SlideShare a Scribd company logo
Basic Block Laying
Tutor Copy
Types of building blocks
The face side of a block usually measures
440mm x 215mm
The thickness can vary from 75mm up to 300mm
The weight from 9.9kg to more than 30kg.
75mm – 300mm
215mm
440mm
Blocks are manufactured to meet compressive strength
standards of between 2.8N/mm² and 7N/mm².
Blocks can be solid, hollow or cellular.
Some blocks have insulating material bonded to one
face or inserted in the voids
Blocks are available in a range of densities.
Blocks that are light in weight are usually less dense
because they are made from an aerated mix.
The heavier blocks are denser.
Aerated block
Load bearing blocks
These blocks are usually made of Portland cement
and a variety of aggregates. The blocks are precast in
moulds and compacted with the aid of vibration, or in
a moulding machine involving the use of compressed
air, or a combination of both.
Block making machine
Non-load bearing blocks
These blocks are usually made of Portland cement and a
variety of lightweight aggregates; therefore they are not
as dense or as strong as load-bearing blocks.
These blocks are pre-cast in moulds or they can be
produced in slab form and cut to size when set.
Two well known manufacturers are Thermalite and
Celcon.
Aerated block making
Lightweight Blocks
These blocks are made from lightweight or low
density materials such as fuel-ash, clinker, or
lightweight aggregates bonded together with
cement.
They are easy to lift and handle and have good
thermal and sound properties
They can absorb water and are be easily broken
during handling and construction.
Lightweight blocks can be cut with a bolster chisel / hammer,
a hand saw or power saw.
It is good working practice to secure blocks when cutting
with hand or powered tools.
Alternative
methods of
bonding a
return quoin.
Special blocks
Many manufacturers provide special blocks that assist in the
bonding and prevent wastage.
These blocks range from coursing blocks to half, quarter and
three-quarter blocks. Other special blocks include return and
reveal blocks which are used to close the cavity at door and
window openings.
Special / Coursing Blocks
To maintain bond within a wall it may be necessary to use
either coursing bricks or blocks. These can be cut from a
whole block or special blocks manufactured to those sizes.
These blocks are built into the
walling at junctions and over
openings in the wall. Ordinary
facing or common bricks
should NEVER be used for this
purpose.
Delivery and storage
Blocks are delivered on site as banded packs or on
pallets.
The blocks must be stacked on a hard level base, or on
battens on drained even ground.
Loose blocks should be stacked
as they are used, i.e. on edge,
and the height of the stack
should be limited to two metres.
Delivery and storage
Blocks may be delivered with or without a shrink-wrap
covering, but all blocks should be covered from the elements
until required for use.
The packs should be placed on pallets if possible for ease of
handling and delivery around the site by a forklift truck.
Unloading
Packs of
blocks
Different finishes to Blockwork.
• Rendering
• External cladding
• Plaster dab method
• Timber batten method
• Metal firring systems
Plug and screw
This is a common type of fixing specially designed for fixing
to all blocks. It consists of a plastic plug which is driven into
a pre-drilled hole. A screw can then be driven into the
hollow centre of the fixing.
Fixings and finishes
Blockwork below ground level
Trench Blocks
These blocks are bigger in size than normal blocks with a face
dimension size of 440mm x 215mm and are available
in a range of thicknesses ranging from 255mm to 355mm.
One trench block is equivalent in size to 2 aggregate blocks,
or 12 bricks, plus wall ties and infill.
Blockwork below ground level
The following typical details illustrate the proper use
of blocks below DPC level.
Render Coating
Painted wall
DPC
Trench block
Plaster
Ground floor
Foundation
Typical solid
foundation in
blockwork
Blocks used below ground level
Blocks are available in a weight less than 20kg with handholds and will
comply with CDM Regulations which cover health and safety issues on site
for repetitive handling.
Solid Blockwork Foundation with
an Insulated Cavity Wall
This form of construction incorporates a blockwork
foundation below ground level with a traditional brick and
block cavity wall above. The cavity can be partially filled or
full filled as required.
This type of construction offers a structure with good sound
and thermal insulation qualities.
Solid Blockwork foundation with
an insulated cavity wall
Facing
Brickwork
DPC
Plaster
Partial fill cavity insulation
Ground floor
Foundation
Trench Blockwork
Block cavity wall foundation
This is an alternative solid block
foundation construction. The blocks
below ground level are laid to form a
cavity which is then filled up to ground
level with a cement / aggregate mix.
The cavity can be partially filled or
fully filled as required.
Block cavity wall foundation
Facing
Brickwork
DPC
Plaster
Partial fill cavity insulation
Ground floor
Foundation
Cavity blockwork
Cement aggregate
mix
Apart from the size of the blocks the building operations
used to erect walls are the same as for brickwork.
There are 10 blocks per square metre as opposed to 60
bricks per square metre
Never mix different types of blocks in the same run of walling,
and do not use common or facing bricks as closers as they
will reduce the thermal and sound insulation qualities of the
blockwork.
Always set out the first course dry so that the position of cut
blocks can be found.
Any adjustment to the width of joints should be made to
achieve and maintain a bond within the wall.
This is called “Dry Bonding”
Blocks should be laid to a regular bond, usually half bond
where possible.
Never lay blocks to a bond of less than quarter bond.
It is not always convenient to
build a junction wall at the same
time as the main wall.
Tee junctions are normally
bonded, or ties can be use with a
straight joint.
Indents may be left to allow
bonding to occur at a later stage.
Indents are gaps where blocks
will be inserted at a later date.
Wall ties
Bonded
Junctions to walls
Junctions to walls
The diagram shows a typical method of constructing
junction walls.
Brick outer leaf Inner leaf walls 100mm
Separating wall 100mm
Nominal 8mm internal render scratch finish
Partial fill
cavity wall 12.5mm gypsum board
mounted on dabs
Tied junction
100mm partition
75mm / 275mm min
Bonding should be set out so that lintels bear preferably
on a whole block. If this is not possible, a minimum two-
thirds length block is acceptable but definitely not less.
(normally by at least 150mm.)
Some types of hollow and cellular blocks may need to be
filled under lintel ends to provide sufficient bearing
strength.
In windy weather, block walls should be restrained by
temporary propping.
In windy weather, the day work lift height may be reduced
as an alternative to propping.
Blocks should be kept dry before use.
Use only specified mortar mixes and ensure that bed and cross
joints are solidly filled.
Maintain gauge to correspond with brickwork gauge.
Building with blocks is quick and the weight of the blocks could
cause fresh soft mortar bed to be squeezed out. This could
result in collapse / loss of gauge / loss of plumb.
Internal Blockwork External Brickwork
Cavity
insulation
and wall
ties
Typical cavity wall construction
using facing bricks and blocks
Closing cavities of external walling
built with blocks
With all cavity walls it is essential that the cavity be closed at
reveals, such as door and window openings. This can be
achieved by using cut blocks or by using special reveal blocks
manufactured for the purpose.
Cavity wall closers
Another way of sealing the cavity at openings is to use
ready made cavity closers. These are usually made from
tough plastic and internally insulated to prevent cold
bridging. They also have provision for fixing clips to be
attached and built in as the brick / block work proceeds.
For bonding purposes, three courses of brickwork are equal
to one course of blockwork.
This makes bonding simple as long as both bricks and blocks
are kept accurately gauged.
Plaster or smooth faced finish
Solid internal wall
Cavity partition wall
Internal plasterSmooth faced blockwork

More Related Content

What's hot

Student l1 blockwork
Student l1 blockworkStudent l1 blockwork
Student l1 blockwork
Luke D'Arcy
 
Tutor cavity wall construction .ppt 1
Tutor cavity wall construction .ppt 1Tutor cavity wall construction .ppt 1
Tutor cavity wall construction .ppt 1
Luke D'Arcy
 
Tutor l1 blockwork
Tutor l1 blockworkTutor l1 blockwork
Tutor l1 blockwork
Luke D'Arcy
 
Cavity wall
Cavity wall Cavity wall
Cavity wall
Malay Talaviya
 
Cavity walls
Cavity wallsCavity walls
Cavity walls
Mani Das
 
Tutor wall ties in cavity walls .ppt 2
Tutor wall ties in cavity walls .ppt 2Tutor wall ties in cavity walls .ppt 2
Tutor wall ties in cavity walls .ppt 2
Luke D'Arcy
 
Cavity wall
Cavity wallCavity wall
Cavity wall
Krishna Prakash
 
Tutor preventing dampness in cavity walls .ppt 3
Tutor preventing dampness in cavity walls .ppt 3Tutor preventing dampness in cavity walls .ppt 3
Tutor preventing dampness in cavity walls .ppt 3
Luke D'Arcy
 
Tutor solid ground floors
Tutor solid ground floors Tutor solid ground floors
Tutor solid ground floors
Luke D'Arcy
 
Tutor cavity insulation .ppt 4
Tutor cavity insulation .ppt 4Tutor cavity insulation .ppt 4
Tutor cavity insulation .ppt 4
Luke D'Arcy
 
Wall types
Wall typesWall types
Wall types
Robbie Blake
 
Tutor solid wall and arches
Tutor solid wall and archesTutor solid wall and arches
Tutor solid wall and arches
Luke D'Arcy
 
Cavity walls
Cavity wallsCavity walls
Cavity walls
Tanisha Agarwal
 
Tutor masonry cladding ppt 2
Tutor masonry cladding ppt 2Tutor masonry cladding ppt 2
Tutor masonry cladding ppt 2
Luke D'Arcy
 
Chapter 4 (e) cavity walls
Chapter 4 (e) cavity wallsChapter 4 (e) cavity walls
Chapter 4 (e) cavity walls
KHUSHBU SHAH
 
Tutor solid walls c and g level2
Tutor solid walls c and g level2Tutor solid walls c and g level2
Tutor solid walls c and g level2
Luke D'Arcy
 

What's hot (20)

Cavity walls
Cavity wallsCavity walls
Cavity walls
 
Student l1 blockwork
Student l1 blockworkStudent l1 blockwork
Student l1 blockwork
 
Cavity Wall Ties
Cavity Wall TiesCavity Wall Ties
Cavity Wall Ties
 
Tutor cavity wall construction .ppt 1
Tutor cavity wall construction .ppt 1Tutor cavity wall construction .ppt 1
Tutor cavity wall construction .ppt 1
 
Tutor l1 blockwork
Tutor l1 blockworkTutor l1 blockwork
Tutor l1 blockwork
 
Cavity wall
Cavity wall Cavity wall
Cavity wall
 
Cavity walls
Cavity wallsCavity walls
Cavity walls
 
Tutor wall ties in cavity walls .ppt 2
Tutor wall ties in cavity walls .ppt 2Tutor wall ties in cavity walls .ppt 2
Tutor wall ties in cavity walls .ppt 2
 
Cavity wall
Cavity wallCavity wall
Cavity wall
 
Tutor preventing dampness in cavity walls .ppt 3
Tutor preventing dampness in cavity walls .ppt 3Tutor preventing dampness in cavity walls .ppt 3
Tutor preventing dampness in cavity walls .ppt 3
 
Tutor solid ground floors
Tutor solid ground floors Tutor solid ground floors
Tutor solid ground floors
 
Tutor cavity insulation .ppt 4
Tutor cavity insulation .ppt 4Tutor cavity insulation .ppt 4
Tutor cavity insulation .ppt 4
 
Wall types
Wall typesWall types
Wall types
 
Tutor solid wall and arches
Tutor solid wall and archesTutor solid wall and arches
Tutor solid wall and arches
 
Masonry part 3
Masonry part 3Masonry part 3
Masonry part 3
 
Cavity walls
Cavity wallsCavity walls
Cavity walls
 
ADVANTAGES OF CAVITY WALLS
ADVANTAGES OF CAVITY WALLSADVANTAGES OF CAVITY WALLS
ADVANTAGES OF CAVITY WALLS
 
Tutor masonry cladding ppt 2
Tutor masonry cladding ppt 2Tutor masonry cladding ppt 2
Tutor masonry cladding ppt 2
 
Chapter 4 (e) cavity walls
Chapter 4 (e) cavity wallsChapter 4 (e) cavity walls
Chapter 4 (e) cavity walls
 
Tutor solid walls c and g level2
Tutor solid walls c and g level2Tutor solid walls c and g level2
Tutor solid walls c and g level2
 

Similar to Tutor l1 blockwork

Concrete Block Walling
Concrete Block WallingConcrete Block Walling
Concrete Block Walling
doogstone
 
walls Construction.ppt
walls Construction.pptwalls Construction.ppt
walls Construction.ppt
jiteshdhule1
 
Introduction to Blockwork
Introduction to BlockworkIntroduction to Blockwork
Introduction to Blockwork
Steve Jarvis
 
Masonry of Building
Masonry of Building Masonry of Building
Masonry of Building
Yasir Hussain
 
Rat Trap Bond - Advantages, Disadvantages, Construction, Purpose, Estimation ...
Rat Trap Bond - Advantages, Disadvantages, Construction, Purpose, Estimation ...Rat Trap Bond - Advantages, Disadvantages, Construction, Purpose, Estimation ...
Rat Trap Bond - Advantages, Disadvantages, Construction, Purpose, Estimation ...
ADNAN AHMAD
 
the house
 the house the house
the house
catherinelindsay
 
Glass blocks
Glass blocksGlass blocks
Glass blocks
sonali parashar
 
Masonary wall
Masonary wallMasonary wall
Masonary wall
Prabhat chhirolya
 
Formwork by chakamba john
Formwork by chakamba johnFormwork by chakamba john
Formwork by chakamba john
John Chakamba
 
Lesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxLesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptx
sydneyaugust1
 
not all done & not all wording showing
not all done & not all wording showingnot all done & not all wording showing
not all done & not all wording showing
Barbara Holler
 
Partition walls
Partition wallsPartition walls
Partition walls
Aglaia Connect
 
Walls.ppt
Walls.pptWalls.ppt
Walls.ppt
AQIBIMRAN3
 
Partition System in building construction
Partition System in building constructionPartition System in building construction
Partition System in building construction
SanaFarooqui19
 
Bonding in brickwork (1)
Bonding in brickwork (1)Bonding in brickwork (1)
Bonding in brickwork (1)
CynthiaOchieng3
 
Types of masonry walls
Types of masonry wallsTypes of masonry walls
Types of masonry walls
Mohit Dwivedi
 
Masonry Structures dfgfdgfgfgbnnvgdfdsfdffdg
Masonry Structures dfgfdgfgfgbnnvgdfdsfdffdgMasonry Structures dfgfdgfgfgbnnvgdfdsfdffdg
Masonry Structures dfgfdgfgfgbnnvgdfdsfdffdg
SanjayExtreme
 
AAC Installation Guidelines
AAC Installation GuidelinesAAC Installation Guidelines
AAC Installation GuidelinesBENAY MUNDA
 
Cavity walls
Cavity wallsCavity walls
Cavity walls
Rimpi Baro
 

Similar to Tutor l1 blockwork (20)

Concrete Block Walling
Concrete Block WallingConcrete Block Walling
Concrete Block Walling
 
walls Construction.ppt
walls Construction.pptwalls Construction.ppt
walls Construction.ppt
 
Introduction to Blockwork
Introduction to BlockworkIntroduction to Blockwork
Introduction to Blockwork
 
Masonry of Building
Masonry of Building Masonry of Building
Masonry of Building
 
Rat Trap Bond - Advantages, Disadvantages, Construction, Purpose, Estimation ...
Rat Trap Bond - Advantages, Disadvantages, Construction, Purpose, Estimation ...Rat Trap Bond - Advantages, Disadvantages, Construction, Purpose, Estimation ...
Rat Trap Bond - Advantages, Disadvantages, Construction, Purpose, Estimation ...
 
the house
 the house the house
the house
 
Glass blocks
Glass blocksGlass blocks
Glass blocks
 
Masonary wall
Masonary wallMasonary wall
Masonary wall
 
Formwork by chakamba john
Formwork by chakamba johnFormwork by chakamba john
Formwork by chakamba john
 
Lesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxLesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptx
 
Bolster
BolsterBolster
Bolster
 
not all done & not all wording showing
not all done & not all wording showingnot all done & not all wording showing
not all done & not all wording showing
 
Partition walls
Partition wallsPartition walls
Partition walls
 
Walls.ppt
Walls.pptWalls.ppt
Walls.ppt
 
Partition System in building construction
Partition System in building constructionPartition System in building construction
Partition System in building construction
 
Bonding in brickwork (1)
Bonding in brickwork (1)Bonding in brickwork (1)
Bonding in brickwork (1)
 
Types of masonry walls
Types of masonry wallsTypes of masonry walls
Types of masonry walls
 
Masonry Structures dfgfdgfgfgbnnvgdfdsfdffdg
Masonry Structures dfgfdgfgfgbnnvgdfdsfdffdgMasonry Structures dfgfdgfgfgbnnvgdfdsfdffdg
Masonry Structures dfgfdgfgfgbnnvgdfdsfdffdg
 
AAC Installation Guidelines
AAC Installation GuidelinesAAC Installation Guidelines
AAC Installation Guidelines
 
Cavity walls
Cavity wallsCavity walls
Cavity walls
 

More from Luke D'Arcy

Tutor types of foundation
Tutor types of foundation Tutor types of foundation
Tutor types of foundation
Luke D'Arcy
 
Tutor transferring levels
Tutor transferring levels Tutor transferring levels
Tutor transferring levels
Luke D'Arcy
 
Tutor sustainability
Tutor sustainabilityTutor sustainability
Tutor sustainability
Luke D'Arcy
 
Tutor stability
Tutor stability Tutor stability
Tutor stability
Luke D'Arcy
 
Tutor site clearance
Tutor site clearance Tutor site clearance
Tutor site clearance
Luke D'Arcy
 
Tutor retaining reinforced brickwork
Tutor retaining reinforced brickwork Tutor retaining reinforced brickwork
Tutor retaining reinforced brickwork
Luke D'Arcy
 
Tutor brickwork below ground level
Tutor brickwork below ground level Tutor brickwork below ground level
Tutor brickwork below ground level
Luke D'Arcy
 
Basic bricklaying skills power point 2015
Basic bricklaying skills power point 2015Basic bricklaying skills power point 2015
Basic bricklaying skills power point 2015
Luke D'Arcy
 
Health and safety c and g
Health and safety c and gHealth and safety c and g
Health and safety c and g
Luke D'Arcy
 
Tutor methods of communication ppt2
Tutor methods of communication ppt2Tutor methods of communication ppt2
Tutor methods of communication ppt2
Luke D'Arcy
 
Tutor construction administration documents ppt3
Tutor construction administration documents ppt3Tutor construction administration documents ppt3
Tutor construction administration documents ppt3
Luke D'Arcy
 
Tutor construction activity documents ppt4
Tutor construction activity documents ppt4Tutor construction activity documents ppt4
Tutor construction activity documents ppt4
Luke D'Arcy
 
Tutor communication skills ppt1
Tutor communication skills ppt1Tutor communication skills ppt1
Tutor communication skills ppt1
Luke D'Arcy
 
Tutor isolated and attached piers .ppt1
Tutor isolated and attached piers .ppt1Tutor isolated and attached piers .ppt1
Tutor isolated and attached piers .ppt1
Luke D'Arcy
 
Tutor lintels .ppt 6
Tutor lintels .ppt 6Tutor lintels .ppt 6
Tutor lintels .ppt 6
Luke D'Arcy
 
Tutor mortars ppt 1a
Tutor mortars ppt 1aTutor mortars ppt 1a
Tutor mortars ppt 1a
Luke D'Arcy
 
Health and Safety in Construction PPT
Health and Safety in Construction  PPTHealth and Safety in Construction  PPT
Health and Safety in Construction PPT
Luke D'Arcy
 
Tutor types of foundations
Tutor types of foundationsTutor types of foundations
Tutor types of foundations
Luke D'Arcy
 
Tutor transferring levels
Tutor transferring levels Tutor transferring levels
Tutor transferring levels
Luke D'Arcy
 
Solid Ground Floors
 Solid Ground Floors  Solid Ground Floors
Solid Ground Floors
Luke D'Arcy
 

More from Luke D'Arcy (20)

Tutor types of foundation
Tutor types of foundation Tutor types of foundation
Tutor types of foundation
 
Tutor transferring levels
Tutor transferring levels Tutor transferring levels
Tutor transferring levels
 
Tutor sustainability
Tutor sustainabilityTutor sustainability
Tutor sustainability
 
Tutor stability
Tutor stability Tutor stability
Tutor stability
 
Tutor site clearance
Tutor site clearance Tutor site clearance
Tutor site clearance
 
Tutor retaining reinforced brickwork
Tutor retaining reinforced brickwork Tutor retaining reinforced brickwork
Tutor retaining reinforced brickwork
 
Tutor brickwork below ground level
Tutor brickwork below ground level Tutor brickwork below ground level
Tutor brickwork below ground level
 
Basic bricklaying skills power point 2015
Basic bricklaying skills power point 2015Basic bricklaying skills power point 2015
Basic bricklaying skills power point 2015
 
Health and safety c and g
Health and safety c and gHealth and safety c and g
Health and safety c and g
 
Tutor methods of communication ppt2
Tutor methods of communication ppt2Tutor methods of communication ppt2
Tutor methods of communication ppt2
 
Tutor construction administration documents ppt3
Tutor construction administration documents ppt3Tutor construction administration documents ppt3
Tutor construction administration documents ppt3
 
Tutor construction activity documents ppt4
Tutor construction activity documents ppt4Tutor construction activity documents ppt4
Tutor construction activity documents ppt4
 
Tutor communication skills ppt1
Tutor communication skills ppt1Tutor communication skills ppt1
Tutor communication skills ppt1
 
Tutor isolated and attached piers .ppt1
Tutor isolated and attached piers .ppt1Tutor isolated and attached piers .ppt1
Tutor isolated and attached piers .ppt1
 
Tutor lintels .ppt 6
Tutor lintels .ppt 6Tutor lintels .ppt 6
Tutor lintels .ppt 6
 
Tutor mortars ppt 1a
Tutor mortars ppt 1aTutor mortars ppt 1a
Tutor mortars ppt 1a
 
Health and Safety in Construction PPT
Health and Safety in Construction  PPTHealth and Safety in Construction  PPT
Health and Safety in Construction PPT
 
Tutor types of foundations
Tutor types of foundationsTutor types of foundations
Tutor types of foundations
 
Tutor transferring levels
Tutor transferring levels Tutor transferring levels
Tutor transferring levels
 
Solid Ground Floors
 Solid Ground Floors  Solid Ground Floors
Solid Ground Floors
 

Recently uploaded

Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
MIRIAMSALINAS13
 
678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf
CarlosHernanMontoyab2
 
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdfAdversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Po-Chuan Chen
 
Honest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptxHonest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptx
timhan337
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
Thiyagu K
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
Jisc
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
GeoBlogs
 
Embracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativeEmbracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic Imperative
Peter Windle
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
beazzy04
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
Vikramjit Singh
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
Anna Sz.
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 

Recently uploaded (20)

Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
 
678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf
 
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdfAdversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
 
Honest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptxHonest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptx
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
Embracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativeEmbracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic Imperative
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 

Tutor l1 blockwork

  • 3. Types of building blocks The face side of a block usually measures 440mm x 215mm The thickness can vary from 75mm up to 300mm The weight from 9.9kg to more than 30kg. 75mm – 300mm 215mm 440mm
  • 4. Blocks are manufactured to meet compressive strength standards of between 2.8N/mm² and 7N/mm². Blocks can be solid, hollow or cellular. Some blocks have insulating material bonded to one face or inserted in the voids
  • 5. Blocks are available in a range of densities. Blocks that are light in weight are usually less dense because they are made from an aerated mix. The heavier blocks are denser. Aerated block
  • 6. Load bearing blocks These blocks are usually made of Portland cement and a variety of aggregates. The blocks are precast in moulds and compacted with the aid of vibration, or in a moulding machine involving the use of compressed air, or a combination of both. Block making machine
  • 7. Non-load bearing blocks These blocks are usually made of Portland cement and a variety of lightweight aggregates; therefore they are not as dense or as strong as load-bearing blocks. These blocks are pre-cast in moulds or they can be produced in slab form and cut to size when set. Two well known manufacturers are Thermalite and Celcon. Aerated block making
  • 8. Lightweight Blocks These blocks are made from lightweight or low density materials such as fuel-ash, clinker, or lightweight aggregates bonded together with cement. They are easy to lift and handle and have good thermal and sound properties They can absorb water and are be easily broken during handling and construction.
  • 9. Lightweight blocks can be cut with a bolster chisel / hammer, a hand saw or power saw. It is good working practice to secure blocks when cutting with hand or powered tools.
  • 11.
  • 12. Special blocks Many manufacturers provide special blocks that assist in the bonding and prevent wastage. These blocks range from coursing blocks to half, quarter and three-quarter blocks. Other special blocks include return and reveal blocks which are used to close the cavity at door and window openings.
  • 13. Special / Coursing Blocks To maintain bond within a wall it may be necessary to use either coursing bricks or blocks. These can be cut from a whole block or special blocks manufactured to those sizes. These blocks are built into the walling at junctions and over openings in the wall. Ordinary facing or common bricks should NEVER be used for this purpose.
  • 14. Delivery and storage Blocks are delivered on site as banded packs or on pallets. The blocks must be stacked on a hard level base, or on battens on drained even ground. Loose blocks should be stacked as they are used, i.e. on edge, and the height of the stack should be limited to two metres.
  • 15. Delivery and storage Blocks may be delivered with or without a shrink-wrap covering, but all blocks should be covered from the elements until required for use. The packs should be placed on pallets if possible for ease of handling and delivery around the site by a forklift truck.
  • 17. Different finishes to Blockwork. • Rendering • External cladding • Plaster dab method • Timber batten method • Metal firring systems
  • 18. Plug and screw This is a common type of fixing specially designed for fixing to all blocks. It consists of a plastic plug which is driven into a pre-drilled hole. A screw can then be driven into the hollow centre of the fixing. Fixings and finishes
  • 19. Blockwork below ground level Trench Blocks These blocks are bigger in size than normal blocks with a face dimension size of 440mm x 215mm and are available in a range of thicknesses ranging from 255mm to 355mm. One trench block is equivalent in size to 2 aggregate blocks, or 12 bricks, plus wall ties and infill.
  • 20. Blockwork below ground level The following typical details illustrate the proper use of blocks below DPC level. Render Coating Painted wall DPC Trench block Plaster Ground floor Foundation Typical solid foundation in blockwork
  • 21. Blocks used below ground level Blocks are available in a weight less than 20kg with handholds and will comply with CDM Regulations which cover health and safety issues on site for repetitive handling.
  • 22. Solid Blockwork Foundation with an Insulated Cavity Wall This form of construction incorporates a blockwork foundation below ground level with a traditional brick and block cavity wall above. The cavity can be partially filled or full filled as required. This type of construction offers a structure with good sound and thermal insulation qualities.
  • 23. Solid Blockwork foundation with an insulated cavity wall Facing Brickwork DPC Plaster Partial fill cavity insulation Ground floor Foundation Trench Blockwork
  • 24. Block cavity wall foundation This is an alternative solid block foundation construction. The blocks below ground level are laid to form a cavity which is then filled up to ground level with a cement / aggregate mix. The cavity can be partially filled or fully filled as required.
  • 25. Block cavity wall foundation Facing Brickwork DPC Plaster Partial fill cavity insulation Ground floor Foundation Cavity blockwork Cement aggregate mix
  • 26. Apart from the size of the blocks the building operations used to erect walls are the same as for brickwork. There are 10 blocks per square metre as opposed to 60 bricks per square metre
  • 27. Never mix different types of blocks in the same run of walling, and do not use common or facing bricks as closers as they will reduce the thermal and sound insulation qualities of the blockwork.
  • 28. Always set out the first course dry so that the position of cut blocks can be found. Any adjustment to the width of joints should be made to achieve and maintain a bond within the wall. This is called “Dry Bonding” Blocks should be laid to a regular bond, usually half bond where possible. Never lay blocks to a bond of less than quarter bond.
  • 29. It is not always convenient to build a junction wall at the same time as the main wall. Tee junctions are normally bonded, or ties can be use with a straight joint. Indents may be left to allow bonding to occur at a later stage. Indents are gaps where blocks will be inserted at a later date. Wall ties Bonded Junctions to walls
  • 30. Junctions to walls The diagram shows a typical method of constructing junction walls. Brick outer leaf Inner leaf walls 100mm Separating wall 100mm Nominal 8mm internal render scratch finish Partial fill cavity wall 12.5mm gypsum board mounted on dabs Tied junction 100mm partition 75mm / 275mm min
  • 31. Bonding should be set out so that lintels bear preferably on a whole block. If this is not possible, a minimum two- thirds length block is acceptable but definitely not less. (normally by at least 150mm.)
  • 32. Some types of hollow and cellular blocks may need to be filled under lintel ends to provide sufficient bearing strength. In windy weather, block walls should be restrained by temporary propping. In windy weather, the day work lift height may be reduced as an alternative to propping. Blocks should be kept dry before use.
  • 33. Use only specified mortar mixes and ensure that bed and cross joints are solidly filled. Maintain gauge to correspond with brickwork gauge. Building with blocks is quick and the weight of the blocks could cause fresh soft mortar bed to be squeezed out. This could result in collapse / loss of gauge / loss of plumb.
  • 34. Internal Blockwork External Brickwork Cavity insulation and wall ties Typical cavity wall construction using facing bricks and blocks
  • 35. Closing cavities of external walling built with blocks With all cavity walls it is essential that the cavity be closed at reveals, such as door and window openings. This can be achieved by using cut blocks or by using special reveal blocks manufactured for the purpose.
  • 36. Cavity wall closers Another way of sealing the cavity at openings is to use ready made cavity closers. These are usually made from tough plastic and internally insulated to prevent cold bridging. They also have provision for fixing clips to be attached and built in as the brick / block work proceeds.
  • 37. For bonding purposes, three courses of brickwork are equal to one course of blockwork. This makes bonding simple as long as both bricks and blocks are kept accurately gauged.
  • 38. Plaster or smooth faced finish Solid internal wall Cavity partition wall Internal plasterSmooth faced blockwork