𝑠θ
)
Maximum hoop stress will occur at θ = 0,
So, Hoop stress =
𝑤𝑟
𝑡
×
1
2
=
4∗1000∗13.6
0.1∗ 2
= 0.272× 106
N/m2
= 0.272 N/mm2
< 5 kN/mm2
( Ok )
Meridional stress at any angle θ, =
𝑤𝑟
𝑡
(
1
1+𝑐𝑜𝑠θ
)
Maximum meridional stress will occur at θ = 28.07 º = Ø,
So, Meridional stress =
𝑤𝑟
𝑡
×
1
1+𝑐𝑜𝑠𝜃
=
4∗1000∗13.6
0.1
×
1
1+0.882
= 0.29× 106
N/m2
= 0.29 N/mm2
< 5 kN/mm2
( Ok )
2.2.4 Area of reinforcement calculation:
Both stresses are within safe limit, hence a minimum reinforcement may be
provided.
Ast = 0.002bt
= 0.002×1000×100
= 200 mm2
per meter (both direction)
Use 8 mm dia. bar @ 200 mm c/c (both direction)
2.2.5 Detailing of reinforcements:
8 mm @ 200 mm c/c
at mid of the slab thickness
100 mm thick dome slab
2.3 Design of Top Ring Beam:
2.3.1 Load calculation:
The horizontal component of Meridional thrust, P = T Cos φ
P = 0.29 × 100 ×1000 ×(0.882) = 25578 N
Total tension tending to rupture the ring beam per meter length of its
circumference,
= P × D/2
= 25578 × (12.8/2)
= 163700 N
2.3.2 Area of reinforcement calculation:
Since steel in contact with water then fs = 165.5 N/mm2
[fs = 0.4fy ]
So, Area of reinforcement required,
Ast =
Tensile force
Allowable stress of steel
=
163700
165.5
= 990.12 mm2
Using 16 mm dia bar (as = 200.1 mm2
), required bar=
990.12
200.1
= 4.94 ≈ 5 nos.
2.3.3 Size of beam calculation:
Equivalent area of the composite section = A + ( n-1 ) Ast
= A + ( 7.17-1 ) × 5 × 200.1
= A + 6174
Take the allowable stress to the composite section is 1.2 kN/mm2
.
or, 1.2 =
163700
A + 6174
or, A = 130242 mm2
Let, beam width is, b = 500 mm and the depth, d = 260.48 ≈ 260 mm
2.3.4 Minimum reinforcement calculation:
Using (#3) 10 mm dia bar, then spacing, Sv =
2.5 As∗fy
b
As = 2 × 0.11 in2
( for two legs )
So, Spacing, Sv =
2.5∗78.54∗413.7
260
= 312.42 mm ≈ 300 mm c/c
2.3.5 Detailing of reinforcements:
2.4 Design of Cylindrical Wall:
2.4.1 Load Calculation:
Let, joint condition is simple joint, i.e., cylindrical wall is free to move at top
and bottom.
Maximum hoop tension at the base of the wall is,
T = γh
𝐷
2
= 10000 × 3.534 ×
12.8
2
[Using, γw = 10000 N/m3
]
T = 226176 N
2.4.2 Area of reinforcement calculation:
Area of the required reinforcement, Ast =
226176
165.5
= 1366.6 mm2
Area of reinforcement on each face = 1366.6/2 = 683.3 mm2
≈ 684 mm2
Using 16 mm dia. bar, the spacing =
1000 ∗ 201
684
= 293.86 mm ≈ 280 mm c/c
Cut 50% bar at a depth of 1.8 m below the top cylinder than base,
So, spacing is = 560 mm c/c
2.4.3 Thickness of cylindrical wall calculation:
Equivalent area of composite section = t×103
+ (7.17–1) × (
1000
280
×2×201)
= 1000t + 8858.35
Since the tension is direct then permissible direct tensile stress = 1.2 N/mm2
or, 1.2 =
226176
1000𝑡+8858.35
or, t = 179.62 mm ≈ 180 mm
Since hoop tension is smaller at the top of cylinder than base,
So, use thickness 150 mm at the top of cylindrical wall.
2.4.4 Distribution of reinforcement calculation:
Average thickness of the wall slab =
180+150
2
= 165 mm
Area of steel required is = 0.0022 × 1000 × 165 = 330 mm2
Using 12 mm bar, the spacing =
113∗1000
330
= 342.4 mm c/c ≈ 300 mm c/c
2.4.5 Detailing of reinforcement:
2.5 Design of bottom ring beam:
2.5.1 Load Calculation:
Load due to top dome = Area of slab x Meridional stress x sin φ
= 100 x 1000 x 0.29 x sin28.07º
= 13646 N /m
Load due to top ring beam = 0.26 x (0.5 - 0.15) x 25000
= 2275 N/m
Load due to cylindrical wall = 0.165 x 3.35 x 25000
= 13819 N /m
Assume, beam size, 900 mm x 500 mm
Self-weight of beam = 0.5 x (0.9 – 0.5) x 25000 = 5000 N /m
Total w1= 34740 N/ m
Horizontal thrust due to vertical load = w1 tan β
= 34740 x tan 45º = 34740 N/ m
Hoop tension due to vertical load, H1 =
34740∗12.8
2
= 222336 N
Hoop tension due to water, H2 = 10000 x 3.35 x 0.6 x 12.8/2 = 128640 N
Total hoop tension, H = 222336 + 128640 = 350976 N
2.5.2 Area of Reinforcement Calculation:
Area of the required reinforcement, Ast =
350976
165.5
= 2120.7 mm2
Using 16 mm dia bar, Nos. of bar =
2120.7
201
= 10.55 ≈ 11 Nos.
2.5.3 Check for Tensile stresses:
Maximum tensile stress =
350976
900∗500+(7.17−1)∗11∗201
= 0.0006 N/mm2
<1.2 N/mm2
( Ok )
2.5.4 Shear reinforcement calculation:
Using 10mm dia bar Spacing, Sv =
2.5 𝐴𝑠𝑣 𝑓𝑦
𝑏
=
2.5∗ 78.54∗4∗165.5
500
= 260 mm c/c ≈ 250 mm c/c
2.5.5 Detailing of reinforcements:
Fig. Detailing of bottom ring beam
2.6 Design of conical dome:
2.6.1 Load Calculation:
Average diameter of Conical dome = 10.4 m
Average depth of water = 3.35 + 2.4/2 = 4.55m
Assume, Thickness of slab 400 mm
Self-weight of slab = (π x 10.8 x 3.39) x 0.4 x 25000 = 1150203 N
Weight of water = (π x 10.8 x 4.55 x 2.4) x 10000 = 370508 N
Load from Top dome, cylindrical wall, bottom ring beam, = 34740× π×10.4
= 370508 N
Total load on Conical dome =1150203+ 370508 + 370508
= 1891219 N
Load at per meter of conical dome base =
1891219
3.1416∗4.54
= 132598 N/m
Meridional thrust, T =
132598
𝑐𝑜𝑠45
= 187522 N
Meridional stress =
187522
1000∗400
= 0.5 N/mm2 < 5.0 N/mm2
, So Safe.
2.6.2 Hoop tension calculation:
General expression for hoop tension
Diameter of conical dome at h m height from base, Dh = 8 + 2 × 2.4/2.4 × h
= 8 + 2h
Intensity of water pressure at height h from base, p
or, p = (5.76 – h) x 10000 x 1 = (57600 – 10000h) N/m
Weight of Conical dome, w1 = 0.4 x 1 x 25000 = 10000 N/m
Hoop tension at any height h, = (𝑝𝑠𝑖𝑛β+ w1 tanβ) ×
8 + 2h
2
= {(57600 – 10000h) sin45 + 10000 tan45)} ×
8 + 2h
2
Maximum Hoop tension (at h = 2.44) = 216056 N
2.6.3 Area of reinforcement calculation:
Area of Reinforcement Calculation, Ast =
216056
165.5
= 1306mm2
Area of steel on each face =
1306
2
= 653 mm2
Using 16 mm dia. bar, Spacing =
201∗1000
653
= 307.8 mm C/C ≈ 300 mm C/C
Check for maximum tensile stress-
=
216056
400∗ 1000 +(12.8 − 1)∗(
1000
100
∗201∗2)
= 0.00001 N/mm2
< 1.2 N/mm2
(Ok)
2.6.4 Distribution Reinforcement Calculation:
Assuming distribution bar as 0.18 %
Ast = 0.0018× 400 × 1000 = 720 mm2
Area of steel on each face = 720 /2 = 360 mm2
Using 12 mm bar, spacing =
113.1∗1000
360
= 314.2 mm ≈ 300 m c/c
2.6.5 Area of reinforcement for B.M.
The conical dome also acts as a slab,
Load on slab, W =
1150203 + 370508
3.1414 ∗8
= 60507.16 N/m
Load on 1m wide and 3m spanned slab, W = 60507.16 N/m
So, Maximum Bending moment =
60507.16 ∗3
12
= 15126.8 N-m
Let, main bar Ø16mm, then effective depth = 400 – 40 -16/2 = 352 mm
Ast =
15126.8∗1000
115 ∗ 352 ∗ 0.866
≈ 430 mm2
Use #5 (16mm) bar, Spacing =
201.1∗1000
430
= 467.67 mm C/C ≈ 400 mm C/C
Since flexural reinforcing bar spacing = 400 mm C/C,
Which will also act as distribution bar as well as main bar.
Use #4 (12mm) bar @ 400 mm C/C as distribution bar at the top of the slab.
2.6.6 Reinforcement Detailing
Fig. Detailing of conical dome slab
2.7 Design of bottom spherical dome:
2.7.1 Load Calculation:
Assume, slab thickness = 400 mm
Let, Radius of dome rb,
rb2 = (rb- 1.6)2 + 4.0 2
∴ rb = 5.8 m
or, sin φ =
4
5.8
= 0.6897
∴ φ = 43.60 < 51.8º So Compression dome
∴ cos φ = 0.724
Self-weight of dome = (2π rb × h) × t × γc = 2π x 5.8 x 1.6 x 0.4 x 25000
= 583080 N
Volume of water above conical dome, V = πR2
hwater – 1
3
π x h2
x (3 x rb – h)
= π × 42
× 4.55 – 1
3
π × 1.62
× (3 × 5.8 – 1.6) = 186.35 m3
Weight of water = 186.35 x 10000 = 1863508 N
Total weight = 583080 + 1863508 = 2446588 N
2.7.2 Check for stress:
Load per unit area w =
2446588
2π x 5.8 x 1.6
= 41960 N/m2
∴ Maximum Hoop stress =
wr
𝑡
×
1
2
=
41960 x 5.8
0.4
×
1
2
= 0.304 x 106
N/m2
= 0.304 N/mm2
< 5 N/mm2
∴ Maximum Meridional stress =
wr
𝑡
×
1
(1+𝑐𝑜𝑠 φ)
=
41960 x 5.8
0.4
×
1
(1+0.724)
= 0.353 x 106
N/m2
= 0.353 N/mm2
< 5 N/mm2
2.7.3 Area of reinforcement calculation:
ρ = 0.18 %
Area of the required reinforcement, Ast =
0.18
100
x 400 x 1000 = 720 mm2
Using #4 (12mm) bar, Spacing =
113.1∗1000
720
= 157.08 mm c/c ≈ 150 mm c/c
in both directions.
R = 4 m
h = 1.6 m
r-h
rb
2.7.4 Details of reinforcement:
Fig: Detailing of Bottom Spherical Dome.
2.8 Design of circular bottom beam:
2.8.1 Load Calculation:
Meridional thrust from conical dome, T = 187522 N/m
Inward thrust from conical dome = 187522× sin 45º = 132598.07 N/m
Meridional thrust from bottom spherical dome = 0.353 × 400 × 1000
= 141200 N/ m
Outward thrust from bottom spherical dome = 141200 × Cos 43.6°
= 102253 N/m
So, Net inward thrust, P = 132598.07 – 102253
= 30345 N/m (Compressive)
Hoop compressive force in Beam =
𝑃𝐷
2
=
30345∗
26.25
3.28
2
= 121380 N
Assuming, Beam size = 450 mm × 800 mm
∴ Hoop stress =
121380
450∗800
= 0.3372 N/mm2
< 5 N/mm2
Vertical load from conical dome = 132598 N/m (Computed earlier)
12 mm @ 150 mm c/c
at mid of the slab thickness
00 mm thick dome slab
Vertical load from bottom spherical dome,
= 2446588/ (π x 8) = 97346.6 N/m
Total Vertical load on beam = 132598 + 97346.6 = 229945 N/m
Self-weight of beam = 0.45 × 0.8 × 25000 = 9000 N/ m
∴ The design load for the beam, 𝜔 = 229945 + 9000 = 238945 N/m
2.8.2 Moment Calculation:
Load on per meter beam, w = 238945 N/m
It is proposed to support the beam by 6 Columns.
Maximum (-ve) Bending moment at support = k1wR2
×
1
3
π
M1 = 0.089 × 238945 × 42
×
1
3
π = 356317 N- m
Maximum (+ve) Bending moment at mid span = k2wR2
×
1
3
π
= 0.045 × 238945 × 42
×
1
3
π = 180160 N- m
Maximum (-ve) Twisting moment (T) at 12.75º from support = k3wR2
×
1
3
π
= 0.009 × 238945 × 42
×
1
3
π = 36032 N- m
2.8.3 Shear Calculation:
Shear force at support section, V1= w ×
2𝜋𝑅
𝑁𝑜.𝑜𝑓 𝐶𝑜𝑙𝑢𝑚𝑛
×
1
2
= 238945 ×
2𝜋∗4
6
×
1
2
= 500445 N
Shear force at the point of maximum torsion,
V2 = 500445 – 500445 ×
12.75
30
= 287755.88 N ( rough, 360/6 column × 2 )
2.8.4 Design of support section (For Moment):
M = 356317 N- m, V1= 500445 N
Effective depth, d = √
Moment 𝑖𝑛 𝑁−𝑚𝑚2
0.5∗𝑓𝑐∗𝑗∗𝑘∗𝑏
deff = √
356317 ∗1000
0.5∗15.06∗0.866∗0.403∗450
= 548.9 mm
Let clear cover = 40 mm, and 2 layers of main bar
Ø of main bar = 25 mm & stirrup = 10 mm
So, Actual effective depth, d = 800 – 40 – 10 – (25 + 25/2)
= 712.5 mm > 548.9 mm, Safe (ok).
Area of Reinforcement =
356317 × 1000
165.5 × 0.866 × 712.5
= 3490 mm2
Use 20 mm Ø bar. So, Nos. of bars = 3490/314.2 = 11.10 ≈ 12 Nos.
2.8.5 Design of support section (For Shear):
Developed shear stress, 𝜏v =
𝑉
𝑏𝑑
=
500445
450 ∗712.5
∴ 𝜏v = 1.56 N/mm2
Maximum allowable shear stress, 𝜏allow = 3.4 √𝑓𝑐
′
∴ 𝜏allow = 3.4 √5030 = 241.13 psi = 1.66 N/mm2
Since 𝜏v < 𝜏allow, this section is safe for shear.,
Here, Percentage of steel ratio ρ =
12.5
30
= 0.417 %
So, allowable concrete shear stress, 𝜏c = 1.1 √𝑓𝑐
′
𝜏c = 1.1 √5030 = 78.01 psi = 0.538 N/mm2
Since 𝜏v > 𝜏c Shear reinforcement is required.
Here, Allowable concrete shear force, Vc = 𝜏c × bd
= 0.538 × 450 × 712.5 = 172496.25 N
Use #3 (10mm) bar 6-legged bar as stirrup, Spacing,
S =
𝐴𝑠𝑣∗𝑓𝑠𝑣∗𝑑
𝑉−𝑉𝑐
=
(6∗78.54) × 210 × 712.5
500445 −172496.25
= 215 mm C/C ≈ 200 mm C/C
2.8.6 Design for torsion:
The maximum torsion occurs at the point of contraflexure
Equivalent moment, Me = M + MT
At point of contraflexure M = 0
And, we know, MT =
𝑇
1.7
(1 +
𝐷
𝐵
)
=
36032∗1000
1.7
(1 +
800
450
) = 175.54 × 106
N-mm
So, the equivalent moment, Me = 58.87 × 106
N-mm
Area of Reinforcement =
58.87 × 106
165.5 x 0.866 x 712.5
= 576.55 mm2
Use 16 mm Ø bar. So, Nos. of bars = 576.55/201.1 = 2.87 ≈ 4
The number of bars at the point of contraflexure is more than the 3, So no
additional bars are required.
Equivalent shear, Ve = V +1.6
𝑇
𝑏
= 500445 + 1.6 ×
36032
450
= 500573 N
Equivalent nominal shear stress, 𝜏ve =
500573
450∗712.5
= 1.56 N/mm2
< 1.66 N/mm2
Let, 10mm Ø bar with 6 legged will be used as stirrup,
so, Asv = 6 × 78.54 = 471.2 mm2
Allowable concrete shear force, Vc = 0.538 × 450 × 712.5 = 172496.25 N
(i) Spacing considering torque and shear force at point of contraflexure
Asv =
𝑇∗𝑆𝑣
𝑏1 ∗ 𝑑1 ∗ 𝑓𝑠𝑣
+
𝑉2∗𝑆𝑣
2.5 𝑑1 ∗𝑓𝑠𝑣
471.2 =
36032∗1000∗𝑆𝑣
384 ∗ 719 ∗210
+
287755.88 ∗𝑆𝑣
2.5 ∗719 ∗ 210
∴ 𝑆v = 340 ≈ 300 mm c/c
b1 = 450 – 2×25 – 2×8
= 384 mm
d1 = 800 – 40 – 25 – 2 × 8
= 719 mm
(ii) Spacing considering equivalent shear force
𝐴vs =
(𝑉𝑒−𝑉𝑐)𝑆𝑣
𝑓𝑠𝑣∗𝑑
or, Sv =
𝐴𝑠𝑣∗𝑓𝑠𝑣∗𝑑
𝑉𝑒−𝑉𝑐
=
471.2 ∗ 210∗712.5
(500573 − 172496.25 )
= 214.9 mm c/c ≈ 200 mm c/c
Hence provide 10 mm-6-legged stirrup at 200 mm c/c from column face to
the point of contraflexure.
2.8.7 Design of mid-section:
Effective depth, d = 712.5 mm
Bending Moment = 180160 N- m
Area of Reinforcement =
180160 × 1000
165.5 × 0.866 × 712.5
= 1764.24 mm2
Use 20 mm Ø bar. So, Nos. of bars = 1764.24/314.2 = 5.62 ≈ 6
2.8.8 Detail Drawing:
Fig. Detailing of Circular Bottom Beam
Fig:-Section showing the details reinforcement in bottom circular beam, column and bracing.
Fig:- Details reinforcement of Intze Tank

More Related Content

Similar to Intze Overhead Water Tank Design by Working Stress - IS Method.pdf

Foundation Reinforcement Calcs & Connection Calcs
Foundation Reinforcement Calcs & Connection CalcsFoundation Reinforcement Calcs & Connection Calcs
Foundation Reinforcement Calcs & Connection CalcsMagdel Kotze
 
Design of footing
Design of footingDesign of footing
Design of footingNripeshJha
 
Design and detailing_of_retaining_walls counter fort.تصميم الجدران الاستنادية...
Design and detailing_of_retaining_walls counter fort.تصميم الجدران الاستنادية...Design and detailing_of_retaining_walls counter fort.تصميم الجدران الاستنادية...
Design and detailing_of_retaining_walls counter fort.تصميم الجدران الاستنادية...Dr.youssef hamida
 
Design ppt
Design pptDesign ppt
Design ppttishu001
 
Sums on Rigid Pavement Design
Sums on Rigid Pavement DesignSums on Rigid Pavement Design
Sums on Rigid Pavement DesignArnabKarmakar18
 
final internship ppt.pptx
final internship ppt.pptxfinal internship ppt.pptx
final internship ppt.pptxKiranKr32
 
Isolated column footing
Isolated column footingIsolated column footing
Isolated column footingkamariya keyur
 
Theatre building PPT.pptx
Theatre building PPT.pptxTheatre building PPT.pptx
Theatre building PPT.pptxDivyaprabaN
 
Design of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an AuditoriumDesign of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an AuditoriumIRJET Journal
 
Worked example extract_flat_slabs
Worked example extract_flat_slabsWorked example extract_flat_slabs
Worked example extract_flat_slabsLuan Truong Van
 
Week 9 Lecture Material_watermark.pdf
Week 9 Lecture Material_watermark.pdfWeek 9 Lecture Material_watermark.pdf
Week 9 Lecture Material_watermark.pdfssuser021946
 
Cantilever Retaining Wall
Cantilever Retaining Wall Cantilever Retaining Wall
Cantilever Retaining Wall Harsh Shani
 
Worked example extract_flat_slabs
Worked example extract_flat_slabsWorked example extract_flat_slabs
Worked example extract_flat_slabsluantvconst
 

Similar to Intze Overhead Water Tank Design by Working Stress - IS Method.pdf (20)

Foundation Reinforcement Calcs & Connection Calcs
Foundation Reinforcement Calcs & Connection CalcsFoundation Reinforcement Calcs & Connection Calcs
Foundation Reinforcement Calcs & Connection Calcs
 
Design of footing
Design of footingDesign of footing
Design of footing
 
Design and detailing_of_retaining_walls counter fort.تصميم الجدران الاستنادية...
Design and detailing_of_retaining_walls counter fort.تصميم الجدران الاستنادية...Design and detailing_of_retaining_walls counter fort.تصميم الجدران الاستنادية...
Design and detailing_of_retaining_walls counter fort.تصميم الجدران الاستنادية...
 
Design ppt
Design pptDesign ppt
Design ppt
 
Sums on Rigid Pavement Design
Sums on Rigid Pavement DesignSums on Rigid Pavement Design
Sums on Rigid Pavement Design
 
Isolated Footing
Isolated FootingIsolated Footing
Isolated Footing
 
RCC BMD
RCC BMDRCC BMD
RCC BMD
 
final internship ppt.pptx
final internship ppt.pptxfinal internship ppt.pptx
final internship ppt.pptx
 
Doubly reinforced beam design
Doubly reinforced beam   designDoubly reinforced beam   design
Doubly reinforced beam design
 
Isolated column footing
Isolated column footingIsolated column footing
Isolated column footing
 
Ch 3-a.pdf
Ch 3-a.pdfCh 3-a.pdf
Ch 3-a.pdf
 
Precast driven pile 450 x450
Precast driven pile 450 x450Precast driven pile 450 x450
Precast driven pile 450 x450
 
2 compression
2  compression2  compression
2 compression
 
Theatre building PPT.pptx
Theatre building PPT.pptxTheatre building PPT.pptx
Theatre building PPT.pptx
 
Design of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an AuditoriumDesign of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an Auditorium
 
Worked example extract_flat_slabs
Worked example extract_flat_slabsWorked example extract_flat_slabs
Worked example extract_flat_slabs
 
Week 9 Lecture Material_watermark.pdf
Week 9 Lecture Material_watermark.pdfWeek 9 Lecture Material_watermark.pdf
Week 9 Lecture Material_watermark.pdf
 
Harshal
HarshalHarshal
Harshal
 
Cantilever Retaining Wall
Cantilever Retaining Wall Cantilever Retaining Wall
Cantilever Retaining Wall
 
Worked example extract_flat_slabs
Worked example extract_flat_slabsWorked example extract_flat_slabs
Worked example extract_flat_slabs
 

More from Er. Suman Jyoti

Presentation on Slab, Beam, Column, and Foundation/Footing
Presentation on Slab,  Beam, Column, and Foundation/FootingPresentation on Slab,  Beam, Column, and Foundation/Footing
Presentation on Slab, Beam, Column, and Foundation/FootingEr. Suman Jyoti
 
विकास निर्माण कार्यमा महिलाहरुको सहभागिता.pdf
विकास निर्माण कार्यमा महिलाहरुको सहभागिता.pdfविकास निर्माण कार्यमा महिलाहरुको सहभागिता.pdf
विकास निर्माण कार्यमा महिलाहरुको सहभागिता.pdfEr. Suman Jyoti
 
A Thesis of NUMERICAL SIMULATION OF FLOW THROUGH OPEN CHANNEL WITH SERIES OF ...
A Thesis of NUMERICAL SIMULATION OF FLOW THROUGH OPEN CHANNEL WITH SERIES OF ...A Thesis of NUMERICAL SIMULATION OF FLOW THROUGH OPEN CHANNEL WITH SERIES OF ...
A Thesis of NUMERICAL SIMULATION OF FLOW THROUGH OPEN CHANNEL WITH SERIES OF ...Er. Suman Jyoti
 
A thesis of numerical simulation of flow through open channel with series of ...
A thesis of numerical simulation of flow through open channel with series of ...A thesis of numerical simulation of flow through open channel with series of ...
A thesis of numerical simulation of flow through open channel with series of ...Er. Suman Jyoti
 
Major project report of diploma civil engineering at mamts gothatar to jorpat...
Major project report of diploma civil engineering at mamts gothatar to jorpat...Major project report of diploma civil engineering at mamts gothatar to jorpat...
Major project report of diploma civil engineering at mamts gothatar to jorpat...Er. Suman Jyoti
 
Survey camp report of Madan Ashrit at Kharipati - Bhaktapur! 100 pages
Survey camp report of Madan Ashrit at Kharipati - Bhaktapur! 100 pagesSurvey camp report of Madan Ashrit at Kharipati - Bhaktapur! 100 pages
Survey camp report of Madan Ashrit at Kharipati - Bhaktapur! 100 pagesEr. Suman Jyoti
 
Engineering materials bsc. civil lab 14 report
Engineering materials bsc. civil lab 14 reportEngineering materials bsc. civil lab 14 report
Engineering materials bsc. civil lab 14 reportEr. Suman Jyoti
 
Cement: Properties, uses and types, manufacturing methods, reaction taking pl...
Cement: Properties, uses and types, manufacturing methods, reaction taking pl...Cement: Properties, uses and types, manufacturing methods, reaction taking pl...
Cement: Properties, uses and types, manufacturing methods, reaction taking pl...Er. Suman Jyoti
 
Aggregates, Types, Properties, Sources, Uses and its test by Suman Jyoti
Aggregates, Types, Properties, Sources, Uses and its test by Suman JyotiAggregates, Types, Properties, Sources, Uses and its test by Suman Jyoti
Aggregates, Types, Properties, Sources, Uses and its test by Suman JyotiEr. Suman Jyoti
 
Economics 50 long questions solve by suman jyoti (dhaka university of enginee...
Economics 50 long questions solve by suman jyoti (dhaka university of enginee...Economics 50 long questions solve by suman jyoti (dhaka university of enginee...
Economics 50 long questions solve by suman jyoti (dhaka university of enginee...Er. Suman Jyoti
 
Ielts speaking by suman jyoti 2020/021
Ielts speaking by suman jyoti 2020/021Ielts speaking by suman jyoti 2020/021
Ielts speaking by suman jyoti 2020/021Er. Suman Jyoti
 
Topographic map level transfer to traverse
Topographic map level transfer to traverseTopographic map level transfer to traverse
Topographic map level transfer to traverseEr. Suman Jyoti
 
Topographic map fly levelling 1
Topographic map fly levelling 1Topographic map fly levelling 1
Topographic map fly levelling 1Er. Suman Jyoti
 
Topographic map detailling 1
Topographic map detailling  1Topographic map detailling  1
Topographic map detailling 1Er. Suman Jyoti
 
Topographic map distance and angular measurement 0
Topographic map  distance and angular measurement  0Topographic map  distance and angular measurement  0
Topographic map distance and angular measurement 0Er. Suman Jyoti
 
Road alignment survey 02
Road alignment survey 02Road alignment survey 02
Road alignment survey 02Er. Suman Jyoti
 
Road alignment survey 01
Road alignment survey 01Road alignment survey 01
Road alignment survey 01Er. Suman Jyoti
 

More from Er. Suman Jyoti (20)

Presentation on Slab, Beam, Column, and Foundation/Footing
Presentation on Slab,  Beam, Column, and Foundation/FootingPresentation on Slab,  Beam, Column, and Foundation/Footing
Presentation on Slab, Beam, Column, and Foundation/Footing
 
विकास निर्माण कार्यमा महिलाहरुको सहभागिता.pdf
विकास निर्माण कार्यमा महिलाहरुको सहभागिता.pdfविकास निर्माण कार्यमा महिलाहरुको सहभागिता.pdf
विकास निर्माण कार्यमा महिलाहरुको सहभागिता.pdf
 
A Thesis of NUMERICAL SIMULATION OF FLOW THROUGH OPEN CHANNEL WITH SERIES OF ...
A Thesis of NUMERICAL SIMULATION OF FLOW THROUGH OPEN CHANNEL WITH SERIES OF ...A Thesis of NUMERICAL SIMULATION OF FLOW THROUGH OPEN CHANNEL WITH SERIES OF ...
A Thesis of NUMERICAL SIMULATION OF FLOW THROUGH OPEN CHANNEL WITH SERIES OF ...
 
A thesis of numerical simulation of flow through open channel with series of ...
A thesis of numerical simulation of flow through open channel with series of ...A thesis of numerical simulation of flow through open channel with series of ...
A thesis of numerical simulation of flow through open channel with series of ...
 
Major project report of diploma civil engineering at mamts gothatar to jorpat...
Major project report of diploma civil engineering at mamts gothatar to jorpat...Major project report of diploma civil engineering at mamts gothatar to jorpat...
Major project report of diploma civil engineering at mamts gothatar to jorpat...
 
Survey camp report of Madan Ashrit at Kharipati - Bhaktapur! 100 pages
Survey camp report of Madan Ashrit at Kharipati - Bhaktapur! 100 pagesSurvey camp report of Madan Ashrit at Kharipati - Bhaktapur! 100 pages
Survey camp report of Madan Ashrit at Kharipati - Bhaktapur! 100 pages
 
Engineering materials bsc. civil lab 14 report
Engineering materials bsc. civil lab 14 reportEngineering materials bsc. civil lab 14 report
Engineering materials bsc. civil lab 14 report
 
Cement: Properties, uses and types, manufacturing methods, reaction taking pl...
Cement: Properties, uses and types, manufacturing methods, reaction taking pl...Cement: Properties, uses and types, manufacturing methods, reaction taking pl...
Cement: Properties, uses and types, manufacturing methods, reaction taking pl...
 
Aggregates, Types, Properties, Sources, Uses and its test by Suman Jyoti
Aggregates, Types, Properties, Sources, Uses and its test by Suman JyotiAggregates, Types, Properties, Sources, Uses and its test by Suman Jyoti
Aggregates, Types, Properties, Sources, Uses and its test by Suman Jyoti
 
Economics 50 long questions solve by suman jyoti (dhaka university of enginee...
Economics 50 long questions solve by suman jyoti (dhaka university of enginee...Economics 50 long questions solve by suman jyoti (dhaka university of enginee...
Economics 50 long questions solve by suman jyoti (dhaka university of enginee...
 
Ielts speaking by suman jyoti 2020/021
Ielts speaking by suman jyoti 2020/021Ielts speaking by suman jyoti 2020/021
Ielts speaking by suman jyoti 2020/021
 
Topographic map level transfer to traverse
Topographic map level transfer to traverseTopographic map level transfer to traverse
Topographic map level transfer to traverse
 
Topographic map fly levelling 1
Topographic map fly levelling 1Topographic map fly levelling 1
Topographic map fly levelling 1
 
Topographic map detailling 1
Topographic map detailling  1Topographic map detailling  1
Topographic map detailling 1
 
Topographic map distance and angular measurement 0
Topographic map  distance and angular measurement  0Topographic map  distance and angular measurement  0
Topographic map distance and angular measurement 0
 
Theodolite traversing
Theodolite traversingTheodolite traversing
Theodolite traversing
 
Road alignment survey 02
Road alignment survey 02Road alignment survey 02
Road alignment survey 02
 
Road alignment survey 01
Road alignment survey 01Road alignment survey 01
Road alignment survey 01
 
Bridge site survey 02
Bridge site survey 02Bridge site survey 02
Bridge site survey 02
 
Bridge site survey 01
Bridge site survey 01Bridge site survey 01
Bridge site survey 01
 

Recently uploaded

Adsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) pptAdsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) pptjigup7320
 
Danikor Product Catalog- Screw Feeder.pdf
Danikor Product Catalog- Screw Feeder.pdfDanikor Product Catalog- Screw Feeder.pdf
Danikor Product Catalog- Screw Feeder.pdfthietkevietthinh
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementDr. Deepak Mudgal
 
INTERRUPT CONTROLLER 8259 MICROPROCESSOR
INTERRUPT CONTROLLER 8259 MICROPROCESSORINTERRUPT CONTROLLER 8259 MICROPROCESSOR
INTERRUPT CONTROLLER 8259 MICROPROCESSORTanishkaHira1
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptAfnanAhmad53
 
Post office management system project ..pdf
Post office management system project ..pdfPost office management system project ..pdf
Post office management system project ..pdfKamal Acharya
 
Fundamentals of Internet of Things (IoT) Part-2
Fundamentals of Internet of Things (IoT) Part-2Fundamentals of Internet of Things (IoT) Part-2
Fundamentals of Internet of Things (IoT) Part-2ChandrakantDivate1
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxMustafa Ahmed
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...ronahami
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...ppkakm
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
Unsatisfied Bhabhi ℂall Girls Ahmedabad Book Esha 6378878445 Top Class ℂall G...
Unsatisfied Bhabhi ℂall Girls Ahmedabad Book Esha 6378878445 Top Class ℂall G...Unsatisfied Bhabhi ℂall Girls Ahmedabad Book Esha 6378878445 Top Class ℂall G...
Unsatisfied Bhabhi ℂall Girls Ahmedabad Book Esha 6378878445 Top Class ℂall G...Payal Garg #K09
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxkalpana413121
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxhublikarsn
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Ramkumar k
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...ssuserdfc773
 

Recently uploaded (20)

Adsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) pptAdsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) ppt
 
Danikor Product Catalog- Screw Feeder.pdf
Danikor Product Catalog- Screw Feeder.pdfDanikor Product Catalog- Screw Feeder.pdf
Danikor Product Catalog- Screw Feeder.pdf
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
INTERRUPT CONTROLLER 8259 MICROPROCESSOR
INTERRUPT CONTROLLER 8259 MICROPROCESSORINTERRUPT CONTROLLER 8259 MICROPROCESSOR
INTERRUPT CONTROLLER 8259 MICROPROCESSOR
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
Post office management system project ..pdf
Post office management system project ..pdfPost office management system project ..pdf
Post office management system project ..pdf
 
Fundamentals of Internet of Things (IoT) Part-2
Fundamentals of Internet of Things (IoT) Part-2Fundamentals of Internet of Things (IoT) Part-2
Fundamentals of Internet of Things (IoT) Part-2
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Unsatisfied Bhabhi ℂall Girls Ahmedabad Book Esha 6378878445 Top Class ℂall G...
Unsatisfied Bhabhi ℂall Girls Ahmedabad Book Esha 6378878445 Top Class ℂall G...Unsatisfied Bhabhi ℂall Girls Ahmedabad Book Esha 6378878445 Top Class ℂall G...
Unsatisfied Bhabhi ℂall Girls Ahmedabad Book Esha 6378878445 Top Class ℂall G...
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
 

Intze Overhead Water Tank Design by Working Stress - IS Method.pdf

  • 1. DESIGN OF AN INTZE TANK COURSE CODE: CE - 4102 COURSE TITLE: STRUCTURAL ANALYSIS AND DESIGN -III SESSIONAL Designed By: SUMAN JYOTI Student Id: 191125 Department of Civil Engineering Dedicated To: TRIBHUVAN UNIVERSITY Kritipur, Nepal KATHMANDU UNIVERSITY Banepa, Nepal DEPARTMENT OF CIVIL ENGINEERING DHAKA UNIVERSITY OF ENGINEERING & TECHNOLOGY, GAZIPUR
  • 2. Design an Intze tank from following data: Future population = 3175 Per capita demand = 130 litre/day Height of the cylindrical wall = 11 ft. Concrete strength, f´c = 5030 psi Steel strength, fy = 60 ksi = 415 Mpa Solution: 1. GEOMETRIC DESIGN: Total quantity of water = 3175 × 130 = 412750 lit/day = 412.75 m3 / day = 14564.94 ft3 / day Let, the diameter of the tank = D in ft. Now, the volume of the tank = capacity of the tank  14564.94 = 𝜋𝐷2 4 × 11ft  D = 41.56 ft ≈ 42 ft 1.1 Dimension and Illustration of Water Tank: Figure: Dimension Proportioning of Intz Water Tank
  • 3. 2. STRUCTURAL DESIGN: 2.1 Materials Property: 2.1.1 Permissible concrete stresses to resistance to cracking: Direct tension, fc = 5√𝑓′𝑐 psi = 5√5030 psi psi = 354.61 psi = 2.445 MPa Tension due to bending, fc = 12√𝑓′𝑐 psi = 12√5030= 851.06 psi = 5.87 MPa Shear = √f′c psi = 2√5030 psi =141.85 psi = 0.978 MPa Direct compression, fc = 0.25 f ′c psi = 1257.5 psi = 8.67 MPa Compression due to bending, fc = 0.45 fc’ psi = 2263.5 psi = 15.06 MPa Modular ratio, n = 29∗106 57000√f′c = 29∗106 57000√5030 = 7.17 2.1.2 Allowable tensile strength of reinforcement (According to BNBC): fs= 0.4 fy = 0.4 × 60 = 24 ksi =165.5 Mpa 2.2 Design of Top Spherical Dome: 2.2.1 Allowable tensile strength of reinforcement (According to BNBC): Radius of top spherical dome = R Let, r be the radius of the dome So, h (2r-h) = R2 or, 5.25 × (2r – 5.25) = 212 or, r = 44.625 ft = 13.6 m Now, sin θ = 21/ 44.625 θ = 28.07 º < 51.8 º (so, compression dome) cos θ = 0.882 2.2.2 Load calculation: Let, the thickness of dome slab = 100 mm Self-weight = 0.1 x 25 = 2.5 kN/m2 Live load = 1.5 kN/m2 So, Total Distributed Load, w = 4 kN/m2 r r-h R = 21ft h = 5.25 ft R
  • 4. 2.2.3 Check for stresses: Let, the thickness of dome Hoop stress at any angle θ, = 𝑤𝑟 𝑡 ( cos2 θ+cosθ−1 1+𝑐𝑜𝑠θ ) Maximum hoop stress will occur at θ = 0, So, Hoop stress = 𝑤𝑟 𝑡 × 1 2 = 4∗1000∗13.6 0.1∗ 2 = 0.272× 106 N/m2 = 0.272 N/mm2 < 5 kN/mm2 ( Ok ) Meridional stress at any angle θ, = 𝑤𝑟 𝑡 ( 1 1+𝑐𝑜𝑠θ ) Maximum meridional stress will occur at θ = 28.07 º = Ø, So, Meridional stress = 𝑤𝑟 𝑡 × 1 1+𝑐𝑜𝑠𝜃 = 4∗1000∗13.6 0.1 × 1 1+0.882 = 0.29× 106 N/m2 = 0.29 N/mm2 < 5 kN/mm2 ( Ok ) 2.2.4 Area of reinforcement calculation: Both stresses are within safe limit, hence a minimum reinforcement may be provided. Ast = 0.002bt = 0.002×1000×100 = 200 mm2 per meter (both direction) Use 8 mm dia. bar @ 200 mm c/c (both direction) 2.2.5 Detailing of reinforcements: 8 mm @ 200 mm c/c at mid of the slab thickness 100 mm thick dome slab
  • 5. 2.3 Design of Top Ring Beam: 2.3.1 Load calculation: The horizontal component of Meridional thrust, P = T Cos φ P = 0.29 × 100 ×1000 ×(0.882) = 25578 N Total tension tending to rupture the ring beam per meter length of its circumference, = P × D/2 = 25578 × (12.8/2) = 163700 N 2.3.2 Area of reinforcement calculation: Since steel in contact with water then fs = 165.5 N/mm2 [fs = 0.4fy ] So, Area of reinforcement required, Ast = Tensile force Allowable stress of steel = 163700 165.5 = 990.12 mm2 Using 16 mm dia bar (as = 200.1 mm2 ), required bar= 990.12 200.1 = 4.94 ≈ 5 nos. 2.3.3 Size of beam calculation: Equivalent area of the composite section = A + ( n-1 ) Ast = A + ( 7.17-1 ) × 5 × 200.1 = A + 6174 Take the allowable stress to the composite section is 1.2 kN/mm2 . or, 1.2 = 163700 A + 6174 or, A = 130242 mm2 Let, beam width is, b = 500 mm and the depth, d = 260.48 ≈ 260 mm 2.3.4 Minimum reinforcement calculation: Using (#3) 10 mm dia bar, then spacing, Sv = 2.5 As∗fy b As = 2 × 0.11 in2 ( for two legs ) So, Spacing, Sv = 2.5∗78.54∗413.7 260 = 312.42 mm ≈ 300 mm c/c
  • 6. 2.3.5 Detailing of reinforcements: 2.4 Design of Cylindrical Wall: 2.4.1 Load Calculation: Let, joint condition is simple joint, i.e., cylindrical wall is free to move at top and bottom. Maximum hoop tension at the base of the wall is, T = γh 𝐷 2 = 10000 × 3.534 × 12.8 2 [Using, γw = 10000 N/m3 ] T = 226176 N 2.4.2 Area of reinforcement calculation: Area of the required reinforcement, Ast = 226176 165.5 = 1366.6 mm2 Area of reinforcement on each face = 1366.6/2 = 683.3 mm2 ≈ 684 mm2 Using 16 mm dia. bar, the spacing = 1000 ∗ 201 684 = 293.86 mm ≈ 280 mm c/c Cut 50% bar at a depth of 1.8 m below the top cylinder than base, So, spacing is = 560 mm c/c 2.4.3 Thickness of cylindrical wall calculation: Equivalent area of composite section = t×103 + (7.17–1) × ( 1000 280 ×2×201) = 1000t + 8858.35 Since the tension is direct then permissible direct tensile stress = 1.2 N/mm2 or, 1.2 = 226176 1000𝑡+8858.35 or, t = 179.62 mm ≈ 180 mm Since hoop tension is smaller at the top of cylinder than base, So, use thickness 150 mm at the top of cylindrical wall.
  • 7. 2.4.4 Distribution of reinforcement calculation: Average thickness of the wall slab = 180+150 2 = 165 mm Area of steel required is = 0.0022 × 1000 × 165 = 330 mm2 Using 12 mm bar, the spacing = 113∗1000 330 = 342.4 mm c/c ≈ 300 mm c/c 2.4.5 Detailing of reinforcement:
  • 8. 2.5 Design of bottom ring beam: 2.5.1 Load Calculation: Load due to top dome = Area of slab x Meridional stress x sin φ = 100 x 1000 x 0.29 x sin28.07º = 13646 N /m Load due to top ring beam = 0.26 x (0.5 - 0.15) x 25000 = 2275 N/m Load due to cylindrical wall = 0.165 x 3.35 x 25000 = 13819 N /m Assume, beam size, 900 mm x 500 mm Self-weight of beam = 0.5 x (0.9 – 0.5) x 25000 = 5000 N /m Total w1= 34740 N/ m Horizontal thrust due to vertical load = w1 tan β = 34740 x tan 45º = 34740 N/ m Hoop tension due to vertical load, H1 = 34740∗12.8 2 = 222336 N Hoop tension due to water, H2 = 10000 x 3.35 x 0.6 x 12.8/2 = 128640 N Total hoop tension, H = 222336 + 128640 = 350976 N 2.5.2 Area of Reinforcement Calculation: Area of the required reinforcement, Ast = 350976 165.5 = 2120.7 mm2 Using 16 mm dia bar, Nos. of bar = 2120.7 201 = 10.55 ≈ 11 Nos. 2.5.3 Check for Tensile stresses: Maximum tensile stress = 350976 900∗500+(7.17−1)∗11∗201 = 0.0006 N/mm2 <1.2 N/mm2 ( Ok ) 2.5.4 Shear reinforcement calculation: Using 10mm dia bar Spacing, Sv = 2.5 𝐴𝑠𝑣 𝑓𝑦 𝑏 = 2.5∗ 78.54∗4∗165.5 500 = 260 mm c/c ≈ 250 mm c/c
  • 9. 2.5.5 Detailing of reinforcements: Fig. Detailing of bottom ring beam 2.6 Design of conical dome: 2.6.1 Load Calculation: Average diameter of Conical dome = 10.4 m Average depth of water = 3.35 + 2.4/2 = 4.55m Assume, Thickness of slab 400 mm Self-weight of slab = (π x 10.8 x 3.39) x 0.4 x 25000 = 1150203 N Weight of water = (π x 10.8 x 4.55 x 2.4) x 10000 = 370508 N Load from Top dome, cylindrical wall, bottom ring beam, = 34740× π×10.4 = 370508 N Total load on Conical dome =1150203+ 370508 + 370508 = 1891219 N Load at per meter of conical dome base = 1891219 3.1416∗4.54 = 132598 N/m Meridional thrust, T = 132598 𝑐𝑜𝑠45 = 187522 N Meridional stress = 187522 1000∗400 = 0.5 N/mm2 < 5.0 N/mm2 , So Safe. 2.6.2 Hoop tension calculation: General expression for hoop tension
  • 10. Diameter of conical dome at h m height from base, Dh = 8 + 2 × 2.4/2.4 × h = 8 + 2h Intensity of water pressure at height h from base, p or, p = (5.76 – h) x 10000 x 1 = (57600 – 10000h) N/m Weight of Conical dome, w1 = 0.4 x 1 x 25000 = 10000 N/m Hoop tension at any height h, = (𝑝𝑠𝑖𝑛β+ w1 tanβ) × 8 + 2h 2 = {(57600 – 10000h) sin45 + 10000 tan45)} × 8 + 2h 2 Maximum Hoop tension (at h = 2.44) = 216056 N 2.6.3 Area of reinforcement calculation: Area of Reinforcement Calculation, Ast = 216056 165.5 = 1306mm2 Area of steel on each face = 1306 2 = 653 mm2 Using 16 mm dia. bar, Spacing = 201∗1000 653 = 307.8 mm C/C ≈ 300 mm C/C Check for maximum tensile stress- = 216056 400∗ 1000 +(12.8 − 1)∗( 1000 100 ∗201∗2) = 0.00001 N/mm2 < 1.2 N/mm2 (Ok) 2.6.4 Distribution Reinforcement Calculation: Assuming distribution bar as 0.18 % Ast = 0.0018× 400 × 1000 = 720 mm2 Area of steel on each face = 720 /2 = 360 mm2 Using 12 mm bar, spacing = 113.1∗1000 360 = 314.2 mm ≈ 300 m c/c
  • 11. 2.6.5 Area of reinforcement for B.M. The conical dome also acts as a slab, Load on slab, W = 1150203 + 370508 3.1414 ∗8 = 60507.16 N/m Load on 1m wide and 3m spanned slab, W = 60507.16 N/m So, Maximum Bending moment = 60507.16 ∗3 12 = 15126.8 N-m Let, main bar Ø16mm, then effective depth = 400 – 40 -16/2 = 352 mm Ast = 15126.8∗1000 115 ∗ 352 ∗ 0.866 ≈ 430 mm2 Use #5 (16mm) bar, Spacing = 201.1∗1000 430 = 467.67 mm C/C ≈ 400 mm C/C Since flexural reinforcing bar spacing = 400 mm C/C, Which will also act as distribution bar as well as main bar. Use #4 (12mm) bar @ 400 mm C/C as distribution bar at the top of the slab. 2.6.6 Reinforcement Detailing Fig. Detailing of conical dome slab
  • 12. 2.7 Design of bottom spherical dome: 2.7.1 Load Calculation: Assume, slab thickness = 400 mm Let, Radius of dome rb, rb2 = (rb- 1.6)2 + 4.0 2 ∴ rb = 5.8 m or, sin φ = 4 5.8 = 0.6897 ∴ φ = 43.60 < 51.8º So Compression dome ∴ cos φ = 0.724 Self-weight of dome = (2π rb × h) × t × γc = 2π x 5.8 x 1.6 x 0.4 x 25000 = 583080 N Volume of water above conical dome, V = πR2 hwater – 1 3 π x h2 x (3 x rb – h) = π × 42 × 4.55 – 1 3 π × 1.62 × (3 × 5.8 – 1.6) = 186.35 m3 Weight of water = 186.35 x 10000 = 1863508 N Total weight = 583080 + 1863508 = 2446588 N 2.7.2 Check for stress: Load per unit area w = 2446588 2π x 5.8 x 1.6 = 41960 N/m2 ∴ Maximum Hoop stress = wr 𝑡 × 1 2 = 41960 x 5.8 0.4 × 1 2 = 0.304 x 106 N/m2 = 0.304 N/mm2 < 5 N/mm2 ∴ Maximum Meridional stress = wr 𝑡 × 1 (1+𝑐𝑜𝑠 φ) = 41960 x 5.8 0.4 × 1 (1+0.724) = 0.353 x 106 N/m2 = 0.353 N/mm2 < 5 N/mm2 2.7.3 Area of reinforcement calculation: ρ = 0.18 % Area of the required reinforcement, Ast = 0.18 100 x 400 x 1000 = 720 mm2 Using #4 (12mm) bar, Spacing = 113.1∗1000 720 = 157.08 mm c/c ≈ 150 mm c/c in both directions. R = 4 m h = 1.6 m r-h rb
  • 13. 2.7.4 Details of reinforcement: Fig: Detailing of Bottom Spherical Dome. 2.8 Design of circular bottom beam: 2.8.1 Load Calculation: Meridional thrust from conical dome, T = 187522 N/m Inward thrust from conical dome = 187522× sin 45º = 132598.07 N/m Meridional thrust from bottom spherical dome = 0.353 × 400 × 1000 = 141200 N/ m Outward thrust from bottom spherical dome = 141200 × Cos 43.6° = 102253 N/m So, Net inward thrust, P = 132598.07 – 102253 = 30345 N/m (Compressive) Hoop compressive force in Beam = 𝑃𝐷 2 = 30345∗ 26.25 3.28 2 = 121380 N Assuming, Beam size = 450 mm × 800 mm ∴ Hoop stress = 121380 450∗800 = 0.3372 N/mm2 < 5 N/mm2 Vertical load from conical dome = 132598 N/m (Computed earlier) 12 mm @ 150 mm c/c at mid of the slab thickness 00 mm thick dome slab
  • 14. Vertical load from bottom spherical dome, = 2446588/ (π x 8) = 97346.6 N/m Total Vertical load on beam = 132598 + 97346.6 = 229945 N/m Self-weight of beam = 0.45 × 0.8 × 25000 = 9000 N/ m ∴ The design load for the beam, 𝜔 = 229945 + 9000 = 238945 N/m 2.8.2 Moment Calculation: Load on per meter beam, w = 238945 N/m It is proposed to support the beam by 6 Columns. Maximum (-ve) Bending moment at support = k1wR2 × 1 3 π M1 = 0.089 × 238945 × 42 × 1 3 π = 356317 N- m Maximum (+ve) Bending moment at mid span = k2wR2 × 1 3 π = 0.045 × 238945 × 42 × 1 3 π = 180160 N- m Maximum (-ve) Twisting moment (T) at 12.75º from support = k3wR2 × 1 3 π = 0.009 × 238945 × 42 × 1 3 π = 36032 N- m 2.8.3 Shear Calculation: Shear force at support section, V1= w × 2𝜋𝑅 𝑁𝑜.𝑜𝑓 𝐶𝑜𝑙𝑢𝑚𝑛 × 1 2 = 238945 × 2𝜋∗4 6 × 1 2 = 500445 N Shear force at the point of maximum torsion, V2 = 500445 – 500445 × 12.75 30 = 287755.88 N ( rough, 360/6 column × 2 )
  • 15. 2.8.4 Design of support section (For Moment): M = 356317 N- m, V1= 500445 N Effective depth, d = √ Moment 𝑖𝑛 𝑁−𝑚𝑚2 0.5∗𝑓𝑐∗𝑗∗𝑘∗𝑏 deff = √ 356317 ∗1000 0.5∗15.06∗0.866∗0.403∗450 = 548.9 mm Let clear cover = 40 mm, and 2 layers of main bar Ø of main bar = 25 mm & stirrup = 10 mm So, Actual effective depth, d = 800 – 40 – 10 – (25 + 25/2) = 712.5 mm > 548.9 mm, Safe (ok). Area of Reinforcement = 356317 × 1000 165.5 × 0.866 × 712.5 = 3490 mm2 Use 20 mm Ø bar. So, Nos. of bars = 3490/314.2 = 11.10 ≈ 12 Nos. 2.8.5 Design of support section (For Shear): Developed shear stress, 𝜏v = 𝑉 𝑏𝑑 = 500445 450 ∗712.5 ∴ 𝜏v = 1.56 N/mm2 Maximum allowable shear stress, 𝜏allow = 3.4 √𝑓𝑐 ′ ∴ 𝜏allow = 3.4 √5030 = 241.13 psi = 1.66 N/mm2 Since 𝜏v < 𝜏allow, this section is safe for shear., Here, Percentage of steel ratio ρ = 12.5 30 = 0.417 % So, allowable concrete shear stress, 𝜏c = 1.1 √𝑓𝑐 ′ 𝜏c = 1.1 √5030 = 78.01 psi = 0.538 N/mm2 Since 𝜏v > 𝜏c Shear reinforcement is required.
  • 16. Here, Allowable concrete shear force, Vc = 𝜏c × bd = 0.538 × 450 × 712.5 = 172496.25 N Use #3 (10mm) bar 6-legged bar as stirrup, Spacing, S = 𝐴𝑠𝑣∗𝑓𝑠𝑣∗𝑑 𝑉−𝑉𝑐 = (6∗78.54) × 210 × 712.5 500445 −172496.25 = 215 mm C/C ≈ 200 mm C/C 2.8.6 Design for torsion: The maximum torsion occurs at the point of contraflexure Equivalent moment, Me = M + MT At point of contraflexure M = 0 And, we know, MT = 𝑇 1.7 (1 + 𝐷 𝐵 ) = 36032∗1000 1.7 (1 + 800 450 ) = 175.54 × 106 N-mm So, the equivalent moment, Me = 58.87 × 106 N-mm Area of Reinforcement = 58.87 × 106 165.5 x 0.866 x 712.5 = 576.55 mm2 Use 16 mm Ø bar. So, Nos. of bars = 576.55/201.1 = 2.87 ≈ 4 The number of bars at the point of contraflexure is more than the 3, So no additional bars are required. Equivalent shear, Ve = V +1.6 𝑇 𝑏 = 500445 + 1.6 × 36032 450 = 500573 N Equivalent nominal shear stress, 𝜏ve = 500573 450∗712.5 = 1.56 N/mm2 < 1.66 N/mm2 Let, 10mm Ø bar with 6 legged will be used as stirrup, so, Asv = 6 × 78.54 = 471.2 mm2 Allowable concrete shear force, Vc = 0.538 × 450 × 712.5 = 172496.25 N
  • 17. (i) Spacing considering torque and shear force at point of contraflexure Asv = 𝑇∗𝑆𝑣 𝑏1 ∗ 𝑑1 ∗ 𝑓𝑠𝑣 + 𝑉2∗𝑆𝑣 2.5 𝑑1 ∗𝑓𝑠𝑣 471.2 = 36032∗1000∗𝑆𝑣 384 ∗ 719 ∗210 + 287755.88 ∗𝑆𝑣 2.5 ∗719 ∗ 210 ∴ 𝑆v = 340 ≈ 300 mm c/c b1 = 450 – 2×25 – 2×8 = 384 mm d1 = 800 – 40 – 25 – 2 × 8 = 719 mm (ii) Spacing considering equivalent shear force 𝐴vs = (𝑉𝑒−𝑉𝑐)𝑆𝑣 𝑓𝑠𝑣∗𝑑 or, Sv = 𝐴𝑠𝑣∗𝑓𝑠𝑣∗𝑑 𝑉𝑒−𝑉𝑐 = 471.2 ∗ 210∗712.5 (500573 − 172496.25 ) = 214.9 mm c/c ≈ 200 mm c/c Hence provide 10 mm-6-legged stirrup at 200 mm c/c from column face to the point of contraflexure. 2.8.7 Design of mid-section: Effective depth, d = 712.5 mm Bending Moment = 180160 N- m Area of Reinforcement = 180160 × 1000 165.5 × 0.866 × 712.5 = 1764.24 mm2 Use 20 mm Ø bar. So, Nos. of bars = 1764.24/314.2 = 5.62 ≈ 6 2.8.8 Detail Drawing: Fig. Detailing of Circular Bottom Beam
  • 18. Fig:-Section showing the details reinforcement in bottom circular beam, column and bracing.