SlideShare a Scribd company logo
1 of 17
Cavity Walls
Cavity Wall Construction
Tutor Copy
Purpose and history
Cavity walling was first introduced to
domestic buildings in the 1920s
replacing traditional solid walls. This
type of wall is designed and
constructed as a means of preventing
heat loss and also moisture
penetrating to the internal face of the
wall, as was common in solid walls,
causing dampness on the inside of
the building.
The walls are often referred to as the
inner leaf and the outer leaf.
50mm minimum
Outer leaf Inner leaf
Cavity wall construction
Purpose and history
In the early days of cavity
walling it was considered good
practice to ventilate the cavity
as the flow of air around the
cavity kept it dry.
The 1960s saw a change in design of cavity walls
due to the increase in fuel prices and the need to
conserve energy in buildings.
This greater emphasis on retaining heat in buildings
led to cavities being sealed because still air is a far
better insulator of heat than air subject to convection
currents.
Current Building Regulations require much
higher resistance to the passage of heat
offered by the materials in a structure.
To achieve this reduction in heat loss, the
cavities are now either partially or totally
filled with an insulation material.
Full fill cavity insulation Partial fill cavity insulation
The two wall leaves need to be held together
so that they become one solid structure.
This needs to be done without allowing any
water to penetrate from the outer leaf to the
inner leaf.
Wall ties must be used and designed so as to
allow water to drip from them rather than
pass across into the internal wall and they
need to be strong enough to hold the two
leaves as one.
Cavity Wall Ties
The walls are supported and tied into one
another by means of specially designed
metal ties called ‘wall ties’.
Ties can be made from stainless steel, Plastic
or Galvanised Steel.
Wall ties are covered in greater depth in the
wall tie unit.
Cavity Wall Ties
Outer leaf
brickwork
Inner leaf
blockwork
Wall tie
Moisture drips off wall tie
Cavity
Building Regulations requirements
for insulated cavity walls
Approved Document L – Conservation of Fuel and
Power – of the current Building Regulations requires
external cavity walls to give a U-value of 0.35W/m² k.
A U-value is a measurement of the rate of heat loss
through a wall, roof or floor.
The lower the U-value, the better the insulation value
of the wall. So a wall with a U-value of 0.35W/m² k
performs better than a wall with a U-value of
0.45W/m² k.
A typical wall design, to meet current regulations,
may consist of:
• 100mm external wall.
• 75mm full fill fibreglass insulation quilt.
• 100mm lightweight thermal block.
• Dry-lined plasterboard on ‘dabs’ on the
inner leaf wall.
This construction provides a U-value of
0.33W/m² k
The following points are a general
guide to good construction.
• Wall leafs should be tied together with wall ties.
• Wall ties should be level or slope slightly downwards towards
the outer leaf of the wall with the drip positioned in the centre of
the cavity and pointing downwards.
• Only wall ties specified in the contract documents should be
used as they may be designed for use with insulating materials.
• The cavities should be clear of mortar droppings if insulation
materials are to be used.
• The ends or cross joints of the facework should be filled solidly
with mortar to prevent water penetration.
• Suitable DPC membranes should be positioned correctly, and
cavity trays should be placed over lintels, and stopped ends
built in to prevent water running off the ends of the trays into the
cavity insulation.
• Weep holes should be formed to drain off water from cavity
trays.
Typical components needed for
bridging cavities at openings.
Tray DPC
DPC stop end
Vertical DPC
Weep hole
Wall construction below ground
level
Cavity walling below ground level can be
constructed in the following ways:
• Cavity wall formed with two walls of common
bricks.
• Cavity wall formed with walls of foundation
blocks.
• Wall formed with solid foundation blocks
that are the full width of the cavity wall above.
Cavity wall formed with two walls of common
bricks
The diagram shows the construction of a
cavity wall formed with two walls of common
bricks.
Constructional features
1. Facework is set out at least one course
below ground level to allow for uneven
ground.
2. Horizontal DPC minimum of 150mm
above ground level.
3. Cavity below ground level filled with
weak mix concrete to resist lateral (side)
pressure crushing the cavity, and to
prevent the cavity filling with water.
4. Weep holes formed at 900mm centres
above the weak mix concrete fill, to allow
escape of any water.
5. Minimum depth of 600mm below ground
level to protect from frost heave.
Cavity wall formed with two walls of common
bricks with services running through
Constructional features
1. Face work is set out at least one course below
ground level to allow for uneven ground.
2. Horizontal DPC minimum of 150mm above
ground level.
3. Cavity below ground level is filled with a weak
mix of concrete to resist lateral (side) pressure
crushing the cavity, and to prevent the cavity
filling with water.
4. Weep holes formed at 900mm centres above
the weak mix concrete fill, to allow escape of
any water.
5. Openings for service ducts below ground level
typically spanned with pre stressed concrete
lintel.
6. Minimum depth of 600mm below ground level
to protect from frost heave.
This form of cavity wall construction would be used when service pipes etc run
through the wall just above the foundation. The services must be protected, so
a pre stressed lintel is inserted to form an opening.
Cavity wall formed with walls of foundation blocks
Constructional features
1. Cavity walls below ground are formed with blocks
that are designed for substructure work and have
a minimum strength of 3.5N/mm² if protected from
frost or, if they are to be exposed to the elements,
7N/mm².
2. Facework is set out at least one course below
ground level to allow for uneven ground that may
expose the first courses. Blockwork below ground
level must be terminated at a level to allow this.
3. Horizontal DPC minimum of 150mm above ground
level.
4. Cavity below ground level is filled with a weak mix
of concrete to resist lateral pressure crushing the
cavity.
5. Weep holes are formed at 900mm centres above
a weak concrete mix placed in the cavity. This is to
allow water to escape.
An alternative form of cavity wall construction makes use of solid foundation blocks.
These blocks are designed to be used for substructure work. They are strong and
dense and are capable of supporting the upper brick or blockwork. This type of block
has a minimum strength of 3.5N/mm² if protected from frost or, if they are to be
exposed to the elements, 7N/mm².
Wall formed with solid foundation
blocks that are the full width of the
cavity wall above
This type of cavity wall construction also makes
use of solid foundation blocks.
Constructional features
1. Cavity wall construction below ground formed
with solid foundation blocks. These may be a
dense or lightweight block depending upon the
design of the foundation.
2. Facework is set out at least one course
below ground level to allow for uneven ground
that may expose the first courses. Blockwork
below ground level must be terminated at a
level to allow this.
3. The cavity begins below ground level but no
infill of weak concrete mix is needed.

More Related Content

What's hot

What's hot (20)

Waterproofing and insulaton
Waterproofing and insulatonWaterproofing and insulaton
Waterproofing and insulaton
 
Partiton wall and adhesives
Partiton wall and adhesivesPartiton wall and adhesives
Partiton wall and adhesives
 
Timber flooring
Timber flooringTimber flooring
Timber flooring
 
Fixtures and fastenings in doors and windows
Fixtures and fastenings in doors and windowsFixtures and fastenings in doors and windows
Fixtures and fastenings in doors and windows
 
Floors and flooring
Floors and flooringFloors and flooring
Floors and flooring
 
stone cladding
  stone cladding  stone cladding
stone cladding
 
Walls
WallsWalls
Walls
 
Doors ppt
Doors pptDoors ppt
Doors ppt
 
Floor finishes
Floor finishesFloor finishes
Floor finishes
 
Brick as building materials
Brick as building materialsBrick as building materials
Brick as building materials
 
Staircase
StaircaseStaircase
Staircase
 
False ceiling
False ceilingFalse ceiling
False ceiling
 
False Ceiling
False CeilingFalse Ceiling
False Ceiling
 
Doors,Windows & Ventilator in Building Construction
Doors,Windows & Ventilator in Building ConstructionDoors,Windows & Ventilator in Building Construction
Doors,Windows & Ventilator in Building Construction
 
Elements of RCC Framed Structure (With Steel Detailing)
Elements of RCC Framed Structure (With Steel Detailing)Elements of RCC Framed Structure (With Steel Detailing)
Elements of RCC Framed Structure (With Steel Detailing)
 
Roof
RoofRoof
Roof
 
Brick bond
Brick bondBrick bond
Brick bond
 
Types of roof
Types of roofTypes of roof
Types of roof
 
Doors and windows
Doors and windowsDoors and windows
Doors and windows
 
Water proofing methods
Water proofing methodsWater proofing methods
Water proofing methods
 

Similar to Tutor cavity wall construction .ppt 1

Lesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxLesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptx
sydneyaugust1
 
Visual Dictionary Final
Visual Dictionary FinalVisual Dictionary Final
Visual Dictionary Final
Sp10rebar
 
Visual dictionary
Visual dictionary Visual dictionary
Visual dictionary
Sp10rebar
 
Visual dictionary GRADE THIS
Visual dictionary GRADE THISVisual dictionary GRADE THIS
Visual dictionary GRADE THIS
Sp10rebar
 
Chapter 6
Chapter 6Chapter 6
Chapter 6
Est
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
Nguyen Bao
 

Similar to Tutor cavity wall construction .ppt 1 (20)

the house
 the house the house
the house
 
Tutor l1 the house
Tutor l1 the houseTutor l1 the house
Tutor l1 the house
 
walls Construction.ppt
walls Construction.pptwalls Construction.ppt
walls Construction.ppt
 
Tutor l1 cavity wall construction
Tutor l1 cavity wall constructionTutor l1 cavity wall construction
Tutor l1 cavity wall construction
 
Chapter 4 (e) cavity walls
Chapter 4 (e) cavity wallsChapter 4 (e) cavity walls
Chapter 4 (e) cavity walls
 
Tutor l1 cavity wall construction
Tutor l1 cavity wall constructionTutor l1 cavity wall construction
Tutor l1 cavity wall construction
 
Lesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxLesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptx
 
Concrete Block Walling
Concrete Block WallingConcrete Block Walling
Concrete Block Walling
 
Btech compile 6 oct 4am
Btech compile 6 oct 4amBtech compile 6 oct 4am
Btech compile 6 oct 4am
 
Visual Dictionary Final
Visual Dictionary FinalVisual Dictionary Final
Visual Dictionary Final
 
Visual dictionary
Visual dictionary Visual dictionary
Visual dictionary
 
Visual dictionary GRADE THIS
Visual dictionary GRADE THISVisual dictionary GRADE THIS
Visual dictionary GRADE THIS
 
Diaphragm Wall
 Diaphragm Wall Diaphragm Wall
Diaphragm Wall
 
Diaphragm wall
Diaphragm wallDiaphragm wall
Diaphragm wall
 
diaphragmwall-141223040711-conversion-gate02.pdf
diaphragmwall-141223040711-conversion-gate02.pdfdiaphragmwall-141223040711-conversion-gate02.pdf
diaphragmwall-141223040711-conversion-gate02.pdf
 
Cavity wall
Cavity wall Cavity wall
Cavity wall
 
1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx
 
Lecture 3[1]
Lecture 3[1]Lecture 3[1]
Lecture 3[1]
 
Chapter 6
Chapter 6Chapter 6
Chapter 6
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 

More from Luke D'Arcy

More from Luke D'Arcy (20)

Tutor types of foundation
Tutor types of foundation Tutor types of foundation
Tutor types of foundation
 
Tutor transferring levels
Tutor transferring levels Tutor transferring levels
Tutor transferring levels
 
Tutor sustainability
Tutor sustainabilityTutor sustainability
Tutor sustainability
 
Tutor stability
Tutor stability Tutor stability
Tutor stability
 
Tutor solid ground floors
Tutor solid ground floors Tutor solid ground floors
Tutor solid ground floors
 
Tutor site clearance
Tutor site clearance Tutor site clearance
Tutor site clearance
 
Tutor retaining reinforced brickwork
Tutor retaining reinforced brickwork Tutor retaining reinforced brickwork
Tutor retaining reinforced brickwork
 
Tutor brickwork below ground level
Tutor brickwork below ground level Tutor brickwork below ground level
Tutor brickwork below ground level
 
Basic bricklaying skills power point 2015
Basic bricklaying skills power point 2015Basic bricklaying skills power point 2015
Basic bricklaying skills power point 2015
 
Health and safety c and g
Health and safety c and gHealth and safety c and g
Health and safety c and g
 
Tutor solid walls c and g level2
Tutor solid walls c and g level2Tutor solid walls c and g level2
Tutor solid walls c and g level2
 
Tutor masonry cladding ppt 2
Tutor masonry cladding ppt 2Tutor masonry cladding ppt 2
Tutor masonry cladding ppt 2
 
Tutor methods of communication ppt2
Tutor methods of communication ppt2Tutor methods of communication ppt2
Tutor methods of communication ppt2
 
Tutor construction administration documents ppt3
Tutor construction administration documents ppt3Tutor construction administration documents ppt3
Tutor construction administration documents ppt3
 
Tutor construction activity documents ppt4
Tutor construction activity documents ppt4Tutor construction activity documents ppt4
Tutor construction activity documents ppt4
 
Tutor communication skills ppt1
Tutor communication skills ppt1Tutor communication skills ppt1
Tutor communication skills ppt1
 
Tutor solid wall and arches
Tutor solid wall and archesTutor solid wall and arches
Tutor solid wall and arches
 
Tutor isolated and attached piers .ppt1
Tutor isolated and attached piers .ppt1Tutor isolated and attached piers .ppt1
Tutor isolated and attached piers .ppt1
 
Tutor wall ties in cavity walls .ppt 2
Tutor wall ties in cavity walls .ppt 2Tutor wall ties in cavity walls .ppt 2
Tutor wall ties in cavity walls .ppt 2
 
Tutor cavity insulation .ppt 4
Tutor cavity insulation .ppt 4Tutor cavity insulation .ppt 4
Tutor cavity insulation .ppt 4
 

Recently uploaded

Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
AnaAcapella
 

Recently uploaded (20)

Details on CBSE Compartment Exam.pptx1111
Details on CBSE Compartment Exam.pptx1111Details on CBSE Compartment Exam.pptx1111
Details on CBSE Compartment Exam.pptx1111
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
 
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdfUGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
What is 3 Way Matching Process in Odoo 17.pptx
What is 3 Way Matching Process in Odoo 17.pptxWhat is 3 Way Matching Process in Odoo 17.pptx
What is 3 Way Matching Process in Odoo 17.pptx
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
 
How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Play hard learn harder: The Serious Business of Play
Play hard learn harder:  The Serious Business of PlayPlay hard learn harder:  The Serious Business of Play
Play hard learn harder: The Serious Business of Play
 
21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx
 
Economic Importance Of Fungi In Food Additives
Economic Importance Of Fungi In Food AdditivesEconomic Importance Of Fungi In Food Additives
Economic Importance Of Fungi In Food Additives
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
Simple, Complex, and Compound Sentences Exercises.pdf
Simple, Complex, and Compound Sentences Exercises.pdfSimple, Complex, and Compound Sentences Exercises.pdf
Simple, Complex, and Compound Sentences Exercises.pdf
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 

Tutor cavity wall construction .ppt 1

  • 3. Purpose and history Cavity walling was first introduced to domestic buildings in the 1920s replacing traditional solid walls. This type of wall is designed and constructed as a means of preventing heat loss and also moisture penetrating to the internal face of the wall, as was common in solid walls, causing dampness on the inside of the building. The walls are often referred to as the inner leaf and the outer leaf. 50mm minimum Outer leaf Inner leaf Cavity wall construction
  • 4. Purpose and history In the early days of cavity walling it was considered good practice to ventilate the cavity as the flow of air around the cavity kept it dry. The 1960s saw a change in design of cavity walls due to the increase in fuel prices and the need to conserve energy in buildings. This greater emphasis on retaining heat in buildings led to cavities being sealed because still air is a far better insulator of heat than air subject to convection currents.
  • 5. Current Building Regulations require much higher resistance to the passage of heat offered by the materials in a structure. To achieve this reduction in heat loss, the cavities are now either partially or totally filled with an insulation material. Full fill cavity insulation Partial fill cavity insulation
  • 6. The two wall leaves need to be held together so that they become one solid structure. This needs to be done without allowing any water to penetrate from the outer leaf to the inner leaf. Wall ties must be used and designed so as to allow water to drip from them rather than pass across into the internal wall and they need to be strong enough to hold the two leaves as one.
  • 7. Cavity Wall Ties The walls are supported and tied into one another by means of specially designed metal ties called ‘wall ties’. Ties can be made from stainless steel, Plastic or Galvanised Steel. Wall ties are covered in greater depth in the wall tie unit.
  • 8. Cavity Wall Ties Outer leaf brickwork Inner leaf blockwork Wall tie Moisture drips off wall tie Cavity
  • 9. Building Regulations requirements for insulated cavity walls Approved Document L – Conservation of Fuel and Power – of the current Building Regulations requires external cavity walls to give a U-value of 0.35W/m² k. A U-value is a measurement of the rate of heat loss through a wall, roof or floor. The lower the U-value, the better the insulation value of the wall. So a wall with a U-value of 0.35W/m² k performs better than a wall with a U-value of 0.45W/m² k.
  • 10. A typical wall design, to meet current regulations, may consist of: • 100mm external wall. • 75mm full fill fibreglass insulation quilt. • 100mm lightweight thermal block. • Dry-lined plasterboard on ‘dabs’ on the inner leaf wall. This construction provides a U-value of 0.33W/m² k
  • 11. The following points are a general guide to good construction. • Wall leafs should be tied together with wall ties. • Wall ties should be level or slope slightly downwards towards the outer leaf of the wall with the drip positioned in the centre of the cavity and pointing downwards. • Only wall ties specified in the contract documents should be used as they may be designed for use with insulating materials. • The cavities should be clear of mortar droppings if insulation materials are to be used. • The ends or cross joints of the facework should be filled solidly with mortar to prevent water penetration. • Suitable DPC membranes should be positioned correctly, and cavity trays should be placed over lintels, and stopped ends built in to prevent water running off the ends of the trays into the cavity insulation. • Weep holes should be formed to drain off water from cavity trays.
  • 12. Typical components needed for bridging cavities at openings. Tray DPC DPC stop end Vertical DPC Weep hole
  • 13. Wall construction below ground level Cavity walling below ground level can be constructed in the following ways: • Cavity wall formed with two walls of common bricks. • Cavity wall formed with walls of foundation blocks. • Wall formed with solid foundation blocks that are the full width of the cavity wall above.
  • 14. Cavity wall formed with two walls of common bricks The diagram shows the construction of a cavity wall formed with two walls of common bricks. Constructional features 1. Facework is set out at least one course below ground level to allow for uneven ground. 2. Horizontal DPC minimum of 150mm above ground level. 3. Cavity below ground level filled with weak mix concrete to resist lateral (side) pressure crushing the cavity, and to prevent the cavity filling with water. 4. Weep holes formed at 900mm centres above the weak mix concrete fill, to allow escape of any water. 5. Minimum depth of 600mm below ground level to protect from frost heave.
  • 15. Cavity wall formed with two walls of common bricks with services running through Constructional features 1. Face work is set out at least one course below ground level to allow for uneven ground. 2. Horizontal DPC minimum of 150mm above ground level. 3. Cavity below ground level is filled with a weak mix of concrete to resist lateral (side) pressure crushing the cavity, and to prevent the cavity filling with water. 4. Weep holes formed at 900mm centres above the weak mix concrete fill, to allow escape of any water. 5. Openings for service ducts below ground level typically spanned with pre stressed concrete lintel. 6. Minimum depth of 600mm below ground level to protect from frost heave. This form of cavity wall construction would be used when service pipes etc run through the wall just above the foundation. The services must be protected, so a pre stressed lintel is inserted to form an opening.
  • 16. Cavity wall formed with walls of foundation blocks Constructional features 1. Cavity walls below ground are formed with blocks that are designed for substructure work and have a minimum strength of 3.5N/mm² if protected from frost or, if they are to be exposed to the elements, 7N/mm². 2. Facework is set out at least one course below ground level to allow for uneven ground that may expose the first courses. Blockwork below ground level must be terminated at a level to allow this. 3. Horizontal DPC minimum of 150mm above ground level. 4. Cavity below ground level is filled with a weak mix of concrete to resist lateral pressure crushing the cavity. 5. Weep holes are formed at 900mm centres above a weak concrete mix placed in the cavity. This is to allow water to escape. An alternative form of cavity wall construction makes use of solid foundation blocks. These blocks are designed to be used for substructure work. They are strong and dense and are capable of supporting the upper brick or blockwork. This type of block has a minimum strength of 3.5N/mm² if protected from frost or, if they are to be exposed to the elements, 7N/mm².
  • 17. Wall formed with solid foundation blocks that are the full width of the cavity wall above This type of cavity wall construction also makes use of solid foundation blocks. Constructional features 1. Cavity wall construction below ground formed with solid foundation blocks. These may be a dense or lightweight block depending upon the design of the foundation. 2. Facework is set out at least one course below ground level to allow for uneven ground that may expose the first courses. Blockwork below ground level must be terminated at a level to allow this. 3. The cavity begins below ground level but no infill of weak concrete mix is needed.