This document discusses asset management and maintenance delivery, focusing on predictive maintenance through diagnostic testing of electrical assets. It provides an overview of asset management principles and decision making, then details various online and offline diagnostic tests for transformers, switchyards, motors, switchgear, and cables. These include tests like oil analysis, thermography, partial discharge testing, and insulation resistance measurements. Condition criteria are outlined to assess asset health and determine maintenance needs based on test results. Consistency in test setup and documentation is emphasized for effective trend analysis.
9. Operation & Maintenance Decision Making
• Maintenance regimes must provide value to the organisation to be justified
Tools to define optimum maintenance frequencies
• FMEA – Failure Mode and effects Analysis
• RCM – Reliability Centred Maintenance
• RBI – Risk Based Inspection – optimise
Where companies have adopted manufacturers maintenance regimes they must look to justify maintenance
schedules. Are labour and resources used efficiently?
10. Maintenance Delivery
Preventive PM – Often manufacturer recommended PM frequencies, functional system checks (SIL), Haz Area
Predictive PdM – Equipment diagnostic testing techniques
Condition Monitoring CM – Machines(PROGNOST®/Bentley Nevada) – Online PD
Corrective - Repair or adjustment for a condition detected in PM/PdM
Emergency – Breakdowns equipment failures
12. PdM - Transformer Diagnostic Testing
Online
• Oil Analysis – DGA – Furans
• Infrared Thermography
• Acoustic Emissions (AE)
• UHF Partial Discharge
• Radio Frequency Interference (RFI)
Note: - The test methods listed are not the only test that
can be performed, this list is made up of common tests
requested by customers.
Offline
• Insulation Resistance
• Power Factor/DDF
• DC Winding Resistance
• Turns Ratio
• Leakage Impedance
• SFRA
• Dirana
13. Review – Offline Transformer Diagnostic Testing
Polarisation Index
IEEE Std 62-1995 Paragraph 6.1.5
IEC 60076-1 (2000), clause 10.1.3
Turns Ratio
IEEE Std 62-1995 Paragraph 6.1.2
IEC 60076-1 (2000), clause 6
turns ratio tolerance should be within 0.5% of the
rating plate specifications for all windings
Winding Resistance
IEEE Std 62-1995 Paragraph 6.1.1
IEC 60076-1 (2000), clause 10.2
winding resistance within 5% tolerance compared to
the rating plate and previous results
Insulation Power Factor/ Tan Delta
IEEE- std 62-1995
IEEE std 57.12.90-1999 clause 10.10 [51]
IEC 60076-1 (2000) clause 10.1.3
Additional tests include but not limited to
• Dirana
• SFRA
PI Condition
<1 Dangerous
1 - 1.1 Poor
1.1 – 1.25 Questionable
1.25 - 2 Fair
>2 2.0 Good
Transformer
Condition of Insulation
Good Maybe
Acceptable
Should be
investigated
New DF < 0.5% - -
Serviced-aged DF < 0.5% 0.5% < DF < 1% Df > 1%
All values measured at 20°C
17. Review – Switchyard Diagnostic Testing
Corona Camera
RFI - Radio Frequency
Interference (RFI)
18. Review – Switchyard Diagnostic Testing
Bushing Test
Capacitance C2 Power & Dissipation Factor
Good <0.5% -
Monitor
>0.5% < 1.0% &
5% variation from
nameplate
Between nameplate power factor & up to
twice nameplate power factor
Poor
>0.5% < 1.0% &
10% variation from
nameplate
Between twice nameplate power factor & up
to 3 times nameplate power factor
Replace
> 1.0% and increasing
> 10% of nameplate
Above 3 times nameplate power factor
19. PdM – Motor Insulation Diagnostic Testing
Offline
• DC Insulation Resistance – PI
• DLA/DDF
• Partial Discharge (PD)
• ElCid
• RSO
• Note: - The test methods listed are not the only test
that can be performed, this list is made up of
common tests requested by customers.
Online
• Partial Discharge
20. Review – Motor Insulation Diagnostic Testing
DC Insulation Resistance
Insulation Power Factor DDF/ Tan Delta
DDF testing proves more beneficial when trending(monitoring change)
PI Condition
<1 Poor
1-2 Questionable
2-4 Fair
>4 Good
Insulation System %PF@2kV %PF Tip-Up
Asphalt-Mica 3.0 or less 2.0 or less
Polyester & Epoxy Mica 1.0 or less 1.0 or less
Pre-1980 Epoxy Mica 1.5 or less 1.5or less
21. Review – Motor Insulation Diagnostic Testing
Partial Discharge
Base lining and continues trending provides best value from PD testing.
ElCiD – Electromagnetic Core imperfection Detection
28. Consistency in Diagnostic Testing Techniques
It is critical that test conditions are recorded when testing to enable trending
• Temperature
• Humidity
• Load
• Test equipment
• Type Model
• Test voltage/current
• Connection arrangements