SlideShare a Scribd company logo
1 of 11
Download to read offline
Insulation Testing
Presented by
Dr. R.K.Saini
General tests carried out on High voltage equipment
1. Sustained low-frequency tests:
(i) Sustained low frequency tests are done at power frequency (50 Hz)
(ii) Tests are made upon specimens of insulation materials for the
determination of dielectric strength and dielectric loss, for routine testing
of supply mains, and for work tests on high voltage transformers, porcelain
insulators and other apparatus.
Devices are subjected to a voltage of = 1 kV + 2 × (working voltage).
A 230 V piece of equipment may thus be subjected to about 1.5 to 2
kV.
2. High Voltage direct current tests:
(i) These tests are done on apparatus expected to operate under
direct voltage conditions
(ii) Also where, due to the inconvenience of the use of high capacity
transformers required for extra high tension alternating
voltage tests and due to transport difficulties, alternating
voltage tests cannot be performed after installation.
3. High-frequency tests
(i)High frequency tests at frequencies varying from several kHz
are important where there is a possibility of high voltage in the
lines
(ii) In insulators which are expected to carry high frequency such
as radio transmitting stations.
(iv) It is also found that high frequency oscillations cause failure
of insulation at a comparatively low voltage due to high dielectric
loss and heating.
High voltage testing can be broadly classified into:
1. Testing of insulating materials (samples of dielectrics)
2. Tests on completed equipment
The tests on insulators can be divided into three groups:
(i) Type tests
(ii) Sample tests
(iii) Routine tests
Type Test:
These tests are done to determine whether the particular design is
suitable for the purpose.
Withstand Test: A 1/50 s wave of the specified voltage. is applied.
Flashover or puncture should not occur. The test is repeated five
times for each polarity.
Flash-over test: The voltage is gradually increased to the 50% impulse
flashover voltage. The test is done for both polarities. There should be
no puncture of insulation during these tests.
Dry One-minute test: The insulator, clean and dry, shall be mounted
as specified and the voltage should be gradually brought up (at
power frequency) and maintained for one minute. There shall not
be puncture or flash-over during the test.
Dry flash-over test: The voltage shall then be increased gradually
until flash-over occurs. This is repeated ten times. There shall be
no damage to the insulator.
One-minute Rain test: The insulator is sprayed throughout the test
with artificial rain drawn from a source of supply at a temperature
within 10 degree Celsius of the ambient temperature of the
neighborhood of the insulator. The rain is sprayed at an angle of 45
degree on the insulator at the rate of 3 mm/minute. The desired
voltage is maintained for one minute.
Wet flash-over test: The voltage shall then be increased gradually
until flash-over occurs. This is repeated ten times. There shall be
no damage to the insulator.
Visible discharge test:
This states that after the room has been darkened and the specified
test voltage applied, after five minutes, there should be no visible
signs of corona.
Sample Test:
The sample is tested fully, up to and including the point of breakdown.
This is done only on a few samples of the insulator.
Temperature cycle test: The complete test shall consist of five
transfers (hot-cold-hot-....), each transfer not exceeding 30 s.
Mechanical loading test: The insulator shall be mechanically loaded
up to the point of failure.
Electro-mechanical test: The insulator is simultaneously subjected
to electrical and mechanical stress. (i.e. it shall be subjected to a
power frequency voltage and a tensile force simultaneously. The
voltage shall be 75% of dry flash-over voltage. There should be no
damage caused.
Overvoltage test: The insulator shall be completely immersed in
an insulating medium (oil), to prevent external flashover
occurring. The specified overvoltage must be reached without
puncture. The voltage is then gradually increased until puncture
occurs.
Porosity test: Freshly broken pieces of porcelain shall show no
dye penetration after having been immersed for 24 hours in an
alcoholic mixture.
Routine Tests
These are to be applied to all insulators and shall be commenced at a
low voltage and shall be increased rapidly until flash-over occurs
every few seconds. The voltage shall be maintained at this value for a
minimum of five minutes, or if failures occur, for five minutes after the
last punctured piece has been removed. At the conclusion of the test
the voltage shall be reduced to about one-third of the test voltage
before switching off.
Mechanical Routine Test: A mechanical load of 20% in excess of the
maximum working load of the insulator is applied after suspending
the insulator for one minute. There should be no mechanical failure of
the insulator.
Thank You

More Related Content

Similar to Tests on insulators.pptx

INSULATOR FAILURE AND PROTECTION.pptx
INSULATOR FAILURE AND PROTECTION.pptxINSULATOR FAILURE AND PROTECTION.pptx
INSULATOR FAILURE AND PROTECTION.pptxArpitaBanik8
 
Flash-over testing of overhead insulators
Flash-over testing of overhead insulatorsFlash-over testing of overhead insulators
Flash-over testing of overhead insulatorsSAGAR D
 
ELECTRICAL SAFETY FOR high rise building.pptx
ELECTRICAL SAFETY FOR high rise building.pptxELECTRICAL SAFETY FOR high rise building.pptx
ELECTRICAL SAFETY FOR high rise building.pptxgprtpo
 
Electrical safty analyzer machine ppt pptx
Electrical safty analyzer machine ppt pptxElectrical safty analyzer machine ppt pptx
Electrical safty analyzer machine ppt pptxMontahaAlduais
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformervikasgupta1965
 
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...Ali Sepehri
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersLiving Online
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalNihal Shiroya
 
Testing of transformer.pptx
Testing of transformer.pptxTesting of transformer.pptx
Testing of transformer.pptxNoorulAmin67
 
Distribution Transformer testing, West Bengal, India
Distribution Transformer testing,  West Bengal, IndiaDistribution Transformer testing,  West Bengal, India
Distribution Transformer testing, West Bengal, IndiaRajuMondal18
 
Impulse testing of transformer
Impulse testing of transformerImpulse testing of transformer
Impulse testing of transformerPreet_patel
 
Hướng dẫn sử dụng Testo 755-1
Hướng dẫn sử dụng Testo 755-1Hướng dẫn sử dụng Testo 755-1
Hướng dẫn sử dụng Testo 755-1Tenmars Việt Nam
 
Hướng dẫn sử dụng Testo 755-1
Hướng dẫn sử dụng  Testo 755-1Hướng dẫn sử dụng  Testo 755-1
Hướng dẫn sử dụng Testo 755-1Tenmars Việt Nam
 
AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100Ali Sepehri
 

Similar to Tests on insulators.pptx (20)

INSULATOR FAILURE AND PROTECTION.pptx
INSULATOR FAILURE AND PROTECTION.pptxINSULATOR FAILURE AND PROTECTION.pptx
INSULATOR FAILURE AND PROTECTION.pptx
 
Flash-over testing of overhead insulators
Flash-over testing of overhead insulatorsFlash-over testing of overhead insulators
Flash-over testing of overhead insulators
 
tcee-161003100321.pptx
tcee-161003100321.pptxtcee-161003100321.pptx
tcee-161003100321.pptx
 
High potential test
High potential testHigh potential test
High potential test
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
ELECTRICAL SAFETY FOR high rise building.pptx
ELECTRICAL SAFETY FOR high rise building.pptxELECTRICAL SAFETY FOR high rise building.pptx
ELECTRICAL SAFETY FOR high rise building.pptx
 
Turkey hv
Turkey hvTurkey hv
Turkey hv
 
Electrical safty analyzer machine ppt pptx
Electrical safty analyzer machine ppt pptxElectrical safty analyzer machine ppt pptx
Electrical safty analyzer machine ppt pptx
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...
AC High voltage Air Break Disconnector Switch Routine Test According to IEC 6...
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of Transformers
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihal
 
Testing of transformer.pptx
Testing of transformer.pptxTesting of transformer.pptx
Testing of transformer.pptx
 
Flashover Tests
Flashover TestsFlashover Tests
Flashover Tests
 
Distribution Transformer testing, West Bengal, India
Distribution Transformer testing,  West Bengal, IndiaDistribution Transformer testing,  West Bengal, India
Distribution Transformer testing, West Bengal, India
 
Impulse testing of transformer
Impulse testing of transformerImpulse testing of transformer
Impulse testing of transformer
 
Hướng dẫn sử dụng Testo 755-1
Hướng dẫn sử dụng Testo 755-1Hướng dẫn sử dụng Testo 755-1
Hướng dẫn sử dụng Testo 755-1
 
Hướng dẫn sử dụng Testo 755-1
Hướng dẫn sử dụng  Testo 755-1Hướng dẫn sử dụng  Testo 755-1
Hướng dẫn sử dụng Testo 755-1
 
AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100AC Circuit Breakers Routine Tests according to IEC 62271-100
AC Circuit Breakers Routine Tests according to IEC 62271-100
 
ET 5 LESSON 2 TEST EQUIPMENT.pptx
ET 5 LESSON 2 TEST EQUIPMENT.pptxET 5 LESSON 2 TEST EQUIPMENT.pptx
ET 5 LESSON 2 TEST EQUIPMENT.pptx
 

Recently uploaded

handbook on reinforce concrete and detailing
handbook on reinforce concrete and detailinghandbook on reinforce concrete and detailing
handbook on reinforce concrete and detailingAshishSingh1301
 
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024EMMANUELLEFRANCEHELI
 
engineering chemistry power point presentation
engineering chemistry  power point presentationengineering chemistry  power point presentation
engineering chemistry power point presentationsj9399037128
 
Fuzzy logic method-based stress detector with blood pressure and body tempera...
Fuzzy logic method-based stress detector with blood pressure and body tempera...Fuzzy logic method-based stress detector with blood pressure and body tempera...
Fuzzy logic method-based stress detector with blood pressure and body tempera...IJECEIAES
 
一比一原版(NEU毕业证书)东北大学毕业证成绩单原件一模一样
一比一原版(NEU毕业证书)东北大学毕业证成绩单原件一模一样一比一原版(NEU毕业证书)东北大学毕业证成绩单原件一模一样
一比一原版(NEU毕业证书)东北大学毕业证成绩单原件一模一样A
 
Databricks Generative AI FoundationCertified.pdf
Databricks Generative AI FoundationCertified.pdfDatabricks Generative AI FoundationCertified.pdf
Databricks Generative AI FoundationCertified.pdfVinayVadlagattu
 
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and ToolsMaximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Toolssoginsider
 
Autodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptxAutodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptxMustafa Ahmed
 
CLOUD COMPUTING SERVICES - Cloud Reference Modal
CLOUD COMPUTING SERVICES - Cloud Reference ModalCLOUD COMPUTING SERVICES - Cloud Reference Modal
CLOUD COMPUTING SERVICES - Cloud Reference ModalSwarnaSLcse
 
01-vogelsanger-stanag-4178-ed-2-the-new-nato-standard-for-nitrocellulose-test...
01-vogelsanger-stanag-4178-ed-2-the-new-nato-standard-for-nitrocellulose-test...01-vogelsanger-stanag-4178-ed-2-the-new-nato-standard-for-nitrocellulose-test...
01-vogelsanger-stanag-4178-ed-2-the-new-nato-standard-for-nitrocellulose-test...AshwaniAnuragi1
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxMustafa Ahmed
 
Working Principle of Echo Sounder and Doppler Effect.pdf
Working Principle of Echo Sounder and Doppler Effect.pdfWorking Principle of Echo Sounder and Doppler Effect.pdf
Working Principle of Echo Sounder and Doppler Effect.pdfSkNahidulIslamShrabo
 
5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...archanaece3
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Ramkumar k
 
Presentation on Slab, Beam, Column, and Foundation/Footing
Presentation on Slab,  Beam, Column, and Foundation/FootingPresentation on Slab,  Beam, Column, and Foundation/Footing
Presentation on Slab, Beam, Column, and Foundation/FootingEr. Suman Jyoti
 
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas SachpazisSeismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas SachpazisDr.Costas Sachpazis
 
DBMS-Report on Student management system.pptx
DBMS-Report on Student management system.pptxDBMS-Report on Student management system.pptx
DBMS-Report on Student management system.pptxrajjais1221
 
Independent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging StationIndependent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging Stationsiddharthteach18
 
21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docxrahulmanepalli02
 
Circuit Breakers for Engineering Students
Circuit Breakers for Engineering StudentsCircuit Breakers for Engineering Students
Circuit Breakers for Engineering Studentskannan348865
 

Recently uploaded (20)

handbook on reinforce concrete and detailing
handbook on reinforce concrete and detailinghandbook on reinforce concrete and detailing
handbook on reinforce concrete and detailing
 
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
 
engineering chemistry power point presentation
engineering chemistry  power point presentationengineering chemistry  power point presentation
engineering chemistry power point presentation
 
Fuzzy logic method-based stress detector with blood pressure and body tempera...
Fuzzy logic method-based stress detector with blood pressure and body tempera...Fuzzy logic method-based stress detector with blood pressure and body tempera...
Fuzzy logic method-based stress detector with blood pressure and body tempera...
 
一比一原版(NEU毕业证书)东北大学毕业证成绩单原件一模一样
一比一原版(NEU毕业证书)东北大学毕业证成绩单原件一模一样一比一原版(NEU毕业证书)东北大学毕业证成绩单原件一模一样
一比一原版(NEU毕业证书)东北大学毕业证成绩单原件一模一样
 
Databricks Generative AI FoundationCertified.pdf
Databricks Generative AI FoundationCertified.pdfDatabricks Generative AI FoundationCertified.pdf
Databricks Generative AI FoundationCertified.pdf
 
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and ToolsMaximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
 
Autodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptxAutodesk Construction Cloud (Autodesk Build).pptx
Autodesk Construction Cloud (Autodesk Build).pptx
 
CLOUD COMPUTING SERVICES - Cloud Reference Modal
CLOUD COMPUTING SERVICES - Cloud Reference ModalCLOUD COMPUTING SERVICES - Cloud Reference Modal
CLOUD COMPUTING SERVICES - Cloud Reference Modal
 
01-vogelsanger-stanag-4178-ed-2-the-new-nato-standard-for-nitrocellulose-test...
01-vogelsanger-stanag-4178-ed-2-the-new-nato-standard-for-nitrocellulose-test...01-vogelsanger-stanag-4178-ed-2-the-new-nato-standard-for-nitrocellulose-test...
01-vogelsanger-stanag-4178-ed-2-the-new-nato-standard-for-nitrocellulose-test...
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptx
 
Working Principle of Echo Sounder and Doppler Effect.pdf
Working Principle of Echo Sounder and Doppler Effect.pdfWorking Principle of Echo Sounder and Doppler Effect.pdf
Working Principle of Echo Sounder and Doppler Effect.pdf
 
5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
Presentation on Slab, Beam, Column, and Foundation/Footing
Presentation on Slab,  Beam, Column, and Foundation/FootingPresentation on Slab,  Beam, Column, and Foundation/Footing
Presentation on Slab, Beam, Column, and Foundation/Footing
 
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas SachpazisSeismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
 
DBMS-Report on Student management system.pptx
DBMS-Report on Student management system.pptxDBMS-Report on Student management system.pptx
DBMS-Report on Student management system.pptx
 
Independent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging StationIndependent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging Station
 
21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx
 
Circuit Breakers for Engineering Students
Circuit Breakers for Engineering StudentsCircuit Breakers for Engineering Students
Circuit Breakers for Engineering Students
 

Tests on insulators.pptx

  • 2. General tests carried out on High voltage equipment 1. Sustained low-frequency tests: (i) Sustained low frequency tests are done at power frequency (50 Hz) (ii) Tests are made upon specimens of insulation materials for the determination of dielectric strength and dielectric loss, for routine testing of supply mains, and for work tests on high voltage transformers, porcelain insulators and other apparatus. Devices are subjected to a voltage of = 1 kV + 2 × (working voltage). A 230 V piece of equipment may thus be subjected to about 1.5 to 2 kV.
  • 3. 2. High Voltage direct current tests: (i) These tests are done on apparatus expected to operate under direct voltage conditions (ii) Also where, due to the inconvenience of the use of high capacity transformers required for extra high tension alternating voltage tests and due to transport difficulties, alternating voltage tests cannot be performed after installation. 3. High-frequency tests (i)High frequency tests at frequencies varying from several kHz are important where there is a possibility of high voltage in the lines (ii) In insulators which are expected to carry high frequency such as radio transmitting stations. (iv) It is also found that high frequency oscillations cause failure of insulation at a comparatively low voltage due to high dielectric loss and heating.
  • 4. High voltage testing can be broadly classified into: 1. Testing of insulating materials (samples of dielectrics) 2. Tests on completed equipment The tests on insulators can be divided into three groups: (i) Type tests (ii) Sample tests (iii) Routine tests
  • 5. Type Test: These tests are done to determine whether the particular design is suitable for the purpose. Withstand Test: A 1/50 s wave of the specified voltage. is applied. Flashover or puncture should not occur. The test is repeated five times for each polarity. Flash-over test: The voltage is gradually increased to the 50% impulse flashover voltage. The test is done for both polarities. There should be no puncture of insulation during these tests.
  • 6. Dry One-minute test: The insulator, clean and dry, shall be mounted as specified and the voltage should be gradually brought up (at power frequency) and maintained for one minute. There shall not be puncture or flash-over during the test. Dry flash-over test: The voltage shall then be increased gradually until flash-over occurs. This is repeated ten times. There shall be no damage to the insulator. One-minute Rain test: The insulator is sprayed throughout the test with artificial rain drawn from a source of supply at a temperature within 10 degree Celsius of the ambient temperature of the neighborhood of the insulator. The rain is sprayed at an angle of 45 degree on the insulator at the rate of 3 mm/minute. The desired voltage is maintained for one minute. Wet flash-over test: The voltage shall then be increased gradually until flash-over occurs. This is repeated ten times. There shall be no damage to the insulator.
  • 7. Visible discharge test: This states that after the room has been darkened and the specified test voltage applied, after five minutes, there should be no visible signs of corona.
  • 8. Sample Test: The sample is tested fully, up to and including the point of breakdown. This is done only on a few samples of the insulator. Temperature cycle test: The complete test shall consist of five transfers (hot-cold-hot-....), each transfer not exceeding 30 s. Mechanical loading test: The insulator shall be mechanically loaded up to the point of failure. Electro-mechanical test: The insulator is simultaneously subjected to electrical and mechanical stress. (i.e. it shall be subjected to a power frequency voltage and a tensile force simultaneously. The voltage shall be 75% of dry flash-over voltage. There should be no damage caused.
  • 9. Overvoltage test: The insulator shall be completely immersed in an insulating medium (oil), to prevent external flashover occurring. The specified overvoltage must be reached without puncture. The voltage is then gradually increased until puncture occurs. Porosity test: Freshly broken pieces of porcelain shall show no dye penetration after having been immersed for 24 hours in an alcoholic mixture.
  • 10. Routine Tests These are to be applied to all insulators and shall be commenced at a low voltage and shall be increased rapidly until flash-over occurs every few seconds. The voltage shall be maintained at this value for a minimum of five minutes, or if failures occur, for five minutes after the last punctured piece has been removed. At the conclusion of the test the voltage shall be reduced to about one-third of the test voltage before switching off. Mechanical Routine Test: A mechanical load of 20% in excess of the maximum working load of the insulator is applied after suspending the insulator for one minute. There should be no mechanical failure of the insulator.