SlideShare a Scribd company logo
1 of 6
Download to read offline
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 310
Achieving Total Quality Management in Construction Project Using Six
Sigma Concept
Dr.Divakar.K1 and Nishaant.Ha2
1Associate Professor in Civil Engineering, Coimbatore Institute of Technology, Coimbatore-641014
2Assistant Professor in Civil Engineering, Kumaraguru College of Technology, Coimbatore-641049
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - A Six Sigma approach is one of the most
efficient quality improvement processes. In this study, six
sigma concepts were applied in construction scheduling
process to avoid delay as well as to maintain the quality of
the construction activities. Detailedscheduleofthebuilding
was analysed & also the updated schedule was verified. At
this stage, DMAIC (Define, Measure, Analyse, Improve and
Control) principle was implemented. The variation in the
scheduling due to delay of the activities was noted down.
Delay reasons and their impacts in the whole project were
calculated. All delayed activities were considered as
“Defects”. DPMO (Defects Per Million Opportunities) was
calculated. By using this value, Sigma Level was identified.
Pareto Chart Analysis was made. WiththehelpofSixSigma,
ways to overcome schedule variation due to delay was
recommended.
Keywords: DMAIC, DPMO, Sigma Level, Pareto Chart.
1. INTRODUCTION
In the current field of construction, time optimization as
well as the quality control is one of the prime
requirements. To achieve this, several quality control
approaches and also delay reduction techniques are
adopted and also followed in the construction field. This
study aims to execute the construction activities as per
the estimated schedule without any variation as well as
with the required quality and satisfactionbythecustomer
or the owner of the project. To obtain this, Six Sigma
concepts and its principles were applied in the analysing
or verifying processofconstructionscheduling,duringthe
execution stage of the construction activities. DMAIC
(Define, Measure, Analyse, Improve & Control)
methodology was adopted. Hence, with the help of Six
Sigma the ways to achieve Total Quality Management in
construction are analysed in this study.
2. LITERATURE REVIEW
Pande P et.al. (2000) explained the power of the sixsigma
movement in the world’s most successful companies.
Adan Valles et.al (2009) applied Six sigma project at a
semiconductor company dedicated to the manufacture of
circuit cartridges for inkjet printers. They were tested
electrically in the final stage of the process measuring
electrical characteristics to accept or reject them .
Low Sui Pheng and Mok Sze Hui (2004) examined the
strategies and concepts of Six Sigma and implemented
those concepts in construction industry. A. D. Lade et.al.
(2015) analysed the quality performance of Ready Mix
Concrete (RMC) plant at Mumbai, India, using the six
sigma philosophy had been evaluated using various
quality tools and sigma value was calculated.Accordingto
the sigma level, recommendations were given for the
improvement. Seung Heon Han et.al. in their study they
developed a general methodology to apply the six sigma
principles on construction operations rather than
construction materials in terms of the barometers to
measure, evaluate, and improve construction
performance. Lean and Six sigma inconstructionfieldwas
analysed with the help of several literature reviews by
Sunil V. Desale et.al. (2013). Abdulaziz Ali Banavi (2013)
was developed and implemented methods toimprovethe
performance and the efficiency of construction processes
prior to and during the construction phase in Design-Bid-
Build (DBB) projects. In order to accomplish these goals,
the three methods Lean, Green, and Six-Sigma were
implemented. The root causes behind waste generation
were determined via developing and administrating a
questionnaire to a local construction company.
Mehmet Tolga Taner (2013) conducted a survey-based
approach which is used to identify the Continuous
Improvement(CI)initiativescommonlypractisedinlarge-
scale Turkish construction companies as well as
understanding the approach of these companies to Six
Sigma. According to the questionnaire survey, the three
most important Critical Success Factors lowering the
performance of companies were found to be high costs,
high amount of waste and lack of a well-implemented
customer management system. Kuo-Liang Lee, and Yang
Su (2013) were demonstrated a Six Sigma project of
determining and improving the key input variables
affecting the cracks in lightweight partition walls. The
case study of residential building was taken in which six
sigma was applied for internal finishing work, six sigma
principle was adopted to improve quality and was
checked against the sigma level by Sneha.P Sawant &
Smitha V. Pataskar (2014).
Theo C. Haupt et.al explained about Total Quality
Management (TQM) and itsimplementationtechniquesin
construction site to achieve quality in several accepts. H.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 311
James Harrington et.al examined the quality and
productivity problems and improvement opportunities
that face the construction industry today were defined.
The latest studies which focused on increase the business
quality through implementing TQM in construction
industry was pointed out and its suitable applications in
the different phases of project constructionwasidentified
by Ahmed S. Agha. The level of effectiveness of the
implementation of TQM principles by the construction
contractors was identified by Abu Hassan et.al. Khaled F.
Sherif examined the existing barriersofTQMandin-depth
survey was conducted in two Libyan construction
companies. Low Sui Pheng et.al (2014) created a
framework for implementing TQM in construction.
3. SIX SIGMA CONCEPT IN CONSTRUCTION
SCHEDULING
The major aim of six sigma approach is to reduce the
defects in the process. The level of six sigma value is 3.4
Defects Per Million Opportunities (DPMO). In scheduling
process, all delayed activities and the activities without
satisfying the predefined quality requirements are
considered as “defects”. Then, number of completed
activities is considered as total number of opportunities.
With the help of these data, Sigma level can be calculated
and the percentage of accuracy can be determined.
Accuracy will gets increased by increasing the level of
sigma value. To overcome these defects and also to
improve the sigma value / accuracy of the project,
predefining the possibilities of defects opportunities
should be worked out during the pre-execution stage
itself and possible counteractions are to be analysed.
During the construction execution stage, updating the
schedule should be done several times and sigma value is
calculated at every stage respectively.Then, possible
counteractions forthe remaining worksshouldbefocused
accurately and also necessary steps should be taken to
avoid same types of defects in the remaining project and
have to work according to that.
4. METHODOLOGY
DMAIC (Define, Measure, Analyse, Improve & Control)
Methodology is one of the prime factors of six sigma
approach. Hence this methodology wascarried out in this
study.Delay Reduction and client satisfaction were
considered as CTQ (Critical To Quality) factor.
4.1 Define
During Define Phase, Detailed updated schedule was
analysed. Basic details of the project are given in (Table
1)
Table 1 Observations
Type of Project IT Building
Total Area 2.2 acres
Built up Area 1.7 acres
No. of Floors B2 + (G+13)
Project started on 01/04/2015
Estimated Duration 365 days
Updated schedule as on 19/02/2016
Total no. of completed
activities
202
No. of delayed activities 53
Re-estimatedcompletionas
on
15/07/2016
4.2 Measure & Analyse Phase
In this phase, Defects Per Million Opportunities (DPMO),
Sigma Level and percentage of accuracy were calculated.
DPMO was calculated using the following formula,
DPMO = ((1,000,000)X) / YZ
Where,
X - Number of Defects
Y - Number of Units
Z - Number of Defect Opportunities/Unit
In this study, Number of Defect Opportunities is the
chances or test by means of which we identify whether
the activities delayed or not. Hence, itwastakenas1.After
applying all the values in the above formula,
DPMO - 262376.2
Sigma level was identified by interpolating the values
from the following standard table 2
Table 2 Sigma Levels and their DPMOs
Sigma Value DPMO
1 690,000
2 308,000
3 66,800
4 6,210
5 320
6 3.4
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 312
Sigma Level - 2.1
Percentage of accuracy & defective percentage was
identified with the help of sigma level value.Thefollowing
table 3 was used for calculating the percentage of
accuracy.
Table 3 Sigma Levels v/s Percentage Accuracy&
Defective Percentage
Sigma
Value
Percentage
Accuracy (%)
Defective
Percentage (%)
1 30.9 69.1
2 69.1 30.9
3 93.3 6.7
4 99.38 0.62
5 99.77 0.023
6 99.99966 0.00034
Percentage Accuracy - 71.52%
Defective Percentage - 28.48%
By referring that updated schedule, delayed activities
were categorized separately. Delayed duration for each
activity was mentioned. According to the higher delayed
duration, the rank was given. Major delayed activities
were identified. Then, delay reasons for the delays were
analyzed and noted down. With respect to maximum
priority, delay reasons were tabulated (Table 4).
Table 4 Delay Reasons and its Priority
S.No Delayed Reasons
No. of
activities
delayed
No. of
days
delayed
1 Shortage of Labour 11 138
2
Delay in drawing
submission & approval
6 73
3
Delay due to verification
& submission of Tender
documents
7 70
4
Delay due to providing
payment by the client
4 48
5
Slow Preparation of
documents
13 45
6
Insufficient information
about the work
1 35
7 Plastering Delayed 1 30
8
Delay in procurement of
materials
4 26
9 Rain Interruption 2 25
10 PO delayed 2 23
11 Delay in concreting 1 10
12 Delay from the client side 1 10
Pareto chart analysis was made.Paretochartconsistsof
both line graph and the bar chart. In descending order
individual values are mentioned and denoted as bars.
Cumulative total of all individual values are denoted as
line graph.
In this study, delay reasons were mentioned in x-axis &
percentage of delay was mentioned in y-axis.
Fig. 1 Pareto Chart Analysis
This analysis showed that 50% of delay reasons caused
80% of delay. Hence, we have to eliminate those delays
having higher priority at the early stage of the project
itself.
Before executing the construction work, possibilitiesof
delay have to be analysed and worked out. All these
analysis should be done for those predicted delays. With
respect to the out comings, possible counteractionshould
be taken and maintained properly.
4.3 Improve & Control Phase
In this phase, general recommendations to overcome the
delays were given. Trail sigma calculations were made.
Then steps to be applied to achieve higher efficiency in
construction projects were discussed. General
recommendations to overcome the delays are shown in
the following table 5
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 313
Table 5 General Recommendations
S.No
Delayed
Reasons
Recommendations
1
Shortage of
Labour
Resource Leveling,
Resource allocations
should be done properly.
2
Delay in
drawing
submission &
approval
Detailed information
about the particular
work is to be analyzed
and given to the design
department. So that they
can preparethedrawings
in time.
3
Delay due to
verification &
submission of
Tender
documents
Proper contractor team
should be employed
4
Delay due to
providing
payment by the
client
Properagreementshould
be framed & payment
should be given
according to that
agreement
5
Slow
Preparation of
documents
Accurate information
should be given. Should
have a proper
communication
6
Insufficient
information
about the work
Before executing the
particular work, all
required information
should be gathered and
documented properly
7
Delay in
procurement of
materials
Material Optimization
should done properly
according to the type of
the work
8 PO delayed
Execution department
should inform the
purchase department
about their material
requirementsinadvance.
9
Delay in
concreting
ResourceLevelingshould
be done
10
Delay from the
client side
Client & the contractor
should have a proper
communication. They
should work accordingto
the agreement
5. TRIAL SIGMA CALCULATION
1. By seeing the delayed activities, it was found that the
many delay parameters werecommon&manydelays
were occurred due to the delay of the preceding
activity.
2. 50% of delayed reasons caused 80% of delay in
duration of the project.
3. If DMAIC principle is applied and the parameters are
identified at the starting stage itself, we can improve
the efficiency by achieving the several milestones of
the project in time.
4. Assuming, that the recommendations given here are
applied at the early stage itselfand also assume that
the major six topmost delayed reasons are rectified
5. According to the schedule, 42 activities willget free.
Now, Defects will be 11 out of 202 opportunities.
6. DPMO & Sigma Level is calculatedasdone earlier.The
obtained values are,
DPMO = 54455.45
Sigma Level = 3.1
7. This value showed that the level of sigma value gets
increased from 2.1 to 3.1, which means the level of
accuracy got increased.
8. The percentage of accuracy for the sigma value 3.1 is
93.91%. (i.e.) 22.39% of accuracy is increased from
the previous accuracy. (Previous accuracy was
71.52%)
9. Hence, its proved that applying Six Sigma principles
in construction scheduling, the efficiency of the
project can be increased in several aspects.
6. STEPS TO BE CARRIED OUT -
RECOMMENDATIONS
1. Several milestones are to be fixed. Each mile stone
will act as a short-term goal according to Six Sigma
concept.
2. For each milestone, we have to calculate the major
parameters of delay according to the type of activity.
3. By analyzing this, we can avoid several shortcomings
at the early stage itself.
4. Hence, it will show the way to complete those
particular activities in time.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 314
5. We can check the efficiency of the schedule by
calculating the sigma value and also percentage of
accuracy at the end of each milestone by analyzing
the updated schedule.
6. At this stage, we can re-estimate the schedule for the
remaining works as per the time limitations,
resources limitations, client specifications, etc…
7. We can also take preventive measures to avoid same
kind of delays in the remaining construction works.
8. During the execution of work,control limitsshouldbe
fixed and have to work accordingtothecontrol limits.
9. Control limits should be fixed within the client
specification limit to achievemaximum efficiencyand
client satisfaction. (i.e.) For example, if the clients
requirement for completing the particular activity
with 100% accuracy within a specified duration. We
have to fix the control limit as less than the specified
duration and have to work accordingtothatduration.
Hence, we can obtain higher level of sigma & also we
can have a proper control in the on-going project.
7. CONCLUSION
In construction industry, six sigma concepts are not
popularized. But, the efficiency of this process is
tremendous. We can achieve near perfect products or
activities with the help of six sigma approach in
construction. Construction scheduling is one of the prime
factors in construction projects. By applying six sigma
approaches and maintaining the activities in the proper
way as per DMAIC principles, we can increase the overall
efficiency of the project. Customer satisfactioncanalsobe
achieved.
This study showed that, Application of Six Sigma
concepts in construction will results Total Quality
Management (TQM), proper time management, quality
control, etc… Hence, this process in construction will also
give more efficiency in almost all construction project
management approaches.
REFERENCES
[1] A. D. Lade, A. S. Nair , P. G. Chaudhary, N. R. Gupta :
DOI: 10.9790/1684-12210104www.iosrjournals.org
1 | Page “Implementing Six Sigma Approach for
Quality Evaluation of a RMC Plant at Mumbai, India”
IOSR Journal of Mechanical and Civil Engineering
(IOSR-JMCE) e-ISSN: 2278-1684,p-ISSN: 2320-334X,
Volume 12, Issue 2 Ver. I (Mar - Apr. 2015), PP 01-04
[2] Adan Valles, Jaime Sanchez, Salvador Noriega, and
Berenice Gómez Nuñez “ImplementationofSixSigma
in a Manufacturing Process: A Case Study”
International Journal ofIndustrial Engineering,16(3),
171-181, 2009.
[3] AbdulazizAliBanavi“Improvingconstruction process
by integrating Green, Lean & Six Sigma” journal from
University of Pittsburg, 2013
[4] Kuo-Liang Lee, and Yang Su (Taiwan) “Applying Six
Sigma to Quality Improvement in Construction”,
American Society of Civil Engineers.(2013)
[5] Low Sui Pheng and Mok Sze Hui “Implementing and
Applying Six Sigma in Construction” Journal of
Construction Engineering and Management, Vol.130,
No. 4, August 1, 2004
[6] Mehmet Tolga Taner, “Critical Success FactorsforSix
Sigma Implementation in Large-scale Turkish
Construction Companies” International Review of
Management and Marketing Vol. 3, No. 4, 2013,
pp.212-225
[7] Pande, P., Neuman, R. P. & Cavanagh, R. R. (2000)
“The six sigma way: how Ge, Motora and other top
companies are honing their performance”.
[8] Seung Heon Han, M.ASCE; Myung Jin Chae, Ph.D., P.E.;
Keon Soon Im, P.E.; and Ho Dong Ryu “Six Sigma-
Based Approach to Improve Performance in
Construction Operations” Journal of Management in
Engineering, Vol. 24, No.1
[9] Sneha.P Sawant & Smitha V. Pataskar, “Applying Six
Sigma Principles in Construction Industry for Quality
Improvement” journal on advances in engineering &
technology ICAET – 2014
[10] Sunil V. Desale, Dr. S. V. Deodhar . “Lean Six Sigma
Principal in Construction: A Literature Review
Related to Conclusions” International Journal of
Emerging Technology and Advanced Engineering,
Volume 3, Issue 5, May 2013)
[11] Theo C. Haupt, Daniel E. Whiteman “Implementing
Total Quality Management on Construction Sites”
[12] The TQM Journal Emerald Article: Applying TQM to
the construction industry - H. James Harrington,
Frank Voehl, Hal Wiggin
[13] Total Quality Management In Construction Industry -
Ahmed S. Agha
[14] Total Quality Management Practices in Large
Construction Companies: A CaseofOmanAbuHassan
Bin Abu Bakar, Khalid Bin Ali and Eziaku Onyeizu
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 315
School of Housing, Building and Planning University
Sains Malaysia, 11800 Penang, Malaysia
[15] Total Quality Management and Construction Project
Management in Libya By Khaled F. Sherif
[16] “Implementing Total Quality Management in
Construction Firms” by Low Sui Pheng and Jasmine
Ann Teo, Journal ofManagementinEngineering,2004
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072

More Related Content

What's hot

IRJET- Optimization of Plastic Injection Molding
IRJET- Optimization of Plastic Injection MoldingIRJET- Optimization of Plastic Injection Molding
IRJET- Optimization of Plastic Injection MoldingIRJET Journal
 
Qnt 561 final exam view 369
Qnt 561 final exam view 369Qnt 561 final exam view 369
Qnt 561 final exam view 369forrest44
 
(New) mkt 571 mkt571 final exam entire answers with questions correct 100%
(New) mkt 571 mkt571 final exam entire answers with questions correct  100%(New) mkt 571 mkt571 final exam entire answers with questions correct  100%
(New) mkt 571 mkt571 final exam entire answers with questions correct 100%twiter343r
 
Recent trends in rapid product development 2-3-4
Recent trends in rapid product development 2-3-4Recent trends in rapid product development 2-3-4
Recent trends in rapid product development 2-3-4IAEME Publication
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET Journal
 
Project Management - Pmi’s opm3 is an example of a __________________ model...
Project Management - Pmi’s opm3 is an example of a   __________________ model...Project Management - Pmi’s opm3 is an example of a   __________________ model...
Project Management - Pmi’s opm3 is an example of a __________________ model...Suma Kamadod
 
Project Management - To determine the cost of particular element in advance o...
Project Management - To determine the cost of particular element in advance o...Project Management - To determine the cost of particular element in advance o...
Project Management - To determine the cost of particular element in advance o...Suma Kamadod
 
Project Management - A fundamental of ‘theory of constraints’ (toc) is to man...
Project Management - A fundamental of ‘theory of constraints’ (toc) is to man...Project Management - A fundamental of ‘theory of constraints’ (toc) is to man...
Project Management - A fundamental of ‘theory of constraints’ (toc) is to man...Suma Kamadod
 
Ops 571 final exam view 369
Ops 571 final exam view 369Ops 571 final exam view 369
Ops 571 final exam view 369forrest44
 
Six Sigma Green Belt - A green belt is going to monitor the number of defects...
Six Sigma Green Belt - A green belt is going to monitor the number of defects...Six Sigma Green Belt - A green belt is going to monitor the number of defects...
Six Sigma Green Belt - A green belt is going to monitor the number of defects...Suma Kamadod
 
Six Sigma Green Belt - A form, in either diagram or table format, that is pre...
Six Sigma Green Belt - A form, in either diagram or table format, that is pre...Six Sigma Green Belt - A form, in either diagram or table format, that is pre...
Six Sigma Green Belt - A form, in either diagram or table format, that is pre...Suma Kamadod
 
Six Sigma Green Belt - To determine the average number of nonconforming parts...
Six Sigma Green Belt - To determine the average number of nonconforming parts...Six Sigma Green Belt - To determine the average number of nonconforming parts...
Six Sigma Green Belt - To determine the average number of nonconforming parts...Suma Kamadod
 
Six Sigma Green Belt - Poka yake is best defined as a. improving machine effi...
Six Sigma Green Belt - Poka yake is best defined as a. improving machine effi...Six Sigma Green Belt - Poka yake is best defined as a. improving machine effi...
Six Sigma Green Belt - Poka yake is best defined as a. improving machine effi...Suma Kamadod
 
ESTIEM Lean Six Sigma Green Belt Project at Continental - Scrap Reduction
ESTIEM Lean Six Sigma Green Belt Project at Continental - Scrap ReductionESTIEM Lean Six Sigma Green Belt Project at Continental - Scrap Reduction
ESTIEM Lean Six Sigma Green Belt Project at Continental - Scrap ReductionESTIEM
 

What's hot (16)

IRJET- Optimization of Plastic Injection Molding
IRJET- Optimization of Plastic Injection MoldingIRJET- Optimization of Plastic Injection Molding
IRJET- Optimization of Plastic Injection Molding
 
ProjectReport_SPCinAM
ProjectReport_SPCinAMProjectReport_SPCinAM
ProjectReport_SPCinAM
 
Qnt 561 final exam view 369
Qnt 561 final exam view 369Qnt 561 final exam view 369
Qnt 561 final exam view 369
 
(New) mkt 571 mkt571 final exam entire answers with questions correct 100%
(New) mkt 571 mkt571 final exam entire answers with questions correct  100%(New) mkt 571 mkt571 final exam entire answers with questions correct  100%
(New) mkt 571 mkt571 final exam entire answers with questions correct 100%
 
Recent trends in rapid product development 2-3-4
Recent trends in rapid product development 2-3-4Recent trends in rapid product development 2-3-4
Recent trends in rapid product development 2-3-4
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
 
Project Management - Pmi’s opm3 is an example of a __________________ model...
Project Management - Pmi’s opm3 is an example of a   __________________ model...Project Management - Pmi’s opm3 is an example of a   __________________ model...
Project Management - Pmi’s opm3 is an example of a __________________ model...
 
Project Management - To determine the cost of particular element in advance o...
Project Management - To determine the cost of particular element in advance o...Project Management - To determine the cost of particular element in advance o...
Project Management - To determine the cost of particular element in advance o...
 
Project Management - A fundamental of ‘theory of constraints’ (toc) is to man...
Project Management - A fundamental of ‘theory of constraints’ (toc) is to man...Project Management - A fundamental of ‘theory of constraints’ (toc) is to man...
Project Management - A fundamental of ‘theory of constraints’ (toc) is to man...
 
Ops 571 final exam view 369
Ops 571 final exam view 369Ops 571 final exam view 369
Ops 571 final exam view 369
 
Six Sigma Green Belt - A green belt is going to monitor the number of defects...
Six Sigma Green Belt - A green belt is going to monitor the number of defects...Six Sigma Green Belt - A green belt is going to monitor the number of defects...
Six Sigma Green Belt - A green belt is going to monitor the number of defects...
 
Six Sigma Green Belt - A form, in either diagram or table format, that is pre...
Six Sigma Green Belt - A form, in either diagram or table format, that is pre...Six Sigma Green Belt - A form, in either diagram or table format, that is pre...
Six Sigma Green Belt - A form, in either diagram or table format, that is pre...
 
Six Sigma Green Belt - To determine the average number of nonconforming parts...
Six Sigma Green Belt - To determine the average number of nonconforming parts...Six Sigma Green Belt - To determine the average number of nonconforming parts...
Six Sigma Green Belt - To determine the average number of nonconforming parts...
 
Six Sigma Green Belt - Poka yake is best defined as a. improving machine effi...
Six Sigma Green Belt - Poka yake is best defined as a. improving machine effi...Six Sigma Green Belt - Poka yake is best defined as a. improving machine effi...
Six Sigma Green Belt - Poka yake is best defined as a. improving machine effi...
 
ESTIEM Lean Six Sigma Green Belt Project at Continental - Scrap Reduction
ESTIEM Lean Six Sigma Green Belt Project at Continental - Scrap ReductionESTIEM Lean Six Sigma Green Belt Project at Continental - Scrap Reduction
ESTIEM Lean Six Sigma Green Belt Project at Continental - Scrap Reduction
 
EARNED VALUE MANAGEMENT
EARNED VALUE MANAGEMENTEARNED VALUE MANAGEMENT
EARNED VALUE MANAGEMENT
 

Similar to IRJET- Achieving Total Quality Management in Construction Project using Six Sigma Concept

IRJET- Quality Audit of Public Building Project by using Six Sigma Techniques
IRJET- Quality Audit of Public Building Project by using Six Sigma TechniquesIRJET- Quality Audit of Public Building Project by using Six Sigma Techniques
IRJET- Quality Audit of Public Building Project by using Six Sigma TechniquesIRJET Journal
 
IRJET- Quality Improvement in Building Construction using Six Sigma
IRJET-  	  Quality Improvement in Building Construction using Six SigmaIRJET-  	  Quality Improvement in Building Construction using Six Sigma
IRJET- Quality Improvement in Building Construction using Six SigmaIRJET Journal
 
IRJET- Application of Lean Six Sigma Principles
IRJET-  	  Application of Lean Six Sigma PrinciplesIRJET-  	  Application of Lean Six Sigma Principles
IRJET- Application of Lean Six Sigma PrinciplesIRJET Journal
 
A LEAN SIX-SIGMA MANUFACTURING PROCESS CASE STUDY
A LEAN SIX-SIGMA MANUFACTURING PROCESS CASE STUDYA LEAN SIX-SIGMA MANUFACTURING PROCESS CASE STUDY
A LEAN SIX-SIGMA MANUFACTURING PROCESS CASE STUDYLinda Garcia
 
Six Sigma Implementation to reduce rejection rate of Pump Casings at local Ma...
Six Sigma Implementation to reduce rejection rate of Pump Casings at local Ma...Six Sigma Implementation to reduce rejection rate of Pump Casings at local Ma...
Six Sigma Implementation to reduce rejection rate of Pump Casings at local Ma...IOSR Journals
 
IE7610_REPORT_GROUP_8
IE7610_REPORT_GROUP_8IE7610_REPORT_GROUP_8
IE7610_REPORT_GROUP_8Parag Kapile
 
Elimination of rework in V Cap by Using Six Sigma Methodology
Elimination of rework in V Cap by Using Six Sigma MethodologyElimination of rework in V Cap by Using Six Sigma Methodology
Elimination of rework in V Cap by Using Six Sigma MethodologyIJERD Editor
 
Improve quality via qms through quality tools
Improve quality via qms through quality toolsImprove quality via qms through quality tools
Improve quality via qms through quality toolsIAEME Publication
 
Improve quality via qms through quality tools
Improve quality via qms through quality toolsImprove quality via qms through quality tools
Improve quality via qms through quality toolsIAEME Publication
 
IOP Conference Series Materials Science and EngineeringPA.docx
IOP Conference Series Materials Science and EngineeringPA.docxIOP Conference Series Materials Science and EngineeringPA.docx
IOP Conference Series Materials Science and EngineeringPA.docxvrickens
 
Adoption Of Six Sigma DMAIC To Reduce Cost Of Poor Quality
Adoption Of Six Sigma DMAIC To Reduce Cost Of Poor QualityAdoption Of Six Sigma DMAIC To Reduce Cost Of Poor Quality
Adoption Of Six Sigma DMAIC To Reduce Cost Of Poor QualitySabrina Baloi
 
IRJET- Agile Management in Construction Industry
IRJET-  	  Agile Management in Construction IndustryIRJET-  	  Agile Management in Construction Industry
IRJET- Agile Management in Construction IndustryIRJET Journal
 
Redesign and manufacturing by using dmadv method
Redesign and manufacturing by using dmadv methodRedesign and manufacturing by using dmadv method
Redesign and manufacturing by using dmadv methodeSAT Journals
 
IRJET- Construction Quality Management on Site
IRJET-  	  Construction Quality Management on SiteIRJET-  	  Construction Quality Management on Site
IRJET- Construction Quality Management on SiteIRJET Journal
 
An Application of DMAIC Methodology for Increasing the Yarn Quality in Textil...
An Application of DMAIC Methodology for Increasing the Yarn Quality in Textil...An Application of DMAIC Methodology for Increasing the Yarn Quality in Textil...
An Application of DMAIC Methodology for Increasing the Yarn Quality in Textil...IOSR Journals
 
APPLYING LEAN SIX SIGMA FOR WASTE REDUCTION IN A MANUFACTURING ENVIRONMENT
APPLYING LEAN SIX SIGMA FOR WASTE REDUCTION IN A MANUFACTURING ENVIRONMENT APPLYING LEAN SIX SIGMA FOR WASTE REDUCTION IN A MANUFACTURING ENVIRONMENT
APPLYING LEAN SIX SIGMA FOR WASTE REDUCTION IN A MANUFACTURING ENVIRONMENT Firdaus Albarqoni
 

Similar to IRJET- Achieving Total Quality Management in Construction Project using Six Sigma Concept (20)

IRJET- Quality Audit of Public Building Project by using Six Sigma Techniques
IRJET- Quality Audit of Public Building Project by using Six Sigma TechniquesIRJET- Quality Audit of Public Building Project by using Six Sigma Techniques
IRJET- Quality Audit of Public Building Project by using Six Sigma Techniques
 
IRJET- Quality Improvement in Building Construction using Six Sigma
IRJET-  	  Quality Improvement in Building Construction using Six SigmaIRJET-  	  Quality Improvement in Building Construction using Six Sigma
IRJET- Quality Improvement in Building Construction using Six Sigma
 
Ijebea14 275
Ijebea14 275Ijebea14 275
Ijebea14 275
 
IRJET- Application of Lean Six Sigma Principles
IRJET-  	  Application of Lean Six Sigma PrinciplesIRJET-  	  Application of Lean Six Sigma Principles
IRJET- Application of Lean Six Sigma Principles
 
A LEAN SIX-SIGMA MANUFACTURING PROCESS CASE STUDY
A LEAN SIX-SIGMA MANUFACTURING PROCESS CASE STUDYA LEAN SIX-SIGMA MANUFACTURING PROCESS CASE STUDY
A LEAN SIX-SIGMA MANUFACTURING PROCESS CASE STUDY
 
Six Sigma Implementation to reduce rejection rate of Pump Casings at local Ma...
Six Sigma Implementation to reduce rejection rate of Pump Casings at local Ma...Six Sigma Implementation to reduce rejection rate of Pump Casings at local Ma...
Six Sigma Implementation to reduce rejection rate of Pump Casings at local Ma...
 
IE7610_REPORT_GROUP_8
IE7610_REPORT_GROUP_8IE7610_REPORT_GROUP_8
IE7610_REPORT_GROUP_8
 
IJIRS_Improvement of Quality Sigma Level of Copper Terminal at Vertical Machi...
IJIRS_Improvement of Quality Sigma Level of Copper Terminal at Vertical Machi...IJIRS_Improvement of Quality Sigma Level of Copper Terminal at Vertical Machi...
IJIRS_Improvement of Quality Sigma Level of Copper Terminal at Vertical Machi...
 
Elimination of rework in V Cap by Using Six Sigma Methodology
Elimination of rework in V Cap by Using Six Sigma MethodologyElimination of rework in V Cap by Using Six Sigma Methodology
Elimination of rework in V Cap by Using Six Sigma Methodology
 
150110746014
150110746014150110746014
150110746014
 
Improve quality via qms through quality tools
Improve quality via qms through quality toolsImprove quality via qms through quality tools
Improve quality via qms through quality tools
 
Improve quality via qms through quality tools
Improve quality via qms through quality toolsImprove quality via qms through quality tools
Improve quality via qms through quality tools
 
IOP Conference Series Materials Science and EngineeringPA.docx
IOP Conference Series Materials Science and EngineeringPA.docxIOP Conference Series Materials Science and EngineeringPA.docx
IOP Conference Series Materials Science and EngineeringPA.docx
 
6 sigma
6 sigma6 sigma
6 sigma
 
Adoption Of Six Sigma DMAIC To Reduce Cost Of Poor Quality
Adoption Of Six Sigma DMAIC To Reduce Cost Of Poor QualityAdoption Of Six Sigma DMAIC To Reduce Cost Of Poor Quality
Adoption Of Six Sigma DMAIC To Reduce Cost Of Poor Quality
 
IRJET- Agile Management in Construction Industry
IRJET-  	  Agile Management in Construction IndustryIRJET-  	  Agile Management in Construction Industry
IRJET- Agile Management in Construction Industry
 
Redesign and manufacturing by using dmadv method
Redesign and manufacturing by using dmadv methodRedesign and manufacturing by using dmadv method
Redesign and manufacturing by using dmadv method
 
IRJET- Construction Quality Management on Site
IRJET-  	  Construction Quality Management on SiteIRJET-  	  Construction Quality Management on Site
IRJET- Construction Quality Management on Site
 
An Application of DMAIC Methodology for Increasing the Yarn Quality in Textil...
An Application of DMAIC Methodology for Increasing the Yarn Quality in Textil...An Application of DMAIC Methodology for Increasing the Yarn Quality in Textil...
An Application of DMAIC Methodology for Increasing the Yarn Quality in Textil...
 
APPLYING LEAN SIX SIGMA FOR WASTE REDUCTION IN A MANUFACTURING ENVIRONMENT
APPLYING LEAN SIX SIGMA FOR WASTE REDUCTION IN A MANUFACTURING ENVIRONMENT APPLYING LEAN SIX SIGMA FOR WASTE REDUCTION IN A MANUFACTURING ENVIRONMENT
APPLYING LEAN SIX SIGMA FOR WASTE REDUCTION IN A MANUFACTURING ENVIRONMENT
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...Call girls in Ahmedabad High profile
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 

Recently uploaded (20)

Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 

IRJET- Achieving Total Quality Management in Construction Project using Six Sigma Concept

  • 1. © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 310 Achieving Total Quality Management in Construction Project Using Six Sigma Concept Dr.Divakar.K1 and Nishaant.Ha2 1Associate Professor in Civil Engineering, Coimbatore Institute of Technology, Coimbatore-641014 2Assistant Professor in Civil Engineering, Kumaraguru College of Technology, Coimbatore-641049 ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - A Six Sigma approach is one of the most efficient quality improvement processes. In this study, six sigma concepts were applied in construction scheduling process to avoid delay as well as to maintain the quality of the construction activities. Detailedscheduleofthebuilding was analysed & also the updated schedule was verified. At this stage, DMAIC (Define, Measure, Analyse, Improve and Control) principle was implemented. The variation in the scheduling due to delay of the activities was noted down. Delay reasons and their impacts in the whole project were calculated. All delayed activities were considered as “Defects”. DPMO (Defects Per Million Opportunities) was calculated. By using this value, Sigma Level was identified. Pareto Chart Analysis was made. WiththehelpofSixSigma, ways to overcome schedule variation due to delay was recommended. Keywords: DMAIC, DPMO, Sigma Level, Pareto Chart. 1. INTRODUCTION In the current field of construction, time optimization as well as the quality control is one of the prime requirements. To achieve this, several quality control approaches and also delay reduction techniques are adopted and also followed in the construction field. This study aims to execute the construction activities as per the estimated schedule without any variation as well as with the required quality and satisfactionbythecustomer or the owner of the project. To obtain this, Six Sigma concepts and its principles were applied in the analysing or verifying processofconstructionscheduling,duringthe execution stage of the construction activities. DMAIC (Define, Measure, Analyse, Improve & Control) methodology was adopted. Hence, with the help of Six Sigma the ways to achieve Total Quality Management in construction are analysed in this study. 2. LITERATURE REVIEW Pande P et.al. (2000) explained the power of the sixsigma movement in the world’s most successful companies. Adan Valles et.al (2009) applied Six sigma project at a semiconductor company dedicated to the manufacture of circuit cartridges for inkjet printers. They were tested electrically in the final stage of the process measuring electrical characteristics to accept or reject them . Low Sui Pheng and Mok Sze Hui (2004) examined the strategies and concepts of Six Sigma and implemented those concepts in construction industry. A. D. Lade et.al. (2015) analysed the quality performance of Ready Mix Concrete (RMC) plant at Mumbai, India, using the six sigma philosophy had been evaluated using various quality tools and sigma value was calculated.Accordingto the sigma level, recommendations were given for the improvement. Seung Heon Han et.al. in their study they developed a general methodology to apply the six sigma principles on construction operations rather than construction materials in terms of the barometers to measure, evaluate, and improve construction performance. Lean and Six sigma inconstructionfieldwas analysed with the help of several literature reviews by Sunil V. Desale et.al. (2013). Abdulaziz Ali Banavi (2013) was developed and implemented methods toimprovethe performance and the efficiency of construction processes prior to and during the construction phase in Design-Bid- Build (DBB) projects. In order to accomplish these goals, the three methods Lean, Green, and Six-Sigma were implemented. The root causes behind waste generation were determined via developing and administrating a questionnaire to a local construction company. Mehmet Tolga Taner (2013) conducted a survey-based approach which is used to identify the Continuous Improvement(CI)initiativescommonlypractisedinlarge- scale Turkish construction companies as well as understanding the approach of these companies to Six Sigma. According to the questionnaire survey, the three most important Critical Success Factors lowering the performance of companies were found to be high costs, high amount of waste and lack of a well-implemented customer management system. Kuo-Liang Lee, and Yang Su (2013) were demonstrated a Six Sigma project of determining and improving the key input variables affecting the cracks in lightweight partition walls. The case study of residential building was taken in which six sigma was applied for internal finishing work, six sigma principle was adopted to improve quality and was checked against the sigma level by Sneha.P Sawant & Smitha V. Pataskar (2014). Theo C. Haupt et.al explained about Total Quality Management (TQM) and itsimplementationtechniquesin construction site to achieve quality in several accepts. H. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072
  • 2. © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 311 James Harrington et.al examined the quality and productivity problems and improvement opportunities that face the construction industry today were defined. The latest studies which focused on increase the business quality through implementing TQM in construction industry was pointed out and its suitable applications in the different phases of project constructionwasidentified by Ahmed S. Agha. The level of effectiveness of the implementation of TQM principles by the construction contractors was identified by Abu Hassan et.al. Khaled F. Sherif examined the existing barriersofTQMandin-depth survey was conducted in two Libyan construction companies. Low Sui Pheng et.al (2014) created a framework for implementing TQM in construction. 3. SIX SIGMA CONCEPT IN CONSTRUCTION SCHEDULING The major aim of six sigma approach is to reduce the defects in the process. The level of six sigma value is 3.4 Defects Per Million Opportunities (DPMO). In scheduling process, all delayed activities and the activities without satisfying the predefined quality requirements are considered as “defects”. Then, number of completed activities is considered as total number of opportunities. With the help of these data, Sigma level can be calculated and the percentage of accuracy can be determined. Accuracy will gets increased by increasing the level of sigma value. To overcome these defects and also to improve the sigma value / accuracy of the project, predefining the possibilities of defects opportunities should be worked out during the pre-execution stage itself and possible counteractions are to be analysed. During the construction execution stage, updating the schedule should be done several times and sigma value is calculated at every stage respectively.Then, possible counteractions forthe remaining worksshouldbefocused accurately and also necessary steps should be taken to avoid same types of defects in the remaining project and have to work according to that. 4. METHODOLOGY DMAIC (Define, Measure, Analyse, Improve & Control) Methodology is one of the prime factors of six sigma approach. Hence this methodology wascarried out in this study.Delay Reduction and client satisfaction were considered as CTQ (Critical To Quality) factor. 4.1 Define During Define Phase, Detailed updated schedule was analysed. Basic details of the project are given in (Table 1) Table 1 Observations Type of Project IT Building Total Area 2.2 acres Built up Area 1.7 acres No. of Floors B2 + (G+13) Project started on 01/04/2015 Estimated Duration 365 days Updated schedule as on 19/02/2016 Total no. of completed activities 202 No. of delayed activities 53 Re-estimatedcompletionas on 15/07/2016 4.2 Measure & Analyse Phase In this phase, Defects Per Million Opportunities (DPMO), Sigma Level and percentage of accuracy were calculated. DPMO was calculated using the following formula, DPMO = ((1,000,000)X) / YZ Where, X - Number of Defects Y - Number of Units Z - Number of Defect Opportunities/Unit In this study, Number of Defect Opportunities is the chances or test by means of which we identify whether the activities delayed or not. Hence, itwastakenas1.After applying all the values in the above formula, DPMO - 262376.2 Sigma level was identified by interpolating the values from the following standard table 2 Table 2 Sigma Levels and their DPMOs Sigma Value DPMO 1 690,000 2 308,000 3 66,800 4 6,210 5 320 6 3.4 International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072
  • 3. © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 312 Sigma Level - 2.1 Percentage of accuracy & defective percentage was identified with the help of sigma level value.Thefollowing table 3 was used for calculating the percentage of accuracy. Table 3 Sigma Levels v/s Percentage Accuracy& Defective Percentage Sigma Value Percentage Accuracy (%) Defective Percentage (%) 1 30.9 69.1 2 69.1 30.9 3 93.3 6.7 4 99.38 0.62 5 99.77 0.023 6 99.99966 0.00034 Percentage Accuracy - 71.52% Defective Percentage - 28.48% By referring that updated schedule, delayed activities were categorized separately. Delayed duration for each activity was mentioned. According to the higher delayed duration, the rank was given. Major delayed activities were identified. Then, delay reasons for the delays were analyzed and noted down. With respect to maximum priority, delay reasons were tabulated (Table 4). Table 4 Delay Reasons and its Priority S.No Delayed Reasons No. of activities delayed No. of days delayed 1 Shortage of Labour 11 138 2 Delay in drawing submission & approval 6 73 3 Delay due to verification & submission of Tender documents 7 70 4 Delay due to providing payment by the client 4 48 5 Slow Preparation of documents 13 45 6 Insufficient information about the work 1 35 7 Plastering Delayed 1 30 8 Delay in procurement of materials 4 26 9 Rain Interruption 2 25 10 PO delayed 2 23 11 Delay in concreting 1 10 12 Delay from the client side 1 10 Pareto chart analysis was made.Paretochartconsistsof both line graph and the bar chart. In descending order individual values are mentioned and denoted as bars. Cumulative total of all individual values are denoted as line graph. In this study, delay reasons were mentioned in x-axis & percentage of delay was mentioned in y-axis. Fig. 1 Pareto Chart Analysis This analysis showed that 50% of delay reasons caused 80% of delay. Hence, we have to eliminate those delays having higher priority at the early stage of the project itself. Before executing the construction work, possibilitiesof delay have to be analysed and worked out. All these analysis should be done for those predicted delays. With respect to the out comings, possible counteractionshould be taken and maintained properly. 4.3 Improve & Control Phase In this phase, general recommendations to overcome the delays were given. Trail sigma calculations were made. Then steps to be applied to achieve higher efficiency in construction projects were discussed. General recommendations to overcome the delays are shown in the following table 5 International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072
  • 4. © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 313 Table 5 General Recommendations S.No Delayed Reasons Recommendations 1 Shortage of Labour Resource Leveling, Resource allocations should be done properly. 2 Delay in drawing submission & approval Detailed information about the particular work is to be analyzed and given to the design department. So that they can preparethedrawings in time. 3 Delay due to verification & submission of Tender documents Proper contractor team should be employed 4 Delay due to providing payment by the client Properagreementshould be framed & payment should be given according to that agreement 5 Slow Preparation of documents Accurate information should be given. Should have a proper communication 6 Insufficient information about the work Before executing the particular work, all required information should be gathered and documented properly 7 Delay in procurement of materials Material Optimization should done properly according to the type of the work 8 PO delayed Execution department should inform the purchase department about their material requirementsinadvance. 9 Delay in concreting ResourceLevelingshould be done 10 Delay from the client side Client & the contractor should have a proper communication. They should work accordingto the agreement 5. TRIAL SIGMA CALCULATION 1. By seeing the delayed activities, it was found that the many delay parameters werecommon&manydelays were occurred due to the delay of the preceding activity. 2. 50% of delayed reasons caused 80% of delay in duration of the project. 3. If DMAIC principle is applied and the parameters are identified at the starting stage itself, we can improve the efficiency by achieving the several milestones of the project in time. 4. Assuming, that the recommendations given here are applied at the early stage itselfand also assume that the major six topmost delayed reasons are rectified 5. According to the schedule, 42 activities willget free. Now, Defects will be 11 out of 202 opportunities. 6. DPMO & Sigma Level is calculatedasdone earlier.The obtained values are, DPMO = 54455.45 Sigma Level = 3.1 7. This value showed that the level of sigma value gets increased from 2.1 to 3.1, which means the level of accuracy got increased. 8. The percentage of accuracy for the sigma value 3.1 is 93.91%. (i.e.) 22.39% of accuracy is increased from the previous accuracy. (Previous accuracy was 71.52%) 9. Hence, its proved that applying Six Sigma principles in construction scheduling, the efficiency of the project can be increased in several aspects. 6. STEPS TO BE CARRIED OUT - RECOMMENDATIONS 1. Several milestones are to be fixed. Each mile stone will act as a short-term goal according to Six Sigma concept. 2. For each milestone, we have to calculate the major parameters of delay according to the type of activity. 3. By analyzing this, we can avoid several shortcomings at the early stage itself. 4. Hence, it will show the way to complete those particular activities in time. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072
  • 5. © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 314 5. We can check the efficiency of the schedule by calculating the sigma value and also percentage of accuracy at the end of each milestone by analyzing the updated schedule. 6. At this stage, we can re-estimate the schedule for the remaining works as per the time limitations, resources limitations, client specifications, etc… 7. We can also take preventive measures to avoid same kind of delays in the remaining construction works. 8. During the execution of work,control limitsshouldbe fixed and have to work accordingtothecontrol limits. 9. Control limits should be fixed within the client specification limit to achievemaximum efficiencyand client satisfaction. (i.e.) For example, if the clients requirement for completing the particular activity with 100% accuracy within a specified duration. We have to fix the control limit as less than the specified duration and have to work accordingtothatduration. Hence, we can obtain higher level of sigma & also we can have a proper control in the on-going project. 7. CONCLUSION In construction industry, six sigma concepts are not popularized. But, the efficiency of this process is tremendous. We can achieve near perfect products or activities with the help of six sigma approach in construction. Construction scheduling is one of the prime factors in construction projects. By applying six sigma approaches and maintaining the activities in the proper way as per DMAIC principles, we can increase the overall efficiency of the project. Customer satisfactioncanalsobe achieved. This study showed that, Application of Six Sigma concepts in construction will results Total Quality Management (TQM), proper time management, quality control, etc… Hence, this process in construction will also give more efficiency in almost all construction project management approaches. REFERENCES [1] A. D. Lade, A. S. Nair , P. G. Chaudhary, N. R. Gupta : DOI: 10.9790/1684-12210104www.iosrjournals.org 1 | Page “Implementing Six Sigma Approach for Quality Evaluation of a RMC Plant at Mumbai, India” IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 2 Ver. I (Mar - Apr. 2015), PP 01-04 [2] Adan Valles, Jaime Sanchez, Salvador Noriega, and Berenice Gómez Nuñez “ImplementationofSixSigma in a Manufacturing Process: A Case Study” International Journal ofIndustrial Engineering,16(3), 171-181, 2009. [3] AbdulazizAliBanavi“Improvingconstruction process by integrating Green, Lean & Six Sigma” journal from University of Pittsburg, 2013 [4] Kuo-Liang Lee, and Yang Su (Taiwan) “Applying Six Sigma to Quality Improvement in Construction”, American Society of Civil Engineers.(2013) [5] Low Sui Pheng and Mok Sze Hui “Implementing and Applying Six Sigma in Construction” Journal of Construction Engineering and Management, Vol.130, No. 4, August 1, 2004 [6] Mehmet Tolga Taner, “Critical Success FactorsforSix Sigma Implementation in Large-scale Turkish Construction Companies” International Review of Management and Marketing Vol. 3, No. 4, 2013, pp.212-225 [7] Pande, P., Neuman, R. P. & Cavanagh, R. R. (2000) “The six sigma way: how Ge, Motora and other top companies are honing their performance”. [8] Seung Heon Han, M.ASCE; Myung Jin Chae, Ph.D., P.E.; Keon Soon Im, P.E.; and Ho Dong Ryu “Six Sigma- Based Approach to Improve Performance in Construction Operations” Journal of Management in Engineering, Vol. 24, No.1 [9] Sneha.P Sawant & Smitha V. Pataskar, “Applying Six Sigma Principles in Construction Industry for Quality Improvement” journal on advances in engineering & technology ICAET – 2014 [10] Sunil V. Desale, Dr. S. V. Deodhar . “Lean Six Sigma Principal in Construction: A Literature Review Related to Conclusions” International Journal of Emerging Technology and Advanced Engineering, Volume 3, Issue 5, May 2013) [11] Theo C. Haupt, Daniel E. Whiteman “Implementing Total Quality Management on Construction Sites” [12] The TQM Journal Emerald Article: Applying TQM to the construction industry - H. James Harrington, Frank Voehl, Hal Wiggin [13] Total Quality Management In Construction Industry - Ahmed S. Agha [14] Total Quality Management Practices in Large Construction Companies: A CaseofOmanAbuHassan Bin Abu Bakar, Khalid Bin Ali and Eziaku Onyeizu International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072
  • 6. © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 315 School of Housing, Building and Planning University Sains Malaysia, 11800 Penang, Malaysia [15] Total Quality Management and Construction Project Management in Libya By Khaled F. Sherif [16] “Implementing Total Quality Management in Construction Firms” by Low Sui Pheng and Jasmine Ann Teo, Journal ofManagementinEngineering,2004 International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 06 | June 2018 www.irjet.net p-ISSN: 2395-0072