BIDDING
It is process of submitting a proposal
(tender) to undertake, or manage the
undertaking of a construction project.
The process starts with a cost estimate
from blueprints
3/25/2020 VISHNU VIJAYAN BMCE
TENDERS
Tender means an invitation to offer for
an item/items or work.
3/25/2020 VISHNU VIJAYAN BMCE
TENDERS
• To invite bids for a project, or to accept a
formal offer such as a takeover bid. Tender
usually refers to the process whereby
governments and financial institutions invite
bids for large projects that must be submitted
within a finite deadline.
3/25/2020 VISHNU VIJAYAN BMCE
Types of tender
• Open Tender:
• Open tender is an arrangement where an advertisement in
local newspapers or trade journals invites contractors to apply
for tender documents
• Limited or Closed Tender /Selective Tender:
• In Limited Tenders, only pre-qualified or known bidders are
allowed to participate.
• Limited Tenders are not advertised in newspapers, as a result other bidder generally do not
come to know that such tender is floated. The Lowest Bidder or L1 generally wins the
contract.
• Single Tender:
• Single Tendering means sending the Tender to one particular
party.
3/25/2020 VISHNU VIJAYAN BMCE
CONTD..
• Negotiated Tender:
• Under Negotiated Tender method normally one contractor is
approached and such tender mainly used for specialist work such as lift
system or airport project at big level, in such case there are limited
number of contractor who do such work in the market. It is based on
one-to-one discussion with contractors to negotiated the terms of
contract.
• Item Rate Tenders:
• In this type of Tenders the contractors are required to quote the rates
for each item mentioned in the price bid. The quantity to be executed
is given in the price bid.
• Percentage Rate Tenders:
• In this type of Tenders a detailed estimate of the quantity of work to
be carried out along with the estimate rates is given in the price bid
form.
3/25/2020 VISHNU VIJAYAN BMCE
TENDERING PROCEDURE – AWARD OF
TENDERS
• Whenever a government agency or firm wants
certain works to be done ,services to be rendered
or any purchases to be made, they float tender in
order to get the work done at competitive prices .
• The person who quotes the lowest price agreeing
to the terms and conditions imposed on him , will
have to sign an agreement stating that he will
perform the said work as per requirement of the
owner/client
3/25/2020 VISHNU VIJAYAN BMCE
TENDER NOTICE
• Whenever an agency or firm wants to float tender.
• Its should be need publicity
• Following information should carry in tender notice:
• Name of the department calling for tender
• Time of work and location
• Designation of the officer inviting tenders
• Last date and time of receipt of tenders
• Period of availability of tender forms
• Cost of tender document
• Time of completion and type of contract
• Earnest money deposit to be paid
• Date ,time and place of opening tenders
• Designation of the officer opening the tenders3/25/2020 VISHNU VIJAYAN BMCE
TENDER DOCUMENT
• A tender document is a document that
explains about a project and its requirements
to the intending bidders.
• A tender document typically contains a notice
inviting tenders, instruction to bidders, the
conditions, form of submission, and bill of
quantities.
3/25/2020 VISHNU VIJAYAN BMCE
Earnest money deposit(EMD)
• While submitting the tender, contractor will
have to deposit an amount is about 2% of the
estimated contract value of the project. This
amount is called
3/25/2020 VISHNU VIJAYAN BMCE
Security deposit
• Once the tender of contractor is accepted by
the client, the contractor to deposit about
10 % of the tender amount with the client.
3/25/2020 VISHNU VIJAYAN BMCE
Tendering stage
• Call for tender
• Issue tender form
• Evaluate tender
• Award contract
• Occupy successful contractors
• Sign contract document
3/25/2020 VISHNU VIJAYAN BMCE
CONTRACTS
• A contract is an agreement
having a lawful object entered
into voluntarily by two or
more parties, each of whom
intends to create one or more
legal obligations between
them.
• The elements of a contract
are "offer" and "acceptance"
by "competent persons3/25/2020 VISHNU VIJAYAN BMCE
ESSENTIAL ELEMENTS OF CONTRACTS
• Offer and acceptance: In order to create a valid contract, there must be a 'lawful offer'
by one party and ‘lawful acceptance' of the same by the other party.
• Competent Parties: For an agreement to be a contract there must be two or more
competent parties. In order to be considered competent, a part must have a certain
legal standing.
• Consideration: There must be a lawful and valuable consideration given by both Parties.
A consideration often called "Something for something." A consideration must, be
possible one.
• Proper Subject Matter: For the subject matter of a contract to be proper, the first
Requirement is that it was be clearly defined as to the rights and obligations of each
party. Second, the purpose of the contract must not violate the law.
• Agreement: For valid contract, there must be a mutual agreement. An agreement is
considered to have been reached when an offer made by one party is accepted by the
second party. Both parties must wish and intend their bargain to be Enforceable by law.
• Proper Form: The terms of a contract must be written so that both parties are very sure
of what their rights and responsibilities are.
• Consent of the Parties: The agreement must be free from Misrepresentation, Duress
Undue influence, etc.
3/25/2020 VISHNU VIJAYAN BMCE
Qualification of contractors
• Contractor are selected by the owners through any one of these
process after conducting negotiation where required
• Public tenders
• Pre qualification
• Limited tenders
• Nomination
• SOME ESSENTIAL QUALIFICATION ARE :
• HE should be financially sound
• He should have sufficient knowledge to read the drawings
• He should be well versed with procedure
• He have Good reputation and experience
• He Should have ability to handle labour and materials properly
• He Should be capable of arranging men and materials as per
requirements
3/25/2020 VISHNU VIJAYAN BMCE
CONTRACT DOCUMENT
• Before the work is given out on contract an agreement or bond is prepared. The
following
• documents shall be attached to the contract agreement or bond which should be duly
• endorsed and sealed. Each page shall bear the signature of the contractor and the
accepting
• authority and all corrections shall be similarly initialled
• TITLE PAGE
• Title page having the name of work, contract bond number, etc.
• INDEX PAGE
• Index page having the contents of the agreement with page references.
• TENDER NOTICE
• Tender notice giving brief descriptions of the work, estimated cost of work, date and
• time of the tender, amount of earnest money and security money, time of completion,
• etc. Earnest money, usually 2% of the estimated cost, is deposited along with tender.
• TENDER TORUS
• Tender torus giving the bill of quantities, contractor’s rates, and total cost of works,
• and time for completion, progress of works, security money, penalty clause, etc.
3/25/2020 VISHNU VIJAYAN BMCE
• BILL OF QUANTITIES OR SCHEDULE OF QUANTITIES
• Bill Of Quantities Or Schedule Of Quantities giving
quantities and rates of each item of work and cost of
each item of work and the total cost of the whole work.
• SCHEDULE OF ISSUE OF MATERIALS
• Schedule of issue of materials giving list of materials to
be issued to the contractor with rates and place of issue.
• GENERAL SPECIFICATIONS
• General specification specifying the class and type of
works in general.
• SPECIFICATIONS DETAILED
• Specification details of each item of work, and of each
material to be used in the work.
• DRAWINGS
• complete set of drawings including plans, elevations,
sections, detailed drawing, etc.and site plan, all fully
dimensioned.3/25/2020 VISHNU VIJAYAN BMCE
IMPORTANT CLAUSES IN CONSTRUCTION
CONTRACTS
• Definition of the terms used:
• Security deposit:
• Delay in completion:
• Payment to contractor:
• Addition and alternations:
• Execution of work:
• Defects and improper work:
• Subletting :
• Arbitration:
3/25/2020 VISHNU VIJAYAN BMCE
Types of contracts
• Types of contracts
• Lump sum
• Cost plus fixed fee contract
• Unit price contract or item rate
• Negotiated contract
• Design build
• Turn key contract
• Build own transfer contract
• Etc.............
3/25/2020 VISHNU VIJAYAN BMCE
Types of contracts
• A construction contract is the warranty that the
executed job will receive the specific amount of
compensation or how the compensation will be
distributed.
• LUMP SUM
• The contractor agrees to build a project with a
specific scope for a fixed price. A lump-sum
contract is suitable if the scope and schedule of
the project are sufficiently defined to allow the
contractor to fully estimate project costs.
3/25/2020 VISHNU VIJAYAN BMCE
• UNIT PRICE
• This kind of contract is based on estimated
quantities of items included in the project and
their unit prices. The final price of the project is
dependent on the quantities needed to carry out
the work. In general, this contract is only suitable
for projects in which the scope is reasonably well
established, and the different types of items (but
not their numbers) can be accurately identified in
the contract documents.
3/25/2020 VISHNU VIJAYAN BMCE
• COST PLUS
• Cost plus is a contract agreement wherein the
purchaser agrees to pay the cost of the work,
including all trade contractor work, labor,
materials, and equipment, plus an amount for
contractor overhead and profit. These types of
contracts are favored where the scope of work is
indeterminate or highly uncertain, and the kinds
of labor, material, and equipment needed are
also uncertain.
3/25/2020 VISHNU VIJAYAN BMCE
MEASUREMENT BOOK
• The measurements of all works and supplies are
recorded in the Measurement Book
• Form No. 23 and payment of all works and supplies are
made on the basis of measurement recorded.
• Its very important account record.
• It recorded by the executive or Assistant Engineers or
sectional officer,(overseers) to whom measurement
books have been issued for the purpose.
3/25/2020 VISHNU VIJAYAN BMCE

More Related Content

What's hot

Construction Bidding Step-by-Step
Construction Bidding Step-by-StepConstruction Bidding Step-by-Step
Construction Bidding Step-by-Step
Doina Dobre, P.Eng, GSC
 
Unit-2_Tender
Unit-2_TenderUnit-2_Tender
Unit-2_Tender
Akash Bharti
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
R.R.G.S Bandara
 
Lump Sum Contract
Lump Sum ContractLump Sum Contract
Lump Sum Contract
efinancemanagement.com
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
Abhishek kumar maurya
 
Contract Management in Civil Engineering Works
Contract Management in Civil Engineering WorksContract Management in Civil Engineering Works
Contract Management in Civil Engineering Works
Dr K M SONI
 
Bid Evaluation
Bid EvaluationBid Evaluation
Bid Evaluation
Vj NiroSh
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
politeknik malaysia
 
The Basics of Tendering & Bidding
The Basics of Tendering & BiddingThe Basics of Tendering & Bidding
The Basics of Tendering & Bidding
Moatasem Mabrouk
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
Dr K M SONI
 
Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)
Michael Audu
 
Fidic contract
Fidic contract Fidic contract
Fidic contract
Yash Patel
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
Vj NiroSh
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
jagadish108
 
Construction tender process
Construction tender processConstruction tender process
Contracts
ContractsContracts
Contracts
krrish706
 
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender Notice
Sakshi Kirar
 
Tendering
TenderingTendering
Tendering
kusha Ahmed
 
Chapter 2 construction project planning and scheduling
Chapter 2 construction project planning and schedulingChapter 2 construction project planning and scheduling
Chapter 2 construction project planning and scheduling
Subash Bhattarai
 

What's hot (20)

Construction Bidding Step-by-Step
Construction Bidding Step-by-StepConstruction Bidding Step-by-Step
Construction Bidding Step-by-Step
 
Unit-2_Tender
Unit-2_TenderUnit-2_Tender
Unit-2_Tender
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Lump Sum Contract
Lump Sum ContractLump Sum Contract
Lump Sum Contract
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
 
Contract Management in Civil Engineering Works
Contract Management in Civil Engineering WorksContract Management in Civil Engineering Works
Contract Management in Civil Engineering Works
 
Bid Evaluation
Bid EvaluationBid Evaluation
Bid Evaluation
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
 
The Basics of Tendering & Bidding
The Basics of Tendering & BiddingThe Basics of Tendering & Bidding
The Basics of Tendering & Bidding
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
 
Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)
 
Fidic contract
Fidic contract Fidic contract
Fidic contract
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
 
Construction tender process
Construction tender processConstruction tender process
Construction tender process
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
Contracts
ContractsContracts
Contracts
 
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender Notice
 
Tendering
TenderingTendering
Tendering
 
Chapter 2 construction project planning and scheduling
Chapter 2 construction project planning and schedulingChapter 2 construction project planning and scheduling
Chapter 2 construction project planning and scheduling
 

Similar to BIDDING-TENDER-CONTRACT

Types of contracts
Types of contractsTypes of contracts
Types of contracts
Tulsi Pokhrel
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptx
jairam131
 
Tanmay presentation
Tanmay presentationTanmay presentation
Tanmay presentation
TanmayBhatt22
 
Qsct tendering dr_clj
Qsct tendering dr_cljQsct tendering dr_clj
Qsct tendering dr_clj
Chandrakant Jejurkar
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
srinivas2036
 
Unit 5 Tendering
Unit 5 Tendering Unit 5 Tendering
Unit 5 Tendering
Padmasinh Patil
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
Archistudent Portal
 
Construction contract
Construction contract Construction contract
Construction contract
Rakshith Reddy
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
Timun Loh
 
Contracts Management
Contracts Management Contracts Management
Contracts Management
Mohib Ullah
 
Unit 1-Contract Documents & Byelaws
Unit 1-Contract Documents & ByelawsUnit 1-Contract Documents & Byelaws
Unit 1-Contract Documents & Byelaws
Kunal Kacholiya
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
SHKLaw
 
Procurement Management
Procurement ManagementProcurement Management
Procurement Management
learnafren
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
kohwenqi
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
Waleed Liaqat
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
mianmohsinmumtazshb
 
Procurement of works
Procurement of worksProcurement of works
Procurement of works
Ayush Joshi
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
ByishimoBTCChef
 
TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
HASMANIRA
 

Similar to BIDDING-TENDER-CONTRACT (20)

Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptx
 
Tanmay presentation
Tanmay presentationTanmay presentation
Tanmay presentation
 
Qsct tendering dr_clj
Qsct tendering dr_cljQsct tendering dr_clj
Qsct tendering dr_clj
 
contract procedure
contract procedurecontract procedure
contract procedure
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Unit 5 Tendering
Unit 5 Tendering Unit 5 Tendering
Unit 5 Tendering
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Construction contract
Construction contract Construction contract
Construction contract
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
Contracts Management
Contracts Management Contracts Management
Contracts Management
 
Unit 1-Contract Documents & Byelaws
Unit 1-Contract Documents & ByelawsUnit 1-Contract Documents & Byelaws
Unit 1-Contract Documents & Byelaws
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
Procurement Management
Procurement ManagementProcurement Management
Procurement Management
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
 
Procurement of works
Procurement of worksProcurement of works
Procurement of works
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
 

More from VISHNU VIJAYAN

RECYCLING OF CONCRETE FROM DEMOLISHED CONSTRUCTION WASTE
RECYCLING OF CONCRETE FROM DEMOLISHED CONSTRUCTION WASTERECYCLING OF CONCRETE FROM DEMOLISHED CONSTRUCTION WASTE
RECYCLING OF CONCRETE FROM DEMOLISHED CONSTRUCTION WASTE
VISHNU VIJAYAN
 
A study on the analysis and modeling of multipurpose concert center by the in...
A study on the analysis and modeling of multipurpose concert center by the in...A study on the analysis and modeling of multipurpose concert center by the in...
A study on the analysis and modeling of multipurpose concert center by the in...
VISHNU VIJAYAN
 
HARBOUR ENGINEERING
HARBOUR ENGINEERING HARBOUR ENGINEERING
HARBOUR ENGINEERING
VISHNU VIJAYAN
 
Foundation Engineering
Foundation Engineering Foundation Engineering
Foundation Engineering
VISHNU VIJAYAN
 
FORM WORK & SLIPFORM
FORM WORK & SLIPFORMFORM WORK & SLIPFORM
FORM WORK & SLIPFORM
VISHNU VIJAYAN
 
STUDY ON SUSTAINABLE AND COST EFFECTIVE BUILDING CONSTRUCTION IN HOUSING SECTOR
STUDY ON SUSTAINABLE AND COST EFFECTIVE BUILDING CONSTRUCTION IN HOUSING SECTORSTUDY ON SUSTAINABLE AND COST EFFECTIVE BUILDING CONSTRUCTION IN HOUSING SECTOR
STUDY ON SUSTAINABLE AND COST EFFECTIVE BUILDING CONSTRUCTION IN HOUSING SECTOR
VISHNU VIJAYAN
 
An Experimental Study on Chitosan for Water Treatment
An Experimental Study on Chitosan for Water TreatmentAn Experimental Study on Chitosan for Water Treatment
An Experimental Study on Chitosan for Water Treatment
VISHNU VIJAYAN
 
Mechanical Strength of Concrete using Bottom Ash as Fine Aggregate
Mechanical Strength of Concrete using Bottom Ash as Fine AggregateMechanical Strength of Concrete using Bottom Ash as Fine Aggregate
Mechanical Strength of Concrete using Bottom Ash as Fine Aggregate
VISHNU VIJAYAN
 
A comparative study on sustainable building construction with conventional re...
A comparative study on sustainable building construction with conventional re...A comparative study on sustainable building construction with conventional re...
A comparative study on sustainable building construction with conventional re...
VISHNU VIJAYAN
 
A study about the status of implementation on safety standards and legal requ...
A study about the status of implementation on safety standards and legal requ...A study about the status of implementation on safety standards and legal requ...
A study about the status of implementation on safety standards and legal requ...
VISHNU VIJAYAN
 
A Study on Strengthening of Bubble Deck Slab with Elliptical Balls by using G...
A Study on Strengthening of Bubble Deck Slab with Elliptical Balls by using G...A Study on Strengthening of Bubble Deck Slab with Elliptical Balls by using G...
A Study on Strengthening of Bubble Deck Slab with Elliptical Balls by using G...
VISHNU VIJAYAN
 
Time-cost-risk optimization in construction work by using ant colony algorithm
Time-cost-risk optimization in construction work by using ant colony algorithmTime-cost-risk optimization in construction work by using ant colony algorithm
Time-cost-risk optimization in construction work by using ant colony algorithm
VISHNU VIJAYAN
 
SURVEYING-LEVELING-MODERN SURVEYING INSTRUMENTS
SURVEYING-LEVELING-MODERN SURVEYING INSTRUMENTSSURVEYING-LEVELING-MODERN SURVEYING INSTRUMENTS
SURVEYING-LEVELING-MODERN SURVEYING INSTRUMENTS
VISHNU VIJAYAN
 
ADVANCED CONCRETE TECHNOLOGY (CE361)
ADVANCED CONCRETE TECHNOLOGY  (CE361)ADVANCED CONCRETE TECHNOLOGY  (CE361)
ADVANCED CONCRETE TECHNOLOGY (CE361)
VISHNU VIJAYAN
 
CONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENTCONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENT
VISHNU VIJAYAN
 
SCIENTIFIC MANAGEMENT
SCIENTIFIC MANAGEMENTSCIENTIFIC MANAGEMENT
SCIENTIFIC MANAGEMENT
VISHNU VIJAYAN
 
PROJECT MANAGEMENT
PROJECT MANAGEMENT PROJECT MANAGEMENT
PROJECT MANAGEMENT
VISHNU VIJAYAN
 
SCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNINGSCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNING
VISHNU VIJAYAN
 
BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE
VISHNU VIJAYAN
 
TOTAL QUALITY MANAGEMENT (TQM)
TOTAL QUALITY MANAGEMENT (TQM)TOTAL QUALITY MANAGEMENT (TQM)
TOTAL QUALITY MANAGEMENT (TQM)
VISHNU VIJAYAN
 

More from VISHNU VIJAYAN (20)

RECYCLING OF CONCRETE FROM DEMOLISHED CONSTRUCTION WASTE
RECYCLING OF CONCRETE FROM DEMOLISHED CONSTRUCTION WASTERECYCLING OF CONCRETE FROM DEMOLISHED CONSTRUCTION WASTE
RECYCLING OF CONCRETE FROM DEMOLISHED CONSTRUCTION WASTE
 
A study on the analysis and modeling of multipurpose concert center by the in...
A study on the analysis and modeling of multipurpose concert center by the in...A study on the analysis and modeling of multipurpose concert center by the in...
A study on the analysis and modeling of multipurpose concert center by the in...
 
HARBOUR ENGINEERING
HARBOUR ENGINEERING HARBOUR ENGINEERING
HARBOUR ENGINEERING
 
Foundation Engineering
Foundation Engineering Foundation Engineering
Foundation Engineering
 
FORM WORK & SLIPFORM
FORM WORK & SLIPFORMFORM WORK & SLIPFORM
FORM WORK & SLIPFORM
 
STUDY ON SUSTAINABLE AND COST EFFECTIVE BUILDING CONSTRUCTION IN HOUSING SECTOR
STUDY ON SUSTAINABLE AND COST EFFECTIVE BUILDING CONSTRUCTION IN HOUSING SECTORSTUDY ON SUSTAINABLE AND COST EFFECTIVE BUILDING CONSTRUCTION IN HOUSING SECTOR
STUDY ON SUSTAINABLE AND COST EFFECTIVE BUILDING CONSTRUCTION IN HOUSING SECTOR
 
An Experimental Study on Chitosan for Water Treatment
An Experimental Study on Chitosan for Water TreatmentAn Experimental Study on Chitosan for Water Treatment
An Experimental Study on Chitosan for Water Treatment
 
Mechanical Strength of Concrete using Bottom Ash as Fine Aggregate
Mechanical Strength of Concrete using Bottom Ash as Fine AggregateMechanical Strength of Concrete using Bottom Ash as Fine Aggregate
Mechanical Strength of Concrete using Bottom Ash as Fine Aggregate
 
A comparative study on sustainable building construction with conventional re...
A comparative study on sustainable building construction with conventional re...A comparative study on sustainable building construction with conventional re...
A comparative study on sustainable building construction with conventional re...
 
A study about the status of implementation on safety standards and legal requ...
A study about the status of implementation on safety standards and legal requ...A study about the status of implementation on safety standards and legal requ...
A study about the status of implementation on safety standards and legal requ...
 
A Study on Strengthening of Bubble Deck Slab with Elliptical Balls by using G...
A Study on Strengthening of Bubble Deck Slab with Elliptical Balls by using G...A Study on Strengthening of Bubble Deck Slab with Elliptical Balls by using G...
A Study on Strengthening of Bubble Deck Slab with Elliptical Balls by using G...
 
Time-cost-risk optimization in construction work by using ant colony algorithm
Time-cost-risk optimization in construction work by using ant colony algorithmTime-cost-risk optimization in construction work by using ant colony algorithm
Time-cost-risk optimization in construction work by using ant colony algorithm
 
SURVEYING-LEVELING-MODERN SURVEYING INSTRUMENTS
SURVEYING-LEVELING-MODERN SURVEYING INSTRUMENTSSURVEYING-LEVELING-MODERN SURVEYING INSTRUMENTS
SURVEYING-LEVELING-MODERN SURVEYING INSTRUMENTS
 
ADVANCED CONCRETE TECHNOLOGY (CE361)
ADVANCED CONCRETE TECHNOLOGY  (CE361)ADVANCED CONCRETE TECHNOLOGY  (CE361)
ADVANCED CONCRETE TECHNOLOGY (CE361)
 
CONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENTCONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENT
 
SCIENTIFIC MANAGEMENT
SCIENTIFIC MANAGEMENTSCIENTIFIC MANAGEMENT
SCIENTIFIC MANAGEMENT
 
PROJECT MANAGEMENT
PROJECT MANAGEMENT PROJECT MANAGEMENT
PROJECT MANAGEMENT
 
SCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNINGSCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNING
 
BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE
 
TOTAL QUALITY MANAGEMENT (TQM)
TOTAL QUALITY MANAGEMENT (TQM)TOTAL QUALITY MANAGEMENT (TQM)
TOTAL QUALITY MANAGEMENT (TQM)
 

Recently uploaded

Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 

Recently uploaded (20)

Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 

BIDDING-TENDER-CONTRACT

  • 1. BIDDING-TENDER-CONTRACT VISHNU VIJAYAN HOD-Department Of Civil Engineering Baselios Mathews II College Of Engineering Sasthamcotta, Kollam,Kerala,INDIA 3/25/2020 VISHNU VIJAYAN BMCE
  • 2. BIDDING It is process of submitting a proposal (tender) to undertake, or manage the undertaking of a construction project. The process starts with a cost estimate from blueprints 3/25/2020 VISHNU VIJAYAN BMCE
  • 3. TENDERS Tender means an invitation to offer for an item/items or work. 3/25/2020 VISHNU VIJAYAN BMCE
  • 4. TENDERS • To invite bids for a project, or to accept a formal offer such as a takeover bid. Tender usually refers to the process whereby governments and financial institutions invite bids for large projects that must be submitted within a finite deadline. 3/25/2020 VISHNU VIJAYAN BMCE
  • 5. Types of tender • Open Tender: • Open tender is an arrangement where an advertisement in local newspapers or trade journals invites contractors to apply for tender documents • Limited or Closed Tender /Selective Tender: • In Limited Tenders, only pre-qualified or known bidders are allowed to participate. • Limited Tenders are not advertised in newspapers, as a result other bidder generally do not come to know that such tender is floated. The Lowest Bidder or L1 generally wins the contract. • Single Tender: • Single Tendering means sending the Tender to one particular party. 3/25/2020 VISHNU VIJAYAN BMCE
  • 6. CONTD.. • Negotiated Tender: • Under Negotiated Tender method normally one contractor is approached and such tender mainly used for specialist work such as lift system or airport project at big level, in such case there are limited number of contractor who do such work in the market. It is based on one-to-one discussion with contractors to negotiated the terms of contract. • Item Rate Tenders: • In this type of Tenders the contractors are required to quote the rates for each item mentioned in the price bid. The quantity to be executed is given in the price bid. • Percentage Rate Tenders: • In this type of Tenders a detailed estimate of the quantity of work to be carried out along with the estimate rates is given in the price bid form. 3/25/2020 VISHNU VIJAYAN BMCE
  • 7. TENDERING PROCEDURE – AWARD OF TENDERS • Whenever a government agency or firm wants certain works to be done ,services to be rendered or any purchases to be made, they float tender in order to get the work done at competitive prices . • The person who quotes the lowest price agreeing to the terms and conditions imposed on him , will have to sign an agreement stating that he will perform the said work as per requirement of the owner/client 3/25/2020 VISHNU VIJAYAN BMCE
  • 8. TENDER NOTICE • Whenever an agency or firm wants to float tender. • Its should be need publicity • Following information should carry in tender notice: • Name of the department calling for tender • Time of work and location • Designation of the officer inviting tenders • Last date and time of receipt of tenders • Period of availability of tender forms • Cost of tender document • Time of completion and type of contract • Earnest money deposit to be paid • Date ,time and place of opening tenders • Designation of the officer opening the tenders3/25/2020 VISHNU VIJAYAN BMCE
  • 9. TENDER DOCUMENT • A tender document is a document that explains about a project and its requirements to the intending bidders. • A tender document typically contains a notice inviting tenders, instruction to bidders, the conditions, form of submission, and bill of quantities. 3/25/2020 VISHNU VIJAYAN BMCE
  • 10. Earnest money deposit(EMD) • While submitting the tender, contractor will have to deposit an amount is about 2% of the estimated contract value of the project. This amount is called 3/25/2020 VISHNU VIJAYAN BMCE
  • 11. Security deposit • Once the tender of contractor is accepted by the client, the contractor to deposit about 10 % of the tender amount with the client. 3/25/2020 VISHNU VIJAYAN BMCE
  • 12. Tendering stage • Call for tender • Issue tender form • Evaluate tender • Award contract • Occupy successful contractors • Sign contract document 3/25/2020 VISHNU VIJAYAN BMCE
  • 13. CONTRACTS • A contract is an agreement having a lawful object entered into voluntarily by two or more parties, each of whom intends to create one or more legal obligations between them. • The elements of a contract are "offer" and "acceptance" by "competent persons3/25/2020 VISHNU VIJAYAN BMCE
  • 14. ESSENTIAL ELEMENTS OF CONTRACTS • Offer and acceptance: In order to create a valid contract, there must be a 'lawful offer' by one party and ‘lawful acceptance' of the same by the other party. • Competent Parties: For an agreement to be a contract there must be two or more competent parties. In order to be considered competent, a part must have a certain legal standing. • Consideration: There must be a lawful and valuable consideration given by both Parties. A consideration often called "Something for something." A consideration must, be possible one. • Proper Subject Matter: For the subject matter of a contract to be proper, the first Requirement is that it was be clearly defined as to the rights and obligations of each party. Second, the purpose of the contract must not violate the law. • Agreement: For valid contract, there must be a mutual agreement. An agreement is considered to have been reached when an offer made by one party is accepted by the second party. Both parties must wish and intend their bargain to be Enforceable by law. • Proper Form: The terms of a contract must be written so that both parties are very sure of what their rights and responsibilities are. • Consent of the Parties: The agreement must be free from Misrepresentation, Duress Undue influence, etc. 3/25/2020 VISHNU VIJAYAN BMCE
  • 15. Qualification of contractors • Contractor are selected by the owners through any one of these process after conducting negotiation where required • Public tenders • Pre qualification • Limited tenders • Nomination • SOME ESSENTIAL QUALIFICATION ARE : • HE should be financially sound • He should have sufficient knowledge to read the drawings • He should be well versed with procedure • He have Good reputation and experience • He Should have ability to handle labour and materials properly • He Should be capable of arranging men and materials as per requirements 3/25/2020 VISHNU VIJAYAN BMCE
  • 16. CONTRACT DOCUMENT • Before the work is given out on contract an agreement or bond is prepared. The following • documents shall be attached to the contract agreement or bond which should be duly • endorsed and sealed. Each page shall bear the signature of the contractor and the accepting • authority and all corrections shall be similarly initialled • TITLE PAGE • Title page having the name of work, contract bond number, etc. • INDEX PAGE • Index page having the contents of the agreement with page references. • TENDER NOTICE • Tender notice giving brief descriptions of the work, estimated cost of work, date and • time of the tender, amount of earnest money and security money, time of completion, • etc. Earnest money, usually 2% of the estimated cost, is deposited along with tender. • TENDER TORUS • Tender torus giving the bill of quantities, contractor’s rates, and total cost of works, • and time for completion, progress of works, security money, penalty clause, etc. 3/25/2020 VISHNU VIJAYAN BMCE
  • 17. • BILL OF QUANTITIES OR SCHEDULE OF QUANTITIES • Bill Of Quantities Or Schedule Of Quantities giving quantities and rates of each item of work and cost of each item of work and the total cost of the whole work. • SCHEDULE OF ISSUE OF MATERIALS • Schedule of issue of materials giving list of materials to be issued to the contractor with rates and place of issue. • GENERAL SPECIFICATIONS • General specification specifying the class and type of works in general. • SPECIFICATIONS DETAILED • Specification details of each item of work, and of each material to be used in the work. • DRAWINGS • complete set of drawings including plans, elevations, sections, detailed drawing, etc.and site plan, all fully dimensioned.3/25/2020 VISHNU VIJAYAN BMCE
  • 18. IMPORTANT CLAUSES IN CONSTRUCTION CONTRACTS • Definition of the terms used: • Security deposit: • Delay in completion: • Payment to contractor: • Addition and alternations: • Execution of work: • Defects and improper work: • Subletting : • Arbitration: 3/25/2020 VISHNU VIJAYAN BMCE
  • 19. Types of contracts • Types of contracts • Lump sum • Cost plus fixed fee contract • Unit price contract or item rate • Negotiated contract • Design build • Turn key contract • Build own transfer contract • Etc............. 3/25/2020 VISHNU VIJAYAN BMCE
  • 20. Types of contracts • A construction contract is the warranty that the executed job will receive the specific amount of compensation or how the compensation will be distributed. • LUMP SUM • The contractor agrees to build a project with a specific scope for a fixed price. A lump-sum contract is suitable if the scope and schedule of the project are sufficiently defined to allow the contractor to fully estimate project costs. 3/25/2020 VISHNU VIJAYAN BMCE
  • 21. • UNIT PRICE • This kind of contract is based on estimated quantities of items included in the project and their unit prices. The final price of the project is dependent on the quantities needed to carry out the work. In general, this contract is only suitable for projects in which the scope is reasonably well established, and the different types of items (but not their numbers) can be accurately identified in the contract documents. 3/25/2020 VISHNU VIJAYAN BMCE
  • 22. • COST PLUS • Cost plus is a contract agreement wherein the purchaser agrees to pay the cost of the work, including all trade contractor work, labor, materials, and equipment, plus an amount for contractor overhead and profit. These types of contracts are favored where the scope of work is indeterminate or highly uncertain, and the kinds of labor, material, and equipment needed are also uncertain. 3/25/2020 VISHNU VIJAYAN BMCE
  • 23. MEASUREMENT BOOK • The measurements of all works and supplies are recorded in the Measurement Book • Form No. 23 and payment of all works and supplies are made on the basis of measurement recorded. • Its very important account record. • It recorded by the executive or Assistant Engineers or sectional officer,(overseers) to whom measurement books have been issued for the purpose. 3/25/2020 VISHNU VIJAYAN BMCE