SlideShare a Scribd company logo
VLF—Verylowfrequencyhighvoltage generator,TandeltaBridge consistsof measuringunit(capacitor
value inpf range) & lossangle analyser.Voltage range: 0 - 60 kV peak,Frequency range: 0.01 Hz -
0.2 Hz,Full report generating software,Displayed data: loss angle, voltage, current, & frequency
To ensure the dielectric strength of insulation or to predict the life of bushing.; diagnositic method of testing cables to
determine the quality of the cable insulation.(
(As with VLF cable testing a sinusoidal 0.1 Hz VLF (v ery low f requency ) AC voltage is used.
That prev ents the dev ice under test f rom damages during tan delta testing and guaranteesdamage-free measurement.
Along the measurement procedure the dissipation f actor is measured at nominal v oltage Vo and at twice the nominal voltage 2 Vo.
A drastic increase of the tan δ at increasing measurement v oltages points to a strong ageing of the cable insulation.
Comparison of the gathered measurement v alues with the data of the same cable collected during the acceptance-test allows classification of the
dielectric condition (new, strongly aged, f aulty ) of the cable).
POWER TRANSFORMER TESTING
SPECIAL TESTS: -
1] Sweep Frequency Response Analysis (SFRA)
2] On Line Partial Discharge Test
3] Dielectric Response Measurement – by PDC or FDS technique.
4] Capacitance & Dissipation Factor ( Tan-Delta ) measurement.
5] 10KV Excitation Current Measurement
6] 10KV Turn Ratio Measurement
7] On Line Water Content Measurement
8] Transformer Oil Test – General Tests, DGA & FURAN
ROUTINE TESTS: -
1] Winding Resistance Measurement.
2] Insulation Resistance / Polarization Index.
3] Turns Ratio.
4] Voltage Ratio.
5] Open & Short Circuit.
6] Magnetic Balance.
7] Vector Group.
CT / PT Testing
1] Capacitance & Dissipation Factor ( Tan-Delta ) measurement..
2] Insulation Resistance / Polarization Index.
3] Polarity
4] Ratio
5] Primary Current Injection.
6] Knee Point Voltage Measurement.
CIRCUIT BREAKER TESTING
1] DCRM ( Dynamic Contact Resistance Measurement with Travel & Velocity)
2] CRM (Contact Resistance Measurement)
3] Timing Measurement Test.
4] Dew Point Measurement Test
5] Vidar Test for Vacuum Interrupter
4] Insulation Resistance
LIGHTENING ARRESSTORS ( L.A. ) TESTING
1] Capacitance & Dissipation Factor ( Tan-Delta ) measurement.
2] Insulation Resistance
3] On Line Leakage Current Measurement ( LCM )
H.T. MOTOR / GENERATOR TESTING
1] Capacitance & Dissipation Factor ( Tan-Delta ) measurement.
2] Insulation Resistance / Polarization Index.
3] Winding Resistance Measurement.
4] Partial Discharge Test.
5] Vibration & Current Signature Analysis.
6] Harmonic Analysis
7] Hi-Pot Test.
XLPE H.T. CABLE TESTING
1] Capacitance & Dissipation Factor ( Tan-Delta ) measurement.
2] VLF Hi-Pot Test
3] VLF Capacitance & Dissipation Factor ( Tan-Delta ) measurement.
4] VLF Partial Discharge Test
5] Insulation Resistance
6] D.C. Hi-Pot Test.
Ac hi-pot test--- portable 0.1 Hz VLF cable test
system for the testing of medium voltage cables.( output voltagesSinusoidal: 0 – 62 kV peak, 0 – 44 kV ef f ,DC:
± 0 - 60 kV
A low frequency causes a higher value of capacitive reactance which leads to lesser power requirement during
the test.Besides, the currents will be limited enabling easier measurement.
In a pure capacitor, the current is ahead of the voltage by 90 degrees.The insulation, in a pure condition, will behave
similarly. However, if the insulation has deteriorated due to the entry of dirt and moisture. The current which flows
through the insulation will also have a resistive component.
This will cause the angle of the current to be less than 90 degrees. This difference in the angle is known as the loss
angle. The tangent of the angle which is Ir/Ic (opposite/adjacent)gives us an indication of the condition of the
insulation. A higher value for the loss angle indicates a high degree of contamination of the insulation.
Method of Testing
The cable or winding whose insulation is to be tested is first disconnected and isolated. The test voltage is applied
from the Very Low Frequency power source and the Tan delta controller takes the measurements. The test voltage is
increased in steps upto the rated voltage of the cable. The readings are plotted in a graph against the applied voltage
and the trend is studied.A healthy insulation would produce a straight line.
The test should be continued only if the graph is a straight line. A rising trend would indicate weak insulation which
may fail if the test voltage is increased beyond the rated voltage of the cable.
Interpretation of the test data
There are not standard formulae or benchmarks to ascertain the success ofa tan delta test.The health of the
insulation which is measured is obtained by observing the nature of the trend which is plotted. A steady,straight
trend would indicate a healthy insulation, while a rising trend would indicate an insulation that has been
contaminated with water and other impurities
TRANSFORMER OIL BUSHING
Condenserbushings manufactured by TELK arc self contained hemlctically scaled and hence practically
maintenancefree.
Preventive maintenance
(I) Porcelain
Porcelain may get chipped or broken. Glaze finish may become roughened or eroded. Small chips and minor cracks
can be repaired using M-seal repair kit to obtain glossy finish. Ifthc body ufthe procelain insulator is affected by a
crack there is possible danger that it can lead to an operating hazard. In such cases the insu lator must be replaced.
(2) Metal parts.
Metal parts may be checked for corrosion and, if required, may be painted periodically.
(3) Test tap.
The test tap shall be examined for proper scaling to prevent entry of moisture.
(4) Oil level
Oil Iccl as indicated by the gungc glasS/lcvel indicalOrs shall be chl.:ckcd periodically. The gauge glasses should
be inspected regularly for cracks which might result from any mechanical cause.Ifthcrc is a leak it should be
repaired as per advice from TELK. If there is no leak, but oillevcl is too low, the problem may be internal and il may
be prudent to replace the bushing.
(5) Surface contamination
This is the naluml deposits or coating of early morning dew. salt fog in SC3 coast areas. smog and mdustrial
pollutants on the porcelain insulator. Build up of contamination can cause flash over ofbushmg ai nonnal voltage.
Danger of flash over occurs when the surface coating becomes partly conducting,usually with thc prcsence of
moisture.To prevent contamin;nioll flashovcr of porcelain insulator, the following methods may be used.
Iland Wiping
Wash,ng WITH cleall Wa!er
Dry Clcamng wlih AIr - blast materials.
Coating with suilnble siliconc compounds.
Bushing Troubles
Operating records show that about 90 percent of all preventable bushing failures are caused by moisture entering the
bushing through leaky gaskets or other openings.Close periodic inspection to find leaks and make repairs as needed
will prevent most outages due to bush-lng failures. Such an external inspection requires little time and expense and
will be well worth the effort. High-voltage bushings, if allowed to deteriorate, may explode with considerable
violence and cause extensive damages to adjacent equipment. Flashovers may be caused by deposits of dirt on the
bushings,particularly in areas where there are contaminants such as salts or conducting dusts in the air. These
deposits should be removed by periodic cleaning.
Testing

More Related Content

What's hot

Transformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsTransformer Differential Protection Setting Calculations
Transformer Differential Protection Setting Calculations
Power System Operation
 
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard EquipmentSimple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
SARAVANAN A
 
Substation Neutral Earthing
Substation Neutral EarthingSubstation Neutral Earthing
Substation Neutral Earthing
Power System Operation
 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting Calculations
Power System Operation
 
CPC100 + TD12 Tan Delta Test Report for 132kV CT.
CPC100 + TD12 Tan Delta Test Report for 132kV CT.CPC100 + TD12 Tan Delta Test Report for 132kV CT.
CPC100 + TD12 Tan Delta Test Report for 132kV CT.
SARAVANAN A
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer Protection
Ang Sovann
 
Introduction to mv switchgear
Introduction to mv switchgearIntroduction to mv switchgear
Introduction to mv switchgear
Modal Holong Education
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
Shankar Singh
 
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Thorne & Derrick International
 
Distribution Transformer testing, West Bengal, India
Distribution Transformer testing,  West Bengal, IndiaDistribution Transformer testing,  West Bengal, India
Distribution Transformer testing, West Bengal, India
RajuMondal18
 
Seminar on Partial Discharge detection methods
Seminar on Partial Discharge detection methodsSeminar on Partial Discharge detection methods
Seminar on Partial Discharge detection methods
Harshit Bhandari
 
Transformer vector group_test_conditions
Transformer vector group_test_conditionsTransformer vector group_test_conditions
Transformer vector group_test_conditions
SARAVANAN A
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
Partha Parida
 
Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601
SARAVANAN A
 
BUS BAR PROTECTION PPT BY:-R.K.PANDIT
BUS BAR  PROTECTION PPT BY:-R.K.PANDITBUS BAR  PROTECTION PPT BY:-R.K.PANDIT
BUS BAR PROTECTION PPT BY:-R.K.PANDIT
RAGHVENDRA KUMAR PANDIT
 
Transformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response AnalysisTransformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response Analysis
HamedPasha1
 
Overcurrent protection
Overcurrent protectionOvercurrent protection
Overcurrent protection
Vincent Wedelich, PE MBA
 
Transformer overcurrent
Transformer overcurrentTransformer overcurrent
Transformer overcurrent
michaeljmack
 
Instrument Transformer Presentation
Instrument Transformer PresentationInstrument Transformer Presentation
Instrument Transformer Presentation
Rishi Raj
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
Ahmed Saada, (PRMG)
 

What's hot (20)

Transformer Differential Protection Setting Calculations
Transformer Differential Protection Setting CalculationsTransformer Differential Protection Setting Calculations
Transformer Differential Protection Setting Calculations
 
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard EquipmentSimple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
Simple Capacitive Voltage Transformer (CVT) Testing for Switchyard Equipment
 
Substation Neutral Earthing
Substation Neutral EarthingSubstation Neutral Earthing
Substation Neutral Earthing
 
Generator Protection Relay Setting Calculations
Generator Protection Relay Setting CalculationsGenerator Protection Relay Setting Calculations
Generator Protection Relay Setting Calculations
 
CPC100 + TD12 Tan Delta Test Report for 132kV CT.
CPC100 + TD12 Tan Delta Test Report for 132kV CT.CPC100 + TD12 Tan Delta Test Report for 132kV CT.
CPC100 + TD12 Tan Delta Test Report for 132kV CT.
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer Protection
 
Introduction to mv switchgear
Introduction to mv switchgearIntroduction to mv switchgear
Introduction to mv switchgear
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
 
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
 
Distribution Transformer testing, West Bengal, India
Distribution Transformer testing,  West Bengal, IndiaDistribution Transformer testing,  West Bengal, India
Distribution Transformer testing, West Bengal, India
 
Seminar on Partial Discharge detection methods
Seminar on Partial Discharge detection methodsSeminar on Partial Discharge detection methods
Seminar on Partial Discharge detection methods
 
Transformer vector group_test_conditions
Transformer vector group_test_conditionsTransformer vector group_test_conditions
Transformer vector group_test_conditions
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
 
Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601
 
BUS BAR PROTECTION PPT BY:-R.K.PANDIT
BUS BAR  PROTECTION PPT BY:-R.K.PANDITBUS BAR  PROTECTION PPT BY:-R.K.PANDIT
BUS BAR PROTECTION PPT BY:-R.K.PANDIT
 
Transformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response AnalysisTransformer Diagnostics | Sweep Frequency Response Analysis
Transformer Diagnostics | Sweep Frequency Response Analysis
 
Overcurrent protection
Overcurrent protectionOvercurrent protection
Overcurrent protection
 
Transformer overcurrent
Transformer overcurrentTransformer overcurrent
Transformer overcurrent
 
Instrument Transformer Presentation
Instrument Transformer PresentationInstrument Transformer Presentation
Instrument Transformer Presentation
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
 

Viewers also liked

Loss tangent delta test
Loss tangent delta testLoss tangent delta test
Loss tangent delta test
Donald Stephen
 
Behavioural base safety
Behavioural base safetyBehavioural base safety
Behavioural base safety
Sanjiv Gunawat
 
Testing/Manufacture/Wire & Cable Testing Equipmetns
Testing/Manufacture/Wire & Cable Testing Equipmetns Testing/Manufacture/Wire & Cable Testing Equipmetns
Testing/Manufacture/Wire & Cable Testing Equipmetns
fec2020
 
Cable tray testing
Cable tray testingCable tray testing
Cable tray testing
Lalit Kumar Jain
 
INTRON_D_eng_02_2012
INTRON_D_eng_02_2012INTRON_D_eng_02_2012
INTRON_D_eng_02_2012
Arie den Boer
 
Introndplus
IntrondplusIntrondplus
Introndplus
Industronic
 
Productivity improvement stratedies
Productivity improvement stratediesProductivity improvement stratedies
Productivity improvement stratedies
Rajasimman Rajarajan
 
Positive and negative behaviour
Positive and negative behaviourPositive and negative behaviour
Positive and negative behaviour
cripatria
 
Cable terminations
Cable terminationsCable terminations
Cable terminations
tonyainscow
 
Introduction to fundamentals of instrument & control
Introduction to fundamentals of instrument & controlIntroduction to fundamentals of instrument & control
Introduction to fundamentals of instrument & control
Mahmoud Wanis
 
Pratical electricity
Pratical electricityPratical electricity
Pratical electricity
Niteesha Jugnarain
 
cable testing and intallation
cable testing and intallationcable testing and intallation
cable testing and intallation
manishgoswami66
 
Cable Tray Installation 211215
Cable Tray Installation 211215Cable Tray Installation 211215
Cable Tray Installation 211215
MUHAMMAD MAJID
 
Behavior Based Safety
Behavior Based Safety Behavior Based Safety
Behavior Based Safety
Surendra Marchande
 
Cut bend and install PVC electrical conduits
Cut bend and install PVC electrical conduitsCut bend and install PVC electrical conduits
Cut bend and install PVC electrical conduits
Stephen Jones
 
System of wiring
System of wiringSystem of wiring
System of wiring
Sharda University SET
 
Productivity Improvement Study
Productivity Improvement StudyProductivity Improvement Study
Productivity Improvement Study
saranshshah
 
EE-55 Power Cables Testing & Fault Location
EE-55 Power Cables Testing & Fault LocationEE-55 Power Cables Testing & Fault Location
EE-55 Power Cables Testing & Fault Location
Rina Florentes
 
Joints and terminations
Joints and terminationsJoints and terminations
Joints and terminations
kariuki kinuthia
 
8 Access Control
8 Access Control8 Access Control
8 Access Control
Alfred Ouyang
 

Viewers also liked (20)

Loss tangent delta test
Loss tangent delta testLoss tangent delta test
Loss tangent delta test
 
Behavioural base safety
Behavioural base safetyBehavioural base safety
Behavioural base safety
 
Testing/Manufacture/Wire & Cable Testing Equipmetns
Testing/Manufacture/Wire & Cable Testing Equipmetns Testing/Manufacture/Wire & Cable Testing Equipmetns
Testing/Manufacture/Wire & Cable Testing Equipmetns
 
Cable tray testing
Cable tray testingCable tray testing
Cable tray testing
 
INTRON_D_eng_02_2012
INTRON_D_eng_02_2012INTRON_D_eng_02_2012
INTRON_D_eng_02_2012
 
Introndplus
IntrondplusIntrondplus
Introndplus
 
Productivity improvement stratedies
Productivity improvement stratediesProductivity improvement stratedies
Productivity improvement stratedies
 
Positive and negative behaviour
Positive and negative behaviourPositive and negative behaviour
Positive and negative behaviour
 
Cable terminations
Cable terminationsCable terminations
Cable terminations
 
Introduction to fundamentals of instrument & control
Introduction to fundamentals of instrument & controlIntroduction to fundamentals of instrument & control
Introduction to fundamentals of instrument & control
 
Pratical electricity
Pratical electricityPratical electricity
Pratical electricity
 
cable testing and intallation
cable testing and intallationcable testing and intallation
cable testing and intallation
 
Cable Tray Installation 211215
Cable Tray Installation 211215Cable Tray Installation 211215
Cable Tray Installation 211215
 
Behavior Based Safety
Behavior Based Safety Behavior Based Safety
Behavior Based Safety
 
Cut bend and install PVC electrical conduits
Cut bend and install PVC electrical conduitsCut bend and install PVC electrical conduits
Cut bend and install PVC electrical conduits
 
System of wiring
System of wiringSystem of wiring
System of wiring
 
Productivity Improvement Study
Productivity Improvement StudyProductivity Improvement Study
Productivity Improvement Study
 
EE-55 Power Cables Testing & Fault Location
EE-55 Power Cables Testing & Fault LocationEE-55 Power Cables Testing & Fault Location
EE-55 Power Cables Testing & Fault Location
 
Joints and terminations
Joints and terminationsJoints and terminations
Joints and terminations
 
8 Access Control
8 Access Control8 Access Control
8 Access Control
 

Similar to Testing

Lightning arresters
Lightning arrestersLightning arresters
Lightning arresters
vishal Barvaliya
 
Electrical Checks And Measurements And Customer Requirements LEAP
Electrical Checks And Measurements And Customer Requirements LEAPElectrical Checks And Measurements And Customer Requirements LEAP
Electrical Checks And Measurements And Customer Requirements LEAP
Jorge I. Villacis Gallo
 
Power-Transformer-Testing-Brochure-ENU.pdf
Power-Transformer-Testing-Brochure-ENU.pdfPower-Transformer-Testing-Brochure-ENU.pdf
Power-Transformer-Testing-Brochure-ENU.pdf
NishanthaSenaratne1
 
Power-Transformer-Testing-Brochure-ENU.pdf
Power-Transformer-Testing-Brochure-ENU.pdfPower-Transformer-Testing-Brochure-ENU.pdf
Power-Transformer-Testing-Brochure-ENU.pdf
NguyenXuanTung12
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushing
Novia Putri
 
Shorted Casing Study - Tim Sievert
Shorted Casing Study - Tim SievertShorted Casing Study - Tim Sievert
Shorted Casing Study - Tim Sievert
nacetwincities
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
vikasgupta1965
 
Mod5part1
Mod5part1Mod5part1
Mod5part1
Asha Anu Kurian
 
Partial Discharge Techniques For Measuring Condition Of MV & HV Switchgear
Partial Discharge Techniques For Measuring Condition Of MV & HV SwitchgearPartial Discharge Techniques For Measuring Condition Of MV & HV Switchgear
Partial Discharge Techniques For Measuring Condition Of MV & HV Switchgear
Thorne & Derrick International
 
Insulation resistance test
Insulation resistance testInsulation resistance test
Insulation resistance test
Donald Stephen
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
johny renoald
 
Tan Delta on MV Cables (Megger)
Tan Delta on MV Cables (Megger)Tan Delta on MV Cables (Megger)
Tan Delta on MV Cables (Megger)
AHMED MOHAMED HEGAB
 
Blind Spots of Low Voltage Testing Webinar Presented by Megger Baker
Blind Spots of Low Voltage Testing Webinar Presented by Megger BakerBlind Spots of Low Voltage Testing Webinar Presented by Megger Baker
Blind Spots of Low Voltage Testing Webinar Presented by Megger Baker
Transcat
 
Module 6part1
Module 6part1Module 6part1
Module 6part1
Asha Anu Kurian
 
Insulation and Dielectric Breakdown Design Paper SM54
Insulation and Dielectric Breakdown Design Paper SM54Insulation and Dielectric Breakdown Design Paper SM54
Insulation and Dielectric Breakdown Design Paper SM54
Subhash Mahla
 
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Thorne & Derrick International
 
CIRCUIT BREAKER USED IN THERMAL POWER PLANTS
CIRCUIT BREAKER USED IN THERMAL POWER PLANTSCIRCUIT BREAKER USED IN THERMAL POWER PLANTS
CIRCUIT BREAKER USED IN THERMAL POWER PLANTS
DigantaSinha1
 
Unit 1-2-b
Unit 1-2-bUnit 1-2-b
Unit 1-2-b
srichakra kripa
 
Quality control (training course)
Quality control (training course)Quality control (training course)
Quality control (training course)
fikireyesus
 
Quality control (training course)
Quality control (training course)Quality control (training course)
Quality control (training course)
fikireyesus
 

Similar to Testing (20)

Lightning arresters
Lightning arrestersLightning arresters
Lightning arresters
 
Electrical Checks And Measurements And Customer Requirements LEAP
Electrical Checks And Measurements And Customer Requirements LEAPElectrical Checks And Measurements And Customer Requirements LEAP
Electrical Checks And Measurements And Customer Requirements LEAP
 
Power-Transformer-Testing-Brochure-ENU.pdf
Power-Transformer-Testing-Brochure-ENU.pdfPower-Transformer-Testing-Brochure-ENU.pdf
Power-Transformer-Testing-Brochure-ENU.pdf
 
Power-Transformer-Testing-Brochure-ENU.pdf
Power-Transformer-Testing-Brochure-ENU.pdfPower-Transformer-Testing-Brochure-ENU.pdf
Power-Transformer-Testing-Brochure-ENU.pdf
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushing
 
Shorted Casing Study - Tim Sievert
Shorted Casing Study - Tim SievertShorted Casing Study - Tim Sievert
Shorted Casing Study - Tim Sievert
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Mod5part1
Mod5part1Mod5part1
Mod5part1
 
Partial Discharge Techniques For Measuring Condition Of MV & HV Switchgear
Partial Discharge Techniques For Measuring Condition Of MV & HV SwitchgearPartial Discharge Techniques For Measuring Condition Of MV & HV Switchgear
Partial Discharge Techniques For Measuring Condition Of MV & HV Switchgear
 
Insulation resistance test
Insulation resistance testInsulation resistance test
Insulation resistance test
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
Tan Delta on MV Cables (Megger)
Tan Delta on MV Cables (Megger)Tan Delta on MV Cables (Megger)
Tan Delta on MV Cables (Megger)
 
Blind Spots of Low Voltage Testing Webinar Presented by Megger Baker
Blind Spots of Low Voltage Testing Webinar Presented by Megger BakerBlind Spots of Low Voltage Testing Webinar Presented by Megger Baker
Blind Spots of Low Voltage Testing Webinar Presented by Megger Baker
 
Module 6part1
Module 6part1Module 6part1
Module 6part1
 
Insulation and Dielectric Breakdown Design Paper SM54
Insulation and Dielectric Breakdown Design Paper SM54Insulation and Dielectric Breakdown Design Paper SM54
Insulation and Dielectric Breakdown Design Paper SM54
 
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
 
CIRCUIT BREAKER USED IN THERMAL POWER PLANTS
CIRCUIT BREAKER USED IN THERMAL POWER PLANTSCIRCUIT BREAKER USED IN THERMAL POWER PLANTS
CIRCUIT BREAKER USED IN THERMAL POWER PLANTS
 
Unit 1-2-b
Unit 1-2-bUnit 1-2-b
Unit 1-2-b
 
Quality control (training course)
Quality control (training course)Quality control (training course)
Quality control (training course)
 
Quality control (training course)
Quality control (training course)Quality control (training course)
Quality control (training course)
 

Testing

  • 1. VLF—Verylowfrequencyhighvoltage generator,TandeltaBridge consistsof measuringunit(capacitor value inpf range) & lossangle analyser.Voltage range: 0 - 60 kV peak,Frequency range: 0.01 Hz - 0.2 Hz,Full report generating software,Displayed data: loss angle, voltage, current, & frequency To ensure the dielectric strength of insulation or to predict the life of bushing.; diagnositic method of testing cables to determine the quality of the cable insulation.( (As with VLF cable testing a sinusoidal 0.1 Hz VLF (v ery low f requency ) AC voltage is used. That prev ents the dev ice under test f rom damages during tan delta testing and guaranteesdamage-free measurement. Along the measurement procedure the dissipation f actor is measured at nominal v oltage Vo and at twice the nominal voltage 2 Vo. A drastic increase of the tan δ at increasing measurement v oltages points to a strong ageing of the cable insulation. Comparison of the gathered measurement v alues with the data of the same cable collected during the acceptance-test allows classification of the dielectric condition (new, strongly aged, f aulty ) of the cable).
  • 2. POWER TRANSFORMER TESTING SPECIAL TESTS: - 1] Sweep Frequency Response Analysis (SFRA) 2] On Line Partial Discharge Test 3] Dielectric Response Measurement – by PDC or FDS technique. 4] Capacitance & Dissipation Factor ( Tan-Delta ) measurement. 5] 10KV Excitation Current Measurement 6] 10KV Turn Ratio Measurement 7] On Line Water Content Measurement 8] Transformer Oil Test – General Tests, DGA & FURAN ROUTINE TESTS: - 1] Winding Resistance Measurement. 2] Insulation Resistance / Polarization Index. 3] Turns Ratio. 4] Voltage Ratio. 5] Open & Short Circuit. 6] Magnetic Balance. 7] Vector Group. CT / PT Testing
  • 3. 1] Capacitance & Dissipation Factor ( Tan-Delta ) measurement.. 2] Insulation Resistance / Polarization Index. 3] Polarity 4] Ratio 5] Primary Current Injection. 6] Knee Point Voltage Measurement. CIRCUIT BREAKER TESTING 1] DCRM ( Dynamic Contact Resistance Measurement with Travel & Velocity) 2] CRM (Contact Resistance Measurement) 3] Timing Measurement Test. 4] Dew Point Measurement Test 5] Vidar Test for Vacuum Interrupter 4] Insulation Resistance LIGHTENING ARRESSTORS ( L.A. ) TESTING 1] Capacitance & Dissipation Factor ( Tan-Delta ) measurement. 2] Insulation Resistance 3] On Line Leakage Current Measurement ( LCM ) H.T. MOTOR / GENERATOR TESTING 1] Capacitance & Dissipation Factor ( Tan-Delta ) measurement. 2] Insulation Resistance / Polarization Index. 3] Winding Resistance Measurement. 4] Partial Discharge Test. 5] Vibration & Current Signature Analysis. 6] Harmonic Analysis 7] Hi-Pot Test. XLPE H.T. CABLE TESTING 1] Capacitance & Dissipation Factor ( Tan-Delta ) measurement. 2] VLF Hi-Pot Test 3] VLF Capacitance & Dissipation Factor ( Tan-Delta ) measurement. 4] VLF Partial Discharge Test 5] Insulation Resistance 6] D.C. Hi-Pot Test. Ac hi-pot test--- portable 0.1 Hz VLF cable test system for the testing of medium voltage cables.( output voltagesSinusoidal: 0 – 62 kV peak, 0 – 44 kV ef f ,DC: ± 0 - 60 kV
  • 4. A low frequency causes a higher value of capacitive reactance which leads to lesser power requirement during the test.Besides, the currents will be limited enabling easier measurement. In a pure capacitor, the current is ahead of the voltage by 90 degrees.The insulation, in a pure condition, will behave similarly. However, if the insulation has deteriorated due to the entry of dirt and moisture. The current which flows through the insulation will also have a resistive component. This will cause the angle of the current to be less than 90 degrees. This difference in the angle is known as the loss angle. The tangent of the angle which is Ir/Ic (opposite/adjacent)gives us an indication of the condition of the insulation. A higher value for the loss angle indicates a high degree of contamination of the insulation. Method of Testing The cable or winding whose insulation is to be tested is first disconnected and isolated. The test voltage is applied from the Very Low Frequency power source and the Tan delta controller takes the measurements. The test voltage is increased in steps upto the rated voltage of the cable. The readings are plotted in a graph against the applied voltage and the trend is studied.A healthy insulation would produce a straight line. The test should be continued only if the graph is a straight line. A rising trend would indicate weak insulation which may fail if the test voltage is increased beyond the rated voltage of the cable.
  • 5. Interpretation of the test data There are not standard formulae or benchmarks to ascertain the success ofa tan delta test.The health of the insulation which is measured is obtained by observing the nature of the trend which is plotted. A steady,straight trend would indicate a healthy insulation, while a rising trend would indicate an insulation that has been contaminated with water and other impurities
  • 6. TRANSFORMER OIL BUSHING Condenserbushings manufactured by TELK arc self contained hemlctically scaled and hence practically maintenancefree. Preventive maintenance (I) Porcelain Porcelain may get chipped or broken. Glaze finish may become roughened or eroded. Small chips and minor cracks can be repaired using M-seal repair kit to obtain glossy finish. Ifthc body ufthe procelain insulator is affected by a crack there is possible danger that it can lead to an operating hazard. In such cases the insu lator must be replaced. (2) Metal parts. Metal parts may be checked for corrosion and, if required, may be painted periodically. (3) Test tap. The test tap shall be examined for proper scaling to prevent entry of moisture. (4) Oil level
  • 7. Oil Iccl as indicated by the gungc glasS/lcvel indicalOrs shall be chl.:ckcd periodically. The gauge glasses should be inspected regularly for cracks which might result from any mechanical cause.Ifthcrc is a leak it should be repaired as per advice from TELK. If there is no leak, but oillevcl is too low, the problem may be internal and il may be prudent to replace the bushing. (5) Surface contamination This is the naluml deposits or coating of early morning dew. salt fog in SC3 coast areas. smog and mdustrial pollutants on the porcelain insulator. Build up of contamination can cause flash over ofbushmg ai nonnal voltage. Danger of flash over occurs when the surface coating becomes partly conducting,usually with thc prcsence of moisture.To prevent contamin;nioll flashovcr of porcelain insulator, the following methods may be used. Iland Wiping Wash,ng WITH cleall Wa!er Dry Clcamng wlih AIr - blast materials. Coating with suilnble siliconc compounds. Bushing Troubles Operating records show that about 90 percent of all preventable bushing failures are caused by moisture entering the bushing through leaky gaskets or other openings.Close periodic inspection to find leaks and make repairs as needed will prevent most outages due to bush-lng failures. Such an external inspection requires little time and expense and will be well worth the effort. High-voltage bushings, if allowed to deteriorate, may explode with considerable violence and cause extensive damages to adjacent equipment. Flashovers may be caused by deposits of dirt on the bushings,particularly in areas where there are contaminants such as salts or conducting dusts in the air. These deposits should be removed by periodic cleaning.