SlideShare a Scribd company logo
 Section 1. Instruction to Tenderers
 Section 2. Tender Data Sheet
 Section 3. General Conditions of Contract
 Section 4. Particular Conditions of Contract
 Section 5. Tender & Contract Forms
 Section 6. Bill of Quantities
 Section 7. General Specifications
 Section 8. Particular Specifications
 Section 9. Drawings
A. General
Scope
Corrupt and Fraudulent cases
Tenderer’s Eligibility
B. Tender Document
Clarification
Addendum
C. Qualification Criteria
Experience
Financial requirements
D. Tender Preparation
Language, Prices, Currency
Tenderer’s Documents
Tender Security
E. Tender Submission
Sealing, Marking and Submitting
Modification, Substitution and Withdrawal
F. Tender Opening & Evaluation
Tender Opening
Preliminary, Technical and Financial Examination
Post-qualification
G. Contract Award
Notifying Award
Performance Security
A. General
Name of the Procuring Entity & Works
Lot No. – Single Lot
B. Tender Document
Address of the Procuring Entity
C. Qualification Criteria
Experience – Tk. 1.5 million over 3 years
Annual Construction Turnover - Tk. 1 million
Liquid Asset – Tk. 500 thousand
D. Tender Preparation
Additional Documents
Validity Period – 90 days
Tender Security – Tk. 60 thousand
E. Tender Submission
Address for Submission
Deadline - 22/07/2013 up to 3:00pm
F. Tender Opening & Evaluation
Tender Opening Address
Time & Date - 22/07/2013 up to 3:30pm
G. Contract Award
Performance Security – 10% of the contract
price
A. General
Definitions
Corrupt, Fraudulent, Collusive or Coercive
Practices
Documents Forming the Contract and Priority of
Documents
Eligibility
A. General
Possession of the Site
Procuring Entity’s Responsibilities
Contractor’s Responsibilities
Taxes and Duties
Contractor’s Personnel
B. Time Control
Start Date
Intended Completion Date
Programme of Works
Extension of the Intended Completion
C. Time Control
Execution of Works
Identifying Defects
Testing
Rejection of Works
Remedial Work
Correction of Defects
D. Cost Control
Contract Price
Bill of Quantities (BOQ)
Changes in the Quantities and Unit Rate or
Price
Variations
Costing of Variation Orders
D. Cost Control
Payment Certificates
Payments to the Contractor
Compensation Events
Retention Money
Liquidated Damages
Performance Security
E. Completion of Contract
Completion
Completion Certificate and Taking Over
Amendment to Contract
Final Account
Release from Performance
F. Termination and Settlement of Disputes
Termination
Payment upon Termination
Property
G. Disputes and Arbitration
Settlement of Disputes
Name of the Contractor and Project Manager
Name of the Procuring Entity
Location of site – Uttara, Sector-12, Dhaka
Brief Description of the Works
Other Documents forming the Contract
Date of Possession of Site
Date of Starting & Completion
Submission of Programme of Works – 10 days
of signing contract
Defect Liability Period – 12 months
Compensation Events – None
Contract Price
Portion of Payments to be Retained –
10% of Performance Security
Amount of Liquidated Damages –
0.1 of 1% of the final contract price
Max Amount of Liquidated Damages –
10% of final contract price
Procuring Entity’s additional cost for completing
uncompleted works –
10% of the contract value of the works not
completed
Location of Arbitration – Dhaka
Tender Forms
a) Tender Submission Letter
b) Tenderer’s Information
c) Bank Guarantee for Tender Security
Contract Forms
a) Notification of Award
b) Contract Agreement
c) Bank Guarantee for Performance
Security
Tender Forms
a) Tender Submission Letter
Tender Price and Validation Date Limit
Attachment: Tender Security
(pay order/bank draft/ bank Guarantee)
Tender Forms
b) Tenderer’s Information
Eligibility and Qualification Information
National Identification of Tenderer
Working Experience
Source of Financial Resources
Tender Forms
c) Bank Guarantee for Tender Security
Valid up to 28 days beyond the expiration date
of tender validity period
Contract Forms
a) Notification of Award
Given to selected tenderer and requests to-
Accept it in writing within 7 working days
Furnish performance security
Sign the contract within 14 working days
Contract Forms
b) Contract Agreement
Most important document on the contract
condition according to which the work will
be executed
Payment of money to the contractor is
done after signing this document by both
party.
Contract Forms
c) Bank Guarantee for Performance Security
For the execution of work under this contract it must
be supported by a bank guarantee for performance
security
Main parts of ‘Bill of Quantities’
Earth Work
RCC Works
Reinforcements
Brick soling, CC, DPC
Brickwork, Plastering & Floor finish
Door and Window Materials
Earthwork
Layout & Marking
Earthwork in excavation
Sand filling
Earth filling
RCC Works
Formwork in footing,
column, grade beam etc.
Concrete in footing,
column, grade beam etc.
Reinforcement
Reinforcement in-
Footing
Grade beam
Column
Slab etc.
Brick soling, CC, DPC
Brick flat soling in
foundation and in floor
Mass concrete (1:3:6) in
foundation, Floor
Damp proof course (DPC)
(1:1.5:3)
Brickwork, plastering
and floor finish
Brick works in
superstructure(cement
sand (F.M. 1.2) mortar
(1:6))
Cement sand plaster with
fresh cement to wall both
inner-and outer
surface(Minimum 12 mm
thick sand (F.M. 1.2)
plaster (1:4)) etc.
Door and window
materials
Door frames.( Preferable
natural seasoned Mehgoni)
Door shutter. (Preferable
solid Gamari wood)
Windows. (Preferable
Aluminum sliding silver
colour)
The tenderers have to estimate the materials according
to the design of the project
The tenderers have to input unit price of the materials
as per specification given
The tenderers have to provide with the sub total and
gross total cost of the materials
The tenderer offering lowest gross total maintaining the
specifications and demand will be preferred for the
contract of the project
 General Items for Site Facilities
 Drawings
 Scaffolding
 Protection of Works
 Samples
 Temporary and Permanent Services
 Safety and Security Measures
 Safe Stairways, Ladders & Platforms
 Preserve & Protect all existing Public Properties
 Environment Protection & Disposal of
Wastes
 Dust Protection
 Weather Protection
 Demolished & Salvaged Materials
 Specification Materials
 Excavation
 Backfilling
 Concrete Materials
 Cement
• Comply with relevant ASTM
• Only OPC shall be used in all of the Structural Elements
 Fine & Coarse Aggregates
 All Aggregates Shall however be tested and
quarry shall be proved to comply with the Contract
Specifications
 Crushed Lime Stone Fines shall not be used
 Admixtures
 Resistance to workability, impermeability
shrinkage cracks
 No other admixture will be permitted unless it has
been approved by the Design Professional
 Reinforcement
 Reinforcing Steel: High yield deformed weld able steel
bars (BS Standard)
 Grade Minimum Yield Strength
 High Yield Steel 414 MPa
 Mild Steel 278 MPa
 Specification for Workmanship
 Shall be of good commercial quality
 Materials’ Testing
 The contractor to accompany the required
materials with a testing certificate from a
laboratory approved by the Engineer
 Any materials that don’t pass the test shall be
rejected
 Basis of measurement and payment is
provided in BOQ
In case of confusion/conflict or the items which have not
been covered here including Cast in Place Concrete,
Concrete Curing, Floor Tile Work, Wall Tile Work, Metal
Fabrication, Windows and Doors, Painting Works,
Drainage Electrical Installations Plumbing and sanitary
Installations, Fire fighting, Local Government Engineering
Department (LGED) Specification on “Building Works” shall
govern.
Ground Floor Plan
Column Layout Plan
Grade Beam Layout Plan & Long Section
Roof Beam Layout Plan & Long Section
Reinforcement Details of Roof
Footing Layout Plan
Footing & Column Schedule
THANK YOU

More Related Content

What's hot

Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
vvsasane
 
Bid Submission and Evaluation
Bid Submission and EvaluationBid Submission and Evaluation
Bid Submission and Evaluation
AkshathaBhandary
 
Tendering process cvc_guidelines
Tendering process cvc_guidelinesTendering process cvc_guidelines
Tendering process cvc_guidelines
Ritesh Kumar Baranwal
 
BIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTBIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACT
VISHNU VIJAYAN
 
Construction tender process
Construction tender processConstruction tender process
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
Melvin Lim
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 
Tenders, their types and process
Tenders, their types and processTenders, their types and process
Tenders, their types and process
Pradipta Vaskar Mukherjee
 
The Basics of Tendering & Bidding
The Basics of Tendering & BiddingThe Basics of Tendering & Bidding
The Basics of Tendering & Bidding
Moatasem Mabrouk
 
tamil nadu tenders act.pptx
tamil nadu tenders act.pptxtamil nadu tenders act.pptx
tamil nadu tenders act.pptx
Pradeep513562
 
Tendering presenation
Tendering presenationTendering presenation
Tendering presenation
JIT KUMAR GUPTA
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
Rajesh Sharma
 
Tender processing
Tender processingTender processing
Tender processingdnyandev_d
 
Fidic 99 ppt by dr karim
Fidic 99 ppt by dr karimFidic 99 ppt by dr karim
Fidic 99 ppt by dr karim
Salama Shurrab
 
Bid and Tender Process Training Presentation
Bid and Tender Process Training PresentationBid and Tender Process Training Presentation
Bid and Tender Process Training Presentation
Michael Lee
 
SBD - 3 - ICTAD
SBD - 3 - ICTADSBD - 3 - ICTAD
SBD - 3 - ICTAD
Vj NiroSh
 
Tender Evaluation.pptx
Tender Evaluation.pptxTender Evaluation.pptx
Tender Evaluation.pptx
ssuser328a4d
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedure
ayushida
 
Module 4 lecture 1
Module  4 lecture 1Module  4 lecture 1
Module 4 lecture 1
Shashi Kumara
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentation
ArchDuty
 

What's hot (20)

Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 
Bid Submission and Evaluation
Bid Submission and EvaluationBid Submission and Evaluation
Bid Submission and Evaluation
 
Tendering process cvc_guidelines
Tendering process cvc_guidelinesTendering process cvc_guidelines
Tendering process cvc_guidelines
 
BIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTBIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACT
 
Construction tender process
Construction tender processConstruction tender process
Construction tender process
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Tenders, their types and process
Tenders, their types and processTenders, their types and process
Tenders, their types and process
 
The Basics of Tendering & Bidding
The Basics of Tendering & BiddingThe Basics of Tendering & Bidding
The Basics of Tendering & Bidding
 
tamil nadu tenders act.pptx
tamil nadu tenders act.pptxtamil nadu tenders act.pptx
tamil nadu tenders act.pptx
 
Tendering presenation
Tendering presenationTendering presenation
Tendering presenation
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
 
Tender processing
Tender processingTender processing
Tender processing
 
Fidic 99 ppt by dr karim
Fidic 99 ppt by dr karimFidic 99 ppt by dr karim
Fidic 99 ppt by dr karim
 
Bid and Tender Process Training Presentation
Bid and Tender Process Training PresentationBid and Tender Process Training Presentation
Bid and Tender Process Training Presentation
 
SBD - 3 - ICTAD
SBD - 3 - ICTADSBD - 3 - ICTAD
SBD - 3 - ICTAD
 
Tender Evaluation.pptx
Tender Evaluation.pptxTender Evaluation.pptx
Tender Evaluation.pptx
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedure
 
Module 4 lecture 1
Module  4 lecture 1Module  4 lecture 1
Module 4 lecture 1
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentation
 

Viewers also liked

Lotus procure : A Complete Overview
Lotus procure : A Complete OverviewLotus procure : A Complete Overview
Lotus procure : A Complete Overview
OSMO IT Solution Pvt. Ltd.
 
Lecture slides4; Construction Project Planning
Lecture slides4; Construction Project PlanningLecture slides4; Construction Project Planning
Lecture slides4; Construction Project Planning
JB Nartey
 
Intro To Procurement And Tendering In Wales Slideset
Intro To Procurement And Tendering In Wales   SlidesetIntro To Procurement And Tendering In Wales   Slideset
Intro To Procurement And Tendering In Wales Slideset
Dawn_Rowley
 
UDL as an Architecture for Learning
UDL as an Architecture for LearningUDL as an Architecture for Learning
UDL as an Architecture for Learning
itslearning, inc.
 
Ethiopian tender practice
Ethiopian tender practiceEthiopian tender practice
Ethiopian tender practice
Eyob Ahmed
 
Bussiness planning process
Bussiness planning processBussiness planning process
Bussiness planning process
Dr Fereidoun Dejahang
 
Re Defining The Learning Architecture In Your School Tony Carrucan
Re Defining The Learning Architecture In Your School Tony CarrucanRe Defining The Learning Architecture In Your School Tony Carrucan
Re Defining The Learning Architecture In Your School Tony Carrucan
tcarrucan
 
Equity powerpoint
Equity powerpointEquity powerpoint
Equity powerpointsbyam
 
Tender Management by Ramon A. Pili
Tender Management by Ramon A. PiliTender Management by Ramon A. Pili
Tender Management by Ramon A. Pili
Vicky Fakhrurrazi
 
Tender calling procedure
Tender calling procedureTender calling procedure
Tender calling procedure
Shourya Puri
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignment
wendyteosy
 
Ct assignment
Ct assignmentCt assignment
Ct assignment
Darren Loong
 
How to tender. The basics.
How to tender. The basics.How to tender. The basics.
How to tender. The basics.convcat11
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 Assignment
Melvin Lim
 
Tendering and Procurement Best Practices
Tendering and Procurement Best PracticesTendering and Procurement Best Practices
Tendering and Procurement Best Practices
SHKLaw
 
Interior Architecture (Design Studio); Sustainability - Part B
Interior Architecture (Design Studio); Sustainability - Part BInterior Architecture (Design Studio); Sustainability - Part B
Interior Architecture (Design Studio); Sustainability - Part B
Larissa Ellen
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
Hasif Alias
 
Tendering procedures 1
Tendering procedures 1Tendering procedures 1
Tendering procedures 1
Mohammed Fadlalla ,PMP ®
 
Tendering and Procurement - Basic Principles
Tendering and Procurement   - Basic PrinciplesTendering and Procurement   - Basic Principles
Tendering and Procurement - Basic Principles
SHKLaw
 
Thesis5th Year Architecture Studio
Thesis5th Year Architecture StudioThesis5th Year Architecture Studio
Thesis5th Year Architecture StudioRobertconklin
 

Viewers also liked (20)

Lotus procure : A Complete Overview
Lotus procure : A Complete OverviewLotus procure : A Complete Overview
Lotus procure : A Complete Overview
 
Lecture slides4; Construction Project Planning
Lecture slides4; Construction Project PlanningLecture slides4; Construction Project Planning
Lecture slides4; Construction Project Planning
 
Intro To Procurement And Tendering In Wales Slideset
Intro To Procurement And Tendering In Wales   SlidesetIntro To Procurement And Tendering In Wales   Slideset
Intro To Procurement And Tendering In Wales Slideset
 
UDL as an Architecture for Learning
UDL as an Architecture for LearningUDL as an Architecture for Learning
UDL as an Architecture for Learning
 
Ethiopian tender practice
Ethiopian tender practiceEthiopian tender practice
Ethiopian tender practice
 
Bussiness planning process
Bussiness planning processBussiness planning process
Bussiness planning process
 
Re Defining The Learning Architecture In Your School Tony Carrucan
Re Defining The Learning Architecture In Your School Tony CarrucanRe Defining The Learning Architecture In Your School Tony Carrucan
Re Defining The Learning Architecture In Your School Tony Carrucan
 
Equity powerpoint
Equity powerpointEquity powerpoint
Equity powerpoint
 
Tender Management by Ramon A. Pili
Tender Management by Ramon A. PiliTender Management by Ramon A. Pili
Tender Management by Ramon A. Pili
 
Tender calling procedure
Tender calling procedureTender calling procedure
Tender calling procedure
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignment
 
Ct assignment
Ct assignmentCt assignment
Ct assignment
 
How to tender. The basics.
How to tender. The basics.How to tender. The basics.
How to tender. The basics.
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 Assignment
 
Tendering and Procurement Best Practices
Tendering and Procurement Best PracticesTendering and Procurement Best Practices
Tendering and Procurement Best Practices
 
Interior Architecture (Design Studio); Sustainability - Part B
Interior Architecture (Design Studio); Sustainability - Part BInterior Architecture (Design Studio); Sustainability - Part B
Interior Architecture (Design Studio); Sustainability - Part B
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
 
Tendering procedures 1
Tendering procedures 1Tendering procedures 1
Tendering procedures 1
 
Tendering and Procurement - Basic Principles
Tendering and Procurement   - Basic PrinciplesTendering and Procurement   - Basic Principles
Tendering and Procurement - Basic Principles
 
Thesis5th Year Architecture Studio
Thesis5th Year Architecture StudioThesis5th Year Architecture Studio
Thesis5th Year Architecture Studio
 

Similar to Tendering Document for the Procurement of Works

Contract presentation
Contract presentation  Contract presentation
Contract presentation
amity university
 
Measurement iv
Measurement ivMeasurement iv
Measurement iv
tfkc1212
 
Fififinalnal
FififinalnalFififinalnal
Fififinalnal
Lai Vlyn
 
Contract_Design_for_Dam_Construction.pdf
Contract_Design_for_Dam_Construction.pdfContract_Design_for_Dam_Construction.pdf
Contract_Design_for_Dam_Construction.pdf
YeshiharegAlemu
 
Contract & Tender Management
Contract & Tender ManagementContract & Tender Management
Contract & Tender Management
Anand Subramaniam
 
Bonny Resume ( Proc)
Bonny Resume ( Proc)Bonny Resume ( Proc)
Bonny Resume ( Proc)Bonny Sam
 
Tender
TenderTender
Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)
Kai Yun Pang
 
Eng ramy nabil 2016
Eng ramy nabil 2016Eng ramy nabil 2016
Eng ramy nabil 2016
ramy nabil
 
tendering
 tendering tendering
tendering
KEVINMISTRY8
 
Contracts & tenders
Contracts & tendersContracts & tenders
Contracts & tenders
Swamy Vanapalli
 
Estimation & Technical Engr CV
Estimation & Technical Engr CVEstimation & Technical Engr CV
Estimation & Technical Engr CVmuhammad abdullah
 
Construction practices
Construction practicesConstruction practices
Construction practices
Arun Kurali
 
MEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATIONMEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATION
Farah Sham
 
Construction Costing Proposal PowerPoint Presentation Slides
Construction Costing Proposal PowerPoint Presentation SlidesConstruction Costing Proposal PowerPoint Presentation Slides
Construction Costing Proposal PowerPoint Presentation Slides
SlideTeam
 
Construction Bid Proposal Template PowerPoint Presentation Slides
Construction Bid Proposal Template PowerPoint Presentation SlidesConstruction Bid Proposal Template PowerPoint Presentation Slides
Construction Bid Proposal Template PowerPoint Presentation Slides
SlideTeam
 
Pre Bid Risk Assessment
Pre Bid Risk AssessmentPre Bid Risk Assessment
Pre Bid Risk Assessment
Sukhdarshan Singh
 
Chapter one new.pptx
Chapter one new.pptxChapter one new.pptx
Chapter one new.pptx
HumnaTolina
 
Construction Work Schedule Proposal PowerPoint Presentation Slides
Construction Work Schedule Proposal PowerPoint Presentation SlidesConstruction Work Schedule Proposal PowerPoint Presentation Slides
Construction Work Schedule Proposal PowerPoint Presentation Slides
SlideTeam
 

Similar to Tendering Document for the Procurement of Works (20)

Contract presentation
Contract presentation  Contract presentation
Contract presentation
 
Measurement iv
Measurement ivMeasurement iv
Measurement iv
 
Fififinalnal
FififinalnalFififinalnal
Fififinalnal
 
Contract_Design_for_Dam_Construction.pdf
Contract_Design_for_Dam_Construction.pdfContract_Design_for_Dam_Construction.pdf
Contract_Design_for_Dam_Construction.pdf
 
Contract & Tender Management
Contract & Tender ManagementContract & Tender Management
Contract & Tender Management
 
Bonny Resume ( Proc)
Bonny Resume ( Proc)Bonny Resume ( Proc)
Bonny Resume ( Proc)
 
Tender
TenderTender
Tender
 
Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)
 
Eng ramy nabil 2016
Eng ramy nabil 2016Eng ramy nabil 2016
Eng ramy nabil 2016
 
tendering
 tendering tendering
tendering
 
Arunkumar_Proc & Contr_25.12.2014
Arunkumar_Proc & Contr_25.12.2014Arunkumar_Proc & Contr_25.12.2014
Arunkumar_Proc & Contr_25.12.2014
 
Contracts & tenders
Contracts & tendersContracts & tenders
Contracts & tenders
 
Estimation & Technical Engr CV
Estimation & Technical Engr CVEstimation & Technical Engr CV
Estimation & Technical Engr CV
 
Construction practices
Construction practicesConstruction practices
Construction practices
 
MEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATIONMEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATION
 
Construction Costing Proposal PowerPoint Presentation Slides
Construction Costing Proposal PowerPoint Presentation SlidesConstruction Costing Proposal PowerPoint Presentation Slides
Construction Costing Proposal PowerPoint Presentation Slides
 
Construction Bid Proposal Template PowerPoint Presentation Slides
Construction Bid Proposal Template PowerPoint Presentation SlidesConstruction Bid Proposal Template PowerPoint Presentation Slides
Construction Bid Proposal Template PowerPoint Presentation Slides
 
Pre Bid Risk Assessment
Pre Bid Risk AssessmentPre Bid Risk Assessment
Pre Bid Risk Assessment
 
Chapter one new.pptx
Chapter one new.pptxChapter one new.pptx
Chapter one new.pptx
 
Construction Work Schedule Proposal PowerPoint Presentation Slides
Construction Work Schedule Proposal PowerPoint Presentation SlidesConstruction Work Schedule Proposal PowerPoint Presentation Slides
Construction Work Schedule Proposal PowerPoint Presentation Slides
 

More from Mohammad Alimuzzaman Bappy

Coal power environment global perspective
Coal power environment global perspectiveCoal power environment global perspective
Coal power environment global perspective
Mohammad Alimuzzaman Bappy
 
Energy Scenario of Denmark
Energy Scenario of DenmarkEnergy Scenario of Denmark
Energy Scenario of Denmark
Mohammad Alimuzzaman Bappy
 
Bod(biochemical oxygen demand)
Bod(biochemical oxygen demand) Bod(biochemical oxygen demand)
Bod(biochemical oxygen demand)
Mohammad Alimuzzaman Bappy
 
Energy as tender
Energy as tenderEnergy as tender
Energy as tender
Mohammad Alimuzzaman Bappy
 
Energy science
Energy scienceEnergy science
Study of Ground Water Recharge from Rainfall in Dhaka City
Study of Ground Water Recharge from Rainfall in Dhaka CityStudy of Ground Water Recharge from Rainfall in Dhaka City
Study of Ground Water Recharge from Rainfall in Dhaka City
Mohammad Alimuzzaman Bappy
 
Organic Chemistry
Organic Chemistry Organic Chemistry
Organic Chemistry
Mohammad Alimuzzaman Bappy
 
Renewable Energy Scenario comparison (USA-Russia-France)
Renewable Energy Scenario comparison (USA-Russia-France)Renewable Energy Scenario comparison (USA-Russia-France)
Renewable Energy Scenario comparison (USA-Russia-France)
Mohammad Alimuzzaman Bappy
 
Climate change coastal zone of bangladesh
Climate change coastal zone of bangladeshClimate change coastal zone of bangladesh
Climate change coastal zone of bangladesh
Mohammad Alimuzzaman Bappy
 
Design of an industrial park
Design of an industrial parkDesign of an industrial park
Design of an industrial park
Mohammad Alimuzzaman Bappy
 
Mrt
MrtMrt
History of The world
History of The world History of The world
History of The world
Mohammad Alimuzzaman Bappy
 
Prediction of energy mix in power production bangladesh context 2030
Prediction of energy mix in power production bangladesh context 2030Prediction of energy mix in power production bangladesh context 2030
Prediction of energy mix in power production bangladesh context 2030
Mohammad Alimuzzaman Bappy
 
Flexural lecture
Flexural lectureFlexural lecture
Flexural lecture
Mohammad Alimuzzaman Bappy
 
Compression member
Compression memberCompression member
Compression member
Mohammad Alimuzzaman Bappy
 
Cement
CementCement

More from Mohammad Alimuzzaman Bappy (16)

Coal power environment global perspective
Coal power environment global perspectiveCoal power environment global perspective
Coal power environment global perspective
 
Energy Scenario of Denmark
Energy Scenario of DenmarkEnergy Scenario of Denmark
Energy Scenario of Denmark
 
Bod(biochemical oxygen demand)
Bod(biochemical oxygen demand) Bod(biochemical oxygen demand)
Bod(biochemical oxygen demand)
 
Energy as tender
Energy as tenderEnergy as tender
Energy as tender
 
Energy science
Energy scienceEnergy science
Energy science
 
Study of Ground Water Recharge from Rainfall in Dhaka City
Study of Ground Water Recharge from Rainfall in Dhaka CityStudy of Ground Water Recharge from Rainfall in Dhaka City
Study of Ground Water Recharge from Rainfall in Dhaka City
 
Organic Chemistry
Organic Chemistry Organic Chemistry
Organic Chemistry
 
Renewable Energy Scenario comparison (USA-Russia-France)
Renewable Energy Scenario comparison (USA-Russia-France)Renewable Energy Scenario comparison (USA-Russia-France)
Renewable Energy Scenario comparison (USA-Russia-France)
 
Climate change coastal zone of bangladesh
Climate change coastal zone of bangladeshClimate change coastal zone of bangladesh
Climate change coastal zone of bangladesh
 
Design of an industrial park
Design of an industrial parkDesign of an industrial park
Design of an industrial park
 
Mrt
MrtMrt
Mrt
 
History of The world
History of The world History of The world
History of The world
 
Prediction of energy mix in power production bangladesh context 2030
Prediction of energy mix in power production bangladesh context 2030Prediction of energy mix in power production bangladesh context 2030
Prediction of energy mix in power production bangladesh context 2030
 
Flexural lecture
Flexural lectureFlexural lecture
Flexural lecture
 
Compression member
Compression memberCompression member
Compression member
 
Cement
CementCement
Cement
 

Recently uploaded

Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 

Recently uploaded (20)

Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 

Tendering Document for the Procurement of Works

  • 1.
  • 2.  Section 1. Instruction to Tenderers  Section 2. Tender Data Sheet  Section 3. General Conditions of Contract  Section 4. Particular Conditions of Contract  Section 5. Tender & Contract Forms  Section 6. Bill of Quantities  Section 7. General Specifications  Section 8. Particular Specifications  Section 9. Drawings
  • 3. A. General Scope Corrupt and Fraudulent cases Tenderer’s Eligibility B. Tender Document Clarification Addendum C. Qualification Criteria Experience Financial requirements
  • 4. D. Tender Preparation Language, Prices, Currency Tenderer’s Documents Tender Security E. Tender Submission Sealing, Marking and Submitting Modification, Substitution and Withdrawal
  • 5. F. Tender Opening & Evaluation Tender Opening Preliminary, Technical and Financial Examination Post-qualification G. Contract Award Notifying Award Performance Security
  • 6. A. General Name of the Procuring Entity & Works Lot No. – Single Lot B. Tender Document Address of the Procuring Entity C. Qualification Criteria Experience – Tk. 1.5 million over 3 years Annual Construction Turnover - Tk. 1 million Liquid Asset – Tk. 500 thousand
  • 7. D. Tender Preparation Additional Documents Validity Period – 90 days Tender Security – Tk. 60 thousand E. Tender Submission Address for Submission Deadline - 22/07/2013 up to 3:00pm
  • 8. F. Tender Opening & Evaluation Tender Opening Address Time & Date - 22/07/2013 up to 3:30pm G. Contract Award Performance Security – 10% of the contract price
  • 9. A. General Definitions Corrupt, Fraudulent, Collusive or Coercive Practices Documents Forming the Contract and Priority of Documents Eligibility
  • 10. A. General Possession of the Site Procuring Entity’s Responsibilities Contractor’s Responsibilities Taxes and Duties Contractor’s Personnel
  • 11. B. Time Control Start Date Intended Completion Date Programme of Works Extension of the Intended Completion
  • 12. C. Time Control Execution of Works Identifying Defects Testing Rejection of Works Remedial Work Correction of Defects
  • 13. D. Cost Control Contract Price Bill of Quantities (BOQ) Changes in the Quantities and Unit Rate or Price Variations Costing of Variation Orders
  • 14. D. Cost Control Payment Certificates Payments to the Contractor Compensation Events Retention Money Liquidated Damages Performance Security
  • 15. E. Completion of Contract Completion Completion Certificate and Taking Over Amendment to Contract Final Account Release from Performance
  • 16. F. Termination and Settlement of Disputes Termination Payment upon Termination Property
  • 17. G. Disputes and Arbitration Settlement of Disputes
  • 18. Name of the Contractor and Project Manager Name of the Procuring Entity Location of site – Uttara, Sector-12, Dhaka Brief Description of the Works Other Documents forming the Contract
  • 19. Date of Possession of Site Date of Starting & Completion Submission of Programme of Works – 10 days of signing contract Defect Liability Period – 12 months Compensation Events – None
  • 20. Contract Price Portion of Payments to be Retained – 10% of Performance Security Amount of Liquidated Damages – 0.1 of 1% of the final contract price Max Amount of Liquidated Damages – 10% of final contract price
  • 21. Procuring Entity’s additional cost for completing uncompleted works – 10% of the contract value of the works not completed Location of Arbitration – Dhaka
  • 22. Tender Forms a) Tender Submission Letter b) Tenderer’s Information c) Bank Guarantee for Tender Security Contract Forms a) Notification of Award b) Contract Agreement c) Bank Guarantee for Performance Security
  • 23. Tender Forms a) Tender Submission Letter Tender Price and Validation Date Limit Attachment: Tender Security (pay order/bank draft/ bank Guarantee)
  • 24. Tender Forms b) Tenderer’s Information Eligibility and Qualification Information National Identification of Tenderer Working Experience Source of Financial Resources
  • 25. Tender Forms c) Bank Guarantee for Tender Security Valid up to 28 days beyond the expiration date of tender validity period
  • 26. Contract Forms a) Notification of Award Given to selected tenderer and requests to- Accept it in writing within 7 working days Furnish performance security Sign the contract within 14 working days
  • 27. Contract Forms b) Contract Agreement Most important document on the contract condition according to which the work will be executed Payment of money to the contractor is done after signing this document by both party.
  • 28. Contract Forms c) Bank Guarantee for Performance Security For the execution of work under this contract it must be supported by a bank guarantee for performance security
  • 29. Main parts of ‘Bill of Quantities’ Earth Work RCC Works Reinforcements Brick soling, CC, DPC Brickwork, Plastering & Floor finish Door and Window Materials
  • 30. Earthwork Layout & Marking Earthwork in excavation Sand filling Earth filling RCC Works Formwork in footing, column, grade beam etc. Concrete in footing, column, grade beam etc.
  • 31. Reinforcement Reinforcement in- Footing Grade beam Column Slab etc. Brick soling, CC, DPC Brick flat soling in foundation and in floor Mass concrete (1:3:6) in foundation, Floor Damp proof course (DPC) (1:1.5:3)
  • 32. Brickwork, plastering and floor finish Brick works in superstructure(cement sand (F.M. 1.2) mortar (1:6)) Cement sand plaster with fresh cement to wall both inner-and outer surface(Minimum 12 mm thick sand (F.M. 1.2) plaster (1:4)) etc. Door and window materials Door frames.( Preferable natural seasoned Mehgoni) Door shutter. (Preferable solid Gamari wood) Windows. (Preferable Aluminum sliding silver colour)
  • 33. The tenderers have to estimate the materials according to the design of the project The tenderers have to input unit price of the materials as per specification given The tenderers have to provide with the sub total and gross total cost of the materials The tenderer offering lowest gross total maintaining the specifications and demand will be preferred for the contract of the project
  • 34.  General Items for Site Facilities  Drawings  Scaffolding  Protection of Works  Samples  Temporary and Permanent Services
  • 35.  Safety and Security Measures  Safe Stairways, Ladders & Platforms  Preserve & Protect all existing Public Properties  Environment Protection & Disposal of Wastes  Dust Protection  Weather Protection  Demolished & Salvaged Materials
  • 36.  Specification Materials  Excavation  Backfilling  Concrete Materials  Cement • Comply with relevant ASTM • Only OPC shall be used in all of the Structural Elements
  • 37.  Fine & Coarse Aggregates  All Aggregates Shall however be tested and quarry shall be proved to comply with the Contract Specifications  Crushed Lime Stone Fines shall not be used  Admixtures  Resistance to workability, impermeability shrinkage cracks  No other admixture will be permitted unless it has been approved by the Design Professional
  • 38.  Reinforcement  Reinforcing Steel: High yield deformed weld able steel bars (BS Standard)  Grade Minimum Yield Strength  High Yield Steel 414 MPa  Mild Steel 278 MPa
  • 39.  Specification for Workmanship  Shall be of good commercial quality  Materials’ Testing  The contractor to accompany the required materials with a testing certificate from a laboratory approved by the Engineer  Any materials that don’t pass the test shall be rejected
  • 40.  Basis of measurement and payment is provided in BOQ In case of confusion/conflict or the items which have not been covered here including Cast in Place Concrete, Concrete Curing, Floor Tile Work, Wall Tile Work, Metal Fabrication, Windows and Doors, Painting Works, Drainage Electrical Installations Plumbing and sanitary Installations, Fire fighting, Local Government Engineering Department (LGED) Specification on “Building Works” shall govern.
  • 41. Ground Floor Plan Column Layout Plan Grade Beam Layout Plan & Long Section Roof Beam Layout Plan & Long Section Reinforcement Details of Roof Footing Layout Plan Footing & Column Schedule
  • 42.
  • 43.
  • 44.
  • 45.
  • 46.